Standardized construction technology for same-layer structure of equal-height climbing system
Through standardized construction technology of the same-layer structure of the same-level structure of the same-rise climbing system, the problems of long construction period, high cost and high coordination difficulties in the construction technology of high-rise building structures have been solved, and the construction efficiency and safety have been improved, reducing environmental impacts have been reduced. The structural system separation and support system design optimize construction process and resource utilization.
Patent Information
- Application Number
- CN202411305712.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-19
- Publication Date
- 2024-12-03
AI Technical Summary
The existing high-rise building structure construction technology has problems such as long construction period, high cost, difficult construction coordination and great environmental impact, especially in the non-concentric synchronous construction method of core cylinder and steel frame.
Standardized construction technology of the same-layer structure of the same-level structure is adopted. By dividing the core cylinder and the steel frame into independent parts for construction, using lantern frames and formwork frames for fine calibration and installation, the temporary support structure is reduced and the steel beam installation is improved. Efficiency, and synchronous construction is carried out at the junction of core cylinder and steel frame to optimize construction process and resource utilization.
It significantly shortens the construction period, reduces costs, improves construction efficiency and safety, reduces the impact on the environment and traffic, and realizes standardized separation of the structural system and systematic design of the support system, improving construction quality and safety .
Smart Images

Figure CN119062000A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a standardized construction technology for a same-layer structure of an equal-height climbing system applicable to a concrete core tube-steel outer frame structural system. Background Art
[0002] With the continuous progress of building science and technology and the improvement of social and economic levels, modern cities have set off a boom in the construction of high-rise and super-high-rise buildings. High-rise buildings are not only a symbol of urban development, but also a manifestation of technological innovation and engineering capabilities. Among the many structural types, the concrete core tube-steel frame structure is widely used in buildings with a height of 100 to 500 meters due to its low complexity and strong structural stability. The advantage of the core tube-steel frame structure lies not only in its stability, but also in its ability to maintain good performance under external forces such as earthquakes and wind loads.
[0003] The synchronous climbing construction technology of equal height is an advanced construction method, in which the core tube and the steel outer frame are constructed synchronously on the same floor and climb upward at the same time. Compared with the traditional non-equal height synchronous construction (the core tube must be constructed in advance, and the steel outer frame can be constructed after a certain period of time), this method has significant advantages. First, the synchronous climbing construction of equal height can significantly shorten the construction period. The traditional method requires the construction of the steel outer frame after the construction of the core tube, which not only prolongs the construction period, but also increases the coordination difficulty of the construction site. The synchronous climbing construction of equal height can simultaneously construct the core tube and the steel outer frame on the same floor, greatly improving the construction efficiency. Secondly, the synchronous climbing construction of equal height can significantly reduce the construction cost. In the traditional method, due to the time difference between the construction of the core tube and the steel outer frame, more temporary support structures are required, which increases the material and labor costs. At the same time, too many support structures will occupy a large amount of construction space, thereby affecting the advancement of the work that can be carried out in coordination, which is not conducive to the division of labor and cooperation. The synchronous climbing construction of equal height reduces the use of temporary support structures by separating the steel frame and the core tube on the same floor, thereby reducing costs, facilitating the coordinated advancement of construction in different areas, and greatly improving construction efficiency. In addition, this method can also reduce indirect costs caused by extended construction period, such as site rental fees, equipment rental fees, etc.
[0004] In addition, the promotion and application of the synchronous climbing construction technology of equal height also has important social and economic benefits. With the increasing shortage of urban land resources, fast and efficient construction technology can better meet the needs of urban development and promote the efficient use of land resources. At the same time, the shortening of the construction period will also help reduce the impact on the surrounding environment and traffic, and improve construction safety and environmental protection. With the continuous development and improvement of this technology, it will be widely used in more super high-rise building projects in the future, injecting new vitality into urban construction. Summary of the invention
[0005] Technical problem: The purpose of the present invention is to overcome the shortcomings of existing high-rise building structure construction technology and provide a standardized and efficient construction technology for the same-layer structure of the core tube-steel outer frame high climbing system.
