Composite reinforcing structure suitable for expressway in permafrost region and construction method
Through the design of the inverted "T" heat pipe and the control of the rock layer, the problem of uneven cooling of the heat pipes and the difficulty of automatic detection on highways in frozen soil areas has been solved, achieving a more uniform cooling effect and automatic detection, and enhancing the stability of the roadbed. and security.
Patent Information
- Application Number
- CN202411091881.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-11
AI Technical Summary
In highways in permafrost areas, the cooling effect of existing heat pipes is uneven, resulting in uneven deformation and longitudinal cracks in the roadbed. Moreover, the automatic detection of heat pipes is difficult and affects normal work.
An inverted "T" heat pipe design is used to extend the evaporation section to both sides of the roadbed at a nearly horizontal angle, and a working condition detection device is installed in the condensation section, combined with the stone layer to control the sun slope effect, to achieve uniform cooling and automatic detection.
It significantly improves the uniformity and range of the cooling effect, avoids uneven deformation and longitudinal cracks of the roadbed, realizes automated detection of heat pipe working conditions, and reduces construction costs.
Smart Images

Figure CN118756532A_ABST
Abstract
Description
Technical field:
[0001] The invention belongs to the field of frozen soil roadbed reinforcement, and in particular relates to a composite reinforcement structure suitable for highways in permafrost areas and a construction method. Background technology:
[0002] Frozen soil refers to all kinds of rock and soil with a temperature below 0℃ and containing ice. It is usually divided into three types: short-term frozen soil, seasonal frozen soil and permafrost. Frozen soil is widely distributed in the world. Permafrost is mainly distributed in high-latitude areas and around the Arctic. my country is the third largest country in the world in terms of frozen soil area, with frozen soil area accounting for about 22.4% of the country's land area. Among them, the Qinghai-Tibet Plateau is the largest area of permafrost in my country, accounting for about 70% of the total permafrost area in the country. Due to its ice-containing characteristics and thermal sensitivity, permafrost is prone to frost heave and thaw settlement when the climate and environment change, causing uneven deformation, longitudinal waves, longitudinal cracks and other diseases on the road, which seriously threatens the long-term safety and stability of road projects. At present, the global temperature is gradually rising, and the permafrost is accelerating its degradation. The SPOCC report released in 2019 predicts that by 2100, the near-surface permafrost may decrease by 69±20% due to climate change. The degradation of permafrost will inevitably lead to a continuous decrease in the upper limit of permafrost, thereby exacerbating the degree of roadbed diseases.
[0003] In order to ensure the stability of permafrost and reduce roadbed diseases, my country has proposed the design concept of "active cooling roadbed" and taken a series of effective measures, such as block stone roadbed, ventilation pipe roadbed, heat pipe, awning, block gravel ventilation composite roadbed, etc., and successfully applied them in the construction of Qinghai-Tibet Railway and Qinghai-Tibet Highway. Among them, heat pipe is an efficient active cooling measure, which can quickly reduce the temperature of the soil near it, thereby achieving a cooling effect. However, in actual use, heat pipe will cause uneven deformation of the roadbed, longitudinal cracks and other diseases. At present, the heat pipes generally used in frozen soil roadbeds are straight-insertion heat pipes and L-shaped oblique-insertion heat pipes. Due to the limitation of their shape, these two types of heat pipes cannot evenly reduce the temperature of the soil under the roadbed. The soil close to the heat pipe cools down relatively quickly and with a large cooling range, while the soil far from the heat pipe cools down relatively slowly and with a relatively small cooling range. This can easily lead to uneven temperature field distribution of the soil under the roadbed, resulting in uneven deformation of the roadbed and the generation of longitudinal cracks. Therefore, providing an engineering measure with uniform and smooth cooling effect is an engineering problem that needs to be solved at present.
