Refined evaluation method for vertical pre-deformation control of super-high-rise building

By establishing a finite element model and monitoring unit in super-high-rise buildings, the stress changes of the horizontal contact rods are monitored in real time, and optimally enclosed and consolidated according to the bending internal force indicators, the accuracy of vertical deformation control of super-high-rise buildings is solved, and the improvement of the improvement of the accuracy of vertical deformation control of super-high-rise buildings is improved. The level of refinement and construction efficiency of vertical pre-deformation compensation are achieved.

WO2024239613A1PCT designated stage expired Publication Date: 2024-11-28SHANGHAI CONSTRUCTION GROUP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/138639
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-25
Filing Date
2023-12-14
Publication Date
2024-11-28

AI Technical Summary

Technical Problem

In the construction of super high-rise buildings, the existing technology cannot effectively judge the construction time of the transverse link members in each layer of transverse truss layer, which affects the accuracy of vertical deformation control of super high-rise buildings, resulting in between the concrete core cylinder and the steel structure outer frame. The vertical differential deformation cannot be effectively compensated.

Method used

By establishing a finite element model of super-high-rise buildings, it is divided into multiple monitoring units to monitor the stress changes of the transverse connecting rods in real time, and perform optimal closed consolidation according to the moment when the bending internal force index is closest to zero, and temporarily or permanently fixed connection nodes. Ensure refined control of vertical deformation compensation.

Benefits of technology

The accurate judgment of the optimal sealing and consolidation time of the horizontal connecting rods is achieved, the vertical pre-deformation control effect of super-high-rise buildings is improved, the lean level in the construction stage is improved, and construction costs are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 000001
    Figure 000001
  • Figure 000002
    Figure 000002
  • Figure 000003
    Figure 000003
Patent Text Reader

Abstract

The present invention relates to the technical field of super-high-rise building construction. Disclosed is a refined evaluation method for vertical pre-deformation control of a super-high-rise building, aiming to solve the problem of being unable to determine the construction time of transverse connecting bars in each transverse truss layer in a targeted manner in existing vertical deformation control methods for a super-high-rise building. The method comprises the steps of: performing finite element analysis on the construction process of a concrete core tube of super-high-rise building to obtain a theoretical compensation value of vertical deformation of the concrete core tube, and dividing the super-high-rise building into a plurality of monitoring units by means of transverse truss layers; performing vertical deformation compensation on each floor of each monitoring unit from bottom to top, and using the moment when the bending internal force index of each transverse connecting rod is closest to zero as the optimal closing and fixed connection time; and before the optimal time, the transverse connecting bars being hingedly connected to the concrete core tube and a steel-structured outer frame, and after each transverse connecting bar releases secondary internal force, permanently closing the transverse connecting bar, and permanently fixedly connecting the transverse connecting bar to the concrete core tube and the steel-structured outer frame.
Need to check novelty before this filing date? Find Prior Art

Description

A refined evaluation method for vertical pre-deformation control of super high-rise buildings Technical Field

[0001] The present invention relates to the technical field of super high-rise building construction, and in particular to a refined evaluation method for vertical pre-deformation control of super high-rise buildings. Background Art

[0002] In the construction of super-high-rise buildings exceeding 300 meters in height, there is a widespread need to control vertical pre-deformation. Under the influence of factors such as deadweight, pressure loads, and shrinkage and creep, the concrete core tube will experience significant vertical deformation, resulting in its final floor height and elevation failing to reach the design values. Without pre-compensation for vertical deformation, the actual top elevation of the super-high-rise building will differ by approximately 50 cm from the design height. At the same time, because the steel structure outer frame surrounding the concrete core tube (which serves as the external enclosure of the super-high-rise building and generally supports the curtain wall) has a low deadweight and is not subject to shrinkage and creep, the steel structure outer frame will experience a large vertical differential deformation relative to the concrete core tube, resulting in large secondary internal forces in the transverse connecting members of the transverse truss layer between the two, affecting their function.

