A rock drilling rig and hydraulic technology, which is applied to reciprocating drilling rigs, impact drilling, drill pipes, etc., can solve the problems of inability to meet the schedule requirements, low efficiency, air pollution and other problems of excavating large volumes of stone, and achieve flexible The effect of fast moving efficiency, cost reduction, and low failure rate
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2012-10-03
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
Technical field
[0001] The invention relates to a rock drilling rig. Background technique
[0002] my country is a mountainous country with rapid economic development. The amount of rock drilling and mining in basic construction areas such as roads and railways, mining, energy, hydropower, national defense, real estate, economic development zones, and quarries is very large. High-performance modern rock drilling equipment almost consumes a lot of foreign exchange imports, while domestic drilling equipment has always been a pneumatic down-the-hole drilling rig to occupy the market. If the domestic low- and medium-pressure pneumatic down-the-hole drilling rigs are adopted, the energy consumption is high, the efficiency is low, the labor intensity of the workers is high, and the air pollution is serious, and it cannot meet the schedule requirements of the large amount of stone excavation. The imported hydraulic drilling rig is used for construction, although the efficiency is high, ...
Examples
Embodiment Construction
[0020] The present invention will be further explained below in conjunction with the drawings and embodiments:
[0021] Such as Figure 1 to Figure 6 As shown, a mounted integrated hydraulic rock drilling rig includes a bottom support 1 and a drill frame 8 which are fixedly connected to each other. The middle of the drill frame 8 is provided with a seventh pin 19 that can be connected to the oil cylinder of an engineering vehicle and The eighth pin shaft 20 connected to the boom of the engineering vehicle.
[0022] The drill frame 8 is welded with a parallel rail 28, the rail 28 is provided with a first slide plate 14, and the first slide plate 14 is fixed with a mounting plate 13 by bolts. The mounting plate 13 is fixed with a chuck 15 perpendicular to the mounting plate 13 and clamps A rock drill 12 is provided in the head 15, and a drill rod 7 is connected to the rock drill 12.
[0023] The top of the drill frame 8 is provided with a driving sprocket 16 and the lower part is pro...