Drawing update system, drawing update method, and program
The drawing update system enhances work efficiency by detecting and highlighting updated areas within construction drawings, addressing the inefficiency in identifying changes due to construction progress differences.
Patent Information
- Application Number
- PCT/JP2023/012259
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-27
- Publication Date
- 2024-10-03
AI Technical Summary
Construction drawing updates are inefficient as workers and managers struggle to identify updated locations and content due to differences between construction progress and drawing versions, leading to poor work efficiency.
A drawing update system that acquires initial and updated drawings, detects changes, generates and overlays layer data to highlight updated areas, and adjusts attention levels, allowing for easy identification of updated locations within the drawings.
Improves work efficiency by clearly indicating updated areas within the drawings, facilitating better understanding and management of construction progress.
Smart Images

Figure JP2023012259_03102024_PF_FP_ABST
Abstract
Description
Drawing update system, drawing update method and program
[0001] The present invention relates to a technique that is effective for updating drawings in accordance with the progress of construction.
[0002] In recent years, technologies related to construction drawings have been attracting attention. For example, Patent Document 1 discloses a technology for distributing (replacing) the latest drawings only to necessary contractors or construction types (jobs) when multiple new and old drawings for a construction project are updated, and distributing drawings appropriate to the project content in time for the project, corresponding to or linked to a schedule database (timeline). Patent Document 2 also discloses a technology that uses a transparent display unit installed in the driver's seat of a construction machine, an eye tracking unit that detects the driver's eye position, a position acquisition unit that detects the position of the construction machine, and a display of drawing data adjusted to be displayed at full size and superimposed at an appropriate position on the construction site based on the eye position and the position of the construction machine.
[0003] JP 2009-301308 A JP 2021-157217 A
[0004] At construction sites, discrepancies occur between the actual building and the construction drawings as construction progresses. To address these discrepancies, the drawings are updated, such as by rewriting or recreating them. At construction sites, workers, managers, and others visually inspect the updated drawings to confirm the updated parts and content. Therefore, in order for workers and managers to understand the updated parts and content, they must compare the drawings before and after the update to identify the updated parts and content, which results in poor work efficiency. Therefore, there is a need for a technology that makes it easy to identify updated parts as construction progresses. However, the technologies described in Patent Documents 1 and 2 do not facilitate the identification of updated parts as construction progresses. Therefore, the present inventors focused on a mechanism for changing the attention level of updated parts as construction progresses.
[0005] The present invention aims to provide a drawing update system, drawing update method, and program that allows workers, managers, etc. to easily understand the updated parts and content by providing drawings in which the attention level of the updated parts is changed in accordance with the progress of construction, thereby improving work efficiency.
[0006] The present invention provides a drawing update system that updates construction drawings in accordance with construction progress, comprising: a first drawing acquisition unit that acquires a first drawing related to construction; a second drawing acquisition unit that acquires a second drawing obtained by updating the first drawing in accordance with construction progress; a detection unit that compares the first drawing with the second drawing and detects updated areas; a second drawing generation unit that generates second drawing layer data to be placed over the second drawing; a second drawing placement unit that places the generated second drawing layer data over the second drawing; an update area attention change unit that changes the attention of the updated area in the placed second drawing layer data; and a second drawing provision unit that provides the second drawing on which the second drawing layer data reflecting the change in attention has been placed.
[0007] According to the present invention, the attention level of an updated portion in layer data placed on a drawing is changed, and a drawing is provided in which layer data that reflects the changed attention level is placed. As a result, workers, managers, etc. can easily recognize that the portion whose attention level has been changed is the updated portion, thereby improving work efficiency.
[0008] Although the present invention is categorized as a system, the same effects and advantages can be obtained even when it is a method or a program.
[0009] According to the present invention, it is possible to improve work efficiency.
[0010] 1 is a diagram illustrating an overview of a drawing updating system 1. FIG. 1 is a diagram illustrating the functional configuration of the drawing updating system 1. FIG. 2 is a diagram illustrating a flowchart of a first drawing acquisition process executed by a computer 10. FIG. 3 is a diagram illustrating a flowchart of a second drawing acquisition process executed by a computer 10. FIG. 4 is a diagram illustrating a schematic example of when an updated portion is detected in a second drawing. FIG. 5 is a diagram illustrating a flowchart of a provision process executed by a computer 10. FIG. 6 is a diagram illustrating a schematic example of a state in which the attention level of layer data for a second drawing has been changed. FIG. 7 is a diagram illustrating a flowchart of a switching process executed by a computer 10. FIG. 8 is a diagram illustrating a flowchart of a construction progress saving process executed by a computer 10. FIG. 9 is a diagram illustrating a flowchart of a list output process executed by a computer 10. FIG. 10 is a diagram illustrating a schematic example of a state in which the attention level of the latest version of a drawing in a list has been changed. FIG. 11 is a diagram illustrating a flowchart of a history output process executed by a computer 10. FIG. 12 is a diagram illustrating a schematic example of a drawing history. FIG. 13 is a diagram illustrating a flowchart of a duplication process executed by a computer 10. FIG. 14 is a diagram illustrating a flowchart of an object takeover process executed by a computer 10. FIG. 15 is a diagram illustrating a schematic example of a state in which a predetermined object has been arranged in layer data for a first drawing. 10 is a diagram showing a schematic example of a state in which the layer data for the second drawing has taken over a predetermined object. FIG. 11 is a diagram showing a flowchart of a construction progress takeover process executed by the computer 10.
[0011] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the following drawings, the same elements are designated by the same numbers or symbols throughout the description of the embodiments.
[0012] [Overview of Drawing Update System 1] FIG. 1 is a schematic diagram illustrating an overview of the drawing update system 1. The components of the drawing update system 1 will be described based on FIG. 1. The drawing update system 1 is a system that updates construction drawings in accordance with the progress of construction, and includes a computer 10 having at least a server function. In this embodiment, the drawing update system 1 includes, in addition to the computer 10, user terminals 20 managed by users such as workers and managers. The computer 10 has server functions and may be implemented, for example, by a single computer or by multiple computers, such as a cloud computer. In this specification, a cloud computer may refer to either a computer that scalably uses any computer to perform a specific function, or a computer that includes multiple functional modules to realize a system and uses the functions in any combination. The user terminal 20 is a terminal device managed by a user such as a worker or manager, and may be, for example, a mobile phone, smartphone, tablet, personal computer, or laptop computer. The number of user terminals 20 may correspond to the number of users, and is not particularly limited and can be designed as appropriate. In addition, the drawing update system 1 may include other terminals and devices in addition to the computer 10 and user terminal 20 described above, and the number, type, and functions thereof are not particularly limited and can be designed as appropriate.
[0013] An outline of the processing steps performed by the drawing update system 1 when updating construction drawings in accordance with the progress of construction will be described.
[0014] The computer 10 acquires a first drawing related to construction (step S1). The computer 10 acquires the first drawing from the user terminal 20. The user terminal 20 accepts input of the first drawing to be sent to the computer 10 via a predetermined application, a browser, or other predetermined software, and transmits the accepted first drawing to the computer 10 as first drawing data. The computer 10 acquires the first drawing related to construction by receiving this first drawing data.
