Section steel column embedded anchor bolt installation auxiliary equipment and auxiliary installation method

By using worms, arc worm gear and other combination structures in the installation of steel column embedded anchor bolts, precision control of anchor bolt positions is solved, and the problems of insufficient anchor bolt position deviation and accuracy in traditional methods are improved, and construction efficiency and Installation accuracy, suitable for complex environments.

CN118997516AActive Publication Date: 2024-11-22CHINA FIRST METALLURGICAL GROUP

Patent Information

Application Number
CN202411202060.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-22
Estimated Expiration
2044-08-29

AI Technical Summary

Technical Problem

In the traditional steel column embedded anchor bolt installation method, there are problems such as position offset and insufficient installation accuracy of the embedded anchor bolt. Especially due to the uneven deformation caused by concrete shrinkage, the steel column installation accuracy is affected, and the lack of effective precision adjustment means is added. Construction difficulty and cost.

Method used

An auxiliary equipment for installation of pre-embedded anchor bolts was designed. Through the combination of worm, arc worm gear, rotating ring, arc rack and screw, the position of anchor bolts is achieved to ensure that anchor bolts are in concrete. There is no deviation or deformation during curing to ensure the alignment of the anchor bolt and the hole position of the steel.

Benefits of technology

It significantly improves installation accuracy, reduces the complexity and error of human operation, improves construction efficiency, adapts to complex terrain and irregular bases, reduces operation difficulty, and is suitable for a variety of construction environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997516A_ABST
    Figure CN118997516A_ABST
Patent Text Reader

Abstract

The invention discloses section steel column embedded anchor bolt installation auxiliary equipment and an auxiliary installation method.The equipment comprises a disc (1), a bubble level (2) and a cylindrical block (3), sleeves (4) are fixedly installed on the outer surface of the circumference of the cylindrical block (3), square sliding rods (6) are slidably installed on the inner walls of the sleeves (4), a shell (7) is fixedly installed at the end, away from the disc (1), of each square sliding rod (6), and an arc groove is formed in the shell (7); a rotating ring (8) is slidably mounted on the inner wall of the arc groove, a notch (11) is formed in the outer surface, away from the disc (1), of the shell (7), and a steel column embedded anchor bolt (24) is arranged in the notch (11). A limiting assembly is arranged between the rotating ring (8) and the shell (7) and comprises a limiting groove (10) formed in the surface of the rotating ring (8), and limiting protrusions (9) are fixedly installed on the top wall and the bottom wall of the shell (7). According to the method, it is ensured that the subsequent steel column pre-embedded anchor bolts can be correctly aligned with the hole positions of the profile steel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of construction equipment, and more specifically, relates to auxiliary equipment for installing pre-buried anchor bolts of steel columns and an auxiliary installation method. Background Art

[0002] In modern building structures, steel columns are one of the main load-bearing components, and their stability and safety are directly related to the reliability of the entire building. The fixation of steel columns usually relies on pre-embedded anchor bolts pre-installed on the concrete foundation or the ground. These anchor bolts, as important components connecting the steel columns and the foundation, not only have to bear the gravity load of the building, but also have to cope with the effects of external environments such as wind and earthquakes. Therefore, the design and installation quality of the pre-embedded anchor bolts of steel columns are crucial to the safety of the building structure. Pre-embedded anchor bolts usually consist of bolts and bases. During the construction process, the anchor bolts are pre-embedded in concrete so that the steel columns can be fixed to the base in subsequent construction. The installation position, depth and horizontality of these anchor bolts directly determine the installation accuracy of the steel columns. Therefore, in engineering practice, how to ensure the accurate installation of the pre-embedded anchor bolts and keep their position stable during the concrete curing process has become an important challenge in the construction process. With the continuous improvement of modern buildings' requirements for safety and construction quality, the requirements for the installation technology of pre-embedded anchor bolts are also getting higher and higher, which provides an important background and technical driving force for the research of this invention.

[0003] The traditional method of installing pre-embedded anchor bolts for steel columns usually includes the following steps: First, determine the position of the anchor bolts according to the design drawings, and then connect multiple steel bars with these anchor bolts to form a stable anchor bolt frame. Next, fix the entire frame on the base by pouring concrete. After the concrete solidifies, these anchor bolts become the basic connectors for the installation of steel columns. In this way, the anchor bolts can be pre-embedded during construction to provide basic support for the subsequent installation of steel columns. However, in actual construction, this traditional method has some inherent shortcomings. Concrete often shrinks to a certain extent during the curing and drying process. Due to the uneven shrinkage of concrete, the anchor bolts embedded in it may undergo slight displacement or deformation. Although this change may not be obvious on a single anchor bolt, when multiple anchor bolts work together, it will lead to a reduction in installation accuracy. This displacement or deformation often causes the hole position of the steel column to be unable to accurately align with the pre-embedded anchor bolt during the subsequent connection process between the steel column and the anchor bolt, thereby affecting the fixing effect of the steel column and may even cause structural safety hazards. In addition, due to the complex construction site environment and the uneven levels of operators, the traditional installation method has high technical requirements for construction workers and the construction process is time-consuming and labor-intensive.

