Rapid construction method suitable for upper half middle wall of super-large section tunnel
By dividing steps in a very large section tunnel and using wall support pipes and curved bottom plates to provide prestressed support, the complexity and stability of the guide hole construction are solved, efficient and safe tunnel construction is achieved, and construction costs and risks are reduced.
Patent Information
- Application Number
- CN202411199268.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-12
AI Technical Summary
In the construction of extra-large section tunnels, traditional methods lead to small cross-sections of guide holes, complex construction, high cost and high safety risks. The lack of support on the walls of the middle-level guide holes is likely to collapse, affecting construction safety and tunnel shape.
Divide the palm surface into three upper, middle and lower steps, and subdivides the left and right working surfaces on each step. The wall support pipe and arc-shaped base plate provide prestressed support, and is applied by inserting longitudinally into the wall support pipe and arc-shaped hole. Elastic prestressing reduces the number of temporary vertical supports, improves the stability of the middle steps, and gradually removes temporary support during construction.
It improves the stability of the wall surface of the middle step guide hole, reduces construction costs and safety risks, simplifies construction processes, improves construction efficiency, and ensures the stability and safety of the tunnel structure. It is suitable for extremely large section tunnels of 300m2 and above.
Smart Images

Figure CN118933803A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel construction, and in particular relates to a method for quickly constructing an upper middle wall of a tunnel with an extra-large cross-section. Background Art
[0002] With the rapid development of transportation construction in the southwest region, large-section tunnels will inevitably pass through mountainous and hilly areas. The large excavation section will increase the difficulty of controlling the stability of the tunnel surrounding rock and easily cause safety accidents. Traditional methods mostly use CD method, CRD method, double-side wall pilot method and multi-pilot method. The core of the relevant methods is to set up multiple pilot tunnels and multiple temporary supports based on the basic principles of the New Austrian Tunneling Method, divide the large section into small sections for construction, and reduce the difficulty and risk of section stability maintenance. However, the relevant methods have obvious disadvantages, such as: 1. The pilot tunnel section is small, and large machinery cannot be used for construction. The process is complex and cross-cutting, which affects the construction progress; 2. There are many temporary supports, which leads to increased construction costs. When removing the vertical supports, there will inevitably be risks such as continuous deformation of the surrounding rock. The risk of removing the support is high, and the large number of support removal processes also means that the safety control measures brought about by the support removal need to be increased.
[0003] In order to solve the above technical problems, some existing construction methods divide the face into three steps: upper, middle and lower, and then further subdivide the three steps. Through the construction of regular pilot tunnels, the construction efficiency can be improved. When constructing the upper pilot tunnel, this method can play a temporary support role through temporary vertical supports, but when constructing the middle pilot tunnel, due to the lack of timely support on the wall of the middle pilot tunnel, the rock and soil at the pilot tunnel is prone to collapse, which will affect the safety of construction and the geometry of the tunnel. Summary of the invention
[0004] In view of this, the purpose of the present invention is to provide a method for rapid construction of the upper middle wall of a tunnel with an extra-large cross-section, which can solve the above-mentioned technical problems.
