A group synchronous lifting structure for construction machinery and building construction

By grouping the climbing frames of construction equipment and using multi-section connections and hydraulic cylinder flip stepping devices, the problems of climbing frames are solved, independent platform lifting is achieved, and construction efficiency and equipment portability are improved.

CN111910912BInactive Publication Date: 2025-01-07SHENZHEN EXCELLENCE INDZATION INTELLIGENT CONSTR DEV CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202010906736.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-09-02
Publication Date
2025-01-07
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The height of the climbing frame in existing construction equipment is high, which makes it difficult to design and manufacture, and has a high load-bearing capacity, affecting the transportation and installation efficiency of the equipment.

Method used

The climbing frame is grouped, and the lifting columns and upper and lower climbing frames are connected by multiple standard sections. The independent climbing and falling action is achieved through hydraulic cylinders and flip stepping devices, and the design of the climbing frame and stepping devices is optimized for easy transportation and installation.

Benefits of technology

The bearing capacity and manufacturing cost of the climbing hydraulic cylinder are reduced, independent lifting of platforms on each floor is achieved, construction efficiency is improved, mold clamping process is simplified, and the length of steel is reduced, making it easier to manufacture and transport.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111910912B_ABST
    Figure CN111910912B_ABST
Patent Text Reader

Abstract

The present invention relates to a group synchronous lifting structure for construction machinery and building construction, comprising a lifting column, an upper climbing frame and a lower climbing frame, the outer sides of the upper climbing frame and the lower climbing frame are both provided with standard interfaces, the upper climbing frame is detachably connected to a steel platform vertically, the lower climbing frame is detachably connected to a truss platform and an operating platform vertically, the upper climbing frame is connected to the lifting column through an upper stepping device, a guide mechanism is provided on the inner side of the upper climbing frame, the upper climbing frame comprises an upper climbing frame upper and an upper climbing frame lower, the upper climbing frame upper and the upper climbing frame lower are connected through an upper climbing hydraulic cylinder, the upper stepping device comprises a stepping block connected to the lifting column and an upper stepping turning device connected to the upper climbing frame, the upper stepping turning device is hinged to the outer side of the upper climbing frame, and the structure and connection relationship of the lower climbing frame are similar to those of the upper climbing frame. The present invention sets two groups of climbing frames, reduces the manufacturing cost of the climbing hydraulic cylinder; each layer of the platform can be independently lifted and lowered, improves efficiency, and is easy to manufacture and transport.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction equipment, and in particular to a group synchronous lifting structure for construction machinery and building construction. Background Art

[0002] The floor-standing assembled formwork system is based on the "multi-functional building machine" and mature industrial technology, and forms a highly integrated construction equipment system through integrated innovation. It can be used for traditional construction methods, as well as new industrialized construction methods such as formwork-free systems, prefabricated assembled buildings, and steel structure buildings; it is suitable for building structures such as frame structures, shear wall structures, frame shear wall structures, and steel structures. The floor-standing assembled formwork system is generally divided into three parts: working platform, climbing frame, and lifting column. The working platform includes a steel platform, a truss platform, an operating platform, and the like. CN210239083U discloses a synchronous lifting structure for construction machinery and construction, which only includes a set of climbing frames. The climbing frame is relatively high, and is connected to the steel structure platform, the truss platform, the operating platform, and other functional components from top to bottom; it has a high rigidity and bears a high load, resulting in high design requirements for the climbing frame body, steps, and guides, and it is difficult to make, install, and transport. Summary of the invention

[0003] In order to overcome the shortcomings of the background technology, the present invention discloses a grouped synchronous lifting structure for construction machinery and building construction, which divides the climbing frames into groups to achieve independent climbing and descending actions of the steel platform and the operating platform, optimizes the design of the climbing frame, stepping device and guide mechanism, and facilitates transportation.

