The system determines optimal resource allocation in growing facilities by using objective functions and constraints to manage plant material placement, addressing the challenges of contamination and resource utilization, and enhancing throughput and efficiency.
Patent Information
- Application Number
- PCT/US2024/026596
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-04-28
- Filing Date
- 2024-04-26
- Publication Date
- 2024-10-31
AI Technical Summary
The complexity of allocating physical space in growing facilities for plant development is exacerbated by contamination concerns, scheduling, and resource utilization, making it difficult to maximize throughput and conserve resources, especially when dealing with various plant generations and types.
A computer-implemented method and system that access data on growing facilities and plant materials to determine resource allocations based on objective functions and constraints, ensuring optimal placement and coexistence of plant materials while considering capacity, availability, preferences, and isolation requirements.
This approach enables objective and efficient allocation of resources, reducing cycle time and conserving resources by optimizing the placement of plant materials within growing facilities, thereby improving throughput and minimizing subjective biases.
Smart Images

Figure US2024026596_31102024_PF_FP_ABST
Abstract
Description
METHODS AND SYSTEMS FOR USE IN ALLOCATING RESOURCES IN GROWING FACILITIES CROSS-REFERENCE TO RELATED APPLICATION
[0001] This application claims the benefit of, and priority to, U.S. Provisional Application No. 63 / 462,951, filed on April 28, 2023. The entire disclosure of the above- referenced application is incorporated herein by reference. FIELD
[0002] The present disclosure generally relates to methods and systems for use in allocating resources in crop advancement growing spaces, and, in particular, to methods and systems for use in allocating positions, resources, etc. within the growing spaces to specific plants based on factors associated with the plants. BACKGROUND
[0003] This section provides background information related to the present disclosure which is not necessarily prior art.
[0004] In plant development, plants are modified through various mechanisms, including selective breeding, genetic modification, etc., to exhibit desirable traits. Seeds and / or plants resulting from the modifications are tested to determine the success of the modifications. In connection therewith, it is known to provide a growing facility, in which the germplasms / seeds are planted, grown, managed and harvested, whereupon the testing of the plants may be implemented. When the modifications are desirable or successful, the specific plants or seeds therefrom may be promoted for further development or for commercialization. SUMMARY
[0005] This section provides a general summary of the disclosure, and is not a comprehensive disclosure of its full scope or all of its features.
[0006] Example embodiments of the present disclosure generally relate to computer- implemented methods for allocating resources in a growing facility, and to systems for implementing the methods. One example method generally includes: in response to one or morerequests to include plant material in a growing facility, where the plant material includes RO generation or non-RO generation plant material: accessing, by a computing device, data representative of the growing facility and data representative of the plant material; determining, by the computing device, a resource allocation, in which the plant material is assigned to one or more areas of the growing facility, based on the accessed data and an objective function; and introducing, by the computing device, the plant material into the determined one or more areas of the growing facility, consistent with the resource allocation.
[0007] Example embodiments of the present disclosure also generally relate to non- transitory computer-readable storage media including executable instructions for allocating resources in a growing facility. In one example embodiment, such a non-transitory computer- readable storage medium includes executable instructions, which when executed by at least one processor, cause the at least one processor to perform one or more of the above operations and / or one or more of the operations described herein.
[0008] Example embodiments of the present disclosure also generally relate to systems for allocating resources in a growing facility. In one example embodiment, such a system generally includes at least one computing device configured to: in response to one or more requests to include plant material in a growing facility, access data representative of the growing facility and data representative of the plant material, wherein the plant material includes R0 generation plant material and / or non-RO generation plant material; determine a resource allocation, in which the plant material is assigned to one or more areas of the growing facility, based on the accessed data and an objective function; and introduce the plant material into the determined one or more areas of the growing facility, consistent with the resource allocation.
[0009] Further areas of applicability will become apparent from the description provided herein. The description and specific examples in this summary are intended for purposes of illustration only and are not intended to limit the scope of the present disclosure.DRAWINGS
[0010] The drawings described herein are for illustrative purposes only of selected embodiments, are not all possible implementations, and are not intended to limit the scope of the present disclosure.
[0011] FIG. 1 is an example system of the present disclosure configured for use in determining an allocation of growing spaces in a growing facility to a series of plant materials, based on factors associated with the plant materials, and then allocating the growing spaces based on the determination;
[0012] FIG. 2 is an example flow diagram of plant materials into different rooms or areas of a growing facility;
[0013] FIG. 3 is a block diagram of an example computing device that may be used in the system of FIG. 1;
[0014] FIG. 4 is an example method, suitable for use with the system of FIG. 1, for determining an allocation of growing spaces in a growing facility to a series of plant materials, based on factors associated with the plant materials, and then for also implementing the determination and allocating the growing spaces to the series of plant materials; and
[0015] FIGS. 5-6 illustrate example output that may be generated by the system of FIG. 1 and / or the method of FIG. 4, illustrating allocation of growing spaces in a growing facility to a series of plant materials.
[0016] Corresponding reference numerals indicate corresponding parts throughout the several views of the drawings.DETAILED DESCRIPTION
[0017] Example embodiments will now be described more fully with reference to the accompanying drawings. The description and specific examples included herein are intended for purposes of illustration only and are not intended to limit the scope of the present disclosure.
[0018] In plant development, new traits are developed to enhance yield, limit pest impacts, and promote disease resistance and herbicide tolerance. The development includes the utilization of resources, such as, for example, physical space in controlled environments, workers, etc. For a specific growing facility, allocation of the physical space, such as, for example, isolated rooms / areas, etc., to different products (c.g., seeds, plant material, etc.), impacts throughput of products within the facility and / or utilization of the growing space (or rooms, areas, etc. therein), which, in turn, impacts the overall speed of the development of the products (e.g., new traits associated with the products, etc.). In connection therewith, various factors impact placement of the products within the facility, including, for example,contamination concerns, schedules, growing stages, etc. For example, certain products cannot be located in the same room with other products because of the potential for cross-contamination. The factors further extend to the same types of products, and also to different types of products, whereby the complexity of allocating physical space(s) in the growing facility is complex, and beyond the capabilities of the human mind, especially when considering objectives of maximizing throughput and / or resource conservation.
[0019] Uniquely, the methods and systems herein provide for an objective determination of allocating physical space(s) in a growing facility to specific plant materials (e.g., in the RO generation, in the non-RO generation, etc.) (e.g., including embryonic plant tissue, plugs / plantlets, seeds, plants, etc.), based on one or more objective functions and / or associated constraints.
[0020] In particular, in connection with R0 generation and / or non-RO generation of plant materials, various factors defines abilities of plant materials to be allocated to a room, area, space, etc. within a growing facility, and then also abilities of the plant materials to co-exist in that room, area, space, etc. with other plant material(s). The factors may include, without limitation, capacity of the room (or area, space, etc.), usage / availability of room(s) (or area(s), space(s), etc.), preferences / priorities, availability of plant materials, durations of stages / processes in each of the rooms (or areas, or spaces, etc.), construct / request limits for the plant material(s), etc. The resource allocation is determined, as described herein, to account for one or more of the above factors, while considering objectives of improving throughput, conserving resources, and / or reducing cycle time, etc. In this manner, highly complex allocations are accomplished in an objective manner, outside of the typical influence of subjective standards, assumptions, and / or human biases.
