Method for starting power generation system, and power generation system

The power generation system stabilizes the transition from motoring to power generation in the organic Rankine cycle by using a bypass line and flow control valve with an induction generator parallel to a main generator, reducing costs and improving efficiency by eliminating the need for an inverter and converter.

WO2024202385A1PCT designated stage expired Publication Date: 2024-10-03MITSUBISHI HEAVY IND LTD +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2024/000635
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-03-30
Filing Date
2024-01-12
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

Existing power generation systems using organic Rankine cycles face challenges in stabilizing the transition from motoring to power generation mode and incur increased costs due to the inclusion of an inverter device with the generator.

Method used

A power generation system comprising a condenser, evaporator, and turbine with a circulation line, bypass line, flow control valve, and induction generator, where the induction generator is parallel to a main generator, and a switching device controls the flow to stabilize the transition from motoring to power generation, reducing the need for an inverter and converter.

Benefits of technology

The system stably starts the induction generator, reduces costs, and suppresses voltage drops and inrush currents, allowing the induction generator to supply power efficiently without the need for additional conversion equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2024000635_03102024_PF_FP_ABST
    Figure JP2024000635_03102024_PF_FP_ABST
Patent Text Reader

Abstract

A method for starting a power generation system, the method comprising: a turbine startup step for adjusting the opening degree of a flow control valve, thereby increasing a main flow rate that is the flow rate of an organic medium flowing into a turbine; a generator motoring step for switching a switching device from a disabled state to an enabled state, and starting power supply from a power grid to an induction generator, when the revolution speed of the induction generator increased by execution of the turbine startup step reaches a desired revolution speed; a turbine acceleration step for adjusting the opening degree of the flow control valve, and further increasing the main flow rate, after execution of the generator motoring step; and a power generation start step for starting supply of power to the power grid by the induction generator, which is switched from motor to generator, when the revolution speed of the induction generator has exceeded a synchronous revolution speed that is greater than the desired revolution speed.
Need to check novelty before this filing date? Find Prior Art

Description

Method for starting a power generation system and power generation system

[0001] The present disclosure relates to a method for starting a power generation system using an organic Rankine cycle, and to a power generation system. This application claims priority to Japanese Patent Application No. 2023-054454, filed with the Japan Patent Office on March 30, 2023, the contents of which are incorporated herein by reference.

[0002] In the power generation system disclosed in Patent Document 1, an organic fluid evaporated in an evaporator drives a power turbine, which generates electricity. The generated electricity is then sent to an onboard power system after its frequency is adjusted by an inverter device.

[0003] JP 2011-231636 A

[0004] In the above power generation system, the generator is equipped with an inverter device, which may increase costs. Furthermore, when the generator performs motoring upon startup of the power generation system, it is preferable that the generator stably switches from motoring mode to power generation mode. However, the above patent document does not disclose a specific configuration.

[0005] An object of the present disclosure is to provide a power generation system startup method that can stably start an induction generator and achieves low costs, and a power generation system.

[0006] A start-up method for a power generation system according to at least one embodiment of the present disclosure is a start-up method for a power generation system including a condenser, an evaporator, and a turbine, the power generation system including: a circulation line through which an organic medium serving as a heat medium flows through the condenser, the evaporator, and the turbine in this order; a bypass line through which the organic medium discharged from the evaporator bypasses the turbine and leads it to the condenser; a flow regulating valve for adjusting a ratio between a bypass flow rate of the organic medium flowing through the bypass line and a main flow rate which is a flow rate of the organic medium flowing into the turbine; an induction generator connected to the turbine; and a switching device configured to switch between an enabling state that enables conduction between the induction generator and a power grid and a disabling state that disables the conduction, the induction generator being provided in parallel with a main generator constituting the power grid and having a larger capacity than the induction generator, the start-up method for the power generation system including: a turbine start-up step of increasing the main flow rate by adjusting an opening of the flow regulating valve; a generator motoring step of switching the switching device from the prohibited state to the permitted state when the target rotation speed is reached, and starting the supply of power from the power grid to the induction generator; a turbine speed-up step of adjusting the opening of the flow regulating valve to further increase the main flow rate after the generator motoring step is performed; and a power generation start step of, when the rotation speed of the induction generator exceeds a synchronous rotation speed that is higher than the target rotation speed, starting the supply of power from the induction generator that has switched from an electric motor to a generator to the power grid.

[0007] a turbine start-up control unit configured to increase the main flow rate by controlling an opening degree of the flow regulation valve; a turbine start-up control unit configured to increase the main flow rate by controlling an opening degree of the flow regulation valve; a flow rate control unit configured to increase the main flow rate by controlling an opening degree of the flow regulation valve; a flow rate control unit configured to increase the main flow rate by controlling an opening degree of the flow regulation valve; an induction generator connected to the turbine; a switching device configured to switch between an enabling state that enables conduction between the induction generator and a power grid and a disabling state that disables conduction; and a controller; The turbine speed control unit includes a generator motoring control unit that switches the switching device from the prohibited state to the permitted state when the rotation speed of the induction generator, which increases due to the opening control of the turbine start-up control unit, reaches a target rotation speed; and a turbine speed increase control unit that adjusts the opening of the flow regulating valve to further increase the main flow rate after the switching device switches to the permitted state so that the rotation speed of the induction generator exceeds a synchronous rotation speed which is higher than the target rotation speed.

[0008] According to the present disclosure, it is possible to provide a power generation system startup method and a power generation system that can stably start an induction generator and achieve low costs.

