Process Planning Method

The process planning method optimizes the manufacturing of offshore wind turbine foundations by allowing early production of components and managing inventory efficiently, addressing inefficiencies in conventional construction methods to shorten project timelines.

JP7614434B1Active Publication Date: 2025-01-15NIPPON STEEL & SUMIKIN ENGINEERING CO LTD

Patent Information

Application Number
JP2024134423
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2025-01-15
Estimated Expiration
2044-08-09

AI Technical Summary

Technical Problem

Conventional construction methods for offshore wind turbine foundations are inefficient, leading to prolonged construction project timelines.

Method used

A process planning method that includes structural analysis using a computer to optimize the manufacturing of monopile foundations, allowing for the production of certain components before the completion of structural analysis, and managing inventory in predetermined increments to streamline the construction process.

Benefits of technology

This approach significantly shortens the construction project timeline by enabling early manufacturing of critical components and reducing excess inventory, thereby accelerating the start of offshore wind turbine operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007614434000001_ABST
    Figure 0007614434000001_ABST
Patent Text Reader

Abstract

The objective is to provide a construction project planning method capable of shortening the construction project schedule. [Solution] A process planning method for planning the processes of a monopile foundation construction project, comprising: a structural analysis process SA3 in which a computer performs multiple structural analyses of a monopile foundation model; and a first fabrication process SB1 that is started after completion of the earthquake response analysis included in the first structural analysis process SA3 and before completion of the earthquake response analysis included in the second structural analysis process SA3, wherein the first fabrication process SB1 does not fabricate the interface flange of the transition piece, but fabricates parts of the transition piece other than the interface flange, and the first fabrication process SB1 fabricates a connection part of the monopile body that is connected to the transition piece in a state that overlaps with it when viewed horizontally, but does not fabricate parts of the monopile body other than the connection part.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a process planning method. [Background technology]

[0002] Conventionally, structures are manufactured in a factory and then assembled and installed at a construction site. Patent document 1 discloses a method of constructing vertical structures in which a unit structure, prefabricated in a factory, consists of a single smooth metal plate with horizontal reinforcing ribs welded to its outer surface. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 62-86273 Summary of the Invention [Problem to be solved by the invention]

[0004] The conventional construction methods have a problem in shortening the construction project schedule.

[0005] The present disclosure has been made in consideration of the above-mentioned circumstances, and aims to provide a process planning method that can shorten the process of a construction project. [Means for solving the problem]

[0006] A process planning method according to one embodiment of the present disclosure is a process planning method for planning the process of a construction project of a monopile foundation having a monopile body and a transition piece and supporting the tower of an offshore wind turbine, the process comprising: a structural analysis process in which a computer performs a structural analysis of a model of the monopile foundation multiple times; and a first production process in which at least a part of the components that constitute the monopile foundation is produced after completion of an earthquake response analysis included in a first structural analysis process and before completion of an earthquake response analysis included in a second structural analysis process, wherein the first production process produces the transition piece, the first production process does not produce an interface flange of the transition piece, and produces a part of the transition piece other than the interface flange, the first production process produces the monopile body, the first production process produces a connection part of the monopile body that is connected in a state where it overlaps with the transition piece in a horizontal view, and does not produce a part of the monopile body other than the connection part. Effect of the Invention

[0007] According to the present disclosure, it is possible to provide a process planning method that can shorten the process of a construction project. [Brief description of the drawings]

[0008] [Figure 1] 1 is a diagram showing a first example of a marine structure according to an embodiment. FIG. [Diagram 2] FIG. 2 is a diagram showing a state in which a plurality of the marine structures shown in FIG. 1 are installed. [Diagram 3] 3 is a cross-sectional view of the monopile body taken along the III-III direction shown in FIG. 1. [Figure 4] FIG. 2 is an enlarged view of a portion IV shown in FIG. [Diagram 5] 3 is a flow chart of a process planning method according to an embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] Hereinafter, an offshore structure and a process planning method for an offshore structure according to an embodiment of the present disclosure will be described with reference to the drawings. The marine structure according to this embodiment is a foundation structure that supports the tower of an offshore wind turbine. The marine structure may be, for example, a jacket foundation, a monopile foundation, or any other structure.