[0015] The computer 10 acquires second drawings, which are obtained by updating the first drawings in accordance with the progress of construction (step S2). The computer 10 acquires second drawings, which are obtained by updating (rewriting, recreating, etc.) the first drawings in accordance with the progress of construction, from the user terminal 20. The user terminal 20 accepts input of second drawings to be sent to the computer 10 via predetermined software such as a predetermined application or browser, and sends the accepted second drawings to the computer 10 as second drawing data. The computer 10 acquires second drawings related to the construction by receiving this second drawing data.
[0016] The computer 10 compares the first drawing with the second drawing and detects updated portions (step S3). The computer 10 extracts feature points and feature quantities from the first drawing and the second drawing. The computer 10 compares the extraction results and detects differences between the first drawing and the second drawing as updated portions.
[0017] The computer 10 generates layer data for the second drawing to be overlaid on the second drawing (step S4), and overlays the generated layer data for the second drawing on the second drawing (step S5). The computer 10 generates layer data for the second drawing that allows the second drawing to be transparently displayed, and overlays the generated layer data for the second drawing on the second drawing.
[0018] The computer 10 changes the attention level of the updated portion in the arranged layer data for the second drawing (step S6). The computer 10 changes the attention level of the detected updated portion in the arranged layer data for the second drawing (by changing the color, adding a border, arranging an icon, highlighting, etc.).
[0019] The computer 10 provides the second drawing in which the layer data for the second drawing that reflects the change in attention level is arranged (step S7). The computer 10 transmits the second drawing in which the layer data for the second drawing that reflects the change in attention level is arranged to the user terminal 20 as second drawing data. The user terminal 20 receives this second drawing data. The user terminal 20 displays the second drawing based on this second drawing data on its own display unit. The computer 10 displays this second drawing on the user terminal 20, thereby providing the second drawing in which the layer data for the second drawing that reflects the change in attention level is arranged.
[0020] The above is an overview of the drawing updating system 1. According to this drawing updating system 1, it is possible to improve work efficiency.
[0021] [Device Configuration] FIG. 2 is a block diagram showing the configuration of the drawing update system 1. The device configuration of the drawing update system 1 will be described with reference to FIG. 2. The drawing update system 1 is a system that updates construction drawings in accordance with the progress of construction, and is configured with at least a computer 10. In this embodiment, the drawing update system 1 is configured with, in addition to the computer 10, a user terminal 20 managed by a user such as a worker or a manager. The drawing update system 1 is a system in which the computer 10 is connected to the user terminal 20 via a network 7 such as a public line network so as to enable data communication. Note that, in the drawing update system 1, the number of user terminals 20 can be designed appropriately depending on the number of users and is not particularly limited. Furthermore, the drawing update system 1 may include other terminals and devices in addition to the computer 10 and the user terminal 20, and the number, type, and functions of the other terminals and devices can be designed appropriately.
[0022] The computer 10 has a server function and may be realized, for example, by a single computer or by multiple computers, such as a cloud computer. The computer 10 includes a control unit such as a CPU (Central Processing Unit), a GPU (Graphics Processing Unit), a RAM (Random Access Memory), and a ROM (Read Only Memory), and a communication unit such as a device for enabling communication with other terminals and devices, a first drawing acquisition unit 11 for acquiring first drawings related to construction, a second drawing acquisition unit 12 for acquiring second drawings updated from the first drawings in accordance with the progress of construction, and a second drawing provision unit 13 for providing second drawings on which layer data for the second drawings reflecting changes in attention level is arranged. The computer 10 includes a memory unit such as a data storage unit using a hard disk, semiconductor memory, recording medium, memory card, etc. The computer 10 includes, as processing units, various devices that perform various processes, a detection unit 14 that compares the first drawing with the second drawing and detects updated areas, a second drawing generation unit 15 that generates layer data for the second drawing to be placed on top of the second drawing, a second drawing placement unit 16 that places the generated layer data for the second drawing on top of the second drawing, and an update area attention change unit 17 that changes the attention level of the updated areas in the placed layer data for the second drawing.
[0023] In the computer 10, the control unit loads a predetermined program, thereby working in cooperation with the communication unit to realize a first drawing acquisition module, a second drawing acquisition module, a second drawing provision module, a second drawing input acceptance module, a first drawing provision module, a first drawing input acceptance module, a switching module, a second drawing construction progress acceptance module, a list output module, a history output module, an object acquisition module, and a first drawing construction progress acceptance module. Also, in the computer 10, the control unit loads a predetermined program, thereby working in cooperation with the memory unit to realize a first drawing storage module and a second drawing storage module. In addition, in computer 10, the control unit reads a specified program and works in cooperation with the processing unit to realize a first drawing generation module, a first drawing placement module, an assignment module, a detection module, a second drawing generation module, a second drawing placement module, an update location attention change module, a second drawing construction progress storage module, a list creation module, a list attention change module, a history creation module, a duplication module, an object placement module, an object storage module, an object handover module, a first drawing construction progress storage module, and a construction progress handover module.
[0024] The user terminal 20 is a terminal device managed by a user, such as the information terminal described above. The user terminal 20 includes a CPU, GPU, RAM, ROM, etc. as a terminal control unit, a device for enabling communication with other terminals and devices, etc. as a communication unit, and various devices for receiving predetermined inputs, inputting and outputting various data and drawings, etc. as an input / output unit.
[0025] Below, we will explain each process executed by the drawing updating system 1 together with the process executed by each of the above-mentioned modules. In this specification, each module may execute its processing content as its own function, or may execute it via a predetermined application.
[0026] [First drawing acquisition process executed by computer 10] The first drawing acquisition process executed by the computer 10 will be described with reference to Fig. 3. The figure shows a flowchart of the first drawing acquisition process executed by the computer 10. This first drawing acquisition process is a detailed description of the first drawing acquisition process (step S1) for acquiring a first drawing related to construction.
[0027] The first drawing acquisition module acquires a first drawing related to construction (step S10). The first drawing acquisition module acquires the first drawing related to construction from the user terminal 20. The user terminal 20 accepts input from the user to launch predetermined software such as a predetermined application or browser. The user terminal 20 accepts input of the first drawing to be sent to the computer 10 via the launched predetermined software. The user terminal 20 transmits the accepted first drawing to the computer 10 as first drawing data. The first drawing acquisition module receives the first drawing data sent by the user terminal 20 and acquires the first drawing related to construction. The first drawing data acquired by the first drawing acquisition module includes first drawing management data related to management of the first drawing, such as the version number, creator, and creation date and time of the first drawing. In other words, the first drawing acquisition module acquires the first drawing and also acquires the first drawing management data. The first drawing acquisition module may acquire the first drawing from (for example, an external system, a predetermined database, or other terminals or devices) other than the user terminal 20. The method by which the first drawing acquisition module acquires the first drawing and management data for the first drawing from the user terminal 20 can be designed as appropriate.