[0004] In view of the technical problems existing in the traditional steel column pre-embedded anchor bolt installation method, the present invention proposes a new type of auxiliary equipment and installation method, aiming to solve the common problems of pre-embedded anchor bolt position offset and insufficient installation accuracy in traditional processes. Based on an in-depth analysis of the prior art, it is found that the change in anchor bolt position caused by concrete shrinkage is one of the main factors affecting the installation accuracy of steel columns. Since concrete will inevitably shrink during the curing process, and this shrinkage is uneven, the anchor bolt may move or deform during the curing process. This subtle change will be magnified in the subsequent docking process between the steel column and the anchor bolt, resulting in misalignment of the installation. In addition, the traditional installation method lacks effective precision adjustment means. After the anchor bolt position changes slightly, the construction personnel are often unable to remedy it through simple manual operations. This not only increases the difficulty of installation, but also easily leads to rework, thereby affecting the construction progress and cost control. On the other hand, since the traditional method relies on the connection of multiple anchor bolts and steel bars to maintain the integrity of the structure, in actual operation, this method has poor environmental adaptability on site, especially in the case of complex terrain or irregular bases, which easily leads to installation difficulties. Summary of the invention

[0005] In view of the above defects or improvement needs of the prior art, the present invention provides an auxiliary equipment and auxiliary installation method for pre-embedded anchor bolts for steel columns. The rotating ring presses the pre-embedded anchor bolts for steel columns between the rotating ring and the shell body through a roller. The rotating ring drives the screw rod to rotate through the arc rack and the circular ring gear, so that the screw rod drives the square sliding column to move downward, and the pressure plate is driven downward through the square sliding column. The downward movement of the pressure plate presses against the top of the pre-embedded anchor bolts for steel columns. The device can limit the horizontal position and the extended length of the pre-embedded anchor bolts for steel columns. During the process of concrete curing and drying, the movement or deformation of the pre-embedded anchor bolts for steel columns caused by concrete shrinkage is avoided, ensuring that the subsequent pre-embedded anchor bolts for steel columns can be correctly aligned with the hole positions of the steel sections, thereby ensuring the correct fixation of the subsequent steel sections.

[0006] In order to achieve the above-mentioned object, according to the first aspect of the present invention, there is provided an auxiliary device for installing pre-buried anchor bolts of a steel column, comprising a disc, a bubble level arranged at the center of the upper surface of the disc, an annular groove is provided on the circumferential outer surface of the disc, and cylindrical blocks are equidistantly rotated and installed on the inner wall of the annular groove in the circumferential direction; wherein,

[0007] The outer surface of the cylindrical block is fixedly mounted with a sleeve, the inner wall of the sleeve is slidably mounted with a square slide bar, the end of the square slide bar away from the disc is fixedly mounted with a shell, an arc groove is arranged inside the shell, a rotating ring is slidably mounted on the inner wall of the arc groove, and the rotating ring and the arc groove are arranged at the same center;

[0008] The outer surface of the shell away from the disc is provided with a notch, the outer surface of the rotating ring is provided with a same notch, and a steel column embedded anchor bolt is arranged inside the notch;

[0009] A limit assembly is provided between the rotating ring and the shell, and the limit assembly includes a limit groove opened on the surface of the rotating ring. The top wall and the bottom wall of the shell are fixedly installed with limit protrusions, and the limit protrusions are slidably connected to the inner wall of the limit groove. The limit protrusions, the limit groove and the rotating ring are arranged at the same center of a circle to ensure that the embedded anchor bolts of the steel column are correctly aligned with the holes of the steel section.

[0010] Furthermore, a first opening is formed through the circumferential outer surface of the shell, and support blocks are symmetrically fixedly mounted on the outer surface of the shell near the first opening.

[0011] Furthermore, a worm is provided between the support blocks, and an arc worm wheel is provided on the outer circumferential surface of the rotating ring, and the arc worm wheel passes through the first opening and meshes with the worm;

[0012] Both ends of the worm screw penetrate through the outer surface of the support block and are provided with hexagonal holes.

[0013] Furthermore, the shell has a third opening extending through the outer surface of the disk near the circumference, and the square slide bar has a sliding sleeve fixedly disposed on the upper surface of the third opening near the third opening;

[0014] A square sliding column is slidably mounted on the inner wall of the sliding sleeve, a pressing plate is fixedly mounted on the top of the square sliding column, and the lower surface of the pressing plate abuts against the top of the embedded anchor bolt of the steel column.

[0015] Furthermore, a screw rod is rotatably mounted on the square slide rod near the upper surface of the third opening, the screw rod is arranged inside the sliding sleeve, and the top of the screw rod is inserted into the square slide column and threadedly connected thereto;

[0016] A circular ring gear is fixedly mounted on the outer surface of the screw rod near the bottom end, and a circular arc rack is provided on the outer surface of the rotating ring near the top circumference, and the circular ring gear is meshed and connected with the circular arc rack.

[0017] Furthermore, a hexagon socket clamping bolt is inserted into the sleeve away from the upper surface of the disc, and the hexagon socket clamping bolt is threadedly connected to the sleeve;

[0018] The bottom end of the hexagon socket clamping bolt passes through the top wall of the sleeve and abuts against the outer surface of the square slide rod;

[0019] The outer surface of one side of the square slide bar is provided with a size scale.

