A construction method for preloaded steel-concrete transfer beam
Through the construction method of preloaded steel concrete conversion beams, the problems of large deflection and stress hysteresis in reinforced concrete beam reinforced by reverse loading and H-shaped steel are solved, and the deflection reduction and stress balance of large span beams are achieved to ensure the reinforcement body The integral stress performance.
Patent Information
- Application Number
- CN202310275968.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-16
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2043-03-16
AI Technical Summary
In the existing reinforced concrete beam reinforcement technology, the deflection of the converting beam is prone to cracking, stress lag, and the strength of the new components is not fully utilized, resulting in poor reinforcement effect.
The construction method of preloaded steel concrete conversion beam is adopted, and the original floor beam is reversely loaded by reverse loading of the upper column beam, the lower column beam, the first jack, the support steel pipe, etc., and the original floor beam is reversed and reinforced. After welding the beam and column, secondary loading is carried out to ensure that the bottom steel of the beam is slightly deformed, and finally tighten it with iron plates to reduce deflection and avoid stress hysteresis effect.
Through three loadings, the deflection of the large-span beam after the joists is pulled out is significantly reduced, ensuring the reinforced integral stress is avoided, and the stress hysteresis effect of new and old concrete is improved, and the bearing capacity and stress performance of the structure are improved.
Smart Images

Figure CN116220427B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of engineering structure reconstruction and reinforcement, and in particular to a construction method of a preloaded steel-concrete transfer beam. Background Art
[0002] "Supporting beams and pulling out columns" is an advanced technical means to expand the column spacing problem. The usual process is to first strengthen the beams and columns, and then cut the columns. The advantages are that the construction is relatively simple and the support and unloading measures are simple and easy to implement. The disadvantage is that the original concrete in the frame column cannot be replaced and technical measures need to be adopted to strengthen the nodes. After the conventional reinforced concrete beam is added to the cross section, there are a series of problems such as excessive deflection of the conversion beam, easy cracking, stress lag, and the strength of the newly added components cannot be fully utilized. Summary of the invention
[0003] The purpose of the present invention is to provide a construction method for preloaded steel-concrete transfer beams. Through reverse loading of the upper column beam, the lower column beam, the first jack, the supporting steel pipe, etc., the original floor beam produces a certain amount of reverse arch; after the H-shaped steel is welded to the steel hoop on the reinforced beam column, a secondary loading is performed at the mid-span position between the original floor beam and the H-shaped steel, causing the newly added H-shaped steel at the bottom of the beam to deform slightly, and then it is plugged with an iron plate. After three loadings, the deflection of the large-span beam after the support beam is removed from the column is greatly reduced, the stress hysteresis effect of the new and old concrete is avoided, and the integral force of the reinforced body is ensured.
[0004] The above technical objectives of the present invention are achieved through the following technical solutions:
[0005] The original building structure includes the original floor beams at the top of the first floor and the first floor structural columns used to support the original floor beams. The first floor structural columns are later divided into reinforced beams and columns and proposed withdrawn columns. 2-3 proposed withdrawn columns are arranged between two adjacent reinforced beams and columns. The second floor structural columns are arranged on the original floor beams. The second floor structural columns correspond to the first floor structural columns one by one and are located directly above the first floor structural columns.
