Operation drawing management system, method and device applied to offshore photovoltaic project

By introducing an operation drawing management system in offshore photovoltaic projects, the problem of inability to adaptively adjust the construction plan and coordinated management in the existing technology is solved, and effective management of offshore photovoltaic project operation drawings and coordinated control of project progress is achieved.

CN119539426APending Publication Date: 2025-02-28NORTHWEST ENGINEERING CORPORATION LIMITED
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411912093.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-24
Publication Date
2025-02-28

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively manage the operation drawings in offshore photovoltaic projects, and it is impossible to adaptively adjust the construction plan according to the actual completion time and coordinate management with the overall project progress.

Method used

Provide a work drawing management system applied to offshore photovoltaic projects, including a progress management module, a drawing review module and a drawing transmission module. Through these modules, the planned completion time of the work drawings is determined based on project construction information, the actual completion time is obtained, and the project construction plan associated with the work drawings is quickly followed up to ensure that the adjusted plan meets the project implementation requirements.

Benefits of technology

The comprehensive management of offshore photovoltaic project operation drawings is realized, the construction plan can be adjusted according to the actual completion time, ensuring the coordinated management of the project progress and the overall construction plan, and improving the effective implementation ability of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119539426A_ABST
    Figure CN119539426A_ABST
Patent Text Reader

Abstract

The invention relates to an operation drawing management system, method and device applied to an offshore photovoltaic project, and relates to the technical field of computers. The system comprises a progress management module used for determining planned completion time of different types of operation drawings according to project construction information; the actual completion time of the operation drawing is obtained, and the project construction scheme associated with the operation drawing is quickly followed up according to the actual completion time, so that the adjusted project construction scheme meets the project implementation requirements; the drawing auditing module is used for sending the to-be-audited drawing to a drawing auditing system and performing drawing auditing operation on the to-be-audited drawing to obtain a drawing auditing result; and the drawing transmission module is used for determining drawing operation stages corresponding to the operation drawings and transmitting the operation drawings in the drawing operation stages to the matched drawing operation system. According to the method, the labor cost can be saved, the management efficiency of the operation drawings is improved, and quick operation and comprehensive management of the operation drawings can be conveniently realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the field of computer technology, and in particular to an operation drawing management system applied to an offshore photovoltaic project, an operation drawing management method applied to an offshore photovoltaic project, and an operation drawing management device applied to an offshore photovoltaic project. Background Art

[0002] In recent years, as the world's attention to renewable energy continues to increase, offshore photovoltaics, as a new type of renewable energy, has gradually become the focus of attention. This technology uses the vast space of the ocean to install photovoltaic panels to collect solar energy and convert it into electricity. Offshore photovoltaic projects have multiple construction stages, and there are corresponding design drawings in different construction stages, such as typical road cross-section drawings, box-type transformer platform related design drawings, etc.; For example, the box-type transformer platform related design drawings can include prefabricated box-type transformer platform pile position drawings, prefabricated box-type transformer platform beam reinforcement drawings, etc. The types of work drawings involved in offshore photovoltaic projects are complex and numerous, and the management of design drawings is one of the important contents of construction project management, so an effective drawing management solution is urgently needed.

[0003] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present disclosure, and therefore may include information that does not constitute the prior art known to ordinary technicians in the field. Summary of the invention

[0004] The purpose of the present disclosure is to provide a work drawing management system for offshore photovoltaic projects, a work drawing management method for offshore photovoltaic projects, a work drawing management device for offshore photovoltaic projects, an electronic device, a computer-readable storage medium and a computer program product, thereby at least to a certain extent overcoming the problem that related drawing management solutions can only record the completion time of the drawings, but cannot adaptively adjust the project construction plan according to the actual completion time and combine it with the coordinated management of the overall progress of the project.

[0005] Other features and advantages of the present disclosure will become apparent from the following detailed description, or may be learned in part by the practice of the present invention.

[0006] According to a first aspect of the present disclosure, there is provided a work drawing management system for offshore photovoltaic projects, including: a progress management module, for determining the planned completion time of different types of work drawings according to project construction information, wherein the planned completion time is used to send prompt information; obtaining the actual completion time of the work drawings, and quickly following up the project construction plan associated with the work drawings according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements; a drawing review module, for obtaining drawings to be reviewed, and sending the drawings to be reviewed to a drawing review system, so as to perform a drawing review operation on the drawings to be reviewed through the drawing review system to obtain drawing review results; a drawing transmission module, for determining the drawing operation stage corresponding to the work drawings, and transmitting the work drawings in each of the drawing operation stages to a matching drawing operation system.

[0007] In an exemplary embodiment of the present disclosure, the progress management module also includes a progress management unit, a job extension unit and a scheme adjustment unit; the progress management unit is used to send a prompt message to the drawing operator associated with the work drawing according to the planned completion time; the job extension unit is used to determine the extended completion time of the work drawing based on the job extension operation of the drawing operator, and update the planned completion time to the extended completion time; the scheme adjustment unit is used to determine the implementation plan information of the sub-project associated with the work drawing according to the project construction information, adopt the critical path method and quickly follow up the project construction plan of the sub-project according to the implementation plan information and the actual completion time, and the implementation plan information includes one or more of the joint scheduling information of the sub-project, project implementation requirements, personnel allocation information, project cost information, and project safety information.

[0008] In an exemplary embodiment of the present disclosure, the operation drawing management system applied to offshore photovoltaic projects also includes a drawing modification module; the drawing modification module is used to obtain approved drawings and send the approved drawings to the drawing operation system, and the drawing operation system is used to provide an operation interface corresponding to the drawing operation personnel at each drawing operation stage; receive the drawing modification operation of the drawing operator on the approved drawings to obtain the modified drawings; send the approved drawings and the modified drawings to the drawing review module to perform the drawing review operation through the drawing review module.

[0009] In an exemplary embodiment of the present disclosure, the drawing modification module also includes a drawing modification unit; the drawing modification unit is used to obtain a first audit result corresponding to the modified drawing; when the first audit result is audit passed, obtain the drawing version number, drawing modification time and drawing modification comparison document of the modified drawing; based on the drawing version number, the drawing modification time and the drawing modification comparison document, generate a drawing modification record file.

[0010] In an exemplary embodiment of the present disclosure, the work drawing management system applied to offshore photovoltaic projects also includes a drawing storage module; the drawing storage module is used to determine the drawings to be stored, store the drawings to be stored in a drawing database, and record the drawing description files of the drawings to be stored in the drawing database, wherein the drawing description files include one or more of the following information: drawing number, operator information, reviewer information, work section information, downloader information, drawing association time information and drawing modification record file.

[0011] In an exemplary embodiment of the present disclosure, the work drawing management system applied to offshore photovoltaic projects also includes a drawing retrieval module; the drawing retrieval module is used to obtain input drawing retrieval information, and the drawing retrieval information includes one or more of drawing number, operator information, reviewer information, section information and downloader information; based on the drawing retrieval information, a drawing retrieval operation is performed in the drawing database to obtain a target drawing.

[0012] In an exemplary embodiment of the present disclosure, the work drawing management system applied to offshore photovoltaic projects also includes a format conversion module and a drawing display module; the format conversion module is used to obtain drawings to be converted and format conversion requirements, and based on the format conversion requirements, convert the drawings to be converted from a first file format to a second file format, the first file format and the second file format include a read-only file format and an editable file format; the drawing display module is used to display the work drawings to drawing operators.

