Arrangement for managing power consumption of an electrical mining or construction machine
By time-shifting peak power demands, the controller optimizes work cycles to prevent power grid overload, ensuring continuous and efficient mining operations.
Patent Information
- Application Number
- PCT/SE2025/050446
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2025-05-09
- Publication Date
- 2026-11-12
AI Technical Summary
Existing power management systems for electrical mining and construction machines struggle to prevent power grid overload during simultaneous operations, leading to costly shutdowns and inefficiencies.
A controller adjusts the planned work cycles of electrical machines to time-shift peak power demands, ensuring they do not exceed the power grid's capacity by delaying or advancing power consumption.
This approach prevents power grid overload by optimizing power consumption, ensuring continuous and efficient mining operations without exceeding the grid's capacity.
Smart Images

Figure SE2025050446_12112026_PF_FP_ABST
Abstract
Description
[0001] ARRANGEMENT FOR MANAGING POWER CONSUMPTION OF AN ELECTRICAL MINING OR CONSTRUCTION MACHINE
[0002] Technical field
[0003] The present disclosure relates to electrical power consumption management at mining sites. In particular, it relates to an arrangement and a method for managing power consumption of at least one electrical mining or construction machine. It further relates to an electrical mining or construction machine, a computer program, and a non-transitory computer-readable storage medium.
[0004] Background
[0005] Mining and / or construction machines, such as face drill rigs, production drill rigs, loaders, haulers, dumpers, rock bolting rigs, cable bolting rigs, and concrete spraying machines, are used in various stages of mining operations. In a strive to reduce greenhouse gas emissions and improve working conditions underground by eliminating harmful exhaust gases, the mining industry has initiated a shift from traditional fossil-fuel powered working machines to electrically powered working machines. The working machines may therefore be connected to a power grid, such as a local power grid of the mine, that provides electrical power to the working machines. Some or all working machines may comprise on-board rechargeable batteries, but it is typically desirable to use grid power whenever possible to reduce downtime and improve energy efficiency of the working machines, in particular for power demanding tasks.
[0006] Power grids in mines are often operating at or near their capacity limits, making it challenging to meet the power demands of multiple, simultaneous mining operations. Mining work cycles may typically involve intermittent power needs, where a combined peak power demand from multiple electrical mining machines operating simultaneously can overload the power grid, leading to costly shutdowns or power failures.Existing solutions that attempt to predict and control power consumption by gathering information from many machines are complex and inefficient. Hence, there is a need for improved arrangements and methods to manage the combined peak power demand of multiple electrical working machines at a mining site, ensuring safe and continuous mining operations without exceeding the power grid's capacity.
[0007] Summary
[0008] In view of above-mentioned and other drawbacks of the prior art, it is a primary object of the present disclosure to provide in at least some aspect improved arrangements and methods for managing power consumption of one or more electrical mining and / or construction machine connected to a power grid. In particular, it is an object to provide such arrangements and methods that reduce the risk of violating a capacity of the power grid during mining operations involving several mining and / or construction machines powered by the power grid, without compromising mining efficiency.
[0009] According to a first aspect of the disclosure, at least the primary object is achieved by an arrangement as proposed and claimed herein. The arrangement is configured for managing power consumption of at least a first electrical working machine within a set of electrical working machines in the form of electrical mining and / or construction machines connected to a power grid. It comprises a controller configured to obtain information relating to a planned work cycle of at least the first electrical working machine over a time period. The controller is further configured to detect that an upper power limitation of the power grid is or will be violated during the time period. In response to said detection, the controller is configured to adjust the planned work cycle of at least the first electrical working machine to an adjusted work cycle in which at least one first peak power demand of the first electrical working machine is time shifted in comparison with the planned work cycle.
[0010] By adjusting the planned work cycle of the first electrical working machine such that the first peak power demand is time shifted, it is possible to advance or delay a power consumption peak of the first electrical working machine such that an overload of the power grid can be avoided.The first peak power demand is the maximum power that the first electrical working machine will demand during the time period, i.e. in connection with performing the planned work cycle. More than one such peak power demands may occur during a work cycle, e.g., as a result of repeatedly performing a power demanding task. When the at least one first peak power demand comprises several peak power demands, at least one of those, or each one, may be time shifted.