[0028] The first drawing generation module generates layer data for the first drawing to be placed over the first drawing (step S11). The layer data for the first drawing is a virtual sheet to be placed over the first drawing and is capable of outputting predetermined objects (memos, images, icons, leader lines, shapes, etc.). The layer data for the first drawing may be placed over the entire first drawing or over a portion of the first drawing. The layer data for the first drawing may be a single virtual sheet or multiple virtual sheets. The first drawing generation module generates layer data for the first drawing that allows the first drawing to be displayed transparently. The structure and properties of the layer data for the first drawing, such as the size, number, and color, are not limited to the above-described example and can be designed as appropriate.
[0029] The first drawing placement module places the generated first drawing layer data on the first drawing (step S12). The first drawing placement module places the generated first drawing layer data on the acquired first drawing. For example, the first drawing placement module places one piece of first drawing layer data of the same size as the acquired first drawing on the acquired first drawing.
[0030] The first drawing storage module stores the first drawing on which the first drawing layer data is arranged (step S13). The first drawing storage module associates the first drawing on which the first drawing layer data is arranged with the first drawing management data and stores them. The first drawing storage module may further associate and store a predetermined identifier (name (site name, construction location name, etc.), management number, etc.). The first drawing storage module may also further associate and store the first drawing before the first drawing layer data is arranged.
[0031] The above is the first drawing acquisition process.
[0032] [Second Drawing Acquisition Process Executed by Computer 10] The second drawing acquisition process executed by the computer 10 will be described with reference to Figure 4. This figure shows a flowchart of the second drawing acquisition process executed by the computer 10. This second drawing acquisition process includes details of a second drawing acquisition process (step S2) that acquires a second drawing obtained by updating the first drawing in accordance with the construction progress, a detection process (step S3) that compares the first drawing with the second drawing and detects updated portions, a second drawing generation process (step S4) that generates second drawing layer data to be overlaid on the second drawing, and a second drawing placement process (step S5) that overlays the generated second drawing layer data on the second drawing. This second drawing acquisition process is performed after the first drawing acquisition process.
[0033] The second drawing acquisition module acquires a second drawing, which is an updated version of the first drawing in accordance with the construction progress (step S20). The second drawing is a drawing obtained by rewriting or recreating the first drawing, in part or in whole, in accordance with the construction progress. This rewriting or recreating is referred to as "updating" in this specification. The second drawing acquisition module acquires this second drawing from the user terminal 20. The user terminal 20 accepts input from the user to launch specified software. The user terminal 20 accepts input from the user via the launched specified software of a second drawing to be sent to the computer 10. This second drawing is an updated version of the first drawing in accordance with the construction progress. The user terminal 20 transmits the accepted second drawing to the computer 10 as second drawing data. The second drawing acquisition module receives the second drawing data sent by the user terminal 20 and acquires a second drawing, which is an updated version of the first drawing in accordance with the construction progress. The second drawing data acquired by the second drawing acquisition module includes second drawing management data related to the management of the second drawing, such as the person who changed the second drawing and the date and time of the change. In other words, the second drawing acquisition module acquires the second drawing and also acquires the second drawing management data. Note that the second drawing acquisition module may acquire the second drawing from a source other than the user terminal 20 (for example, an external system, a specified database, or other terminals or devices). Furthermore, the method by which the second drawing acquisition module acquires the second drawing and second drawing management data from the user terminal 20 can be designed as appropriate.
[0034] The assignment module assigns a higher version number to the acquired second drawing than the acquired first drawing (step S21). The assignment module identifies the version number of the first drawing based on the acquired first drawing management data. The assignment module generates a version number for the acquired second drawing that is higher than the identified version number of the first drawing. For example, if the version number of the first drawing is "0001," the assignment module generates a higher version number, such as "0002." Note that if a version number already exists in the second drawing management data and the existing version number is lower than or the same as that of the first drawing, the assignment module can simply generate a higher version number. Furthermore, if a version number already exists in the second drawing management data and the existing version number is higher than that of the first drawing, the assignment module may use the existing version number as is or may generate a new version number. The assignment module adds the generated version number to the acquired second drawing management data. The assignment module assigns a higher version number to the acquired second drawing than to the acquired first drawing by adding the generated version number to the acquired second drawing management data.
[0035] The detection module compares the first drawing with the second drawing and detects updated portions (step S22). The detection module extracts feature quantities and feature points from the first drawing and also extracts feature quantities and feature points from the second drawing. The detection module may extract feature quantities and feature points for specific locations, such as rooms, equipment, or components, in each drawing, or may extract overall feature quantities and feature points from each drawing. The detection module compares the feature quantities and feature points extracted for each drawing. Based on the comparison results, the detection module detects differences between the first and second drawings from the second drawing. These differences include, for example, changes in room dimensions, components, or equipment. The detected differences in the second drawing are areas where the first drawing has been rewritten or redesigned, and these areas are detected as updated portions in the second drawing (see FIG. 5 ). The detection module detects differences based on the results of comparing the extracted feature amounts and feature points, thereby comparing the first drawing with the second drawing and detecting updated portions.
[0036] The updated portion detected by the detection module will be described with reference to FIG. 5 . This figure is a diagram schematically illustrating an example in which the detection module detects an updated portion in a second drawing. In this figure, a second drawing 30 is shown. The second drawing 30 is a drawing in which the first drawing (not shown) has been updated in accordance with the progress of construction. The second drawing 30 shows a detected updated portion 31. The updated portion 31 is surrounded by a rectangular frame and colored to indicate the location of the detected updated portion. Note that the updated portion 31 is merely an example for the purpose of explanation, and therefore it is not necessary to actually surround the portion with a frame or color it, and it is sufficient to simply detect the updated portion 31.
[0037] Returning to FIG. 4 , the second drawing acquisition process will be described in more detail. The second drawing generation module generates second drawing layer data to be placed on the second drawing (step S23). The second drawing layer data is a virtual sheet to be placed on the second drawing and is capable of outputting predetermined objects (memos, images, icons, leader lines, shapes, etc.). The second drawing layer data may be placed on the entire second drawing or on a portion of the second drawing. The second drawing layer data may be a single virtual sheet or multiple virtual sheets. The second drawing generation module generates layer data for the second drawing that allows the second drawing to be displayed transparently. The structure and properties of the second drawing layer data, such as the size, number, and color, are not limited to the above example and can be designed as appropriate.
[0038] The second drawing placement module places the generated second drawing layer data on the second drawing (step S24). The second drawing placement module places the generated second drawing layer data on the acquired second drawing. For example, the second drawing placement module places one piece of second drawing layer data of the same size as the acquired second drawing on the acquired second drawing.
[0039] The second drawing storage module stores the second drawing in which the second drawing layer data is placed and the updated portion (step S24). The second drawing storage module stores the second drawing in which the second drawing layer data is placed, the second drawing management data, and the detected updated portion of the second drawing, in association with each other. The second drawing storage module may further store a predetermined identifier (name (site name, construction location name, etc.), management number, etc.) in association with each other. The second drawing storage module may also store the second drawing before the second drawing layer data is placed in association with each other. The second drawing storage module may also store the first drawing, which is the drawing before the update of the second drawing, in association with each other.
