Tunnel multi-stage buffer supporting structure and construction method thereof

By using a multi-stage buffer support structure with ring support frame, transverse support beam, main energy dissipation member and secondary energy dissipation member in the tunnel, the traditional support method is solved in soft rock using a combination design of elastic material and hollow energy dissipation pipe. The stability and construction difficulty issues during large deformation achieve stable support and protection, reducing project costs.

CN118933842APending Publication Date: 2024-11-12CHINA CONSTR SEVENTH ENG DIVISION CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410854222.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The traditional initial support method of tunnel cannot be effectively adapted when the soft rock is deformed, resulting in damage to the support structure, increasing the cost of engineering and construction difficulty, and may lead to economic losses and delays in construction due to large deformation.

Method used

It adopts a multi-stage buffer support structure, including an ring support frame, a transverse support beam, a main energy dissipation member and a secondary energy dissipation member. Through the combination of elastic material and hollow energy dissipation pipe, an arc-shaped concave and convex structure is formed, which absorbs loads and transfers them to the filling material. Using the deformation of the filler material and the energy absorption function of the energy dissipation tube, multi-angle deformation energy dissipation is provided to avoid load transmission to the inside of the tunnel.

Benefits of technology

It effectively avoids the problem of damage to the support structure due to large deformation of soft rock, provides stable support and protection, adapts to deformation impacts in the tunnel, ensures construction safety and structural stability, and reduces engineering costs and construction complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933842A_ABST
    Figure CN118933842A_ABST
Patent Text Reader

Abstract

The invention relates to a tunnel multi-stage buffer supporting structure and a construction method thereof, the tunnel multi-stage buffer supporting structure comprises multiple groups of ring supporting frames, transverse supporting beams, main energy dissipation components and auxiliary energy dissipation components, the ring supporting frames are arranged at intervals, and the transverse supporting beams are transversely fixed on the outer walls of the ring supporting frames; the main energy dissipation component comprises a main energy dissipation body, an energy dissipation pipe and a filling material; a clamping seat is arranged on the transverse supporting beam, the upper portion of the main energy dissipation body is of a protruding structure protruding upwards, the lower portion of the main energy dissipation body is fixedly clamped in the clamping seat in a matched mode, and the energy dissipation pipe is arranged in the middle area of the main energy dissipation body through filling materials. The auxiliary energy dissipation component comprises auxiliary energy dissipation bodies, the main energy dissipation bodies and the transverse supporting beams are combined together to form main energy dissipation units, and the auxiliary energy dissipation bodies are clamped between the adjacent main energy dissipation units in a matched mode. The main energy dissipation body is provided with a grouting opening communicated with the internal energy dissipation pipe. The auxiliary energy dissipation components and the main energy dissipation components are matched and alternately distributed to form an arc-shaped concave-convex structure, multi-angle deformation type energy dissipation is provided, and deformation impact in a tunnel is resisted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel engineering, and in particular to a tunnel multi-level buffer support structure and a construction method thereof. Background Art

[0002] At present, when constructing soft rock large deformation tunnels, traditional initial support methods do use high-rigidity steel frames, high-strength concrete spraying, increased reserved deformation, multiple supports, and reinforced concrete secondary lining. These measures are based on the concept of "strong support and hard top", that is, trying to resist the deformation of soft rock by enhancing the rigidity and strength of the support structure. However, in actual projects, this method often cannot solve the problem of large deformation of soft rock well, and may even cause the support structure to be damaged due to large deformation, resulting in economic losses and construction delays.

[0003] The defects of tunnel hard support are mainly reflected in the following aspects: Stiffness mismatch: The deformation characteristics of soft rock do not match the stiffness of the hard support structure. When the soft rock undergoes large deformation, the hard support structure may be destroyed because it cannot adapt to this deformation.

[0004] Stress concentration: The hard support structure forms a rigid boundary around the tunnel, which may cause stress concentration on the contact surface between the support structure and the surrounding rock, thereby increasing the risk of failure.

[0005] High cost: The use of materials such as high-strength concrete and steel bars increases the cost of the project.

