Advanced grouting repair method for large-deformation soft rock roadway

Through the advance grouting repair method and combined with the dynamic support structure, the problems of high cost, complex construction and insufficient surrounding rock strength in the repair of large-deformed soft rock tunnels are solved, and efficient reinforcement and stability of the surrounding rock in the tunnel are achieved to ensure that Repaired tunnel safety and durability.

CN118933905APending Publication Date: 2024-11-12宁夏红墩子煤业有限公司

Patent Information

Application Number
CN202411337603.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing technology has high cost, high risk, long construction time, weak support strength and secondary rework problems when repairing large-deformed soft rock tunnels, and traditional methods are difficult to achieve the maximum integrity and strength improvement of surrounding rock.

Method used

Adopting the advance grouting repair method, by evaluating the deformation index of the surrounding rock of the tunnel, determining the drilling angle and number of grouting holes, performing pre-grouting reinforcement, combining the installation of active and passive support structures, dynamically adjusting the support parameters to realize the tunnel High strength reinforcement and stability improvement of surrounding rocks.

Benefits of technology

The rapid, safe and efficient repair of large-deformed soft rock tunnels has been achieved, the self-stabilization ability and load bearing strength of the tunnel surrounding rock has been improved, material loss and secondary re-repair risks have been reduced, and the integrity and stability of the tunnel after repair have been ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933905A_ABST
    Figure CN118933905A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of soft rock roadway repair, and discloses an advanced grouting repair method for a large-deformation soft rock roadway, which comprises the following steps: S1, introducing an evaluation parameter P, and classifying roadways in a to-be-repaired area according to an evaluation model; s2, according to the type of the roadway, the drilling angle of a grouting hole and the number of times of grouting are determined; s3, punching, pre-grouting and hole sealing are conducted on the to-be-repaired area according to the step S2; and S4, the inner wall of the roadway is cleaned, and the shrinkage ratio of roadway deformation is repaired to 1. According to the dynamic advanced pre-grouting repair method for the large-deformation soft rock roadway, through roadway deformation evaluation, pre-grouting filling and cementation reinforcement of loose surrounding rock, a high-strength reinforced arch is formed, then cleaning repair is conducted, active / passive reinforcement supporting is matched, and finally the purpose of rapid, safe and efficient repair of the large-deformation soft rock roadway is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of soft rock tunnel repair, in particular to an advanced grouting repair method for a large-deformation soft rock tunnel. Background Art

[0002] At present, as the depth of coal mining in western my country increases year by year, soft rock tunnels in the west often experience continuous deformation and damage under high stress, and the tunnel cross-section continues to shrink. In order to ensure the use function of the tunnel, the tunnel cross-section must be enlarged and the tunnel support must be re-performed. For this type of tunnel, the traditional technical method is to repair it by cleaning first and then supporting it. This type of repair method has the problems of high cost, high risk, complicated support procedures, long construction time, and high support labor intensity. In addition, during the construction process, the tunnel surrounding rock is affected by the combined effects of construction and ground stress, which will inevitably cause additional deformation and crack development in the adjacent surrounding rock, and the maximum integrity of the soft rock tunnel surrounding rock cannot be guaranteed. The rock formation strength is greatly reduced, resulting in technical defects such as difficulty in tunnel repair and weakened support strength.

[0003] In response to this type of engineering problem and the defects of current repair technology solutions, a repair method with mature technology, simple structure, simple construction operation, low manufacturing cost and dynamic support that can adapt to the deformation of tunnel surrounding rock is proposed based on the analysis of the mechanical mechanism of deformation and failure of soft rock tunnel surrounding rock and the mechanical principle of tunnel surrounding rock control. The purpose is to economically and effectively realize the deformation repair of large deformation soft rock tunnel surrounding rock, which is a key technology urgently needed for safe and efficient production in soft rock mining areas in western my country.

[0004] In order to repair the roadway roof fall disaster, Chinese patent publication number CN 106089246 A discloses a roadway roof fall disaster repair method based on grouting anchor rods, which mainly classifies the surrounding rock by judging its stability, and then takes different angles to drill holes and inject grout according to different categories, and finally repairs the roadway with roof fall. This patent provides a roadway roof fall treatment method for grouting to fill and reinforce the empty top area and collapsed gangue. Although it can achieve simple repair of roadway roof fall, this method can only repair roadway roof fall, and cannot achieve cleaning and repair of the entire deformed roadway, and continuing to use the failed anchor rods cannot achieve the expected support effect, so this method still has certain defects and shortcomings.