[0006] Technical solution: The standardized construction technology for the same-layer structure of the equal-height climbing system applied by the present invention adopts the following technical solution: First, the core tube and the steel outer frame are divided into two independent parts for construction. The steel outer frame is constructed from the inside out to reserve construction space for the core tube. When installing the steel column, the steel column needs to be processed in sections, and the height of each section of the steel column is one to two stories high. The steel column is hoisted in a clockwise direction, and the initial calibration is first carried out, and then the closed fine calibration is carried out to eliminate the cumulative error, and finally the overall fine calibration is carried out. When tying the wall column reinforcement, the horizontal reinforcement of the shear wall and the hidden column stirrups need to be tied to the bottom position of the steel structure embedded parts to create conditions for the subsequent installation of the steel structure embedded parts. At the same time, the lantern frame is installed at the junction of the core tube and the steel frame. The lantern frame adopts a buckle frame, which is designed as three rows, with an I-beam on the top and an adjustable base underneath, and is set at the separation port of all structural systems, including the separation between the steel outer frame column and the beam and the separation between the beams. After the lantern frame is erected, the formwork frame is installed between the steel beams.
[0007] Furthermore, the mechanical and electrical pre-embedded work of the shear wall needs to be started in advance and pre-embedded in sequence. First, use a level to mark the horizontal line, then use a total station to lay out the axis, and determine the pre-embedded position by the intersection of the two lines. During the pre-embedded process, it is necessary to simultaneously install and calibrate the outer ring main beam, and complete the welding of the node and the high-strength bolt connection. Next, the outer ring main beam is inspected for flaws and repainted. During this period, the preparation of the wall column formwork can also be carried out simultaneously to ensure the continuity and efficiency of the construction.
[0008] Furthermore, in order to improve the efficiency of steel beam installation, especially at the connection between the steel beam and the core tube, special attention should be paid to the docking process of the embedded parts and the steel beam. First, the steel beam can be pre-installed in place, one side is connected to the steel column or main steel beam, and the other side is placed on the already built lantern frame. This method can quickly position the steel beam without affecting other construction processes. Next, the embedded parts are connected to the steel beam. When installing the steel beam, it is necessary to ensure that the steel bars have been tied to the bottom of the steel beam to ensure that the embedded parts will not be disturbed when placed. After the installation of the embedded parts is completed, the upper steel bars are tied to avoid interference problems during the docking process. After the installation of all steel beams and embedded parts is completed, unified adjustment work is carried out. This not only ensures the accuracy and stability of the entire structure, but also reduces the time and workload of individual adjustments. In the core tube, the wall column formwork is supported simultaneously, and the beam and slab formwork is prepared. The construction of each link needs to be closely coordinated. The pre-installation of steel beams and the docking of embedded parts, the support of wall and column formwork, the preparation of beam and slab formwork, etc. must be carried out according to the established construction plan to ensure that each step does not interfere with each other and is smoothly connected.
[0009] Furthermore, in the core tube part, it is necessary to coordinate the support and reinforcement of the wall column formwork and lay the beam and slab formwork. In addition, the operating frame in the shaft needs to be installed in advance to ensure the convenience of subsequent operations and construction safety. In the steel frame part, the welding position of the radial beam is first repainted and inspected to ensure the integrity and safety of the structure. At the same time, the steel bar binding work of the outer frame steel column and the hoisting and correction of the ring steel beam are carried out.
[0010] Furthermore, in the core tube part, it is necessary to simultaneously reinforce and inspect the wall column formwork and tie the beam and slab reinforcement. It should be noted that the reinforcement of the wall column formwork must be completed before the corrugated steel sheet of the steel outer frame is laid. In the steel frame part, it is necessary to coordinate the bolt connection and welding of the circumferential steel beam connection, and weld the angle steel at the junction of the steel column and the steel beam. Subsequently, the outer frame steel column formwork is supported and reinforced.
[0011] Furthermore, in the core tube part, it is necessary to tie the steel bars on the plate surface and pre-embed the electromechanical pipelines. In the steel frame part, the angle steel near the core tube is first installed, welded, inspected and repainted. After completing these steps, the corrugated steel plates are laid in two shifts day and night to ensure that the coordinated construction progress is not affected and maintain efficient operation.
