CO2 drive continuous gas injection pipe completion pipe string and putting process
By using coiled tubing and multi-functional suspension sealing devices in the CO2 flooding oilfield completion process, the problems of high cost, long cycle and high leakage rate in the existing technology have been solved, and efficient control and safety improvement of gas seals have been achieved to meet the needs Meet the demand for economical and efficient gas injection in industrialization.
Patent Information
- Application Number
- CN202310465006.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-26
- Publication Date
- 2024-10-29
AI Technical Summary
The existing CO2 flooding oilfield completion technology has problems such as high cost, long cycle, high leakage rate and high safety risks. In particular, due to the complex pipe string structure and multiple tubing threads, the gas seal detection is difficult and the pressure is high. Increased operating costs and risks.
The coiled tubing and wellhead multi-functional suspension sealing device and downhole gas sealing device are used. Through the special thread buckle type and CO2 corrosion-resistant steel body material, the Y441 coiled tubing gas injection special gas sealing packer and setting ball seat are designed to achieve gas sealing. The continuous gas injection pipe completion string structure and the corresponding injection process are formulated.
It reduces the risk of gas seal management and control, improves the inspection cycle and operation efficiency, meets the demand for economical and efficient gas injection in the industrialization of CO2 oil flooding, reduces costs and risks, and improves the safety of the wellbore and the integrity of the gas injection channel.
Smart Images

Figure CN118855428A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of oilfield recovery enhancement, and particularly relates to a CO2 flooding continuous gas injection pipe completion string and a placement process. Background Art
[0002] In the early stage, Changqing Oilfield carried out a CO2 flooding pilot test in the Huang 3 well area of Jiyuan Oilfield, using the following method: Figure 1 The conventional gas injection string structure shown in the figure has the following problems in the completion process of the existing technical solutions: 1. The completion cost is high. It is necessary to match the gas-tight oil pipe, gas injection wellhead, gas-tight packer and supporting tools, and the gas-tight detection must be carried out simultaneously when the oil pipe is connected. The cost of this item alone is as high as 300,000 to 400,000 yuan for a single well; 2. The completion cycle is long. The gas-tight oil pipe needs to be professionally washed and buckled, and the gas-tight detection must be carried out at the same time. It usually takes about 7 days to complete a single well; 3. The probability of leakage is high. The completion string structure is complex, and the oil pipe has many threads, resulting in a high probability of leakage, and once the casing is pressurized, the safety risk of the wellbore becomes higher; 4. Because it involves pressurized operations, the cost and risk of completing the well again are high. Summary of the invention
[0003] In view of the above problems, the present invention discloses a CO2 flooding continuous gas injection pipe completion string, comprising: a wellhead multifunctional suspension sealing device, a wellhead large-diameter gas injection gate valve, a continuous oil pipe, a safety release and a packer;
[0004] One end of the wellhead large-diameter gas injection gate valve is connected to the wellhead multifunctional suspension sealing device, and the other end is connected to one end of the casing large four-way valve;
[0005] One end of the coiled tubing is suspended and sealed at the wellhead by a wellhead multifunctional suspension and sealing device, and the other end is connected to a safety release end;
[0006] The other end of the safety release is connected to one end of the packer.
[0007] Furthermore, it also includes: seating the tee;
[0008] One end of the setting ball seat is connected to the other end of the packer.
[0009] Furthermore, it also includes: bottom blocking;
[0010] One end of the bottom plug is connected to the other end of the setting ball seat.
[0011] Furthermore, it also includes: guide shoes;
[0012] One end of the guide shoe is connected to the other end of the bottom plug.
[0013] Furthermore, it also includes: a connector;
[0014] One end of the connector is connected to the coiled tubing, and the other end is connected to the safety release.
[0015] Furthermore, the connection buckles of the completion string are all airtight special thread buckles.
[0016] Furthermore, the protective fluid in the annulus between the completion string and the casing is an oil-based protective fluid.
[0017] Furthermore, the packer is a Y441 air-tight packer specially used for continuous tubing gas injection.
[0018] Furthermore, the wellhead multifunctional suspension sealing device, connector, safety release and packer are all made of 13Cr steel material that is resistant to CO2 corrosion;
[0019] The coiled tubing is made of 18Cr or 2205 steel material that is resistant to CO2 corrosion.