[0020] Furthermore, a plurality of first positioning holes are formed in the upper surface of the cylindrical block at equal intervals in the circumferential direction;

[0021] A plurality of second positioning holes are formed in the upper surface of the disk at equal intervals in the circumferential direction.

[0022] The second positioning hole is matched with the first positioning hole, and T-shaped pins are inserted into the inner walls of the second positioning hole and the first positioning hole.

[0023] Furthermore, the disc is fixedly installed with support rods equidistantly near the outer surface of the bottom circumference, and the support rods are inserted with support bolts at one end away from each other. The support bolts are threadedly connected to the support rods, and the bottom ends of the support bolts pass through the outer surface of the support rods and are rotatably installed with a support plate.

[0024] Furthermore, an arc groove is formed on the outer surface of the rotating ring close to the notch, the rotating ring and the arc groove are arranged at the same center, and a plurality of rollers are equidistantly mounted on the inner wall of the arc groove in a circumferential direction.

[0025] According to a second aspect of the present invention, a method for auxiliary installation of pre-embedded anchor bolts for section steel columns is provided, which is implemented by using the auxiliary device for installing pre-embedded anchor bolts for section steel columns, and comprises:

[0026] S100: Place the disc on the predetermined construction site and use a bubble level to calibrate the equipment horizontally. Adjust the support bolts at the bottom of the disc so that the bubble level shows that the equipment has reached a completely horizontal state.

[0027] S200: Match the first positioning hole on the cylindrical block with the second positioning hole on the disc, insert the T-shaped pin, firmly fix the cylindrical block to the outer circumference of the disc, adjust the square slide bar in the sleeve, adjust the position of the square slide bar to make it fixedly connected with the housing, and rotate the hexagon socket clamping bolt to lock the position of the square slide bar;

[0028] S300: Place the steel column embedded anchor bolt in the notch of the rotating ring, rotate the worm, drive the arc worm wheel to rotate, thereby driving the rotating ring to rotate, and adjust the position of the steel column embedded anchor bolt to make it consistent with the horizontal plane position required by the design;

[0029] S400: By adjusting the screw rod, the pressure plate is in close contact with the top of the embedded anchor bolt of the steel column. The rotating screw rod drives the circular ring gear to mesh with the arc rack of the rotating ring. By finely adjusting the position of the pressure plate, the height and horizontal position of the anchor bolt are ensured to fully meet the design requirements.

[0030] S500: Check the fixing of each part of the equipment, especially whether the square slide bar, worm gear, sleeve and pressure plate are firmly locked to ensure that the equipment will not shift during the concrete pouring process;

[0031] S600: Loosen the hexagon socket clamping bolt to unlock the square slide bar, then remove the T-pins in turn, remove the cylindrical block and the anchor bolts installed on it, and the embedded anchor bolts of the steel column should be kept at the accurate predetermined position and height for subsequent installation of the steel column.

[0032] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:

[0033] 1. In the equipment of the present invention, the worm drives the rotating ring to rotate through the circular arc worm gear, and the rotating ring drives the roller to move. Since the gap on the shell is slowly filled by the rotating ring, the rotating ring presses the embedded anchor bolt of the steel column between the rotating ring and the shell through the roller, and the rotating ring drives the screw rod to rotate through the circular arc rack and the circular ring gear, so that the screw rod drives the square sliding column to move downward, and the pressure plate is driven downward by the square sliding column. The downward movement of the pressure plate presses against the top of the embedded anchor bolt of the steel column. The horizontal position and the extended length of the embedded anchor bolt of the steel column can be limited by this device. During the process of concrete curing and drying, the movement or deformation of the embedded anchor bolt of the steel column caused by concrete shrinkage is avoided, ensuring that the subsequent embedded anchor bolt of the steel column can be correctly aligned with the hole position of the steel section, thereby ensuring the correct fixation of the subsequent steel section.

[0034] 2. The equipment of the present invention, through the precise transmission design of the worm and the arc worm wheel, realizes the fine adjustment and precise control of the position of the pre-embedded anchor bolts of the steel column. Through the cooperation of the limit assembly and the pressure plate, the equipment can ensure that the position of the anchor bolt does not shift or deform during the concrete pouring and curing process, thereby ensuring the perfect docking of the anchor bolt and the hole position of the steel column, significantly improving the installation accuracy, significantly improving the construction efficiency, and reducing the complexity and error of manual operation.

[0035] 3. The equipment of the present invention realizes high-precision anchor bolt installation through structural optimization. The design of the equipment takes into account the complexity of the construction site, has good adaptability and durability, and can maintain stable operation in various environments.

[0036] 4. The equipment of the present invention can adapt to the ground conditions of different construction sites through the combination of the support structure and the bubble level, ensuring that the equipment works in a horizontal state, thereby ensuring installation accuracy. In addition, the cylindrical block and the positioning hole of the disc are used in conjunction, so that the equipment has high stability during the construction process and is not easily displaced due to external forces.