[0012] Furthermore, in the core tube part, the slab surface reinforcement binding and mechanical and electrical pipelines are embedded. In the steel frame part, the corrugated steel plate needs to be closed and bolted. After the corrugated steel plate is installed, the operating frame is converted into a support frame, and the corrugated steel plate part close to the core tube is supported by the top support of the inner support wood beam. At the same time, the support and reinforcement of the outer frame steel column formwork are carried out.
[0013] Furthermore, it is necessary to cut the wooden formwork and seal it according to the on-site conditions of the pump pipe hole, wire laying hole and other openings. The reserved position of the pipe well should be located in advance, and the pipe casing that can be buried in place at one time should be ensured to be in place at one time. It should be noted that the steel bar binding, water and electricity installation and curtain wall embedded parts installation must be interspersed. After a part of the floor decking is installed, you can start to drive bolts and lay steel bars, and carry out water and electricity installation and other work simultaneously. For the flanged parts that need to be formed in one time, on the one hand, it is necessary to intervene in the construction in advance, and on the other hand, a certain amount of time should be reserved in the overall construction schedule. For the anti-slopes that need secondary pouring or reserved uncast parts, they will be poured simultaneously during the masonry construction stage.
[0014] Furthermore, the entire structure is poured with concrete. Truck pumps are used to pour concrete from the 1st to the 5th floor, and a concrete placing machine is used for pouring concrete above the 5th floor. Considering that the synchronous climbing technology is mainly used in high-rise buildings, which are usually used as shopping malls and office buildings with high floor heights, and because it is difficult to handle construction procedures at night, the concrete pouring should start in the morning. Two pump pipes are set up on the floor pump pipe, and concrete pouring starts from the core tube to ensure that the concrete can be evenly distributed and solidified in time. This method can not only ensure the construction progress, but also improve the construction quality, and is adapted to the special needs of building high-rise buildings.
[0015] Beneficial effects: (1) Standardized separation of structural systems: The separation of structural systems is the core idea of the synchronous climbing construction method, which can significantly shorten the construction period and improve construction efficiency. The structural system is standardized and separated into the core tube and the steel frame, and the steel frame is further refined into "column-beam separation" and "beam-beam separation". This structural system separation design makes it possible to temporarily support the separated structure through the support system, thereby realizing the independent construction of each part. At the same time, this separation design improves the flexibility and safety of construction, enables the construction of each part to be carried out simultaneously, reduces the mutual interference and coordination difficulty of different construction areas, and further optimizes the construction quality and efficiency; (2) Systematic design of the support system: A temporary support system is set up at the separation end of the structural system, and the connections between the support system and the steel beams (radiant beams), and between the steel columns and the steel beams (radiant beams) are all considered to be simply supported. This system can use a systematic load calculation method to calculate the support load and design the support form. The calculation process is simple and has a high safety factor, ensuring the reliability of the support system. This design effectively reduces the difficulty of front-line technicians in the design of the core support system for synchronous climbing at the same height, and significantly improves the safety of structural construction; (3) Process-based construction of steel-concrete structures: A detailed construction flow chart is prepared for the two independent structures, the core tube and the steel outer frame. By strictly controlling the key processes and clearly displaying the construction process, the construction of the two independent structures can be effectively connected. This method not only improves the one-time pass rate of construction quality, but also realizes the visual control of the construction progress, thereby optimizing the overall construction efficiency and quality management; (4) Rational use of the operating system: The operating system is integrated with the support system to enhance the stability of the support system. Through the special design of the support system, the construction space can be effectively utilized. As the construction progresses, the function of the operating frame can be converted into the support system, thereby achieving efficient use of resources. This not only improves the economy and environmental protection of the construction, but also ensures the stability and safety of the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A standardized and efficient construction technology flow chart for a same-layer structure of a core tube-steel outer frame high-rise system provided by the present invention; Figure 2 This is a schematic diagram of the side elevation of the lantern stand, where 1 represents the steel beam, 2 represents the core tube structure, 3 represents the I-beam used for padding, 4 represents the top support, 5 represents the vertical pole, 6 and 7 represent the diagonal rods, 8 represents the horizontal rod, and 9 represents the adjustable base. DETAILED DESCRIPTION
[0017] The present invention will be further described below with reference to the accompanying drawings: Figure 1 A standardized construction technology for the same-layer structure of the equal-height climbing system is demonstrated, which mainly includes the following steps: First, the core tube and the steel outer frame structure are divided into two independent parts for construction. Before the formal construction, the two parts of the structure are uniformly positioned and laid out. At the interface between the main beam and the core tube, the embedded points of the steel beam are marked with red paint to ensure that these positions can be accurately identified and located in the following construction steps. In the construction area of the core tube, the wall column reinforcement needs to be tied first. In order to ensure the firmness of the reinforcement and the smooth progress of the construction, the horizontal reinforcement of the wall column and the hidden column stirrups need to be tied to the bottom position of the embedded steel structure. This not only helps to form a stable foundation framework, but also creates favorable construction conditions for the subsequent installation of embedded steel structure parts. At the same time, during the process of tying the wall column reinforcement, the erection of the cross frame needs to be carried out simultaneously. The erection of the cross frame can provide the necessary temporary support for the entire structure to ensure that there is no excessive displacement or structural deformation during the construction process.