[0005] In response to the repair problem of the tunnel along the high ground pressure three soft coal seam, Chinese patent publication number CN 113107489A discloses a method for pre-grouting reinforcement of the tunnel along the high ground pressure three soft coal seam. By selecting suitable grouting materials to grout the coal rock mass, the tunnel is transformed from traditional post-repair to pre-active reinforcement, ensuring the support stability of the tunnel along the empty space. Although the patent proposes such a pre-grouting reinforcement method, it is not adapted to different geological conditions, so that the method is limited to being used only under similar engineering geological conditions, and the grouting reinforcement method is limited to traditional steel pipe grouting, grouting anchor rod grouting and grouting anchor cable grouting. In the coal rock mass area with developed cracks and soft and broken, the slurry is easy to diffuse, resulting in large consumption, serious waste and it is difficult to reach the predetermined grouting pressure, so the pre-grouting reinforcement method still has certain limitations.

[0006] Due to the large deformation, long duration and large loosening range of the surrounding rock of this type of soft rock tunnel, the currently used soft rock tunnel repair method has poor pertinence and low efficiency in reinforcing the broken surrounding rock. If it is not repaired in time after deformation, it will seriously affect the overall stability of the tunnel. In addition, the deformation of soft rock tunnels in different sections is different. If a single repair plan is used blindly, the repair effect will be too poor in areas with severe deformation, and even lead to the emergence of secondary repair problems. In areas with lighter deformation, there will be excessive support, waste of materials, and greatly increased cost. Therefore, in order to solve the problem of repairing soft rock tunnels with large deformation, it is necessary to adopt pre-grouting reinforcement measures to improve the integrity of the surrounding rock, enhance the efficiency and safety of construction, ensure the overall strength of the surrounding rock, and avoid the emergence of secondary large deformation problems. At the same time, it should have a flexible and dynamic support parameter adjustment mechanism to achieve the engineering goals of reducing costs and increasing efficiency under the premise of ensuring the quality and quantity of the repair construction. Summary of the invention

[0007] In order to solve the technical problems raised in the background technology, the present invention provides an advanced grouting repair method for a large deformation soft rock tunnel.

[0008] The present invention is implemented by the following technical solution: A method for repairing a large-deformation soft rock tunnel by advanced grouting, comprising the following steps:

[0009] Step S1, introducing the evaluation parameter P, and classifying the lanes in the area to be repaired according to the evaluation model;

[0010] Step S2, determining the drilling angle of the grouting hole and the number of grouting times according to the tunnel type;

[0011] Step S3, performing pre-grouting and hole sealing on the area to be repaired according to step S2;

[0012] Step S4, cleaning the inner wall of the tunnel to restore the shrinkage ratio of the tunnel deformation to 1;

[0013] Step S5: Install the active support structure;

[0014] Step S6: Install the passive support structure;

[0015] Step S7: When the repair reaches a cycle step distance of 8 m, remove and transport the waste rock in the roadway, and then repeat Steps S3 - S6.

[0016] Preferably, in Step S1, introduce the evaluation parameter P, and calculate the deformation of the roadway surrounding rock according to the evaluation model, i.e., formula (1);

[0017]

[0018] In the formula: D is the deformation index of the roadway surrounding rock; P is the evaluation parameter for the classification of surrounding rock deformation; R is the RQD value of the rock quality index; f is the lithology Prandtl coefficient; S is the shrinkage ratio of the roadway deformation, and its value is the ratio of the current value to the designed value of the roadway cross - section size;

[0019] According to the calculated deformation index D of the roadway surrounding rock, different values of the deformation index D are used to evaluate the deformation of the surrounding rock of the roadway to be repaired, so as to correspond to different support and repair parameters required for the roadway. The classification criteria are as follows:

[0020] When 8 < D <= 10, the roadway belongs to a slightly deformed roadway;

[0021] When 6 < D <= 8, the roadway belongs to a generally deformed roadway;

[0022] When 4 < D <= 6, the roadway belongs to a large - deformed roadway;

[0023] When 2 < D <= 4, the roadway belongs to a severely deformed roadway;

[0024] When 0 <= D <= 2, the roadway belongs to a scrapped roadway.

