Crane with a luffable boom
The crane's transfer device simplifies the connection of luffing cables by using a movable frame and coupling mechanism, addressing the challenges of relative movements and complex structures in offshore wind turbine maintenance, allowing for efficient and reliable operations in floating conditions.
Patent Information
- Application Number
- PCT/EP2024/064253
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-05-26
- Filing Date
- 2024-05-23
- Publication Date
- 2024-12-05
AI Technical Summary
Current cranes used for maintaining offshore wind turbines, especially those with floating foundations, face challenges in connecting luffing cables due to relative movements between the crane base and boom, limiting maintenance operations to calm seas and low wind speeds, and requiring complex structures or additional cranes, which are impractical in floating conditions.
A crane with a transfer device comprising a movable frame connected to the slewing unit or boom, a coupling device to engage the luffing sheave block, and a transfer drive assembly to move the frame and couple the sheave block with the luffing stay, allowing for efficient and reliable luffing motion of the boom without the need for additional cranes or complex structures.
The solution significantly reduces the effort, time, and complexity of connecting luffing cables, enabling reliable maintenance operations on floating wind turbines in varying sea conditions, extending the operational window for maintenance and reducing costs by eliminating the need for towing turbines to shore.
Smart Images

Figure EP2024064253_05122024_PF_FP_ABST
Abstract
Description
[0001] CRANE WITH A LUFFABLE BOOM
[0002] The present invention relates to a crane comprising a base, a slewing unit mounted on the base, and a luffable boom connected to the slewing unit. The slewing unit comprises a luffing winch driving a luffing cable to which a luffing sheave block is connected. The boom comprises a luffing stay connected to a distal portion of the boom.
[0003] In the field of offshore wind generally two categories exist, namely fixed foundation wind turbines and floating foundation turbines. Fixed foundation wind turbines have a foundation that is secured to the seabed, e.g. a monopile or a jacket, so that water depth forms a limitation of the applicability thereof. Therefore, in particular for deeper water, floating foundations are better suited. It is projected that in the future the majority of offshore generation of electrical energy will be done by floating foundation type wind turbines.
[0004] For maintenance, e.g. involving removing, installing, or replacing a wind turbine component of the fixed offshore wind turbines, it is known to use a vessel mounted crane having a sufficient reach. Often, the vessel is a jack-up vessel to provide stability of the crane during maintenance operation. It is also known to use a vessel in floating conditions for such operations. Typically, these vessels have a large hull, e.g. embodied as a semi-submersible crane vessel, to provide a sufficiently stable platform for the maintenance operation to be carried out. Even with these large vessels, the relative movement between the top of the boom of the crane and the nacelle of the wind turbine is such that maintenance can only be done with calm seas and low wind speeds. Thus the operational windows for performing maintenance is limited.
[0005] Performing such maintenance operations at sea for a floating wind turbine cannot involve the use of a stable jack-up vessel as water depth make the use thereof impossible or impractical. These problems increase by continued increase of the dimensions of the offshore wind turbines. Currently, an effective solution is towing the entire floating wind turbine back to shore to perform maintenance operations, like replacement of one or more blades of the gearbox, and / or of the generator.
[0006] By introducing solutions to perform maintenance operations on the floating foundation in floating conditions at the site of the offshore windfarm a cost efficient approach is found. The approach is, for example, suitable for floating foundations comprising multiple buoyant stabilising columns with one of the columns supporting a tower of the wind turbine, e.g. three or four of such columns. An example of such a floating foundation is disclosed in WO2016 / 205746 and has three buoyant stabilizing columns with one of the columns supporting the tower of the wind turbine. In the field, there are also mono buoyant body floating foundations. For example, a spar type foundation has a single buoyant stabilizing column on which the wind turbine tower is mounted. Other known designs have a circular or rectangular ring shaped floating body, whereon the tower of the wind turbine is erected, e.g. at the centre or at the side, typically at a corner, of the floating mono-body. The present invention is primarily aimed at wind turbines of the floating foundation comprising multiple buoyant stabilizing columns type.
[0007] In W02023 / 041730A1 a system for performing maintenance operations on a floating foundation in floating conditions, e.g. at the site of an offshore windfarm, by use of a transferable crane is disclosed. The crane comprises a revolving superstructure, a boom, a hoisting winch and hoisting cable to lift and / or lower a wind turbine component, e.g. wind turbine blade.