[0004] In order to achieve the above-mentioned invention object, the present invention adopts the following technical scheme:

[0005] A group synchronous lifting structure for construction machinery and building construction, comprising a lifting column, an upper climbing frame and a lower climbing frame, wherein the lifting column is formed by connecting a plurality of standard sections in sequence through bolts, the lifting column is fixed to the wall through a fixed wall attachment device, the lifting column is fixed to the foundation, standard interfaces are arranged on the outer sides of the upper climbing frame and the lower climbing frame, the upper climbing frame is detachably connected to a steel platform vertically, the lower climbing frame is detachably connected to a gantry platform and an operating platform vertically, the upper climbing frame is connected to the lifting column through an upper stepping device, the lower climbing frame is connected to the lifting column through a lower stepping device, and a guide mechanism is arranged on the inner sides of the upper climbing frame and the lower climbing frame. The upper climbing frame comprises an upper climbing frame upper part and an upper climbing frame lower part, the upper climbing frame upper part and the upper climbing frame lower part are connected by an upper climbing hydraulic cylinder, the upper stepping device comprises a stepping block connected to the lifting column and an upper stepping turning device connected to the upper climbing frame, the upper stepping turning device is hinged on the outer side of the upper climbing frame, the lower climbing frame comprises a lower climbing frame upper part and a lower climbing frame lower part, the lower climbing frame upper part and the lower climbing frame lower part are connected by an upper climbing hydraulic cylinder, the lower stepping device comprises a stepping block connected to the lifting column and a lower stepping turning device connected to the lower climbing frame, the lower stepping turning device is hinged on the outer side of the lower climbing frame.

[0006] Preferably, the upper step flipping device and the lower step flipping device both comprise a flipping hydraulic cylinder and a step, and the flipping hydraulic cylinder is hinged to the step.

[0007] Preferably, two guide mechanisms are arranged on the inner sides of both sides of the four corner positions of the upper climbing frame.

[0008] Preferably, the upper climbing frame is vertically connected to the steel platform at the bottom.

[0009] Preferably, the lower climbing frame is vertically connected to the gantry platform and the operating platform.

[0010] Preferably, a formwork system is mounted under the steel platform.

[0011] Preferably, it also includes an intelligent control system for controlling the extension and retraction of the tilting hydraulic cylinder, the upward climbing hydraulic cylinder and the downward climbing hydraulic cylinder.

[0012] Due to the adoption of the above-mentioned technical solution, the present invention has the following beneficial effects:

[0013] Since two sets of climbing frames are set up, the required bearing capacity of each set of climbing frames is reduced, and the force borne by the climbing hydraulic cylinder is also reduced accordingly, thereby optimizing the design of the climbing frame body, stepping device, and guide mechanism, and reducing the manufacturing cost of the climbing hydraulic cylinder; the upper climbing frame and the lower climbing frame can complete independent climbing and falling actions, and each platform can be raised and lowered independently. After the steel platform is mounted with the template, it can be lowered alone to complete the mold dropping action; the steel platform with the template mounted can be raised and lowered alone, avoiding the overall lifting of the platform during the mold closing process, optimizing the action sequence of the entire system, and improving efficiency; the length of the steel section used for the climbing frame is reduced to less than 12 meters, which is convenient for production and transportation. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0015] Figure 1 A front view of an embodiment of the present invention;

[0016] Figure 2 It is a left side view of an embodiment of the present invention;

[0017] Figure 3 Assembly drawing of upper climbing frame, lower climbing frame and lifting column;

[0018] Figure 4 for Figure 3 A partial enlarged view of point B in the middle;

[0019] Figure 5 for Figure 3 A partial enlarged view of point C in the middle;

[0020] Figure 6 for Figure 4 EE profile diagram;

[0021] Figure 7 for Figure 5 FF cross-section diagram;

[0022] Figure 8 for Figure 7 A partial enlarged view of point D in the middle;

[0023] Fig. 9 It is a structural diagram of the lower climbing frame in the embodiment;