[0025] Preferably, in Step S2, drill a hole with a depth of 8 m along the radial direction on the roadway cross - section plane, and the extension direction of the hole forms an angle α with the roadway axial plane;

[0026] When the roadway belongs to a slightly deformed roadway, no grouting repair is required;

[0027] When the roadway belongs to a generally deformed roadway, α = 15°, and the number of segmented grouting is 1;

[0028] When the roadway belongs to a large - deformed roadway, α = 25°, and the number of segmented grouting is 2;

[0029] When the roadway belongs to a severely deformed roadway, α = 35°, and the number of segmented grouting is 3;

[0030] When the tunnel is a scrapped tunnel, no grouting repair is required (not applicable).

[0031] Preferably, in step S3, the grouting holes are subjected to the "three-part grouting method" in groups, i.e., time-division grouting, segmented grouting, and pressure-division grouting; in S3, after the grouting is completed, the grouting holes are sealed with corks wrapped in jute.

[0032] Preferably, the time-sharing grouting operation is as follows: there is a certain interval between the grouting times of two adjacent groups of grouting holes, and the grouting holes are grouted in the order from bottom to top, from both sides to the center, and every other grouting hole. The intermittent time of the intermittent grouting method is controlled at 1 to 2 hours, leaving a certain solidification time for the slurry reinforcement, which is beneficial for the slurry to fully penetrate, fill and solidify in the broken surrounding rock of the soft rock tunnel, thereby improving the reinforcement effect of the tunnel.

[0033] Preferably, the operation of the segmented grouting is as follows: the grouting area is divided into several segments according to the length of the grouting segment and the number of segmented grouting times, the slurry is pumped into the grouting hole, and the grouting is started from the grouting point farthest from the grouting device. After the grouting of the initial segment is completed, the grouting device is moved to the grouting point of the next segment and the injection is continued. In the process of each grouting segment, all grouting work must be completed before the grouting agent begins to harden, and in order to maintain the uniformity of the grouting, the flow rate and speed of the grouting agent should be controlled during each grouting to avoid the generation of bubbles and ensure the quality of the grouting.

[0034] Preferably, when grouting is performed at different grouting points in each section, the grouting effect, diffusion range, economy and other factors are considered, and the slurry injection pressure at each grouting point needs to be controlled to ensure that the broken surrounding rock forms a high-strength reinforced arch of surrounding rock with good quality;

[0035] During grouting, different grouting pressures are implemented in each segmented grouting area through the adjustment of the grouting pressure regulating valve: the pressure of the first grouting is controlled at 1.5MPa, and the second grouting is carried out after waiting for about 1 hour for the strength of the cement stone body to increase. The pressure of the second grouting is controlled at 2MPa, and the pressure of the third grouting is controlled at 2.5MPa. Among them, the pressure needs to be gradually adjusted from small to large during each grouting section.

[0036] Preferably, in step S4, the tunnel surrounding rock can be cleaned without waiting for the pre-injected grout to completely solidify. The period of time when the pneumatic pick is used for cleaning is also the time reserved for slurry reinforcement, which can improve the tunnel repair efficiency by about 20%.

[0037] Preferably, step S5 is operated as follows: when the cleaning step distance reaches the designed spacing between anchor rods / cables, the rock mass that meets the size standard is re-drilled, the anchor rods / cables are inserted, the tray and nuts are re-installed and prestress is applied, and the construction of the new active support is completed;

[0038] Preferably, the operation of step S6 is as follows: after the construction of the anchor rods and anchor cables is completed, a U-shaped steel shed is erected inside the tunnel, and grouting is sprayed on the inner surface of the tunnel to complete the construction of passive support.

[0039] Preferably, in step S7, tunnel expansion and repair, support installation and advance pre-grouting can be carried out simultaneously at different locations, and the three process working surfaces are advanced forward synchronously, which can greatly improve the repair efficiency of large deformation soft rock tunnels.

[0040] In S7, when the first repair cycle is completed, the grouting high-strength reinforcement arch is about 9 to 10 meters. The reasons for choosing to carry out the repair cycle in advance are: 1. To ensure the continuity and integrity of the entire radial direction of the compression zone; 2. To improve the efficiency of tunnel cleaning and repair, and to give the slurry in the subsequent cycles sufficient time to cement the loose surrounding rock; 3. To maintain the continuity of the construction work, reduce the mutual influence of each construction team, and reduce the loss and waste of materials.