[0006] Construction difficulty: Multiple supports and secondary lining increase the difficulty and complexity of construction, which may lead to extended construction period.

[0007] Based on this, it is necessary to study a tunnel multi-level buffer support structure and its construction method. Summary of the invention

[0008] In view of this, the purpose of the present invention is to provide a tunnel multi-level buffer support structure and a construction method thereof, which effectively solves the problem that the existing tunnel multi-level buffer support structure is easily damaged due to large deformation of soft rock.

[0009] To achieve the above object, the technical solution adopted by the present invention is: a tunnel multi-level buffer support structure, including a ring support frame, a transverse support beam, a main energy dissipation component and a secondary energy dissipation component, the ring support frame is arranged in multiple groups at intervals, the transverse support beam is fixed to the outer wall of the ring support frame in the transverse direction, and is combined to form a support frame foundation; The main energy dissipation component includes a main energy dissipation body, an energy dissipation pipe and a filling material; a holder is arranged on the transverse support beam, the main energy dissipation body is a hollow structure with closed ends, the upper part of the main energy dissipation body is a convex structure protruding upward, and the lower part thereof is adapted to be fixedly mounted in the holder, and the energy dissipation pipe is arranged in the middle area of ​​the main energy dissipation body through the filling material; The auxiliary energy dissipation component comprises an auxiliary energy dissipation body, a main energy dissipation body and a transverse support beam are combined together to form a main energy dissipation unit, and the auxiliary energy dissipation body adapter is mounted between adjacent main energy dissipation units; The main energy dissipation body is provided with a grouting port connected to the internal energy dissipation pipe.

[0010] Furthermore, the auxiliary energy dissipation body is a conical structure, the lower part of which is adapted to be clamped between the transverse support beams, and the upper part is an inwardly concave groove structure, and the groove structure and the convex structure form an energy dissipation body that is concavely configured on the outside of the support frame foundation.

[0011] Furthermore, the groove structure and the protrusion structure are both arc-shaped structures.

[0012] Furthermore, energy dissipation grooves are provided on the mating surfaces of the auxiliary energy dissipation body and the main energy dissipation body.

[0013] Furthermore, the energy dissipation pipe is a hollow structure, which is assembled in the middle of the main energy dissipation body by filling materials on all sides. Partitions are arranged on the energy dissipation pipe at intervals, and hollow grouting areas and filling trough areas are alternately formed between the partitions. The energy dissipation pipe is provided with a connecting hole connecting the hollow grouting area and the inner cavity of the energy dissipation pipe.

[0014] Furthermore, the energy dissipation pipe is provided with inner ribs and reinforcing ribs inside, the inner ribs are arranged along the radial direction of the energy dissipation pipe, and the ends of the inner ribs do not contact each other, and the reinforcing ribs connect the inner ribs.

[0015] Furthermore, the energy dissipation body includes a base body and a cover body, and the cover body is an upwardly protruding arc structure and is fixed to the upper part of the base body by bolts.

[0016] Furthermore, the filling material is an elastic material.

[0017] Furthermore, the cross section of the ring support frame is an I-shaped structure, and the cross section of the transverse support beam is a U-shaped structure.

[0018] Furthermore, a construction method of a tunnel multi-level buffer support structure comprises the following steps: Step 1: Set up the support frame foundation The ring support frame and the cross support beam combination are erected in the tunnel; Step 2: Install the main energy dissipation components Assemble the main energy dissipation components in sections in the transverse support beam in sequence, so that the grouting ports of each section of the main energy dissipation components are connected; Step 3: Install the auxiliary energy dissipation components The auxiliary energy dissipation component is fixedly assembled between the main energy dissipation body and the transverse support beam; Step 4: First concrete mortar pouring Inject concrete mortar into the gap between the main energy dissipation body and the tunnel to fill the gap between the main energy dissipation body and the tunnel; Step 5: Secondary Grouting Inject mortar into the energy dissipation pipe to fill the internal cavity of the main energy dissipation body.