[0004] A heat pipe is a heat transfer system with countercurrent circulation of vapor and liquid. The evaporation section is filled with a low-boiling-point working fluid. In winter or at night when the outside ambient temperature is lower than the soil at the bottom of the roadbed, the heat pipe starts working, and the low-boiling-point working fluid absorbs heat to the boiling point and evaporates into gas. Under the action of the pressure difference, the steam rises along the wall of the evaporation section to the condensation section, contacts the colder wall of the pipe, releases latent heat of vaporization, and condenses into liquid. Due to the action of gravity, the low-boiling-point working fluid flows back to the evaporation section along the wall of the condensation section to absorb heat and evaporate again, and this cycle repeats. During long-term use, heat pipes may leak working fluid, accumulate non-condensable gases on the upper part, and may be damaged during installation and transportation. These will affect the normal operation of the heat pipe. Usually, the working condition detection of heat pipes requires inspection personnel to collect inspection data in the low temperature environment of winter or night when the heat pipes work. The detection is difficult and the efficiency is low. Therefore, automated detection of heat pipes can not only improve detection efficiency, but also reduce the consumption of human resources. Summary of the invention:
[0005] The purpose of the invention is to: in view of the large scale of wide highways, the strong heat absorption of asphalt pavements, the current problem of accelerated permafrost degradation caused by global temperature rise, and the current situation that conventional roadbed cooling measures are not ideal, the present invention proposes a composite structure and construction method suitable for highways with more significant cooling effect. Through the inverted "T" design of the two-way bending section of the heat pipe, the evaporation section of the heat pipe can extend from the middle to both sides of the roadbed at an angle close to the horizontal, thereby achieving balanced and smooth cooling of the soil under the roadbed, and a working condition detection device is installed on the condensation section of the heat pipe to realize automatic detection of the working condition of the heat pipe, so that it can efficiently and quickly determine whether the heat pipe is in a normal working state. At the same time, by laying block stone layers of different thicknesses on the roadbed slope, the yin and yang slope effects caused by the difference in solar radiation on both sides of the highway are effectively regulated, thereby enhancing the safety and stability of the roadbed of wide high-grade highways in permafrost areas.
[0006] In order to achieve the above object, the technical solution of the present invention is as follows:
[0007] A composite reinforced structure and construction method suitable for highways in permafrost areas, characterized in that the roadbed structure 1 is provided with a block stone layer 2, a roadbed fill layer 3, and a pavement structure layer 5 in order from bottom to top, and an XPS insulation board 4 is arranged in the roadbed fill layer 3 in the roadbed structure 1; an inverted "T"-shaped heat pipe 6 is arranged on the top surface of the roadbed structure 1, and the inverted "T"-shaped heat pipe 6 adopts a two-way bending section design and is installed in the central isolation belt 9 of the road surface and arranged along the direction of the highway, the bending point of the lower end of the inverted "T"-shaped heat pipe 6 is located in the active layer below the roadbed structure 1, and the end of the bottom bend of the inverted "T"-shaped heat pipe 6 is located near the upper limit of permafrost; the sunny side and the shady slope of the roadbed structure 1 are respectively provided with shady slope block stone slope protection 7 and sunny slope block stone slope protection 8.
[0008] Preferably, the roadbed structure 1 has a slope ratio of 1:1.5.
[0009] Preferably, the particle size of the piece stone layer 2 is 15cm to 30cm, and the thickness is 1.5m.
[0010] Preferably, the block stones used in the sunny slope block stone slope protection 8 of the roadbed structure 1 have a particle size of 15cm-25cm and a laying thickness of 1.6m; the block stones used in the shady slope block stone slope protection 7 of the roadbed structure 1 have a particle size of 15cm-25cm and a laying thickness of 0.8m.
[0011] Preferably, the XPS insulation board 4 is made of polystyrene resin as a main raw material.
[0012] Preferably, the inverted "T"-shaped heat pipe 6 is divided into a condensation section 62 and an evaporation section 61. The length of the heat pipe condensation section is not less than 8m, and the length of the evaporation section is 8m to 15m. The bent end of the bottom of the heat pipe is located near the upper limit of permafrost. The acute angle between the evaporation section 61 of the inverted "T"-shaped heat pipe 6 and the horizontal plane is 3° to 5°; the inverted "T"-shaped heat pipe 6 is arranged in the central isolation section 9 of the road surface, and the arrangement spacing is 3m to 4m.
[0013] Preferably, the evaporation section 61 is filled with a low-boiling-point working fluid, which absorbs heat to reach the boiling point and evaporates into gas. Under the action of the air pressure difference, the steam rises along the tube wall of the evaporation section 61 to the condensation section 62, contacts the colder tube wall to release latent heat of vaporization, and condenses into liquid. Due to the action of gravity, the low-boiling-point working fluid flows back to the evaporation section 61 along the tube wall of the condensation section 62 to absorb heat and evaporate again, and the cycle repeats.