[0037] 5. The method of the present invention designs multiple mechanical adjustment mechanisms, including hexagon socket clamping bolts, sleeves, screws, etc. These designs allow operators to use common tools for adjustment and fixing. The entire installation process does not require complicated operating steps, which reduces the difficulty of operation and improves construction efficiency. It is not only suitable for the installation of embedded anchor bolts for steel columns, but also can adapt to other construction projects that require high-precision embedded parts positioning. The equipment has a simple structure, is easy to disassemble and maintain, and is suitable for various complex construction environments, with broad application prospects. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1This is a schematic diagram of the overall structure of an auxiliary device for installing pre-buried anchor bolts on steel columns proposed by the present invention;

[0039] Figure 2 This is a schematic diagram of the structure of a pre-buried anchor bolt installation auxiliary device for a steel column proposed by the present invention;

[0040] Figure 3 This is a schematic diagram of a state in which a rotating ring of a pre-buried anchor bolt installation auxiliary device for a steel column proposed by the present invention is in a loosened state;

[0041] Figure 4 This is a schematic diagram of the locking state of the rotating ring of the auxiliary equipment for installing pre-buried anchor bolts on a steel column proposed by the present invention;

[0042] Figure 5 A schematic diagram of a worm gear of a pre-buried anchor bolt installation auxiliary device for a steel column proposed by the present invention;

[0043] Figure 6 A cross-sectional schematic diagram of an auxiliary device for installing pre-buried anchor bolts on a steel column proposed by the present invention;

[0044] Figure 7 A schematic diagram of an arc worm gear of an auxiliary device for installing pre-buried anchor bolts on a steel column proposed by the present invention;

[0045] Figure 8 A schematic diagram of an arc rack of an auxiliary device for installing pre-buried anchor bolts on a steel column proposed by the present invention;

[0046] Fig. 9 The disc of the auxiliary equipment for installing pre-buried anchor bolts of steel columns proposed by the present invention is intended;

[0047] Fig.10 This is a schematic diagram of a housing of an auxiliary device for installing pre-buried anchor bolts on a steel column proposed by the present invention;

[0048] Fig.11 This is a schematic diagram of a rotating ring of a pre-buried anchor bolt installation auxiliary device for a steel column proposed by the present invention;

[0049] Fig.12 A schematic diagram of a limiting groove of a pre-buried anchor bolt installation auxiliary device for a steel column proposed by the present invention;

[0050] Fig.13 The present invention provides a schematic flow chart of a method for auxiliary installation of pre-buried anchor bolts for steel columns.

[0051] In all the drawings, the same reference numerals represent the same technical features, specifically: 1. disc; 2. bubble level; 3. cylindrical block; 4. sleeve; 5. hexagon socket clamping bolt; 6. square slide rod; 7. shell; 8. rotating ring; 9. limiting protrusion; 10. limiting groove; 11. notch; 12. first opening; 13. third opening; 14. arc worm gear; 15. arc rack; 16. roller; 17. support block; 18. worm; 19. sleeve; 20. pressure plate; 21. square slide column; 22. screw rod; 23. ring gear; 24. steel column embedded anchor bolt; 25. support rod; 26. support bolt; 27. support plate; 28. T-pin; 29. ​​first positioning hole; 30. second positioning hole; 31. size scale mark. DETAILED DESCRIPTION

[0052] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0053] like Figure 1-12As shown, an embodiment of the present invention provides an auxiliary device for installing embedded anchor bolts of steel columns, which realizes high-precision positioning and installation of embedded anchor bolts through the combination of a series of precision mechanical components. The core structure of the device includes a disc 1, a bubble level 2, a cylindrical block 3, a sleeve 4, a square slide rod 6, a shell 7, a rotating ring 8, a limit assembly, a worm 18, a sleeve 19, a pressure plate 20, a screw 22 and a supporting structure. The specific connection relationship is: the disc 1 is used as the base of the device, the cylindrical block 3 is connected to the outer circumference of the disc 1 through an annular groove, and the sleeve 4 is fixedly installed. The square slide rod 6 is slidably installed in the sleeve 4, and one end of the square slide rod 6 is connected to the shell 7. The shell 7 is provided with an arc groove inside. The rotating ring 8 is installed in the groove and meshes with the worm 18 and the arc worm wheel 14. The pressure plate 20 is fixed on the square slide column 21, and its position is adjusted by the screw 22. The slide column is installed in the sleeve 19, and the sleeve is fixed on the square slide rod 6. The support structure is connected to the disc 1 through the support bolts 26 to adjust the horizontal state of the equipment. The rotating ring 8 is driven to rotate by the worm 18 to achieve precise adjustment of the position of the pre-embedded anchor bolts 24 of the steel column. The limit assembly ensures the stability of the rotating ring 8 during rotation. Finally, through the cooperation of the pressure plate 20 and the sliding sleeve 19, the height and position of the anchor bolts are accurately controlled to achieve the purpose of precise installation. In the equipment of the present invention, the worm drives the rotating ring to rotate through the circular arc worm gear, and the rotating ring drives the roller to move. Since the gap on the shell is slowly filled by the rotating ring, the rotating ring presses the embedded anchor bolt of the steel column between the rotating ring and the shell through the roller. The rotating ring drives the lead screw to rotate through the circular arc rack and the circular ring gear, so that the lead screw drives the square sliding column to move downward, and the pressure plate is driven downward through the square sliding column. The downward movement of the pressure plate presses against the top of the embedded anchor bolt of the steel column. The horizontal position and the extended length of the embedded anchor bolt of the steel column can be limited by this device. During the process of concrete solidification and drying, the movement or deformation of the embedded anchor bolt of the steel column caused by concrete shrinkage is avoided, ensuring that the subsequent embedded anchor bolt of the steel column can be correctly aligned with the hole position of the steel section, thereby ensuring the correct fixation of the subsequent steel section.