[0021] FIG. 1 illustrates an example system 100 for allocating resources within a growing facility (e.g., to specific plants and / or plant material based on factors associated with the plants, etc.), and in which one or more aspects of the present disclosure may be implemented. Although, in the described embodiment, parts of the system 100 are presented in one arrangement, other embodiments may include the same or different parts arranged otherwise depending, for example, on available resources, capacity of resources, plant materials present, and arrangements of the resources in the growing facilities, etc.
[0022] As shown in FIG. 1 , the system 100 generally includes a growing facility 102, which may include a variety of different types, sizes, etc., of areas for planting, growing and / or harvesting crops, etc., in connection with plant development practices or otherwise. In this example embodiment, the growing facility 102 is an indoor space. Nonetheless, it should be appreciated that in other system embodiments, the growing facility 102 may include an outdoor space(s), or potentially, combinations of indoor space(s) and outdoor space(s) (e.g., fields, greenhouses, combinations thereof, etc.). In addition, it should be understood that the growing facility 102 may include a contiguous area, or may include distinct areas spaced apart within a geographic region (e.g., multiple disconnected areas within a single property, or across a limited region, etc.).
[0023] As illustrated, the growing facility 102 is separated into multiple different areas 104a-d (e.g., rooms, spaces, sections, plots, etc.). The areas 104a-d, in this example embodiment, are isolated from one another, whereby the occurrences in one area are unaffected by the occurrences in another area (e.g., pollination, treatment, etc.). Also, the areas 104a-d are (or define or are included in) environmentally-controlled (EC) spaces, in which environmental conditions are controlled to specific parameters, as desired or required. The environmental conditions may include and / or may relate to, for example, temperature, moisture, humidity, solar radiation, wind, or other environmental condition, etc. Further, with regard to the isolation, the environmental conditions in the areas 104a-d may be controlled independently, such that temperature in area 104a, for example, may be different than temperature in area 104c, etc.
[0024] It should be appreciated that different areas may be defined, either by space or by climate-control in other embodiments, whereby different conditions may be extended, or not, to the different areas. That said, each of the areas 104a-d is associated with a specific space (or spacing or size), and consequently, a specific capacity. It should be further appreciated that two or more of the areas 104a-d may each include a common (and / or shared) area, or the areas 104a- d may each include different areas. What’s more, the areas 104a-d should not be understood to be limited to any particular area or size or shape or construction. The areas 104a-d may, for example, include an entire greenhouse or a substantial or limited partition thereof, or an entire field or substantial or limited portion thereof, etc. In one example, a growing facility may include more than a hundred areas each defined by a room (e.g., each having a size of between about 30 ft2and about 3000 ft2(e.g., a size of about 48 ft2, about 100 ft2, about 1000 ft2, about2400 ft2, etc ), etc.), and each being physically separated and / or isolated from one another (e.g., by walls, etc.).
[0025] Moreover, in this example embodiment, the areas 104a-d are each associated with a capacity, e.g., a capacity to hold plant material, etc. As indicated above, the size of an area is indicative of its capacity, in general. In one example, one of the areas 104a-d may have a size of about 48 ft2, and in connection therewith may have a capacity of (e.g., an ability to contain, support, hold, etc.) between about 10 and about 30 separate R0 generation plant materials (e.g., depending on plant material type, etc.). In another example, one of the areas 104a-d may have a size of about 2400 ft2, and in connection therewith may have a capacity of (e.g., an ability to contain, support, hold, etc.) between about 480 and about 960 separate R0 generation plant materials (e.g., depending on plant material type, etc.). In yet another example, one of the areas 104a-d may have a size suitable to accommodate a capacity of between about 200 and about 1000 non-RO generation plant materials (e.g., depending on plant material type, etc.).
[0026] While only four areas 104a-d are illustrated in the example system 100, it should be appreciated that a different number of areas may be included in other growing facility embodiments. For example, FIG. 2 illustrates example growing facility 200 that includes a series of areas illustrated as rooms, and designated as Room #1, Room #2, Room #3 through Room #L, Room #M, Room #N, etc. As such, as shown in this example, the number of rooms included in the growing facility 200 may be variable and may be specific to a particular growing facility embodiment. Consistent therewith, it should be appreciated that the number of areas (e.g., rooms, etc.) included in a growing facility embodiment may include dozens, or hundreds, or thousands, or more or less, etc.
[0027] As indicated above, the growing facility 102, in whole or in part, is associated with the development of certain plant materials, which in this exemplary embodiment, may be (or may include) first generations of a transgenic plant or R0 generation plant material, and / or may be (or may include) non-RO plant materials. In particular, a R0 generation plant in this example may be cultured from tissue in a plant transformation process and grown in one or more of the areas 104a-d in the growing facility 102. In connection therewith, samples of a leaf or a root of the plant may be taken at an appropriate developmental stage (or stages), and / or the plant may be pollinated and harvested at an appropriate time, etc. The first generation of the plant isalso called the RO generation herein. The seed harvested from the RO generation plant is referred to as R1 seed and, in turn, the next generation (e.g., seed harvested from a plant grown from the R1 seed, etc.) is R2 seed, etc., or more generally, a non-RO generation, etc. An example development process may involve hundreds of thousands of plant materials from (or at) the RO generation, which are placed in the growing space 102, to be advanced into later generations. The same processes / operations may then be repeated for the non-RO generations of plant materials, as desired, or may be performed for non-RO generations of plant materials obtained otherwise, etc.
[0028] It should be appreciated that data indicative of the growing facility 102, the areas 104a-d, aspects thereof (e.g., size, capacity, locations, etc.) and also usage of the growing facility 102 (e.g., plant material already located therein, if any, etc.) is accessible to a computing device 106 of the system 100. For example, such data may be compiled and stored in a data structure 108 included in the system 100, which is then accessible to the computing device 106 as desired.
[0029] The growing facility 102 in developing plants may be configured to develop one type of plant or multiple different types of plants. In one example embodiment, the growing facility 100 may be limited to different varieties of com or maize, while in other example embodiments the growing facility 100 include multiple different types of plants. The different types of plants may include, without limitation, com or maize (Zea mays), soybean (Glycine max), cotton (Gossypium hirsutum), peanut (Arachis hypogaea), barley (Hordeum vulgare),' oats (Avena sativa),' orchard grass (Dactylis glomerata), rice (Oryza sativa, including indica and japonica varieties); sorghum (Sorghum bicolor),' sugar cane (Saccharum sp),' tall fescue (Festuca arundinacea),' turfgrass species (e.g., species: Agrostis stolonifera, Poapratensis, Stenotaphrum secundatum, etc.); wheat (Triticum aestivum), and alfalfa (Medicago sativa), members of the genus Brassica, including broccoli, cabbage, cauliflower, canola, and rapeseed, carrot, Chinese cabbage, cucumber, dry bean, eggplant, fennel, garden beans, gourd, leek, lettuce, melon, okra, onion, pea, pepper, pumpkin, radish, spinach, squash, sweet com, tomato, watermelon, honeydew melon, cantaloupe and other melons, banana, castorbean, coconut, coffee, Poplar, Southern pine, Radiata pine, Douglas Fir, Eucalyptus, apple and other tree species, orange, grapefruit, lemon, lime and other citrus, clover, linseed, olive, palm, Capsicum, Piper, andPimenta peppers, sugarbeet, sunflower, sweetgum, tea, tobacco, and other fruit, vegetable, tuber, and / or root crops.