[0008] During the operation of hoisting the transferable crane from a vessel to a floating foundation, the crane base and crane boom are hoisted onto the floating foundation as two separate parts. Once both parts are stationed on the floating foundation this introduces a problem of connecting the luffing cables between the base and the boom, which is required for enabling luffing motion of the boom and perform maintenance operations on the wind turbine.
[0009] Another known approach is using a separate crane for hoisting of one portion of the luffing cables to another portion of the luffing cables, for example a portion of the luffing cables positioned on the base to a portion of the luffing cables on the boom. The separate crane can for example be positioned on the vessel which is also used for hoisting of the crane and boom onto the floating foundation. However, on sea this is not a viable approach as different dynamics between the floating foundation and the vessel yield relative movements between the two.
[0010] The present invention aims to provide a crane which overcomes, or at least reduces one of the above mentioned problems.
[0011] The present invention provides a crane according to claim 1.
[0012] The crane is provided with a transfer device comprising: - a movable frame of which a part is connected to either the slewing unit or to the boom, preferably hinged to the boom,
[0013] - a coupling device on the movable frame and configured to engage the luffing sheave block,
[0014] - a transfer drive assembly which is configured to move the movable frame.
[0015] The transfer device is configured to engage the luffing sheave block in a resting position thereof, wherein the luffing sheave block is supported by the slewing unit, e.g. by the support structure thereof, and to then move the movable frame by means of the transfer drive assembly so as to transfer the luffing sheave block to a position at the inner end of the luffing stay, wherein the coupling device is configured to enable coupling of the luffing sheave block and the inner end of the luffing stay to one another in order to allow for luffing motion of the boom, and wherein the coupling device is configured to uncouple the transfer device from the interconnected luffing sheave block and the inner end of the luffing stay prior to luffing of the boom by means of the luffing winch.
[0016] Due to the presence of the transfer device, the process of connecting the luffing sheave block to the inner end of the luffing stay can be significantly improved in terms of effort, time involved, and reliability of the handling of the luffing sheave block.
[0017] The crane is, preferably, a transferable crane, i.e. is configured to be temporarily mounted on the floating foundation of a wind turbine. In such embodiment, the invention allows to construct the transferable crane on, for example, a floating foundation and omits the need of a complex structure which aids the coupling procedure of different luffing crane parts, or omits the need for another crane for hoisting of one cable portion to another.
[0018] The slewing unit allows rotation around a vertical axis by means of, for example, bearing means, e.g. a slew bearing.
[0019] The transfer device comprises a movable frame. A part of the movable frame is connected to either the slewing unit or the boom. By having the movable frame attached to one of these components, the difference between moving dynamics of said parts is minimized, which is beneficial during the coupling procedure. The movable frame is able to reach the luffing sheave block in the resting position thereof and the inner end of the luffing stay.
[0020] In an embodiment, the movable frame is hingeable. Other examples of means of movement for the movable frame are a slideable frame, rolling frame, or telescopic frame. In an embodiment, the movable frame is hingeable along an axis parallel to a luffing hinge axis of the boom. Preferably, the movable frame is hinged to the boom.
[0021] In an embodiment, the movable frame comprises an elongated shape, for example a slender rectangular shape. This keeps the structure of the movable frame relatively light in weight while providing sufficient stiffness.
[0022] The transfer device comprises a coupling device to carry out coupling of the luffing sheave block to the inner end of the luffing stay. Preferably, the coupling device comprises a coupling drive. The coupling device comprises, for example, a hook coupling mechanism or a quick link type of connector or a latch type of connector. The coupling drive is, for example, configured to form a connection between the luffing sheave block and the inner end of the luffing stay.
[0023] The coupling device is configured to engage the luffing sheave block and assists the transfer device to transfer the luffing sheave block between the resting position supported by the slewing unit and the inner end of the luffing stay.
[0024] The coupling device is configured to uncouple the transfer device from the interconnected luffing sheave block and the inner end of the luffing stay prior to luffing of the boom by means of the luffing winch. The coupling device disengages from the luffing sheave block and remains connected to the transfer device.
[0025] The transfer device comprises a transfer drive assembly to move the movable frame. In embodiments, the transfer drive assembly comprises one or more tugger lines and one or more tugger line winches configured to move the movable frame.