[0011] The expression “time shifted” is to be understood as “shifted to a different point in time”, i.e., either delayed or advanced. Hence, the first peak power demand of the adjusted work cycle is delayed or advanced in time in comparison with the first peak power demand of the planned work cycle. The time shifting may be achieved by initiating a planned task associated with the first peak power demand at an earlier or later point in time, thereby advancing or delaying the first power peak demand, respectively. The time shifting may additionally be achieved by performing the planned task faster or slower such that the first peak power demand occurs earlier or later, respectively. The time shifting may hence either be performed such that the task associated with the first peak power demand takes the same amount of time to complete, but is performed at an earlier or later point in time, or such that, the task associated with the first peak power demand is initiated at an earlier or later point in time, and in addition takes a shorter or longer time to complete.
[0012] The first electrical working machine, as well as the other working machines within the set of working machines, may be any kind of electrical mining machine or construction machine. Such electrical working machines may include production, exploration, and construction mining rigs for surface applications, for example face drill rigs, production drill rigs, rock bolting rigs, and cable bolting rigs. Such electrical working machines may also include, but are not limited to, loaders, haulers, dumpers, scrapers, excavators, crushers, and concrete spraying machines used in mining and / or construction sites. The working machines within the set may be of the same type, or of different types.The power grid may be a common power grid from which the set of electrical working machines is configured to receive electric power for performing operations according to work cycles. Each electrical working machine within the set of electrical working machines may hence be electrically connected to the same power grid.
[0013] The information relating to the planned work cycle of a working machine may comprise information relating to tasks that the electrical working machine is to perform during the work cycle, and that may be used to predict an electric power consumption of the working machine during the work cycle and to determine, at least, its at least one peak power demand and the time at which the peak power demand will occur. The information may be received from a mine operation planner. For example, the work cycle can be defined by an excavation plan in at least one mining area. The excavation plan can for instance be, but is not limited to, a drilling plan, a charging plan, or a mining plan. The drilling plan may, e.g., define when and where to drill. Based on the information therein and on characteristics of the working machine, the controller of the arrangement for managing power consumption may predict the power consumption as a function of time for the planned work cycle. The characteristics of the working machine may include, but are not limited to, machine rating, peak power, power consumption in different operational modes such as drill, idle, rod change, etc., power factor, and inrush current.
[0014] The time period may be a future time period of a predetermined duration, such as a prediction or planning time horizon during which the upper power limitation and / or the power demand of the electrical working machines can be predicted. The time period may have a duration corresponding to a drill cycle or similar, typically a few minutes, although it may be longer or shorter. Typically, the work cycle may have a duration ranging from one minute to about an hour, and the work cycle may be repeated during a shift lasting several hours. The time period may be an immediately upcoming time period or a time period starting after an initial delay.
[0015] The proposed arrangement may be implemented in various ways. For example, the controller may be comprised in the first electrical working machine or in an off-board central control unit. In both cases, the arrangement may be centralized, in whichcase the controller may be configured to receive data from several working machines within the set, and to determine and provide adjusted work cycles to at least some of the working machines within the set. The arrangement may further be decentralized, or distributed, wherein each electrical working machine within the set comprises its own controller.
[0016] According to some embodiments, the controller is configured to adjust the planned work cycle in response to detecting that the upper power limitation is or will be violated at the time of the first peak power demand. Hence, it can be ensured that the first power peak demand is time shifted when this will contribute to complying with the upper power limitation.
[0017] According to some embodiments, the controller is configured to adjust the planned work cycle such that a total power demand of the set of electrical working machines does not exceed the upper power limitation at any point in time during the time period, such as at a point in time of a total peak power demand. The total peak power demand is the maximum power that the set of electrical working machines will demand during the time period. By way of example, ensuring that the total power demand does not exceed the upper power limitation at any point in time may be achieved by adjusting the planned work cycle such that, in the adjusted work cycle, the first peak power demand does not coincide in time with the peak power demand of any of the other electrical working machines within the set. Depending on the upper power limitation and on the power consumption associated with the planned work cycles, the controller may be configured to adjust the planned work cycles of several electrical working machines to ensure that the upper power limitation is not violated.