[0040] The above is the second drawing acquisition process. After executing the second drawing acquisition process, if the computer 10 acquires a third drawing, which is an updated version of the second drawing based on the construction progress, it simply executes the same process as the second drawing acquisition process for the newly acquired third drawing. Subsequently, if the computer 10 acquires a fourth drawing, which is an updated version of the third drawing based on the construction progress, a fifth drawing, which is an updated version of the fourth drawing based on the construction progress, ..., an n-th drawing, which is an updated version of the n-1th drawing (n is an integer greater than or equal to 3), it simply executes the same process as the second drawing acquisition process for each of the n-th drawing. As a result, the version number of the n-th drawing will always be the highest version number. Furthermore, as a result of the duplication process, object inheritance process, and construction progress inheritance process (described below), the updates made to the n-1th drawing are reflected in the layer data for the n-th drawing.
[0041] [Providing Process Executed by Computer 10] The providing process executed by the computer 10 will be described with reference to Figure 6. This figure shows a flowchart of the providing process executed by the computer 10. This providing process shows details of an updated portion attention change process (step S6) that changes the attention level of an updated portion in the arranged second drawing layer data, and a second drawing providing process (step S7) that provides a second drawing in which second drawing layer data reflecting the changed attention level has been arranged. This providing process uses the second drawing acquired by the second drawing acquisition process and the detected updated portion.
[0042] The update portion attention change module changes the attention of the update portion in the placed layer data for the second drawing (step S30). The attention change of the update portion may be, for example, a color change, the addition of a border, the placement of an icon, or highlighting. The update portion attention change module changes the attention of the update portion (update portion 31 shown in FIG. 5) in the placed layer data for the second drawing (see FIG. 7). Here, the update portion attention change module does not change the attention of the update portion in the second drawing itself, but changes the attention of the portion corresponding to the update portion in the layer data for the second drawing placed on this second drawing.
[0043] The attention level changed by the update portion attention level change module will be described with reference to FIG. 7 . This figure is a schematic diagram illustrating an example of a state in which the attention level of layer data for a second drawing has been changed. In this figure, a second drawing 30 is shown. A transparent virtual sheet of layer data for a second drawing 32 is placed on top of the second drawing 30. In the second drawing 30, the layer data for a second drawing 32 corresponding to the update portion 31 has its attention level changed, and the update portion 31 is enclosed by a frame 33. The update portion attention level change module changes the attention level by adding the frame 33 to the portion of the layer data for a second drawing 32 corresponding to the update portion 31. The method for changing the attention level of the update portion 31 is not limited to the example described above and can be designed as appropriate.
[0044] 6, the providing process will be described. The second drawing storage module stores the second drawing in which the second drawing layer data reflecting the change in attention level is arranged (step S31). The second drawing storage module further associates the second drawing in which the second drawing layer reflecting the change in attention level is arranged with the second drawing stored by the process of step S25 and stores the second drawing.
[0045] The second drawing providing module provides the second drawing in which the second drawing layer data reflecting the change in attention level is arranged (step S32). The second drawing providing module transmits the second drawing in which the second drawing layer data reflecting the change in attention level arranged to the user terminal 20 as post-attention level changed second drawing data based on a request from the user terminal 20 or the like. This post-attention level changed second drawing data may include data other than drawings, such as second drawing management data. The user terminal 20 receives this post-attention level changed second drawing data and displays it on its own display. At this time, the user terminal 20 displays the second drawing based on the post-attention level changed second drawing data on its own display via predetermined software. The user terminal 20 displays the second drawing 30 shown in FIG. 7 on its own display via predetermined software. If the user terminal 20 also receives data other than drawings, such as second drawing management data, it may display this data together, or may switch between displaying and hiding this data by accepting a predetermined input (tap, swipe, etc.).
[0046] The above is the provision process. After executing the provision process, when the computer 10 acquires the above-described nth drawing, it simply executes the same processes as the second drawing acquisition process and provision process on the nth drawing. As a result, the updates up to the n-1th drawing are reflected in the layer data of the nth drawing as a result of the duplication process, object handover process, and construction progress handover process described below. The computer 10 provides the nth drawing in which the layer data reflecting these updates is arranged. Note that the computer 10 may also provide the first drawing together with the second drawing in the provision process. In this case, when providing the nth drawing, the computer 10 may provide the n-1th drawing together with the nth drawing, or may provide multiple drawings prior to the nth drawing.
[0047] [Switching Process Executed by Computer 10] The switching process executed by the computer 10 will be described with reference to Fig. 8. This figure shows a flowchart of the switching process executed by the computer 10. This switching process is a process that uses the second drawing provided by the providing process.
[0048] The second drawing input receiving module receives a predetermined input for the provided second drawing (step S40). The user terminal 20 receives a predetermined input (such as a swipe operation) for the second drawing, which the user terminal 20 displays and which contains layer data for the second drawing that reflects the provided change in attention level. For example, the user inputs a swipe operation or the like for the second drawing displayed by the user terminal 20. The user terminal 20 transmits the received input content to the computer 10. By receiving this input content, the second drawing input receiving module receives the predetermined input for the provided second drawing.
[0049] The first drawing providing module provides a first drawing based on the received predetermined input (step S41). The first drawing providing module transmits the first drawing, which is the drawing before updating the second drawing provided by the providing process, as first drawing data to the user terminal 20 based on the received input. This first drawing data may include data other than drawings, such as first drawing management data. Here, the first drawing providing module may transmit the first drawing with first drawing layer data arranged therein, or may transmit the first drawing without first drawing layer data arranged therein. The user terminal 20 receives this first drawing data and displays it on its display unit. At this time, the user terminal 20 displays the first drawing based on the first drawing data on its display unit via predetermined software. If the user terminal 20 also receives data other than drawings, such as first drawing management data, it may display this data together, or may switch between displaying and hiding this data by accepting predetermined input.
[0050] The first drawing input acceptance module accepts a predetermined input for the provided first drawing (step S42). The user terminal 20 accepts a predetermined input (such as a swipe operation) for the provided first drawing displayed by the user terminal 20. For example, the user inputs a swipe operation or the like for the first drawing displayed by the user terminal 20. The user terminal 20 transmits the accepted input content to the computer 10. By receiving this input content, the first drawing input acceptance module accepts the predetermined input for the provided first drawing.