[0026] For example, the one or more tugger line winches are connected to the base and the tugger lines are guided by rollers, wherein rollers are attached to the base and wherein rollers are attached to the boom. Another example of a transfer drive assembly is, for example, a torque supplier.
[0027] In an embodiment, a first tugger line winch is mounted on the slewing unit and a first tugger line extends via a roller on the slewing unit, e.g. on the support structure, to the movable frame, and wherein a second tugger line winch is mounted on the slewing unit or on the boom, wherein a second tugger line extends from the movable frame via a roller mounted on the boom to the second tugger line winch.
[0028] By activation of the one or more tugger line winches the movable frame is transferred due to the movement of said tugger lines.
[0029] In an embodiment, the tugger lines are guided by rollers attached to the slewing unit and boom. Guide rollers serve as guides to the tugger lines and allow the tugger lines to follow a certain path.
[0030] In an embodiment, the boom is a telescopically extensible boom. This allows the boom to be relatively compact, as compared to a non-telescopic boom, during transportation on, for example a vessel, while also being able to have sufficient reach to lift wind turbine components to heights suitable for maintenance purposes. For example, the boom is first brought into a raised orientation and then the boom is extended telescopically.
[0031] In an embodiment, the boom further comprises a jib. The crane jib allows for lifting loads over a greater distance and height compared to a single boom structure, which is beneficial to the lifting conditions on a floating foundation. The length of the telescopic boom plus jib having a working radius of preferably over 100 meters in length.
[0032] In an embodiment, the crane is configured such that the luffing motion of the boom, luffing motion of the jib, and telescopic movement of the boom can be altered individually. This provides the crane with a greater freedom of movement.
[0033] In an embodiment, after use of the crane, the transfer device, in particular the coupling device, is used to detach the connection between the luffing sheave block and inner end of the luffing stay in order to separate the base and the boom. This enables a crane vessel to lift the base and boom as separate portions back onto the vessel.
[0034] The present invention also relates to a floating foundation comprising the crane according to the invention, e.g. with an offshore wind turbine thereon.
[0035] The present invention also relates to a method for coupling of the luffing sheave and luffing stay, wherein the steps are followed:
[0036] - connecting the transfer device to the luffing sheave block; - transferring the luffing sheave block from a resting position supported by the slewing unit to the inner end of the luffing stay by means of the movable frame of the transfer device;
[0037] - coupling of the luffing sheave block and the inner end of the luffing stay by means of the coupling device.
[0038] The present invention also relates to a method for installation and / or removal of a wind turbine component of a wind turbine having a tower that is erected on a floating foundation which is in a floating condition, e.g. at the site of an offshore windfarm, wherein use is made of the crane according to the invention, wherein the base and boom are initially provided as separate parts, and wherein arranging of the crane onto the floating foundation comprising the steps of:
[0039] - arranging the base with the slewing unit on the floating foundation;
[0040] - mounting the boom to the slewing unit already arranged on the floating foundation;
[0041] - moving of the transfer device to the luffing sheave block ;
[0042] - connecting the transfer device to the luffing sheave block by means of the coupling device;
[0043] - transferring the luffing sheave from a resting position supported by the slewing unit to the inner end of the luffing stay by means of the movable frame;
[0044] - coupling of the luffing sheave block to the inner end of the luffing stay;
[0045] - uncoupling of the transfer device and transferring the transfer device to a resting position;
[0046] - luffing the boom by means of the luffing winch.
[0047] The invention will now be described with reference to the drawings. In the drawings:
[0048] Fig. 1 schematically depicts a floating foundation comprising a crane;
[0049] Fig. 2 schematically depicts a boom and transfer device;
[0050] Fig. 3 schematically depicts a base, boom and transfer device;
[0051] Fig. 4 shows a part of figure 3;
[0052] Figs. 5.1-5.5 depicts the steps performed during the operation of the transfer device.
[0053] In Fig. 1 an exemplary embodiment of a transferable crane 9 according to the invention is shown.
[0054] The crane 9 is preferably a transferable crane, i.e. is configured to be temporarily mounted on the floating foundation 1 of a wind turbine 2.