[0009] FIG. 1 is a schematic diagram of a power generation system according to an embodiment; FIG. 2 is a graph schematically showing a change over time in the rotation speed of an induction generator performing a startup operation according to an embodiment; FIG. 3 is a schematic diagram showing a functional configuration of a controller according to an embodiment; FIG. 4 is a flowchart showing a startup method of a power generation system according to an embodiment; FIG. 5 is a flowchart showing a method of operating a power generation system when a trip occurs according to an embodiment;

[0010] Several embodiments of the present disclosure will be described below with reference to the accompanying drawings. However, the dimensions, materials, shapes, relative arrangements, etc. of components described as embodiments or shown in the drawings are not intended to limit the scope of the present disclosure and are merely illustrative examples. For example, expressions expressing relative or absolute arrangements, such as "in a certain direction," "along a certain direction," "parallel," "orthogonal," "center," "concentric," or "coaxial," not only strictly express such arrangements, but also express relative displacements with a tolerance or angle or distance to the extent that the same function is achieved. For example, expressions expressing the equality of things, such as "same," "equal," and "homogeneous," not only express strict equality, but also express tolerance or differences to the extent that the same function is achieved. For example, expressions expressing shapes such as a square or cylindrical shape not only express shapes such as a square or cylindrical shape in the strict geometric sense, but also express shapes including concave and convex portions, chamfered portions, etc., to the extent that the same effect is achieved. On the other hand, the expressions "comprise," "include," or "have" one component are not exclusive expressions that exclude the existence of other components. Note that similar components may be assigned the same reference numerals and descriptions thereof may be omitted.

[0011] <Overall Configuration of Power Generation System 1> Figure 1 is a schematic diagram of a power generation system 1 according to an embodiment of the present disclosure. The power generation system 1 of this example includes a power grid 5, a main generator 2 connected to the power grid 5, an emergency generator 3 connected in parallel to the main generator 2 via the power grid 5, and a predetermined device 7 configured to receive a supply of power from the power grid 5. The predetermined device 7 may be anything that operates when power is supplied, and an example of the predetermined device 7 is one or more driving devices such as a motor. The power generation system 1 may be installed on a ship or on land, but the following example illustrates a power generation system 1 installed on a ship. Note that the emergency generator 3 is not an essential component of the present disclosure.

[0012] The power system 5 includes a bus 8 and switching devices 9A to 9C. The switching device 9A is configured to switch the conduction state between the bus 8 and the main generator 2. Similarly, the switching device 9B is configured to switch the conduction state between the bus 8 and the emergency generator 3, and the switching device 9C is configured to switch the conduction state between the bus 8 and a predetermined device 7. As an example, the switching devices 9A to 9C are circuit breakers configured to switch between an allowable state that allows conduction and a prohibitable state that prohibits conduction.

[0013] Power generation system 1 further includes power generation system 10 configured to utilize an organic medium, which may be, for example, R-245fa or R1233zd(E) (i.e., HFO-1233zd(E)), as a heat transfer medium. Power generation system 10 includes induction generator 15 configured to rotate integrally with turbine 13. Induction generator 15 is provided in parallel with main generator 2 and emergency generator 3 via bus 8 of power grid 5. Note that the capacity of main generator 2 is greater than the capacity of induction generator 15 and emergency generator 3. During normal operation of power generation system 1, predetermined equipment 7 receives power from each of main generator 2 and induction generator 15, but the frequency of the power supply depends on the frequency of main generator 2. Therefore, induction generator 15 does not require a converter or inverter.

[0014] <Configuration of Power Generation System 10> The power generation system 10 includes a condenser 11, an evaporator 12, and a turbine 13. The condenser 11 is configured to condense the organic medium using cooling water such as natural water (more specifically, seawater). The evaporator 12 is configured to evaporate the organic medium using heat contained in, for example, hot water. The turbine 13 is configured to rotate using the gaseous organic medium as a working medium.

[0015] The power generation system 10 further includes a circulation line 20 through which the organic medium flows in sequence through the condenser 11, the evaporator 12, and the turbine 13. The circulation line 20 includes a condenser-evaporator line 23 connecting the condenser 11 and the evaporator 12, an evaporator-turbine line 21 connecting the evaporator 12 and the turbine 13, and a turbine condenser line 22 connecting the turbine 13 and the condenser 11. The condenser-evaporator line 23 is provided with a pump device 16 for sending the organic medium discharged from the condenser 11 to the evaporator 12.

[0016] The power generation system 10 further includes a bypass line 25 for guiding the organic medium discharged from the evaporator 12 to the condenser 11, bypassing the turbine 13. An inlet 25A of the bypass line 25 is connected to the evaporator-turbine line 21 between the evaporator 12 and the turbine 13, and an outlet 25B of the bypass line 25 is connected to the turbine-condenser line 22 between the turbine 13 and the condenser 11.

[0017] The power generation system 10 includes a flow regulation valve 30 for adjusting the ratio between a bypass flow rate, which is the flow rate of the organic medium flowing through the bypass line 25, and a main flow rate, which is the flow rate of the organic medium flowing into the turbine 13. The flow regulation valve 30 illustrated in FIG. 1 includes a first flow regulation valve 31 provided in the evaporator turbine line 21 and a bypass flow regulation valve 35 provided in the bypass line 25. The first flow regulation valve 31 is located between an inlet 25A of the bypass line 25 and the turbine 13. By controlling the opening degrees of each of the first flow regulation valve 31 and the bypass flow regulation valve 35, the main flow rate is adjusted and the rotation speed of the turbine 13 is controlled. Note that the power generation system 10 of this example further includes an on-off valve 29 provided in the evaporator turbine line 21 between the inlet 25A and the first flow regulation valve 31.

[0018] The power generation system 10 further includes a switching device 14 for switching the conduction state between the induction generator 15 and the bus 8 of the power system 5. As an example, the switching device 14 is a circuit breaker configured to switch between an enabling state that allows conduction and a disabling state that prohibits conduction.