[0051] The switching module switches between the first drawing and the second drawing based on a predetermined input for the first drawing or the second drawing (step S43). The user terminal 20 accepts a predetermined input (such as a swipe operation) for the provided first drawing or the second drawing displayed by the user terminal 20. For example, the user inputs a swipe operation or the like for the first drawing or the second drawing displayed by the user terminal 20. The user terminal 20 transmits the accepted input to the computer 10. The switching module receives this input. If the switching module determines, based on the received input, that the drawing currently displayed by the user terminal 20 is the first drawing, it transmits a command to the user terminal 20 to switch the drawing displayed by the user terminal 20 to the second drawing. On the other hand, if the switching module determines, based on the received input, that the drawing currently displayed by the user terminal 20 is the second drawing, it transmits a command to the user terminal 20 to switch the drawing displayed by the user terminal 20 to the first drawing. The user terminal 20 receives this command and switches the drawing it is displaying. That is, if the drawing it is displaying is the second drawing, the user terminal 20 displays the first drawing, and if the drawing it is displaying is the first drawing, the user terminal 20 displays the second drawing. As a result, the switching module switches between the first drawing and the second drawing based on a predetermined input for the first drawing or the second drawing. Note that the switching between the first drawing and the second drawing may be performed not by a command sent by the computer 10, but by the user terminal 20 itself generating a command to switch between the first drawing and the second drawing and switching the display content.
[0052] The above is the switching process. After executing the switching process, when the computer 10 provides the above-mentioned nth drawing, it only needs to execute the same process as the switching process for the nth drawing. As a result, the computer 10 switches between the nth drawing and the n-1th drawing. Note that when the nth drawing is provided, the computer 10 may not only switch between the nth drawing and the n-1th drawing, but also between the nth drawing and multiple drawings prior to the nth drawing. In this case, the computer 10 switches between the previous and next drawings, such as switching between the nth drawing and the n-1th drawing, and between the n-1th drawing and the n-2th drawing.
[0053] [Construction progress saving process executed by computer 10] The construction progress saving process executed by the computer 10 will be described with reference to Fig. 9. The figure is a flowchart of the construction progress saving process executed by the computer 10. This construction progress saving process is a process that uses the second drawings provided by the providing process.
[0054] The construction progress reception module for the second drawing accepts the input of construction progress into the layer data for the second drawing (step S50). The user terminal 20 accepts the input of construction progress for the second drawing, which it displays and which has arranged the layer data for the second drawing that reflects the provided change in attention level. For example, the user inputs the construction progress using a virtual keyboard or the like displayed on the user terminal 20. The user terminal 20 transmits the accepted input content to the computer 10. By receiving this input content, the construction progress reception module for the second drawing accepts the input of construction progress into the layer data for the second drawing.
[0055] The second drawing construction progress storage module stores the received construction progress in the second drawing layer data (step S51). The second drawing construction progress storage module inputs the received construction progress into a predetermined position in the second drawing layer data. The predetermined position is, for example, the position where the user terminal 20 received the construction progress, or a predetermined position in the second drawing layer data. The second drawing construction progress storage module inputs the received construction progress into the predetermined position in the second drawing layer data, thereby saving the received construction progress in the second drawing layer data.
[0056] The second drawing storage module stores the second drawing on which the layer data for the second drawing that stores the construction progress is arranged (step S52). The second drawing storage module further associates the second drawing on which the layer data for the second drawing that stores the construction progress is arranged with the second drawing stored by the processing of step S25 or step S31 and stores the second drawing.
[0057] The above is the construction progress saving process. After executing the construction progress saving process, when the above-mentioned nth drawing is provided, the computer 10 can execute the same process as the construction progress saving process for the nth drawing. As a result, the construction progress up to the n-1th drawing is saved in the layer data for the nth drawing as a result of the duplication process, object inheritance process, and construction progress inheritance process described below.
[0058] [List Output Processing Executed by Computer 10] The list output processing executed by the computer 10 will be described with reference to Fig. 10. The figure is a flowchart of the list output processing executed by the computer 10. This list output processing is processing that uses the drawings acquired by the first drawing acquisition processing and the second drawing acquisition processing.
[0059] The list creation module creates a list of the acquired drawings (step S60). The drawings used by the list creation module when creating the list may be the first and second drawings acquired by the first and second drawing acquisition processes, or may include an nth drawing acquired after the second drawing acquisition process is executed. This list may, for example, be a list of thumbnails of each drawing or a list of the version numbers of each drawing. The order may be random, or may be in descending or ascending order of the order in which they were acquired. The list creation module links each acquired drawing to the created list. Note that the contents of the list created by the list creation module are not limited to the above example and can be designed as appropriate.
[0060] The list attention level change module changes the attention level of the latest drawing in the created list (step S61). The change in the attention level of a drawing can be, for example, a color change, the addition of a border, the addition of an icon, or highlighting. The list attention level change module determines which drawing is the latest based on the version number of each drawing in the created list. The list attention level change module determines which drawing has the highest version number assigned to each drawing as the latest drawing. The list attention level change module changes the attention level of the determined drawing (see FIG. 11). Note that if the drawings were sorted in descending order when the list was created, the list attention level change module may determine the first drawing as the latest version, or if the drawings were sorted in ascending order, the list attention level change module may determine the last drawing as the latest version.
[0061] The attention level changed by the list attention level change module will be described with reference to FIG. 11 . This figure is a schematic diagram illustrating an example of a state in which the attention level of the latest version of a drawing in a created list has been changed. This figure shows a list 40. The list 40 lists the version numbers 41 (41a to 41i) of each acquired drawing and the thumbnails 42 (42a to 42i) of each drawing. In this figure, the list 40 lists the thumbnails 42 of each drawing with version numbers 41 "0001" to "0009" in ascending order of acquisition. That is, the version number 41a and the drawing thumbnail 42a are the first drawing, and the larger the alphabet, the newer the drawing. The version number 41i and the drawing thumbnail 42i are the latest drawing. The list attention level change module determines the thumbnail 42 of the drawing with the largest version number 41 assigned to each drawing as the thumbnail 42 of the latest drawing. In the same figure, since the largest version number 41 among the version numbers 41 is "0009," the list attention level change module determines that the thumbnail 42i of the drawing having the version number 41i of "0009" is the latest version of the drawing. The list attention level change module changes the attention level of the thumbnail 42i of the drawing having the version number 41i of "0009." In the same figure, the list attention level change module adds an icon 43 near the thumbnail 42i of this drawing to change its attention level. Note that, as described above, the list attention level change module may change the attention level by methods other than the icon 43. Furthermore, the location of the icon 43 is not limited to the location shown in the figure, and other locations and methods may be used, such as near the thumbnail 42i of the latest version of the drawing or by connecting the thumbnail 42i of the latest version of the drawing with a leader line. This also applies when changing the attention level by methods other than the icon 43.
[0062] Returning to FIG. 10 , the list output process will be described in more detail. The list output module outputs a list reflecting the change in attention level (step S62). The list output module transmits the list reflecting the change in attention level to the user terminal 20 as post-attention level change list data based on a request from the user terminal 20. The user terminal 20 receives this post-attention level change list data and displays it on its display unit. At this time, the user terminal 20 displays a list based on the post-attention level change list data on its display unit via predetermined software. The user terminal 20 displays the list 40 shown in FIG. 10 on its display unit via predetermined software. The user terminal 20 displays actual drawings linked to the list 40 on its display unit by accepting a predetermined input. For example, a user taps a thumbnail 42 of a drawing they desire in the list 40 displayed by the user terminal 20. Based on this tap, the user terminal 20 displays a drawing corresponding to the thumbnail 42 of the drawing entered by the user on its display unit.