[0018] According to some embodiments, the information relating to the planned work cycle comprises information relating to the planned work cycles of all electrical working machines within the set of electrical working machines over the time period, wherein the controller is further configured to determine a combined power profile describing a total power demand of the set of electrical working machines as a function of time over the time period based on at least the obtained information relating to theplanned work cycles. The information relating to the planned work cycles of all working machines within the set enables an accurate prediction of the total power demand, including the total peak power demand. Thereby, it can be ensured that a relevant adjustment of the planned work cycle is made to ensure compliance with the upper power limitation. As used herein, the term “power profile” is to be understood as a power consumption profile.
[0019] According to some embodiments, the controller is configured to determine a set of predicted power profiles for the set of electrical working machines during the time period based on at least the obtained information relating to the planned work cycles, each power profile being associated with one of the electrical working machines and comprising at least a peak power demand and a time stamp indicating a point in time at which the peak power demand is predicted, wherein the combined power profile is determined based on the set of predicted power profiles. The time stamped peak power demands of each working machine allows an accurate prediction of any time intervals or points in time during the time period at which the upper power limitation is likely to be exceeded.
[0020] According to some embodiments, the first peak power demand is associated with a first task performed by the first electrical working machine, and the controller is further configured to adjust the planned work cycle by adjusting a maximum amount of power allocated to the first task. By adjusting the maximum amount of power allocated to the first task, the first task may take more or less time to complete, thereby enabling a further time shifting of the first peak power demand.
[0021] According to some embodiments, the controller is configured to adjust the planned work cycle of the first electrical working machine such that the first task is completed faster with the adjusted work cycle in comparison with the planned work cycle. This may be achieved by enabling a power boost of the first electrical working machine, thereby advancing the first peak power demand in time. The power boost may preferably be combined with advancing the initiation of the first task.According to some embodiments, the controller is configured to adjust the planned work cycle such that first task is completed slower with the adjusted work cycle in comparison with the planned work cycle. This may be achieved by enabling derating the first electrical working machine, thereby delaying the first peak power demand in time. The derating may preferably be combined with delaying the initiation of the first task.
[0022] According to some embodiments, the information relating to the planned work cycle further comprises information relating to the planned work cycle of a second electrical working machine within the set of electrical working machines over the time period, wherein the controller is configured to adjust the planned work cycle of the first electrical working machine such that the first peak power demand occurs at a different point in time in comparison with a second peak power demand of the second electrical working machine. By ensuring that the peak power demands do not occur simultaneously, violation of the upper power limitation may be more easily be avoided.
[0023] According to some embodiments, the controller is configured to adjust the planned work cycles of at least two electrical working machines within the set of electrical working machines. The planned work cycles may be adjusted such that the peak power demands of both electrical working machines are time shifted in comparison with the planned work cycles, e.g., such that peak power demands of the respective electrical working machines do not overlap in time.
[0024] According to some embodiments, the controller is further configured to control the first electrical working machine to perform the adjusted work cycle. In this case, the controller is preferably located within the first electrical working machine, either in a centralized or in a decentralized configuration.
[0025] According to some embodiments, the arrangement comprises at least one electronic control unit arranged in the first electrical working machine. In some embodiments, the arrangement comprises several electronic control units, such as in a leaderfollower configuration or in a distributed, decentralised configuration. In someembodiments, the arrangement is provided within a central control unit separate from the set of working machines.
[0026] According to a second aspect of the disclosure, an electrical mining or construction machine comprising the arrangement of the first aspect is provided. The mining or construction machine may be of any of the types mentioned above. Effects and features of the second aspect of the disclosure are largely analogous to those described above in connection with the first aspect of the disclosure.
[0027] According to a third aspect of the disclosure, a method for managing power consumption of at least a first electrical working machine within a set of electrical working machines in the form of electrical mining and / or construction machines powered by a power grid is provided. The method comprises:
[0028] - obtaining information relating to a planned work cycle of at least the first electrical working machine over a time period;
[0029] - detecting that an upper power limitation of the power grid is or will be violated during the time period; and
[0030] - in response to said detection, adjusting the planned work cycle of at least the first electrical working machine to an adjusted work cycle in which at least one first peak power demand of the first electrical working machine is time shifted in comparison with the planned work cycle.
[0031] The method is computer-implemented and may be performed by a processing circuitry, such as by the controller of the arrangement of the first aspect. Effects and features of the third aspect of the disclosure are largely analogous to those described above in connection with the first aspect of the disclosure. In particular, the method may comprise performing all functions of the controller as described in connection with the first aspect.