[0024] Fig.10 for Fig. 9 A top view of

[0025] Figure markings: 1-lifting column, 101-standard section, 2-upper climbing frame, 201-upper climbing frame, 202-upper climbing frame, 203-upper climbing hydraulic cylinder, 3-lower climbing frame, 301-lower climbing frame, 302-lower climbing frame, 303-lower climbing hydraulic cylinder, 4-steel platform, 5-truss platform, 6-operating platform, 7-upper step device, 701-upper step turning device, 8-lower step device, 801-lower step turning device, 9-guide mechanism, 10-step block, 11-turning hydraulic cylinder, 12-step, 13-template system, 14-double-beam truss. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] In the description of the present invention, it should be noted that the terms "upper", "lower", "horizontal", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0028] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, it can be a mechanical connection, it can be an electrical connection, it can be a direct connection, it can be connected through an intermediate medium, and it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0029] Please refer to Figures 1-8, a group synchronous lifting structure for construction machinery and building construction includes a lifting column 1, an upper climbing frame 2 and a lower climbing frame 3. The lifting column 1 is formed by connecting a plurality of standard sections 101 in sequence through bolts. The lifting column 1 is fixed to the wall through a fixed wall attachment device, and the lifting column 1 is fixed to the foundation. Standard interfaces are set on the outer sides of the upper climbing frame 2 and the lower climbing frame 3. The upper climbing frame 2 is detachably connected to the steel platform 4 vertically, and the lower climbing frame 3 is detachably connected to the truss platform 5 and the operating platform 6 platform vertically. The upper climbing frame 2 is connected to the lifting column 1 through an upper stepping device 7, and the lower climbing frame 3 is connected to the lifting column 1 through a lower stepping device 8. A guide mechanism 9 is set on the inner sides of the upper climbing frame 2 and the lower climbing frame 3. The upper climbing frame 2 includes The upper climbing frame 201 and the upper climbing frame lower 202 are connected by an upper climbing hydraulic cylinder 203. The upper stepping device 7 includes a stepping block 10 connected to the lifting column 1 and an upper stepping turning device 701 connected to the upper climbing frame 201. The upper stepping turning device 701 is hinged to the outer side of the upper climbing frame 2. The lower climbing frame 3 includes a lower climbing frame upper 301 and a lower climbing frame lower 302. The lower climbing frame upper 301 and the lower climbing frame lower 302 are connected by a lower climbing hydraulic cylinder 303. The lower stepping device 8 includes a stepping block 10 connected to the lifting column 1 and a lower stepping turning device 801 connected to the lower climbing frame upper 301. The lower stepping turning device 801 is hinged to the outer side of the lower climbing frame 3.

[0030] For further information, please refer to Figure 6-8 The upper step flipping device 701 and the lower step flipping device 801 both include a flipping hydraulic cylinder 11 and a step 12 , and the flipping hydraulic cylinder 11 is hinged to the step 12 .

[0031] Further, please refer to 9-10, two guide mechanisms 9 are set on the inner sides of both sides of the four corner positions of the upper climbing frame 2.

[0032] Further, the lower part 202 of the upper climbing frame is vertically connected to the steel platform 4. The lower part 202 of the upper climbing frame is fixedly connected to the steel platform 4 by bolts.

[0033] Further, the upper part 301 of the lower climbing frame is vertically connected with the gantry platform 5 and the operating platform 6. The upper part 301 of the lower climbing frame is fixedly connected with the gantry platform 5 and the operating platform 6 by bolts.

[0034] Furthermore, a formwork system 13 is mounted below the steel platform 4 .

[0035] Furthermore, it also includes an intelligent control system for controlling the extension and retraction of the turning hydraulic cylinder 11 , the upward climbing hydraulic cylinder 203 and the downward climbing hydraulic cylinder 303 .

