Special sand table deduction system for nuclear power overhaul

By designing a special sand table deduction system for nuclear power overhaul, the problems of low efficiency, insufficient effectiveness and lack of recording of action items have been solved, and automatic capture and summary of action items, monthly plan assessment and process standardization have been realized, and the deduction efficiency and queryability have been improved.

CN119048043APending Publication Date: 2024-11-29CNNC NUCLEAR POWER OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411215422.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In the special sand table deduction for nuclear power overhaul, there are problems such as low extracorporeal circulation efficiency of the action items, insufficient effectiveness of the action items, lack of process records, and the effect is affected by the experience and ability of the special person in charge.

Method used

A special sand table deduction system for nuclear power overhaul was designed, including information acquisition module, system classification module, deduction element module, action item module, conference management module and management support platform to realize automatic capture and summary of action item progress, monthly plan assessment, Digital archiving and process standardization.

Benefits of technology

The extracorporeal circulation efficiency of the action items has been improved, the effectiveness of the action items has been improved, which facilitates subsequent inquiries and improvements, and avoids the effect of the special deduction being affected by the experience and ability of the special person in charge.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119048043A_ABST
    Figure CN119048043A_ABST
Patent Text Reader

Abstract

The invention specifically relates to a nuclear power overhaul special sand table deduction system comprising an information acquisition module used for acquiring special sand table deduction scripts and action items; the system classification module is used for forming content and action items of each element deduced by a special sand table; the deduction element module is used for displaying the content and action items of each element deduced by the special sand table; the action item module is used for recording action items of all elements deduced by the special sand table, confirming the action items of all the elements deduced by the special sand table, and updating the action items according to the action items fed back monthly; the conference management module is used for receiving the action items and monthly feedback action items; and the management support platform is used for taking the action item as a responsible person of the monthly task issuing action item to form the monthly feedback action item. According to the invention, automatic capturing and gathering of action item progress, linking of action items and monthly plan assessment, digital archiving of a special deduction process and standardization of a special deduction process are realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of nuclear power overhaul special sand table simulation, and in particular to a nuclear power overhaul special sand table simulation system. Background Art

[0002] In the current nuclear power plant overhaul and maintenance work, in order to standardize the organization and management of overhaul site work, sand table simulations are conducted on special projects that may reduce or irreversibly affect the indicators of overhaul safety, quality, progress and cost. Such special projects often have high safety risks, high management difficulties, occupy key paths or long maintenance windows, and involve collaboration among multiple professionals or departments.

[0003] At present, the special project deduction adopts the form of meeting, with the special project logic diagram as the main deduction tool. The project leader convenes the work leader, the heads of the departments and offices, the heads of the cooperating departments and other relevant offices, and discusses the order of each step on the special project logic diagram according to their respective understanding and cognition, and forms action items for the shortcomings that can be thought of. After the special project deduction, the project leader needs to prepare meeting minutes and action items, and follow up on the implementation of the action items.

[0004] At present, special project simulations have the following problems: action items are circulated outside the body, relying on the project leader to communicate with the action item leaders one by one and promote feedback, which is inefficient; action items are not effective enough, especially action items that are the responsibility of external departments, which progress relatively slowly and are not easy to achieve closed-loop management; the process of special project simulations is not recorded, and most special project simulations will have a new project leader to start over, which is not conducive to later generations' inquiry, learning and improvement, and is not conducive to the inheritance and iteration of technology; the content and materials of special project simulations need to be prepared according to the professional level of the project leader, and the effect of special project simulations is affected by the experience and ability of the project leader, which may lead to situations where the special project simulation is not in place and many factors are not well considered. Summary of the invention

[0005] One of the purposes of the present invention is to provide a nuclear power overhaul special sand table simulation system to solve the problem of low extracorporeal circulation efficiency of action items in existing nuclear power overhaul special sand table simulations, realize automatic capture and summary of action item progress, reduce offline communication and confirmation links, and the special project person in charge no longer needs to communicate with the action item person in charge one by one and promote feedback, thereby improving the extracorporeal circulation efficiency of the action items.

[0006] The second purpose of the present invention is to provide a nuclear power overhaul special sand table simulation system to solve the problem of insufficient effectiveness of action items in existing nuclear power overhaul special sand table simulations, and to link action items with monthly plan assessments. The person in charge of the special project can constrain the action items that are responsible for the department and external departments, thereby improving the effectiveness of the action items.