[0055] In the figure 1 the inventive transfer device has already been used to couple the luffing sheave block 18 to the inner end 12a of the luffing stay to enable the luffing motion of the telescopic boom 4 by means of the luffing cable 14 which now is connected to the luffing stay 12.
[0056] In the figures components of the crane 9 are visible:
[0057] - a base 3;
[0058] - a slewing unit 6 mounted on the base 3, which unit has a support structure 7 as well as a luffing winch 15 and a luffing cable 14 with a luffing sheave block 18 connected to the luffing cable 14,
[0059] - a boom 4, which is hingeably connected to the slewing unit 6 and is configured to carry out a luffing motion, which boom comprises a luffing stay 12 having an inner end 12a and an outer end 12b, which outer end is connected to a distal portion of the boom 4, here of the stationary part of the telescopic boom 4,
[0060] - a transfer device 16 having a movable frame 5 and configured to transfer the luffing sheave block 18 from an initial or resting position on the slewing unit 6 to the inner end 12a of the luffing stay 12, and a coupling device 17 configured to engage the luffing sheave block 18 and to couple the luffing sheave block 18 and the inner end 12a of the luffing stay 12 as to form a connection between the luffing winch 15 and luffing stay 12 to enable luffing motion of the boom 4.
[0061] The support structure 7 here is embodied as a so-called A-frame.
[0062] The resting position of the block 18 may comprise a block resting member 7b on the support structure, e.g. as part of a boom stop 7c.
[0063] In the shown embodiment, the movable frame 5 is attached to the boom 4.
[0064] Fig. 2 shows the boom 4 with the movable frame 5. Mounted on the boom is a strut 10 having a first member 11a and a second member 11 b to enable motion of an end portion of the boom, for example luffing motion of a jib.
[0065] Fig. 3 shows the base 3, the boom 4, and the transfer device. Here the base 3 is shown with a slewing unit 6 having an exemplary support structure 7. In this exemplary embodiment the luffing cable 14 is guided around a part, for example a sheave 7a, of the support structure 7 and is a luffing sheave block 18 present at an end portion of the luffing cable. The transfer device 16 with its movable frame 5 and coupling device 17 is visible. In the shown embodiment the movable frame 5 is hingeable around a transfer device hinge axis 19 relative to the boom 4.
[0066] In the shown embodiment, the movable frame 5 is hingeable about the axis 19 in a direction substantially parallel to that of the boom 4, which is hingeable about axis 4a relative to the slewing unit.
[0067] The path of the coupling device 17 on the outer end of the movable frame 5 is indicated by the frame path 13, which is in a plane substantially parallel to that of the boom 4.
[0068] In the shown embodiment the movable frame 5 comprises an elongated shape, for example a slender rectangular shape.
[0069] In Fig. 4 an embodiment of the transfer device 16 comprising one or more tugger lines 20 and tugger line winches 22 configured to move the movable frame 5 is shown.
[0070] In the exemplary embodiment shown the tugger line winches 22 are connected to the slewing unit 6 of the base 3.
[0071] In the exemplary embodiment shown the tugger lines 20 are guided by rollers 21 attached to the slewing unit 6 and boom 4.
[0072] In more detail, a first tugger line winch 22 is mounted on the slewing unit and a first tugger line 20 extends via a roller 21 on the slewing unit, here on the support structure 7 to the movable frame, and a second tugger line winch 22 is mounted on the slewing unit or on the boom, and wherein a second tugger line 20 extends from the movable frame 5 via a roller 21 mounted on the boom 4 to the second tugger line winch 20. This allows the pivotal frame 5 to be moved between a position wherein the coupling device 17 can engage on the block 18 in the resting position thereof on the slewing unit 6 and to then move the block 18 to the inner end 12a of the stay 12 which rests on the boom 4. Then the coupling between the block 18 and the inner end 12a is effected, e.g. automatically. After this, the device 16 is disengaged from the block 18, e.g. the frame 5 being placed in a resting position thereof on the boom. Subsequently, the luffing winch 15 is operated to tension the luffing arrangement and then cause the luffing motion of the boom 4.
[0073] The boom 4 is a telescopically extensible boom. In another embodiment, not shown in the figures, the boom further comprises a jib.
[0074] In another embodiment the crane is configured such that the luffing motion of the boom, luffing motion of the jib, and telescopic movement of the boom can be altered individually.