[0063] This completes the list output process.
[0064] [History output process executed by computer 10] The history output process executed by the computer 10 will be described with reference to Fig. 12. The figure is a flowchart of the history output process executed by the computer 10. This history output process is a process related to each drawing acquired by the first drawing acquisition process and the second drawing acquisition process.
[0065] The history creation module creates a history of the acquired drawings (step S70). The drawing history includes first drawing management data, such as the version number, creation date and time, and creator of the first drawing, and management data for each drawing from the second drawing onwards, such as the version number, change date and time, and changer of each drawing from the second drawing onwards. The history creation module creates a list of each drawing management data, arranged in ascending or descending order in chronological order, as a history, based on the first drawing management data acquired with the first drawing and each drawing management data acquired with the second drawing onwards (see FIG. 13). Note that the content and creation method of the history are not limited to the above example and can be designed as appropriate.
[0066] The drawing history created by the history creation module will be described with reference to FIG. 13 . This figure is a diagram that schematically illustrates an example of a history of a created drawing. The figure shows a history 50. In the history 50, the version number, creation date and time, and creator fields for the first drawing are filled with information based on the first drawing management data acquired along with the first drawing. Furthermore, the version number, change date and time, and changer fields for each drawing from the second drawing onward are filled with information based on the version number assigned to each drawing from the second drawing onward and the drawing management data acquired along with each drawing. The history creation module sorts each drawing management data in ascending order in chronological order to create the history 50. As described above, the content and creation method of the history 50 can be designed as appropriate.
[0067] Returning to Fig. 12, the history output process will be described. The history output module outputs the history of the acquired drawing (step S71). The history output module transmits the history of the created drawing as history data to the user terminal 20 based on a request from the user terminal 20, etc. The user terminal 20 receives this history data and displays it on its own display unit. At this time, the user terminal 20 displays the history of the drawing based on this history data on its own display unit via predetermined software. The user terminal 20 displays the history 50 shown in Fig. 13 on its own display unit via predetermined software.
[0068] This completes the history output process.
[0069] [Replication process executed by computer 10] The replication process executed by the computer 10 will be described with reference to Fig. 14. This figure shows a flowchart of the replication process executed by the computer 10. This replication process is a process that uses the layer data for the first drawing generated by the first drawing acquisition process.
[0070] The duplication module duplicates the first drawing layer data (step S80). The duplication module duplicates the first drawing layer data generated in the first drawing acquisition process. Here, the duplication module does not duplicate only the first drawing layer data, but also duplicates objects placed in the first drawing layer data by the object handover process (described later) and data placed or saved in the first drawing layer data, such as construction progress data input by the construction progress handover process, and duplicates the first drawing layer data that includes all of these.
[0071] The second-drawing placement module places the duplicated layer data for the first drawing on the second drawing (step S81). The second-drawing placement module places the duplicated layer data for the first drawing on top of the layer data for the second drawing placed on the second drawing by the second-drawing acquisition process. The second-drawing placement module may place the duplicated layer data for the first drawing on top of the layer data for the second drawing, or may place it between the second drawing and the layer data for the second drawing.
[0072] The second drawing storage module stores the second drawing on which the copied layer data for the first drawing is arranged (step S82). The second drawing storage module further associates the second drawing on which the copied layer data for the first drawing is arranged with the second drawing stored by the processing of step S25 or step S31 and stores the second drawing.
[0073] The above is the duplication process. As a result of the duplication process, two layer data, the duplicated layer data for the first drawing and the duplicated layer data for the second drawing, are arranged on the second drawing. After executing the second drawing acquisition process, when the computer 10 acquires the above-mentioned nth drawing, it only needs to perform a process similar to the duplication process on the n-1th drawing. As a result, each layer data up to the n-1th drawing is duplicated on the nth drawing, and each of the duplicated layer data is arranged on the nth drawing.
[0074] [Object takeover processing executed by computer 10] The object takeover processing executed by the computer 10 will be described with reference to Fig. 15. This figure shows a flowchart of the object takeover processing executed by the computer 10. This object takeover processing is processing that uses the drawings acquired by the first drawing acquisition processing and the second drawing acquisition processing.
[0075] The object acquisition module acquires the placement status of a specific object (step S90). The object may be, for example, an icon (e.g., a camera icon, a stamp icon, a comment icon), a leader line, a figure, or a mark. The object may be associated with a corresponding function (e.g., launching a photography application for a camera icon). The placement status of the object may be, for example, the object's type and placement location. The user terminal 20 accepts input of the placement status of a specific object for the first drawing displayed on its display unit by a switching process or the like. The user terminal 20 accepts input (e.g., tap) of the type of object to be placed and the placement location of the object. For example, the user taps the desired icon type from the object types displayed on the user terminal 20 and taps the location where the object should be placed in the first drawing. The user terminal 20 transmits the accepted object type and placement location as object data to the computer 10. By receiving this object data, the object acquisition module acquires the placement status of the specific object. The object placement status is not limited to the above example and can be designed as appropriate.
[0076] The object placement module places a predetermined object in the layer data for the first drawing (step S91). The object placement module places the object in the layer data for the first drawing based on the acquired placement status of the predetermined object. The object placement module places an object corresponding to the object type in a location in the layer data for the first drawing that corresponds to the placement location of the object (see FIG. 16).
[0077] The objects arranged by the object placement module will be described with reference to FIG. 16 . This figure is a schematic diagram illustrating an example of a state in which predetermined objects are arranged in layer data for a first drawing. In this figure, a first drawing 60 is shown. Generated layer data 61 for a first drawing is overlaid on the first drawing 60. The object placement module places objects 62 to 64 on this layer data 61 for a first drawing based on the acquired object placement status. In this figure, object 62 represents a memo icon, object 63 represents a star-shaped graphic, and object 64 represents a camera icon. Object 62 is associated with predetermined text, images, etc. Object 63 is associated with information such as the importance of the location or the presence of a message. Object 64 is associated with the launch of a photography application, etc.
[0078] 15, the object transfer process will be described in more detail. The object save module saves the placement status of the placed object in the layer data for the first drawing (step S92). The object save module saves the placement status of the placed object in the layer data for the first drawing by adding the placement status of the object to the layer data for the first drawing.
[0079] The object takeover module takes over the arrangement status of the saved objects to the layer data for the second drawing (step S93). The object takeover module places the objects saved in the layer data for the first drawing in the layer data for the second drawing by inputting the arrangement status of the objects saved in the layer data for the first drawing into the layer data for the second drawing that has been arranged in the second drawing, and takes over the arrangement status of the saved objects to the layer data for the second drawing (see FIG. 17). Note that the method by which the object takeover module takes over the arrangement status of the saved objects to the layer data for the second drawing is not limited to the example described above, and can be designed as appropriate.