[0007] The third purpose of the present invention is to provide a nuclear power overhaul special sand table simulation system to solve the problem that the special simulation process of the existing nuclear power overhaul special sand table simulation is not recorded, which is not conducive to subsequent query, learning and improvement, as well as the inheritance and iteration of technology, and to realize digital archiving of the special simulation process, which is convenient for subsequent query, learning and improvement, as well as the inheritance and iteration of technology.

[0008] The fourth object of the present invention is to provide a nuclear power overhaul special sand table simulation system to solve the problem that the content and materials of the existing nuclear power overhaul special sand table simulation need to be prepared according to the professional level of the special person in charge, and the effect of the special simulation is affected by the experience and ability of the special person in charge, so as to standardize the special simulation process and avoid the effect of the special simulation being affected by the experience and ability of the special person in charge.

[0009] In order to solve the above problems, the present invention provides a nuclear power overhaul special sandbox simulation system, comprising:

[0010] The information acquisition module is used to generate sandbox simulation scripts for special projects and issue them to the project leader; receive the special sandbox simulation scripts uploaded by the project leader and the action items sent by the meeting management module and send them to the system classification module;

[0011] The system classification module is used to receive the special sand table simulation scripts and action items sent by the information acquisition module and classify them according to the elements of the special sand table simulation, form the content and action items of each element of the special sand table simulation and send them to the simulation element module;

[0012] The deduction element module is used to receive the content and action items of each element of the special sand table deduction sent by the system classification module; and display the content and action items of each element of the special sand table deduction;

[0013] The action item module is used to record the action items of each element of the special sand table simulation; after confirming the action items of each element of the special sand table simulation, the action items of each element of the special sand table simulation are sent to the meeting management module; receive the action items of monthly feedback sent by the meeting management module, and update the action items according to the action items of monthly feedback;

[0014] Meeting management module, used to receive action items sent by the action item module and send them to the management support platform; receive action items for monthly feedback sent by the management support platform and send them to the action item module and information acquisition module;

[0015] The management support platform is used to receive action items sent by the conference management module and serve as the person responsible for issuing action items as monthly tasks; the person responsible for the action items provides monthly feedback on the action items, forms monthly feedback action items and sends them to the conference management module.

[0016] As one of the feasible ways, the nuclear power overhaul special sandbox simulation system also includes:

[0017] The personal task management module opens permissions to the person responsible for the action items, and is used to receive and display the action items of the person responsible for the action items sent by the meeting management module; receive the action items of the person responsible for the action items sent by the meeting management module for monthly feedback, and update the action items of the person responsible for the action items according to the action items of the person responsible for the action items sent by the monthly feedback;

[0018] The meeting management module is also used to send the action items of the action item responsible person to the personal task management module of the action item responsible person; and send the action items of the action item responsible person for monthly feedback to the personal task management module of the action item responsible person.

[0019] As one of the feasible ways, the nuclear power overhaul special sandbox simulation system also includes: a personal multi-task platform;

[0020] The personal task management module interacts with the personal multi-task platform data and is also used to extract and display the action items of the person in charge of the action items in the personal multi-task platform;

[0021] The personal multi-task platform interacts with the management support platform data to extract and display action items in the management support platform.

[0022] As one of the feasible ways, the information acquisition module generates a sandbox simulation script compilation task for the project and issues it to the project leader, including the following steps:

[0023] Get the overhaul project list, which includes the following fields of each project: organization and whether sandbox simulation is required. The "organization" field of the project includes the department and name of the project leader, and the "sandbox simulation" field of the project is "yes" or "no".

[0024] Filter all special information with "Yes" in the "Is Sand Table Simulation Required" field in the overhaul special list to generate an overhaul special sand table simulation list;

[0025] According to the requirements of the overhaul preparation nodes, a sandbox simulation plan for the special project in the overhaul special sandbox simulation list is generated 4 months before the overhaul. The sandbox simulation plan for the special project includes the sandbox simulation time for the special project.

[0026] Before the sandbox simulation of the project, generate the sandbox simulation script compilation task of the project and send it to the project leader;

[0027] The project leader uploads the sandbox simulation script of the project and completes the sandbox simulation script compilation task of the project;

[0028] The special sand table simulation script includes all the elements and contents of the special sand table simulation.