[0041] Compared with the prior art, the present invention has the following beneficial effects:

[0042] The dynamic advance pre-grouting repair method for large deformation soft rock tunnels proposed in the present invention is to form a high-strength reinforced arch through tunnel deformation evaluation, pre-grouting filling, and cementation reinforcement of loose surrounding rock, and then clean and repair it, and then cooperate with active / passive reinforcement support to finally achieve the purpose of completing the rapid, safe and efficient repair of large deformation soft rock tunnels. This method is a repair method with simple process, safe operation, rapid repair and reliable reinforcement.

[0043] The advanced pre-grouting repair method proposed in the present invention can use slurry to cement the loose and broken soft rock into a whole, forming a whole high-strength grouting reinforcement arch on the surrounding rock section, greatly improving the self-stabilizing ability and bearing strength of the surrounding rock of the deformed tunnel, preventing the further deformation of the surrounding rock and the continuous shrinkage of the tunnel, and while improving the tunnel support strength, it also provides construction premise and safety guarantee for the cleaning and repair of the soft rock tunnel;

[0044] The dynamic repair method of the soft rock tunnel with large deformation is applicable to the present invention. The repair support parameters can be dynamically adjusted according to different deformation conditions encountered in different positions of the tunnel and during the construction process. The repair construction efficiency can be improved while the surrounding rock of the tunnel is consolidated by grouting in advance, and the loss of materials and the probability of secondary repair can be reduced. The bearing capacity of the grouting reinforcement arch is greatly improved, the repair process is safer, the integrity of the repaired tunnel is stronger, and the stability is higher. At the same time, the construction process can also well fit the actual on-site conditions of the project.

[0045] The grouting slurry of the present invention not only cements and breaks the surrounding rock, but also blocks the holes and cracks of the rock, isolates the air, and can prevent the surrounding rock from contacting the air and being soaked by water to cause further collapse, solves the problem of continuous reduction in the strength of the tunnel surrounding rock and the recurrence of large deformation of the tunnel after repair, and can also avoid gas leakage and air leakage, and eliminate gas and fire hazards;

[0046] Compared with the traditional method, the repair method proposed by the present invention has clear technical methods and procedures, and the simultaneous advancement of multiple working surfaces in each process solves the problems of low efficiency of traditional processes and long-term operation of construction workers on dangerous working surfaces, which makes personal safety difficult to ensure. While greatly improving the efficiency of tunnel repair, the present invention also makes tunnel repair safer and saves more materials. The cleaning and support teams each perform their duties to ensure that the repaired tunnel is more stable and durable. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] Figure 1 This is a schematic diagram of the distribution of grouting drilling holes in the necked-down section roadway;

[0048] Figure 2 This is a schematic diagram of the initial drilling and grouting effect;

[0049] Figure 3 This is a schematic diagram of the grouting drilling arrangement in the tunnel after one cycle step of excavation.

[0050] Description of main symbols:

[0051] 1. Design boundary of tunnel; 2. Grouting hole; 3. Space inside tunnel; 4. Boundary of tunnel to be repaired; 5. Grouting area; 6. Grouted and consolidated rock mass; 7. Neck section. DETAILED DESCRIPTION

[0052] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.

[0053] Embodiment 1:

[0054] This scheme proposes a method for repairing soft rock tunnels with large deformation by advanced grouting, including the following steps:

[0055] Step S1, introducing the evaluation parameter P, and classifying the lanes in the area to be repaired according to the evaluation model;

[0056] Step S2, determining the drilling angle of the grouting hole and the number of grouting times according to the tunnel type;

[0057] Step S3, performing pre-grouting and hole sealing on the area to be repaired according to step S2;

[0058] Step S4. Clean the inner wall of the roadway to restore the shrinkage ratio of the roadway deformation to 1;

[0059] Step S5. Install the active support structure;

[0060] Step S6. Install the passive support structure;

[0061] Step S7. When the repair reaches a cyclic step distance of 8 m, remove and transport the gangue in the roadway, and then repeat steps S3 - S6.