[0005] In order to achieve the above object, the present invention provides the following technical solutions: The invention discloses a method for quickly constructing the upper middle wall of a tunnel with a particularly large cross section, comprising the following steps: First, the tunnel face is divided into three steps: upper, middle and lower. Then, the three steps are further divided into two working faces: left and right. The left guide hole of the upper step is the leading guide hole, and its working face is smaller than that of the right guide hole of the upper step. The edge positions of the left and right working faces of the middle step are marked to determine the construction position of the wall support pipe. Step (1), first excavate the left pilot tunnel of the upper step, then excavate at each advance. After the left pilot tunnel of the upper step is excavated to a predetermined length, a left end face groove is excavated at the end position. The shape of the left end face groove is consistent with the shape of the left working surface of the middle step. After excavation, the permanent support side of the excavated part is supported in time, and temporary vertical supports are applied at the remaining positions; Step (2), after the temporary vertical support is constructed, the left wall support pipe at the edge of the left guide hole of the middle step is constructed, and the left wall support pipe is inserted longitudinally into the left working surface of the middle step until the left wall support pipe extends out of the left end face groove; from the left guide hole of the upper step, a left arc hole is constructed along the edge of the left guide hole of the middle step, and a left support is constructed in the left arc hole; Step (3), after the construction of the left wall support pipe is completed, the right guide hole of the upper step is excavated. After the right guide hole of the upper step is excavated to a predetermined length, a right end face groove is excavated at the end position. The shape of the right end face groove is consistent with the shape of the right working surface of the middle step, and the permanent support side of the excavated part is supported in time; Step (4), constructing a right wall support pipe at the edge of the right guide hole of the middle step, inserting the right wall support pipe into the right working surface of the middle step along the longitudinal direction until the right wall support pipe extends out of the right end surface groove; constructing a right arc hole from the right guide hole of the upper step along the edge of the right guide hole of the middle step, and constructing a right support in the right arc hole; Step (5), after the left and right guide tunnels of the upper step are excavated for a certain distance, radial prestressed anchor cables are applied to the left and right guide tunnels of the upper step; Step (6), repeat steps (1) to (5) until the left and right guide holes on the upper step are dug through; Step (7), after the radial anchor cables of the left and right guide holes of the upper step have been applied for a certain distance, the temporary vertical supports of a single cycle of advance are removed from the starting section; Step (8), finally, slope excavation and support are performed on the left and right working surfaces of the middle step and the lower step.
[0006] Furthermore, the left support and the right support are constructed in a symmetrical manner. In step (2), the construction of the left support specifically includes: Step (2.1), fix the arc guide rail, extend the arc guide rail into the left arc hole, the arc guide rail and the bottom of the left arc hole are separated by a certain distance, fix the arc guide rail to the primary support steel frame in the left guide hole of the upper step, and the opening of the arc guide rail faces the inner side of the tunnel; Step (2.2), install the arc bottom plate, extend the arc bottom plate into the left arc hole along the extension direction of the arc guide rail, and adjust the position of the arc bottom plate so that the outer arc surface of the arc bottom plate contacts the left wall support tube; Step (2.3), applying prestress, installing a prestressed member in the arc-shaped guide rail, and applying elastic prestress to the arc-shaped bottom plate through the prestressed member; Furthermore, when installing the arc-shaped bottom plate, the pin shaft on the arc-shaped bottom plate is inserted into the slide groove provided on the arc-shaped guide rail. The prestressed member adopts an arc-shaped composite plate, and multiple layers of arc-shaped composite plates are inserted in the space between the arc-shaped bottom plate and the arc-shaped guide rail in turn. The position of the arc-shaped composite plate is continuously adjusted so that it applies an elastic pre-support force radially outward to the left wall support tube.
[0007] Furthermore, a steel sleeve is fixed on the outer side of the arc guide rail, and the multi-layer arc-shaped composite plate and the arc-shaped bottom plate are limitedly installed in the arc guide rail.
[0008] Furthermore, in step (8), firstly, the left and right working faces of the middle step are excavated by slope cutting, and the permanent support side of the excavated part is supported in time, radial anchor cables are installed in the left and right guide holes of the middle step, and impurities in the left wall support pipe are removed; after the middle step is excavated for a certain distance, the left and right working faces of the lower step are excavated by slope cutting, and support treatment is carried out in time; after the lower step is excavated for a certain distance, the initial support of the invert is installed to close the ring.
[0009] Furthermore, when constructing the radial anchor cables of the left and right guide holes in the middle step, the radial anchor cables are simultaneously passed through the through holes on the left wall support tube and the arc-shaped bottom plate and tightened, grouting is poured into the inner side of the left wall support tube, and the radial anchor cables are simultaneously connected and anchored to the left wall support tube and the arc-shaped bottom plate.
[0010] Furthermore, in step (3), when constructing the right guide tunnel of the upper step, the staggered distance continues to advance the construction of the left guide tunnel of the upper step.
[0011] Furthermore, in step (5), the anchor cable construction is divided into two stages: drilling and grouting and tensioning. There is a waiting period for the slurry strength between the two stages. During the period of waiting for tensioning during the first cycle of drilling and grouting, the second cycle of drilling and grouting is carried out.