[0003] To reduce the vertical differential deformation between the concrete core and the steel outer frame, scientific and reasonable vertical pre-deformation compensation is valuable and necessary. However, the research on the vertical differential deformation compensation mechanism is still unclear. Engineers are unable to effectively confirm the differential deformation of the transverse connecting members caused by vertical pre-deformation compensation. As a result, they are unable to accurately determine the construction time of the transverse connecting members, which affects the accuracy of vertical deformation control in super-high-rise buildings.

[0004] Summary of the Invention

[0005] Existing methods for controlling vertical deformation of super-high-rise buildings are unable to precisely determine the construction time of the transverse connecting rods in each transverse truss layer, which affects the accuracy of vertical deformation control of super-high-rise buildings. The purpose of this invention is to provide a refined assessment method for vertical pre-deformation control of super-high-rise buildings.

[0006] The technical solution adopted by the present invention to solve the technical problem is: a refined evaluation method for vertical pre-deformation control of super high-rise buildings, the steps are as follows:

[0007] S1: Establish a finite element model of the concrete core tube of a super high-rise building and conduct finite element analysis on its construction process to obtain the sum of the theoretical compensation values ​​for the vertical deformation of the concrete core tube caused by its own weight and the shrinkage and creep of the concrete material; assume that the super high-rise building has n transverse truss layers, and set each floor between the bottom floor and the first transverse truss layer as the first monitoring unit, each floor between the second and third transverse truss layers as the second monitoring unit, and so on. The n transverse truss layers divide the super high-rise building into n+1 monitoring units.

[0008] S2: Based on the theoretical compensation value of vertical deformation obtained in step S1, vertical deformation compensation is performed on each floor of the first monitoring unit from bottom to top. The two ends of all transverse connecting rods in the first transverse truss layer are hingedly connected to the concrete core tube and the steel structure outer frame respectively. After the vertical deformation caused by the deadweight of the concrete core tube is fully exerted, the elevation of the first transverse truss layer and the stress changes of the upper and lower wing plates of the transverse connecting rods are monitored in real time. The connection nodes between the two ends of the transverse connecting rods and the concrete core tube and the steel structure outer frame are temporarily fixed. The moment when the bending internal force index of the transverse connecting rod is closest to zero is used as its optimal closed consolidation time.

[0009] S3: When the theoretical compensation value of vertical deformation is large, the transverse connecting rod is bent downward as a whole, and the temporary fixation of the connection nodes between the transverse connecting rod and the concrete core tube and the steel structure outer frame is converted to permanent closed consolidation; when the theoretical compensation value of vertical deformation is small, the transverse connecting rod is bent upward as a whole, and the temporary fixation between the transverse connecting rod and the concrete core tube and the steel structure outer frame is loosened, so that the two ends of the transverse connecting rod return to a free rotation state and the secondary internal force is released, and then the connection nodes between the transverse connecting rod and the concrete core tube and the steel structure outer frame are converted to permanent closed consolidation;

[0010] S4: Repeat the above steps S2 and S3, and perform vertical deformation compensation for each floor of the remaining n monitoring units from bottom to top, and permanently seal and consolidate all the transverse connecting rods in each transverse truss layer with the connection nodes of the concrete core tube and the steel structure outer frame.