[0013] In an exemplary embodiment of the present disclosure, the drawing review module includes a drawing review unit, which is used to determine the drawing reviewer associated with the drawing to be reviewed; determine the review authority level of each of the drawing reviewers, and each of the drawing reviewers conducts a level-by-level review of the drawings to be reviewed based on the review authority level; or obtain pre-configured drawing review rules, the drawing review rules including the drawing review level; based on the drawing review level, conduct a level-by-level review of the drawings to be reviewed.

[0014] According to a second aspect of the present disclosure, there is provided a method for managing work drawings applied to offshore photovoltaic projects, which is applied to any one of the above-mentioned work drawing management systems applied to offshore photovoltaic projects, and the method comprises: receiving a drawing work operation of a drawing work personnel, and determining an operation type of the drawing work operation; determining a drawing work interface corresponding to the operation type based on the work drawing management system applied to offshore photovoltaic projects; calling an associated operation module from the work drawing management system applied to offshore photovoltaic projects through the drawing operation interface, so as to perform relevant operations on the work drawings based on the associated operation module; obtaining an actual completion time of the work drawings, and quickly following up a project construction plan associated with the work drawings according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0015] According to a third aspect of the present disclosure, there is provided a work drawing management device for offshore photovoltaic projects, which is applied to any one of the above-mentioned work drawing management systems for offshore photovoltaic projects, and the device includes: an operation type determination module, which is used to receive a drawing operation operation of a drawing operator and determine the operation type of the drawing operation operation; an operation interface determination module, which is used to determine a drawing operation interface corresponding to the operation type based on the work drawing management system for offshore photovoltaic projects; a drawing operation module, which is used to call an associated operation module from the work drawing management system for offshore photovoltaic projects through the drawing operation interface, so as to perform relevant operations on the work drawings based on the associated operation module; and a plan adjustment module, which is used to obtain the actual completion time of the work drawing, and quickly follow up the project construction plan associated with the work drawing according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0016] According to a fourth aspect of the present disclosure, there is provided an electronic device, comprising: a processor; and a memory, wherein the memory stores computer-readable instructions, and when the computer-readable instructions are executed by the processor, the method for managing work drawings applied to offshore photovoltaic projects according to any one of the above items is implemented.

[0017] According to a fifth aspect of the present disclosure, there is provided a computer-readable storage medium having a computer program stored thereon, wherein when the computer program is executed by a processor, the method for managing work drawings applied to an offshore photovoltaic project according to any one of the above items is implemented.

[0018] According to a sixth aspect of the present disclosure, there is provided a computer program product, comprising a computer program, which, when executed by a processor, implements any one of the above-described methods for managing work drawings applied to offshore photovoltaic projects.

[0019] The technical solution provided by the present disclosure may have the following beneficial effects:

[0020] The work drawing management system applied to offshore photovoltaic projects in the exemplary embodiment of the present disclosure, on the one hand, performs progress management, review and transmission of various types of drawings through the work drawing management system, thereby realizing comprehensive management of work drawings. On the other hand, the progress management of work drawings is combined with the overall project management, and the project construction plan associated with the work drawings is quickly followed up. The drawing management plan is applied to the overall coordination process of the project progress, and the effective implementation of the project can be promoted under the premise of meeting the project implementation requirements.

[0021] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The drawings herein are incorporated into the specification and constitute a part of the specification, showing embodiments consistent with the present disclosure, and together with the specification, are used to explain the principles of the present disclosure. Obviously, the drawings described below are only some embodiments of the present disclosure, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0023] Figure 1 It is a system structure diagram of the operation drawing management system applied to offshore photovoltaic projects disclosed in the present invention;

[0024] Figure 2 This is a schematic diagram of the home page of the operation drawing management system for offshore photovoltaic projects disclosed in the present invention;

[0025] Figure 3 is another system structure diagram of the operation drawing management system applied to offshore photovoltaic projects disclosed in the present invention;

[0026] Figure 4 It is a page schematic diagram of a drawing modification page of the operation drawing management system applied to an offshore photovoltaic project disclosed in the present invention;

[0027] Figure 5 It is a page schematic diagram of a drawing review page of the operation drawing management system applied to an offshore photovoltaic project disclosed in the present invention;

[0028] Figure 6 A flowchart of a method for managing work drawings applied to an offshore photovoltaic project according to an exemplary embodiment of the present disclosure is schematically shown;

[0029] Figure 7 A block diagram of a work drawing management device applied to an offshore photovoltaic project according to an exemplary embodiment of the present disclosure is schematically shown;

[0030] Figure 8 A schematic diagram schematically illustrates a computer-readable storage medium according to an exemplary embodiment of the present disclosure;

[0031] Fig. 9 A block diagram of an electronic device according to an exemplary embodiment of the present disclosure is schematically shown. DETAILED DESCRIPTION

[0032] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in many forms and should not be construed as limited to the embodiments set forth herein; rather, these embodiments are provided so that this disclosure will be comprehensive and complete and will fully convey the concepts of the example embodiments to those skilled in the art. The same reference numerals in the figures represent the same or similar parts, and thus their repeated description will be omitted.

[0033] In addition, the described features, structures or characteristics may be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present disclosure. However, those skilled in the art will appreciate that the technical solutions of the present disclosure may be practiced without one or more of the specific details, or other methods, components, devices, steps, etc. may be adopted. In other cases, known structures, methods, devices, implementations, materials or operations are not shown or described in detail to avoid blurring the various aspects of the present disclosure.

[0034] The block diagrams shown in the accompanying drawings are merely functional entities and do not necessarily correspond to physically independent entities. That is, these functional entities may be implemented in software form, or these functional entities or parts of functional entities may be implemented in one or more software hardened modules, or these functional entities may be implemented in different networks and / or processor devices and / or microcontroller devices.

[0035] Offshore photovoltaics refers to a new form of energy that transfers photovoltaic power stations from land to sea and uses marine resources to generate electricity. Due to complex environmental factors, technical challenges, economic issues, and issues related to integration with other industries, offshore photovoltaic projects are highly complex and have multiple different construction stages. Different types of work drawings are involved in different construction stages, and the amount of data for each type of work drawing is also large. How to manage a large number of work drawings has become an urgent problem to be solved in the industry. In related solutions, the work drawings are still managed by relevant operating personnel. Manual management methods have the problems of low management efficiency, easy errors, and inability to be combined with the coordinated management of the overall project progress.

[0036] Based on this, in this example embodiment, firstly, a work drawing management system applied to an offshore photovoltaic project is provided. Figure 1 This is a system structure diagram of the operation drawing management system applied to offshore photovoltaic projects disclosed in the present invention. Figure 1 , the operation drawing management system applied to offshore photovoltaic projects can include the following modules.

[0037] The progress management module 110 is used to determine the planned completion time of different types of work drawings according to the project construction information, and the planned completion time is used to send prompt information; obtain the actual completion time of the work drawings, and quickly follow up the project construction plan associated with the work drawings according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements;

[0038] The drawing review module 120 is used to obtain drawings to be reviewed, and send the drawings to be reviewed to a drawing review system so that the drawing review system can perform a drawing review operation on the drawings to be reviewed and obtain drawing review results;

[0039] The drawing transmission module 130 is used to determine the drawing operation stage corresponding to the operation drawing, and transmit the operation drawing in each drawing operation stage to a matching drawing operation system.