[0012] Furthermore, in step (8), the secondary lining is applied promptly after the primary support is closed into a ring.
[0013] The beneficial effects of the present invention are: 1. The present invention discloses a method for quickly constructing the upper middle wall of a tunnel with a large cross section. After the construction of the left and right guide holes of the upper step is completed, the left wall support pipe and the right wall support pipe are respectively constructed to support the edge of the middle step. When the guide holes on both sides of the middle step are constructed, the stability of the wall of the guide hole of the middle step can be improved to prevent tunnel deformation caused by landslides.
[0014] 2. In the method disclosed in the present invention, multiple wall support tubes provide pre-tightening force through the support, which can achieve the effect of synchronous tightening, ensure the continuity of the support, and change the support range of the multiple wall support tubes from line support to surface support, so as to achieve better support effect.
[0015] 3. The above-mentioned support method has a simple support structure and will not damage the construction site on a large scale, thus ensuring the safety of the construction. By extending the support pipe longitudinally into the wall, the construction process is convenient and the cost is greatly saved. After the construction is completed, there is no need to dismantle the device, so that it can be integrated with the primary support steel frame, which improves the construction efficiency, ensures the structural stability of the tunnel, and reduces the difficulty and risk of maintaining the stability of the section.
[0016] 4. The present invention simplifies the construction process of extra-large cross-section tunnels, reduces the number of working surfaces, and overcomes the difficulty of large-scale equipment in and out. The present invention can significantly reduce the complexity of construction, dispatch large-scale equipment, and thus improve construction efficiency.
[0017] 5. While expanding the working surface area, the present invention adopts prestressed anchor cable support in the arch, which achieves the effect of reducing the span in mechanics, and at the same time reduces the risk of structural force system transformation when removing temporary vertical supports, thereby ensuring structural safety.
[0018] 6. The present invention only applies temporary vertical support in the middle of the upper step, which reduces the number of overall temporary supports, that is, the temporary vertical support and horizontal support of the middle and lower steps are eliminated, and the vertical support does not fall to the bottom, which greatly reduces the difficulty of constructing the middle and lower steps, and can reduce construction costs while ensuring construction efficiency.
[0019] 7. The present invention is particularly suitable for 300m 2 Extra-large cross-section tunnels of 1000 m and above provide a reference for other projects and have a certain degree of universality.
[0020] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration: Figure 1 It is a schematic diagram of the cross-sectional structure of a super-large tunnel of the present invention; Figure 2 It is a schematic diagram of the coordination between the left wall support tube and the arc bottom plate; Figure 3 ① Schematic diagram of pilot tunnel excavation; Figure 4 This is a schematic diagram of the excavation of ①② pilot tunnels and the construction of temporary vertical supports; Figure 5 This is a schematic diagram of the construction of prestressed anchor cables in the arch parts ① and ②; Figure 6 This is a schematic diagram of staggered excavation of the middle and lower steps; Figure 7 Schematic diagram of the invert and secondary lining construction.
[0022] The markings in the attached drawings are as follows: left end face groove 1, temporary vertical support 2, left wall support tube 3, left arc hole 4, radial anchor cable 5, arc guide rail 6, arc bottom plate 7, pin shaft 8, slide groove 9, arc superimposed plate 10, fixed steel sleeve 11. DETAILED DESCRIPTION
[0023] like Figures 1 to 7 As shown, the present invention discloses a method for rapid construction of the upper middle wall of a large-section tunnel. The specific embodiment of the invention is applied to the Dashanpo Tunnel section of the Chongqing-Kunming High-speed Railway. 2 In combination with the on-site construction conditions, in order to reduce the construction complexity and improve the construction efficiency, the construction method of the present invention is adopted, including the following steps: First, the tunnel face is divided into three steps: upper, middle and lower. Then, the three steps are further divided into two working faces: left and right. The left guide hole of the upper step is the leading guide hole, and its working face is smaller than that of the right guide hole of the upper step. The edge positions of the left and right working faces of the middle step are marked to determine the construction position of the wall support pipe. Step (1), first excavate the left guide hole of the upper step, then excavate every advance. After the left guide hole of the upper step is excavated to a predetermined length, a left end face groove 