[0032] According to a fourth aspect of the disclosure, a computer program is provided that comprises computer program code which, when executed by a computer, causes the computer to execute the method according to the third aspect.According to a fifth aspect of the disclosure, a non-transitory computer-readable storage medium having stored thereon the computer program of the fourth aspect is provided.
[0033] Further features of, and advantages with, the present disclosure will become apparent when studying the appended claims and the following description. The skilled person realize that different features may be combined to create embodiments other than those described in the following, without departing from the scope of the invention.
[0034] Brief Description of the Drawings
[0035] With reference to the appended drawings, below follows a more detailed description of embodiments of the disclosure cited as examples.
[0036] Fig 1 schematically illustrates a work site comprising a set of electrical working machines.
[0037] Fig. 2 is a flowchart illustrating a method according to the disclosure.
[0038] Fig. 3 illustrates power curves of a set of working machines.
[0039] Fig. 4 is a diagram illustrating an arrangement for managing power consumption according to a first embodiment.
[0040] Fig. 5 is a diagram illustrating an arrangement for managing power consumption according to a second embodiment.
[0041] Fig. 6 is a diagram illustrating an arrangement for managing power consumption according to a third embodiment.
[0042] Fig. 7 is a schematic diagram showing functional units of an arrangement according to an embodiment.Fig. 8 shows one example of a computer program product comprising computer readable means according to an embodiment.
[0043] The drawings show diagrammatic, exemplifying embodiments of the present disclosure and are thus not necessarily drawn to scale. It shall be understood that the embodiments shown and described are exemplifying and that the disclosure is not limited to these embodiments. It shall also be noted that some details in the drawings may be exaggerated in order to better describe and illustrate the disclosure. Like reference characters refer to like elements throughout the description, unless expressed otherwise.
[0044] Detailed Description
[0045] Fig. 1 schematically illustrates a work site 300, such as a mining environment, at which a set of electrical working machines 100, 100’, 100” in the form of mining machines are electrically connected to a common power grid 200. The working machines 100, 100’, 100” are configured to use power from the power grid 200 for performing tasks at the work site 300, such as for drilling in accordance with a drilling plan. The working machines 100, 100’, 100” are electrically connected via cable connections to the common power grid 200 such that power can be fed to the working machines for instant use during drilling and, if applicable, for charging of any on-board batteries of the working machines 100, 100’, 100”. During drilling, each working machine 100, 100’, 100” typically consumes a relatively high amount of power from the power grid 200. If grid power is limited, such as if intermittent power sources are used, there is a risk that the power grid 200 becomes overloaded during simultaneous drilling, with shutdowns or power failures of the working machines 100, 100’, 100” as a result. To avoid such failures, it is important that a combined power demand from the working machines 100, 100’, 100” does not exceed the available power from the power grid 200 at any point in time. An arrangement 1 for managing power consumption of the set of working machines 100, 100’, 100” is provided for this purpose, in Fig. 1 schematically depicted as a central control unit separate from the working machines 100, 100’, 100”, although in other embodiments the arrangement 1 may be located on-board one or several ones of the working machines. The arrangement 1 is communicatively connected to the workingmachines 100, 100’, 100’ and the working machines 100, 100’, 100” may further be communicatively connected to one another. The arrangement 1 is further communicatively connected to a grid controller 2 of the power grid 200, from which it can receive information relating to, e.g., a power capacity of the power grid 200. Although the set of working machines 100, 100’, 100” is illustrated with three identical working machines, the set may comprise another number of working machines, such as more than three working machines, wherein some or all working machines may be of the same type. The set may comprise several electrical working machines of different types.
[0046] Fig. 2 illustrates a method for managing power consumption of at least a first electrical working machine 100 within the set of electrical working machines 100, 100’, 100” powered by the power grid 200. The method is computer-implemented and comprises at least actions S1 , S2, S3 described in the following, that may be performed by processing circuitry, such as by a controller of the arrangement 1. Optional actions are marked with dashed lines in Fig. 2.
[0047] S1 : Obtaining information relating to a planned work cycle of at least the first electrical working machine 100 over a time period, AT. In this action, information relating to planned work cycles of some or all working machines 100, 100’, 100” within the set of working machines may be obtained. The information defines how the set of working machines 100, 100’, 100” is to be operated in accordance with the planned work cycles during the time period. The time period is a future time period, such as an immediately upcoming time period or a time period starting at a later, defined, point in time. The information may, e.g., define when and where drilling is to be performed by the respective working machines 100, 100’ 100”.