[0006] A construction method for a preloaded steel-concrete transfer beam comprises the following steps:
[0007] Step 1: In order to make the new and old concrete bear the force synergistically, the internal force and stress of the reinforced beam-column structure system should be reinforced when the stress is low (or even zero). This project adopts full-span support unloading to ensure the effectiveness of reinforcement and the safety of the construction process; within the 1 / 2 beam span of the planned column expansion, the scaffolding steel pipe top-supporting screw rod is used to support the second floor slab in this range, and the dead weight falls directly to the ground; the screw rod rotates on the scaffolding steel pipe to adjust the height of the screw rod, thereby supporting the second floor slab;
[0008] Step 2: Set a lower column beam on the planned column, and set an upper column beam on the second-story structural column above the planned column. The lower column beam supports the upper column beam through four sets of supporting steel pipes, the first jack and a digital axial force meter;
[0009] Specifically, the first steel plate is embedded at the four corners of the upper end of the lower column beam, and the second steel plate is embedded at the four corners of the lower end of the upper column beam; the lower end of the supporting steel pipe is welded to the first steel plate, and a flange chassis is fixed on the top of the supporting steel pipe. The first jack and the digital axial force meter are arranged between the flange chassis and the second steel plate, and a linen cloth is clamped between the first jack and the digital axial force meter. The digital axial force meter can clearly show the size of the supporting force of the first jack on the upper column beam. The supporting force of the first jack on the upper column beam is 0.7 to 0.8 times the dead load of the proposed extraction column. The dead load refers to the supporting force of the original proposed extraction column on the original floor beam. After tightening, tighten it with 6 M16 screws.
[0010] Step 3: Statically cut the concrete at the top of the column to be extracted; use a hole-drilling machine to make a series of holes at the location that needs to be cut, and finally statically cut off the target. The upper end of the hole needs to be leveled, and a portion of the lower end of the hole needs to be cut again.
[0011] Step 4: Load the original floor beams involved in the proposed extraction column with reverse top loading; the original floor beams involved in the proposed extraction column can be 2 or 3 spans, and 1 or 2 sets of column-holding beams are set on the top of the original column as reverse top fulcrums. The reverse top load is in accordance with the "Technical Specifications for Reinforcement of Existing Building Foundations" JGJ123-2000, page 79, 9.3.5~9.3.6. The maximum value of each jacking of the fourth section of the jacking project shall not exceed 10mm. The main consideration is the influence of the position sequence on the structure, and the jacking load is limited according to the allowable deformation of the structure of 0.003~0.005L. If the maximum spacing of the jacks is 1.2m, the allowable deformation of the structure is (0.003~0.005)x1200=3.6~6.0mm. It is divided into three times, single column synchronously, and two columns alternately. The original floor beams have been loaded before reinforcement and most of them have cracks. By means of the reverse top, the cracks in the original floor beams are reduced or even closed, and the original floor beams are made to produce a reverse arch to offset part of the load deflection of the original floor beams. The added solid components can also be stressed in time, thereby improving the stress performance of the original floor beam structure and increasing the bearing capacity of the original floor beams.
[0012] The upper column beam is loaded for the second time through the first jack. After the second loading (reverse top loading), the supporting force of the first jack on the upper column beam is 0.8 to 1 times of the dead load plus live load of the proposed column.
[0013] Step 5: After the column to be removed is cut off, H-shaped steel is installed between the upper end of the column to be removed and the original floor beam, and steel hoops are set on the reinforced beams and columns. Both ends of the H-shaped steel are welded to the steel hoops on the corresponding two reinforced beams and columns.
[0014] The steel-concrete composite beam structure is a structural system composed of steel and concrete, in which the steel is the core part. The concrete is restrained by stirrups and equipped with appropriate longitudinal main reinforcement and stirrups. A layer of reinforced concrete shell is poured outside the steel structure to prevent local deformation of the steel structure, enhance the overall stiffness of the steel, and enhance the durability and fire resistance of the structure. The steel-concrete composite beam gives full play to the dual advantages of high tensile strength of steel and high compressive strength of concrete. The main construction process is:
[0015] 1) Surface treatment of concrete in the steel hoop area: According to the requirements of the design drawings and combined with on-site measurement and positioning, place a large sample of the steel plate position on the surface of the concrete to be reinforced with steel, and grind it to expose the solid concrete stone and form a flat rough surface. Use a sharp chisel to lightly chisel the uneven surface, then use a wire brush to remove the loose materials on the surface, and finally rinse it with high-pressure water. After it is completely dry, wipe the surface with absorbent cotton dipped in acetone or blow it dry with oil-free high-pressure air.