1 is excavated at the end position. The width of the left end face groove 1 can at least accommodate the pipe jacking machine to facilitate the subsequent pipe jacking operation. The shape of the left end face groove 1 is consistent with the shape of the left working surface of the middle step. After excavation, the permanent support side of the excavated part is supported in time. The support includes system anchor rods, primary support steel frames and sprayed concrete support, and temporary vertical supports 2 are applied at other locations; Step (2), after the construction of the temporary vertical support 2 is completed, the left wall support tube 3 at the edge of the left guide tunnel of the middle step is constructed, and three left wall support tubes 3 are constructed in sequence from bottom to top, and the left wall support tube 3 is inserted longitudinally into the left working surface of the middle step until the left wall support tube 3 extends out from the left end surface groove 1; from the left guide tunnel of the upper step, a left arc hole 4 is constructed along the edge of the left guide tunnel of the middle step, and the bending direction of the left arc hole 4 is adapted to the curvature of the inner wall of the tunnel, and a left support is constructed in the left arc hole 4; the left support and the right support are constructed in a symmetrical manner, and the structures of the two are exactly the same. After the construction of the left support is completed, the right support is constructed. Taking the left support as an example, in step (2), the construction of the left support specifically includes: Step (2.1), fix the arc guide rail 6, the cross section of the arc guide rail 6 is U-shaped, with both ends open, which is convenient for installing the arc bottom plate 7 and the arc composite plate 10. Extend the arc guide rail 6 into the left arc hole 4, with a certain distance between the arc guide rail 6 and the bottom of the left arc hole 4, and fix the arc guide rail 6 to the primary support steel frame in the left guide hole of the upper step, with the opening of the arc guide rail 6 facing the inner side of the tunnel; Step (2.2), installing the arc bottom plate 7, which is made of elastic steel plate material, extending the arc bottom plate 7 into the left arc hole 4 along the extension direction of the arc guide rail 6, and adjusting the position of the arc bottom plate 7 so that the outer arc surface of the arc bottom plate 7 contacts the left wall support tube 3; In some other embodiments, the arc bottom plate 7 may also be made of other materials with elastic stress, such as an elastic steel plate, which not only has a certain elastic recovery ability, but also has the advantages of high strength and low cost.
[0024] Step (2.3), applying prestress, installing a prestressed member in the arc-shaped guide rail 6, and applying elastic prestress to the arc-shaped bottom plate 7 through the prestressed member, so that the arc-shaped bottom plate 7 provides an outward elastic supporting force for the support tube; Step (3), after the construction of the left wall support pipe 3 is completed, the right guide tunnel of the upper step is excavated. After the right guide tunnel of the upper step is excavated to a predetermined length, a right end face groove is excavated at the end position. The shape of the right end face groove is consistent with the shape of the right working surface of the middle step, and the permanent support side of the excavated part is supported in time; when constructing the right guide tunnel of the upper step, the staggered distance continues to promote the construction of the left guide tunnel of the upper step. The stability of the tunnel construction can be increased by the staggered distance construction method of construction and support at the same time.
[0025] Step (4), construct the right wall support tube at the edge of the right guide hole of the middle step, insert the right wall support tube into the right working surface of the middle step along the longitudinal direction until the right wall support tube extends out of the right end surface groove; construct the right arc hole along the edge of the right guide hole of the middle step from the right guide hole of the upper step, and construct the right support in the right arc hole; Step (5), after the left and right guide holes of the upper step are excavated for a certain distance, radial prestressed anchor cables are applied to the left and right guide holes of the upper step; the anchor cable construction is divided into two stages: drilling and grouting and tensioning. There is a window period of waiting for the slurry strength between the two stages. During the period of waiting for tensioning during the first cycle of drilling and grouting, the second cycle of drilling and grouting is carried out.
[0026] Step (6), repeat steps (1) to (5) until the left and right guide holes of the upper step are dug through; Step (7), after the radial anchor cables 5 of the left and right guide holes of the upper step have been applied for a certain distance, the temporary vertical supports 2 of a single cycle of footage are removed from the starting section; Step (8), finally slope excavate the left and right working surfaces of the middle step and the lower step and provide support.