[0019] The beneficial effect of the above technical solution is as follows: the present invention adopts a ring support frame and a transverse support beam combined structure as a support basis in the structure, forms an internal support structure in the tunnel, forms a holder on the transverse support beam based on the structure, mounts the main energy dissipation component in the holder, and then assembles the auxiliary energy dissipation component between the main energy dissipation body and the transverse support beam. The surface of the main energy dissipation component is an outwardly protruding arc structure, and the interior is connected to the energy dissipation pipe through elastic energy-absorbing filling material. The arc-shaped protruding structure can absorb the load generated from the outside from different angles, and after being deformed itself, the load is transferred to the filling material. When the filling material is squeezed and deformed, the energy is absorbed by the energy dissipation pipe.

[0020] At the same time, the auxiliary energy dissipation component cooperates with the main energy dissipation component, and an inner concave structure is formed in the middle. The two are alternately distributed to form an arc-shaped concave-convex structure, which can provide deformation-type energy dissipation from various angles. When deformation impact occurs in the tunnel, it can provide deformable resistance to loads at different angles, provide better stability, and avoid carrying the load to the main body inside the tunnel.

[0021] Structurally, the present invention configures hollow grouting areas and filling trough areas at intervals in the main energy dissipation component, so that a relatively stable rigid support can be formed through grouting after resisting the load, thereby providing a stable support foundation for later use.

[0022] The present invention provides elastic support for tunnel deformation in the early stage by configuring elastic energy dissipation support structures and gaps at intervals in the implementation structure. After the deformation is completed, the gaps are filled by grouting to form rigid support, which provides guarantee for later protection, can adapt to deformation impact in the tunnel, and ensure construction safety.

[0023] In summary, the surface of the main energy dissipation body of the present invention is designed to be an arc-shaped structure protruding outward, which can absorb external loads from multiple angles. The interior is connected to the energy dissipation pipe through elastic energy-absorbing filling materials to achieve energy absorption and dissipation. The auxiliary energy dissipation component cooperates with the main energy dissipation component to form an inner concave structure. The two are alternately distributed to form an arc-shaped concave-convex structure, providing multi-angle deformation-type energy dissipation to resist the deformation impact in the tunnel; through the combination of elasticity and rigidity, the elastic energy dissipation support structure and gaps arranged at intervals in the early stage provide elastic support for tunnel deformation. After the deformation is completed, the gaps are filled by grouting to form a rigid support to ensure the long-term stability of the tunnel structure and construction safety; it can adapt well to the deformation impact in the tunnel, provide safe and stable support and protection for tunnel construction, and provide an effective solution for tunnel construction that can both resist deformation impact and ensure structural stability through the unique support and energy dissipation structure design. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the implementation structure of the present invention; Figure 2 It is a schematic diagram of the main structure of the present invention; Figure 3 It is a front view structural schematic diagram of the present invention; Figure 4 It is a schematic diagram of the construction structure of the present invention; Figure 5 Structural diagram of the main energy dissipation component Figure 6 Schematic diagram of the internal structure of the energy dissipation tube; Figure 7 Schematic diagram of the connection structure of the main energy dissipation components.

[0025] Figure numerals: 1-ring support frame, 2-transverse support beam, 3-main energy dissipation component, 31-main energy dissipation body, 32-energy dissipation pipe, 321-tube body, 322-inner rib, 323-reinforcement rib, 33-filling material, 34-cover body, 35-staggered mouth, 36-partition, 37-hollow grouting area, 38-filling trough area, 39-connecting port, 4-auxiliary energy dissipation component, 5-grouting port, 6-combined beam, 7-baffle, 8-bolt, 9-energy dissipation trough. DETAILED DESCRIPTION

[0026] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments: Embodiment 1. This embodiment aims to provide a tunnel multi-level buffer support structure and a construction method thereof, which are mainly used for tunnel construction. During the excavation process of soft rock tunnels, large deformations are prone to occur, resulting in instability, cracking, and even collapse. In order to cope with this situation, this embodiment aims at the problem that the tunnel multi-level buffer support structure is easily damaged due to large deformation of soft rock. This embodiment provides a tunnel multi-level buffer support structure to improve the stability and safety of tunnel construction in soft rock formations during tunnel excavation.