[0040] According to the operation drawing management system applied to offshore photovoltaic projects in this example embodiment, on the one hand, the operation drawing management system performs progress management, review and transmission of various types of drawings, thereby realizing comprehensive management of operation drawings. On the other hand, the progress management of operation drawings is combined with the overall project management, and the project construction plan associated with the operation drawings is quickly followed up. The drawing management plan is applied to the overall coordination process of the project progress, and the effective implementation of the project can be promoted under the premise of meeting the project implementation requirements.

[0041] Next, the operation drawing management system (hereinafter referred to as the drawing management system) applied to an offshore photovoltaic project in this example embodiment will be further described.

[0042] The progress management module 110 is used to determine the planned completion time of different types of work drawings based on the project construction information. The planned completion time is used to send prompt information; obtain the actual completion time of the work drawings, and quickly follow up the project construction plan associated with the work drawings based on the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0043] In an exemplary embodiment of the present disclosure, project construction information may be information based on different construction stages of the engineering project, and the project construction information may include basic project information, project progress information, bill of quantities information, quality management information, safety management information, document management information, etc. The planned completion time, also known as the expected delivery time, may refer to the deadline determined by the initial plan to complete the work drawing, that is, the deadline for the completion of the work drawing according to the schedule. The actual completion time may be the time point when the work drawing is actually completed. The prompt information may be information used to prompt the drawing operator of the processing progress of the work drawings related to it. The project construction plan may be the actual implementation plan of a project.

[0044] In this embodiment, the work drawings involved in each construction stage are mainly determined based on the project construction information. The entire project construction stage may include multiple different types of work drawings. In order to respond to the requirements of construction content and construction progress, the work drawings and planned delivery times involved in the photovoltaic area, booster station, transmission line and other stages are specified. After the work drawings are determined, the planned completion time of each different type of work drawings can be determined according to the construction plan included in the project construction information. For example, the planned completion time of work drawing 1 is time point 1, and the planned completion time of work drawing 2 is time point 2, and time point 1 is earlier than time point 2, then work drawing 1 must be completed before work drawing 2.

[0045] In some other construction scenarios of the present disclosure, the drawing of some work drawings needs to rely on the completion results of other work drawings, such as the drawing of work drawing 4 needs to rely on work drawing 3, and work drawing 3 affects the completion progress of multiple subsequent work drawings, that is, only after work drawing 3 is completed can the subsequent related work drawings be drawn. At this time, ensuring that work drawing 3 is completed within the planned completion time is very important to the construction progress of the entire project, and the specific progress of work drawing 3 needs to be closely monitored.

[0046] refer to Figure 2 , Figure 2 This is a schematic diagram of the homepage of the work drawing management system for offshore photovoltaic projects disclosed in the present invention. The homepage of the drawing management system displays multiple different work drawings in a list format. The page provides operation controls, related projects, planned completion time, current remaining time, and extension application entry for the work drawings, so that relevant operators can view the time information of a certain drawing.

[0047] In addition, the specific conditions of offshore photovoltaic projects are complex. One work drawing may correspond to one process stage and multiple process stages, and affect the actual implementation of subsequent process stages. Therefore, in the progress management of work drawings, it is necessary to pay close attention to the actual completion of such work drawings and record the actual completion time. If the actual completion time of the work drawing is different from the planned completion time, the associated projects related to the work drawing are determined, and the project construction plan of the above project is adjusted according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0048] The project construction plan can be an implementation plan formulated based on a construction project. It may include but is not limited to the organizational plan (the composition of each functional department, their respective responsibilities, mutual relations, etc.), the personnel composition plan (project leader, heads of each department, heads of each professional, etc.), the technical plan (schedule arrangement, key technical plan, major construction step plan, etc.), the safety plan (overall safety requirements, construction risk factor analysis, safety measures, major construction step safety plan, etc.), the material supply plan (material supply process, acceptance and inspection process, temporary (urgent) material procurement process, etc.), in addition, depending on the size of the project, it may also include on-site security plan, logistics support plan, etc.

[0049] For example, if the actual completion time of the work drawing is different from the planned completion time, the planned completion time of the subsequent related work drawings or project construction can be adjusted by fast tracking. Specifically, the project construction plan associated with the work drawing is adjusted by using the fast tracking technology in project management. Fast tracking is a method of changing multiple activities that are generally implemented in sequence to parallel implementation, that is, running multiple activities in parallel on the critical path to reduce the overall project time. This method can compress the project schedule, but it may also lead to mutual interference of parallel activities, resource conflicts, and even rework, thereby increasing risks.

[0050] When using the quick follow-up technology to adjust the project construction plan associated with the work drawings, the Gantt chart tool can be used to visually display the time schedule and progress of the project tasks to better control the project progress. In the specific project progress adjustment process, if the actual completion time is earlier than the planned completion time, the operation time interval of the subsequent related projects can be adjusted accordingly, such as extending the operation time of the subsequent related projects, or retaining the operation time of the subsequent related projects and only adjusting the start and end completion time. If the actual completion time is later than the planned completion time, the operation time of some subsequent related projects is compressed so that the adjusted project construction plan meets the pre-specified project implementation requirements. Project implementation requirements can refer to the specific requirements of a series of work carried out from the project's survey and design, construction preparation, planning and arrangement, engineering construction, production preparation, completion acceptance, until the project is completed and put into production.

[0051] The drawing review module 120 is used to obtain drawings to be reviewed, and send the drawings to be reviewed to a drawing review system so that the drawing review system can perform a drawing review operation on the drawings to be reviewed and obtain drawing review results.

[0052] In an exemplary embodiment of the present disclosure, the drawing to be reviewed may be a work drawing waiting for a drawing reviewer to perform a drawing review operation. The drawing review system may be an electronic system for managing drawing review operations. The drawing review operation may be an operation in which a drawing reviewer reviews and verifies whether a certain work drawing complies with the drawing work criteria. The drawing review result may be a specific review result of whether the work drawing is qualified after the drawing reviewer completes the drawing review operation.

[0053] The work drawings that have been completed and uploaded by the drawing operators are regarded as drawings to be reviewed. The drawings to be reviewed need to be reviewed through the drawing review system to determine whether the drawings meet the drawing work criteria and subsequent project construction conditions. The drawings to be reviewed are sent to the drawing review system, and the drawing reviewers conduct drawing review operations on the drawings to be reviewed through the drawing review system. The drawing reviewers can modify, return, delete, annotate, and other operations on the drawings to obtain the review results of whether the drawings are qualified. If the work drawing meets the drawing work criteria, the drawing review result is judged as passed; if the work drawing does not meet the drawing work criteria and needs further modification, the drawing review result is judged as failed.

[0054] The drawing transmission module 130 is used to determine the drawing operation stage corresponding to the operation drawing, and transmit the operation drawing in each drawing operation stage to a matching drawing operation system.

[0055] In an exemplary embodiment of the present disclosure, the drawing operation phase may be all the operation phases involved in the operation drawing, and one operation drawing may be used for only one operation phase or may run through multiple operation phases. The drawing operation system may be an electronic system provided to the drawing operation personnel for drawing operation.