[0020] The present invention also discloses a CO2 flooding continuous gas injection pipe completion string placement process, comprising the following steps:
[0021] Install the wellhead device: install the wellhead large-diameter gas injection gate valve, the wellhead multifunctional hanging sealing device, the four-gate blowout preventer, the blowout preventer, the pipe cutter, the blowout preventer box and the injection head from bottom to top on the large casing cross-way;
[0022] Wellhead equipment pressure test: Conduct water seal and air seal pressure tests on the four-gate blowout preventer, blowout preventer, blowout preventer box and ground pipelines of the wellhead blowout prevention equipment in turn;
[0023] Installation of downhole tool string and pressure test: Start the coiled tubing operation vehicle, lower the coiled tubing, chamfer the outer wall of the bottom end of the coiled tubing, install the air-tight connector and perform a tensile test, install the safety release, packer, setting ball seat, bottom plug and guide shoe in sequence, and perform water-tight and air-tight pressure tests on the downhole tool string as a whole;
[0024] Running the continuous gas injection string: During the running of the coiled tubing, the casing production channel of the casing big four-way is opened, and the coiled tubing is lowered to the designed depth;
[0025] Circulating annular protection fluid: After the coiled tubing is lowered to the predetermined position, the annular protection fluid is used to positively pressurize the coiled tubing to remove the bottom plug and establish an oil-casing circulation channel;
[0026] Packer sealing and sealing verification: throw soluble balls to pressurize, observe the change of liquid volume at the blowdown nozzle until no liquid comes out, and judge that the packer sealing mechanism has been started and sealed, and continue to pressurize until there is a sudden pressure drop, the shear sleeve has been opened and the gas injection channel has been established;
[0027] Suspension sealing and pressure test: After the packer is tested and sealed, a downward pressure of 3 to 4 tons is applied to the coiled tubing, and the multifunctional suspension sealing device at the wellhead is started to suspend and seal the continuous gas injection string. The pressure test tooling is used to verify the airtightness of the multifunctional suspension sealing device at the wellhead;
[0028] Cutting the pipe: Use a pipe cutter or a manual cutter to cut the coiled tubing;
[0029] Restore the gas injection wellhead: Install the gas injection wellhead on the wellhead multifunctional suspension sealing device, and restore the original gas injection wellhead according to the production process design requirements.
[0030] Compared with the prior art, the embodiments of the present invention have at least the following advantages: conventional gas-sealed oil pipes are replaced by continuous oil pipes, and a multifunctional wellhead suspension sealing device and a downhole gas sealing device are provided as auxiliary devices, which greatly reduces the risk of gas seal management and control, improves the inspection cycle and operating efficiency, and meets the needs of economical and efficient gas injection for the industrialization of CO2 oil recovery.
[0031] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or be understood by implementing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures pointed out in the description and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0033] Figure 1 A schematic diagram of the structure of a conventional gas injection string is shown;
[0034] Figure 2 It shows a schematic diagram of the structure of a CO2 flooding continuous gas injection pipe completion string according to an embodiment of the present invention;
[0035] Figure 3 The figure shows a process flow chart of placing a CO2 flooding continuous gas injection pipe completion string according to an embodiment of the present invention.
[0036] Figure numerals: 1. Multifunctional wellhead suspension sealing device; 2. Large-diameter wellhead gas injection gate valve; 3. Continuous oil pipe; 4. Connector; 5. Safety release; 6. Packer; 7. Sealing ball seat; 8. Bottom plug; 9. Guide shoe. DETAILED DESCRIPTION
[0037] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0038] Figure 2 The schematic diagram of the CO2 flooding continuous gas injection pipe completion string structure according to an embodiment of the present invention is shown. Figure 2 As shown, the CO2 flooding continuous gas injection pipe completion string proposed by the present invention comprises: a wellhead multifunctional suspension sealing device 1, a wellhead large-diameter gas injection gate valve 2, a continuous oil pipe 3, a safety release 5 and a packer 6;
[0039] One end of the wellhead large-diameter gas injection gate valve 2 is connected to the wellhead multifunctional suspension sealing device 1, and the other end is connected to one end of the casing large four-way valve;
[0040] One end of the coiled tubing 3 is suspended and sealed at the wellhead by the wellhead multifunctional suspension and sealing device 1, and the other end is connected to one end of the safety release 5;
[0041] The other end of the safety release handle 5 is connected to the top of the packer 6.