[0016] 2) Drilling and embedding screws: According to the requirements of the design drawings and the position of the anchor bolt holes on the finished steel plate, mark the positions where holes need to be drilled, and use the reinforced concrete protective layer tester to check the concrete reinforcement layout to avoid hitting the reinforcement when drilling. The hole diameter and hole depth should be constructed strictly according to the design requirements, and the screws should be embedded after the holes are drilled.
[0017] 3) On-site die punching of the hoop steel plate and surface treatment of the steel plate bonding surface: Cut the steel plate according to the actual layout on the concrete on site, and perform die punching according to the screws embedded on site. Perform matching punching on the steel plates to be assembled, and then use a polishing grinder or wire brush grinder to remove rust and roughen the bonding surface of the steel plate. The grinding lines should be perpendicular to the force direction of the steel plate; wipe the surface of the steel plate clean with absorbent cotton dipped in acetone.
[0018] 4) Install the hoop steel plate: fix the steel plate on the screw and ensure that the gap between the steel plate and the concrete surface is more than 3mm to ensure the thickness of the injection glue layer; the adjacent steel plates are treated by gas shielded welding and full welding.
[0019] 5) H-beam installation.
[0020] 6) Use steel clamps for sealing: stick the injection nozzle to the injection hole at the bottom of the steel plate (two symmetrical ones), insert the exhaust pipe at the corners and edges of the steel plate, with a spacing of 30 to 40 cm between the exhaust holes, seal around the screw with steel glue, and then seal the top and bottom of the steel plate with sealing glue.
[0021] 7) Pouring structural adhesive: After the edge sealing adhesive is cured, use a pump to pour the steel bonding adhesive from the injection nozzle into the gap between the steel plate and the concrete. The pouring work continues until the adhesive flows out of all exhaust pipes. During the pouring process, use a rubber hammer to knock on the steel plate to confirm whether it is poured densely.
[0022] 8) Both ends of the H-shaped steel are fixed on the steel clamps on the corresponding two reinforced beam columns.
[0023] Step 6: Use the second jack to preload the H-beam mid-span (i.e. the third loading), and set a tight iron plate between the H-beam and the bottom of the original floor beam;
[0024] After all the steel sections and support clamps are welded, and the glue poured into the steel clamps is cured for 3 days, the third loading is carried out at 1 / 1000 to 2 / 1000 of the mid-span of the steel beam, causing the newly added steel sections at the bottom of the beam to deform slightly, and then it is plugged with iron plates, and then the second jack is taken out. After three loadings, the deflection of the long-span beam after the support beam is removed is effectively reduced, the stress hysteresis effect of the new and old concrete is avoided, and the integral force of the reinforced body is ensured.
[0025] The mid-span portion of the H-shaped steel is fixed on an inverted steel clamp, on which a pair of symmetrically arranged second jacks are fixed, and the other ends of the second jacks are pressed against the bottom surface of the original floor beam.
[0026] The width of the H-beam being pushed down in the middle of the span is 1 / 1000 to 2 / 1000 of the total length of the H-beam.
[0027] Step 7: Tie the original floor beams and newly added H-shaped steel bars as a whole and pour high-strength, non-shrinkage, self-leveling special concrete;
[0028] Step 8: After the concrete strength of the preloaded steel-concrete transfer beam formed after the casting of the original floor beams and H-shaped steel reaches the design value, unload in stages.
[0029] After the reinforced beam reaches the set strength, remove the support of the first jack on the upper column beam, and then remove the supporting steel pipes, etc.; remove the remaining part of the column to be removed by static cutting.