[0056] The drawing management system contains a large number of work drawings. For each drawing, the drawing work stage of the drawing can be determined, and the work drawing can be transferred to the system of the corresponding personnel. The corresponding personnel may include but are not limited to engineers, owners, on-site construction personnel, etc. related to the drawing process. For each different work drawing, the work drawing can be transferred to the matching drawing work system according to the drawing work stage of the drawing.

[0057] For example, work drawing 1 is in the stage of being completed, work drawing 2 is in the stage of being reviewed, and work drawing 3 is in the stage of being reviewed and passed, etc. Work drawing 1 is transferred to the drawing work system, work drawing 2 is transferred to the drawing review system, and work drawing 3 is transferred to the drawing database connected to the drawing management system, so that subsequent users can search for work drawing 3.

[0058] In addition, the drawing transmission module 130 is also used to transmit the work drawings to the printing device or scanning device corresponding to the drawing manager, and the printing device prints the drawings by itself, so that the drawing manager can perform the entry operation of the paper drawings.

[0059] In an exemplary embodiment of the present disclosure, the progress management module 110 also includes a progress management unit, a job extension unit and a scheme adjustment unit; the progress management unit is used to send prompt information to the drawing operator associated with the work drawing according to the planned completion time; the job extension unit is used to determine the extended completion time of the work drawing based on the job extension operation of the drawing operator, and update the planned completion time to the extended completion time; the scheme adjustment unit is used to determine the implementation plan information of the sub-project associated with the work drawing according to the project construction information, adopt the critical path method and adjust the project construction plan of the sub-project according to the implementation plan information and the actual completion time, and the implementation plan information includes one or more of the joint scheduling information of the sub-project, project implementation requirements, personnel allocation information, project cost information, and project safety information.

[0060] The drawing operator may be a related operator who performs various operations on the work drawings, and the drawing operation operations may include operations such as drawing, modifying and reviewing the work drawings. The work extension operation may be an operation to delay (or postpone) the planned completion time of the work drawings. The delayed completion time may be the planned completion time of the work drawings that is changed after the work extension operation.

[0061] After determining the planned completion time of the work drawing, the progress management unit can send reminder information to the drawing operators associated with the work drawing. For example, the deadline for completion of each work drawing (i.e., the planned completion time) is displayed on the drawing management system, and time reminder information is sent to the user according to the preset reminder cycle. When the difference between the planned completion time and the current time is less than the pre-configured time threshold, a time reminder message is sent to the operator to remind the relevant operator to complete the work drawings related to them in a timely manner. A prominent notification is issued to those who fail to submit work drawings on time. After the drawing operator completes and uploads a drawing, the actual completion time of the work drawing can be recorded.

[0062] During the project construction process, some emergencies are inevitable, which may cause some work drawings to fail to be completed on schedule. In order to deal with such situations, the progress management module also provides a work extension unit to implement the delayed submission process of drawings. Specifically, drawing operators can perform work extension operations through the work extension unit. Drawing operators can use the work extension operation to re-determine the planned drawing submission time as the delayed completion time.

[0063] The original planned completion time is updated with the deferred completion time, and the deferred completion time is used as the latest planned drawing delivery time. In the subsequent process, the drawing management system can send prompt information to the drawing operators based on the deferred completion time. By setting the operation extension unit, special situations in the drawing management process can be flexibly responded to, making the drawing management solution more adaptable and flexible.

[0064] The progress management module can also adjust the project construction plan through the plan adjustment unit. Since the offshore photovoltaic project is large and complex, multiple sub-projects can be formed after task splitting. The project construction information contains relevant information of all sub-projects in the entire project. When the actual completion time of a certain work drawing is inconsistent with the planned completion time, first determine the sub-project related to the work drawing, and determine the implementation plan information of each sub-project from the project construction information. The implementation plan information of the sub-project is a specific implementation plan formulated before the project construction, which is used to guide the actual implementation of the sub-project.

[0065] For example, the implementation plan information of a subproject may include one or more of the joint scheduling information of the subproject, project implementation requirements, personnel allocation information, project cost information, and project safety information. The joint scheduling information of the subproject may include the design of the work drawings and the production schedule of the part of the project; it may also include the scheduling relationship between the subproject and other subprojects in the entire project construction; it may also include the relationship between the subproject and other subprojects in terms of completion time. The joint scheduling information of the subproject may be configured according to the specific project construction plan, and the present disclosure does not make any special limitation on this.

[0066] Then, according to the implementation plan information and actual completion time of the sub-project, during the specific implementation process of the sub-project, the project construction plan of the sub-project is adaptively adjusted, and the adjusted project construction plan must comply with the pre-established project implementation requirements.

[0067] In the process of adjusting the project construction plan of the sub-project through quick follow-up, if the work drawings contain multiple related sub-projects, the critical path method can be used to coordinate the project construction plans of multiple sub-projects. The critical path method can identify the most important tasks and activities in the project, thereby determining the critical path of the project, helping relevant personnel focus on the most important tasks and avoid project delays. The critical path method can be a method of determining the completion date and total construction period of the project by finding the critical path and its time length.

[0068] Specifically, in the process of work drawing management, all sub-project tasks associated with the work drawings are organized into a flow chart, and their durations are recorded next to the task ID. Arrows indicate the order of activities, and the earliest start (Earliest Start-time, ES) time is marked on the left side of the activity, and the earliest finish (Earliest Finish-time) time is marked on the right side.

[0069] Mark the start time (S) to the left and right of the first activity; usually, this value is 0; then, mark the earliest start (ES) time of each activity, which is given by the largest number to the right of the activity's immediate predecessor (i.e., its earliest finish time, or EF). If an activity has multiple predecessors, the one with the later EF time is used as the ES of that activity. The EF of an activity is given by its earliest start time (ES) and its duration (t), which is ES + t. So, if an activity has an ES of 20 and will last for 10 days, its EF is 30. Mark all of these numbers in a flowchart with all of the subproject tasks, and the longest path will be the "Critical Path". The last number to the right of the last task in the sequence is the shortest time required to complete the project.

[0070] In the critical path method, it is necessary to focus on the float time of the work drawings. The float time defines the time that a task can be delayed without causing a delay in the project, including the "free float" of any subsequent related tasks and the "total float" of any delays in the entire project. Calculating the float of all activities in the project is crucial to better allocate resources, and the relevant scheduling personnel can control and adjust it according to the needs of project implementation. When the actual completion time of the work drawings is inconsistent with the planned completion time, the schedule management module can use the critical path method and adjust the actual construction plan of the project based on the actual completion time to achieve overall coordination of the project progress.

[0071] Further, refer to Figure 3In an exemplary embodiment of the present disclosure, there is also provided an operation drawing management system 300 applied to an offshore photovoltaic project. The operation drawing management system 300 applied to an offshore photovoltaic project also includes a drawing modification module 310; the drawing modification module 310 is used to obtain approved drawings and send the approved drawings to a drawing operation system, and the drawing operation system is used to provide an operation interface corresponding to drawing operators at each drawing operation stage; receive drawing modification operations of drawing operators on approved drawings to obtain modified drawings; send the approved drawings and modified drawings to the drawing review module to perform drawing review operations through the drawing review module.

[0072] The approved drawing may be a work drawing whose approval result is approved. The drawing modification operation may be an operation of modifying an approved drawing. The modified drawing may be a work drawing that has undergone the drawing modification operation.