[0075] After use of the crane 9 the transfer device 16, preferably the coupling device 17, is used to detach said connection of the luffing sheave block 18 and inner end of the luffing stay 12 in order to separate the base 3 and the boom 4.
[0076] In the figures 5.1-5.5 a method for coupling of the luffing sheave block 18 and luffing stay on the crane, wherein the steps are followed:
[0077] - connecting the coupling device 17 to the luffing sheave block 18;
[0078] - transferring the luffing sheave block 18 from the initial position on the slewing unit 6 to the inner end of the luffing stay 12 with the movable frame 5 of the transfer device 16;
[0079] - coupling of the luffing sheave block 18 and to the inner end of the luffing stay 12a by the coupling device 17.
[0080] The floating foundation is not shown in figures 5.1-5.5.
[0081] In Fig. 5.1 the transfer device 16, in particular the frame 5 thereof, is shown in a resting position on the boom 4 after the base 3 with the slewing unit 6 and boom 4 have been placed on the floating foundation 1. The transfer device has the movable frame 5 and coupling device 17.
[0082] In Fig. 5.2 the outer end of the movable frame 5 of the transfer device 16 is moved to the luffing sheave block 18 and the coupling device 17 is coupled to the luffing sheave block 18 which is connected to the luffing cable portion 14. The movable frame path 13 is indicated in the figure. In this exemplary embodiment the movable frame 5 of the transfer device 16 hinges around the transfer device hinge 19.
[0083] Fig. 5.3 shows the movable frame 5 during the process of transferring the luffing sheave block 18 from the initial or resting position on the slewing unit to the inner end 12a of the luffing stay 12 which lies on the boom 4, the boom 4 being substantially horizontal. A transfer drive assembly, here with tugger lines 20 and tugger line winches 22 is used to cause the movement of the transfer device 16. In Fig. 5.4 the movable frame 5 is moved to the inner end of the luffing stay 12, and the coupling device 17 is used for the coupling process between the luffing sheave block 18 and the inner end of the luffing stay 12. During the movement of the transfer device and the luffing sheave block, the luffing cable 14 is now let out by the winch 15.
[0084] Fig. 5.5 shows the luffing sheave block 18 connected to the inner end 12a of the luffing stay. In the embodiment shown, the luffing winch 15 has partially let out the luffing cable 14 as to partially raise the luffing stay 12. The transfer device 16 and movable frame 5 are put into a resting position on the boom 4.
[0085] So, in general, the transfer device 16 is configured and operated to engage the luffing sheave block 18 in a resting position thereof, wherein the luffing sheave block is supported by the slewing unit, e.g. by the support structure 7 thereof, and to then move the movable frame 5 by means of the transfer drive assembly 20,22 so as to transfer the luffing sheave block 18 to a position at the inner end 12a of the luffing stay 12, wherein the coupling device 17 is configured to enable coupling of the luffing sheave block 18 and the inner end 12a of the luffing stay to one another in order to allow for luffing motion of the boom 4, and wherein the coupling device 17 is configured to uncouple the transfer device 16 from the interconnected luffing sheave block 18 and the inner end 12a of the luffing stay prior to luffing of the boom by means of the luffing winch 15.
[0086] After the above procedure has been completed the crane is able to perform luffing motion of the boom 4 by means of the winch 15. For example, the maintenance operations on the wind turbine 2 on a floating foundation 1 are performed using the crane 9.
Claims
C L A I M S1. Crane (9) comprising:- a base (3),- a slewing unit (6) mounted on the base, the slewing unit comprising a support structure (7) and a luffing winch (15), wherein a luffing cable (14) is guided by a sheave (7a) of the support structure, and wherein a luffing sheave block (18) is connected to the luffing cable,- a boom (4), which is hingeably connected to the slewing unit 96) and is configured to carry out a luffing motion, wherein the boom comprises a luffing stay (12) having an inner end (12a) and an outer end (12b), which outer end is connected to a distal portion of the boom, characterized in that the crane is further provided with a transfer device (16) comprising:- a movable frame (5) of which a part is connected to either the slewing unit (6) or to the boom (4),- a coupling device (17) on the movable frame (5) and configured to engage the luffing sheave block (18),- a transfer drive assembly (20, 22) which is configured to move the movable frame (5), wherein the transfer device is configured to engage the luffing sheave block (18) in a resting position thereof, wherein the luffing sheave block is supported by the slewing unit, e.g. by the support structure (7) thereof, and to then move the movable frame (5) by means of the transfer drive assembly (20,22) so as to transfer the luffing sheave block (18) to a position at the inner end (12a) of the luffing stay (12), wherein the coupling device (17) is configured to enable coupling of the luffing sheave block (18) and the inner end (12a) of the luffing stay to one another in order to allow for luffing motion of the boom (4), and wherein the coupling device (17) is configured to uncouple the transfer device (16) from the interconnected luffing sheave block (18) and the inner end (12a) of the luffing stay prior to luffing of the boom by means of the luffing winch (15).