[0029] As one of the achievable methods, the action item module records the action items of each element of the special sand table simulation, including recording the action items of each element of the special sand table simulation generated during the special sand table simulation;

[0030] The action item module records the action items of each element of the special sand table simulation generated during the special sand table simulation, including the following steps:

[0031] During the special sand table simulation process, the personnel participating in the special sand table simulation discuss the action items of each element of the special sand table simulation on the content of each element of the special sand table simulation displayed in the simulation element module, and record the action items under each element of the special sand table simulation based on the results of the discussion on the action items of each element of the special sand table simulation.

[0032] As one of the achievable ways, the action item module confirms the action items of each element of the special sand table simulation, including confirming the action items of each element of the special sand table simulation generated during the special sand table simulation during the special sand table simulation summary after the special sand table simulation is completed;

[0033] The action item module confirms the action items of each element of the special sandbox simulation generated during the special sandbox simulation during the summary of the special sandbox simulation, including the following steps:

[0034] During the summary of the special sand table exercise, the action items of each element of the special sand table exercise generated during the special sand table exercise are confirmed, and the responsible persons and planned completion time of the action items are further clarified.

[0035] As one of the achievable ways, after the action item module confirms the action items of each element of the special sandbox simulation generated during the special sandbox simulation during the summary of the special sandbox simulation, it identifies whether the latest status of the action items of each element of the special sandbox simulation generated during the special sandbox simulation are all closed;

[0036] If the latest status of the action items of each element of the special sand table simulation generated during the special sand table simulation is closed, the special sand table simulation is judged to be successful, and a prompt is given to enter the special sand table simulation review.

[0037] As one of the feasible ways, the action item module records the action items of each element of the special sand table simulation, and also includes recording the action items of each element of the special sand table simulation generated during the special sand table simulation review process;

[0038] The action item module records the action items of each element of the special sand table simulation generated during the special sand table simulation review, including the following steps:

[0039] During the review of the special sand table simulation, the personnel involved in the special sand table simulation review the special sand table simulation process, analyze the factors that exceed expectations and / or are unexpected in the sand table simulation of each element of the special sand table simulation, and confirm whether the factors that exceed expectations and / or are unexpected in the sand table simulation of each element of the special sand table simulation are included in the content of each element of the special sand table simulation; the personnel involved in the special sand table simulation summarize the rules and capacity improvement of the special sand table simulation, analyze the factors that are conducive and / or unfavorable to the rules and capacity improvement of each element of the special sand table simulation, and confirm whether the factors that are conducive and / or unfavorable to the rules and capacity improvement of each element of the special sand table simulation are included in the content of each element of the special sand table simulation;

[0040] If it is confirmed that the factors that exceed expectations and / or are unexpected in the sandbox simulation of each element of the special sandbox simulation are the contents of each element of the special sandbox simulation, then the action items formed by the factors that exceed expectations and / or are unexpected in the sandbox simulation are recorded under each element of the special sandbox simulation;

[0041] If it is confirmed that the factors that are conducive and / or unfavorable to the improvement of sand table simulation rules and capabilities are the contents of the various elements of the special sand table simulation, then the action items formed by the factors that are conducive and / or unfavorable to the improvement of sand table simulation rules and capabilities are recorded under each element of the special sand table simulation.

[0042] As one of the achievable methods, the action item module confirms the action items of each element of the special sand table simulation, and also includes confirming the action items of each element of the special sand table simulation generated during the special sand table simulation review;

[0043] The action item module confirms the action items of each element of the special sand table simulation generated during the special sand table simulation review, including the following steps:

[0044] Confirm the action items of each element of the special sand table simulation generated during the review of the special sand table simulation, and further clarify the responsible persons and planned completion time of the action items.

[0045] As one of the possible implementation methods, the action item includes the following field information: content, status, responsible person and planned completion time; the status of the action item includes open and closed.

[0046] Beneficial technical effects of the present invention:

[0047] The nuclear power overhaul special sandbox simulation system of the present invention can realize automatic capture and summary of action item progress, reduce offline communication confirmation links, and the project leader no longer needs to communicate with the action item leader one by one to promote feedback, thereby improving the extracorporeal circulation efficiency of the action items; it can realize the linkage between action items and monthly plan assessments, and the project leader can constrain the action items that the department is responsible for and the action items that other departments are responsible for, thereby improving the effectiveness of the action items; it can realize digital archiving of the special simulation process, which is convenient for subsequent query, learning and improvement, as well as the inheritance and iteration of technology; it can realize the standardization of the special simulation process, and avoid the special simulation effect being affected by the experience and ability of the project leader. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 It is a structural schematic diagram of an embodiment of a nuclear power overhaul special sandbox simulation system of the present invention. DETAILED DESCRIPTION

[0049] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used in the specification of the application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned figure descriptions are intended to cover non-exclusive inclusions.