[0062] S4. After the grouting solidifies, loose rocks around the roadway are consolidated into a stable whole under the action of the grouting liquid. Subsequently, along the designed roadway contour line, use a pneumatic pick to remove the deformed part of the roadway surrounding rock, that is, restore the shrinkage ratio S of the deformation to 1, and cut off the exposed bolts and cables outside the repaired rock mass, as well as clean the deformed and damaged steel mesh, etc. Repeat the above steps to continuously advance the cleaning and repair working face;

[0063] Preferably, in step S1, introduce the evaluation parameter P, and calculate the deformation of the roadway surrounding rock according to the evaluation model, that is, formula (1);

[0064]

[0065] In the formula: D is the deformation index of the roadway surrounding rock; P is the evaluation parameter for the classification of surrounding rock deformation; R is the RQD value of the rock quality index; f is the lithology Prandtl coefficient; S is the shrinkage ratio of the roadway deformation, and its value is the ratio of the current value to the designed value of the roadway cross - section size;

[0066] According to the calculated deformation index D of the roadway surrounding rock, different values of the deformation index D are used to evaluate the deformation of the surrounding rock of the roadway to be repaired, so as to correspond to different support and repair parameters required for the roadway. The classification criteria are as follows:

[0067] When 8 < D <= 10, the roadway belongs to a slightly deformed roadway;

[0068] When 6 < D <= 8, the roadway belongs to a generally deformed roadway;

[0069] When 4 < D <= 6, the roadway belongs to a large - deformed roadway;

[0070] When 2 < D <= 4, the roadway belongs to a severely deformed roadway;

[0071] When 0 <= D <= 2, the roadway belongs to a scrapped roadway.

[0072] Preferably, in step S2, drill holes with a depth of 8 m along the radial direction on the roadway cross - section plane, and the extension direction of the drill holes forms an angle α with the axial plane of the roadway;

[0073] When the tunnel is a slightly deformed tunnel, grouting repair is not required;

[0074] When the tunnel is a general deformation tunnel, α = 15°, and the number of segmented grouting is 1;

[0075] When the tunnel is a large deformation tunnel, α = 25°, and the number of segmented grouting is 2;

[0076] When the tunnel is a severely deformed tunnel, α = 35°, and the number of segmented grouting is 3;

[0077] When the tunnel is a scrapped tunnel, no grouting repair is required (not applicable).

[0078] Preferably, in step S3, the grouting holes are subjected to the "three-part grouting method" in groups, i.e., time-division grouting, segmented grouting, and pressure-division grouting; in S3, after the grouting is completed, the grouting holes are sealed with corks wrapped in jute.

[0079] Preferably, the time-sharing grouting operation is as follows: there is a certain interval between the grouting times of two adjacent groups of grouting holes, and the grouting holes are grouted in the order from bottom to top, from both sides to the center, and every other grouting hole. The intermittent time of the intermittent grouting method is controlled at 1 to 2 hours, leaving a certain solidification time for the slurry reinforcement, which is beneficial for the slurry to fully penetrate, fill and solidify in the broken surrounding rock of the soft rock tunnel, thereby improving the reinforcement effect of the tunnel.

[0080] Preferably, the operation of the segmented grouting is as follows: the grouting area is divided into several segments according to the length of the grouting segment and the number of segmented grouting times, the slurry is pumped into the grouting hole, and the grouting is started from the grouting point farthest from the grouting device. After the grouting of the initial segment is completed, the grouting device is moved to the grouting point of the next segment and the injection is continued. In the process of each grouting segment, all grouting work must be completed before the grouting agent begins to harden, and in order to maintain the uniformity of the grouting, the flow rate and speed of the grouting agent should be controlled during each grouting to avoid the generation of bubbles and ensure the quality of the grouting.

[0081] Preferably, when grouting is performed at different grouting points in each section, the grouting effect, diffusion range, economy and other factors are considered, and the slurry injection pressure at each grouting point needs to be controlled to ensure that the broken surrounding rock forms a high-strength reinforced arch of surrounding rock with good quality;

[0082] During grouting, different grouting pressures are implemented in each segmented grouting area through the adjustment of the grouting pressure regulating valve: the pressure of the first grouting is controlled at 1.5MPa, and the second grouting is carried out after waiting for about 1 hour for the strength of the cement stone body to increase. The pressure of the second grouting is controlled at 2MPa, and the pressure of the third grouting is controlled at 2.5MPa. Among them, the pressure needs to be gradually adjusted from small to large during each grouting section.