[0048] S11 : Determining a set of predicted power profiles for the set of electrical working machines during the time period AT based on at least the obtained information relating to the planned work cycles, each power profile being associated with one of the electrical working machines and comprising at least a peak power demand and a time stamp indicating a point in time at which the peak power demand is predicted. Hence, based on the information relating to the planned work cycles, and oncharacteristics of the working machines 100, 100’, 100”, a power demand of the working machines 100, 100’, 100” over the time period may be determined. For example, power profiles describing power demand P of one or more of the electrical working machines 100, 100’, 100” as a function of time t over the time period AT may be determined. Such power profiles P1_p, P2_p for the planned work cycles of a first and a second working machine 100, 100” are illustrated in the upper diagram of Fig. 3, wherein P1_p is a predicted power profile associated with the first working machine 100, and P2_p is a predicted power profile associated with the second working machine 100’. Each power profile P1_p, P2_p comprises a peak power demand PP1 , PP2, respectively, and a time stamp indicating a point in time at which the peak power demand is predicted. The peak power demand of an electrical working machine is the maximum power that it will demand at any point in time during the time period. With the planned work cycles, the first and second peak power demands PP1, PP2 of the first and second work machines 100, 100’, respectively, coincide at the same point in time t1.
[0049] S12: Determining a combined power profile describing a total power demand of the set of electrical working machines as a function of time over the time period based on at least the obtained information relating to the planned work cycles. A combined power profile Ptot_p, describing a total power demand of the electrical working machines 100, 100’ as a function of time t over the time period AT, as illustrated in the upper diagram of Fig. 3, has a peak power demand PP at the point in time t1.
[0050] S13: Receiving information relating to a power capacity of the power grid 200.
[0051] S2: Detecting that an upper power limitation, Plim, of the power grid 200 is or will be violated during the time period AT. The upper power limitation may, e.g., correspond to a maximum power that the power grid 200 will be able to supply to the set of working machines 100, 100’, 100” during the time period. The upper power limitation may be set to a fixed value over the time period, or to a value that varies over time. Violation of the upper power limitation may be detected either by receiving a notification from the grid controller 2 in the action S13, or by determining, in the arrangement 1 , that the total power demand Ptot of the set of electrical workingmachines 100, 100’, 100” exceeds or will exceed the upper power limitation during the time period, wherein the upper power limitation may be received from the grid controller 2 in the action S13. With reference to Fig. 3, the combined peak power demand PP of the first and second working machines 100, 100” will, with the planned work cycles, exceed the upper power limitation Plim during a time interval centered at the point in time t1.
[0052] S3: In response to said detection that the upper power limitation Plim is or will be violated, adjusting the planned work cycle of at least the first electrical working machine 100 to an adjusted work cycle in which the first peak power demand of the first electrical working machine 100 is time shifted in comparison with the planned work cycle. The adjustment may be carried out in response to detecting that the upper power limitation Plim is or will be violated at the time t1 of the first peak power demand. With reference to Fig. 3, the lower diagram illustrates the power profile P1_a associated with the adjusted work cycle of the first working machine 100. The planned work cycle P2_p of the second working machine 100’ has in this example not been adjusted. By adjusting the work cycle of the first working machine 100, the first peak power demand PP1 has been delayed in comparison with the planned work cycle, as well as in comparison with the second peak power demand PP2, and now occurs at a point in time t2. Since the first and second peak power demands PP1, PP2 no longer coincides, a combined power profile Ptot_a, describing the total power demand of the electrical working machines 100, 100’ as a function of time t after adjustment of the planned work cycle, no longer violates the upper power limitation Plim at any point in time during the time period.