[0054] Among them, the main body of the equipment is a disc 1, and a bubble level 2 is arranged at the center of its upper surface to ensure the horizontal state of the equipment when it is installed. An annular groove is provided on the circumferential outer surface of the disc 1, and four cylindrical blocks 3 are installed equidistantly in the circumferential direction of the inner wall of the annular groove. A sleeve 4 is fixedly installed on the outer surface of each cylindrical block 3, and a square slide bar 6 is slidably installed in the sleeve 4. One end of the square slide bar 6 is fixedly installed on the shell 7. Through this structural design, the equipment can flexibly adjust the position of the embedded anchor bolts of the steel column to ensure that it is consistent with the design requirements. The equipment of the present invention can adapt to the ground conditions of different construction sites through the combination of the supporting structure and the bubble level, ensuring that the equipment works in a horizontal state, thereby ensuring the installation accuracy. In addition, the cylindrical blocks are used in conjunction with the positioning holes of the disc, so that the equipment has high stability during the construction process and is not easily displaced due to external forces.

[0055] The shell 7 is provided with an arc groove inside, and a rotating ring 8 is slidably mounted on the inner wall of the arc groove. The rotating ring 8 and the arc groove share a common center. This design ensures the stability and accuracy of the rotating ring during rotation. The outer surface of the shell 7 is provided with a notch 11, and the outer surface of the rotating ring 8 is also provided with the same notch, and a steel column embedded anchor bolt 24 is arranged in the notch. By rotating the rotating ring 8, the position of the anchor bolt can be accurately adjusted to keep it at the horizontal position required by the design drawing.

[0056] In order to prevent the rotating ring 8 from unnecessary displacement during operation, a limit assembly is provided between the housing 7 and the rotating ring. The limit assembly includes a limit groove 10 provided on the upper and lower surfaces of the rotating ring, and the top wall and the bottom wall of the housing 7 are fixedly mounted with a limit protrusion 9. The limit protrusion 9 is slidably matched with the inner wall of the limit groove 10 to ensure the stability of the rotating ring 8 during the rotation process, thereby ensuring the installation accuracy of the steel column embedded anchor bolt 24.

[0057] The transmission structure of the equipment is composed of a worm 18 and an arc worm wheel 14. The worm 18 passes through the outer surface of the shell 7 and meshes with the arc worm wheel 14 through the first opening 12. The arc worm wheel 14 is fixedly mounted on the outer periphery of the rotating ring 8. By rotating the worm 18, the operator can drive the rotating ring 8 to rotate, thereby achieving precise positioning of the pre-embedded anchor bolts 24 of the steel column. Both ends of the worm 18 pass through the outer surface of the support block 17 and are provided with hexagonal holes for easy operation with standard tools. The precise meshing of the worm 18 and the worm wheel 14 ensures the transmission efficiency and positioning accuracy of the equipment, while improving the simplicity and controllability of the operation. The equipment of the present invention, through the precise transmission design of the worm and the arc worm wheel, achieves fine-tuning and precise control of the position of the pre-embedded anchor bolts of the steel column. Through the cooperation of the limit assembly and the pressure plate, the equipment can ensure that the position of the anchor bolt does not shift or deform during the concrete pouring and curing process, thereby ensuring the perfect docking of the anchor bolt with the hole of the steel column, significantly improving the installation accuracy, significantly improving the construction efficiency, and reducing the complexity and errors of manual operation.

[0058] During the construction process, in order to ensure the height and position of the steel column embedded anchor bolt 24 are accurate, a sliding sleeve 19 is installed on the square slide rod 6, and a square slide column 21 is slidably installed in the sliding sleeve 19, and a pressure plate 20 is fixedly installed on the top of the slide column. The pressure plate 20 contacts the top of the anchor bolt 24 through its lower surface, and applies necessary pressure during the concrete pouring and curing process to prevent the anchor bolt from being displaced due to concrete shrinkage or external force. In order to accurately control the movement of the pressure plate 20, a screw rod 22 is also installed on the upper surface of the square slide rod 6. The screw rod 22 is arranged inside the sliding sleeve 19 and is connected to the square slide column 21 through a threaded connection. The top is meshed with the arc rack 15 of the rotating ring 8 through a circular ring gear 23. By rotating the screw rod 22, the position and height of the pressure plate 20 can be accurately adjusted to ensure that the installation depth of the steel column embedded anchor bolt 24 meets the design requirements.