[0042] A wellhead multifunctional hanging and sealing device 1, a wellhead device used for hanging and sealing a coiled tubing 3 at a wellhead;
[0043] The wellhead large-diameter gas injection gate valve 2 is used to connect the wellhead multifunctional suspension sealing device 1 and the casing large four-way, and at the same time ensure that the large-diameter packer 6 can pass smoothly through the wellhead device;
[0044] Coiled tubing 3, used for continuous gas injection string;
[0045] Safety release 5, a downhole tool used to release the coiled tubing 3 from the packer 6 by dropping a ball to pressurize the packer 6 when the packer 6 cannot be released normally;
[0046] The packer 6 is a downhole tool used to isolate the annular space between the coiled tubing 3 and the casing of the oil and gas well.
[0047] The present invention replaces conventional gas-sealed oil pipes with continuous oil pipes 3, and assists with the wellhead multifunctional suspension sealing device 1 and the downhole gas sealing device, thereby greatly reducing the gas seal management and control risks, improving the inspection cycle and operation efficiency, and meeting the economical and efficient gas injection needs of CO2 oil recovery industrialization.
[0048] In some embodiments, a CO2 flooding continuous gas injection pipe completion string further includes: a setting ball seat 7;
[0049] One end of the setting ball seat 7 is connected to the bottom end of the packer 6 .
[0050] The sealing ball seat 7 is used to realize the sealing of the packer 6 .
[0051] In some embodiments, a CO2 flooding continuous gas injection pipe completion string further includes: a bottom plug 8;
[0052] One end of the bottom plug 8 is connected to the bottom end of the setting ball seat 7 .
[0053] The bottom plug 8 is used for one-way sealing during the lowering of the pipe string to prevent the bottom hole pressure from rising into the coiled tubing 3.
[0054] In some embodiments, a CO2 flooding continuous gas injection pipe completion string further includes: a guide shoe 9;
[0055] One end of the guide shoe 9 is connected to the bottom end of the bottom plug 8 .
[0056] The guide shoe 9 is used to prevent the bottom of the continuous gas injection string from scraping the casing wall and guide the continuous gas injection string to the designed position smoothly.
[0057] In some embodiments, a CO2 flooding continuous gas injection pipe completion string further includes: a connector 4;
[0058] One end of the connector 4 is connected to the bottom end of the coiled tubing 3 , and the other end is connected to the top end of the safety release 5 .
[0059] The connector 4 is used to connect the coiled tubing 3 and the special downhole tool of the safety release 5.
[0060] In some embodiments, the downhole tool connection buckle type of the completion string is a gas-tight special threaded buckle BGT2, which achieves structural integrity and sealing integrity through metal-to-metal interference fit sealing, and has the advantages of high connection strength and good sealing performance.
[0061] In some embodiments, the protective fluid in the annulus between the completion string and the casing is an oil-based protective fluid. Exemplarily, the formula of the oil-based protective fluid is mainly industrial white oil + imidazoline corrosion inhibitor. The imidazoline corrosion inhibitor is mainly an environmentally friendly imidazoline corrosion inhibitor such as an amide imidazoline derivative (IM).
[0062] In some embodiments, the packer 6 is a Y441 continuous tubing gas injection special gas-tight seal packer that is sealed by a ball-throwing hydraulic seat and unsealed by lifting. The packer is made of 13Cr steel, has an external design of a "three-rubber tube combination + expansion ring + copper bowl protection" structure, and uses a "metal + rubber" composite sealing method inside, which greatly improves the overall gas sealing performance and service life of the tool; at the same time, in order to cope with the characteristics of the weak tensile strength of the continuous tubing 3, the distribution position of the anchoring and sealing mechanism is carefully designed, the force of the central pipe and the size of the pin are optimized, and the unsealing tonnage is reduced to the greatest extent.
[0063] In some embodiments, the wellhead multifunctional suspension sealing device 1, the connector 4, the safety release 5 and the packer 6 are all made of a steel body material 13Cr which is resistant to CO2 corrosion;
[0064] The coiled tubing 3 is made of CO2 corrosion resistant steel material 18Cr or 2205. The use of CO2 corrosion resistant material can effectively prevent CO2 from corroding the tubing string and increase the overall service life of the continuous gas injection tubing string.
[0065] The CO2-driven continuous gas injection pipe completion string of the present invention relies on the advantages of the continuous oil pipe itself and the ability to operate under pressure, and through the optimization of carbon corrosion-resistant continuous oil pipe, the development of long-term gas-tight seal packers, the development of gas-tight special tools, and the research on continuous gas injection pipe placement and completion technology, a CO2-driven continuous gas injection pipe completion technology is formed. The invention is of great significance in improving the wellbore integrity of the injection well, reducing the overall cost, and realizing the full life cycle management of the gas injection well, and is also expected to provide a new injection solution for CO2 injection oil recovery.