[0027] The rapid construction method of the present invention has the advantages of simple construction method, less process conversion, high safety and reliability, greatly improving construction efficiency and reducing construction costs, and is particularly suitable for cross-sectional sizes exceeding 300m 2 The tunnel has certain advantages such as large cross-section versatility.
[0028] In this embodiment, when installing the arc bottom plate 7, the pin 8 on the arc bottom plate 7 is inserted into the slide groove 9 provided on the arc guide rail 6, so that the arc bottom plate 7 can rotate around the axis of the pin 8. The prestressed member adopts an arc-shaped composite plate 10, and multiple layers of arc-shaped composite plates 10 are inserted into the space between the arc bottom plate 7 and the arc guide rail 6 in sequence, and the position of the arc-shaped composite plate 10 is continuously adjusted so that it applies an elastic pre-support force radially outward to the left wall support tube 3. When the arc-shaped composite plate 10 is continuously inserted from the upper side of the arc bottom plate 7, the arc-shaped composite plate 10 can prop up the upper end of the arc bottom plate 7. Under the action of the lever, the lower end of the arc bottom plate 7 and part of the arc-shaped composite plate 10 are displaced in the radial outward direction, thereby applying prestress to the supporting steel pipe.
[0029] After the positions of the arc-shaped composite plate 10 and the arc-shaped bottom plate 7 are determined, the two can also play a certain elastic buffering effect. When the rock and soil layer is displaced under the influence of soil pressure, explosion or even earthquake, the pressure of the rock and soil layer on the middle step can also be buffered by the arc-shaped composite plate 10 and the arc-shaped bottom plate 7, thereby reducing the impact of the above situation on the construction progress.
[0030] In this embodiment, a steel sleeve 11 is fixed on the outer side of the arc guide rail 6, and the multi-layer arc composite plate 10 and the arc bottom plate 7 are limitedly installed in the arc guide rail 6, which can play a limiting effect, facilitate the installation of the arc composite plate 10, and ensure the structural integrity when constructing the middle step guide hole in the later stage.
[0031] As a further improvement of the embodiment of the present invention, in this embodiment, in step (8), firstly, the left and right working faces of the middle step are excavated by slope cutting, and the permanent support side of the excavated part is supported in time, radial anchor cables 5 of the left and right guide holes of the middle step are installed, and impurities in the left wall support pipe 3 are removed; after the middle step is excavated for a certain distance, the left and right working faces of the lower step are excavated by slope cutting, and support treatment is carried out in time; after the lower step is excavated for a certain distance, the initial support of the invert is installed and closed into a ring. After the initial support is closed into a ring, the secondary lining is installed in time.
[0032] In this embodiment, when constructing the radial anchor cables 5 of the left and right guide holes in the middle step, the radial anchor cables 5 are simultaneously passed through the through holes on the left wall support tube 3 and the arc-shaped bottom plate 7 and then tightened, and grouting is poured into the inner side of the left wall support tube 3, and the radial anchor cables 5 are simultaneously connected and anchored to the left wall support tube 3 and the arc-shaped bottom plate 7, which facilitates the connection of the above structure.
[0033] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.