[0014] The above-mentioned composite reinforcement structure and construction method applicable to highways in permafrost areas are as follows:
[0015] Step 1: Level the natural foundation on the highway design route.
[0016] Step 2: dig a pre-buried groove for the inverted "T"-shaped heat pipe 6 from the center of the foundation downward on the leveled natural foundation, with an excavation width of 0.5m, a horizontal excavation length of 15m, and a vertical excavation depth of 3m. Bury the inverted "T"-shaped heat pipe 6 in the pre-buried groove. After the burial is completed, backfill the pre-buried groove with fine sand and lightly compact it.
[0017] Step 3: Lay a stone layer 3 on the natural foundation after the inverted "T"-shaped heat pipe 6 is pre-buried, with a designed thickness of 1.5m and a stone particle size of 15cm to 30cm; lay a roadbed fill layer 3 on the top of the stone layer 3; lay the XPS insulation board 4 flatly in the middle of the roadbed fill layer 3, and finally lay the pavement structure layer 5 on the top of the roadbed fill layer 3, and compact it lightly for multiple times.
[0018] Step 4: Lay the sunny slope block stone slope protection 8 on the sunny slope of the roadbed structure 1, with the block stone particle size of 15cm~25cm and the laying thickness of 1.6m; finally, lay the shady slope block stone slope protection 7 on the shady slope of the roadbed structure 1, with the block stone particle size of 15cm~25cm and the laying thickness of 0.8m, and the sunny slope block stone slope protection 8 and the shady slope block stone slope protection 7 are interconnected with the block stone layer 3, and the entire roadbed structure forms an integral block stone structure layer.
[0019] Compared with the existing technologies and measures, the present invention has the following beneficial effects:
[0020] 1. The cooling effect is significantly improved, and the cooling range is significantly increased.
[0021] In view of the strong heat absorption of asphalt pavements of high-grade wide highways and the accelerated degradation of frozen soil due to rising global temperatures, the composite structure of the frozen soil roadbed of the present invention combines three active cooling measures: heat pipes, crushed stones, and insulation boards. In winter, when the soil temperature is higher than the outside temperature, the temperature of the evaporation section at the bottom of the heat pipe is higher than the temperature of the upper condensation section, and the heat pipe begins to work effectively, absorbing heat through the evaporation section, thereby reducing the soil temperature around the heat pipe. At the same time, high-density cold air enters the soil along the crushed stone layers on both sides of the roadbed under the action of gravity, absorbs and takes away the heat in the soil, and releases it into the air, achieving a double cooling effect, ensuring that the roadbed can have sufficient cold storage capacity in winter; in the warm season, when the outside temperature is higher than the soil temperature, the insulation board can effectively isolate the external heat A large amount of heat enters the interior of the roadbed. At the same time, when the surface of the block gravel layer is heated in the warm season, the hot air rises, thereby reducing the heat input to a certain extent. In addition, the cold air preserved under the block stone layer at the bottom of the roadbed in winter can maintain the temperature of the lower part of the roadbed at a relatively low level. The present invention fully utilizes the cooling efficiency of the three major measures of heat pipes, block gravel and insulation boards with the design concept of cooling in cold seasons and heat insulation in warm seasons, thereby significantly improving the cooling effect of the present invention. At the same time, through the inverted "T" design of the two-way bending of the heat pipe, the cooling range is significantly increased. The evaporation section of the heat pipe at the lower part of the roadbed can cover the entire range of the horizontal projection of the road surface, thereby effectively alleviating the phenomenon of heat accumulation in the central area of the roadbed due to the heat accumulation effect at the lower part of the highway roadbed.
[0022] 2. The cooling effect is smoother and more uniform
[0023] The design of the bidirectional bending section of the heat pipe allows the evaporation section of the heat pipe to extend from the middle of the roadbed to both sides of the roadbed at a nearly horizontal angle. Compared with ordinary L-shaped heat pipes, the cooling range is larger, more uniform and smoother, avoiding the uneven distribution of the temperature field in the lower part of the roadbed and the mechanical properties of the roadbed caused by the uneven cooling range of the L-shaped heat pipe, thereby effectively suppressing the occurrence of roadbed longitudinal cracks, uneven settlement and other diseases.