[0027] like Figure 1-2 As shown in , a multi-level buffer support structure for a tunnel includes a ring support frame 1, a transverse support beam 2, a main energy dissipation component 3 and an auxiliary energy dissipation component 4. The ring support frame 1 is arranged in multiple groups at intervals, and the transverse support beam 2 is fixed to the outer wall of the ring support frame 1 in the transverse direction, and is combined to form a support frame foundation; during implementation, the cross section of the ring support frame 1 is an I-shaped structure, and the cross section of the transverse support beam 2 is a U-shaped structure. The ring support frame 1 can be composed of multiple sections, and adjacent ring support frames 1 are spliced ​​by connecting pieces extending outward, and then fixed and combined by bolts. The transverse support beam 2 is a U-shaped channel steel structure, which has a card slot inside, and is fixed to the surface of the ring support frame 1 by welding. During implementation, the transverse support beam 2 can be a structure composed of multiple sections, and the splicing position can be set in the area where the support frame is replaced.

[0028] like Figure 4-5 As shown in the figure, the main energy dissipation component 3 includes a main energy dissipation body 31, an energy dissipation pipe 32 and a filling material 33; a holder is arranged on the transverse support beam 2, and the main energy dissipation body 31 is a hollow structure with closed ends and an interior, and the main energy dissipation body 31 is adapted to be installed in the holder, and its overall shape has a square structure in the lower part and an upwardly protruding arc structure in the upper part, and the two ends are blocked by side panels, and there is a hollow structure inside.

[0029] like Figure 4 As shown in , the upper part of the main energy dissipation body 31 is a convex structure protruding upward, and the lower part thereof is adapted to be fixedly mounted in the holder, and the energy dissipation pipe 32 is arranged in the middle area of ​​the main energy dissipation body 31 through the filling material 33; the filling material 33 is an elastic material, and the elastic material can be deformed and absorb energy, such as a rubber material, which can be compressed and absorb external loads. Specifically, the filling material 33 is arranged in the upper area, and its upper part is adapted to the arc-shaped structure protruding upward. In this embodiment, the upper part of the main energy dissipation body 31 is an arc-shaped structure, which can absorb deformation from all directions to dissipate energy. The filling material 33 can support from the inside and provide support and energy dissipation for the deformation of the main energy dissipation body 31. Finally, after the filling material 33 is deformed, the load is transferred to the hollow energy dissipation pipe 32, so as to achieve the purpose of multi-angle and multi-level wave absorption and energy dissipation.

[0030] like Figure 5As shown in the figure, the main energy dissipation body 31 structurally includes a seat body and a cover body 34. The cover body 34 is an upwardly protruding arc structure and is connected to the seat body through a staggered opening. It is fixed and assembled to the upper part of the seat body by bolts, and a connection is established with the socket through the seat body structure. Subsequently, the filling material 33 and the energy dissipation pipe 32 are arranged in the seat body, and then the cover body is fixedly assembled on the seat body to realize the assembly of the energy dissipation body.

[0031] The surface of the main energy dissipation body 31 is designed as an outwardly convex arc structure, which can absorb external loads from multiple angles. The interior is connected to the energy dissipation pipe 32 through elastic energy-absorbing filling material 33 to achieve energy absorption and dissipation.

[0032] The auxiliary energy dissipation component 4 includes an auxiliary energy dissipation body, a main energy dissipation body 31 and a transverse support beam 2 are combined to form a main energy dissipation unit, and the auxiliary energy dissipation body is adapted to be clamped between adjacent main energy dissipation units; the auxiliary energy dissipation body is a conical structure, and its lower part is adapted to be clamped between the transverse support beams 2. In the clamping structure, bolt holes can be arranged on the back side of the auxiliary energy dissipation body, and the baffle 7 is arranged on the back side of the transverse support beam 2. The auxiliary energy dissipation body is reinforced and fixed from the back side by bolts 8. Of course, the stability of the auxiliary energy dissipation body can also be achieved by welding or by fixing the bolt baffle. The stable structure is that the bottom of the auxiliary energy dissipation body is fixed, the upper part of the auxiliary energy dissipation body is clamped, and the upper part of the auxiliary energy dissipation body is an inwardly concave groove structure. The groove structure and the convex structure form an energy dissipation body that is concavely and convexly configured on the outside of the support frame foundation.