[0080] The objects inherited by the object takeover module will be described with reference to FIG. 17 . This figure is a schematic diagram illustrating an example of a state in which the layer data for the second drawing has inherited a specific object. The figure shows a second drawing 70. This second drawing 70 is a drawing after the first drawing 60 has been updated. The second drawing 70 is overlaid with the generated layer data for the second drawing 71. Furthermore, as a result of the attention level being changed by the providing process, the layer data for the second drawing 71 has a border 73 added to the corresponding portion of the updated portion 72. The updated portion 72 is similar to the updated portion 31 in FIG. 7 , and the border 73 is similar to the border 33 in FIG. 7 . The object takeover module inputs the placement status of the objects 62 to 64 stored in the layer data for the first drawing 61 into the layer data for the second drawing 71 placed in the second drawing 70, thereby placing the objects 62 to 64 stored in the layer data for the first drawing 61 in the layer data for the second drawing 71. Objects 74 to 76 are objects placed in the layer data 71 for the second drawing. Object 74 is the result of taking over from object 62, object 75 is the result of taking over from object 63, and object 76 is the result of taking over from object 64. The functions and the like associated with each of the objects 74 to 76 are the same as those of the corresponding objects 62 to 64. The types and placement locations of the objects 74 to 76 depend on the types and placement locations of the objects 62 to 64 taken over from the layer data 61 for the first drawing.
[0081] 15, the object inheritance process will be described. The second drawing storage module stores the second drawing on which the layer data for the second drawing, which has inherited the object arrangement status, is arranged (step S94). The second drawing storage module further associates the second drawing on which the layer data for the second drawing, which has inherited the object arrangement status, is arranged with the second drawing stored by the process of step S25 or step S31, and stores the second drawing.
[0082] The above is the object takeover process. As a result of the object takeover process, the second drawing has updated portions with changed attention levels and specified objects in the layer data for the second drawing. After executing the second drawing acquisition process, when the computer 10 acquires the above-mentioned nth drawing, it simply executes the same process as the object takeover process for the n-1th drawing. As a result, the objects placed in the layer data of the n-1th drawing are taken over to the nth drawing.
[0083] The difference between the above-mentioned duplication process and the object handover process is that the duplication process places two layer data, layer data for the first drawing and layer data for the second drawing, on the second drawing, while the object handover process places only layer data for the second drawing on the second drawing.
[0084] [Construction progress handover process executed by computer 10] The construction progress handover process executed by the computer 10 will be described with reference to Fig. 18. The figure is a flowchart of the construction progress handover process executed by the computer 10. This construction progress handover process is a process that uses the first drawing provided by the switching process or the like.
[0085] The construction progress receiving module for the first drawing receives input of construction progress into the layer data for the first drawing (step S100). The user terminal 20 receives the input of construction progress for the first drawing displayed on its display unit by switching processing or the like. For example, the user inputs construction progress using a virtual keyboard or the like displayed on the user terminal 20. The user terminal 20 transmits the received input content to the computer 10. By receiving this input content, the construction progress receiving module for the first drawing receives the input of construction progress into the layer data for the first drawing.
[0086] The construction progress storage module for first drawing stores the received construction progress in the layer data for first drawing (step S101). The construction progress storage module for first drawing inputs the received construction progress into a predetermined position in the layer data for first drawing. The predetermined position is, for example, the position where the user terminal 20 received the construction progress, or a predetermined position in the layer data for first drawing. The construction progress storage module for first drawing inputs the received construction progress into the predetermined position in the layer data for first drawing, thereby saving the received construction progress in the layer data for first drawing.
[0087] The first drawing storage module stores the first drawing on which the layer data for the first drawing that stores the construction progress is arranged (step S102). The first drawing storage module further associates the first drawing on which the layer data for the first drawing that stores the construction progress is arranged with the first drawing stored by the processing of step S13 and stores the first drawing.
[0088] The construction progress handover module handovers the saved construction progress to the layer data for the second drawing (step S103). The construction progress handover module handovers the saved construction progress to the layer data for the second drawing by inputting the construction progress saved in the layer data for the first drawing into the layer data for the second drawing arranged on the second drawing. Note that the method by which the construction progress handover module handovers the saved construction progress to the layer data for the second drawing is not limited to the example and can be designed as appropriate.
[0089] The second drawing storage module stores the second drawing on which the layer data for the second drawing that has inherited the construction progress is arranged (step S104). The second drawing storage module further associates the second drawing on which the layer data for the second drawing that has inherited the construction progress is arranged with the second drawing stored by the processing of step S25 or step S31 and stores the second drawing.
[0090] The above is the construction progress handover process. As a result of the construction progress handover process, the second drawing has the construction progress input received in the first drawing layer data in the layer data for the second drawing. When the computer 10 acquires the above-mentioned nth drawing after executing the second drawing acquisition process, it simply executes the same process as the construction progress handover process for the n-1th drawing. As a result, the construction progress is saved in the layer data for the n-1th drawing, and the nth drawing is inherited from the construction progress saved in the layer data of the n-1th drawing.
[0091] The difference between the above-mentioned duplication process and the construction progress handover process is that the duplication process places two layer data, layer data for the first drawing and layer data for the second drawing, on the second drawing, while the construction progress handover process places only layer data for the second drawing on the second drawing.
[0092] Although the above-described processes are described as separate processes, the computer 10 may be configured to execute a combination of some or all of the above-described processes. Also, the computer 10 may be configured to execute each process at a timing other than the timing described above.
[0093] The above-described means and functions are realized by a computer (including a CPU, an information processing device, and various terminals) reading and executing a predetermined program. The program may be provided, for example, from a computer via a network (Software as a Service (SaaS)) or as a cloud service. The program may also be provided in a form recorded on a computer-readable recording medium. In this case, the computer reads the program from the recording medium, transfers it to an internal or external recording device, records it, and executes it. The program may also be pre-recorded on a recording device (recording medium) and provided to the computer from the recording device via a communication line.
[0094] Although the embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments. Furthermore, the effects described in the embodiments of the present invention are merely a list of the most preferable effects resulting from the present invention, and the effects of the present invention are not limited to those described in the embodiments of the present invention.
[0095] A first aspect disclosed in this embodiment is a drawing updating system that updates construction drawings in accordance with construction progress, and includes: a first drawing acquisition unit 11 that acquires a first drawing related to construction; a second drawing acquisition unit 12 that acquires a second drawing obtained by updating the first drawing in accordance with construction progress; a detection unit 14 that compares the first drawing with the second drawing and detects updated areas; a second drawing generation unit 15 that generates second drawing layer data to be placed on top of the second drawing; a second drawing placement unit 16 that places the generated second drawing layer data on top of the second drawing; an update area attention change unit 17 that changes the attention level of the updated area in the placed second drawing layer data; and a second drawing provision unit 13 that provides the second drawing on which the second drawing layer data reflecting the change in attention level has been placed.
[0096] A second aspect disclosed in this embodiment provides the drawing update system according to the first aspect, further comprising: an assigning unit that assigns to the acquired second drawing a version number that is higher than the version number of the acquired first drawing.
[0097] A third aspect disclosed in this embodiment provides a drawing updating system according to the first aspect, further comprising: a second drawing input receiving unit that receives a predetermined input for the provided second drawing; a first drawing providing unit that provides the first drawing based on the received predetermined input; a first drawing input receiving unit that receives the predetermined input for the provided first drawing; and a switching unit that switches between the first drawing and the second drawing based on the predetermined input for the first drawing or the second drawing.