[0019] The rotation speed of the induction generator 15 changes by adjusting the main flow rate through the opening control of the flow regulation valve 30. When the switching device 14 switches from the prohibited state to the permitted state while the rotation speed of the induction generator 15 is below the synchronous rotation speed, the induction generator 15 receives power supply from the power grid 5 and operates as an electric motor. In other words, the induction generator 15 motors. As a result, the rotation speed of the induction generator 15 increases to the synchronous rotation speed. Here, the synchronous rotation speed is the rotation speed of the induction generator 15 that corresponds to the frequency of the power grid 5. The synchronous rotation speed may be the rated rotation speed of the induction generator 15.

[0020] On the other hand, if switching device 14 maintains the permitted state and the rotation speed of induction generator 15 exceeds the synchronous rotation speed, the electromotive force generated in the stator coil of induction generator 15 by the rotation of the rotor of induction generator 15 exceeds the potential of bus 8 that has been supplying power to induction generator 15, and the direction of power flow between induction generator 15 and power grid 5 is switched. At this time, induction generator 15 functions as a generator and supplies power to power grid 5. The power is supplied to predetermined equipment 7.

[0021] FIG. 2 is a graph showing the change in the rotational speed of the induction generator 15 over time during the startup operation of the power generation system 10. The horizontal axis of the graph represents time, and the vertical axis represents the rotational speed of the induction generator 15. The startup operation of the power generation system 10 of this example is outlined below. At the start of startup, the switching device 14 is in the prohibited state. First, the organic medium flows into the turbine 13, causing the induction generator 15 to start rotating (0≦t<t1). When the rotational speed of the induction generator 15 reaches a target rotational speed that is lower than the synchronous rotational speed (t=t1), the switching device 14 switches to the permitted state. In this case, the induction generator 15 starts motoring by receiving power from the power grid 5. When the rotational speed of the induction generator 15 further increases due to the opening control of the flow regulation valve 30 and exceeds the synchronous rotational speed (t>t2), the induction generator 15 functions as a generator and supplies power to the power grid 5. In this way, the rotation speed of the turbine 13 is increased by the organic medium before motoring starts, so that at the start of motoring, the voltage drop in the power grid 5 can be suppressed and the inrush current of the induction generator 15 can be reduced.

[0022] The target rotation speed is, for example, 95% or more and less than 100% of the synchronous rotation speed. In this case, it is possible to suppress the voltage drop in the power grid 5 and reduce the inrush current of the induction generator 15, as well as reduce the starting torque of the turbine 13.

[0023] <Heat Source System of Evaporator 12> Returning to FIG. 1 , the power generation system 10 includes a hot water supply line 121 for supplying hot water to the evaporator 12 as a heat source for evaporating the organic medium, a hot water discharge line 122 for flowing hot water discharged from the evaporator 12, a hot water bypass line 125 connected to the hot water supply line 121 and the hot water discharge line 122 so as to bypass the evaporator 12, and a hot water flow control valve 127. The hot water flow control valve 127 is configured to change the ratio between a main hot water flow rate, which is the flow rate of hot water flowing into the evaporator 12, and a hot water bypass flow rate, which is the flow rate of hot water flowing through the hot water bypass line 125. In this example, the hot water flow control valve 127 is a three-way valve provided at the connection position of the hot water bypass line 125 and the hot water supply line 121. In other examples, the hot water flow control valve 127 may be a flow control valve provided in each of the hot water supply line 121 and the hot water flow control valve 127.

[0024] The hot water flowing through the hot water supply line 121 is water heated by the heating device 70. The heating device 70 in this example is a heat exchanger configured to heat water through heat exchange between the water and exhaust gas discharged from the marine main engine 79. In other words, the hot water supply line 121 in this example is configured to supply hot water heated by the exhaust gas discharged from the marine main engine 79 to the evaporator 12. However, as described above, the power generation system 10 may be installed on land. In this case, the heating device 70 may be, for example, a boiler, and the marine main engine 79 is not an essential component of the present disclosure. Furthermore, a boiler may be provided on the ship, and jacket water, which is engine cooling water, may be used as the heat source.

[0025] If the aperture of the flow regulation valve 30 is constant, the greater the heat capacity of the hot water flowing into the evaporator 12, the greater the main flow rate of the organic medium flowing from the evaporator 12 into the turbine 13, and the greater the output power of the induction generator 15 (i.e., the load on the induction generator 15). When the controller 90, a component of the power generation system 10, determines that the power measured by the power meter 91 exceeds the specified power, it controls the aperture of the hot water flow regulation valve 127 to increase the hot water bypass flow rate and reduce the main hot water flow rate (details will be described later).

[0026] <Controller 90> The controller 90 has the following mechanical configuration. The controller 90 is configured as a computer and includes a processor, memory (storage medium), and an external communication interface. The processor may be a CPU, GPU, MPU, DSP, or a combination thereof. In other embodiments, the processor may be implemented as an integrated circuit such as a PLD, ASIC, FPGA, or MCU. The memory is configured to temporarily or non-temporarily store various data and may be implemented, for example, by at least one of RAM, ROM, and flash memory. The processor executes various control processes according to instructions from programs loaded into the memory. These control processes include the processor sending control signals to the switching devices 9A-9C, 14, the flow regulation valve 30, the hot water flow regulation valve 127, and the on-off valve 29, and acquiring measurement results from the power meter 91 and the rotation speed meter 98.

[0027] 3 is a schematic diagram showing the functional configuration of a controller 90 according to an embodiment of the present disclosure. The controller 90 includes a turbine startup control unit 81, a generator motoring control unit 82, and a turbine speed increase control unit 83.