[0030] For each of the plant materials (e.g., plants, etc.) included in the growing facility 102, data is gathered about the material (and as desired, stored in the data structure 108 for subsequent use by the computing device 106, etc.). For example, common data, such as, for example, the type and variety of the plant material, along with plant material identifiers are compiled and stored in the data structure 108.
[0031] In addition, growth profiles for the plant materials are also stored in the data structure 108, whereby a progress from a plant date to a harvest date may be indicated / estimated, etc. In connection with the above, the R0 generation and non-RO generation plant materials generally are associated with workplans and workflows. In general, for example, a workplan may include a group or set of plant material to be evaluated, for example, for a transgene or edit. The workplan may include a unique or pseudo unique numeric identifier, for example, 12345 (e.g., for the plant material(s) associated with the workplan, for the workplan itself, etc.). And, a workflow, in general, may be a path and quantity that the workplan (e.g., the group or set of plant material included in the workplan, etc.) follows as it moves through the growing facility 102. That said, an example workflow may include: step 1 : location A, duration: 18 days; step 2: location T, duration 88 days, etc. As such, the workplans enter a workflow based on a combination of characteristics, or similarly, the workflow is prescribed to the workplan depending on the purpose of the plants / plant materials in the workplan (e.g., characteristic 1 : species, characteristic 2: genotype and characteristic 3: pollination instruction, etc.). As such, the workplans may be specific to different constructs, which may include a vector in a particular sequence of DNA that is introduced into plant cells via transformation, etc. The workplan and workflow, and corresponding data, is again compiled and stored in the data structure 108 for subsequent use.
[0032] It should be understood that the same or different types of plant materials (in the same or different generations) in the areas 104a-d may be associated with the same or different isolation requirements, for example, to ensure that performance of the plant materials is based on the plant material itself and not any other reasonable factor (e.g., contamination from other plant materials, etc.). The requirements may be defined as various rules, which, for example, indicate that plant material #12345 cannot be in the same area as plant material#54321 , in general or at specific times, etc. The rules may be plant material specific, time specific, plant-type specific, area specific (e.g., certain rules may be specific to pollination areas, etc.), etc. For example, in general, com plant materials may be required to be isolated from soybean plant materials, regardless of timing, etc. Similarly, certain corn plant material may be required to be isolated from other corn plant material in pollination areas only, etc. It should be appreciated that the various isolation rules may be compiled through research, experiment, and / or analysis, and stored in the data structure 108 as desired.
[0033] With regard to introducing the plant materials into the growing facility 102, requests are generally received, for example, from an operator of the growing facility 102, which may include a breeder, a scientist, a worker, etc., who is associated with the growing facility 102. The requests, in general, may include an indication of the particular R0 generation or non-RO generation plant material (e.g., by identifier, by type (e.g, corn versus soy, etc.), etc.), a quantity of the plant material, a start date, an availability date (e.g, immediately, future date, etc.), and a preference of an area (or room or location) in the growing facility 102, etc. It should be appreciated that many different requests for different plant materials may be received from the operator over days, weeks, or months, and that each of the requests is stored in the data structure 108.
[0034] In a first example embodiment, the computing device 106 of the system 100 is configured to determine a resource allocation 110 of the growing facility 102, whereby the products, z.e., the RO-generation plant materials in this first example embodiment, are to be distributed or introduced into the areas 104a-d of the growing facility 102, based on the requests and data included in the data structure 108.
[0035] As part thereof, and in connection with the above, the computing device 106 is configured to access the relevant data from the data structure 108, where, as indicated above, the data is related to the growing facility 102 and / or the plant materials to be introduced therein. The computing device 106 is coupled to the data structure 108 to access the data therein. As above, the data is representative of (for example, and without limitation): the growing facility 102 (e.g., capacities, exiting allocations, etc.); the plant materials of the request(s), including, without limitation, growth times, product identifiers, environmental condition requirements, etc.; and also isolation restrictions / rules; etc.
[0036] It should be appreciated that the computing device 106 is configured to determine the resource allocation 110 based on existing products residing or disposed in the growing facility 102, if any, and also a demand for the areas 104a-d in the growing facility 102. The demand includes a current demand, based on products on-hand and / or delivered to the growing facility 102 (e.g, existing requests in controlled environment, etc.), and also forecasted products (e.g, a future demand, etc.), which are expected to arrive at the growing facility 102 within an interval (e.g., a next two weeks, a given two-week period, etc.). In connection therewith, the forecasted products may include committed (future) deliveries of plant products to the growing facility (e.g., from suppliers, upstream sources, etc.). In addition, or alternatively, the forecasted products to be delivered to the growing facility may include plant products determined (or identified) based on a historical analysis, a demand analysis, etc. For instance, in one example, a determination of the forecasted products to be delivered to the growing facility 102 may be based on (or may initially be based on) committed delivery products from a supplier. However, there may be attrition along the way with regard to the committed delivery products, so the number of plant products actually delivered may deviate from a target number. As such, the estimated delivery number of plant products may be revised through analysis based on one or more probabilistic models of attrition frequencies (e.g., taking into account historical attrition, current circumstances that may cause or affect attrition, etc.). Such revisions may be performed at one or more desired times in order to improve accuracy of the demand and outcome / output of the analyses described herein with regard to allocating resources in the growing facility 102 to the plant products.
[0037] The computing device 106 is configured to express the above data as variables and then to implement an objective function, subject to one or more constraints, which provide for, among other limitations, isolation, capacity, etc. In connection therewith, Table 1 includes example variables, which are descriptive of the growing facility 102 and the areas 104a-d in this example embodiment, as may be defined by the computing device 106.Table 1
[0038] Based on the above variables, the computing device 106 is configured, by the objective function, such as the example objective function provided below as Equation (1), for use in determining the resource allocation 110.
[0039] It should be understood that the example objective function of Equation (1) is based on the minimization and / or maximization of certain aspects of locating the products in the growing facility 102. In this example embodiment, in order from left to right, the objective function is provided to limit and / or minimize one or more combinations of the following: (1) a limit / minimize total usage of dummy resources, where total dummy resource presence, if any, is represented as TDP; (2) a limit / minimize total cycle time (CT) of all received requests; (3) enhance / maximize a number of requests located in the areas 104a-d by same group, where such total group preferred allocation is represented as TGP; (4) enhance / maximize a number of requests with the same workplan type in an area, where the total group preferred workplan allocation is represented as TGPW; (5) enhance / maximize a relative capacity utilization rate (CPR); (6) minimize a total number of areas (or rooms) (TR) occupied; (7) enhance / maximize a number of requests located in areas in a primary list (e.g, a first preference, etc ), where TPP represents total placement in the primary list; (8) enhance / maximize a number of requests located in areas in an overflow list (e.g, a second preference, etc.), where TPO represents total placement in the overflow list; (9) enhance / maximize a number of requests located in rooms preferred by their types (TP A); (10) limit / minimize a number of areas with distinctive constructs, where total construction violation is represented as TCV; and (11) enhance / maximize a number of R0 plant materials, for example, and their support requests in the same area, where the total R0 support pair is TRSP, etc.
[0040] It should be understood, also, that the objective function described herein may be different from that of Equation (1) in other example embodiments, whereby one or more of the terms may be omitted and / or where one or more other terms may be included, etc.
[0041] Beyond the objective function, which imposes the above features / objectives to maximize or minimize certain aspects of the resource allocation, the computing device 106 isalso configured to be limited in determining the resource allocation 110 by multiple constraints, which are required. The multiple constraints imposed in this example embodiment are described below and illustrated with reference to Equations (2)-(12).