[0036] Generally, the floor-standing assembled formwork system includes multiple lifting columns 1, each lifting column 1 is equipped with an upper climbing frame 2 and a lower climbing frame 3, the steel platform 4 is connected to the lower climbing frame 202 on each lifting column 1, the operating platform 6 is connected to the lower climbing frame 301 on each lifting column 1, the gantry platform 5 is a group of parallel components, the gantry platform 5 is connected to the lower climbing frame 301 on the lifting column 1 on the same side, and the double-beam gantry 14 is placed on the gantry platform 5.

[0037] With the above technical solution, since two sets of climbing frames are set, the required bearing capacity of each set of climbing frames is reduced, and the force borne by the climbing hydraulic cylinder is also reduced, thereby optimizing the design of the climbing frame body, the stepping device, and the guide mechanism 9, and reducing the manufacturing cost of the climbing hydraulic cylinder; the upper climbing frame 2 and the lower climbing frame 3 can complete independent climbing and falling actions, and each layer of the platform can be independently raised and lowered. After the steel platform 4 is mounted with the template, it can be lowered alone to complete the mold drop action. The length of the steel used in the climbing frame is reduced to less than 12 meters, which is convenient for production and transportation.

[0038] Specifically, the upper climbing frame 2 uses the upper climbing hydraulic cylinder 203 to lift and lower the steel platform 4 according to the needs of the formwork system 13; the lower climbing frame 3 uses the lower climbing hydraulic cylinder 303 to lift the operating platform 6 and the gantry platform 5 upward as the number of floors increases. The entire operating platform 6 and the gantry platform 5 only need to be built once to complete the construction of the entire building. When one floor is built, the lower climbing hydraulic cylinder 303 allows the lower climbing frame 3 and the operating platform 6 to increase the height of one floor upward to prepare for the pouring of the next floor.

[0039] The present invention also provides a method for raising a steel platform 4, comprising the following steps:

[0040] S1, initial state, the step 12 of the upper climbing frame 201 and the step 12 of the lower climbing frame 202 are in contact with the step block 10 on the standard section 101;

[0041] S2, the step 12 of the upper climbing frame 201 is turned to a vertical state under the retracting action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the support is provided by the lower 202 of the upper climbing frame and the upper climbing hydraulic cylinder 203;

[0042] S3, the upper climbing frame 201 starts to rise under the extension of the upper climbing hydraulic cylinder 203, and the guide mechanism 9 provides guidance for the upper climbing frame 201;

[0043] S4, after the upper climbing frame 201 reaches the position, the step 12 of the upper climbing frame 201 is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0044] S5, the step 12 of the lower 202 of the upper climbing frame is turned to a vertical state under the retracting action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the upper 201 of the upper climbing frame and the upper climbing hydraulic cylinder 203 provide support;

[0045] S6, the lower part 202 of the upper climbing frame starts to rise under the action of the cylinder contraction of the upper climbing hydraulic cylinder 203, and the guide mechanism 9 provides guidance for the lower part 202 of the upper climbing frame;

[0046] S7, after the lower part 202 of the upper climbing frame reaches the position, the step 12 of the lower part 202 of the upper climbing frame is turned to the horizontal position under the extension cylinder action of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0047] S8, a climbing link is completed, the above steps are repeated, and the upper climbing frame 2 is continuously lifted along the lifting column 1.

[0048] The present invention also provides a method for lowering a steel platform 4, comprising the following steps:

[0049] T1, initial state, the step 12 of the upper climbing frame 201 and the step 12 of the lower climbing frame 202 are in contact with the step block 10 on the standard section 101;

[0050] T2, the step 12 of the lower 202 of the upper climbing frame is turned to a vertical state under the retracting action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the upper 201 of the upper climbing frame and the upper climbing hydraulic cylinder 203 provide support;

[0051] T3, the lower part 202 of the upper climbing frame begins to descend under the extension of the upper climbing hydraulic cylinder 203, and the guide mechanism 9 provides guidance for the lower part 202 of the upper climbing frame;