[0011] The present invention provides a refined evaluation method for super-high-rise vertical pre-deformation control. By performing finite element analysis on the construction process of the concrete core tube of a super-high-rise building, the theoretical compensation value of the vertical deformation of the concrete core tube caused by the deadweight and shrinkage creep of the concrete material is obtained. The super-high-rise building is divided into multiple monitoring units by the transverse truss layer. Vertical deformation compensation is performed on each floor of each monitoring unit from bottom to top. The time history data of the stress change of all transverse connecting rods in the transverse truss layer at the top of each monitoring unit is monitored in real time. The moment when the bending internal force index of the transverse connecting rod is closest to zero is used as the optimal closed consolidation time of the transverse connecting rod. Before the optimal closed consolidation time, the transverse connecting rod is hingedly connected to the concrete core tube and the steel structure outer frame, so that the connection between the transverse connecting rod and the two is easy to loosen. The two ends of the structure are returned to the free rotation state and the secondary internal force is released. When the transverse connecting rods are in the optimal internal force state, the connection nodes between the transverse connecting rods and the concrete core tube and the steel structure outer frame are permanently closed and consolidated. This refined evaluation method for super-high-rise vertical pre-deformation control can accurately judge the optimal closed consolidation time of all transverse connecting rods in each transverse truss layer, effectively improving the control effect of vertical pre-deformation during the construction phase of super-high-rise buildings, and improving the lean level of vertical deformation compensation of super-high-rise buildings. Moreover, the method is simple to operate and reduces construction costs.

[0012] Furthermore, it also includes step S5: after the transverse connecting member is permanently closed and consolidated, if the bending internal force index of the transverse connecting member continues to decrease and does not converge, the fixed constraints at both ends of the transverse connecting member are released again, and after the secondary internal force is released, the transverse connecting member is permanently closed and consolidated again.

[0013] Furthermore, the step S4 also includes: when the optimal closed consolidation time of the transverse connecting member is required to be advanced, the actual compensation value of the vertical deformation should be lower than the optimal compensation value, wherein the optimal compensation value is set to 1 to 1.5 times the theoretical compensation value.

[0014] Furthermore, step S4 also includes: when the internal force state of the transverse connecting member after permanent sealing and consolidation is required to be optimal, the actual compensation value of the vertical deformation should be lower than the optimal compensation value, wherein the optimal compensation value is set to 0.6 to 1 times the theoretical compensation value. DETAILED DESCRIPTION

[0015] The concrete core of a super-high-rise building is constructed of high-strength concrete. Due to the effects of deadweight compression and concrete shrinkage and creep, the vertical deformation of the concrete core will continue to change slowly over an extended period of time, lasting up to 5 to 10 years after the super-high-rise structure is topped out. Based on existing experience, the maximum vertical deformation compensation for super-high-rise buildings is generally located in the middle layers, with a compensation value of approximately 30 to 40 cm. The vertical deformation compensation value gradually decreases from the middle layers toward the ends. These values ​​will vary to a certain extent with the height of the super-high-rise building, the construction environment, and the concrete mix ratio.

[0016] The concrete core and steel outer frame of super-high-rise buildings are connected by transverse connecting rods. These ensure that the concrete core and steel outer frame participate in the lateral load. Compared with the vertical deformation of the concrete core during construction, the vertical deformation of the steel outer frame is negligible. Therefore, the time for consolidation of the transverse connecting rods and the two is preferably selected after the concrete core has fully deformed vertically. At this time, the transverse connecting rods perform their connecting function in the internal force state of tension or compression rods, and the coupled stress state of bending tension or bending compression is avoided. This allows the material properties of the transverse connecting rods to be fully utilized and the secondary internal forces to be minimized. However, due to the impact of construction progress, engineering units generally require that the transverse connecting rods be closed and consolidated as soon as possible to avoid adverse effects on subsequent construction processes. From the above analysis, it can be seen that before the transverse connecting rods are closed and consolidated, the concrete core tube has completed most of the vertical deformation. After the transverse connecting rods are closed and consolidated, the internal force is the smallest and the internal force state is optimal. Therefore, the engineering unit can obtain the earliest closing and consolidation time of the transverse connecting rods in advance to accurately judge the construction time of the transverse connecting rods in a targeted manner.