[0042] For example, Equation (2) requires the area / size of / for an area (or room) (e.g., area 104c, etc.) assigned to a given request to be limited to the capacity of that area. And, Equation (3) requires that the start date in the request be equal to the date in which plant products are able to be introduced to the area (e.g., the computing device 106 accesses data (e.g., experiment data, etc.) for existing plant products already in the area and / or already in the growing facility 102 (e.g., via the data structure 108, etc.) and uses such data in determining the start date, based on overall capacity, etc.).
[0043] Equation (4) requires the end date in the request to be equal to the date in which the plant product(s) are to be removed (or are to leave) the area (e.g., based on experiment data for the plant product(s) and / or given area as included in the data structure 108, etc.), and Equation (5) requires confirmation that the requested location in the request is equal to the desired and / or assigned location for the given plant product(s) (e.g., again based on experiment data for the plant product(s) and / or given area as included in the data structure 108, etc.).
[0044] Equation (6) requires the start date of next step to be equal to end date of previous date of any request, and Equation (7) requires the start date of a request to be within its allowable planting date range (e.g., accounting for demand (e.g., current demand, future demand, etc.), etc.).(7)
[0045] Equation (8) requires the assignment of the request to a compatible area (or room), and Equation (9) defines the total number of requests assigned (with reference to rooms). alternative(reqStep_interval[rs], all(s in locations: s not in incomp atibleRoomsByRequestedStepaaray[rs]) reqStep!nLoc_interval [rs] [s]) (8) reqSteplnLoc_int[rs] == sum(s in locations: s not in incompatibleRoomsBy RequestedStep_array[rs]) s. index * presenceOf(reqSteplnLoc_interval[rs] [s]) (9)
[0046] Equation (10) restricts the request from being assigned to an incompatible area (or room) As a note, in this example embodiment, Equation (10) may be optional in view of Equation (8) above, which includes a similar restriction. Equation (11) requires that an area (or room) is only used for one step at a certain time. And, Equation (12) requires isolation of request by isolation rules.! presenceOf(reqStepInLoc_interval[rs][s]) (10) alwaysEqual(roomUsageTypeState[s] reqStep!nLoc_interval[rs] [s] , steplndex[rs.stepDescript]) (11) forall(iorspl_red in isolatedOrderedRequestsByStepsPairLocation_reduced_set){ noOverlap(p [iorspl_red])(12)
[0047] It should be appreciated that more or less constraints may be employed in other embodiments, whereby other rules associated with the example resource allocation 110 may be imposed, as required in / by a constraint, or potentially, preferred as an additional or alternative term (or constraint) of the objective function.
[0048] In view of the above, in the embodiment of FIG. 1, the computing device 106 is configured to determi ne / generate the resource allocation 110, based on the objective function of Equation (1) subject to the above constraints of Equations (2)-(12). The output, then, is in the form of a schedule indicating particular dates to introduce plant materials to rooms of the growing facility 102, particular dates to move plant materials to different rooms of the growing facility 102, particular dates to remove plant materials from rooms and / or from the growing facility 102 all together, etc. In specific examples, the horizon for the resource allocation 110 may include about one year, or about one year and six weeks, or about eighteen months, or more or less. The first day of the resource allocation 110 is the day on which the resource allocation 110 is determined / generated, with the resource allocation 110 then extending to the given horizon. It should be appreciated that other suitable horizons, which are longer or shorter may be included in other examples.
[0049] FIGS. 5-6 illustrate example resource allocations that may be output by the computing device. For instance, FIG. 5 illustrates an example table 500 illustrating resource allocation for a particular room area or location (e.g., location GH025, etc.) within a growing facility. And, FIG 6 illustrates an example chart 600 illustrating resource allocation withing a particular room or area or location (e.g., location GH025, etc.) of a growing facility.
[0050] In some examples, the schedule may be generated once for each plant material, or workplan, to be included in the growing facility 102, for instance, such that the schedule then provides an indication of a particular date to move the plant material into a given (or assigned) area (or room) of the growing facility 102 and then also a date to remove the plant material from the area (or room). The schedule may then be generated daily for additional workplans, whereby prior workplans are maintained consistent with the original schedule. In this way, the generated schedules for the projected plants provide an interval or lead time (e.g., a 6-week, etc.) for the operator and / or the facility 102 to prepare the space and media for the upcoming plants. In other examples, the schedule for the facility 102 may be generated at particular / desired time frames (e.g., daily, twice a week, weekly, monthly, at desired intervals,randomly, etc ), and may include data relating to multiple different plant materials for the given time frame. For instance, the schedule may include an indication of all plant materials to be moved into the different rooms of the growing facility 102, and the respective dates for such actions, for all dates within the given time frame. Similarly, the schedule may include an indication of all plant materials to be moved out of the different rooms of the growing facility 102, and the respective dates for such actions, for all dates within the given time frame.
[0051] In a second example embodiment, the computing device 106 of the system 100 is configured to determine a resource allocation 110 of the growing facility 102, whereby the products, i.e., the non-RO generation plant materials in this second example embodiment, are to be distributed or introduced into the areas 104a-d of the growing facility 102, based on the requests and data included in the data structure 108.
[0052] As part thereof, and in connection with the above, the computing device 106 is configured to access the relevant data from the data structure 108, where, as indicated above, the data is related to the growing facility 102 and / or the plant materials to be introduced therein. The computing device 106 is coupled to the data structure 108 to access the data therein. As above, the data is representative of (for example, and without limitation): the growing facility 102 (e.g., capacities, exiting allocations, etc.); the plant materials of the request(s), including, without limitation, growth times, product identifiers, environmental condition requirements, etc.; and also isolation restrictions / rules; etc.
[0053] It should be appreciated that, in this example embodiment, the computing device 106 is configured to determine the resource allocation 110 based on existing non-RO plant materials residing or disposed in the growing facility 102, if any, and also products on-hand and / or delivered to the growing facility 102.
[0054] The computing device 106 is configured to express the above data as variables and then to implement an objective function, subject to one or more constraints, which provide for, among other limitations, isolation, capacity, etc. Specifically, to start in this example embodiment, Q represents a set of requests for inclusion of non-RO plant material into the growing facility. In association with the request, q EQ. And then, an earliest day the plant material is available to start is represented as aq, and a latest day it is available to start is represented as bq. In connection therewith, a planning horizon, which is D days long, is alsodefined. The request q is also associated with a priority, pq, with a lower value indicating greater priority and P representing a largest priority value.
[0055] Also, a number of events, Eq, is associated with the request where theevents must be processed via a workflow that is defined by the request and incudes a sequence of steps. It should be understood that different requests may involve the same steps, where S represents the set of possible workflow steps.is a set of sequences of workflow steps, and a data element Further,associated with the request q EQ is a workflow, And, associated with stepof theworkflow wqassociated with request is a time, in days, the given step requires.
[0056] All workflow steps s ES require the use of an area, whereby may be the setof areas available on day d and the areas where step s can potentially be performedon day d. The set of available areas is indexed by d as some areas (also referred to as rooms) that may be committed to other activities on some days. For each request q and workflow set 5 Ewq, there is a per-event room space requirement, as well as a set of preferred locationsFurther, for each event associated with request q and workflow set .s , there is a set ofstrongly preferred location units, . Further associated with area ris a space capacity, cr.It should be appreciated that biological concerns may further constrain the assignment of requests to areas, whereby a set I of request pairs may exist that cannot be assigned to thesame area on the same day.