[0073] The working drawings that have been reviewed and approved in the drawing management system are considered approved drawings. Approved drawings can be sent to the drawing operation system so that drawing operators at various drawing operation stages can obtain, query or modify the drawings. The drawing operation system can provide corresponding operation interfaces for drawing operators at different drawing operation stages.

[0074] For example, in the to-be-completed stage, an operation interface for drawing drawing personnel is provided, and the operation interface may include drawing drawing tools, etc. In the drawing review stage, an operation interface for drawing modification operations is provided to drawing personnel, and the operation interface may include drawing drawing tools, annotation tools, etc. In the completed stage, an operation interface for drawing download and preview functions is provided, and the operation interface may include download, preview and other operation controls.

[0075] Drawing operators can make further modifications to drawings that have passed the review. The entry to the drawing modification module is linked to staff with designated permissions, who can modify the drawings. For example, when the project construction requirements or construction operation guidelines change, the drawing reviewer can modify the drawings based on the above changes. Figure 4 , Figure 4 The diagram is a schematic diagram of a drawing modification page of the operation drawing management system for offshore photovoltaic projects disclosed in the present invention. The operator can call the drawing modification control of drawing 4 through the operation control to modify drawing 4.

[0076] If a drawing modification operation is received from a drawing operator on a drawing that has been approved, the modified drawing generated based on the drawing modification operation is determined, and the approved drawing (original drawing) and the modified drawing can be sent to the drawing review module together, so that the drawing reviewer can perform a drawing review operation on the modified drawing again based on the drawing review module to determine whether the modified drawing can replace the original drawing. Through the drawing modification module, the drawing operator can modify the drawing according to the actual drawing requirements, making the entire drawing operation process more flexible.

[0077] In an exemplary embodiment of the present disclosure, the drawing modification module 310 also includes a drawing modification unit; the drawing modification unit is used to obtain a first audit result corresponding to the modified drawing; when the first audit result is audit passed, obtain the drawing version number, drawing modification time and drawing modification comparison document of the modified drawing; based on the drawing version number, drawing modification time and drawing modification comparison document, generate a drawing modification record file.

[0078] Among them, the first audit result may be the drawing audit result corresponding to the modified drawing. The drawing version number may be the identification number of the specific version corresponding to the modified drawing. The drawing modification time may be the time when the drawing operator modifies the approved drawing and re-uploads it to the drawing management system. The drawing modification comparison document may be a comparison document used to compare the differences between the drawings before and after the modification. For example, the drawing modification comparison document may include a drawing modification comparison page (including modification annotation traces) and a drawing modification replacement page (excluding modification annotation traces, clean version of the working drawing). The drawing modification record file may be a file used to record the modification history information of the working drawing.

[0079] After completing the drawing review operation of the modified drawing and the original drawing, the review result of the modified drawing is used as the first review result. If the first review result is passed, it is considered that the modified drawing can replace the original drawing, and the drawing replacement operation will be performed later. Specifically, the drawing version number, drawing modification time, and drawing modification comparison document of the modified drawing are obtained.

[0080] For example, if the current modified drawing has been modified for the second time, the drawing version number can be "V2.0". If the drawing review operation fails in this round of modification and multiple modifications are required, the drawing version number can be updated for each modification. If the drawing modification operation is performed again in the second round of modification, the drawing version number will be updated to "V2.1". The drawing modification time can be the time point when the modified drawing is uploaded. The drawing modification comparison document can be the original document, the comparison page of the modified document, and the replacement page, etc.

[0081] Based on the above content, a drawing modification record file can be generated. The drawing modification record file records the modification history of the job drawing, including the time information, version information and personnel information of each modification, which is convenient for tracing back the versions of the job drawing at different stages.

[0082] In an exemplary embodiment of the present disclosure, continue to refer to Figure 3 The operation drawing management system 300 applied to offshore photovoltaic projects also includes a drawing storage module 320; the drawing storage module 320 is used to determine the drawings to be stored, store the drawings to be stored in the drawing database, and record the drawing description files of the drawings to be stored in the drawing database. The drawing description files include one or more of the following information: drawing number, operator information, reviewer information, section information, downloader information, drawing association time information and drawing modification record file.

[0083] Among them, the drawing database may be a database for storing work drawings. The drawing description file may be a file for describing relevant information of the work drawings. The drawing number may be a unique number for identifying a work drawing. The operator information may be information about the operator who completes the work drawing. The reviewer information may be information about the reviewer who performs the review operation on the work drawing. The section information may be information about the work department where the operator, reviewer, and downloader are located. The downloader information may be information about the person who downloads the work drawing. The drawing-related time information may be various types of time information related to the work drawing.

[0084] For drawings that have passed the review and need to be stored in the drawing database, they can be determined as drawings to be stored. The drawing storage module is used to store the drawings to be stored in the drawing database. When storing drawings that have passed the review, it is necessary to determine the drawing description file of the drawing in order to perform subsequent management of the drawings that have passed the review. The drawing description file includes but is not limited to the following fields: drawing number, operator information, reviewer information, section information, downloader information, drawing association time information, and drawing modification record file. The drawings that have passed the review are stored, and subsequent relevant personnel can query or obtain the work drawings from the drawing database.

[0085] In an exemplary embodiment of the present disclosure, continue to refer to Figure 3 The operation drawing management system 300 applied to offshore photovoltaic projects also includes a drawing retrieval module 330; the drawing retrieval module 330 is used to obtain input drawing retrieval information, and the drawing retrieval information includes one or more of the drawing number, operator information, reviewer information, section information and downloader information; based on the drawing retrieval information, a drawing retrieval operation is performed in the drawing database to obtain the target drawing.

[0086] The drawing search information may be query information input by a user based on a specific query requirement of a certain work drawing, for example, the drawing search information may include keywords of the drawing name, etc. The drawing search operation may be a search process based on the drawing search module to determine the required work drawing from the drawing database. The target drawing may be the work drawing that the searcher wants to find.

[0087] The present disclosure also provides a drawing retrieval module 330 for receiving a search operation for a work drawing by a relevant person. For example, a user can input drawing retrieval information through an operation interface, and the drawing retrieval information can include but is not limited to drawing number, operator information, reviewer information, section information, and downloader information. When performing a drawing retrieval operation, only one item can be used as the drawing retrieval information, or multiple items can be combined to construct a drawing retrieval item.

[0088] When the drawing management system receives the input drawing retrieval information, it can perform drawing retrieval operations in the drawing database based on the drawing retrieval information, search and determine the target drawings that meet the drawing retrieval information, and display the target drawings to relevant personnel. The drawing database stores only approved work drawings. Through the drawing retrieval module, personnel at different work stages can obtain and use relevant work drawings from the drawing database.

[0089] In an exemplary embodiment of the present disclosure, continue to refer to Figure 3 The operation drawing management system 300 applied to offshore photovoltaic projects also includes a format conversion module 340 and a drawing display module 350; the format conversion module 340 is used to obtain the drawings to be converted and the format conversion requirements, and based on the format conversion requirements, convert the drawings to be converted from a first file format to a second file format, the first file format and the second file format include a read-only file format and an editable file format; the drawing display module 350 is used to display the operation drawings to the drawing operators.