2. Crane according to claim 1 , wherein the movable frame (5) is hingeable, e.g. hingeable mounted to the boom (4), e.g. hingeable along an axis (19) which is parallel to a luffing hinge axis (4a) of the boom (4).
3. Crane according to claim 1 or 2, wherein the movable frame (5) has an elongated shape, for example a slender rectangular shape.
4. Crane according to any one or more of the preceding claims, wherein the coupling device (17) comprises a coupling drive.
5. Crane according to any one or more of the preceding claims, wherein the coupling device (17) is configured to remain connected to the movable frame (5) after coupling of the luffing sheave block (18) to the inner end (12a) of the luffing stay.
6. Crane according to any one or more of the preceding claims, wherein the transfer drive assembly comprises tugger line winches (22) and one or more tugger lines (20) connected to the movable frame (5).
7. Crane according to claim 6, wherein a first tugger line winch (22) is mounted on the slewing unit and a first tugger line (20) extends via a roller (21) on the slewing unit, e.g. on the support structure (7) to the movable frame, and wherein a second tugger line winch (22) is mounted on the slewing unit or on the boom, and wherein a second tugger line (20) extends from the movable frame (5) via a roller (21) mounted on the boom (4) to the second tugger line winch (20).
8. Crane according to any one or more of the preceding claims, wherein the boom (4) is a telescopically extensible boom.
9. A floating foundation comprising the crane (9) according to any one or more of the preceding claims, e.g. with an offshore wind turbine (2) thereon.
10. Method for coupling of the luffing sheave block (18) and the inner end (12a) of the luffing stay of a crane (9) according to any one or more of the preceding claims, comprising the steps of:- connecting the coupling device (17) of the transfer device (16) to the luffing sheave block (18), while said luffing sheave block is in a resting position supported by the slewing unit (6);- transferring the luffing sheave block (18) from the resting position supported by the slewing unit (6) to the inner end (12a) of the luffing stay by means of the movable frame (5) of the transfer device (16), wherein transferring of the luffing sheave block is driven by the transfer drive assembly of the transfer device (16);- coupling of the luffing sheave block (18) and the inner end (12a) of the luffing stay (12).
11. Method for installation and / or removal of a wind turbine component, of a wind turbine having a tower that is erected on a floating foundation which is in a floating condition, e.g. atthe site of an offshore windfarm, wherein use is made of the crane (9) according to any one or more of the preceding claims, wherein the base (3, 6, 7) and boom (4) are initially provided as separate parts, and wherein arranging of the crane (9) onto the floating foundation comprising the steps of: - arranging the base (3) with the slewing unit (6) on the floating foundation (1);- mounting the boom (4) to the slewing unit (6) already arranged on the floating foundation (1);- moving of the transfer device (16) to engage the luffing sheave block (18) in a resting position on the slewing unit (6); - connecting the transfer device (16) to the luffing sheave block (18) with the coupling device(17);- transferring the luffing sheave block (18) from the resting position supported by the slewing unit to the inner end (12a) of the luffing stay by means of the movable frame (5);- coupling of the luffing sheave block (18) to the inner end (12a) of the luffing stay by means of the coupling device (17);- uncoupling of the transfer device (16) and transferring the transfer device to a resting position;- luffing the boom (4) by means of the luffing winch (15).
Citation Information
Patent Citations
Floating wind turbine platform structure with optimized transfer of wave and wind loads
WO2016205746A1
Installation and / or removal of a wind turbine component for a floating foundation wind turbine
WO2023041730A1
Crane comprising counterjib, and method for erecting the counterjib
US20230051341A1
Arrangement of a crane on a floating wind power station
WO2023031360A1