[0053] The actions described above may be repeatedly performed over time to ensure that the upper power limitation is not exceeded during an extended time period. For example, the actions may be performed before each new work cycle of a working machine 100, 100’, 100” at the work site 300. When no violation of the upper power limit is detected, the working machines 100, 100’, 100” are operated according to the planned work cycles.Fig. 4 is a schematic diagram of an implementation of the arrangement 1 according to a first embodiment. Fig. 4 illustrates a first electrical working machine 100 and a second electrical working machine 100’ connected to the power grid 200, such as in the mining environment illustrated in Fig. 1. The first and second working machines 100, 100’ are configured to use power from the power grid 200 in connection with performing tasks according to respective work cycles of the working machines 100, 100’. An arrangement 1 in the form of a central control unit 1 , located off-board both working machines 100, 100’, is provided for managing power consumption of the working machines 100, 100’. The arrangement 1 comprises a controller 410, which is communicatively connected to a grid controller 2 and a mine operation planner 3. The controller 410 obtains, in the action S1 as described above, information relating to planned work cycles of the working machines 100, 100’ over the time period AT from the mine operation planner 3. Based on the information received from the mine operation planner 3, the controller 410 calculates the power demands of the working machines 100, 100” as a function of time during the time period.
[0054] From the grid controller 2, the controller 410 receives information relating to the power supply from the power grid 200 during the time period. The information may e.g. include a capacity of the power grid 200 during the time period, i.e., a maximum power output of the power grid 200 as a function of time over the time period. The received information may include an upper power limitation Plim of the power grid 200 during the time period, or information enabling the determination of the upper power limitation. Based on the obtained information relating to the power capacity of the power grid 200 and on the calculated the power demands of the working machines 100, 100”, the controller 410 detects that the upper power limitation Plim of the power grid 200 is or will be violated during the time period AT. In response to the detection, the controller 410 adjusts the planned work cycle of the first electrical working machine 100, and optionally of the second working machine 100’, as described above with reference to Figs 2-3. The controller 410 thereafter communicates the adjusted work cycle of the first working machine 1 to a first machine control unit 101 of the first working machine 100. If an adjusted work cycle of the second working machine 100’ has been determined, this adjusted work cycle is communicated to a second machine control unit 10T of the second workingmachine 100’. The machine control units 101, 10T thereafter implement the adjusted work cycles in the respective working machines 100, 100’.
[0055] Instead of providing the arrangement 1 in a central control unit located off-board the working machines, the arrangement 1 may be provided on-board one of the working machines within the set of working machines, e.g., forming part of the first machine control unit 101 or as a separate control unit. The first machine control unit 101 may in that case constitute a leader control unit, with the second control unit being a follower control unit that receives and implements instructions from the leader control unit.
[0056] Fig. 5 illustrates an implementation of the arrangement 1 according to a second embodiment, in which a decentralized, or distributed, configuration is used. A first and second arrangement 1, T, respectively, is provided in each one of the first and second working machines 100, 100’, the first and second arrangements 1, T comprising a respective controller (not illustrated) configured to perform the actions as described above. Both the arrangements 1, T are communicatively connected to the grid controller 2 and the mine operation planner 3 and receive information relating to the power grid capacity and the planned work cycles of the respective working machines 100, 100’. The arrangements 1, T are communicatively connected to one another such that the adjustment of one or both work cycles can be coordinated. For example, the first arrangement 1 may determine a time-stamped first peak power demand, e.g., included in a first power profile of the first working machine 100 associated with its planned work cycle, based on information received from the mine operation planner 3. Similarly, the second arrangement T may determine a time-stamped second peak power demand, such as included in a second power profile of the second working machine 100’ associated with its planned work cycle, based on information received from the mine operation planner 3. The first power profile is communicated from the first arrangement 1 to the second arrangement T and vice versa, such that each arrangement 1 , T may determine a combined power profile and detect whether a combined peak power demand violates the upper power limitation at any point in time during the time period. The second arrangement T may, in response to detecting that the combined peak powerdemand violates or will violate the upper power limitation during the time period, be configured to await further input from the first arrangement 1. The first arrangement 1 may instead, in response to the detection, adjust the planned work cycle of the first electrical working machine 100 to an adjusted work cycle in which the first peak power demand of the first electrical working machine 100 is time shifted in comparison with the planned work cycle, such that the upper power limitation will no longer be violated. The first arrangement 1 thereafter communicates an adjusted first power profile, including peak power demand with time stamping, associated with the adjusted work cycle, to the second arrangement T. The second arrangement T, in response to receiving the adjusted first power profile, calculates an updated combined power profile. If the second arrangement T finds that the upper power limitation is no longer violated, it implements the planned work cycle in the second working machine 100’ during the time period. The first arrangement 1 implements the adjusted work cycle in the first working machine 100. It is thereby ensured that the upper power limitation is not exceeded during the time period.