[0033] Both the groove structure and the convex structure are arc-shaped structures. The auxiliary energy dissipation component 4 cooperates with the main energy dissipation component 3, and an inner concave structure is formed in the middle. The two are alternately distributed to form an arc-shaped concave-convex structure, which can provide deformation-type energy dissipation from various angles. When deformation impact occurs in the tunnel, it can provide deformable resistance to loads at different angles, provide better stability, and avoid transferring the load to the main body inside the tunnel.

[0034] The auxiliary energy dissipation component 4 cooperates with the main energy dissipation component 3 to form an inner concave structure, and the two are alternately distributed to form an arc-shaped concave-convex structure, providing multi-angle deformation-type energy dissipation to resist deformation impact in the tunnel.

[0035] In the implementation of this embodiment, a hollow structure is formed in the main energy dissipation body 31 through the hollow energy dissipation tube 32. The hollow structure can receive excessive deformation. After the deformation is completed, a solid rigid support point is formed inside to enhance the overall rigidity. That is, the main energy dissipation body 31 in this embodiment has a variable deformation body, which can cope with deformation in the initial stage, and can strengthen the main structure in the later stage of deformation, and provide greater rigidity to ensure later use.

[0036] This embodiment also provides a construction method for a tunnel multi-level buffer support structure, comprising the following steps: Step 1: Set up the support frame foundation The ring support frame 1 and the transverse support beam 2 are assembled and erected in the tunnel; during construction, the ring support frame 1 is first constructed at intervals in the tunnel, and then the transverse support beam 2 is fixed to the outer surface of the ring support frame 1, or the ring support frame 1 and the transverse support beam 2 are assembled in advance outside to form a multi-section assembly frame, and then the assembly frame is moved into the tunnel by a mobile tooling, and then the multi-section assembly beams are connected together by assembling them on the transverse support beam 2.

[0037] Step 2: Install the main energy dissipation component 3 The main energy dissipation components 3 are assembled in sections in the transverse support beam 2 in sequence, so that the grouting ports of each section of the main energy dissipation components 3 are connected; the grouting ports are adapted to the assembly relationship when connected, and sealing gaskets are applied in the set structure, and the adjacent main energy dissipation components 3 are tightly fitted and establish a fixed relationship with the holder, such as welding.

[0038] When implementing Figure 3 As shown in , the structure can be pre-assembled with the composite beam 6 of step one and constructed as an integrated structure, and then transported into the tunnel.

[0039] Step 3: Install the auxiliary energy dissipation component 4 The auxiliary energy dissipation component 4 is fixedly assembled between the main energy dissipation body 31 and the transverse support beam 2; during construction, a support point is provided on the inner side of the transverse support beam 2 through a baffle, and the auxiliary energy dissipation component 4 is arranged on the inner side of the transverse support beam 2. The two are mutually limited and combined and fixedly connected by bolts.

[0040] For this fixing method, the present embodiment can configure the connection between the auxiliary energy dissipation component 4 and the main energy dissipation component 3 as an inclined surface compression fit, that is, when the auxiliary energy dissipation component 4 is tightened by bolts, the main energy dissipation component 3 can be further stabilized.

[0041] The main energy dissipation component 3 is clamped in the clamping seat, and then the auxiliary energy dissipation component 4 is assembled between the main energy dissipation body 31 and the cross support beam 2. Structurally, the surface of the main energy dissipation component 3 is an outwardly protruding arc structure, and the interior is connected to the energy dissipation pipe 32 through an elastic energy-absorbing filling material 33. The arc-shaped protruding structure can absorb the external load from different angles, and after deforming itself, it transfers the load to the filling material 33. When the filling material 33 is squeezed and deformed, the energy is absorbed by the energy dissipation pipe 32.