[0052] T4, after the lower part 202 of the upper climbing frame reaches the position, the step 12 of the lower part 202 of the upper climbing frame is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0053] T5, the step 12 of the upper climbing frame 201 is turned to a vertical state under the retraction action of the flip hydraulic cylinder 11 to avoid interference with the cross bar of the standard section 101. At this time, the support is provided by the lower 202 of the upper climbing frame and the upper climbing hydraulic cylinder 203;

[0054] T6, the upper climbing frame 201 starts to descend under the action of the cylinder contraction of the upper climbing hydraulic cylinder 203, and the guide mechanism 9 provides guidance for the upper climbing frame 201;

[0055] T7, after the upper climbing frame 201 reaches the position, the step 12 of the upper climbing frame 201 is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0056] T8, a descending link is completed, the above steps are repeated, and the upper climbing frame 2 continues to descend along the lifting column 1.

[0057] The present invention also provides a method for raising the operating platform 6, comprising the following steps:

[0058] P1, initial state, the step 12 on the upper 301 of the lower climbing frame and the step 12 on the lower 302 of the lower climbing frame are in contact with the step block 10 on the standard section 101;

[0059] P2, the step 12 on the lower climbing frame 301 is turned to a vertical state under the retraction action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the support is provided by the lower climbing frame 302 and the lower climbing hydraulic cylinder 303;

[0060] P3, the lower climbing frame 301 starts to rise under the extension of the lower climbing hydraulic cylinder 303, and the guide mechanism 9 provides guidance for the lower climbing frame 301;

[0061] P4, after the lower climbing frame 301 reaches the position, the step 12 of the lower climbing frame 301 is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0062] P5, the step 12 of the lower climbing frame 302 is turned to a vertical state under the retracting action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the support is provided by the upper 301 of the lower climbing frame and the lower climbing hydraulic cylinder 303;

[0063] P6, the lower climbing frame 302 starts to rise under the action of the contraction of the lower climbing hydraulic cylinder 303, and the guide mechanism 9 provides guidance for the lower climbing frame 302;

[0064] P7, after the lower climbing frame 302 reaches the position, the step 12 of the lower climbing frame 302 is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0065] P8. One climbing link is completed, and the above steps are repeated, and the lower climbing frame 3 is continuously lifted along the lifting column 1.

[0066] The present invention also provides a method for lowering the operating platform 6, comprising the following steps:

[0067] Q1, initial state, the step 12 on the upper 301 of the lower climbing frame and the step 12 on the lower 302 of the lower climbing frame are in contact with the step block 10 on the standard section 101;

[0068] Q2, the step 12 of the lower climbing frame 302 is turned to a vertical state under the retracting action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the support is provided by the upper 301 of the lower climbing frame and the lower climbing hydraulic cylinder 303;

[0069] Q3, the lower climbing frame 302 begins to descend under the extension of the lower climbing hydraulic cylinder 303, and the guide mechanism 9 provides guidance for the lower climbing frame 302;

[0070] Q4. After the lower climbing frame 302 reaches the position, the step 12 of the lower climbing frame 302 is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0071] Q5. The step 12 on the lower climbing frame 301 is turned to a vertical state under the retracting action of the flip hydraulic cylinder 11 to avoid interference with the crossbar of the standard section 101. At this time, the support is provided by the lower climbing frame 302 and the lower climbing hydraulic cylinder 303;

[0072] Q6. The upper part 301 of the lower climbing frame starts to descend under the action of the contraction of the lower climbing hydraulic cylinder 303, and the guide mechanism 9 provides guidance for the upper part 301 of the lower climbing frame;

[0073] Q7. After the lower climbing frame 301 reaches the position, the step 12 of the lower climbing frame 301 is turned to the horizontal position under the extension of the turning hydraulic cylinder 11, and the step 12 contacts the step block 10 on the standard section 101;

[0074] Q8. A descending link is completed, and the above steps are repeated, and the lower climbing frame 3 continues to descend along the lifting column 1.