[0030] H-beam installation: To ensure the safe construction of the column replacement with steel beam, the column, beam and plate replacement support construction should be carried out safely and reliably before the concrete is chiseled out and poured. Construction process: H-beam is processed and spliced, placed in the designated position → erecting construction scaffolding and floor support scaffolding → marking the lower column beam, determining the position of the steel bar, installing the support plate and steel hoop → drilling the screw hole for fixing the H-beam at the bottom of the original floor beam → fitting the screw hole → fixing the fitting on the upper surface of the H-beam → setting up temporary steel bracket → lifting the entire H-beam and placing it on the steel bracket → implanting, installing, supporting the formwork, pouring and curing the steel bar for the column beam → installing the supporting steel pipe, jack, axial force meter and tightening → applying prestress → static cutting of the intended column → installing the longitudinal and transverse H-beam → after the H-beam is pushed down 1 / 1000-2 / 1000 in the middle of the span, the iron plate is tightened (spacing 800) → implanting the screw to fix the H-beam.
[0031] The outstanding effects of the present invention are:
[0032] Through the reverse loading of the upper column beam, the lower column beam, the first jack, the supporting steel pipe, etc., the original floor beam produces a certain amount of reverse arch; after the H-shaped steel and the steel hoop on the reinforced beam column are welded, the secondary loading is carried out at the mid-span position between the original floor beam and the H-shaped steel, causing the newly added H-shaped steel at the bottom of the beam to deform slightly, and then it is tightened with an iron plate. After three loadings, the deflection of the large-span beam after the support beam is removed from the column is greatly reduced, avoiding the stress hysteresis effect of the new and old concrete, and ensuring that the reinforced body is subjected to the force as a whole. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the assembly of the original floor beam, structural column and H-beam of the present invention;
[0034] Figure 2 for Figure 1 Schematic diagram of the structure of the middle B part;
[0035] Figure 3 for Figure 2 Schematic diagram of the structure of part C;
[0036] Figure 4 for Figure 1 Schematic diagram of the structure of the D part in the middle;
[0037] Figure 5 for Figure 1 The cross-sectional view of EE in FIG.
[0038] Figure 6 It is a schematic diagram of the assembly of the upper column beam, the lower column beam, etc. of the present invention;
[0039] Figure 7 for Figure 6 A partial enlarged view of A.
[0040] Figure numerals: 11. Original floor beam; 12. Reinforced beam-column; 13. Proposed extraction column; 14. Second-floor structural column; 21. Lower column-embracing beam; 22. Upper column-embracing beam; 23. First steel plate; 24. Second steel plate; 25. Supporting steel pipe; 26. Flange chassis; 27. First jack; 28. Digital axial force meter; 29. H-shaped steel; 30. Steel hoop; 31. Second jack; 32. Anti-top steel clamp; 33. Steel corbel; 34. New stirrups; 35. Special concrete; 36. M16 screw; 37. Tightening iron plate; 38. New longitudinal reinforcement. DETAILED DESCRIPTION
[0041] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0042] The following references Figures 1 to 7 The present invention is described:
[0043] The original building structure includes the original floor beam 11 at the top of the first floor and the first floor structural columns used to support the original floor beam. The first floor structural columns are later divided into reinforced beam columns 12 and proposed withdrawn columns 13. 2-3 proposed withdrawn columns are arranged between two adjacent reinforced beam columns 12. The original floor beam 11 is provided with second-floor structural columns 14. The second-floor structural columns 14 are arranged one-to-one with the first-floor structural columns and are located directly above the first-floor structural columns.