[0098] A fourth aspect disclosed in this embodiment provides a drawing update system according to the first aspect, further comprising: a second drawing construction progress receiving unit that receives input of the construction progress into the second drawing layer data; and a second drawing construction progress storage unit that stores the received construction progress in the second drawing layer data.
[0099] A fifth aspect disclosed in this embodiment provides a drawing update system according to the first aspect, further comprising: a creation unit that creates a list of the acquired drawings; a list attention change unit that changes the attention level of the latest version of the drawing in the created list; and a list output unit that outputs the list reflecting the change in attention level.
[0100] A sixth aspect disclosed in this embodiment provides the drawing updating system according to the first aspect, further comprising: a history output unit that outputs the acquired history of the drawing.
[0101] A seventh aspect disclosed in this embodiment provides a drawing update system according to the first aspect, further comprising: a first drawing generation unit that generates layer data for a first drawing to be placed over the first drawing; and a first drawing placement unit that places the generated layer data for a first drawing over the first drawing.
[0102] An eighth aspect disclosed in this embodiment provides a drawing update system described in the seventh aspect, further comprising: a duplication unit that duplicates the layer data for the first drawing; and a second drawing placement unit 16 that places the duplicated layer data for the first drawing on the second drawing.
[0103] A ninth aspect disclosed in this embodiment provides a drawing update system according to the seventh aspect, further comprising: an object placement unit that places a predetermined object in the layer data for the first drawing; an object storage unit that stores the placement status of the placed object in the layer data for the first drawing; and an object handover unit that transfers the stored placement status of the object to the layer data for the second drawing.
[0104] A tenth aspect disclosed in this embodiment provides a drawing update system according to the seventh aspect, further comprising: a construction progress receiving unit for first drawing that receives input of the construction progress into the layer data for the first drawing; and a construction progress storage unit for first drawing that stores the received construction progress in the layer data for the first drawing.
[0105] An eleventh aspect disclosed in this embodiment provides a drawing update system according to the seventh aspect, further comprising a construction progress handover unit that handovers the stored construction progress to the second drawing layer data.
[0106] 1 Drawing update system 7 Network 10 Computer 11 First drawing acquisition unit 12 Second drawing acquisition unit 13 Second drawing provision unit 14 Detection unit 15 Second drawing generation unit 16 Second drawing placement unit 17 Update portion attention change unit 20 User terminal 30 Second drawing 31 Update portion 32 Layer data for second drawing 33 Border line 40 List 41 (41a to 41i) Version number 42 (42a to 42i) Drawing thumbnail 43 Icon 50 History 60 First drawing 61 Layer data for first drawing 62 Object 63 Object 64 Object 70 Second drawing 71 Layer data for second drawing 72 Update portion 73 Border line 74 Object 75 Object 76 Object
Claims
1. A drawing updating system for updating construction drawings in accordance with construction progress, comprising: a first drawing acquisition unit for acquiring a first drawing related to construction; a second drawing acquisition unit for acquiring a second drawing obtained by updating the first drawing in accordance with construction progress; a detection unit for comparing the first drawing with the second drawing and detecting updated areas; a second drawing generation unit for generating layer data for the second drawing to be placed over the second drawing; a second drawing placement unit for placing the generated layer data for the second drawing over the second drawing; an update area attention change unit for changing the attention of the updated areas in the placed layer data for the second drawing; and a second drawing provision unit for providing the second drawing on which the second drawing layer data reflecting the change in attention has been placed.
2. A drawing update system as described in claim 1, further comprising: an assignment unit that assigns to the acquired second drawing a version number higher than that of the acquired first drawing.
3. The drawing updating system of claim 1, further comprising: a second drawing input receiving unit that receives a specified input for the provided second drawing; a first drawing providing unit that provides the first drawing based on the received specified input; a first drawing input receiving unit that accepts the specified input for the provided first drawing; and a switching unit that switches between the first drawing and the second drawing based on the specified input for the first drawing or the second drawing.
4. The drawing update system as described in claim 1, further comprising: a second drawing construction progress receiving unit that receives input of the construction progress into the second drawing layer data; and a second drawing construction progress storage unit that stores the received construction progress in the second drawing layer data.
5. A drawing update system as described in claim 1, further comprising: a creation unit that creates a list of the acquired drawings; a list attention change unit that changes the attention level of the latest drawing in the created list; and a list output unit that outputs the list reflecting the change in attention level.
6. The drawing updating system according to claim 1, further comprising: a history output unit that outputs the history of the acquired drawing.
7. A drawing update system as described in claim 1, further comprising: a first drawing generation unit that generates layer data for a first drawing to be overlaid on the first drawing; and a first drawing placement unit that overlays the generated layer data for the first drawing on the first drawing.
8. A drawing update system as described in claim 7, further comprising: a duplication unit that duplicates the layer data for the first drawing; and wherein the placement unit for the second drawing places the duplicated layer data for the first drawing on the second drawing.
9. A drawing update system as described in claim 7, further comprising: an object placement unit which places a specified object in the layer data for the first drawing; an object storage unit which stores the placement status of the placed object in the layer data for the first drawing; and an object transfer unit which transfers the stored placement status of the object to the layer data for the second drawing.
10. A drawing update system as described in claim 7, further comprising: a construction progress receiving unit for the first drawing that receives input of the construction progress into the layer data for the first drawing; and a construction progress storage unit for the first drawing that stores the received construction progress in the layer data for the first drawing.
11. The drawing update system according to claim 10, further comprising a construction progress handover unit that handovers the stored construction progress to the second drawing layer data.
12. A drawing updating method executed by a computer for updating construction drawings in accordance with construction progress, comprising the steps of: acquiring a first drawing related to construction; acquiring a second drawing obtained by updating the first drawing in accordance with construction progress; comparing the first drawing with the second drawing and detecting updated areas; generating layer data for the second drawing to be placed over the second drawing; overlaying the generated layer data for the second drawing on the second drawing; changing the attention level of the updated areas in the placed layer data for the second drawing; and providing the second drawing on which the layer data for the second drawing reflecting the change in attention level is placed.
13. A computer-readable program for causing a computer that updates construction drawings in accordance with construction progress to execute the following steps: acquiring a first drawing related to construction; acquiring a second drawing obtained by updating the first drawing in accordance with construction progress; comparing the first drawing with the second drawing and detecting updated areas; generating layer data for the second drawing to be placed over the second drawing; placing the generated layer data for the second drawing over the second drawing; changing the attention level of the updated areas in the placed layer data for the second drawing; and providing the second drawing on which the layer data for the second drawing reflecting the change in attention level is placed.
Citation Information
Patent Citations
System for preparing drawing
JP1998240793A
Building design construction managing system
JP2002197126A
Information delivery system of construction related drawing, and the like
JP2009301308A
Image processing device and program for image processing
JP2019160122A
Information processor, information processing method, and program
JP2021140593A