[0050] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0051] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.

[0052] refer to Figure 1 , shows a schematic structural diagram of an embodiment of a nuclear power overhaul special sandbox simulation system, the nuclear power overhaul special sandbox simulation system comprising:

[0053] The information acquisition module is used to generate sandbox simulation scripts for special projects and issue them to the project leader; receive the special sandbox simulation scripts uploaded by the project leader and the action items sent by the meeting management module and send them to the system classification module;

[0054] The system classification module is used to receive the special sand table simulation scripts and action items sent by the information acquisition module and classify them according to the elements of the special sand table simulation, form the content and action items of each element of the special sand table simulation and send them to the simulation element module;

[0055] The deduction element module is used to receive the content and action items of each element of the special sand table deduction sent by the system classification module; and display the content and action items of each element of the special sand table deduction;

[0056] The action item module is used to record the action items of each element of the special sand table simulation; after confirming the action items of each element of the special sand table simulation, the action items of each element of the special sand table simulation are sent to the meeting management module; receive the action items of monthly feedback sent by the meeting management module, and update the action items according to the action items of monthly feedback;

[0057] Meeting management module, used to receive action items sent by the action item module and send them to the management support platform; receive action items for monthly feedback sent by the management support platform and send them to the action item module and information acquisition module;

[0058] The management support platform is used to receive action items sent by the conference management module and serve as the person responsible for issuing action items as monthly tasks; the person responsible for the action items provides monthly feedback on the action items, forms monthly feedback action items and sends them to the conference management module.

[0059] In this embodiment, as one of the achievable methods, the nuclear power overhaul special sandbox simulation system also includes:

[0060] The personal task management module opens permissions to the person responsible for the action items, and is used to receive and display the action items of the person responsible for the action items sent by the meeting management module; receive the action items of the person responsible for the action items sent by the meeting management module for monthly feedback, and update the action items of the person responsible for the action items according to the action items of the person responsible for the action items sent by the monthly feedback;

[0061] The meeting management module is also used to send the action items of the action item responsible person to the personal task management module of the action item responsible person; and send the action items of the action item responsible person for monthly feedback to the personal task management module of the action item responsible person.

[0062] In this embodiment, as one of the achievable methods, the nuclear power overhaul special sandbox simulation system also includes: a personal multi-task platform;

[0063] The personal task management module interacts with the personal multi-task platform data and is also used to extract and display the action items of the person in charge of the action items in the personal multi-task platform;

[0064] The personal multi-task platform interacts with the management support platform data to extract and display action items in the management support platform.

[0065] In this embodiment, as one of the achievable methods, the information acquisition module generates a sandbox simulation script compilation task for a special project and issues it to the person in charge of the special project, including the following steps:

[0066] Get the overhaul project list, which includes the following fields of each project: organization and whether sandbox simulation is required. The "organization" field of the project includes the department and name of the project leader, and the "sandbox simulation" field of the project is "yes" or "no".

[0067] Filter all special information with "Yes" in the "Is Sand Table Simulation Required" field in the overhaul special list to generate an overhaul special sand table simulation list;

[0068] According to the requirements of the overhaul preparation nodes, a sandbox simulation plan for the special project in the overhaul special sandbox simulation list is generated 4 months before the overhaul. The sandbox simulation plan for the special project includes the sandbox simulation time for the special project.

[0069] Before the sandbox simulation of the project, generate the sandbox simulation script compilation task of the project and send it to the project leader;

[0070] The project leader uploads the sandbox simulation script of the project and completes the sandbox simulation script compilation task of the project;

[0071] The special sand table simulation script includes all the elements and contents of the special sand table simulation.

[0072] In this embodiment, as one of the feasible ways, the project leader constructs a sand table simulation script for the special project based on the actual situation of the past special projects and the sand table simulation situation, and divides the sand table simulation process of the special project into the various elements and content of each element of the special sand table simulation; the elements of the special sand table simulation include participants, basic information, special project preparation, organizational structure, implementation plan, implementation simulation, technical difficulties, external interface, experience feedback, on-site simulation and scenario preset.