[0017] The following describes in detail the refined evaluation method for super-high-rise vertical pre-deformation control in this embodiment. The steps are as follows:

[0018] S1: Establish a finite element model of the concrete core tube of a super high-rise building and conduct finite element analysis on its construction process to obtain the sum of the theoretical compensation values ​​for the vertical deformation of the concrete core tube caused by its own weight and the shrinkage and creep of the concrete material; assume that the super high-rise building has n transverse truss layers, and set each floor between the bottom floor and the first transverse truss layer as the first monitoring unit, each floor between the second and third transverse truss layers as the second monitoring unit, and so on. The n transverse truss layers divide the super high-rise building into n+1 monitoring units.

[0019] S2: Based on the theoretical compensation value of vertical deformation obtained in step S1, vertical deformation compensation is performed on each floor of the first monitoring unit from bottom to top. The two ends of all transverse connecting rods in the first transverse truss layer are hingedly connected to the concrete core tube and the steel structure outer frame respectively. Since the hinged connection nodes can rotate but cannot displace, the transverse connecting rods are only tension rods or compression rods, and no bending internal force will occur. After the vertical deformation caused by the deadweight of the concrete core tube is fully exerted, generally after the structural construction exceeds half of the total height of the building, multiple strain sensors are installed on the upper and lower wing plates of the transverse connecting rods along the axial direction. The initial value of the strain sensor is set to zero. The stress deformation of the upper and lower wing plates of the transverse connecting rods is monitored in real time, and the elevation of the elevation observation point of the first transverse truss layer is monitored in real time. Then, the two ends of the transverse connecting rod are temporarily fixed to the connection nodes of the concrete core tube and the steel structure outer frame, that is, temporarily restricting its rotation. At this time, under the long-term influence of concrete material shrinkage and creep, the concrete core tube will be in a bending stress state, which is a bending-tension or bending-compression internal force state. The change in the bending stress state reflects the vertical deformation of the concrete core tube. As the vertical deformation caused by concrete shrinkage and creep factors is fully exerted, the bending internal force index of the transverse connecting rod will gradually converge to a specific boundary value. The moment when the bending internal force index of the transverse connecting rod is closest to zero is taken as its optimal closed consolidation time. According to the direction of the bending internal force, an evaluation index is established, with the compression of the upper flange plate as the positive direction and the tension of the upper flange plate as the negative direction, representing the influence of concrete shrinkage and creep factors on the control of vertical deformation.

[0020] S3: When the theoretical compensation value of vertical deformation is large, the strain sensor of the upper wing plate of the transverse connecting member presents a negative value, while the strain sensor of the lower wing plate presents a positive value, that is, the upper wing plate is compressed and the lower wing plate is tensile, and the transverse connecting member as a whole is in a downward bending state; as the deadweight of the superstructure gradually increases, the vertical deformation caused by the deadweight will be in the opposite direction to the vertical deformation caused by the shrinkage and creep of the concrete, and gradually offset, and the bending internal force evaluation index of the transverse connecting member tends to zero. The moment when the bending internal force index of the transverse connecting member is closest to zero is taken as its optimal closed consolidation time, and the temporary fixation of the connection node between the transverse connecting member and the concrete core tube and the steel structure outer frame is converted to permanent closed consolidation. The optimal closed consolidation time is basically when the superstructure reaches a relatively high floor height, such as more than 80% of the total height of a super high-rise building;

[0021] When the theoretical compensation value of vertical deformation is small, the strain sensor of the upper wing plate of the transverse connecting rod presents a positive value, while the strain sensor of the lower wing plate presents a negative value, that is, the upper wing plate is under tension and the lower wing plate is under compression, and the transverse connecting rod as a whole is in an upward bending state; as the deadweight of the superstructure gradually increases, the vertical deformation caused by the deadweight will be in the same direction as the vertical deformation caused by shrinkage creep, and the bending internal force index of the transverse connecting rod will gradually increase. However, the farther the floor is from the transverse truss layer, the greater its deadweight will be on the vertical strength of the concrete core tube at the location of the transverse truss layer. The smaller the influence of lateral deformation, the smaller the bending internal force will be. The time corresponding to the convergence boundary is the optimal closed consolidation time, which is generally when the superstructure reaches a relatively low floor height, such as 50% to 70% of the total height of a super high-rise building. The temporary fixation between the transverse connecting rods and the concrete core tube and the steel structure outer frame is loosened, so that the two ends of the transverse connecting rods return to a free rotation state and release the secondary internal force. Then, the connection nodes between the transverse connecting rods and the concrete core tube and the steel structure outer frame are converted to permanent closed consolidation.