[0028] The turbine startup control unit 81 is configured to increase the main flow rate of the organic medium flowing into the turbine 13 by controlling the opening of the flow regulation valve 30 when the power generation system 10 begins to start up. More specifically, the turbine startup control unit 81 is configured to send a control signal to the first flow regulation valve 31 to increase its opening, and to the bypass flow regulation valve 35 to decrease its opening. When these control signals are sent, the induction generator 15 starts up together with the turbine 13, and the rotation speed of the induction generator 15 increases. Note that the turbine startup control unit 81 in this example also executes processing to send an open signal to the on-off valve 29. When the open signal is input, the on-off valve 29 switches from a closed state to an open state.

[0029] The generator motoring control unit 82 is configured to switch the switching device 14 from the prohibited state to the permitted state when the rotation speed of the induction generator 15, which is increased by the aperture control of the turbine startup control unit 81, reaches the target rotation speed. More specifically, the generator motoring control unit 82 is configured to determine whether the measurement result of the rotation speed measuring device 98 has reached the target rotation speed. When the generator motoring control unit 82 determines that the measurement result has reached the target rotation speed, the generator motoring control unit 82 transmits a control signal to the switching device 14 to switch from the prohibited state to the permitted state. When this control signal is transmitted, the rotation speed of the induction generator 15 is equal to or lower than the synchronous rotation speed, so the induction generator 15 performs motoring using power supplied from the power grid 5 (more specifically, using power supplied from the main generator 2). Thereafter, the rotation speed of the induction generator 15 increases to the synchronous rotation speed.

[0030] After the switching device 14 switches from the prohibited state to the permitted state, the turbine speed-up control unit 83 adjusts the opening of the flow regulation valve 30 to further increase the main flow rate of the organic medium flowing into the turbine 13 so that the rotational speed of the induction generator 15 exceeds the synchronous rotational speed. More specifically, the turbine speed-up control unit 83 is configured to send a control signal to the first flow regulation valve 31 to further increase the opening, and to the bypass flow regulation valve 35 to further decrease the opening. As a more detailed example, the first flow regulation valve 31 is configured to be fully opened. As a result of the further increase in the main flow rate of the organic medium flowing into the turbine 13, the rotational speed of the induction generator 15 exceeds the synchronous rotational speed. The induction generator 15 switches from an electric motor to a generator, and power is supplied from the induction generator 15 to the power grid 5.

[0031] According to the above configuration, motoring power is supplied from the power grid 5 to the induction generator 15 after the rotational speed of the induction generator 15 reaches the target rotational speed. This reduces the inrush current of the induction generator 15 at the start of motoring, enabling stable startup of the induction generator 15. This also reduces voltage drops in the power grid 5 and the starting torque of the turbine 13. Furthermore, the turbine speed increase control unit 83 increases the mainstream flow of the organic refrigerant, causing the rotational speed of the induction generator 15 to exceed the synchronous rotational speed, and the induction generator 15 switches from a motor to a generator. Since the organic medium continuously flows into the turbine 13, the generator rotational speed is prevented from fluctuating around the synchronous rotational speed. Furthermore, when the induction generator 15 starts generating power, the induction generator 15 can supply power to the specified device 7 together with the main generator 2. Since the induction generator 15 does not supply power to the specified device 7 alone, an inverter and converter for the induction generator 15 are not required, resulting in a more cost-effective power generation system 10. As a result, the power generation system 10 can stably start the induction generator 15 and achieves low costs.

[0032] The inrush current of induction generator 15 is the peak current that flows through the stator coil of induction generator 15 at the moment motoring starts. After a certain amount of time has passed since motoring started, the current flowing through the stator coil becomes smaller than the peak current.

[0033] Continuing with the description of the configuration of the controller 90, the controller 90 may further include a trip determination unit 84, a shutoff control unit 85, and a turbine deceleration control unit 86, although these are not essential components of the present disclosure.

[0034] The trip determination unit 84 is configured to determine whether to trip the power generation system 10. More specifically, the trip determination unit 84 is configured to determine whether the trip conditions of the power generation system 10 are satisfied. As an example, when at least one of the following events (A) to (C) occurs, it is determined that the trip conditions are satisfied: (A) Vibrations exceeding a specified level are applied to the power generation system 10; (B) A trip command is input to the controller 90; or (C) The switching device 14 is switched from a permitted state to a prohibited state.

[0035] The cutoff control unit 85 is configured to switch the switching device 14 from the permitted state to the prohibited state when the trip determination unit 84 determines that the power generation system 10 will trip. More specifically, when a trip condition is satisfied, the cutoff control unit 85 sends a control signal to the switching device 14 to switch from the permitted state to the prohibited state. When the switching device 14 switches to the prohibited state, the power supply by the induction generator 15 stops.

[0036] The cutoff control unit 85 of this example does not execute the control process when the event (C) above occurs (because the switching device 14 has already been switched to the prohibited state). That is, the cutoff control unit 85 of this example switches the switching device 14 to the prohibited state only when at least one of the events (A) or (B) among the events (A) to (C) above occurs.

[0037] Furthermore, when the switching device 14 switches from the permitted state to the prohibited state, the main generator 2 supplies power to the predetermined device 7 while supplementing the power supplied by the induction generator 15. Such power supply from the main generator 2 is performed without the controller 90 performing any special control process.