[0059] The overall stability of the equipment is ensured by the support structure. Four support rods 25 are evenly distributed on the outer circumference of the bottom of the disc 1. Support bolts 26 are installed at the ends of the support rods 25. The bottom ends of the support bolts 26 are connected to the support plates 27. The support bolts 26 are threaded to adjust the height of the equipment, so that the equipment can adapt to different construction site conditions and ensure that the equipment remains stable during operation.

[0060] In addition, in order to further fix the position of the square slide bar 6, a hexagon socket clamping bolt 5 is provided on the upper surface of the sleeve 4. The hexagon socket clamping bolt 5 is threadedly connected to the sleeve 4, and the bottom end of the bolt abuts against the outer surface of the square slide bar 6. By rotating the hexagon socket clamping bolt 5, the slide bar 6 can be locked in a proper position to prevent the slide bar from accidentally moving during operation. This design ensures the operational stability of the equipment, especially in the case of frequent position adjustment, and can maintain high-precision anchor bolt positioning.

[0061] In actual operation, the installation and adjustment process of the equipment is completed by a variety of positioning components. The upper surface of the cylindrical block 3 is provided with a plurality of first positioning holes 29 arranged at equal distances, and the upper surface of the disc 1 is provided with four second positioning holes 30 at equal distances. By inserting the T-shaped pin 28, the various parts of the equipment can be quickly and accurately fixed in the predetermined position, ensuring the operational stability and accuracy of the entire equipment. This design simplifies the installation and disassembly process of the equipment and improves the construction efficiency.

[0062] like Fig.13 As shown, in another embodiment of the present invention, a method for auxiliary installation of pre-embedded anchor bolts based on steel columns is provided. The method ensures that the pre-embedded anchor bolts maintain a high degree of accuracy and stability during the installation process through a step-by-step operation process, and avoids the position offset or deformation of the anchor bolts caused by human errors or external forces during the construction process. The following are the specific operation steps.

[0063] Step 1: Initial installation and leveling of the equipment

[0064] First, place the disc 1 of the equipment on the predetermined construction site. When placing the equipment, ensure that the approximate position of the disc meets the requirements of the construction drawings. Use the bubble level 2 that comes with the equipment to calibrate the equipment horizontally. Adjust the support bolts 26 at the bottom of the disc 1 so that the bubble level shows that the equipment has reached a completely horizontal state. At this time, the support rods 25 of the equipment should be evenly distributed and the support plate 27 should be firmly in contact with the ground to ensure the overall stability of the equipment. After the horizontal calibration is completed, the operator should check again whether the support bolts and support plates are firm to ensure that the equipment will not shake or shift due to uneven ground or external forces during subsequent operations.

[0065] Step 2: Accurate positioning and fixing of equipment

[0066] After the initial installation of the equipment is completed, adjust the cylindrical block 3 on the disc 1 to the correct position according to the anchor position required by the construction drawings. The operator matches the first positioning hole 29 on the cylindrical block 3 with the second positioning hole 30 on the disc 1, inserts the T-pin 28, and firmly fixes the cylindrical block 3 to the outer circumference of the disc 1. Next, adjust the square slide bar 6 in the sleeve 4, and by adjusting the position of the square slide bar, fix it to the housing 7 to ensure the adjustment flexibility of the equipment. By rotating the hexagon socket clamping bolt 5, the position of the square slide bar 6 is locked to prevent position movement during subsequent construction.

[0067] Step 3: Initial positioning of embedded anchor bolts

[0068] After the initial position of the equipment is fixed, the steel column embedded anchor bolt 24 is placed in the notch 11 of the rotating ring 8. At this time, the initial position of the anchor bolt should roughly meet the design requirements, but it does not need to be completely accurate, because the subsequent steps of the equipment will further adjust the position of the anchor bolt. By rotating the worm 18, the arc worm wheel 14 is driven to rotate, thereby driving the rotation of the rotating ring 8. By rotating the rotating ring 8, the position of the steel column embedded anchor bolt 24 is adjusted to be consistent with the horizontal plane position required by the design. During the adjustment process, the operator should constantly check the position of the anchor bolt to ensure that it is accurate on the horizontal plane.

[0069] Step 4: Fine adjustment of anchor bolt position

[0070] After the initial positioning of the embedded anchor bolt 24 is completed, the position of the anchor bolt is further finely adjusted using the combined structure of the sliding sleeve 19 and the square sliding column 21. By adjusting the screw rod 22, the pressure plate 20 is brought into close contact with the top of the embedded anchor bolt 24 of the steel column, and appropriate pressure is applied. During the adjustment process, the rotating screw rod 22 drives the annular gear 23 to engage with the arc rack 15 of the rotating ring 8. By finely adjusting the position of the pressure plate 20, it is ensured that the height and horizontal position of the anchor bolt fully meet the design requirements. The pressure adjustment of the pressure plate 20 is very critical. When applying pressure, sufficient force should be ensured to fix the anchor bolt, but it should not be too large to avoid deformation or damage to the anchor bolt. The operator should flexibly adjust the amount of pressure applied according to the specific conditions of the construction site.