[0066] Figure 3 The following is a flow chart of the placement process of the CO2 flooding continuous gas injection pipe completion string according to an embodiment of the present invention. Figure 3 As shown, based on the above-mentioned CO2 flooding continuous gas injection pipe completion string, this embodiment proposes a CO2 flooding continuous gas injection pipe completion string placement process, including the following steps:
[0067] Install the wellhead device: After the construction preparation is completed as required, install the wellhead large-diameter gas injection gate valve 2, the wellhead multifunctional suspension sealing device 1, the four-gate blowout preventer, the blowout preventer, the pipe cutter, the blowout preventer box and the injection head from bottom to top above the large casing cross-way, and the injection head with the guy rope on. Use a crane to steadily hang the injection head and fix it with a ground anchor; connect the ground anchor and the guy rope, adjust the guy rope tension and make the injection head face the coiled tubing operation vehicle and be located directly above the blowout preventer group; connect and install other ground pipelines, including the connection water pressure test process;
[0068] Wellhead equipment pressure test: according to the design requirements, the four-gate blowout preventer, blowout preventer, blowout preventer box and ground pipeline of the wellhead blowout prevention equipment shall be tested for water seal and air seal in turn;
[0069] Install downhole tool string and pressure test: start the coiled tubing operation vehicle, lower the coiled tubing 3 through the gooseneck pipe, pass it through the injection head and the blowout preventer box, and extend it about 500mm below the blowout preventer. Try to ensure that the coiled tubing 3 is vertical, chamfer the outer wall of the bottom end of the coiled tubing 3, install the air-tight connector 4 and perform a tensile test, install the safety release 5, the packer 6, the sealing ball seat 7, the bottom plug 8 and the guide shoe 9 in sequence, and perform water-tight and air-tight pressure tests on the downhole tool string as a whole as required;
[0070] Lower the continuous gas injection string: During the process of lowering the coiled tubing 3 into the well, open the casing production channel of the casing big four-way, and do not lift or lower it violently during the lowering process; lower the coiled tubing 3 steadily to the designed depth as required;
[0071] Circulating annular protection fluid: After the coiled tubing 3 is lowered to the predetermined position, the annular protection fluid is used to positively pressurize the coiled tubing 3 to remove the bottom plug 8 and establish an oil-casing circulation channel; the annular protection fluid is replaced in a positive circulation until the protection fluid returns from the blowdown port;
[0072] The packer 6 is set and tested: a soluble ball is added to pressurize the packer 6, and the change in the amount of liquid in the discharge port is observed until no liquid is discharged. It is determined that the packer 6 setting mechanism has been started and set. The pressure is continuously pressed until a sudden pressure drop occurs, the shear sleeve is opened, and a gas injection channel is established; the packer 6 is tested by annular pressure pressing;
[0073] Suspension sealing and pressure test: After the packer 6 is tested and sealed, the coiled tubing 3 applies a downward pressure of 3 to 4 tons, starts the wellhead multifunctional suspension sealing device 1, suspends and seals the continuous gas injection string, and uses the pressure test tool to verify the airtightness of the wellhead multifunctional suspension sealing device 1;
[0074] Cutting the pipe: Use a special pipe cutter or a manual cutter to cut the coiled tubing 3;
[0075] Restore the gas injection wellhead: install the gas injection wellhead on the wellhead multifunctional suspension sealing device 1, and restore the original gas injection wellhead according to the design requirements of the production process.
[0076] When the tubing string is pulled out, the coiled tubing 3 can be pulled out under pressure to avoid formation contamination caused by well killing.
[0077] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0078] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0079] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0080] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0081] In the description of the present invention, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In the present invention, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine different embodiments or examples described in the present invention and features of different embodiments or examples without contradiction.
[0082] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein; and these modifications or substitutions do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A CO 2 Continuous gas injection pipe completion string, It is characterized in that include: A wellhead multifunctional hanging sealing device (1), a wellhead large-diameter gas injection gate valve (2), a coiled tubing (3), a safety release (5) and a packer (6); One end of the wellhead large-diameter gas injection gate valve (2) is connected to the wellhead multifunctional suspension sealing device (1), and the other end is connected to one end of the casing large four-way valve; One end of the coiled tubing (3) is suspended and sealed at the wellhead by a wellhead multifunctional suspension and sealing device (1), and the other end is connected to one end of a safety release device (5); The other end of the safety release (5) is connected to one end of the packer (6).