[0057] Further, in this exemplary embodiment, decision variables are defined as, for example, the binary decision variable where bqrepresents whetherrequest q begins on day d. Additionally, the binary variable represents whether events instep associated with the request q are assigned to area r on day d. Also, the integer decision variable D represents the number of events ofrequest q in step that are assigned to begin processing in area r on day d. And, finally, inthis embodiment, the binary variable / represents whether area r is usedon day d.
[0058] Given the above, in this second example embodiment, the computing device 106 is configured to model a balanced assignment of events to rooms, where represents thelargest difference in assignments of events to areas on a given day. The objective function here, as represented by the equations below (e.g., by Equation (13) or Equation (14), etc.), is then defined as a weighted combination of seven example terms, as defined below, which are expressed as percentages, each of which is given its own weight, «
[0059] In this example embodiment, the first term (at the top) in the objective of the model is the percentage of requests that are processed during the horizon, or interval being planned / scheduled. The second term (from the top) is the percentage of event steps that are assigned to a preferred location. The third term is the percentage of event steps that are assigned to a strongly preferred location unit. The fourth term is the average percentage of the largest priority value of the requests assigned. The fifth term is the percentage of potential area days that are not assigned. The sixth term is the average area utilization over the horizon. And, the seventh term is the largest imbalance in room assignments of any given day.
[0060] It should be understood, also, that the objective function described herein may be different in other example embodiments, whereby one or more of the terms may be omitted and / or where one or more other terms may be included, etc.
[0061] In connection with the example objective function(s) provided above, and other suitable objective functions, the computing device 106 is configured to impose multiple constraints. In particular, in this example embodiment, the computing device 106 is configured to impose one or more of the constraints expressed below, and referenced as Equation (15) through Equation (25).
[0062] The constraint of Equation (14) ensures that each request q is started at most one time. The definition of the x variables in the constraint of Equation (14) ensures that a request only starts within its window (i.e., between the earliest day the plant material is available to start, aq, and a latest day it is available to start, bq). The constraint of Equation (15) ensures that if a request q starts on a given day then all of its events start on that same day, in some area (or room). The constraint of Equation (16) ensures that each step in the workflow of a request q begins immediately after its predecessor ends. The constraint of Equation (17) ensure that capacity limits for each area are observed.
[0063] What’s more, the constraint of Equation (18) ensures that when events are assigned to begin processing in a room on a given day, their presence is recorded in that area for the duration of that step. The constraint of Equation (19) ensures that at most one step of one request q is in an area r on any given day d. The constraint of Equation (20) ensures that eachstep of a request q is in an area r for a limited number of days. The constraint of Equation (21) enforces isolation requirements. The constraint of Equation (22) determines the largest difference in assignments of event steps to areas on any given day in the planning horizon. The M terms ensure the difference is only based on areas that are used on a given day. Finally, the constraints of Equation (24) further define the decision variables and their domains.
[0064] It should be appreciated that more or less constraints may be employed in other embodiments, whereby other rules associated with the example resource allocation 110 may be imposed, as required in / by a constraint, or potentially, preferred as an additional or alternative term (or constraint) of the objective function.
[0065] In view of the above, in the embodiment of FIG. 1, the computing device 106 is configured to determine / generate the resource allocation 110, to populate non-RO generation plant materials, based on the above objective function subject to the above constraints. The output, then, is in the form of a schedule indicating particular dates to introduce the non-RO generation plant materials to areas of the growing facility 102 and particular dates to remove the non-RO generation plant materials from the growing facility 102, etc.
[0066] In some examples, the schedule may be generated once for each plant material, or workplan, to be included in the growing facility 102, for instance, such that the schedule then provides an indication of a particular date to move the plant material into a given (or assigned) area (or room) of the growing facility 102 and then also a date to remove the plant material from the area (or room). The schedule may then be generated daily for additional workplans, whereby prior workplans are maintained consistent with the original schedule (i.e., treated as fixed). In this way, the generated schedules for the projected plants provide an interval or lead time (e.g., a 6-week, etc.) for the operator and / or the facility 102 to prepare the space and media for the upcoming plants.
[0067] In other examples, the schedule for the facility 102 may be generated at parti cular / desired time frames (e.g., daily, twice a week, weekly, monthly, at desired intervals, randomly, etc.), and may include data relating to multiple different plant materials for the given time frame. For instance, the schedule may include an indication of all plant materials to be moved into the different rooms of the growing facility 102, and the respective dates for such actions, for all dates within the given time frame. Similarly, the schedule may include an indication of all non-RO generation plant materials to be moved out of the different rooms of thegrowing facility 102, and the respective dates for such actions, for all dates within the given time frame.
[0068] That said, once the resource allocation 110 is determined / generated, the computing device 106 is configured to implement the resource allocation 110 in the growing facility 102, for example, based on (or in accordance with) the determined schedule. In connection therewith, implementation of the resource allocation 110 may include providing instructions to a human (e.g., via a printer, via display at a computing device associated with the human, etc.) whereby the human may then introduce R0 generation plant products or non-RO generation plant products to desired areas / rooms of the growing facility 102 and / or remove plant products from desired areas / rooms of the growing facility 102; providing instructions to one or more controls at the growing facility 102 to automatically introduce plant products to desired areas / rooms of the growing facility 102 and / or remove plant products from desired areas / rooms of the growing facility 102 through control of one or more aspects of the facility 102 (e.g., plant material conveyors associated with the areas / rooms of the growing facility 102, etc.); or a combination thereof.
[0069] For instance, in one R0 generation example embodiment, the computing device 106 may be configured to implement the resource allocation 110 through issuing instructions consistent with the schedule to one or more users associated with the growing facility 102, or part thereof dedicated to R0 generation. This may include printing specific instructions or displaying specific instructions on a display device associated with the user(s). In such example, the user(s) may then take part in directing one or more plant products into the growing facility 102, and / or into particular areas / rooms of the growing facility 102 (designated for R0 generation), consistent with the instructions. In addition, the user(s) may also take part in moving and / or removing plant materials from the growing facility, and / or form particular areas / rooms of the growing facility 102, consistent with the instructions. As such, the given resources at the growing facility are applied to, or assigned to, the R0 generation plant materials in the desired manner, and in accordance with the resource allocation 110.
[0070] In addition, in one non-RO generation example embodiment, the computing device 106 may be configured to implement the resource allocation 110 through issuing instructions consistent with the schedule to one or more users associated with the growing facility 102, or part thereof dedicated to non-RO generation. This may include printing specificinstructions or displaying specific instructions on a display device associated with the user(s). In such example, the user(s) may then take part in directing one or more non-RO generation plant products into the growing facility 102 and / or into particular areas / rooms of the growing facility 102 (designated for non-RO generation), consistent with the instructions. In addition, the user(s) may also take part in moving and / or removing plant materials from the growing facility, and / or form particular areas / rooms of the growing facility 102, consistent with the instructions. As such, the given resources at the growing facility are applied to, or assigned to, the non-RO generation plant materials in the desired manner, and in accordance with the resource allocation 110.
[0071] In one or more embodiments, an operator (not shown) at the growing facility 102 may review the resource allocation 110 (for R0 generations and / or non-RO generations) and provide an approval or implementation instruction, whereby the computing device 106 is configured to implement the resource allocation 110 further based on the approval and / or implementation command.