[0090] The drawing to be converted may be a work drawing to be converted into a format. The format conversion requirement may be a specific requirement for converting the format of the drawing, for example, the format conversion requirement may include specific content for converting the work drawing from an original format to a target format. The first file format may be the original format of the work drawing obtained from the drawing management system. The second file format may be a target format that the user wants to convert the work drawing into.

[0091] The work drawings have a variety of different file formats. In order to meet the needs of different users for drawing formats, the drawing management system also provides a format conversion module 340 for converting a drawing from the original format in the system to the target format required by the user. Common work drawing file formats may include but are not limited to three-dimensional design drawing format (DraWinG, DWG), drawing exchange file (Drawing Exchange Forma, DXF), design graphic file format (Design, DGN) and web graphic format (Design Web File, DWF).

[0092] The format conversion module can be used to obtain drawings to be converted and format conversion requirements corresponding to the drawings to be converted. According to the format conversion requirements, the format conversion module can convert the drawings to be converted from the original first file format to the required second file format, and convert qualified drawings from the original first file format to an editable unified format or a non-editable unified format, etc. For example, if the job drawings obtained from the drawing management system are in a read-only file format (first file format), when the user has a rewrite requirement, they can be converted to an editable file format (second file format). Through the format conversion module, flexible format conversion of job drawings can be achieved, so that the job drawings meet various usage scenarios.

[0093] It is easy for those skilled in the art to understand that the first file format and the second file format are only used to distinguish two different file formats corresponding to the work drawings, and should not impose any limitations on the present disclosure.

[0094] In addition, the drawing management system also provides a drawing display module 350, which is used to display the work drawings in the system to the corresponding drawing workers according to the specific operations of the relevant workers, and preview the relevant work drawings for project construction.

[0095] In an exemplary embodiment of the present disclosure, the drawing review module 120 includes a drawing review unit, which is used to determine the drawing reviewers associated with the drawings to be reviewed; determine the review authority level of each drawing reviewer, and each drawing reviewer conducts a level-by-level review of the drawings to be reviewed based on the review authority level; or obtain pre-configured drawing review rules, the drawing review rules including the drawing review level; based on the drawing review level, conduct a level-by-level review of the drawings to be reviewed.

[0096] The drawing reviewer may be a person who reviews and verifies whether the work drawings comply with the drawing work criteria. The review authority level may be the authority level corresponding to each drawing reviewer. The drawing review rules may be the rule document based on which the work drawings are reviewed for standardization and correctness. The drawing review level may be the importance level of the work drawings themselves.

[0097] In order to meet the review requirements of drawings of different importance levels, the drawing review operation can also be carried out in different levels. Furthermore, the drawing review module also provides a drawing review unit, which provides a one-level or multi-level review of personnel, or a one-level or multi-level review plan according to the importance of the drawing. Figure 5 , Figure 5 It is a page schematic diagram of a drawing review page of the work drawing management system applied to an offshore photovoltaic project disclosed in the present invention.

[0098] from Figure 5 It can be seen that the drawing review unit provides a scheme for step-by-step review based on personnel levels: first determine the drawing reviewers associated with the drawings to be reviewed. For example, drawing 1 to be reviewed requires three different reviewers (reviewer 1, reviewer 2 and reviewer 3) to perform the review operation; secondly, determine the review authority level of each drawing reviewer, and the review authority levels of the reviewers are from high to low: reviewer 2, reviewer 1 and reviewer 3; then, different drawing reviewers can review the drawings to be reviewed step by step based on the above review authority levels, and finally obtain the drawing review results.

[0099] The drawing review unit also provides a solution for step-by-step review based on the drawing review level: obtain the pre-configured drawing review rules, which define different types of drawing review levels. For example, the drawing review levels from high to low are: drawing type 2, drawing type 3, and drawing type 1. When there are multiple different types of drawings to be reviewed in the drawing review unit, the relevant reviewers will review the drawings to be reviewed one by one according to the drawing review level. The drawing review unit can review the drawings to be reviewed step by step according to the level of the reviewer or the importance of the drawings, so that important drawings can be reviewed and processed in a timely manner to avoid affecting the project progress.

[0100] In summary, the disclosed operation drawing management system for offshore photovoltaic projects includes: a progress management module, which is used to determine the planned completion time of different types of operation drawings according to project construction information, and the planned completion time is used to send prompt information; obtain the actual completion time of the operation drawings, and quickly follow up the project construction plan associated with the operation drawings according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements; a drawing review module, which is used to obtain the drawings to be reviewed, and send the drawings to be reviewed to the drawing review system, so as to perform drawing review operations on the drawings to be reviewed through the drawing review system, and obtain the drawing review results; a drawing transmission module, which is used to determine the drawing operation stage corresponding to the operation drawings, and transmit the operation drawings in each drawing operation stage to the matching drawing operation system. On the one hand, the operation drawing management system performs progress management, review and transmission of various types of drawings, so as to realize the comprehensive management of the operation drawings. On the other hand, the progress management of the operation drawings is combined with the overall project management, and the project construction plan associated with the operation drawings is quickly followed up. The drawing management plan is applied to the overall coordination process of the project progress, and the effective implementation of the project can be promoted under the premise of meeting the project implementation requirements. On the other hand, the drawing management system provides a variety of operation function modules adapted to the work drawings, which can meet the work and management of drawings in a variety of different situations.

[0101] Secondly, the present disclosure also provides a method for managing work drawings applied to offshore photovoltaic projects. The method can be implemented based on the above-mentioned work drawing management system applied to offshore photovoltaic projects. The server can be used to implement the method for managing work drawings applied to offshore photovoltaic projects of the present disclosure, and the terminal device can also be used to implement the method described in the present disclosure. The terminals described in the present disclosure may include mobile terminals such as mobile phones, tablet computers, laptops, PDAs, personal digital assistants (PDAs), and fixed terminals such as desktop computers. Figure 6 The following is a schematic diagram of a method for managing work drawings applied to an offshore photovoltaic project according to some embodiments of the present disclosure. Figure 6 The operation drawing management method applied to offshore photovoltaic projects may include the following steps:

[0102] Step S610: receiving a drawing operation performed by a drawing operator, and determining an operation type of the drawing operation.

[0103] According to some exemplary embodiments of the present disclosure, a drawing operator can perform a drawing operation based on a drawing management system, and the drawing operation can be an operation related to drawing production by the drawing operator. After receiving the drawing operation, the drawing management system can determine the specific operation type of the drawing operation, for example, the operation type can include making drawings, reviewing drawings, uploading drawings, and modifying drawings.

[0104] Step S620: determining a drawing operation interface corresponding to the operation type based on the operation drawing management system applied to the offshore photovoltaic project.

[0105] According to some exemplary embodiments of the present disclosure, after determining the operation type of the drawing operator, the drawing management system can determine the drawing operation interface corresponding to the operation type. The drawing operation interface can be an application program interface for calling a matching associated operation module. The drawing management system can call the matching drawing operation module through the drawing operation interface.

[0106] Step S630: calling the associated operation module from the operation drawing management system applied to the offshore photovoltaic project through the drawing operation interface, so as to perform relevant operations on the operation drawing based on the associated operation module.