[0018] In the steel outer frame part, the steel column and lantern frame support system are installed simultaneously. When installing the steel column, it is necessary to process it in sections. Usually, the height of each section of the steel column is controlled to be one to two stories high to meet the needs of different building heights. In this process, the height difference of each steel column must be strictly controlled, and the height difference of the top of each steel column on the same floor shall not be greater than 5mm. In order to ensure the overall horizontality of the structure, the elevation difference of the steel column shall not be greater than L / 1000 and not greater than 5mm. In addition, the misalignment of the connection between the upper and lower columns shall not be greater than 3mm, and the verticality deviation of the steel column shall not be greater than L / 1000 and not greater than 5mm. After the steel column is in place, a crowbar is used to fine-tune the concentricity of the ear plate and the connecting plate. Then, the steel column is gradually fixed firmly by inserting the bolts and tightening them in batches. In order to ensure the stability of the steel column during construction, it is also necessary to pull and fix the steel column cable wind rope as a temporary support. After completing these steps, the construction personnel can use the fall arrester and safety belt to climb to the top of the column through the steel ladder to unhook. The hoisting process of the steel column is carried out in a clockwise direction, from the outside of the structure to the inside. This hoisting method helps to reduce the deviations that occur during the construction process and ensure the symmetry and stability of the overall structure. During the hoisting process, a preliminary calibration is first performed to ensure that the approximate position of the steel column meets the design requirements. Then, through more refined calibration steps, the accumulated errors are gradually eliminated, and finally the overall precise calibration is achieved. This process not only ensures the installation accuracy of the steel column, but also lays a solid foundation for the subsequent structural construction, avoiding structural safety hazards caused by accumulated errors.
[0019] At the junction of the steel beam and the core tube, the synchronous installation of the lantern frame is one of the key steps to ensure the stability of the structure. Figure 2As shown, in order to ensure the strength and stability of the structure, all support frames must be set up in three layers in a row. Specifically, the upper part of the lantern frame uses I-beam 3 as a top support, and the lower part is padded with an adjustable base 9 to ensure that the support system can adapt to different construction requirements and provide sufficient stability. The setting of the lantern frame requires special attention to its position in the structural system, especially to ensure that it is installed at the separation ports of all structural systems, including the separation of the steel outer frame column and the beam, and the separation of the beam and the beam. This design can effectively prevent the structure from being deformed too much during the construction process because the structure has not yet been formed. In order to further enhance the stability of the lantern frame, the vertical poles 5 must be staggered to avoid unnecessary stress concentration in the multi-layer structure. This is particularly important for lantern frames with two or more layers. The crossbar supporting the steel beam on the top support 4 can be made of I-beam according to the on-site material conditions, and the height of the support frame also needs to be adjusted accordingly according to the actual situation. At the same time, wooden squares are inserted into the top support 4 to fix the web of the I-beam to prevent it from slipping. The lantern frame plays a vital role in construction, especially at the position where the steel beam is close to the core tube. The lantern frame here, as part of the support system, can provide support for the steel beams before the concrete strength of the core tube reaches 100%. In order to ensure that the lantern frame and the operating frame can be connected as a whole in the outer part of the core tube and form a through passage, the lantern frame retains three rows of vertical poles. The vertical pole spacing is set to 300mm and 600mm from the core tube to the outside, respectively. The 600mm spacing area can be paved with foot pedals to facilitate the passage of construction workers. After the lantern frame is erected, it is necessary to install the formwork frame between the steel beams. This step is to ensure the accurate positioning of the steel beams and provide a reliable support foundation for subsequent concrete pouring and other construction work. The installation of the formwork frame needs to be closely integrated with the structure of the lantern frame to ensure that the entire support system can provide sufficient strength and stability during the construction process, thereby ensuring the construction quality of the entire building structure.