[0038] The turbine deceleration control unit 86 is configured to decelerate the turbine 13 by controlling the opening degree of the flow regulation valve 30 when a trip condition of the power generation system 10 is satisfied. More specifically, the turbine deceleration control unit 86 is configured to send a control signal to the bypass flow regulation valve 35 to increase the opening degree, and to send a control signal to the first flow regulation valve 31 to decrease the opening degree. When these control signals are sent, the bypass flow rate of the organic medium increases and the mainstream flow rate of the organic medium decreases, causing the turbine 13 to decelerate.

[0039] In this example, a control signal for setting the opening degree to 0% is sent from the turbine deceleration control unit 86 to the first flow regulation valve 31. In other words, the turbine 13 is stopped by the control processing of the turbine deceleration control unit 86. Furthermore, in this example, the turbine deceleration control unit 86 is configured to also send a close signal to the on-off valve 29 when the trip condition is satisfied. With this configuration, the on-off valve 29 is closed when the trip condition is satisfied, reliably preventing the inflow of the organic medium into the turbine 13. Furthermore, in this example, the on-off valve 29 and the first flow regulation valve 31 are provided between the inlet 25A of the bypass line 25 and the turbine 13 (see FIG. 1), so that the turbine 13 can quickly perform a stop operation in accordance with the control processing of the turbine deceleration control unit 86.

[0040] Furthermore, in this example, when the trip condition of the power generation system 10 is satisfied, the hot water flow adjustment valve 127 is opened. The hot water bypass flow rate increases, and the amount of heat input to the evaporator 12 decreases.

[0041] According to the above configuration, when the trip condition is satisfied, the turbine deceleration control unit 86 controls the opening of the flow regulation valve 30. This allows the process of decelerating the turbine 13 to be immediately executed when the power generation system 10 trips. Furthermore, even if the power generation system 10 stops generating power due to a trip of the power generation system 10, the main generator 2 continues to supply power while supplementing the power supplied by the induction generator 15, allowing the predetermined equipment 7 to continue operating.

[0042] The following continues the description of the configuration of the controller 90. Although not essential components of the present disclosure, the controller 90 may further include an overload determination unit 87 and a generator load reduction control unit 88.

[0043] The overload determination unit 87 is configured to determine whether the output power of the induction generator 15 has exceeded a specified power based on the measurement results of the power meter 91. The specified power is a threshold value for determining whether the output power (i.e., the load) of the induction generator 15 is excessive. The generator load reduction control unit 88 is configured to control the aperture of the hot water flow control valve 127 to reduce the main hot water flow rate flowing into the evaporator 12 and to increase the hot water bypass flow rate when it is determined that the output power of the induction generator 15 has exceeded the specified power. In this example, the main hot water flow rate and the hot water bypass flow rate are controlled by controlling the aperture of the hot water flow control valve 127, which is a three-way valve.

[0044] If the heat capacity of the hot water flowing into the evaporator 12 increases due to an increase in the output of the marine main engine 79, the amount of heat input from the hot water to the evaporator 12 increases, which increases the main flow rate of the organic medium flowing into the turbine 13, and this may result in excessive output power from the induction generator 15. In this regard, with the above-described configuration, when it is determined that the output power of the induction generator 15 has exceeded the specified power, the main hot water flow rate is reduced, thereby preventing the load on the induction generator 15 from becoming excessive.

[0045] If the power generation system 10 is an ORC system instead of the waste heat ORC system shown in FIG. 1 , a seawater supply line is provided instead of the hot water supply line 121, a seawater bypass line is provided instead of the hot water bypass line 125, a seawater control valve is provided instead of the hot water flow adjustment valve 127, and liquid LNG is supplied to the condenser 11 instead of cooling water. The temperature of the seawater flowing through the seawater supply line is maintained almost constant. Vaporized LNG discharged from the condenser 11 is supplied to the demand destination. Since the amount of LNG required by the demand destination changes, the amount required to condense the organic medium in the condenser 11 fluctuates. Therefore, when an ORC system is applied, the process by which the seawater control valve is controlled when an overload occurs differs from the process by which the hot water flow adjustment valve 127 is controlled in the waste heat ORC system.

[0046] Specifically, when the demand for LNG at the demand destination decreases, the amount of liquid LNG supplied to the condenser 11 also decreases. In this case, the amount of heat held in the circulation line 20 increases, and if this amount of heat held exceeds a predetermined value, an overload occurs in the induction generator 15. In this case, the seawater control valve is controlled to release seawater into the seawater bypass line, thereby reducing the amount of heat input to the evaporator 12 (the amount of heat input to the circulation line 20).

[0047] <Start-up method of power generation system 10> A start-up method of the power generation system 10 will be described with reference to Figures 3 and 4. Figure 4 is a flowchart showing an operation method of the power generation system 10 according to an embodiment of the present disclosure. The operation method includes a start-up method of the power generation system 10. At least a part of the operation method is realized by control processing of a processor constituting the controller 90. In the following description, "step" may be abbreviated as "S", and the processor of the controller 90 may be abbreviated as "processor". Before the operation method of the power generation system 10 is started, the turbine 13 is stopped, and the switching device 14 is in a prohibited state.

[0048] First, a turbine startup step (S11) is executed in which the opening of the flow regulation valve 30 is adjusted to increase the main flow rate of the organic medium flowing into the turbine 13. S11 is executed by a processor, and the processor that executes S11 is an example of the turbine startup control unit 81. By executing S11, the rotation speed of the turbine 13 gradually increases.

[0049] Next, a generator motoring step (S13) is executed. In S13, when the rotation speed of induction generator 15 reaches the target rotation speed, switching device 14 switches from the inhibited state to the permitted state, and power supply from power grid 5 to induction generator 15 begins. At this timing, induction generator 15 starts as an electric motor. S13 is executed by a processor, and the processor that executes S13 is an example of generator motoring control unit 82.