[0044] A construction method for a preloaded steel-concrete transfer beam comprises the following steps:
[0045] Step 1: In order to make the new and old concrete bear the force synergistically, the internal force and stress of the reinforced beam-column structure system should be reinforced when the stress is low (or even zero stress). This project adopts full-span support unloading to ensure the effectiveness of reinforcement and the safety of the construction process; within the 1 / 2 beam span of the planned column 13, the scaffolding steel pipe top-supporting screw rod is used to support the second floor slab in this range, and the dead weight falls directly to the ground; the screw rod rotates on the scaffolding steel pipe to adjust the height of the screw rod, thereby supporting the second floor slab;
[0046] Step 2: A lower column beam 21 is arranged on the intended extraction column 13, and an upper column beam 22 is arranged on the second-story structural column 14 above the intended extraction column 13. The lower column beam 21 supports the upper column beam 22 through four groups of supporting steel pipes 25, the first jack 27 and the digital axial force meter 28;
[0047] Specifically, the first steel plate 23 is embedded at the four corners of the upper end of the lower column beam 21, and the second steel plate 24 is embedded at the four corners of the lower end of the upper column beam 22; the lower end of the support steel pipe 25 is welded to the first steel plate 23, and a flange chassis 26 is fixed to the top of the support steel pipe 25. The first jack 27 and the digital axial force meter 28 are arranged between the flange chassis 26 and the second steel plate 24, and a linen cloth is clamped between the first jack 27 and the digital axial force meter 28. The digital axial force meter can clearly show the size of the support force of the first jack on the upper column beam. The support force of the first jack 27 on the upper column beam 22 is 0.7 to 0.8 times the dead load of the proposed extraction column. The dead load refers to the support force of the original proposed extraction column on the original floor beam. After tightening, use 6 M16 screws 36 to tighten.
[0048] Step 3: statically cut the top concrete of the intended extraction column 13; use a hole-drilling machine to punch a series of holes at the location that needs to be cut, and finally statically cut off the target. The upper end of the hole needs to be flushed, and the lower end of the hole needs to be cut again.
[0049] Step 4: Load the original floor beams involved in the proposed extraction column with reverse top loading; the original floor beams involved in the proposed extraction column can be 2 or 3 spans, and 1 or 2 sets of column-holding beams are set on the top of the original column as reverse top fulcrums. The reverse top load is in accordance with the "Technical Specifications for Reinforcement of Existing Building Foundations" JGJ123-2000, page 79, 9.3.5~9.3.6. The maximum value of each jacking of the fourth section of the jacking project shall not exceed 10mm. The main consideration is the influence of the position sequence on the structure, and the jacking load is limited according to the allowable deformation of the structure of 0.003~0.005L. If the maximum spacing of the jacks is 1.2m, the allowable deformation of the structure is (0.003~0.005)x1200=3.6~6.0mm. It is divided into three times, single column synchronously, and two columns alternately. The original floor beams have been loaded before reinforcement and most of them have cracks. By means of the reverse top, the cracks in the original floor beams are reduced or even closed, and the original floor beams are made to produce a reverse arch to offset part of the load deflection of the original floor beams. The added solid components can also be stressed in time, thereby improving the stress performance of the original floor beam structure and increasing the bearing capacity of the original floor beams.
[0050] The upper column beam 22 is loaded for the second time by the first jack 27. After the second loading (i.e., reverse loading), the supporting force of the first jack 27 on the upper column beam 22 is 0.8 to 1 times of the planned column dead load plus the live load.
[0051] Step 5: After the proposed column 13 is cut off, an H-shaped steel 29 is installed between the upper end of the proposed column 13 and the original floor beam 11, and a steel clamp 30 is set on the reinforced beam column 12. Both ends of the H-shaped steel 29 are welded to the steel clamps 30 on the corresponding two reinforced beam columns 12.
[0052] The steel-concrete composite beam structure is a structural system composed of steel and concrete, in which the steel is the core part. The concrete is restrained by stirrups and equipped with appropriate longitudinal main reinforcement and stirrups. A layer of reinforced concrete shell is poured outside the steel structure to prevent local deformation of the steel structure, enhance the overall stiffness of the steel, and enhance the durability and fire resistance of the structure. The steel-concrete composite beam gives full play to the dual advantages of high tensile strength of steel and high compressive strength of concrete. The main construction process is:
[0053] 1) Surface treatment of concrete in the steel hoop area: According to the requirements of the design drawings and combined with on-site measurement and positioning, place a large sample of the steel plate position on the surface of the concrete to be reinforced with steel, and grind it to expose the solid concrete stone and form a flat rough surface. Use a sharp chisel to lightly chisel the uneven surface, then use a wire brush to remove the loose materials on the surface, and finally rinse it with high-pressure water. After it is completely dry, wipe the surface with absorbent cotton dipped in acetone or blow it dry with oil-free high-pressure air.