[0020] Furthermore, in the core tube part, the mechanical and electrical pre-embedded work of the shear wall can be carried out simultaneously with the binding of the wall column reinforcement to ensure construction efficiency and accuracy. Start the pre-embedded work from the southeast corner in order. In the specific operation, first use the level to mark the horizontal line, then use the total station to lay out the axis, and determine the pre-embedded position by the intersection of the two lines. At the same time, the preparation of the wall column formwork can be started synchronously, so that the formwork support can be started immediately after the reinforcement binding is completed, reducing waiting time and improving construction efficiency. In the steel outer frame part, the outer frame steel frame column operating frame is installed first. The erection of the operating frame needs to be based on the positioning of the lantern frame to ensure the stability and consistency of the entire structure. Since the lantern frame is an important support point of the structure, it is strictly forbidden to move the position of the lantern frame during construction. After the operating frame is erected, it must be firmly connected to the lantern frame at every step to ensure the coordination between the two. The welding and flaw detection of the steel column are carried out simultaneously. Then the outer ring main beam is installed and corrected. After the main beam is installed in place, the node welding and high-strength bolt connection need to be carried out immediately. Subsequently, the outer ring main beam was subjected to NDT inspection and repainting.
[0021] Furthermore, in the core tube, the wall column formwork is supported simultaneously, and preparations are made for the subsequent installation of the beam and slab formwork. Accurate measurements should be made according to the design requirements, and the formwork should be fixed with a suitable support system to prevent displacement or deformation during concrete pouring. The preparation of the beam and slab formwork needs to be closely connected with the support of the wall column formwork to ensure the continuity and efficiency of the subsequent construction. In the steel outer frame, the radial steel beam is hoisted, corrected and connected. In order to improve the efficiency of steel beam installation, especially at the connection between the steel beam and the core tube, special attention should be paid to the docking process between the embedded parts and the steel beam. First, the steel beam can be pre-installed in place, one side is connected to the steel column or main steel beam, and the other side is placed on the built lantern frame. This method can quickly locate the steel beam without affecting other construction processes. Subsequently, the embedded parts are installed to ensure that the embedded parts can accurately dock with the steel beam and connect firmly. When installing the steel beam, it is necessary to ensure that the steel bars are tied to the bottom of the steel beam to ensure that the embedded parts will not be disturbed when placed. After the installation of the embedded parts is completed, the upper steel bars are tied to avoid interference problems during the docking process. Subsequently, after the installation of all steel beams and embedded parts is completed, all steel beams and embedded parts will be uniformly adjusted. This not only ensures the accuracy and stability of the entire structure, but also reduces the time and workload of individual adjustments in the later construction. The construction of each link needs to be closely coordinated. The pre-installation of steel beams and the docking of embedded parts, the support of wall column formwork, and the preparation of beam and slab formwork all need to be carried out according to the established construction plan to ensure that each step can be smoothly connected.
[0022] Furthermore, in the core tube part, the wall column formwork is supported and reinforced, and the beam and slab formwork is laid in coordination. After the beam and slab formwork is laid, the elevation, flatness and elevation error of the beam and slab bottom formwork are checked with a level. In addition, the operating frame in the shaft should be installed in advance to ensure that the construction personnel can operate conveniently and safely during the vertical structure construction. This not only helps to improve the construction efficiency, but also effectively reduces the safety hazards caused by the lack of temporary operating platforms. In the steel outer frame part, the welding position of the radial beam is first repainted and flaw detection is carried out to ensure the integrity and safety of the structure. Then the hoisting and correction of the circumferential steel beam are carried out. During this process, attention must be paid to the balance and stability of the steel beam to avoid tilting or displacement. At the same time, during the hoisting of the circumferential steel beam, the steel bar binding work of the outer frame steel column can be carried out in coordination. The coordinated implementation of the above construction steps not only improves the construction efficiency, but also ensures the full utilization of the construction space.