[0057] In yet another embodiment, illustrated in Fig. 6, the set of working machines comprises a so-called mixed fleet of working machines, wherein a first electrical working machine 100 and a second electrical working machine 100’ are not communicatively connected to one another, and in which only the first working machine 100 comprises an arrangement 1 according to an example of the disclosure. In this embodiment, the second working machine 100’ uses power from the power grid 200 and operates according to a work cycle as determined by the mine operation planner 3. The grid controller 2 may detect when a combined power demand of the set of working machines 100, 100’ is above the upper power limitation, and communicate the violation to the arrangement 1 provided in the first working machine 100. In response to receiving the notification from the grid controller 2, the arrangement 1 may adjust the planned work cycle of the first working machine 100 to an adjusted work cycle in which the first peak power demand of the first electrical working machine 100 is time shifted in comparison with the planned work cycle in the same way as described above. The planned work cycle of the second working machine 100’ is not affected. In some embodiments, a control unit 10T of the second working machine 100’ may be able to predict andcommunicate its power needs to the grid controller 2, including a time-stamped peak power demand, whereby the grid controller 2 may predict that the upper power limitation will be exceeded during a future time period. However, in other embodiments, the grid controller 2 may not be able to receive such information from the second control unit 10T. In those embodiments, the upper power limitation may be set to a value below an actual power capacity of the power grid 2, such that, when the grid controller 2 detects a violation of the upper power limitation, the power grid 2 is still able to supply power to the working machines 100, 100’ since its actual power capacity has not been exceeded. In this way, the arrangement 1 may adjust its planned work cycle such that power demanding tasks of the first working machine 100 are delayed to prevent violation of the upper power limitation.
[0058] In addition to the time shifting achieved by delaying or advancing initiation of the task associated with the first peak power demand, the arrangement 1 according to any one of the embodiments described above may further be configured to adjust the planned work cycle by adjusting a maximum amount of power allocated to a first task associated with the first peak power demand. The allocated power may be increased, corresponding to a power boost of the first working machine 100, such that the first task is completed faster with the adjusted work cycle in comparison with the planned work cycle. The allocated power may also be reduced, corresponding to a derating of the first working machine 100, such that the first task is completed slower with the adjusted work cycle in comparison with the planned work cycle. Such an increment or reduction of the allocated power may preferably be combined with an advancement or a delay of the initiation of the first task, respectively, such that a further time shift is achieved. The boosting or derating may, by way of example, be achieved by increasing or decreasing a drilling speed, respectively, when the work cycle is a drilling cycle.
[0059] Fig. 7 shows an embodiment of the arrangement 1 for managing power consumption of at least a first electrical working machine within a set of electrical working machines in the form of electrical mining and / or construction machines connected to a power grid according to the disclosure. The arrangement 1 comprises a processing circuitry 410, also referred to as a controller 410, and a storage medium 430. Thestorage medium 430 contains instructions executable by the processing circuitry 410, whereby the arrangement 1 is operative for performing any one of the embodiments of the method for managing power consumption described in this disclosure. The storage medium 430 may comprise persistent storage, which, for example, can be any single one or combination of magnetic memory, optical memory, solid state memory or even remotely mounted memory. The arrangement 1 may further comprise a communication interface 420. The communication interface 420 may be considered to comprise conventional means for communication with other entities, such as with control units of the working machines, with the grid controller, the mine operation planner, etc. It may e.g. comprise a wireless transmitter and receiver, comprising analogue and / or digital components. The instructions executable by the processing circuitry 410 may be arranged as a computer program product 520 stored in said storage medium 430.
[0060] Fig. 8 shows one example of a computer program product 520 comprising computer readable means 540 on which a computer program 530 can be stored, which computer program 530 can cause the processing circuitry 410 and thereto operatively coupled entities and devices, such as the communications interface 420 and the storage medium 430, to execute methods according to embodiments described herein.
[0061] Even though the invention has been described with reference to specific exemplifying embodiments thereof, many different alterations, modifications and the like will become apparent for those skilled in the art.