[0054] 2) Drilling and embedding screws: According to the requirements of the design drawings and the position of the anchor bolt holes on the finished steel plate, mark the positions where holes need to be drilled, and use the reinforced concrete protective layer tester to check the concrete reinforcement layout to avoid hitting the reinforcement when drilling. The hole diameter and hole depth should be constructed strictly according to the design requirements, and the screws should be embedded after the holes are drilled.
[0055] 3) On-site die punching of the hoop steel plate and surface treatment of the steel plate bonding surface: Cut the steel plate according to the actual layout on the concrete on site, and perform die punching according to the screws embedded on site. Perform matching punching on the steel plates to be assembled, and then use a polishing grinder or wire brush grinder to remove rust and roughen the bonding surface of the steel plate. The grinding lines should be perpendicular to the force direction of the steel plate; wipe the surface of the steel plate clean with absorbent cotton dipped in acetone.
[0056] 4) Install the hoop steel plate: fix the steel plate on the screw and ensure that the gap between the steel plate and the concrete surface is more than 3mm to ensure the thickness of the injection glue layer; the adjacent steel plates are treated by gas shielded welding and full welding.
[0057] 5) H-beam installation.
[0058] 6) Use steel clamps for sealing: stick the injection nozzle to the injection hole at the bottom of the steel plate (two symmetrical ones), insert the exhaust pipe at the corners and edges of the steel plate, with a spacing of 30 to 40 cm between the exhaust holes, seal around the screw with steel glue, and then seal the top and bottom of the steel plate with sealing glue.
[0059] 7) Pouring structural adhesive: After the edge sealing adhesive is cured, use a pump to pour the steel bonding adhesive from the injection nozzle into the gap between the steel plate and the concrete. The pouring work continues until the adhesive flows out of all exhaust pipes. During the pouring process, use a rubber hammer to knock on the steel plate to confirm whether it is poured densely.
[0060] 8) Both ends of the H-shaped steel are fixed on the steel clamps 30 on the corresponding two reinforced beam columns 12.
[0061] Step 6: Preload the H-shaped steel 29 in the middle of the span by the second jack 31 (i.e., the third loading), and set a plugging iron plate 37 between the H-shaped steel 29 and the bottom of the original floor beam 11;
[0062] After all the steel sections and support clamps are welded, and the glue poured into the steel clamps is cured for 3 days, the third loading is carried out at 1 / 1000 to 2 / 1000 of the mid-span of the steel beam, causing the newly added steel sections at the bottom of the beam to deform slightly, and then it is plugged with iron plates, and then the second jack is taken out. After three loadings, the deflection of the long-span beam after the support beam is removed is effectively reduced, the stress hysteresis effect of the new and old concrete is avoided, and the integral force of the reinforced body is ensured.
[0063] The mid-span portion of the H-shaped steel 29 is fixed on an inverted steel fixture 32, on which a pair of symmetrically arranged second jacks 31 are fixed, and the other ends of the second jacks 31 are pressed against the bottom surface of the original floor beam.
[0064] The width of the H-shaped steel 29 being pushed down in the middle of the span is 1 / 1000 to 2 / 1000 of the total length of the H-shaped steel 29.
[0065] Step 7: Tie the original floor beam 11 and the newly added H-shaped steel 29 with steel bars and pour high-strength, non-shrinkage, self-leveling special concrete;
[0066] Step 8: After the concrete strength of the preloaded steel-concrete transfer beam formed by pouring the original floor beam 11 and H-shaped steel 29 reaches the design value, it is unloaded in stages.
[0067] After the reinforced beam reaches the set strength, remove the support of the first jack on the upper column beam, and then remove the supporting steel pipes, etc.; remove the remaining part of the column to be removed by static cutting.