[0050] Next, a turbine speed-up step (S15) is executed in which the opening of the flow regulation valve 30 is adjusted to further increase the main flow rate flowing into the turbine 13. S15 is executed by a processor, and the processor that executes S15 is an example of the turbine speed-up control unit 83. Execution of S15 further increases the rotation speed of the induction generator 15. Note that the first flow regulation valve 31 is fully opened when the output of the induction generator 15 relative to the amount of heat input from the hot water supply line 121 to the evaporator 12 is maximized. The first flow regulation valve 31 is fully opened when t≧t2 in FIG. 2 .

[0051] After S15 is executed, a power generation start step (S17) is executed. In S17, the rotation speed of induction generator 15 exceeds the synchronous rotation speed, and induction generator 15 switches from an electric motor to a generator, and starts supplying power to power grid 5. S17 is a step that is implemented after S15 is executed, and the processor does not need to perform any special control processing in S17. After S17 is executed, the flowchart in FIG. 4 ends.

[0052] <Operation Method of Power Generation System 10 When Trip Occurs> FIG. 5 is a flowchart showing an operation method of the power generation system 10 when a trip occurs.

[0053] If it is determined that the trip condition is satisfied, the switching device 14 is switched from the permitted state to the prohibited state (S21). S21 is executed by a processor, and the processor that executes S21 is an example of the cutoff control unit 85.

[0054] Next, a turbine deceleration step (S23) is executed in which the bypass flow rate of the organic medium is increased and the main flow rate of the organic medium flowing into the turbine 13 is reduced by controlling the opening of the flow regulation valve 30. In this example, in S23, the turbine 13 is stopped and the induction generator 15 is also stopped. S23 is executed by a processor, and the processor that executes S23 is an example of the turbine deceleration control unit 86.

[0055] Next, the opening control of the hot water flow adjustment valve 127 is executed (S24), the hot water bypass flow rate increases, and the amount of heat input to the evaporator 12 decreases.

[0056] Next, a power supply continuation step (S25) is executed in which the main generator 2 continues to supply power to the predetermined equipment 7 while supplementing the power previously supplied to the predetermined equipment 7 by the induction generator 15. S25 is executed automatically as a result of execution of S21. No special control processing by the processor is required in S25. The flowchart of FIG. 5 then ends.

[0057] <Operation Method of Power Generation System 10 When Overload Occurs> Fig. 6 is a flowchart showing the operation method of power generation system 10 when an overload occurs. First, it is determined whether the load on induction generator 15 is excessive based on the measurement result of power meter 91 (S27). S27 is executed by a processor, and the processor executing S27 is an example of overload determination unit 87. If it is determined that the load on induction generator 15 is not excessive (S27: NO), the flowchart in Fig. 6 ends. Operation of power generation system 10 continues thereafter.

[0058] If it is determined that the load on the induction generator 15 is excessive (S27: YES), a generator load reduction step (S29) is executed. In S29, the opening of the hot water flow control valve 127 is controlled to reduce the main hot water flow rate flowing into the evaporator 12 and increase the hot water bypass flow rate. S29 is executed by a processor, and the processor that executes S29 is an example of the generator load reduction control unit 88. Then, the flowchart in FIG. 6 ends.

[0059] As described above, the flow regulation valve 30 (see FIG. 1 ) includes the first flow regulation valve 31 provided in the evaporator turbine line 21 between the inlet 25A of the bypass line 25 and the turbine 13, and the bypass flow regulation valve 35 provided in the bypass flow regulation valve 35. Then, in the turbine startup step (S11) and the turbine speed increase step (S15), the opening degree of the bypass flow regulation valve 35 is decreased, and the opening degree of the first flow regulation valve 31 is increased. With the above configuration, the first flow regulation valve 31 is disposed immediately before the turbine 13, so that the mainstream flow rate of the organic medium flowing into the turbine 13 can be accurately controlled in each of S11 and S15.

[0060] <Summary> The contents described in the above-described embodiments can be understood, for example, as follows.

[0061] 1) A power generation system (10) according to an embodiment of the present disclosure is a method for starting up a power generation system including a condenser (11), an evaporator (12), and a turbine (13), the power generation system including: a circulation line (20) through which an organic medium serving as a heat medium flows through the condenser, the evaporator, and the turbine in that order; a bypass line (25) through which the organic medium discharged from the evaporator bypasses the turbine and leads it to the condenser; a flow control valve (30) for adjusting a ratio between a bypass flow rate of the organic medium flowing through the bypass line and a main flow rate which is the flow rate of the organic medium flowing into the turbine; an induction generator (15) connected to the turbine; and a switching device (14) configured to switch between an enabling state that enables conduction between the induction generator and a power grid (5) and a disabling state that disables the conduction, the induction generator being provided in parallel with a main generator (2) that constitutes the power grid and has a larger capacity than the induction generator, the method for starting up the power generation system comprising: The method comprises a turbine start-up step (S11) of increasing the main flow rate by adjusting the opening of the flow regulating valve; a generator motoring step (S13) of switching the switching device from the prohibited state to the permitted state to start supplying power from the power grid to the induction generator when the rotation speed of the induction generator, which increases as a result of the turbine start-up step, reaches a target rotation speed; a turbine speed-up step (S15) of adjusting the opening of the flow regulating valve to further increase the main flow rate after the generator motoring step is executed; and a power generation start step (S17) of starting supplying power to the power grid from the induction generator, which has switched from an electric motor to a generator, when the rotation speed of the induction generator exceeds a synchronous rotation speed which is higher than the target rotation speed.