[0083] Preferably, in step S4, the tunnel surrounding rock can be cleaned without waiting for the pre-injected grout to completely solidify. The period of time when the pneumatic pick is used for cleaning is also the time reserved for slurry reinforcement, which can improve the tunnel repair efficiency by about 20%.

[0084] Preferably, when the cleaning step distance reaches the designed spacing between anchor rods / cables, the rock mass with the size meeting the standard is re-drilled, the anchor rods / cables are inserted, the tray and nuts are re-installed and prestress is applied to complete the construction of the new active support;

[0085] The operation of step S6 is as follows: after the construction of the anchor rods and anchor cables is completed, a U-shaped steel shed is erected inside the tunnel, and grouting is performed on the inner surface of the tunnel to complete the construction of passive support.

[0086] Preferably, in step S7, tunnel expansion and repair, support installation and advance pre-grouting can be carried out simultaneously at different locations, and the three process working surfaces are advanced forward synchronously, which can greatly improve the repair efficiency of large deformation soft rock tunnels.

[0087] In S7, when the first repair cycle is completed, the grouting high-strength reinforcement arch is about 9 to 10m. The reasons for choosing to carry out the repair cycle in advance are: 1. To ensure the continuity and integrity of the entire radial direction of the compression zone; 2. To improve the efficiency of tunnel cleaning and repair, and to give the slurry in the subsequent cycle sufficient time to cement the loose surrounding rock; 3. To maintain the continuity of the construction work, reduce the mutual influence of each construction team, and reduce the loss and waste of materials.

[0088] Embodiment 2:

[0089] This embodiment is described by taking a certain lane as an example, and the specific steps are as follows.

[0090] Step S1, determine the deformation situation: by sampling and analyzing the on-site actual rock, the RQD value and Proctor coefficient of the surrounding rock of the section are obtained, and by measuring the cross-sectional dimensions of the on-site tunnel, the shrinkage ratio of the tunnel deformation is calculated. Finally, the deformation index D=5 of the tunnel surrounding rock in this example is determined by calculation. According to the classification standard, it can be known that the tunnel belongs to a large deformation tunnel.

[0091] Step S2, determine support parameters: Based on the determined deformation, by comparing with the grouting parameter reference table, it can be determined that the drilling extension direction to be adopted in this example is 25° with the axial plane of the tunnel, and the number of segmented grouting is two times.

[0092] Step S3. Drill holes for pre-grouting and seal the repaired area: By reasonably designing the number and position of the grouting holes 2, the planned grouting scheme is completed to ensure the reinforcement effect while minimizing the cost. In this example, the grouting material is ordinary Portland cement single-liquid slurry, the slurry specific gravity is 1.3-1.6g / cm3, and the water-cement weight ratio is 1:1.

[0093] First, drill 2 holes 8m deep in the axial direction at the necking point of the forward working face of the roadway cleaning. The grouting holes 2 are arranged at intervals at the top and bottom plates and the two sides of the rectangular arch roadway. The upward angle of the grouting holes on the top plate is 25° with the tangent plane of the roadway contour surface. The grouting holes at the left and right sides and the bottom plate also extend 25° downward to the surrounding rock side. There are 5 holes on the top plate of the roadway, 4 holes on the two sides, and 4 holes on the bottom plate. Among them, the grouting holes at the left and right sides and the top plate are drilled by an anchor machine, and the grouting holes at the bottom corners on both sides are drilled by a pneumatic drill, and the water and coal rock powder in the hole are blown away with a sweeper. The diameter of the grouting holes is designed to be Ф28mm, and the group spacing is set to 8m.