[0042] Step 4: First concrete mortar pouring Concrete mortar is injected into the gap between the energy dissipation pipe 32 and the main energy dissipation body 31 and the tunnel. During construction, the construction is carried out in sections, and the two ends of the construction section are closed by templates. Then, mortar is injected into the gap between the energy dissipation pipe 32 and the main energy dissipation body 31 and the tunnel through the grouting pipe. After solidification, the other section is constructed. In principle, the construction method of first the two sides and then the middle can be used to fill the gap between the energy dissipation pipe 32 and the main energy dissipation body 31 and the tunnel with mortar.

[0043] Through the first grouting, the gap between the main energy dissipator 31 and the tunnel is filled with concrete mortar. When the tunnel is deformed, the deformation will be transferred to the main energy dissipator 31 and the auxiliary energy dissipator through the injected mortar, avoiding rigid strain.

[0044] At the same time, the auxiliary energy dissipation component 4 cooperates with the main energy dissipation component 3, and an inner concave structure is formed in the middle thereof. The two are alternately distributed to form an arc-shaped concave-convex structure, which can provide deformation-type energy dissipation from various angles. When a deformation impact occurs in the tunnel, it can provide deformable load resistance at different angles, provide better stability, and avoid transmitting the load to the main body inside the tunnel.

[0045] Step 5: Secondary Grouting Inject mortar into the energy dissipation pipe 32 to fill the internal cavity of the main energy dissipation body 31. After the strain period, fill the internal gap of the main energy dissipation body 31 with mortar to make the internal structure more stable and ensure the later support effect.

[0046] Embodiment 2: This embodiment further illustrates the implementation structure of the energy dissipation pipe 32.

[0047] like Figure 5-7 As shown in , the energy dissipation pipe 32 of this embodiment is a hollow structure, which is assembled in the middle of the main energy dissipation body 31 through the filling material 33 on all sides. The energy dissipation pipe 32 is provided with partitions 36 at intervals, and hollow grouting areas 37 and filling trough areas 38 are formed alternately between the partitions 36. The energy dissipation pipe 32 is provided with a connecting hole 39 connecting the hollow grouting area and the inner cavity of the energy dissipation pipe 32. In the early stage of strain, the internal structure can resist a certain load. After strain, mortar is added to the hollow grouting area and the inside of the energy dissipation pipe 32, so that a mortar support foundation distributed at intervals can be formed inside the main energy dissipation body 31 to ensure the support needs in the later stage.

[0048] like Figure 6 The tube body 321 of the energy dissipation tube shown in the figure is provided with inner ribs 322 and reinforcing ribs 323. The inner ribs 322 are arranged along the radial direction of the energy dissipation tube 32, and the ends of the inner ribs 322 do not contact each other. The reinforcing ribs 323 connect the inner ribs. In this embodiment, the reinforcing ribs are non-continuous rod-shaped structures.

[0049] like Figure 7As shown in the structure, this embodiment can form a relatively stable rigid support through grouting after resisting the load by dissipating the hollow grouting area 37 and the filling trough area 38 at intervals in the main energy dissipation component 3, providing a stable support foundation for later use. The hollow grouting area 37 and the filling trough area 38 are alternately distributed, and the elastic energy dissipation support structure and the gap are arranged at intervals to provide elastic support for tunnel deformation in the early stage, and after the deformation is completed, the gap is filled by grouting to form a rigid support, which provides a guarantee for later protection, can adapt to the deformation impact in the tunnel, and ensure construction safety.

[0050] Embodiment 3: This embodiment further illustrates the implementation structure of the auxiliary energy dissipation body.

[0051] As shown in the figure, the main energy dissipation body 31 is provided with a grouting port connected to the internal energy dissipation pipe 32, and the matching surface of the auxiliary energy dissipation body and the main energy dissipation body 31 is provided with an energy dissipation groove 9, and the energy dissipation groove 9 is also injected with mortar after the later strain to form an energy dissipation zone between the main energy dissipation body and the auxiliary energy dissipation body.