2. The CO according to claim 1 2 Continuous gas injection pipe completion string, It is characterized in that Also includes: Setting tee (7); One end of the setting ball seat (7) is connected to the other end of the packer (6).
3. CO according to claim 2 2 Continuous gas injection pipe completion string, It is characterized in that Also includes: Bottom plugging (8); One end of the bottom plug (8) is connected to the other end of the setting ball seat (7).
4. The CO according to claim 3 2 Continuous gas injection pipe completion string, It is characterized in that Also includes: Guide shoe (9); One end of the guide shoe (9) is connected to the other end of the bottom plug (8).
5. The CO according to claim 1 2 Continuous gas injection pipe completion string, It is characterized in that Also includes: Connector (4); One end of the connector (4) is connected to the coiled tubing (3), and the other end is connected to the safety release (5).
6. CO according to claim 4 or 5 2 Continuous gas injection pipe completion string, It is characterized in that The connection buckles of the completion string are all airtight special thread buckles.
7. The CO according to claim 1 2 Continuous gas injection pipe completion string, It is characterized in that The protective fluid in the annulus between the completion string and the casing is an oil-based protective fluid.
8. The CO according to claim 1 2 Continuous gas injection pipe completion string, It is characterized in that The packer (6) is a Y441 airtight packer specially used for continuous tubing gas injection.
9. The CO according to claim 5 2 Continuous gas injection pipe completion string, It is characterized in that The wellhead multifunctional suspension sealing device (1), connector (4), safety release (5) and packer (6) are all made of CO2-resistant 2 The corroded steel body is made of 13Cr; The coiled tubing (3) is resistant to CO 2 The corroded steel body is made of 18Cr or 2205.
10. A CO 2 The technology of placing the completion string of continuous gas injection pipe in flooding, It is characterized in that The following steps are involved: Install the wellhead device: install the wellhead large-diameter gas injection gate valve (2), the wellhead multifunctional hanging sealing device (1), the four-gate blowout preventer, the blowout preventer, the pipe cutter, the blowout preventer box and the injection head in order from bottom to top above the large four-way of the casing; Wellhead equipment pressure test: Conduct water seal and air seal pressure tests on the four-gate blowout preventer, blowout preventer, blowout preventer box and ground pipelines of the wellhead blowout prevention equipment in turn; Installation of downhole tool string and pressure test: Start the coiled tubing operation vehicle, lower the coiled tubing (3), chamfer the outer wall of the bottom end of the coiled tubing (3), install the air-tight connector (4) and perform a tensile test, install the safety release (5), the packer (6), the sealing ball seat (7), the bottom plug (8) and the guide shoe (9) in sequence, and perform water-tight and air-tight pressure tests on the entire downhole tool string in sequence; Lowering the continuous gas injection string: During the process of lowering the continuous oil pipe (3) into the well, the casing production channel of the casing big four-way is opened, and the continuous oil pipe (3) is lowered to the designed depth; Circulating annular protection fluid: After the coiled tubing (3) is lowered to a predetermined position, annular protection fluid is used to positively pressurize the coiled tubing (3) to remove the bottom plug (8) and establish an oil-casing circulation channel; The packer (6) is set and tested: a soluble ball is added to pressurize the packer (6) and the change in the amount of liquid at the discharge port is observed until no liquid is discharged. It is determined that the packer (6) setting mechanism has been started and set. The pressure is continuously pressed until a sudden pressure drop occurs and the shear sleeve is opened and a gas injection channel is established. Suspension sealing and pressure testing: After the packer (6) passes the sealing test, the coiled tubing (3) applies a downward pressure of 3 to 4 tons, starts the wellhead multifunctional suspension sealing device (1), suspends and seals the continuous gas injection string, and uses a pressure testing tool to verify the airtightness of the wellhead multifunctional suspension sealing device (1); Cutting the pipe: Use a pipe cutter or a manual cutter to cut the coiled tubing (3); Restoring the gas injection wellhead: Install the gas injection wellhead on the wellhead multifunctional suspension sealing device (1), and restore the original gas injection wellhead according to the design requirements of the production process.
Citation Information
Cited By
Coiled tubing four-ram blowout preventer suspension device and using method
CN120990522A