[0094] Then, the "three-part grouting method" is implemented for the grouting holes in groups: First, divide the time, first grout the grouting holes at the bottom of both sides, then grout the grouting holes at the two sides, and finally grout the grouting holes at the top plate. At the same time, grouting is carried out in the form of grouting in alternate groups. The grouting hole groups are numbered 1, 2, 3...n (where n is a natural number) in sequence. First, pour the groups with odd numbers, and then return to pour the groups with even numbers. At the same time, the interval time of grouting is controlled at 1 to 2 hours; Second, segmented grouting, the grouting area is divided into two sections according to the determined support parameters, and the slurry is pumped into the grouting hole 2, starting from the farthest distance from the grouting device. Start grouting from the grouting point. After a period of time after the initial grouting is completed, move the grouting device to the grouting point of the next section and continue grouting. In the process of each grouting section, all grouting work must be completed before the grouting agent begins to harden. In order to maintain the uniformity of grouting, the flow rate and speed of the grouting agent should be controlled during each grouting to avoid the generation of bubbles and ensure the quality of grouting. Third, divide the pressure and implement different grouting pressures in each segmented grouting area. In this example, the first grouting pressure is controlled at 1.5MPa. Wait for 30 minutes when the strength of the cement stone body is increased before the second grouting is carried out. The pressure of the second grouting is controlled at 2MPa.

[0095] Finally, seal the hole after the grouting is completed. Wrap jute around the outside of the cork, insert the cork and jute into the grouting hole, and wedge the cork firmly at the hole mouth with a hammer or other tools.

[0096] Step S4, after the grouting solidifies, use a pneumatic pick to remove the deformed part 4 of the tunnel surrounding rock along the tunnel design contour line 1, so that the deformation shrinkage ratio S is restored to 1, so that the cleaning and repair work surface continues to move forward, and cut off the anchor rods and anchor cables exposed outside the rock body after repair, and clean up the deformed and damaged steel mesh, etc., wherein, when cleaning the tunnel surrounding rock, there is no need to wait for the pre-grouting liquid to completely solidify. The period of time during which the pneumatic pick is used for cleaning is also the time reserved for slurry reinforcement.

[0097] Step S5, installing active support: when the repair step distance reaches the designed spacing distance of 8m between anchor rods / anchor cables, re-drill holes in the repaired rock mass, install anchor rods / cables, re-install trays and nuts and apply pre-tightening force to complete the construction of new active support;

[0098] Step S6, installing passive support: after the construction of anchor rods and anchor cables is completed, a U-shaped steel shed is erected inside the tunnel, and grouting is performed on the inner surface to complete the construction of new passive support;

[0099] Step S7: When the cleaning and repair reaches a cycle step distance of 8m, the repair is stopped, the waste rock is removed and transported out, and steps S3 to S6 are repeated until the soft rock tunnel area to be repaired is completely repaired.

[0100] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.

Claims

1. A method for repairing a large-deformation soft rock tunnel by advanced grouting, characterized in that: It includes the following steps: Step S1: Introduce the evaluation parameter P, and classify the roadway in the area to be repaired according to the evaluation model; Step S2: Determine the drilling angle of the grouting holes and the number of grouting times according to the roadway type; Step S3: Drill holes and pre-grout the area to be repaired according to Step S2 and seal the holes; Step S4: Clean the inner wall of the roadway and restore the shrinkage ratio of the roadway deformation to 1; Step S5: Install the active support structure; Step S6: Install the passive support structure; Step S7: When the repair reaches a cycle step distance of 8 m, remove and transport the gangue in the roadway, and then repeat Steps S3 to S6.

2. The method for repairing a large deformation soft rock tunnel by advanced grouting according to claim 1, characterized in that: In Step S1, introduce the evaluation parameter P, and calculate the deformation of the roadway surrounding rock according to the evaluation model, that is, Formula (1); In the formula: D is the deformation index of the roadway surrounding rock; P is the evaluation parameter for surrounding rock deformation classification; R is the RQD value of the rock mass quality index; f is the lithological Proctor coefficient; S is the shrinkage ratio of the roadway deformation, and its value is the ratio of the current value to the designed value of the roadway cross-section size; According to the calculated roadway surrounding rock deformation index D, different values of the deformation index D are used to evaluate the surrounding rock deformation of the roadway to be repaired, so as to correspond to different support repair parameters required for the roadway. The classification criteria are: When 8 < D <= 10, the roadway belongs to a slightly deformed roadway; When 6 < D <= 8, the roadway belongs to a generally deformed roadway; When 4 < D <= 6, the roadway belongs to a large-deformation roadway; When 2 < D <= 4, the roadway belongs to a severely deformed roadway; When 0 <= D <= 2, the roadway belongs to a scrapped roadway.

3. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: In Step S2, drill a hole with a depth of 8 m along the radial direction on the roadway cross-section plane, and the extension direction of the hole forms an angle α with the roadway axial plane; When the roadway belongs to a slightly deformed roadway, no grouting repair is required; When the roadway belongs to a generally deformed roadway, α = 15°, and the number of segmented grouting times is 1; When the roadway belongs to a large-deformation roadway, α = 25°, and the number of segmented grouting times is 2; When the roadway belongs to a severely deformed roadway, α = 35°, and the number of segmented grouting times is 3; When the roadway belongs to a scrapped roadway, no grouting repair is required.

4. The method for repairing a soft rock tunnel with large deformation by advanced grouting according to claim 1, characterized in that: In Step S3, use the "three-part grouting method" for the grouting holes in groups, that is, time-sharing grouting, segmented grouting, and pressure-divided grouting; in S3, after grouting, use a cork wrapped with jute to seal the grouting holes.

5. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: The operation of the time-sharing grouting is as follows: There is a certain interval in the grouting time of adjacent two groups of grouting holes, and the grouting holes are grouted in the order from bottom to top, from both sides to the center, and grouting every other one. The intermittent time of the intermittent grouting method is controlled within 1 to 2 hours, leaving a certain setting time for the slurry consolidation, which is beneficial to the full penetration and filling of the slurry in the broken surrounding rock of the soft rock roadway and improves the reinforcement effect on the roadway.

6. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: The operation of the segmented grouting is as follows: the grouting area is divided into several sections according to the length of the grouting section and the number of segmented grouting times, the slurry is pumped into the grouting hole, and the grouting is started from the grouting point farthest from the grouting device. After the grouting of the initial section is completed, the grouting device is moved to the grouting point of the next section and the injection is continued. In the process of each grouting section, all grouting work must be completed before the grouting agent begins to harden, and in order to maintain the uniformity of the grouting, the flow rate and speed of the grouting agent should be controlled during each grouting to avoid the generation of bubbles and ensure the quality of the grouting.

7. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: The operation of the partial pressure grouting is as follows: when grouting is performed at different grouting points in each section, the grouting effect, diffusion range, economy and other factors must be considered, and the slurry injection pressure at each grouting point must be controlled to ensure that the broken surrounding rock forms a high-strength reinforcement arch of surrounding rock with good quality; During grouting, different grouting pressures are implemented in each segmented grouting area through the adjustment of the grouting pressure regulating valve: the pressure of the first grouting is controlled at 1.5MPa, and the second grouting is carried out after waiting for about 1 hour for the strength of the cement stone body to increase. The pressure of the second grouting is controlled at 2MPa, and the pressure of the third grouting is controlled at 2.5MPa. Among them, the pressure needs to be gradually adjusted from small to large during each grouting section.

8. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: In step S4, the tunnel surrounding rock can be cleaned without waiting for the pre-grouting liquid to completely solidify.

9. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: The operation of step S5 is as follows: when the cleaning step distance reaches the designed spacing between anchor rods / cables, the rock mass with the size meeting the standard is re-drilled, the anchor rods / cables are inserted, the tray and nuts are re-installed and prestress is applied, and the construction of the new active support is completed; The operation of step S6 is as follows: after the construction of the anchor rods and anchor cables is completed, a U-shaped steel shed is erected inside the tunnel, and grouting is performed on the inner surface of the tunnel to complete the construction of passive support.

10. The advanced grouting repair method for a large deformation soft rock tunnel according to claim 1, characterized in that: In step S7, tunnel expansion and repair, support installation and advance pre-grouting can be carried out simultaneously at different locations.

Citation Information

Patent Citations

  • Supporting structure for soft rock roadway in deep mine and supporting method

    CN108775252A

  • Repairing process for improving compressive strength of underground coal mine roadway surrounding rock loose circles

    CN111411983A

  • Close-distance coal seam group strong dynamic pressure roadway cooperative control method

    CN115788533A

  • Bolt-grouting supporting method for coal-pillar-free mining entry retaining

    CN117167085A

  • Releasing-cracking-supporting cooperative burst prevention method based on coal body pressure relief and roof pre-cracking

    WO2023201906A1

Cited By

  • Expansive broken skarn contact zone tunneling construction method

    CN119878190A

  • A construction method for tunneling in the contact zone of expansive broken skarn

    CN119878190B