[0010] (About offshore structures) FIG. 1 is a diagram showing a first example of a marine structure 1 according to an embodiment. FIG. 2 is a diagram showing a state in which a plurality of marine structures 1 shown in FIG. 1 are installed. As shown in Fig. 1, in this embodiment, the marine structure 1 is a monopile foundation. As shown in Fig. 2, a plurality of marine structures 1 may exist in the same wind farm or sea area (hereinafter, installation site A), for example.

[0011] In this embodiment, the marine structure 1, which is a monopile foundation, has a monopile body 10, a transition piece 20, and an auxiliary facility 30, as shown in FIG. The monopile body 10 is a cylindrical member that is driven into the seabed OF. In this embodiment, the monopile body 10 refers to, for example, a steel pipe at least a portion of which is embedded in the ground. In this embodiment, at least one of the inner and outer surfaces of the monopile body 10 may be coated with anti-corrosion coating. In this embodiment, the monopile body 10 is formed by connecting multiple unit cylindrical bodies 11, which are cylindrical members having any length, in the longitudinal direction, as shown in Fig. 1. The monopile body 10 may be made of steel or any other material. Furthermore, in this embodiment, the multiple marine structures 1 installed at the same installation location A as described above may have some or all of the shape of the monopile body 10 in common, or the shape may be set individually as appropriate to suit the conditions such as the ground and water depth at the respective installation locations of the multiple marine structures 1.

[0012] FIG. 3 is a cross-sectional view of the monopile body 10 taken along the line III-III in FIG. In this embodiment, the monopile body 10 may be formed so that its cross-sectional shape in transverse section is circular, as shown in Fig. 3. A tubular unit 11 having such a cross-sectional shape may be formed, for example, by connecting ends of a plurality of curved plates 11A as shown in Fig. 3, by bending a steel plate, or by integrally molding a tubular member. Alternatively, the monopile body 10 may be formed to have an elliptical cross-sectional shape, or any other cross-sectional shape.

[0013] As described above, the monopile body 10 is formed by connecting a plurality of unit tubular bodies 11 in the longitudinal direction. At this time, in the monopile body 10, the portion that is installed underground, and in particular the portion close to the surface (seabed surface) of the seabed OF, may be subjected to a relatively large bending moment compared to other portions. For this reason, the unit tubular bodies 11 located in these portions may have a larger plate thickness than the unit tubular bodies 11 located in other portions.

[0014] FIG. 4 is an enlarged view of part IV shown in FIG. A cable C may be provided inside the monopile body 10 as shown in Fig. 4. The cable C is, for example, a cable for connecting various devices (not shown) provided inside the offshore wind turbine WM with a submarine cable (not shown) laid on the seabed OF. To enable the submarine cable (not shown) to be connected to the cable C shown in Fig. 4, a hole (not shown) may be provided in a side wall of the monopile body 10 near the seabed surface. When the cable C and the submarine cable (not shown) are connected by a joint (not shown), the boundary between the cable C and the submarine cable (not shown) may be confirmed by the location of the joint (not shown). Also, the boundary between the cable C and the submarine cable (not shown) may be confirmed by considering the cable that has landed on the seabed as the submarine cable (not shown).