[0022] S4: Repeat steps S2 and S3 above, performing vertical deformation compensation on each floor of the remaining n monitoring units, starting from bottom to top. When the bending internal force evaluation index of the transverse connecting rods in each transverse truss layer approaches zero, the connection nodes between the transverse connecting rods, the concrete core tube, and the steel structure outer frame are permanently sealed and consolidated. In this embodiment, the transverse connecting rods are generally H-shaped steel rods.

[0023] The present invention is a refined evaluation method for super high-rise vertical pre-deformation control. By performing finite element analysis on the construction process of the concrete core tube of a super high-rise building, the theoretical compensation value of the vertical deformation caused by the deadweight of the concrete core tube and the shrinkage and creep of the concrete material is obtained. The super high-rise building is divided into multiple monitoring units by the transverse truss layer. The vertical deformation compensation is performed on each floor of each monitoring unit from bottom to top. The time history data of the stress change of all transverse connecting rods in the transverse truss layer at the top of each monitoring unit is monitored in real time. The moment when the bending internal force index of the transverse connecting rod is closest to zero is used as the optimal closed consolidation time of the transverse connecting rod. Before the optimal closed consolidation time, the transverse connecting rod and the concrete are connected. The concrete core tube and the steel structure outer frame are both hingedly connected, which makes it easy to loosen the connection between the transverse connecting rods and the two, so that their two ends return to a free rotation state and release the secondary internal force. When the transverse connecting rods are in an optimal internal force state, the connection nodes between the transverse connecting rods and the concrete core tube and the steel structure outer frame are permanently closed and consolidated; this refined evaluation method for super-high-rise vertical pre-deformation control can accurately judge the optimal closing and consolidation time of all transverse connecting rods in each transverse truss layer, effectively improving the control effect of vertical pre-deformation during the construction stage of super-high-rise buildings, and improving the lean level of vertical deformation compensation of super-high-rise buildings. Moreover, the method is simple to operate and reduces construction costs.

[0024] The refined assessment method for super-high-rise vertical pre-deformation control in this embodiment also includes step S5. After the transverse connecting members are permanently sealed, the vertical deformation caused by concrete shrinkage and creep is still in effect. Therefore, the data monitored by the strain sensors can continue to be analyzed. The bending internal force index after the transverse connecting members are permanently sealed and consolidated will always be less than zero. Theoretically, this value should converge quickly. If it continues to decrease and does not converge, it indicates that the transverse connecting members were sealed and fixed too early. The fixed constraints at both ends of the transverse connecting members should be released again. After the secondary internal forces are released, the transverse connecting members should be permanently sealed and consolidated again.

[0025] The step S4 further includes: when the optimal closed consolidation time of the transverse connecting member is required to be advanced, the given actual compensation value of the vertical deformation should be slightly lower than the optimal compensation value, wherein the optimal compensation value is set to 1 to 1.5 times the theoretical compensation value, and the deformation caused by concrete shrinkage and creep is limited by the constraint of the transverse connecting member.

[0026] The step S4 further includes: when the internal force state of the transverse connecting member after permanent sealing and consolidation is required to be optimal, the given actual compensation value of the vertical deformation should be slightly lower than the optimal compensation value, wherein the optimal compensation value is set to 0.6 to 1 times the theoretical compensation value.

[0027] The above description is only a description of the preferred embodiments of the present invention and does not limit the scope of the present invention. Any changes and modifications made by ordinary technicians in the field of the present invention based on the above disclosure shall fall within the scope of the claims.