[0062] According to the configuration 1), the timing at which motoring power is supplied from the power grid to the induction generator occurs after the rotational speed of the induction generator reaches a target rotational speed. This reduces the inrush current of the induction generator at the start of motoring, enabling stable startup of the induction generator. This also reduces voltage drops in the power grid and the starting torque of the turbine. Furthermore, the increase in the mainstream flow of organic refrigerant during the turbine acceleration step causes the rotational speed of the induction generator to exceed the synchronous rotational speed, and the induction generator switches from a motor to a generator. During the power generation start step, the induction generator, together with the main generator, can supply power to the specified equipment. Since the induction generator does not independently supply power to the specified equipment, an inverter and converter for the induction generator are not required, thereby reducing the cost of the power generation system. As described above, a power generation system startup method is realized that enables stable startup of the induction generator and achieves low cost.

[0063] 2) In some embodiments, the method for starting the power generation system described in 1) above further includes a turbine deceleration step (S23) of increasing the bypass flow rate and reducing the main flow rate by controlling the opening of the flow regulating valve when a specified trip condition is satisfied after the power generation start step is performed.

[0064] According to the above configuration 2), the step of decelerating the turbine can be immediately executed in response to a trip of the power generation system.

[0065] 3) In some embodiments, there is provided a method for starting a power generation system as described in 1) or 2) above, wherein in the power generation start step, the induction generator supplies power together with the main generator to a predetermined device (7) connected to the power grid, and the power generation system start-up method further includes a power supply continuation step (S25) in which, when a specified trip condition is satisfied and the switching device is switched to the prohibited state, the main generator continues to supply power to the predetermined device while supplementing the power that had been supplied by the induction generator.

[0066] According to the above configuration 3), even if the power generation system stops generating power due to a trip of the power generation system, the predetermined equipment can continue to operate by the power supply from the main generator.

[0067] 4) In some embodiments, there is provided a method for starting up a power generation system as described in 1) or 3) above, wherein the power generation system comprises: a hot water supply line (121) for supplying hot water heated by exhaust gas discharged from a marine main engine (79) to the evaporator as a heat source for evaporating the organic medium; a hot water discharge line (122) through which the hot water discharged from the evaporator flows; a hot water bypass line (25) connected to the hot water supply line and the hot water discharge line so as to bypass the evaporator; and a hot water flow control valve (127) for changing a ratio between a main hot water flow rate which is a flow rate of the hot water flowing into the evaporator and a hot water bypass flow rate of the hot water flowing through the hot water bypass line, and the start-up method for a power generation system further comprises a generator load reduction step (S29) of controlling an opening degree of the hot water flow control valve to reduce the main hot water flow rate and increase the hot water bypass flow rate when it is determined that the output power of the induction generator has exceeded a specified power.

[0068] If the heat content of the hot water flowing into the evaporator increases due to an increase in the output of the main engine of the marine vessel, the amount of heat input from the hot water to the evaporator increases, which in turn increases the main flow rate of the organic medium flowing into the turbine, which may result in excessive output power from the induction generator.In this regard, according to the configuration of 4) above, if it is determined that the output power of the induction generator has exceeded the specified power, the main hot water flow rate is reduced, thereby preventing excessive load on the induction generator.

[0069] 5) In some embodiments, there is provided a method for starting up a power generation system according to any one of 1) to 4) above, wherein the circulation line is an evaporator turbine line connected to the evaporator and the turbine, and includes an evaporator turbine line (21) to which an inlet (25A) of the bypass line is connected between the evaporator and the turbine, and the flow control valve includes a first flow control valve (31) provided in the evaporator turbine line between the inlet of the bypass line and the turbine, and a bypass flow control valve (35) provided in the bypass line, and in each of the turbine start-up step and the turbine speed increase step, the opening degree of the bypass flow control valve is reduced and the opening degree of the first flow control valve is increased.

[0070] According to the configuration of 5) above, the first flow regulation valve is disposed immediately before the turbine, so that the main flow rate can be controlled with high precision in each of the turbine startup step and the turbine speed increase step.

[0071] 6) A power generation system (10) according to at least one embodiment of the present disclosure is a power generation system including a condenser (11), an evaporator (12), and a turbine (13), the power generation system including: a circulation line (20) through which an organic medium serving as a heat medium flows through the condenser, the evaporator, and the turbine in that order; a bypass line (25) through which the organic medium discharged from the evaporator bypasses the turbine and leads it to the condenser; a flow control valve (30) for adjusting the ratio between a bypass flow rate of the organic medium flowing through the bypass line and a main flow rate which is the flow rate of the organic medium flowing into the turbine; an induction generator (15) connected to the turbine; a switching device (14) configured to switch between an enabling state that enables conduction between the induction generator and a power grid (5) and a prohibiting state that prohibits the conduction; and a controller (90), wherein the induction generator is provided in parallel with a main generator (2) which constitutes the power grid and has a larger capacity than the induction generator, and the controller The system includes a turbine start-up control unit (81) for increasing the main flow rate by controlling the opening of the flow regulating valve; a generator motoring control unit (82) for switching the switching device from the prohibited state to the permitted state when the rotation speed of the induction generator, which increases due to the control of the opening of the turbine start-up control unit, reaches a target rotation speed; and a turbine speed increase control unit (83) for adjusting the opening of the flow regulating valve to further increase the main flow rate after the switching device switches to the permitted state so that the rotation speed of the induction generator exceeds a synchronous rotation speed which is higher than the target rotation speed.

[0072] According to the configuration 6) above, the same effects as those of the configuration 1) above can be obtained.