[0072] In addition, it should be appreciated that the computing device 106 is configured to update, or again determine, the resource allocation 110, based on the objective function and constraints, as described above, at one or more intervals. For example, the resource allocation 110 may be updated each Monday, or other day of the week, or month, or weekly, or monthly, etc. The interval may be based on a specific day / date, or may be based on changes in the demand, either current or forecasted, etc. Once the resource allocation is updated at whatever interval, the computing device 106 is again configured to implement the resource allocation, as explained above, for use in introducing plant material into the growing facility 102, removing plant material from the growing facility, etc.
[0073] FIG. 3 illustrates an example computing device 300 that may be used in the system 100, for example, in connection with the computing device 106 and / or the data structure 108, etc., whereby each includes and / or is implemented in at least one computing device consistent with computing device 300. In connection therewith, the computing device 300 may be uniquely, or specifically, configured, by executable instructions, to implement the various algorithms, functions, etc. and other operations described herein with regard to the computing device 106. It should be appreciated that the system 100, as described herein, may include avariety of different computing devices, either consistent with computing device 300 or different from computing device 300.
[0074] The example computing device 300 may include, for example, one or more servers, workstations, personal computers, laptops, tablets, smartphones, or other suitable computing devices, combinations thereof, etc. In addition, the computing device 300 may include a single computing device, or it may include multiple computing devices located in close proximity or distributed over a geographic region, and coupled to one another via one or more networks. Such networks may include, without limitations, the Internet, an intranet, a private or public local area network (LAN), wide area network (WAN), mobile network, telecommunication networks, combinations thereof, or other suitable network(s), etc. In one example embodiment, the data structure 112 of the system 100 includes at least one server computing device, while the computing device 106 includes at least one separate computing device, which is coupled to the data structure 112, directly and / or by one or more LANs, etc.
[0075] With that said, the illustrated computing device 300 includes a processor 302 and a memory 304 that is coupled to (and that is in communication with) the processor 302. The processor 302 may include, without limitation, one or more processing units (e.g., in a multi-core configuration, etc.), including a central processing unit (CPU), a microcontroller, a reduced instruction set computer (RISC) processor, an application specific integrated circuit (ASIC), a programmable logic device (PLD), a gate array, and / or any other circuit or processor capable of the functions described herein. The above listing is example only, and thus is not intended to limit in any way the definition and / or meaning of processor herein.
[0076] The memory 304, as described herein, is one or more devices that enable information, such as executable instructions and / or other data, to be stored and retrieved. The memory 304 may include one or more computer-readable storage media, such as, without limitation, dynamic random access memory (DRAM), static random access memory (SRAM), read only memory (ROM), erasable programmable read only memory (EPROM), solid state devices, flash drives, CD-ROMs, thumb drives, tapes, hard disks, and / or any other type of volatile or nonvolatile physical or tangible computer-readable media. The memory 304 may be configured to store, without limitation, environmental conditions, rules / restrictions, plant material profiles, and / or other types of data (and / or data structures) suitable for use as described herein, etc.
[0077] In various embodiments, computer-executable instructions may be stored in the memory 304 for execution by the processor 302 to cause the processor 302 to perform one or more of the functions described herein, such that the memory 304 is a physical, tangible, and non-transitory computer-readable storage media. Such instructions often improve the efficiencies and / or performance of the processor 302 that is performing one or more of the various operations herein (e.g., one or more operations of method 400, etc.) whereby such performance may transform the computing device 300 into a special-purpose computing device. It should be appreciated that the memory 304 may include a variety of different memories, each implemented in one or more of the functions or processes described herein.
[0078] In the example embodiment, the computing device 300 also includes an output device 306 that is coupled to (and is in communication with) the processor 302. The output device 306 outputs, or presents, to a user of the computing device 300 (e.g., a facility operator, etc.) by, for example, displaying and / or otherwise outputting information such as, but not limited to, the resource allocation 110 to be approved for implementation, etc. It should be further appreciated that, in some embodiments, the output device 306 may comprise a display device such that various interfaces (e.g., applications (network-based or otherwise), etc.) may be displayed at computing device 300, and in particular at the display device, to display such information and data, etc. And in some examples, the computing device 300 may cause the interfaces to be displayed at a display device of another computing device, including, for example, a server hosting a website having multiple webpages, or interacting with a web application employed at the other computing device, etc. Output device 306 may include, without limitation, a liquid crystal display (LCD), a light-emitting diode (LED) display, an organic LED (OLED) display, an “electronic ink” display, combinations thereof, etc. In some embodiments, output device 306 may include multiple units.
[0079] The computing device 300 further includes an input device 308 that receives input from the user (e.g., a request from an operator, or an implementation command from an operator, etc.). The input device 308 is coupled to (and is in communication with) the processor 302 and may include, for example, a keyboard, a pointing device, a mouse, a stylus, a touch sensitive panel (e.g., a touch pad or a touch screen, etc.), another computing device, and / or an audio input device. Further, in some example embodiments, a touch screen, such as that included in a tablet or similar device, may perform as both output device 306 and input device308. In at least one example embodiment, the output device 306 and the input device 308 may be omitted.
[0080] In addition, the illustrated computing device 300 includes a network interface 310 coupled to (and in communication with) the processor 302 (and, in some embodiments, to the memory 304 as well). The network interface 310 may include, without limitation, a wired network adapter, a wireless network adapter, a telecommunications adapter, or other devices capable of communicating to one or more different networks. The one or more different networks may include one or more of, without limitation, a local area network (LAN), a wide area network (WAN) (e.g., the Internet, etc.), a mobile network, a virtual network, and / or another suitable public and / or private network capable of supporting communication among two or more of the parts illustrated in FIG. 1, or any combination thereof. In at least one embodiment, the network interface 310 is employed to receive inputs to the computing device 300. In some example embodiments, the computing device 300 may include the processor 302 and one or more network interfaces incorporated into or with the processor 302.
[0081] FIG. 4 illustrates an example method 400 for determining a resource allocation for (or at) a growing facility (e.g., for allocating resources at the growing facility to specific plants based on factors associated with the plants, etc.). The example method 400 is described herein in connection with the system 100, and may be implemented, in whole or in part, in the computing device 106 of the system 100. Further, for purposes of illustration, the example method 400 is also described with reference to the computing device 106, the data structure 108, and more generally, the system 100, and also the computing device 300 of FIG. 3. However, it should be appreciated that the method 400, or other methods described herein, are not limited to the system 100, the distributions in FIG. 2, or the computing device 300. And, conversely, the systems, data structures, and computing devices described herein are not limited to the example method 400.
[0082] At the outset in method 400, it should be appreciated that relevant data related to the growing facility 102 (and areas 104a-d thereof), the plant material(s) at the growing facility 102, etc., is stored and accessible in the data structure 108.
[0083] Initially, then, at 402, one or more requests is / are received at the computing device 106 to include plant material, for example, R0 generation or non-RO generation plant products, in one or more of the areas 104a-d of the growing facility 102. The requests may eachinclude, among other things, an identification of the plant material (e.g., by identifier, type, etc.), a preferred area or location in the growing facility 102, if any, and an expected availability of the plant material, etc. Here, the method 400 may include receiving multiple requests to include plant materials in one or more areas 104a-d of the growing facility 102 over an interval (e.g., a day, multiple days, a week, etc.), etc.