[0024] 3. Realized automatic detection of heat pipe working conditions
[0025] When the heat pipe is working, the low-boiling-point working fluid in the evaporation section absorbs heat and becomes steam. After encountering the colder pipe wall above, it releases heat and condenses into liquid and refluxes. As the steam continues to rise, the steam becomes less and less, and the heat released during condensation also becomes less and less, which will cause a temperature difference between the upper and lower sections of the condensation section. The present invention arranges infrared thermometers at different positions of the heat pipe condensation section, so as to automatically detect the pipe wall temperature of the heat pipe condensation section at different positions, and at the same time, the detection data can be transmitted to the data storage device through the cable. Finally, according to the measured pipe wall temperatures at the upper and lower positions of the condensation section, it is detected whether the heat pipe is in a normal working state.
[0026] 4. The roadbed construction cost is more economical
[0027] The present invention improves the convective heat exchange efficiency between the block stone layer and the air near the sunny slope by laying a thicker block stone layer on the sunny slope of the roadbed, enhances the cooling effect of the block stone layer on the sunny slope of the roadbed, effectively limits the increase in the temperature of the sunny slope of the roadbed, and makes the temperature field distribution of the roadbed more uniform. The block stone raw materials are cheap, and the transportation and construction are convenient. While solving the yin and yang slope effect caused by the difference in solar radiation on both sides of the roadbed, more costs can be saved. In addition, the inverted "T"-shaped heat pipe with a two-way bending section design adopted by the present invention only needs to arrange one heat pipe in the center of the road surface in the same horizontal direction to achieve the cooling effect on both sides of the roadbed. Compared with ordinary L-shaped oblique heat pipes and ordinary straight-insertion heat pipes, which need to arrange multiple heat pipes to achieve the cooling effect on both sides of the roadbed, the cost is greatly saved, thereby making the roadbed construction of the present invention more economical and ensuring a good cooling effect. Description of the drawings:
[0029] Figure 1 The present invention is a structural schematic diagram of a composite reinforcement structure and a construction method suitable for highways in permafrost areas.
[0030] Figure 2 It is a schematic diagram of the structure of the inverted "T"-shaped heat pipe.
[0031] Figure 3 It is a three-dimensional schematic diagram of the arrangement of the inverted "T"-shaped heat pipes along the road.
[0032] Figure 4 The present invention is a top view of the composite reinforcement structure and construction method suitable for highways in permafrost areas.
[0033] Figure 5 The present invention is a cross-sectional view along the center line of the pavement of a composite reinforcement structure and construction method suitable for highways in permafrost regions.
[0034] Figure 6 It is a schematic diagram of the structure of the inverted “T” type heat pipe condensation section detection device. Specific implementation method:
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the composite reinforcement structure of the highway in the permafrost region in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] The embodiment of the present invention provides a composite reinforcement structure and construction method suitable for highways in permafrost areas. With the design concept of "active cooling of roadbed", three measures of heat pipes, block crushed stone and insulation board are combined to actively cool the soil at the bottom of the roadbed of highways in permafrost areas to prevent permafrost degradation; prevent uneven temperature field distribution caused by uneven cooling range of conventional heat pipes; prevent "heat concentration effect" formed in the middle of the roadbed due to excessive roadbed width; prevent "yin and yang slope effect" caused by differences in solar radiation; thereby effectively avoiding uneven deformation of the roadbed caused by degradation of the lower frozen soil during operation, and ensuring the long-term stability and safety of the roadbed. The present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0037] like Figure 1 As shown, a composite reinforcement structure and construction method suitable for highways in permafrost areas are characterized in that: the active cooling composite reinforcement measures of the present invention include a roadbed 1, and the roadbed 1 is sequentially arranged from bottom to top with a piece stone layer 2, a roadbed fill layer 3, and a pavement structure layer 5; an XPS insulation board 4 is arranged in the roadbed fill layer 3; an inverted "T"-shaped heat pipe 6 is arranged on the top surface of the roadbed structure 1; the sunny side and the shady slope of the roadbed 1 are respectively provided with sunny slope block stone slope protection 8 and shady slope block stone slope protection 7.