[0073] 1: Power generation system 2: Main generator 3: Emergency generator 5: Power system 7: Equipment 8: Busbar 9A-9C: Switching device 10: Power generation system 11: Condenser 12: Evaporator 13: Turbine 14: Switching device 15: Induction generator 16: Pumping device 20: Circulation line 21: Evaporator-turbine line 22: Turbine condenser line 23: Condenser-evaporator line 25: Bypass line 25A: Inlet 25B: Outlet 29: Opening / closing valve 30: Flow regulation valve 31: First flow regulation valve 35: Bypass flow regulation valve 70: Heating equipment 79: Marine main engine 81: Turbine start-up control unit 82: Generator motoring control unit 83: Turbine speed-up control unit 84: Trip determination unit 85: Shut-off control unit 86 : Turbine deceleration control unit 87 : Overload determination unit 88 : Generator load reduction control unit 90 : Controller 91 : Power meter 98 : Rotation speed meter 121 : Hot water supply line 122 : Hot water discharge line 125 : Hot water bypass line 127 : Hot water flow adjustment valve

Claims

1. A method for starting up a power generation system including a condenser, an evaporator, and a turbine, the power generation system comprising: a circulation line for an organic medium as a heat medium to flow through the condenser, the evaporator, and the turbine in that order; a bypass line for directing the organic medium discharged from the evaporator to the condenser, bypassing the turbine; a flow regulating valve for adjusting a ratio between a bypass flow rate of the organic medium flowing through the bypass line and a main flow rate which is the flow rate of the organic medium flowing into the turbine; an induction generator connected to the turbine; and a switching device configured to switch between an enabling state which permits conduction between the induction generator and a power grid and a prohibiting state which prohibits the conduction, the induction generator being provided in parallel with a main generator constituting the power grid and having a larger capacity than the induction generator, the startup method for the power generation system comprising: a turbine startup step of increasing the main flow rate by adjusting an opening degree of the flow regulating valve; a generator motoring step of switching the switching device from the prohibited state to the permitted state to start supplying power from the power grid to the induction generator when the rotation speed of the induction generator, which increases as a result of execution of the turbine start-up step, reaches a target rotation speed; a turbine speed-up step of adjusting an opening of the flow regulating valve to further increase the main flow rate after execution of the generator motoring step; and a power generation start step of, when the rotation speed of the induction generator exceeds a synchronous rotation speed which is higher than the target rotation speed, the induction generator, which has switched from an electric motor to a generator, starts supplying power to the power grid.

2. A method for starting a power generation system as described in claim 1, further comprising a turbine deceleration step of increasing the bypass flow rate and reducing the main flow rate by controlling the opening of the flow regulating valve when a specified trip condition is satisfied after execution of the power generation start step.

3. A method for starting a power generation system as described in claim 1 or 2, wherein in the power generation start step, the induction generator supplies power together with the main generator to a specified device connected to the power grid, and the start-up method for the power generation system further comprises a power supply continuation step in which, when a specified trip condition is satisfied and the switching device is switched to the prohibited state, the main generator continues to supply power to the specified device while supplementing the power that was being supplied by the induction generator.

4. The power generation system comprises a hot water supply line for supplying hot water heated by exhaust gas discharged from a marine main engine to the evaporator as a heat source for evaporating the organic medium, a hot water discharge line through which the hot water discharged from the evaporator flows, a hot water bypass line connected to the hot water supply line and the hot water discharge line so as to bypass the evaporator, and a hot water flow regulating valve for changing a ratio between a main hot water flow rate which is the flow rate of the hot water flowing into the evaporator and a hot water bypass flow rate of the hot water flowing through the hot water bypass line, and the start-up method of the power generation system according to claim 1 or 2 further comprises a generator load reduction step of controlling an opening degree of the hot water flow regulating valve to reduce the main hot water flow rate and increase the hot water bypass flow rate when it is determined that the output power of the induction generator has exceeded a specified power.

5. A method for starting up a power generation system as described in claim 1 or 2, wherein the circulation line includes an evaporator turbine line connected to the evaporator and the turbine, and an inlet of the bypass line is connected between the evaporator and the turbine, and the flow control valve includes a first flow control valve provided in the evaporator turbine line between the inlet of the bypass line and the turbine, and a bypass flow control valve provided in the bypass line, and in each of the turbine start-up step and the turbine speed increase step, the opening degree of the bypass flow control valve is reduced and the opening degree of the first flow control valve is increased.

6. A power generation system including a condenser, an evaporator, and a turbine, comprising: a circulation line for an organic medium serving as a heat medium to flow through the condenser, the evaporator, and the turbine in that order; a bypass line for directing the organic medium discharged from the evaporator to the condenser, bypassing the turbine; a flow regulating valve for adjusting a ratio between a bypass flow rate of the organic medium flowing through the bypass line and a main flow rate which is the flow rate of the organic medium flowing into the turbine; an induction generator connected to the turbine; a switching device configured to switch between an allowed state which permits conduction between the induction generator and a power system and a prohibited state which prohibits the conduction; and a controller, wherein the induction generator is provided in parallel with a main generator constituting the power system and having a larger capacity than the induction generator, and the controller comprises: a turbine start-up control section for increasing the main flow rate by controlling an aperture of the flow regulating valve; and a generator motoring control section for switching the switching device from the prohibited state to the permitted state when the rotation speed of the induction generator, which is increased by controlling the aperture control of the turbine start-up control section, reaches a target rotation speed. a turbine speed increase control unit for adjusting an opening degree of the flow regulating valve to further increase the main flow rate so that the rotational speed of the induction generator exceeds a synchronous rotational speed that is higher than the target rotational speed after the switching device switches to the permitted state.

Citation Information

Patent Citations

  • Waste heat utilization method, waste heat utilization system and treatment method of boiler exhaust gas

    JP2014009624A

  • Compressor system and waste heat recovery power generation method

    JP2017129076A

  • Binary power generation device and binary power generation method

    JP2020002892A