[0023] Furthermore, in the core tube part, it is necessary to simultaneously carry out the reinforcement, acceptance and adjustment of the wall column formwork and the binding of the beam and slab reinforcement. It is particularly important to note that in order to ensure the smooth progress of subsequent work, the reinforcement of the wall column formwork must be completed before the laying of the corrugated steel plate of the steel outer frame part. This sequential arrangement can effectively avoid interference and unnecessary rework in subsequent construction. In the steel frame part, it is necessary to coordinate the bolt connection and welding of the circumferential steel beam connection, and weld the angle steel at the junction of the steel column and the steel beam. Subsequently, the support and reinforcement of the outer frame steel column formwork are carried out. The supported formwork must meet the design size and position requirements. Reinforcement measures may include the use of additional support systems or strengthening the connection parts of the formwork to ensure that during the construction process, the formwork will not be deformed due to external forces, thereby affecting the quality of the final structure. These steps need to be closely coordinated to ensure the smooth progress of the construction process, improve construction efficiency, and ensure the stability and construction quality of the structure.
[0024] Furthermore, in the core tube part, it is necessary to tie the plate surface steel bars and carry out the pre-embedding of the electromechanical pipelines at the same time. The tying of the plate surface steel bars is a crucial part of the entire structural construction. It provides the necessary support for the upper structure. Therefore, it is necessary to ensure that the steel bars are firmly tied according to the design specifications, the spacing is uniform, and the position is accurate. The pre-embedding of the electromechanical pipelines also needs to be carried out at the same time to avoid interference with the completed structure in subsequent construction. In the steel frame part, the angle steel near the core tube position is first installed, welded, flaw detected and repainted. After completing these steps, the corrugated steel plates are laid in two shifts day and night. In order to ensure that the construction progress is not affected and maintain efficient operation, the laying of the corrugated steel plates needs to be carried out continuously. The corrugated steel plates should be laid perpendicular to the direction of the secondary beam. This arrangement can provide better support effect and ensure the overall rigidity and stability of the structure. According to the design requirements of the drawings, additional supports are required for the parts with spans exceeding the specification requirements to prevent excessive deformation or sinking of the steel plates under load. If the junction of the corrugated steel sheet and the core tube is at the cantilever end and the cantilever length exceeds the specified requirements, additional support measures must be taken. Such support can not only enhance the bearing capacity of the cantilever part, but also prevent structural deformation caused by loads during construction or use.
[0025] Furthermore, in the core tube part, the slab surface reinforcement is continued to be tied, and the pre-embedded work of mechanical and electrical pipelines is completed simultaneously. The slab surface reinforcement should be tied strictly in accordance with the design specifications, especially at the junction with the core tube, the arrangement and fixation of the reinforcement must be very firm to prevent displacement or deformation during the concrete pouring process. In the steel frame part, the corrugated steel plate needs to be closed and bolted. As an important part of the load-bearing structure, the installation quality of the corrugated steel plate is directly related to the safety and durability of the entire building. During the construction process, it is strictly forbidden to cut the corrugated steel plate at will. The specifications, position and number of bolts must also meet the design standards to ensure that the steel plates can be firmly connected together to form an integral force-bearing structure. When tying the reinforcement on the corrugated steel plate, the bottom reinforcement must be fixed to prevent the position of the bottom reinforcement from changing during the concrete pouring, thereby affecting the force of the entire plate surface. After the installation of the corrugated steel plate is completed, the operating frame is converted into a support frame to further enhance the stability of the structure. The corrugated steel plate near the core tube is supported by the top-supported internal wooden beams. This support method can effectively disperse the load and prevent the steel plate from bending or deforming during construction and use. At the same time, the outer frame steel column formwork is supported and reinforced to prevent any deformation or offset during the subsequent concrete pouring process.