[0038] like Figure 1 The slope ratio of the roadbed of the highway of the present invention is shown to be 1:1.5, and the road surface width is 26m.
[0039] like Figure 1 As shown, the inverted "T"-shaped heat pipe 6 of the present invention is installed in the central isolation zone 9 of the road surface. The inverted "T"-shaped heat pipe adopts an inverted "T"-shaped design with a bidirectional bending section. The bending point of the lower end of the inverted "T"-shaped heat pipe 6 is located in the active layer below the roadbed structure 1, and the end of the bottom bend of the inverted "T"-shaped heat pipe 6 is located near the upper limit of permafrost; the inverted "T"-shaped heat pipe 6 is divided into a condensation section 62 and an evaporation section 61. The length of the heat pipe condensation section is not less than 8m, and the length of the evaporation section is 8m-15m. The acute angle between the evaporation section 61 of the inverted "T"-shaped heat pipe 6 and the horizontal plane is 3°-5°. The evaporation section 61 is filled with a low-boiling-point working medium. The low-boiling-point working medium absorbs heat to reach the boiling point and evaporates into gas. Under the action of the air pressure difference, the steam rises along the tube wall of the evaporation section 61 to the condensation section 62, contacts with the colder tube wall to release latent heat of vaporization, condenses into liquid, and flows back to the evaporation section 61 along the tube wall of the condensation section 62 due to gravity, and then absorbs heat and evaporates.
[0040] like Figure 1 As shown, the XPS insulation board 4 of the present invention is made of polystyrene resin as the main raw material and has a thickness of 5 cm to 10 cm.
[0041] like Figure 1As shown, the block stone particle size used in the sunny slope block stone slope protection 8 of the roadbed structure 1 of the present invention is 15cm~25cm, and the laying thickness is 1.6m. The block stone particle size used in the shady slope block stone slope protection 7 is 15cm~25cm, and the laying thickness is 0.8m. The sunny slope block stone slope protection 8 and the shady slope block stone slope protection 7 are interconnected with the block stone layer 3, and the entire roadbed structure forms an asymmetric "U"-shaped integral block stone structure layer.
[0042] The present invention provides a composite reinforcement structure and a construction method suitable for highways in permafrost areas, which mainly include the following construction steps:
[0043] (1) Level the natural foundation along the designed highway route.
[0044] (2) According to the designed roadbed depth and roadbed width, a trench is excavated on the natural foundation. The excavation width is 0.5m, the horizontal excavation length is 15m, and the vertical excavation depth is 2m.
[0045] (3) Use lifting equipment to lift the inverted "T"-shaped heat pipe 6 into the trench, place it steadily, backfill with fine sand, and compact it lightly.
[0046] (4) Fill the 1.5m thick block stone layer 3, roadbed fill layer 3, XPS insulation board 4, and pavement structure layer 5 in sequence and compact them lightly several times.
[0047] (5) According to the engineering construction specifications, a 0.8m thick block stone slope protection is laid on the shady slope of the roadbed structure 1, and a 1.6m thick block stone slope protection is laid on the sunny slope of the roadbed.
[0048] Note 1: When lightly compacting the soil near the inverted "T"-shaped heat pipe 6, a small tamping machine is required and a high number of light strikes are performed to avoid damage to the inverted "T"-shaped heat pipe 6 due to excessive compaction.
[0049] Matters not covered by the present invention are known technologies. The above embodiments are only for illustrating the technical concept and features of the present invention. The purpose is to enable people familiar with this technology to understand the contents of the present invention and implement them accordingly. It cannot be used to limit the protection scope of the present invention. Any equivalent changes or modifications made according to the spirit of the present invention should be included in the protection scope of the present invention.
Claims
1. A composite reinforcement structure and construction method suitable for highways in permafrost areas, belonging to the field of frozen soil roadbed reinforcement, characterized in that: The invention comprises a roadbed structure (1) above the ground, characterized in that: the roadbed structure (1) is provided with a block stone layer (2), a roadbed fill layer (3), and a road surface structure layer (5) in order from bottom to top; a shady slope block stone slope protection (7) and a sunny slope block stone slope protection (8) are provided on both sides of the roadbed structure (1); an inverted "T"-shaped heat pipe (6) is provided on the top of the roadbed structure (1); and an XPS thermal insulation board (4) is provided in the middle of the roadbed fill layer (3).
2. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 1, characterized in that: The inverted "T"-shaped heat pipe (6) is divided into a condensation section (62) and an evaporation section (61); the length of the condensation section of the heat pipe is not less than 8 m, and the length of the evaporation section is 8 m to 15 m.
3. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 1, characterized in that: The inverted "T"-shaped heat pipe (6) is installed in the central isolation zone (9) of the road surface. The heat pipe adopts a bidirectional bending section design to form an inverted "T" shape. The acute angle between the bottom evaporation section (61) and the horizontal plane is 3° to 5°. The evaporation section (61) can completely cover the range of the horizontal projection of the road surface. The bending point at the lower end of the inverted "T"-shaped heat pipe (6) is located in the active layer below the roadbed structure (1). The bent end of the bottom of the inverted "T"-shaped heat pipe (6) is located near the upper limit of permafrost. The inverted "T"-shaped heat pipe (6) is arranged in the central isolation zone (9) of the road surface along the direction of the highway, and the arrangement spacing is 3m to 4m.
4. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 2, characterized in that: The inverted "T"-shaped heat pipe condensation section (62) is equipped with a detection device (620) for detecting the working state of the inverted "T"-shaped heat pipe (6), and a heat sink (621) is arranged in the area above the inverted "T"-shaped heat pipe condensation section (62) for dissipating heat released by condensation of the working fluid into the air.
5. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 4, characterized in that: The detection device (620) comprises a data storage device (6201), an infrared thermometer (6202) and a protective shell (6203); the data storage device (6201) and the infrared thermometer (6202) are connected via a transmission cable.
6. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 5, characterized in that: The infrared thermometers (6202) are provided with two, the upper infrared thermometer is installed in the middle of the area where the heat sink (621) is arranged, and is used to detect the temperature of the pipe wall there, and the lower infrared thermometer is installed in the middle position between the bottom of the area where the heat sink (621) is arranged and the ground, and is used to detect the temperature of the pipe wall there. The protective shell (6203) is made of insulating glass and is used to waterproof and heat-insulate the infrared thermometer.
7. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 1, characterized in that: The roadbed structure (1) has a slope ratio of 1:1.5; the block stone layer (2) has a particle size of 15 cm to 30 cm and a thickness of 1.5 m; the block stone particle size used in the sunny slope block stone slope protection (8) of the roadbed structure (1) has a particle size of 15 cm to 25 cm and a laying thickness of 1.6 m; the block stone particle size used in the shady slope block stone slope protection (7) of the roadbed structure (1) has a particle size of 15 cm to 25 cm and a laying thickness of 0.8 m.
8. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 7, characterized in that: The block stone layer (2), the sunny slope block stone slope protection (8) and the shady slope block stone slope protection (7) are connected to form an asymmetric "U"-shaped integral structure.
9. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 1, characterized in that: The XPS thermal insulation board (4) is made of polystyrene resin as the main raw material and has a thickness of 5 cm to 10 cm.
10. A composite reinforcement structure and construction method suitable for highways in permafrost regions according to claim 1, characterized in that: This is accomplished by the following steps: S1. Level the natural foundation on the highway design route; S2. Dig trenches on the natural foundation according to the designed roadbed depth and roadbed width, with an excavation width of 0.5m, a horizontal excavation length of 15m, and a vertical excavation depth of 2m; S3, using the lifting equipment to lift the inverted "T" shaped heat pipe 6 into the trench, place it steadily, backfill with fine sand and tap it to compact it; S4, fill the block stone layer 3 with a thickness of 1.5m, the roadbed fill layer 3, the XPS insulation board 4, and the pavement structure layer 5 in order and compact them lightly for several times; S5. According to the engineering construction specifications, a 0.8m thick block stone slope protection is laid on the shady slope of the roadbed structure 1, and a 1.6m thick block stone slope protection is laid on the sunny slope of the roadbed.
Citation Information
Cited By
Ventilation roadbed intelligent regulation and control system and method for annual cooling capacity supply closed-loop regulation and control
CN120867156A
Dispersion type active cooling system suitable for block stone ventilation roadbed and construction method of dispersion type active cooling system
CN121066012A