[0071] Step 5: Final fixing of anchor bolts and equipment inspection

[0072] After ensuring that the position and height of the anchor bolt 24 fully meet the design requirements, the operator should check the fixing of each part of the equipment again, especially whether the locking of the square slide bar 6, the worm 18, the sliding sleeve 19, and the pressing plate 20 is stable, to ensure that the equipment will not shift during the concrete pouring process. At this time, the operator can pour the concrete. During the concrete pouring process, the equipment will continue to maintain the position of the anchor bolt to ensure that it will not shift or deform during the concrete curing period.

[0073] Step 6: Equipment disassembly and construction completion

[0074] After the concrete is completely cured, the operator can start to dismantle the equipment. First, loosen the hexagon socket clamping bolt 5 to unlock the fixation of the square slide bar 6, then remove the T-pin 28 in turn, remove the cylindrical block 3 and the anchor bolts installed on it. During the equipment dismantling process, care should be taken to avoid any impact or vibration on the already cured concrete and anchor bolts, so as not to affect the final installation quality. All equipment parts should be dismantled in order and properly kept for subsequent reuse.

[0075] Step 7: Installation of subsequent steel columns

[0076] After the equipment is disassembled, the steel column embedded anchor bolt 24 should be kept at the accurate predetermined position and height, and the operator can carry out the subsequent steel column installation work. Due to the precise adjustment of the equipment, the position of the steel column and the anchor bolt is completely aligned, and the installation and fixing of the steel column can be completed smoothly.

[0077] During the entire installation process, the auxiliary equipment of the present invention provides a high degree of accuracy and stability, significantly improves the installation quality of the embedded anchor bolts, and avoids many errors in traditional manual operations. This method not only saves manpower and time, but also greatly improves the construction efficiency and engineering quality, and is suitable for various engineering projects that require high-precision anchor bolt installation. The method of the present invention designs multiple mechanical adjustment mechanisms, including hexagon socket clamping bolts, sleeves, screws, etc. These designs allow operators to use common tools for adjustment and fixing. The entire installation process does not require complicated operating steps, reduces the difficulty of operation, and improves construction efficiency. It is not only suitable for the installation of embedded anchor bolts for steel columns, but also can adapt to other construction projects that require high-precision embedded parts positioning. The equipment has a simple structure, is easy to disassemble, and is easy to maintain. It is suitable for various complex construction environments and has broad application prospects.

[0078] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A pre-buried anchor bolt installation auxiliary device for steel columns, characterized in that: The invention comprises a disk (1) and a bubble level (2) arranged at the center of the upper surface of the disk (1); the outer circumferential surface of the disk (1) is provided with an annular groove, and cylindrical blocks (3) are equidistantly mounted on the inner wall of the annular groove in a circumferential direction; wherein: The outer circumferential surface of the cylindrical block (3) is fixedly mounted with a sleeve (4), the inner wall of the sleeve (4) is slidably mounted with a square slide bar (6), the end of the square slide bar (6) away from the disc (1) is fixedly mounted with a shell (7), an arc groove is provided inside the shell (7), a rotating ring (8) is slidably mounted on the inner wall of the arc groove, and the rotating ring (8) and the arc groove are arranged at the same center; The outer surface of the shell (7) away from the disc (1) is provided with a notch (11), the outer surface of the rotating ring (8) is provided with a similar notch (11), and a steel column embedded anchor bolt (24) is provided inside the notch (11); A limit assembly is provided between the rotating ring (8) and the shell (7), the limit assembly comprising a limit groove (10) provided on the surface of the rotating ring (8), the top wall and the bottom wall of the shell (7) are both fixedly mounted with limit protrusions (9), the limit protrusions (9) are slidably connected to the inner wall of the limit groove, the limit protrusions (9), the limit groove and the rotating ring (8) are arranged at the same center of a circle, so as to ensure that the embedded anchor bolts (24) of the steel column are correctly aligned with the hole positions of the steel sections.

2. The auxiliary equipment for installing pre-buried anchor bolts of steel columns according to claim 1 is characterized in that: A first opening (12) is provided through the circumferential outer surface of the shell (7), and a support block (17) is symmetrically fixedly mounted on the outer surface of the shell (7) near the first opening (12).

3. The auxiliary equipment for installing pre-buried anchor bolts of steel columns according to claim 2 is characterized in that: A worm (18) is provided between the support blocks (17); a circular arc worm wheel (14) is provided on the circumferential outer surface of the rotating ring (8); the circular arc worm wheel (14) passes through the first opening (12) and meshes with the worm (18); Both ends of the worm (18) penetrate through the outer surface of the support block (17) and are provided with hexagonal holes.

4. A pre-buried anchor bolt installation auxiliary device for steel columns according to any one of claims 1 to 3, characterized in that: The shell (7) is provided with a third opening (13) through the outer surface of the circumference of the disk (1), and the square slide rod (6) is fixedly provided with a slide sleeve (19) on the upper surface of the square slide rod (6) near the third opening (13); A square sliding column (21) is slidably mounted on the inner wall of the sliding sleeve (19), a pressing plate (20) is fixedly mounted on the top of the square sliding column (21), and the lower surface of the pressing plate (20) abuts against the top of the steel column embedded anchor bolt (24).