Claims
1. A method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section, characterized in that: The following steps are included: First, the tunnel face is divided into three steps: upper, middle and lower. Then, the three steps are further divided into two working faces: left and right. The left guide hole of the upper step is the leading guide hole, and its working face is smaller than that of the right guide hole of the upper step. The edge positions of the left and right working faces of the middle step are marked to determine the construction position of the wall support pipe. Step (1), first excavate the left pilot tunnel of the upper step, then excavate at each advance. After the left pilot tunnel of the upper step is excavated to a predetermined length, a left end face groove is excavated at the end position. The shape of the left end face groove is consistent with the shape of the left working surface of the middle step. After excavation, the permanent support side of the excavated part is supported in time, and temporary vertical supports are applied at the remaining positions; Step (2), after the temporary vertical support is constructed, the left wall support pipe at the edge of the left guide hole of the middle step is constructed, and the left wall support pipe is inserted longitudinally into the left working surface of the middle step until the left wall support pipe extends out of the left end face groove; from the left guide hole of the upper step, a left arc hole is constructed along the edge of the left guide hole of the middle step, and a left support is constructed in the left arc hole; Step (3), after the construction of the left wall support pipe is completed, the right guide hole of the upper step is excavated. After the right guide hole of the upper step is excavated to a predetermined length, a right end face groove is excavated at the end position. The shape of the right end face groove is consistent with the shape of the right working surface of the middle step, and the permanent support side of the excavated part is supported in time; Step (4), constructing a right wall support pipe at the edge of the right guide hole of the middle step, inserting the right wall support pipe into the right working surface of the middle step along the longitudinal direction until the right wall support pipe extends out of the right end surface groove; constructing a right arc hole from the right guide hole of the upper step along the edge of the right guide hole of the middle step, and constructing a right support in the right arc hole; Step (5), after the left and right guide tunnels of the upper step are excavated for a certain distance, radial prestressed anchor cables are applied to the left and right guide tunnels of the upper step; Step (6), repeat steps (1) to (5) until the left and right guide holes on the upper step are dug through; Step (7), after the radial anchor cables of the left and right guide holes of the upper step have been applied for a certain distance, the temporary vertical supports of a single cycle of advance are removed from the starting section; Step (8), finally, slope excavation and support are performed on the left and right working surfaces of the middle step and the lower step.
2. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 1 is characterized in that: The left support and the right support are constructed in a symmetrical manner. In step (2), the construction of the left support specifically includes: Step (2.1), fix the arc guide rail, extend the arc guide rail into the left arc hole, the arc guide rail and the bottom of the left arc hole are separated by a certain distance, fix the arc guide rail to the primary support steel frame in the left guide hole of the upper step, and the opening of the arc guide rail faces the inner side of the tunnel; Step (2.2), install the arc bottom plate, extend the arc bottom plate into the left arc hole along the extension direction of the arc guide rail, and adjust the position of the arc bottom plate so that the outer arc surface of the arc bottom plate contacts the left wall support tube; Step (2.3), applying prestress, installing a prestressed member in the arc-shaped guide rail, and applying elastic prestress to the arc-shaped bottom plate through the prestressed member.
3. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 2 is characterized in that: When installing the arc bottom plate, the pin shaft on the arc bottom plate is inserted into the slide groove provided on the arc guide rail. The prestressed member adopts an arc-shaped composite plate, and multiple layers of arc-shaped composite plates are inserted in the space between the arc bottom plate and the arc guide rail in turn. The position of the arc-shaped composite plate is continuously adjusted so that it applies an elastic pre-support force radially outward to the left wall support tube.
4. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 3 is characterized in that: A steel sleeve is fixed on the outer side of the arc guide rail, and the multi-layer arc-shaped superimposed plate and the arc-shaped bottom plate are limitedly installed in the arc guide rail.
5. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 4 is characterized in that: In step (8), first, the left and right working faces of the middle step are excavated by slope cutting, and the permanent support side of the excavated part is supported in time, radial anchor cables are installed on the left and right guide holes of the middle step, and impurities in the left wall support pipe are removed; after the middle step is excavated for a certain distance, the left and right working faces of the lower step are excavated by slope cutting, and support treatment is carried out in time; after the lower step is excavated for a certain distance, the initial support of the invert is installed to close the ring.
6. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 5 is characterized in that: When constructing the radial anchor cables of the left and right guide holes in the middle step, the radial anchor cables are simultaneously passed through the through holes on the left wall support tube and the arc-shaped bottom plate and tightened, grouting is poured into the inner side of the left wall support tube, and the radial anchor cables are simultaneously connected and anchored to the left wall support tube and the arc-shaped bottom plate.
7. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 1 is characterized in that: In step (3), when constructing the right guide tunnel of the upper step, the construction of the left guide tunnel of the upper step is continuously advanced by staggering.
8. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 1 is characterized in that: In step (5), the anchor cable construction is divided into two stages: drilling and grouting and tensioning. There is a waiting period for the slurry strength between the two stages. During the period of waiting for tensioning during the first cycle of drilling and grouting, the second cycle of drilling and grouting is carried out.
9. The method for rapid construction of the upper middle wall of a tunnel with a particularly large cross section according to claim 1 is characterized in that: In step (8), the secondary lining is applied promptly after the primary support is closed into a ring.