[0062] Additionally, variations to the disclosed embodiments can be understood and effected by the skilled person in practicing the claimed invention, from a study of the drawings, the disclosure, and the appended claims. In the claims, the word "comprising" does not exclude other elements or steps, and the indefinite article "a" or "an" does not exclude a plurality. The mere fact that certain measures are recited in mutually different dependent claims does not indicate that a combination of these measures cannot be used to advantage.
Claims
CLAIMS1. An arrangement (1 ) for managing power consumption of at least a first electrical working machine (100) within a set of electrical working machines (100, 100’, 100”) in the form of electrical mining and / or construction machines connected to a power grid (200), the arrangement (1) comprising a controller (410) configured to:- obtain information relating to a planned work cycle of at least the first electrical working machine (100) over a time period (AT);- detect that an upper power limitation (Plim) of the power grid is or will be violated during the time period; and- in response to said detection, adjust the planned work cycle of at least the first electrical working machine (100) to an adjusted work cycle in which at least one first peak power demand of the first electrical working machine (100) is time shifted in comparison with the planned work cycle.
2. The arrangement of claim 1 , wherein the controller is configured to adjust the planned work cycle in response to detecting that the upper power limitation is or will be violated at the time of the first peak power demand.
3. The arrangement of claim 1 or 2, wherein the controller is configured to adjust the planned work cycle such that a total power demand of the set of electrical working machines does not exceed the upper power limitation at any point in time during the time period.
4. The arrangement of any one of the preceding claims, wherein the information relating to the planned work cycle comprises information relating to the planned work cycles of all electrical working machines within the set of electrical working machines over the time period, and wherein the controller is further configured to:- determine a combined power profile (Ptot) describing a total power demand of the set of electrical working machines as a function of time over the time period based on at least the obtained information relating to the planned work cycles.
5. The arrangement of claim 4, wherein the controller is configured to determine a set of predicted power profiles (P1 , P2) for the set of electrical working machines during the time period based on at least the obtained information relating to the planned work cycles, each power profile being associated with one of the electrical working machines and comprising at least a peak power demand and a time stamp indicating a point in time at which the peak power demand is predicted, and wherein the combined power profile is determined based on the set of predicted power profiles.
6. The arrangement of any one of the preceding claims, wherein the first peak power demand is associated with a first task performed by the first electrical working machine, and wherein the controller is further configured to adjust the planned work cycle by adjusting a maximum amount of power allocated to the first task.
7. The arrangement of claim 6, wherein the controller is configured to adjust the planned work cycle of the first electrical working machine such that the first task is completed faster with the adjusted work cycle in comparison with the planned work cycle, or such that the first task is completed slower with the adjusted work cycle in comparison with the planned work cycle.
8. The arrangement of any one of the preceding claims, wherein the information relating to the planned work cycle further comprises information relating to the planned work cycle of a second electrical working machine (100’) within the set of electrical working machines (100, 100’, 100”) over the time period, and wherein the controller (410) is configured to adjust the planned work cycle of the first electrical working machine (100) such that the first peak power demand occurs at a different point in time in comparison with a second peak power demand of the second electrical working machine (100’).
9. The arrangement of any one of the preceding claims, wherein the controller is configured to adjust the planned work cycles of at least two electrical working machines within the set of electrical working machines.
10. The arrangement of any one of the preceding claims, wherein the controller (410) is further configured to control the first electrical working machine (100) to perform the adjusted work cycle.
11. The arrangement of any one of the preceding claims, wherein the arrangement (1) comprises at least one electronic control unit arranged in the first electrical working machine (100).
12. An electrical mining or construction machine (100) comprising the arrangement (1 ) of any one of the preceding claims.
13. A method for managing power consumption of at least a first electrical working machine (100) within a set of electrical working machines (100, 100’, 100”) in the form of electrical mining and / or construction machines powered by a power grid (200), the method comprising:- obtaining (S1 ) information relating to a planned work cycle of at least the first electrical working machine over a time period;- detecting (S2) that an upper power limitation (Plim) of the power grid is or will be violated during the time period ; and- in response to said detection, adjusting (S3) the planned work cycle of at least the first electrical working machine to an adjusted work cycle in which at least one first peak power demand of the first electrical working machine (100) is time shifted in comparison with the planned work cycle.
14. A computer program (530) comprising computer program code which, when executed by a computer (400), causes the computer to execute the method according to claim 13.
15. A non-transitory computer-readable storage medium (540) having stored thereon the computer program (530) of claim 14.