[0073] In this embodiment, as one of the achievable methods, the action item module records the action items of each element of the special sandbox simulation, including recording the action items of each element of the special sandbox simulation generated during the special sandbox simulation;

[0074] The action item module records the action items of each element of the special sand table simulation generated during the special sand table simulation, including the following steps:

[0075] During the special sand table simulation process, the personnel participating in the special sand table simulation discuss the action items of each element of the special sand table simulation on the content of each element of the special sand table simulation displayed in the simulation element module, and record the action items under each element of the special sand table simulation based on the results of the discussion on the action items of each element of the special sand table simulation.

[0076] In this embodiment, as one of the achievable ways, the action item module confirms the action items of each element of the special sandbox simulation, including confirming the action items of each element of the special sandbox simulation generated during the special sandbox simulation during the special sandbox simulation summary after the special sandbox simulation is completed;

[0077] The action item module confirms the action items of each element of the special sandbox simulation generated during the special sandbox simulation during the summary of the special sandbox simulation, including the following steps:

[0078] During the summary of the special sand table exercise, the action items of each element of the special sand table exercise generated during the special sand table exercise are confirmed, and the responsible persons and planned completion time of the action items are further clarified.

[0079] In this embodiment, as one of the achievable ways, after the action item module confirms the action items of each element of the special sandbox simulation generated in the special sandbox simulation process during the special sandbox simulation summary, it identifies whether the latest status of the action items of each element of the special sandbox simulation generated in the special sandbox simulation process are all closed;

[0080] If the latest status of the action items of each element of the special sand table simulation generated during the special sand table simulation is closed, the special sand table simulation is judged to be successful, and a prompt is given to enter the special sand table simulation review.

[0081] In this embodiment, as one of the achievable methods, the action item module records the action items of each element of the special sandbox simulation, and also includes recording the action items of each element of the special sandbox simulation generated during the special sandbox simulation review process;

[0082] The action item module records the action items of each element of the special sand table simulation generated during the special sand table simulation review, including the following steps:

[0083] During the review of the special sand table simulation, the personnel involved in the special sand table simulation review the special sand table simulation process, analyze the factors that exceed expectations and / or are unexpected in the sand table simulation of each element of the special sand table simulation, and confirm whether the factors that exceed expectations and / or are unexpected in the sand table simulation of each element of the special sand table simulation are included in the content of each element of the special sand table simulation; the personnel involved in the special sand table simulation summarize the rules and capacity improvement of the special sand table simulation, analyze the factors that are conducive and / or unfavorable to the rules and capacity improvement of each element of the special sand table simulation, and confirm whether the factors that are conducive and / or unfavorable to the rules and capacity improvement of each element of the special sand table simulation are included in the content of each element of the special sand table simulation;

[0084] If it is confirmed that the factors that exceed expectations and / or are unexpected in the sandbox simulation of each element of the special sandbox simulation are the contents of each element of the special sandbox simulation, then the action items formed by the factors that exceed expectations and / or are unexpected in the sandbox simulation are recorded under each element of the special sandbox simulation;

[0085] If it is confirmed that the factors that are conducive and / or unfavorable to the improvement of sand table simulation rules and capabilities are the contents of the various elements of the special sand table simulation, then the action items formed by the factors that are conducive and / or unfavorable to the improvement of sand table simulation rules and capabilities are recorded under each element of the special sand table simulation.

[0086] In this embodiment, as one of the achievable methods, the action item module confirms the action items of each element of the special sand table simulation, and also includes confirming the action items of each element of the special sand table simulation generated during the special sand table simulation review process;

[0087] The action item module confirms the action items of each element of the special sand table simulation generated during the special sand table simulation review, including the following steps:

[0088] Confirm the action items of each element of the special sand table simulation generated during the review of the special sand table simulation, and further clarify the responsible persons and planned completion time of the action items.

[0089] In this embodiment, as one of the implementable ways, the action item includes the following field information: content, status, responsible person and planned completion time; the status of the action item includes open and closed.

[0090] In this embodiment, as one of the feasible ways, the “participants” element includes: the department and names of the project leader, work leader, main members of the working group, responsible team leader, specialist, section chief, and those who cooperate with the professional leader and internal and external experts.