[0068] H-beam installation: To ensure the safe construction of the column replacement with steel beam, the column, beam and plate replacement support construction should be carried out safely and reliably before the concrete is chiseled out and poured. Construction process: H-beam is processed and spliced, placed in the designated position → erecting construction scaffolding and floor support scaffolding → marking the lower column beam, determining the position of the steel bar, installing the support plate and steel hoop → drilling the screw hole for fixing the H-beam at the bottom of the original floor beam → fitting the screw hole → fixing the fitting on the upper surface of the H-beam → setting up temporary steel bracket 33 → lifting the entire H-beam and placing it on the steel bracket → implanting, installing, supporting the formwork, pouring and curing the steel bar for the column beam → installing the supporting steel pipe, jack, axial force meter and tightening → applying prestress → static cutting of the intended column → installing the longitudinal and transverse H-beam → after the H-beam is pushed down 1 / 1000-2 / 1000 in the middle of the span, the iron plate is tightened (spacing 800) → implanting the screw to fix the H-beam.
[0069] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications of the above assumptions should also be regarded as the scope of protection of the present invention.
Claims
1. A construction method for a preloaded steel-concrete transfer beam, characterized in that: The following steps are involved: Step 1: In the range of 1 / 2 of the beam span to be expanded outside the planned column, use scaffolding steel pipe top support screw rods to support the second floor slab in this range; Step 2: a lower column-holding beam (21) is arranged on the intended extraction column (13), an upper column-holding beam (22) is arranged on the second-story structural column (14) above the intended extraction column (13), and the lower column-holding beam (21) supports the upper column-holding beam (22) via four sets of supporting steel pipes (25), a first jack (27) and a digital axial force meter (28); Step 3: statically cut the top concrete of the proposed extraction column (13); Step 4: Carry out reverse top loading on the original floor beam section involved in the proposed extraction column; Step 5: After the proposed extraction column (13) is cut off, an H-shaped steel (29) is installed between the upper end of the proposed extraction column (13) and the original floor beam (11), a steel clamp (30) is arranged on the reinforced beam column (12), and both ends of the H-shaped steel (29) are welded to the steel clamps (30) on the corresponding two reinforced beam columns (12); Step 6: Preload the mid-span of the H-shaped steel (29) by using the second jack (31), and set a tightening iron plate (37) between the H-shaped steel (29) and the bottom of the original floor beam (11); Step 7: The original floor beam (11) and the newly added H-shaped steel (29) are integrally tied with steel bars and poured with high-strength, non-shrinkage, self-leveling special concrete; Step 8: After the concrete strength of the preloaded steel-concrete transfer beam formed by pouring the original floor beam (11) and the H-shaped steel (29) reaches the design value, unloading is performed in stages; In the second step, a first steel plate (23) is embedded at the four corners of the upper end of the lower column beam (21), and a second steel plate (24) is embedded at the four corners of the lower end of the upper column beam (22); the lower end of the support steel pipe (25) is welded to the first steel plate (23), a flange chassis (26) is fixed to the top of the support steel pipe (25), a first jack (27) and a digital axial force meter (28) are arranged between the flange chassis (26) and the second steel plate (24), and a linen cloth is sandwiched between the first jack (27) and the digital axial force meter (28); In the third step, a series of holes are punched at the locations on the proposed extraction column (13) that need to be cut using a hole punching machine, thereby cutting off the connection between the proposed extraction column (13) and the original floor beam (11); In the fourth step, the upper column beam (22) is subjected to secondary loading by the first jack (27). After the secondary loading, the supporting force of the first jack (27) on the upper column beam (22) is 0.8 to 1 times the planned column dead load plus the live load.
2. The construction method of a preloaded steel-concrete transfer beam according to claim 1, characterized in that: In the second step, the supporting force of the first jack (27) on the upper column beam (22) is 0.7 to 0.8 times the dead load of the column to be extracted.
3. The construction method of a preloaded steel-concrete transfer beam according to claim 1, characterized in that: In the sixth step, the width of the H-shaped steel (29) being pushed down in the mid-span is 1 / 1000 to 2 / 1000 of the total length of the H-shaped steel (29).