[0075] Furthermore, a method for raising the steel platform 4 also includes a process of adding the lifting column 1, and the steps include the following steps:

[0076] A1. The hoisting mechanism hoists the standard section 101 to be added onto the lifting column 1 whose height needs to be increased;

[0077] A2. Tighten the bolts.

[0078] Furthermore, a method for lowering the steel platform 4 also includes a process of reducing the lifting column 1, and the steps include the following steps:

[0079] B1. Lower the upper climbing frame 2 to the designated position;

[0080] B2. Remove the bolts between the standard section 101 to be removed and the standard section 101 to be retained and evacuate;

[0081] B3. The hoisting mechanism hoists the standard section 101 to be subtracted onto the steel platform 4 or the ground.

[0082] Through the above technical solution, as the floors increase, the lifting column 1 can be easily added to provide support for the climbing frame, thereby improving the lifting of each platform; after the construction is completed, the lifting column 1 can be easily reduced.

[0083] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element.

[0084] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.

[0085] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A synchronous lifting structure for construction machinery and building construction, comprising a lifting column, an upper climbing frame and a lower climbing frame, characterized in that: The lifting column is formed by connecting a plurality of standard sections in sequence through bolts. The lifting column is fixed to the wall through a fixed wall attachment device. The lifting column is fixed to the foundation. Standard interfaces are arranged on the outer sides of the upper climbing frame and the lower climbing frame. The upper climbing frame is detachably connected to the steel platform vertically. The lower climbing frame is detachably connected to the gantry platform and the operating platform vertically. The upper climbing frame is connected to the lifting column through an upper stepping device. The lower climbing frame is connected to the lifting column through a lower stepping device. A guiding mechanism is arranged on the inner sides of the upper climbing frame and the lower climbing frame. The upper climbing frame includes an upper climbing frame upper and an upper climbing frame lower. The upper frame and the lower frame of the upper climbing frame are connected by an upper climbing hydraulic cylinder, the upper stepping device includes a stepping block connected to the lifting column and an upper stepping turning device connected to the upper climbing frame, the upper stepping turning device is hinged on the outer side of the upper climbing frame, the lower climbing frame includes an upper lower climbing frame and a lower lower climbing frame, the upper lower climbing frame and the lower lower climbing frame are connected by a lower climbing hydraulic cylinder, the lower stepping device includes a stepping block connected to the lifting column and a lower stepping turning device connected to the lower climbing frame, the lower stepping turning device is hinged on the outer side of the lower climbing frame; the template system is mounted below the steel platform; The upper step turning device and the lower step turning device both comprise a turning hydraulic cylinder and a step, and the turning hydraulic cylinder is hinged to the step.

2. The synchronous lifting structure for construction machinery and building construction according to claim 1 is characterized in that: Two guide mechanisms are arranged on the inner sides of both sides of the four corner positions of the upper climbing frame.

3. The synchronous lifting structure for construction machinery and building construction according to claim 1 is characterized in that: The upper climbing frame is vertically connected to the steel platform at the bottom.

4. The synchronous lifting structure for construction machinery and building construction according to claim 1 is characterized in that: The lower climbing frame is vertically connected to the gantry platform and the operating platform.

5. The synchronous lifting structure for construction machinery and building construction according to claim 1 is characterized in that: It also includes an intelligent control system for controlling the extension and retraction of the tilting hydraulic cylinder, the upward climbing hydraulic cylinder and the downward climbing hydraulic cylinder.

Citation Information

Patent Citations

  • Inner roof external climbing type formwork construction platform for super high-rise building construction

    CN106437130A

  • Synchronous lifting structure for building machinery and building construction

    CN210239083U

  • Grouped synchronous lifting structure for building machinery and building construction

    CN212535058U