[0107] According to some exemplary embodiments of the present disclosure, after determining the drawing operation interface, the drawing management system calls the associated operation module according to the drawing operation interface, and the associated operation module can be a system module provided to the drawing operator to perform related operations. For example, when the operator selects the drawing production control, the drawing operation interface will call the drawing production module and provide the corresponding operation interface to the user. When the operator selects the drawing modification control, the drawing management system will call the drawing modification module through the drawing operation interface, and provide the operation interface corresponding to the drawing modification module, so that the operator can perform the drawing modification operation. When the operator selects the drawing review control, the drawing management system will call the drawing review module through the drawing operation interface, and provide the operation interface corresponding to the drawing review module, so that the operator can perform the drawing review operation.

[0108] Step S640, obtaining the actual completion time of the work drawing, and quickly following up the project construction plan associated with the work drawing according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0109] According to some exemplary embodiments of the present disclosure, an offshore photovoltaic project may include multiple different types of work drawings. During the entire project implementation process, it is necessary to pay close attention to the actual completion of various work drawings and record the actual completion time. If the actual completion time of a work drawing is different from the planned completion time, the associated project related to the work drawing is determined, and the project construction plan of the above project is adjusted according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0110] According to the operation drawing management method applied to offshore photovoltaic projects in this example embodiment, on the one hand, the drawing management system can determine the corresponding drawing operation interface according to the user's operation type, and call the matching associated operation module to meet the user's specific operation needs, providing the user with a flexible drawing operation solution. On the other hand, according to the actual completion time of the drawing, the associated project construction plan can be quickly followed up, which can achieve overall coordination of the project and promote the effective implementation of the project under the premise of meeting the project implementation requirements.

[0111] It should be noted that, although the steps of the method of the present invention are described in a specific order in the drawings, this does not require or imply that the steps must be performed in this specific order, or that all the steps shown must be performed to achieve the desired results. Additionally or alternatively, some steps may be omitted, multiple steps may be combined into one step, and / or one step may be decomposed into multiple steps, etc.

[0112] In addition, in this exemplary embodiment, a work drawing management device for an offshore photovoltaic project is also provided. Figure 7 The operation drawing management device 700 applied to an offshore photovoltaic project may include: an operation type determination module 710 , an operation interface determination module 720 , a drawing operation module 730 , and a scheme adjustment module 740 .

[0113] Specifically, the operation type determination module 710 is used to receive the drawing operation operation of the drawing operation personnel and determine the operation type of the drawing operation operation; the operation interface determination module 720 is used to determine the drawing operation interface corresponding to the operation type based on the operation drawing management system applied to the offshore photovoltaic project; the drawing operation module 730 is used to call the associated operation module from the operation drawing management system applied to the offshore photovoltaic project through the drawing operation interface, so as to perform relevant operations on the operation drawings based on the associated operation module; the plan adjustment module 740 is used to obtain the actual completion time of the operation drawings, and quickly follow up the project construction plan associated with the operation drawings according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

[0114] The specific details of the virtual modules of the above-mentioned operation drawing management devices applied to offshore photovoltaic projects have been described in detail in the corresponding operation drawing management methods applied to offshore photovoltaic projects. The undisclosed details can be found in the implementation method content of the method part, and will not be repeated here.

[0115] It should be noted that although several modules or units of the operation drawing management device applied to offshore photovoltaic projects are mentioned in the above detailed description, this division is not mandatory. In fact, according to the embodiments of the present disclosure, the features and functions of two or more modules or units described above can be embodied in one module or unit. Conversely, the features and functions of one module or unit described above can be further divided into multiple modules or units for embodiment.

[0116] The exemplary embodiments of the present disclosure also provide a computer program product. The computer program product includes a computer program, and when the computer program is executed by a processor, the above-mentioned operation drawing management method applied to an offshore photovoltaic project is implemented.

[0117] In one embodiment, the computer program product may be a tangible product containing the computer program, such as a computer-readable storage medium storing the computer program. Figure 8 , Figure 8 The schematic diagram of a computer-readable storage medium according to an exemplary embodiment of the present disclosure is schematically shown. The computer-readable storage medium 800 can be a storage medium based on electrical, magnetic, optical, electromagnetic, infrared, etc. signals, including but not limited to: random access memory (RAM), read-only memory (ROM), magnetic tape, floppy disk, flash memory (Flash), mechanical hard disk (HDD), solid state drive (SSD), etc. Exemplarily, the computer program product can be implemented as a non-volatile storage medium storing a computer program, such as a read-only memory, a NAND flash memory (NandFlash), etc.

[0118] In one embodiment, the computer program product may be an intangible product including a computer program. Exemplarily, the computer program product may be implemented as a virtual digital product, such as a digital file storing an executable file, an installation package, etc. of the computer program.

[0119] The code of the computer program can be written in one or more programming languages. Programming languages ​​such as C language, Java, C++, etc. The program code can be executed entirely on the user computing device, or partially on the user computing device, or as a separate software package, or partially on the user computing device and partially on a remote computing device, or entirely on a remote computing device or server. In the case of a remote computing device, the remote computing device can be connected to the user computing device through any type of network, such as a local area network (LAN), a wide area network (WAN), etc., or can be connected to an external computing device (e.g., an Internet connection provided by an operator).

[0120] The computer program may be carried or transmitted via electrical, magnetic, optical, electromagnetic, infrared, or other signals. The electronic device may convert the signal carrying the computer program into a digital signal, thereby running the computer program. When the computer program is run on an electronic device, its code is used to enable the electronic device to execute (more specifically, the processor of the electronic device may execute) the method steps of various exemplary embodiments of the present disclosure, such as the above-mentioned method for managing work drawings applied to offshore photovoltaic projects.

[0121] The exemplary embodiments of the present disclosure also provide an electronic device, which may include a processor and a memory. The memory stores executable instructions of the processor, such as a computer program. The processor executes the method steps of various exemplary embodiments of the present disclosure by executing the executable instructions. In addition, the electronic device may also include a display for displaying a graphical user interface.

[0122] Reference below Fig. 9 , the electronic device is exemplified in the form of a general-purpose computing device. It should be understood that Fig. 9 The electronic device 900 shown is merely an example and should not limit the functions and scope of use of the embodiments of the present disclosure.

[0123] like Fig. 9 As shown, the electronic device 900 may include: a processor 910 , a memory 920 , a bus 930 , an I / O (input / output) interface 940 , a network adapter 950 , and a display 960 .

[0124] The memory 920 may include a volatile memory, such as a RAM 921, a cache unit 922, and may also include a non-volatile memory, such as a ROM 923. The memory 920 may also include one or more program modules 924, such program modules 924 include but are not limited to: an operating system, one or more application programs, other program modules, and program data, each of which or a combination thereof may include the implementation of a network environment. For example, the program module 924 may include each module in the above-mentioned device.

[0125] The processor 910 may include one or more processing units. For example, the processor 910 may include an AP (Application Processor), a modem processor, a GPU (Graphics Processing Unit), an ISP (Image Signal Processor), a controller, an encoder, a decoder, a DSP (Digital Signal Processor), a baseband processor and / or an NPU (Neural-Network Processing Unit), etc.

[0126] The processor 910 may be used to execute executable instructions stored in the memory 920, such as executing the above-mentioned method for managing work drawings applied to offshore photovoltaic projects.

[0127] The bus 930 is used to realize the connection between different components of the electronic device 900, and may include a data bus, an address bus, and a control bus.