[0026] Further, the steel bar binding and electromechanical pipeline pre-embedding work on the corrugated steel plate began. First of all, it is necessary to cut the wooden template according to the on-site conditions of the pump pipe hole, the wire laying hole and other openings, and seal them to prevent leakage or other problems during the subsequent construction process. The reserved position of the pipeline well should be located in advance to ensure that the pipe casing that can be buried in place at one time is in place at one time. It is worth noting that the steel bar binding, water and electricity installation and curtain wall embedded parts installation must be interspersed. The water and electricity installation must be carried out simultaneously with the steel bar binding to ensure that the pipeline can pass through the steel mesh smoothly to avoid rework or adjustment in the later stage. The installation of curtain wall embedded parts also needs to be carried out at the same time to ensure that the embedded parts can be accurately placed in place when the curtain wall is installed. After a part of the floor decking is installed, bolting and laying of steel bars can be started, and water and electricity installation and other work can be carried out simultaneously. For the flanged parts that need to be formed in one time, on the one hand, it is necessary to intervene in the construction in advance. These parts are usually the weak links of the structure, and special attention needs to be paid to their stress conditions. Therefore, in the overall construction schedule, sufficient time must be reserved for these parts to ensure the construction quality. For the anti-ridges that require secondary pouring or reserved uncast areas, pouring will be carried out simultaneously during the masonry construction phase.
[0027] Further, the entire structure is poured with concrete, a process that is essential to ensure the overall strength and stability of the building. Truck pumps are used for concrete pouring on floors 1 to 5. The use of truck pumps can effectively improve the pouring efficiency and ensure that the concrete can quickly and evenly cover the entire floor. Above the 5th floor, a concrete placing boom is used for concrete pouring. The concrete placing boom can transport concrete to higher floors to ensure the continuity and quality of the pouring process. Considering that the synchronous climbing technology is mainly used in high-rise buildings, such buildings are usually used as shopping malls and office buildings, so the floor height is relatively high and the structural design is complex. Since night construction may face problems such as difficult procedures and noise restrictions, concrete pouring should start in the morning. This arrangement not only helps to utilize the working time throughout the day and ensure that the concrete can solidify under suitable conditions, but also reduces the inconvenience caused by night construction. In order to ensure the uniformity of concrete pouring and timely solidification, the construction team will adopt a double-tube arrangement strategy for the floor pump pipe setting. Specifically, two pump pipes will be set up to pour concrete starting from the core tube to ensure that the concrete can be evenly distributed and solidified in time. The double-tube arrangement effectively disperses the concrete delivery pressure, ensuring that the concrete can evenly cover the entire floor, while reducing the possibility of voids or uneven areas during the pouring process so that the concrete can develop strength more quickly.
[0028] The present invention is not limited to the specific implementation methods described above. The above is only the preferred implementation process of the present invention and does not limit the protection scope of this application. The specific implementation process can be adjusted according to actual engineering needs. Without departing from the spirit of the present invention and the protection scope of the claims, those skilled in the art can perform various forms of process changes under the guidance of the present invention, and these changes are all included in the protection scope of the present invention.
Claims
1. A standardized construction technology for the same-layer structure of the equal-height climbing system, characterized in that: The method comprises the following steps: S1. Tie up the wall column reinforcement, install the steel column and lantern frame; S2. Pre-embedded mechanical and electrical equipment of shear walls and installation of outer ring main beams; S3. Wall column formwork support and radial beam installation; S4. Support and reinforcement of wall column formwork and installation of ring steel beams; S5. Acceptance and adjustment of beam and column reinforcement binding and wall and column formwork, and steel node connection; S6. Tie up steel bars on the slab surface, embed electromechanical pipelines, install angle steels and lay corrugated steel plates; S7. Closing and connection of corrugated steel plates; S8. Tie-up of corrugated steel plates and pre-embedding of electromechanical pipelines; S9. Concrete pouring.
2. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S1, when the wall column reinforcement is tied, the shear wall horizontal reinforcement and the hidden column stirrups need to be tied to the lower opening of the steel structure embedded parts to provide construction conditions for the installation of the steel structure embedded parts. When installing the steel column, the steel column needs to be deepened in sections, and the length of a single steel column is 1-2 floors high. The steel column is hoisted from the outside to the inside in a clockwise direction, and the single piece initial calibration and closed fine calibration are carried out in turn to eliminate the cumulative error, and then the overall fine calibration of the inter-section is carried out. At the same time, the lantern frame is installed in coordination, using a buckle frame with a multi-row design, with an I-beam on the top and a base underneath, and is set at the separation ports of all structural systems, including steel outer frame column-beam separation and beam-beam separation. After the lantern frame is erected, formwork frames are set up between the steel beams.
3. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S2, the mechanical and electrical pre-embedded work of the shear wall needs to be started in advance and embedded in sequence. First, use a level to draw a horizontal line, then use a total station to lay out the axis, and determine the embedded position by the cross intersection of the two lines. Synchronously install the outer ring main beam, and weld the nodes and connect with high-strength bolts. Then, perform flaw detection and repainting on the outer ring main beam, and during this period, the wall column formwork preparation work can be carried out simultaneously.
4. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S3, in order to improve the efficiency of steel beam installation, the connection between the steel beam and the core tube, as well as the docking between the embedded parts and the steel beam are mainly considered. First, install the steel beam in place, connect one side to the steel column or main steel beam, and place the other side on the lantern frame, and then connect the embedded parts to the steel beam. The key to improving efficiency is to tie the steel bars to the bottom of the steel beam so that the embedded parts are not disturbed when placed. After the embedded parts are installed, the upper steel bars are tied, and then unified adjustments are made later. In the core tube, the wall column formwork is supported, and the beam and slab formwork is prepared in coordination.
5. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S4, the core tube part needs to coordinate the support and reinforcement of the wall column formwork, as well as the laying of the beam and slab formwork. At the same time, the operating frame in the shaft should be followed up in advance to ensure the convenience of subsequent operations and construction safety. In the steel outer frame part, the welding position of the radial beam needs to be repainted and inspected first, and the steel bar binding of the outer frame steel column is coordinated, and then the hoisting and correction of the annular steel beam is carried out.
6. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S5, the core tube part needs to simultaneously carry out the reinforcement of the wall column formwork and its acceptance adjustment, as well as the beam and slab reinforcement binding. It should be noted that the reinforcement of the wall column formwork must be completed before the corrugated steel sheet of the steel outer frame is laid. In the steel frame part, the bolt connection and welding of the circumferential steel beam connection need to be coordinated, and the angle steel at the junction of the steel column and the steel beam needs to be welded, and then the outer frame steel column formwork is supported and reinforced.
7. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S6, the core tube part cooperates with the slab surface reinforcement binding and pre-embedded mechanical and electrical pipelines, etc. In the steel frame part, the angle steel near the core tube position needs to be installed, welded, inspected and repainted, and then the corrugated steel plate is laid in two shifts day and night.
8. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S7, the core tube part needs to continue with the slab surface reinforcement binding and pre-embedded mechanical and electrical pipelines. In the steel frame part, the corrugated steel sheet is closed and bolted. After the corrugated steel sheet is installed, the operating frame is converted into a support frame, and the corrugated steel sheet close to the core tube is supported by the top support and inner support wooden beams. At the same time, the outer frame steel column formwork is supported and reinforced.
9. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In the step S8, the openings such as the pump pipe hole and the wiring hole are cut on site, and wooden templates are made and sealed. The reserved position of the pipe well is positioned in advance, and the buried casing part that can be in place at one time is buried in place at one time. It should be noted that the steel bar binding, water and electricity installation and curtain wall embedded parts installation must be interspersed. After a part of the floor decking is installed, start to drive bolts, lay steel bars, and start water and electricity installation. For the flanging parts that need to be formed in one time, on the one hand, it is necessary to intervene in advance, and on the other hand, consider reserving a certain amount of time in the overall construction schedule. For the anti-slopes that need secondary pouring or reserved uncast parts, they will be poured with the masonry construction in the masonry construction stage.
10. The standardized construction technology for the same-layer structure of the equal-height climbing system according to claim 1 is characterized in that: In step S9, concrete is poured for the entire structure. A car pump can be used for pouring concrete on the 1st to 5th floors, and a concrete placing machine can be used for pouring concrete above the 5th floor. Considering that the synchronous climbing technology is particularly suitable for high-rise buildings, such high-rise buildings are generally used as shopping malls and office buildings. Therefore, concrete pouring should start early in the morning. Consider setting up two pump pipes for the floor pump pipes, and pouring starts from the core tube. When the concrete strength of the core tube reaches more than 95%, the lantern frame can be removed.