[0091] In this embodiment, as one of the feasible ways, the "basic information" elements include: special code, special responsibility director, implementation window, special category, construction responsible person, construction period target, whether it is a critical path, construction responsible director, safety target, technical responsible person, work mode and quality indicators.

[0092] In this embodiment, as one of the achievable methods, the "special preparation" element includes: special document preparation status and challenges, special material preparation status and challenges, special contract preparation status and challenges, and special work order preparation status and challenges;

[0093] The preparation of special documents includes the following: the preparation progress of the construction plan and design plan, the consistency between the design plan and the construction plan, and whether the regulations have come into effect;

[0094] The preparation of special materials includes the following: whether spare parts and materials are complete, the number, model, integrity, size, surface condition and validity period of spare parts, whether the material collection and hanging are consistent with the regulations, whether the information of the physical objects is consistent with that of the materials, whether the key dimensions have been measured on site, and whether the spare parts need secondary processing and assembly;

[0095] Special contract preparation status includes the following: outsourcing technical specifications, outsourcing budget application, outsourcing project application status, and outsourcing contract status;

[0096] The preparation status of special work orders includes the following: whether the work order is complete, whether the coordinating sub-work orders are complete, whether the work order needs to be split, the rationality of the quality plan and its consistency with the plan, the rationality of the work order maintenance classification and foreign object protection classification, and whether the relevant permits are complete; relevant permits include: radiation protection license, ISP1 / 2, hot work, flammable and explosive, fire barrier opening license, temporary water and electricity application, temporary storage application, operation risk analysis form, welding application, non-destructive testing application, excavation application, electromagnetic interference prevention risk analysis, fire hydrant use application, foreign object protection plan, and chemical use approval.

[0097] In this embodiment, as one of the feasible ways, the "organizational structure" element includes the following contents: clarify the list of organizational structure personnel and assign responsibilities to the responsible persons; the organizational structure includes: implementation responsible department, technical responsible department, person in charge of cooperative units, cooperating department, operation department, supervision department, planning department and others; cooperating departments include lifting department, scaffolding department, transportation department and welding department, and the responsible persons include responsible directors and responsible section chiefs.

[0098] In this embodiment, as one of the feasible ways, the "implementation plan" elements include the following: whether the logic diagram has been compiled and prefabricated in P6, the rationality of the logic diagram, the matching of the logic diagram with the window, and whether there is room for optimization of the logic diagram.

[0099] In this embodiment, as one of the feasible ways, the elements of "implementation simulation" include the following: risk analysis challenge, tool challenge, personnel challenge, coordination challenge, program data challenge, program step challenge, clear control person in charge, and whether the emergency plan is complete;

[0100] The risk analysis challenge includes the following: whether the risk analysis is comprehensive and whether the preventive measures are in place. Nine major risk categories are pre-made and checked to challenge the preventive measures for each risk category;

[0101] Tool challenges include the following: whether the tools are complete, whether there are special tools, tool sources, tool status, whether verification has been done, and whether the tools are sent for inspection during the overhaul window;

[0102] Personnel challenges include the following: Qualifications, numbers, experience and job holders overhaul ticket analysis;

[0103] The challenges of coordinated operations include the following: review and completeness of lifting, insulation, scaffolding, painting, transportation, sampling, measurement, door opening, pit digging, wall demolition, hole opening, PT, RT, UT, visual inspection, ET, decontamination, wiring removal, blind plate removal, drainage, temporary online, mandatory signaling, corrosion prevention, temporary water and electricity, machining, nuclear cleaning, disassembly and assembly of fireproof plugging, coordinated alignment and lubrication;

[0104] The data challenges of the program include the following: whether the three "whatevers" are met;

[0105] The challenges of step-by-step verification include the following: who, what tools, where, what operations, what spare parts are needed, what are the expected results, why the step needs to be performed, what are the risks, and how to prevent them;

[0106] Identify the responsible persons for control, including responsible department heads, responsible section heads, team leaders, heads of cooperative units, work leaders, working group members, quality assurance, industrial safety, nuclear safety, radiation protection and fire supervisors;

[0107] Whether the emergency plans for special projects, technical reforms that affect unit status transitions, and nuclear safety-related technical reforms are complete.