[0084] At 404, the computing device 106 accesses the data relevant to the growing facility 102 in the data structure 108 (or elsewhere as required or desired), based on the request(s). The data, for example, may be consistent with the capacities of the areas 104a-d of the growing facility 102, data representative of the plant materials to be included in the growing facility 102 (e.g., workplans, start dates, etc.), and other data, as explained above or as defined or referenced in the equations and / or constraints described above.
[0085] The computing device 106 then determines, at 406, the resource allocation 110 for the requested plant materials in the growing facility 102, based on the accessed data, the objective function (e.g., as defined in Equation (1), etc.) and associated constraints described herein (e.g., Equations (2)-(12), etc.).
[0086] At 408, the computing device 106 implements the resource allocation 110, automatically or based on an instruction from an associated operator. Initially, for example, the computing device 106 implements the allocation by introducing plant materials from a source into one or more areas 104a-d of the growing facility 102. The introduction of the plant materials may include depositing the germplasm of the R0 generation into soil, in this example, in seed trays, via automated mechanisms alone or in combination with worker intervention, or by planting non-RO generation seeds into soil, in another example, again, in seed trays, via automated mechanisms alone or in combination with worker intervention. After introducing the plant materials into the one or more areas 104a-d, the plant materials are located in the area(s) 104a-d until removed for one or more operations associated with the corresponding plants (e.g., pollination, harvest, transplant, etc.). In connection therewith, the plant materials are exposed, while in the one or more areas 104a-d, to environmental conditions, as prescribed, and permitted to grow, in connection with different growth stages, pollination operations, and / or harvest operations, etc.
[0087] It should be appreciated that the method 400 may be repeated, as necessary, to accommodate additional requests for inclusion of additional plant materials into the growing facility 102, etc.
[0088] In view of the above, it can be seen that the methods and systems herein provide for objective determination of allocating physical space(s) in a growing facility to specific plant materials including, for example, R0 generation plant materials, non-RO generation plant materials, etc. based on one or more objective functions and / or associated constraints. In doing so, various factors such as, for example, capacity of the room (or area, space, etc.), usage / availability of room(s) (or area(s), space(s), etc.), preferences / priorities, availability of plant materials, durations of stages / processes in each of the rooms (or areas, or spaces, etc.), construct / request limits for the plant material(s), etc. are accounted for in defining abilities of plant materials to be allocated to a room, area, space, etc. within the growing facility, and then also abilities of the plant materials to co-exist in that room, area, space, etc. with other plant material(s). As such, the methods and systems herein accomplish highly complex allocations of resources in an objective manner, outside of the typical influence of subjective standards, assumptions, and / or human biases.
[0089] With that said, it should be appreciated that the functions described herein, in some embodiments, may be described in computer executable instructions stored on a computer readable media, and executable by one or more processors. The computer readable media is a non-transitory computer readable media. By way of example, and not limitation, such computer readable media can include RAM, ROM, EEPROM, CD-ROM or other optical disk storage, magnetic disk storage or other magnetic storage device, or any other medium that can be used to carry or store desired program code in the form of instructions or data structures and that can be accessed by a computer. Combinations of the above should also be included within the scope of computer-readable media.
[0090] It should also be appreciated that one or more aspects of the present disclosure may transform a general-purpose computing device into a special-purpose computing device when configured to perform one or more of the functions, methods, and / or processes described herein.
[0091] As will be appreciated based on the foregoing specification, the abovedescribed embodiments of the disclosure may be implemented using computer programming orengineering techniques, including computer software, firmware, hardware or any combination or subset thereof, wherein the technical effect may be achieved by performing at least one of the following operations: (a) in response to one or more requests to include plant material in a growing facility, where the plant materials include RO generation plant materials and / or non-RO generation plant materials, accessing data representative of the growing facility and data representative of the plant material; (b) determining a resource allocation, in which the plant material is assigned to one or more areas of the growing facility, based on the accessed data and an objective function; (c) introducing the plant material into the determined one or more areas of the growing facility, consistent with the resource allocation; (d) and / or (e) receiving the one or more requests, from a facility operator of the growing facility, each of the one or more requests including an indication of the plant material.
[0092] Examples and embodiments are provided so that this disclosure will be thorough, and will fully convey the scope to those who are skilled in the art. Numerous specific details are set forth such as examples of specific components, devices, and methods, to provide a thorough understanding of embodiments of the present disclosure. It will be apparent to those skilled in the art that specific details need not be employed, that example embodiments may be embodied in many different forms and that neither should be construed to limit the scope of the disclosure. In some example embodiments, well-known processes, well-known device structures, and well-known technologies are not described in detail. In addition, advantages and improvements that may be achieved with one or more example embodiments disclosed herein may provide all or none of the above mentioned advantages and improvements and still fall within the scope of the present disclosure.
[0093] Specific values disclosed herein are example in nature and do not limit the scope of the present disclosure. The disclosure herein of particular values and particular ranges of values for given parameters are not exclusive of other values and ranges of values that may be useful in one or more of the examples disclosed herein. Moreover, it is envisioned that any two particular values for a specific parameter stated herein may define the endpoints of a range of values that may also be suitable for the given parameter (i.e., the disclosure of a first value and a second value for a given parameter can be interpreted as disclosing that any value between the first and second values could also be employed for the given parameter). For example, if Parameter X is exemplified herein to have value A and also exemplified to have value Z, it isenvisioned that parameter X may have a range of values from about A to about Z. Similarly, it is envisioned that disclosure of two or more ranges of values for a parameter (whether such ranges are nested, overlapping or distinct) subsume all possible combination of ranges for the value that might be claimed using endpoints of the disclosed ranges. For example, if parameter X is exemplified herein to have values in the range of 1 - 10, or 2 - 9, or 3 - 8, it is also envisioned that Parameter X may have other ranges of values including 1 - 9, 1 - 8, 1 - 3, 1 - 2, 2 - 10, 2 - 8, 2 - 3, 3 - 10, and 3 - 9.
[0094] The terminology used herein is for the purpose of describing particular example embodiments only and is not intended to be limiting. As used herein, the singular forms "a,” “an,” and “the” may be intended to include the plural forms as well, unless the context clearly indicates otherwise. The terms “comprises,” “comprising,” “including,” and “having,” are inclusive and therefore specify the presence of stated features, integers, steps, operations, elements, and / or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and / or groups thereof. The method steps, processes, and operations described herein are not to be construed as necessarily requiring their performance in the particular order discussed or illustrated, unless specifically identified as an order of performance. It is also to be understood that additional or alternative steps may be employed.
[0095] When a feature is referred to as being “on,” “engaged to,” “connected to,” “coupled to,” “associated with,” “in communication with,” or “included with” another element or layer, it may be directly on, engaged, connected or coupled to, or associated or in communication or included with the other feature, or intervening features may be present. As used herein, the term “and / or” and “at least one of’ includes any and all combinations of one or more of the associated listed items.
[0096] None of the elements recited in the claims are intended to be a means-plus- function element within the meaning of 35 U.S.C. §112(f) unless an element is expressly recited using the phrase “means for,” or in the case of a method claim using the phrases “operation for” or “step for.”
[0097] Although the terms first, second, third, etc. may be used herein to describe various features, these features should not be limited by these terms. These terms may be only used to distinguish one feature from another. Terms such as “first,” “second,” and othernumerical terms when used herein do not imply a sequence or order unless clearly indicated by the context. Thus, a first feature discussed herein could be termed a second feature without departing from the teachings of the example embodiments.