5. The auxiliary equipment for installing pre-buried anchor bolts of steel columns according to claim 4 is characterized in that: A screw rod (22) is rotatably mounted on the upper surface of the square slide rod (6) near the third opening (13); the screw rod (22) is arranged inside the slide sleeve (19), and the top of the screw rod (22) is inserted into the square slide column (21) and threadedly connected thereto; A circular ring gear (23) is fixedly mounted on the outer surface of the screw rod (22) near the bottom end, and a circular arc rack (15) is provided on the outer surface of the rotating ring (8) near the top circumference, and the circular ring gear (23) is meshingly connected with the circular arc rack (15).

6. A pre-buried anchor bolt installation auxiliary device for steel columns according to any one of claims 1 to 3, characterized in that: A hexagon socket clamping bolt (5) is inserted into the sleeve (4) away from the upper surface of the disc (1), and the hexagon socket clamping bolt (5) is threadedly connected to the sleeve (4); The bottom end of the hexagon socket clamping bolt (5) passes through the top wall of the sleeve (4) and abuts against the outer surface of the square slide rod (6); A size scale mark (31) is provided on the outer surface of one side of the square slide rod (6).

7. A pre-buried anchor bolt installation auxiliary device for steel columns according to any one of claims 1 to 3, characterized in that: A plurality of first positioning holes (29) are formed in an equidistant manner through the upper surface of the cylindrical block (3) in the circumferential direction; A plurality of second positioning holes (30) are formed in an equidistant manner through the upper surface of the disk (1) in the circumferential direction. The second positioning hole (30) is arranged to match the first positioning hole (29), and T-shaped pins (28) are inserted into the inner walls of the second positioning hole (30) and the first positioning hole (29).

8. A pre-buried anchor bolt installation auxiliary device for steel columns according to any one of claims 1 to 3, characterized in that: The disc (1) is fixedly provided with support rods (25) at equal distances near the outer surface of the bottom circumference, and the support rods (25) are both provided with support bolts (26) at one end away from each other, and the support bolts (26) are threadedly connected to the support rods (25), and the bottom ends of the support bolts (26) penetrate the outer surface of the support rods (25) and are rotatably provided with support plates (27).

9. An auxiliary device for installing pre-buried anchor bolts for steel columns according to any one of claims 1 to 3, characterized in that: The rotating ring (8) is provided with an arc groove on its outer surface close to the notch (11); the rotating ring (8) and the arc groove are arranged at the same center of a circle; and a plurality of rollers (16) are equidistantly mounted on the inner wall of the arc groove in a circumferential direction.

10. A method for auxiliary installation of pre-buried anchor bolts of steel columns, characterized in that: The method is implemented by using the auxiliary equipment for installing pre-buried anchor bolts for steel columns as described in any one of claims 1 to 9, comprising: S100: placing the disc (1) on a predetermined construction site, and using a bubble level (2) to calibrate the level of the device, adjusting the support bolts (26) at the bottom of the disc (1) so that the bubble level (2) indicates that the device has reached a completely horizontal state; S200: Match the first positioning hole (29) on the cylindrical block (3) with the second positioning hole (30) on the disc (1), insert the T-shaped pin (28), firmly fix the cylindrical block (3) on the outer circumference of the disc (1), adjust the square slide bar (6) in the sleeve (4), adjust the position of the square slide bar to make it fixedly connected with the housing (7), and rotate the hexagon socket clamping bolt (5) to lock the position of the square slide bar (6); S300: placing the steel column embedded anchor bolt (24) in the notch (11) of the rotating ring (8), rotating the worm (18), driving the circular arc worm wheel (14) to rotate, thereby driving the rotating ring (8) to rotate, and adjusting the position of the steel column embedded anchor bolt (24) to be consistent with the horizontal plane position required by the design; S400: By adjusting the screw rod (22), the pressure plate (20) is brought into close contact with the top of the pre-embedded anchor bolt (24) of the steel column. The screw rod (22) is rotated to drive the annular gear (23) to mesh with the arc rack (15) of the rotating ring (8). By finely adjusting the position of the pressure plate (20), it is ensured that the height and horizontal position of the anchor bolt fully meet the design requirements. S500: Check the fixing conditions of various parts of the equipment, especially whether the square slide bar (6), the worm (18), the slide sleeve (19), and the pressure plate (20) are firmly locked to ensure that the equipment will not shift during the concrete pouring process; S600: Loosen the hexagon socket clamping bolt (5) to unlock the square slide bar (6), then remove the T-pin (28) in turn, remove the cylindrical block (3) and the anchor bolts installed thereon, and keep the steel column embedded anchor bolts (24) at the accurate predetermined position and height for the subsequent steel column installation work.

Citation Information

Patent Citations

  • Positioning device and construction method for independent foundation pre-buried column leg anchor bolts

    CN110485742A

  • High-density reinforced concrete structure at concrete short column embedded bolt joint and construction method

    CN115262774A

  • Embedded part

    CN115324208A

  • Special lifting appliance for spool of steel cord double-twisting machine

    CN117142333A

  • Anchor bolt structure for iron tower installation for communication engineering

    CN220666506U

Cited By

  • Positioning auxiliary device for laying prefabricated stand column in track inspection pit

    CN120350582A

  • Deviation rectifying, adjusting and positioning mechanism for steel structure anchor bolt

    CN121272965A