Claims

1. A refined evaluation method for vertical pre-deformation control of super high-rise buildings, characterized in that: Here are the steps: S1: Establish a finite element model of the concrete core tube of a super high-rise building, and perform finite element analysis on its construction process to obtain the sum of theoretical compensation values ​​of vertical deformation of the concrete core tube caused by the deadweight and shrinkage creep of concrete materials; assume that the super high-rise building has n transverse truss layers, and set each floor between the bottom floor and the first transverse truss layer as the first monitoring unit, and each floor between the second transverse truss layer and the third transverse truss layer as the second monitoring unit, ..., and so on. The n transverse truss layers divide the super high-rise building into n+1 monitoring units; S2: According to the theoretical compensation value of vertical deformation obtained in step S1, vertical deformation compensation is performed on each floor of the first monitoring unit from bottom to top. The two ends of all transverse connecting rods in the first transverse truss layer are respectively hingedly connected to the concrete core tube and the steel structure outer frame. After the vertical deformation caused by the deadweight of the concrete core tube is fully exerted, the elevation of the first transverse truss layer and the stress changes of the upper wing plate and the lower wing plate of the transverse connecting rod are monitored in real time. The connection nodes of the two ends of the transverse connecting rod and the concrete core tube and the steel structure outer frame are temporarily fixed. The moment when the bending internal force index of the transverse connecting rod is closest to zero is taken as its optimal closed consolidation time. S3: When the theoretical compensation value of vertical deformation is large, the transverse connecting rod is bent downward as a whole, and the temporary fixation of the connection nodes between the transverse connecting rod and the concrete core tube and the steel structure outer frame is converted into permanent closed consolidation; when the theoretical compensation value of vertical deformation is small, the transverse connecting rod is bent upward as a whole, and the temporary fixation between the transverse connecting rod and the concrete core tube and the steel structure outer frame is released, so that the two ends of the transverse connecting rod return to a free rotation state and release the secondary internal force, and then the connection nodes between the transverse connecting rod and the concrete core tube and the steel structure outer frame are converted into permanent closed consolidation; S4: Repeat the above steps S2 and S3, and perform vertical deformation compensation for each floor of the remaining n monitoring units from bottom to top, and permanently close and consolidate all the transverse connecting rods in each transverse truss layer with the connection nodes of the concrete core tube and the steel structure outer frame.

2. The refined evaluation method for vertical pre-deformation control of super high-rise buildings according to claim 1 is characterized in that: The method further comprises step S5: after the transverse connecting rod is permanently closed and consolidated, if the bending internal force index of the transverse connecting rod continues to decrease and does not converge, the fixed constraints at both ends of the transverse connecting rod are released again, and after the secondary internal force is released, the transverse connecting rod is permanently closed and consolidated again.

3. The refined evaluation method for vertical pre-deformation control of super high-rise buildings according to claim 1 is characterized in that: The step S4 also includes: when the optimal closed consolidation time of the transverse connecting rod is required to be advanced, the actual compensation value of the vertical deformation should be lower than the optimal compensation value, wherein the optimal compensation value is set to 1 to 1.5 times the theoretical compensation value.

4. The refined evaluation method for vertical pre-deformation control of super high-rise buildings according to claim 1 is characterized in that: The step S4 also includes: when the internal force state of the transverse connecting rod after permanent closure and consolidation is required to be optimal, the actual compensation value of the vertical deformation should be lower than the optimal compensation value, wherein the optimal compensation value is set to 0.6 to 1 times of the theoretical compensation value.

Citation Information

Patent Citations

  • Construction method for super high-rise door-shaped building

    CN103352567A

  • High-rise frame-tube structure vertical absolute deformation and differential deformation monitoring device and method

    CN105466366A

  • Vertical deformation construction monitoring method for super high-rise building

    CN112699454A

  • Construction method of suspension steel structure

    CN115467417A

  • Refined evaluation method for vertical pre-deformation control of super high-rise building

    CN116579215A