[0098] The foregoing description of the embodiments has been provided for purposes of illustration and description. It is not intended to be exhaustive or to limit the disclosure. Individual elements or features of a particular embodiment are generally not limited to that particular embodiment, but, where applicable, are interchangeable and can be used in a selected embodiment, even if not specifically shown or described. The same may also be varied in many ways. Such variations are not to be regarded as a departure from the disclosure, and all such modifications are intended to be included within the scope of the disclosure.
Claims
CLAIMSWhat is claimed is:
1. A method for allocating resources in a growing facility, the method comprising: in response to one or more requests to include plant material in a growing facility, accessing, by a computing device, data representative of the growing facility and data representative of the plant material; determining, by the computing device, a resource allocation, in which the plant material is assigned to one or more areas of the growing facility, based on the accessed data and an objective function; and introducing, by the computing device, the plant material into the determined one or more areas of the growing facility, consistent with the resource allocation.
2. The method of claim 1, further comprising receiving the one or more requests, from a facility operator of the growing facility, each of the one or more requests including an indication of the plant material; and3. The method of claim 1, wherein the plant material includes a mix of one or more of: com plant material, cotton plant material, canola plant material, soybean plant material, rice plant material, wheat plant material, sugar cane plant material, sugar beet plant material, and / or alfalfa plant material.
4. The method of claim 1, wherein the areas of the growing facility include rooms of the growing facility; and wherein the plant material includes RO generation plant material and / or non-RO generation plant material.
5. The method of claim 4, wherein the plant material includes RO generation plant material; wherein the objective function is consistent with:wherein TDP represents a total dummy presence, CT represents a total cycle time, TGP represents a total group preferred allocation, TGPW represents a total group preferred workplan allocation, CPR represents a relative capacity utilization rate, TR represents a total number of rooms occupied, TPP represents total placement in primary rooms, TPO represents total placement in overflow rooms, TP A represents a number of requests located in rooms preferred by their types, TCV represents a total construction violation, and TRSP represents a total RO support pair.
6. The method of claim 1, wherein determining the resource allocation is based on demand, which includes a current demand and a future demand.
7. The method of claim 1, wherein the plant material includes non-RO generation plant material; and wherein the objective function is consistent with:
8. The method of claim 1, wherein the plant material includes non-RO generation plant material; and wherein the objective function is consistent with:
9. The method of claim 1, wherein introducing, by the computing device, the plant material into the determined one or more areas of the growing facility includes issuing instructions to one or more users associated with the facility, consistent with the resource allocation.
10. The method of any one of the above claims, further comprising growing the plant material in the determined one or more areas of the growing facility.
11. A system for allocating resources in a growing facility, the system comprising at least one computing device configured to: in response to one or more requests to include plant material in a growing facility, access data representative of the growing facility and data representative of the plant material, wherein the plant material includes RO generation plant material and / or non-RO generation plant material; determine a resource allocation, in which the plant material is assigned to one or more areas of the growing facility, based on the accessed data and an objective function; and introduce the plant material into the determined one or more areas of the growing facility, consistent with the resource allocation.
12. The system of claim 11, wherein the at least one computing device is further configured to receive the one or more requests from a facility operator of the growing facility, each of the one or more requests including an indication of the plant material.
13. The system of claim 11, wherein the plant material includes a mix of one or more of: corn plant material, cotton plant material, canola plant material, soybean plant material, rice plant material, wheat plant material, sugar cane plant material, sugar beet plant material, and / or alfalfa plant material.
14. The system of claim 11, wherein the areas of the growing facility include rooms of the growing facility.
15. The system of claim 11 , wherein the plant material includes RO generation plant material; wherein the objective function is consistent with:wherein TDP represents a total dummy presence, CT represents a total cycle time, TGP represents a total group preferred allocation, TGPW represents a total group preferred workplan allocation, CPR represents a relative capacity utilization rate, TR represents a total number of rooms occupied, TPP represents total placement in primary rooms, TPO represents total placement in overflow rooms, TPA represents a number of requests located in rooms preferred by their types, TCV represents a total construction violation, and TRSP represents a total RO support pair.
16. The system of claim 11 , wherein the plant material includes non-RO generation plant material; and wherein the objective function is consistent with:
17. The system of claim 11, wherein the plant material includes non-RO generation plant material; and wherein the objective function is consistent with:
18. The system of claim 11 , wherein the at least one computing device is configured, in order to introduce the plant material into the determined one or more areas of the growing facility, to issue instructions to one or more users associated with the facility, consistent with the resource allocation.
19. The system of any one of claims 11-18, further comprising the growing facility.
20. A non-transitory computer readable storage medium including executable instructions for use in allocating resources in a growing facility, which, when executed by at least one processor, cause the at least one processor to: in response to one or more requests to include plant material in a growing facility, access data representative of the growing facility and data representative of the plant material, wherein the plant material includes RO generation plant material and / or non-RO generation plant material; determine a resource allocation, in which the plant material is assigned to one or more areas of the growing facility, based on the accessed data and an objective function; and introduce the plant material into the determined one or more areas of the growing facility, consistent with the resource allocation.
21. The non-transitory computer readable storage medium of claim 20, wherein the executable instructions, when executed by the at least one processor, further cause the at least one processor to receive the one or more requests from a facility operator of the growing facility, each of the one or more requests including an indication of the plant material.
22. The non-transitory computer readable storage medium of claim 21, wherein the plant material includes a mix of one or more of: corn plant material and soybean plant material; and / or wherein the plant material includes a mix of one or more of: com plant material, cotton plant material, canola plant material, soybean plant material, rice plant material, wheat plant material, sugar cane plant material, sugar beet plant material, and / or alfalfa plant material.
23. The non-transitory computer readable storage medium of any one of claims 20- 22, wherein the areas of the growing facility include rooms of the growing facility.
24. The non-transitory computer readable storage medium of claim 23, wherein the plant material includes RO generation plant material; wherein the objective function is consistent with:wherein TDP represents a total dummy presence, CT represents a total cycle time, TGP represents a total group preferred allocation, TGPW represents a total group preferred workplan allocation, CPR represents a relative capacity utilization rate, TR represents a total number of rooms occupied, TPP represents total placement in primary rooms, TPO represents total placement in overflow rooms, TPA represents a number of requests located in rooms preferred by their types, TCV represents a total construction violation, and TRSP represents a total RO support pair.
25. The non-transitory computer readable storage medium of claim 20, wherein the plant material includes non-RO generation plant material; and wherein the objective function is consistent with:
26. The non-transitory computer readable storage medium of claim 20, wherein the plant material includes non-RO generation plant material; and wherein the objective function is consistent with:
27. The non-transitory computer readable storage medium of claim 25 or claim 26, wherein the objective function is subject to one or more constraints, and wherein the one or more constraints include one or more of Equations (15) through (25) herein.
28. The non-transitory computer readable storage medium of any one of claims 20- 27, wherein the at least one computing device is configured, in order to introduce the plant material into the determined one or more areas of the growing facility, to issue instructions to one or more users associated with the facility, consistent with the resource allocation.
Citation Information
Patent Citations
Methods And Systems For Use In Implementing Resources In Plant Breeding
US20200305373A1
Satellite-based agricultural modeling
US20220036483A1
Integrated plant breeding methods for complementary pairings of plants and microbial consortia
US20220232789A1