[0052] The embodiments of the present invention described above do not constitute a limitation on the protection scope of the present invention. The basic concept of the present invention is to provide elastic support for tunnel deformation through the combination of elasticity and rigidity, and the elastic energy dissipation support structure and gaps are arranged at intervals in the early stage. After the deformation is completed, the gaps are filled with grouting to form a rigid support to ensure the long-term stability of the tunnel structure and construction safety. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. A multi-level buffer support structure for a tunnel, characterized in that: It includes a ring support frame, a transverse support beam, a main energy dissipation component and a secondary energy dissipation component. The ring support frame is arranged in multiple groups at intervals. The transverse support beam is fixed to the outer wall of the ring support frame in the transverse direction and combined to form a support frame foundation. The main energy dissipation component includes a main energy dissipation body, an energy dissipation pipe and a filling material; a holder is arranged on the transverse support beam, the main energy dissipation body is a hollow structure with closed ends, the upper part of the main energy dissipation body is a convex structure protruding upward, and the lower part thereof is adapted to be fixedly mounted in the holder, and the energy dissipation pipe is arranged in the middle area of ​​the main energy dissipation body through the filling material; The auxiliary energy dissipation component comprises an auxiliary energy dissipation body, a main energy dissipation body and a transverse support beam are combined together to form a main energy dissipation unit, and the auxiliary energy dissipation body adapter is mounted between adjacent main energy dissipation units; The main energy dissipation body is provided with a grouting port connected to the internal energy dissipation pipe.

2. The multi-level buffer support structure for a tunnel according to claim 1 is characterized in that: The auxiliary energy dissipation body is in a conical structure, the lower part of which is adapted to be clamped between the transverse support beams, and the upper part is an inwardly concave groove structure, and the groove structure and the convex structure form an energy dissipation body that is concavely and convexly configured on the outside of the support frame foundation.

3. The multi-level buffer support structure for a tunnel according to claim 2 is characterized in that: The groove structure and the protrusion structure are both arc-shaped structures.

4. The multi-level buffer support structure for a tunnel according to claim 1, characterized in that: An energy dissipation groove is arranged on the matching surface of the auxiliary energy dissipation body and the main energy dissipation body.

5. The multi-level buffer support structure for a tunnel according to claim 1, characterized in that: The energy dissipation pipe is a hollow structure, which is assembled in the middle of the main energy dissipation body by filling materials on all sides. Partitions are arranged on the energy dissipation pipe at intervals, and hollow grouting areas and filling trough areas are alternately formed between the partitions. The energy dissipation pipe is provided with a connecting hole connecting the hollow grouting area and the inner cavity of the energy dissipation pipe.

6. The multi-level buffer support structure for a tunnel according to claim 1, characterized in that: The energy dissipation pipe is provided with inner ribs and reinforcing ribs inside. The inner ribs are arranged along the radial direction of the energy dissipation pipe, and the ends of the inner ribs do not contact each other. The reinforcing ribs connect the inner ribs.

7. The multi-level buffer support structure for a tunnel according to claim 1, characterized in that: The energy dissipation body comprises a seat body and a cover body. The cover body is in an upwardly convex arc structure and is fixedly assembled on the upper part of the seat body by bolts.

8. The multi-level buffer support structure for a tunnel according to any one of claims 1 to 7, characterized in that: The filling material is an elastic material.

9. The multi-level buffer support structure for a tunnel according to claim 1, characterized in that: The cross section of the ring support frame is an I-shaped structure, and the cross section of the transverse support beam is a U-shaped structure.

10. The construction method of the tunnel multi-level buffer support structure according to claim 1, characterized in that: The steps include: Step 1: Set up the support frame foundation The ring support frame and the cross support beam combination are erected in the tunnel; Step 2: Install the main energy dissipation components Assemble the main energy dissipation components in sections in the transverse support beam in sequence, so that the grouting ports of each section of the main energy dissipation components are connected; Step 3: Install the auxiliary energy dissipation components The auxiliary energy dissipation component is fixedly assembled between the main energy dissipation body and the transverse support beam; Step 4: First concrete mortar pouring Inject concrete mortar into the gap between the main energy dissipation body and the tunnel to fill the gap between the main energy dissipation body and the tunnel; Step 5: Secondary Grouting Inject mortar into the energy dissipation pipe to fill the internal cavity of the main energy dissipation body.