[0108] In this embodiment, as one of the feasible ways, the "technical difficulties" element includes the following contents: analysis of technical difficulties in the work steps; technical difficulties include: limited space, poor accessibility; residual water and residual pressure, pressure and live operation; high requirements for matching dimensions and standards; new personnel, new projects, process changes, tool changes, spare parts changes, window changes, poor space accessibility; weather, radiation, noise, temperature and other environmental restrictions.

[0109] In this embodiment, as one of the feasible ways, the "external interface" element includes the following contents: how to connect with each cooperating department and whether the interface person is clear; what are the steps of negative interface and whether each cooperating department is aware of the negative interface requirements.

[0110] In this embodiment, as one of the feasible ways, the "experience feedback" element includes the following contents: the project leader investigates at least two experience feedback examples similar to the project at home and abroad, and explains the significance of reference; for the second-time implementation of the project, summarizes the experience feedback from the last implementation; and the experience feedback added by experts in the previous project sandbox simulation.

[0111] In this embodiment, as one of the feasible ways, the "on-site simulation" element includes the following contents: whether an on-site sand table simulation is needed; how to arrange the personnel, time and place of the on-site sand table simulation.

[0112] In this embodiment, as one of the feasible ways, the "scenario preset" element includes the following contents: unexpected scenario preset is made in combination with the "technical difficulties" and "experience feedback" elements in the special sandbox simulation process, and the unexpected scenario preset is as comprehensive and reasonable as possible; whether the unexpected scenario preset response measures are effective; internal and external experts propose new unexpected scenarios, and the project leader provides answers.

[0113] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A nuclear power overhaul special sandbox simulation system, characterized in that: include: The information acquisition module is used to generate sandbox simulation scripts for special projects and issue them to the project leader; receive the special sandbox simulation scripts uploaded by the project leader and the action items sent by the meeting management module and send them to the system classification module; The system classification module is used to receive the special sand table simulation scripts and action items sent by the information acquisition module and classify them according to the elements of the special sand table simulation, form the content and action items of each element of the special sand table simulation and send them to the simulation element module; The deduction element module is used to receive the content and action items of each element of the special sand table deduction sent by the system classification module; and display the content and action items of each element of the special sand table deduction; The action item module is used to record the action items of each element of the special sand table simulation; after confirming the action items of each element of the special sand table simulation, the action items of each element of the special sand table simulation are sent to the meeting management module; Receive the action items of monthly feedback sent by the conference management module, and update the action items according to the action items of monthly feedback; Meeting management module, used to receive action items sent by the action item module and send them to the management support platform; receive action items for monthly feedback sent by the management support platform and send them to the action item module and information acquisition module; The management support platform is used to receive action items sent by the conference management module and serve as the person responsible for issuing action items as monthly tasks; the person responsible for the action items provides monthly feedback on the action items, forms monthly feedback action items and sends them to the conference management module.

2. The nuclear power overhaul special sandbox simulation system according to claim 1 is characterized in that: Also includes: The personal task management module opens permissions to the person responsible for the action items and is used to receive and display the action items of the person responsible for the action items sent by the meeting management module; Receive the action items of the action item responsible person for the monthly feedback sent by the conference management module, and update the action items of the action item responsible person according to the action items of the action item responsible person for the monthly feedback; The meeting management module is also used to send the action items of the action item responsible person to the personal task management module of the action item responsible person; Send the action items of the action item responsible person for the monthly feedback to the personal task management module of the action item responsible person.

3. The nuclear power overhaul special sandbox simulation system according to claim 2 is characterized in that: Also includes: Personal multi-tasking platform; The personal task management module interacts with the personal multi-task platform data and is also used to extract and display the action items of the person in charge of the action items in the personal multi-task platform; The personal multi-task platform interacts with the management support platform data to extract and display action items in the management support platform.

4. The nuclear power overhaul special sandbox simulation system according to claim 1 is characterized in that: The information acquisition module generates a sandbox simulation script for the project and issues it to the project leader, including the following steps: Get the overhaul special list. The overhaul special list includes the following fields of each overhaul special: organization and whether sandbox simulation is required. The "Organization" field of a special includes the department and name of the person in charge of the special. The "Sandbox simulation" field of a special is "Yes" or "No". Filter all special information whose "Is Sand Table Simulation Required" field is "Yes" in the overhaul special list to generate an overhaul special sand table simulation list; According to the requirements of the overhaul preparation nodes, a sandbox simulation plan for the special project in the overhaul special sandbox simulation list is generated 4 months before the overhaul. The sandbox simulation plan for the special project includes the sandbox simulation time for the special project. Before the sandbox simulation of the project, generate the sandbox simulation script compilation task of the project and send it to the project leader; The project leader uploads the sandbox simulation script of the project and completes the sandbox simulation script compilation task of the project; The special sand table simulation script includes all the elements and contents of the special sand table simulation.