[0128] The electronic device 900 can communicate with one or more external devices 1000 (eg, a keyboard, a mouse, an external controller, etc.) through the I / O interface 940 .

[0129] The electronic device 900 can communicate with one or more networks through the network adapter 950. For example, the network adapter 950 can provide mobile communication solutions such as 3G / 4G / 5G, or provide wireless communication solutions such as wireless LAN, Bluetooth, near field communication, etc. The network adapter 950 can communicate with other modules of the electronic device 900 through the bus 930.

[0130] The electronic device 900 may display a graphical user interface through the display 960 , such as an operating interface of a work drawing management system applied to an offshore photovoltaic project.

[0131] although Fig. 9Not shown, other hardware and / or software modules may also be provided in the electronic device 900, including but not limited to: microcode, device drivers, redundant processors, external disk drive arrays, RAID systems, tape drives, and data backup storage systems, etc.

[0132] As can be seen from the above, the technical solution of the present disclosure can be implemented as a method, an apparatus, a system, a computer program product, a storage medium, an electronic device, etc. Those skilled in the art can understand that various aspects of the present disclosure can be specifically implemented in the following forms, namely: a complete hardware implementation, a complete software implementation (including firmware, microcode, etc.), or an implementation combining hardware and software, such as being respectively referred to as a "circuit", "module" or "system".

[0133] It should be understood that the present disclosure is not limited to the specific method steps or structures described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from the scope thereof. Those skilled in the art will easily think of other embodiments based on the specific embodiments provided by the present disclosure. Therefore, the specific embodiments provided by the present disclosure are only exemplary, and the scope and spirit of the present disclosure are indicated by the claims, and any variations, uses or adaptive changes of the present disclosure should be covered, which follow the general principles of the present disclosure and include common knowledge or customary technical means in the technical field that are not disclosed in the present disclosure.

Claims

1. An operation drawing management system applied to offshore photovoltaic projects, characterized in that: include: The progress management module is used to determine the planned completion time of different types of work drawings according to the project construction information, and the planned completion time is used to send prompt information; obtain the actual completion time of the work drawings, and quickly follow up the project construction plan associated with the work drawings according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements; A drawing review module is used to obtain drawings to be reviewed, and send the drawings to be reviewed to a drawing review system so that the drawing review system can perform a drawing review operation on the drawings to be reviewed and obtain drawing review results; The drawing transmission module is used to determine the drawing operation stage corresponding to the operation drawing, and transmit the operation drawings in each of the drawing operation stages to a matching drawing operation system.

2. The system according to claim 1, characterized in that The progress management module also includes a progress management unit, a job extension unit and a plan adjustment unit; The progress management unit is used to send prompt information to the drawing operator associated with the work drawing according to the planned completion time; The job extension unit is used to determine the extended completion time of the job drawing based on the job extension operation of the drawing operator, and update the planned completion time to the extended completion time; The scheme adjustment unit is used to determine the implementation plan information of the sub-project associated with the work drawing based on the project construction information, and adopt the critical path method to quickly follow up the project construction plan of the sub-project based on the implementation plan information and the actual completion time. The implementation plan information includes one or more of the joint scheduling information of the sub-project, project implementation requirements, personnel allocation information, project cost information, and project safety information.

3. The system according to claim 1, characterized in that The operation drawing management system applied to offshore photovoltaic projects also includes a drawing modification module; The drawing modification module is used to obtain drawings that have passed the review and send the drawings that have passed the review to the drawing operation system. The drawing operation system is used to provide an operation interface corresponding to the drawing operation personnel at each drawing operation stage; receiving a drawing modification operation of the drawing operator on the approved drawing to obtain a modified drawing; The drawings that have passed the review and the modified drawings are sent to the drawing review module so that the drawing review operation is performed through the drawing review module.

4. The system according to claim 3, characterized in that The drawing modification module also includes a drawing modification unit; The drawing modification unit is used to obtain a first review result corresponding to the modified drawing; When the first review result is passed, obtaining the drawing version number, drawing modification time and drawing modification comparison document of the modified drawing; A drawing modification record file is generated based on the drawing version number, the drawing modification time and the drawing modification comparison document.

5. The system according to claim 1, characterized in that The operation drawing management system applied to offshore photovoltaic projects also includes a drawing storage module; The drawing storage module is used to determine the drawings to be stored, store the drawings to be stored in a drawing database, and record the drawing description files of the drawings to be stored in the drawing database. The drawing description files include one or more of the following information: drawing number, operator information, reviewer information, work section information, downloader information, drawing association time information and drawing modification record file.

6. The system according to claim 5, characterized in that The operation drawing management system applied to offshore photovoltaic projects also includes a drawing retrieval module; The drawing retrieval module is used to obtain input drawing retrieval information, wherein the drawing retrieval information includes one or more of the drawing number, operator information, reviewer information, section information, and downloader information; Based on the drawing retrieval information, a drawing retrieval operation is performed in the drawing database to obtain a target drawing.

7. The system according to any one of claims 1 to 6, characterized in that: The operation drawing management system applied to offshore photovoltaic projects also includes a format conversion module and a drawing display module; The format conversion module is used to obtain the drawing to be converted and the format conversion requirement, and based on the format conversion requirement, convert the drawing to be converted from a first file format to a second file format, wherein the first file format and the second file format include a read-only file format and an editable file format; The drawing display module is used to display the operation drawings to the drawing operation personnel.

8. The system according to claim 1, characterized in that The drawing review module includes a drawing review unit, which is used to determine the drawing reviewer associated with the drawing to be reviewed; Determine the review authority level of each of the said drawing reviewers; Each of the drawing reviewers reviews the drawings to be reviewed level by level based on the review authority level; or Obtaining pre-configured drawing review rules, wherein the drawing review rules include drawing review levels; Based on the drawing review level, the drawings to be reviewed are reviewed level by level.

9. A method for managing operation drawings applied to offshore photovoltaic projects, characterized in that: The method for the operation drawing management system for offshore photovoltaic projects as claimed in any one of claims 1 to 8 comprises: Receiving a drawing operation performed by a drawing operator, and determining an operation type of the drawing operation; Determining a drawing operation interface corresponding to the operation type based on the operation drawing management system applied to the offshore photovoltaic project; Through the drawing operation interface, calling the associated operation module from the operation drawing management system applied to the offshore photovoltaic project, so as to perform relevant operations on the operation drawings based on the associated operation module; The actual completion time of the work drawing is obtained, and the project construction plan associated with the work drawing is quickly followed up according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.

10. A work drawing management device applied to an offshore photovoltaic project, characterized in that: The operation drawing management system for offshore photovoltaic projects according to any one of claims 1 to 8, the device comprising: An operation type determination module, used for receiving a drawing operation performed by a drawing operator, and determining an operation type of the drawing operation; An operation interface determination module, used to determine a drawing operation interface corresponding to the operation type based on the operation drawing management system applied to the offshore photovoltaic project; A drawing operation module, used to call a related operation module from the operation drawing management system applied to the offshore photovoltaic project through the drawing operation interface, so as to perform related operations on the operation drawings based on the related operation module; The scheme adjustment module is used to obtain the actual completion time of the work drawing, and quickly follow up the project construction plan associated with the work drawing according to the actual completion time, so that the adjusted project construction plan meets the project implementation requirements.