5. The nuclear power overhaul special sandbox simulation system according to claim 1 is characterized in that: The action item module records the action items of each element of the special sand table simulation, including recording the action items of each element of the special sand table simulation generated during the special sand table simulation; The action item module records the action items of each element of the special sand table simulation generated during the special sand table simulation, including the following steps: During the special sand table simulation process, the personnel participating in the special sand table simulation discuss the action items of each element of the special sand table simulation on the content of each element of the special sand table simulation displayed in the simulation element module, and record the action items under each element of the special sand table simulation based on the results of the discussion on the action items of each element of the special sand table simulation.

6. The nuclear power overhaul special sandbox simulation system according to claim 5 is characterized in that: The action item module confirms the action items of each element of the special sand table simulation, including confirming the action items of each element of the special sand table simulation generated during the special sand table simulation during the special sand table simulation summary after the special sand table simulation is completed; The action item module confirms the action items of each element of the special sandbox simulation generated during the special sandbox simulation during the summary of the special sandbox simulation, including the following steps: During the summary of the special sand table exercise, the action items of each element of the special sand table exercise generated during the special sand table exercise are confirmed, and the responsible persons and planned completion time of the action items are further clarified.

7. The nuclear power overhaul special sandbox simulation system according to claim 6 is characterized in that: After confirming the action items of each element of the special sandbox simulation generated during the special sandbox simulation during the summary of the special sandbox simulation, the action item module identifies whether the latest status of the action items of each element of the special sandbox simulation generated during the special sandbox simulation are all closed; If the latest status of the action items of each element of the special sand table simulation generated during the special sand table simulation is closed, the special sand table simulation is judged to be successful, and a prompt is given to enter the special sand table simulation review.

8. The nuclear power overhaul special sandbox simulation system according to claim 7 is characterized in that: The action item module records the action items of each element of the special sand table simulation, and also includes recording the action items of each element of the special sand table simulation generated during the special sand table simulation review; The action item module records the action items of each element of the special sand table simulation generated during the special sand table simulation review, including the following steps: During the review of the special sand table simulation, the personnel involved in the special sand table simulation review the special sand table simulation process, analyze the factors that exceed expectations and / or are unexpected in the sand table simulation of each element of the special sand table simulation, and confirm whether the factors that exceed expectations and / or are unexpected in the sand table simulation of each element of the special sand table simulation are included in the content of each element of the special sand table simulation; the personnel involved in the special sand table simulation summarize the rules and capacity improvement of the special sand table simulation, analyze the factors that are conducive and / or unfavorable to the rules and capacity improvement of each element of the special sand table simulation, and confirm whether the factors that are conducive and / or unfavorable to the rules and capacity improvement of each element of the special sand table simulation are included in the content of each element of the special sand table simulation; If it is confirmed that the factors that exceed expectations and / or are unexpected in the sandbox simulation of each element of the special sandbox simulation are the contents of each element of the special sandbox simulation, then the action items formed by the factors that exceed expectations and / or are unexpected in the sandbox simulation are recorded under each element of the special sandbox simulation; If it is confirmed that the factors that are conducive and / or unfavorable to the improvement of sand table simulation rules and capabilities are the contents of the various elements of the special sand table simulation, then the action items formed by the factors that are conducive and / or unfavorable to the improvement of sand table simulation rules and capabilities are recorded under each element of the special sand table simulation.

9. The nuclear power overhaul special sandbox simulation system according to claim 8 is characterized in that: The action item module confirms the action items of each element of the special sand table simulation, and also includes confirming the action items of each element of the special sand table simulation generated during the special sand table simulation review; The action item module confirms the action items of each element of the special sand table simulation generated during the special sand table simulation review, including the following steps: Confirm the action items of each element of the special sand table simulation generated during the review of the special sand table simulation, and further clarify the responsible persons and planned completion time of the action items.

10. The nuclear power overhaul special sandbox simulation system according to claim 1 is characterized in that: An action item includes the following field information: content, status, responsible person, and planned completion time; the status of an action item includes open and closed.