[0015] The transition piece 20 is disposed on the upper part of the monopile body 10, as shown in Figures 1 and 4. Specifically, the transition piece 20 is provided so as to overlap with a part of the monopile body 10 including its upper end when viewed in the horizontal direction. That is, the upper part of the monopile body 10 is inserted into the transition piece 20 from below. As shown in Figure 4, it is preferable that the part of the monopile body 10 including its upper end and the transition piece 20 have a cone shape. That is, it is preferable that the part of the monopile body 10 including its upper end and the transition piece 20 have a truncated cone shape whose diameter decreases from the bottom to the top. 4, a portion of the monopile body 10 including its upper end and the transition piece 20 may be fixed by grout G in a state in which they are arranged so as to overlap each other when viewed in the horizontal direction. The grout G is injected into the gap (annular space) between the upper part of the monopile body 10 and the transition piece 20. The transition piece 20 may be made of, for example, steel, or any other suitable material. The transition piece 20 disposed on the upper part of the monopile body 10 as described above connects the monopile body 10 to the tower T of the offshore wind turbine WM. The tower T extends upward from the connection position with the transition piece 20. The offshore wind turbine WM is installed on the ocean. In this embodiment, the transition piece 20 has an interface flange IF as shown in FIG. 4. The interface flange IF is provided at the upper end of the transition piece 20. In this embodiment, a similar interface flange IF is also provided at the lower end of the tower T of the offshore wind turbine WM. The connection between the transition piece 20 and the tower T of the offshore wind turbine WM is achieved by joining the interface flanges IF provided on the transition piece 20 and the tower T of the offshore wind turbine WM with bolts B as shown in FIG. 4. Note that the transition piece 20 may have a function of adjusting the connection angle with the tower T. With this configuration, the tower T of the offshore wind turbine WM can be adjusted to extend in the vertical direction when connected to the lower end of the tower T of the offshore wind turbine WM. A cable C may be provided inside the transition piece 20 as shown in Fig. 4. A hole H having a circular, elliptical or any other shape may be provided inside the transition piece 20 to pass the cable C through. As described above, a plurality of marine structures 1 may exist at the same installation site A as shown in Fig. 2. In this case, it is preferable that the shape of the hole H provided inside the transition piece 20 in the plurality of marine structures 1 is the same. In this embodiment, the transition pieces 20 may have a common structure in a plurality of marine structures 1 provided at the same installation site A as described above, or may have different structures.

[0016] The auxiliary facilities 30 are provided to enable workers to move and perform various operations on the marine structure 1. In this embodiment, the auxiliary facilities 30 include, for example, a mooring facility 31, a ladder 32, a landing 33, a work platform 34, and a passageway 35, as shown in Fig. 4. Each of the auxiliary facilities 30 may be made of, for example, steel, or any other material. In this embodiment, the auxiliary facilities 30 may have a common structure for the multiple marine structures 1 installed at the same installation site A as described above, or may be different.

[0017] The mooring equipment 31 is a member for mooring a work boat in the marine structure 1. In this embodiment, the mooring equipment 31 shown in Fig. 4 has, for example, a pair of rod-shaped members extending in the vertical direction. With the work boat moored to the mooring equipment 31, a worker moves from the work boat to the marine structure 1. The ladder 32 is used for a worker who has moved to the marine structure 1 to move up and down. In this embodiment, the ladder 32 shown in Fig. 4 is provided between a pair of rod-shaped members of the mooring equipment 31, for example. 4, the landing 33 is provided at the upper end of the ladder 32. In this embodiment, the landing 33 is a place where a worker who moves from the work boat to the marine structure 1 and moves upward using the ladder 32 gets off. The work floor 34 is a place where workers perform various tasks. The work floor 34 may be provided with a davit crane DC for lifting materials, for example, as shown in FIG. The passage 35 is a portion where a worker moves. In this embodiment, the passage 35 includes the ladder 32 and the landing 33. In other words, in this embodiment, the ladder 32 and the landing 33 may be collectively referred to as the passage 35. The marine structure 1 according to this embodiment is constituted by the above components.

[0018] (About process planning) Next, a process planning method according to this embodiment will be described. The process planning method according to this embodiment is a method for planning the process of a construction project of an offshore structure 1 that supports the tower T of an offshore wind turbine WM. The process planning method described below is applied to the manufacture of the offshore structure 1 according to this embodiment. The offshore structure 1 according to this embodiment is manufactured through a process based on the process planning method, and installed offshore. In this embodiment, producing the marine structure 1 includes procuring materials, processing the materials to form various components, and assembling the various components to form the marine structure 1.

[0019] FIG. 5 is a flow chart of a process planning method according to the embodiment. As shown in FIG. 5, the process planning method according to this embodiment includes a design review flow SA and a production flow SB. The design review flow SA is a flow for reviewing the shape of the marine structure 1. As shown in Fig. 5, the design review flow SA includes a preliminary investigation process SA1, a shape review process SA2, and a structure analysis process SA3.

[0020] The preliminary investigation process SA1 is a process of investigating the specific conditions, including ground conditions and wave conditions, at the installation site A where the marine structure 1 and the offshore wind turbine WM will be installed. Specifically, in the preliminary investigation process SA1, for example, wind observation, geological investigation, bathymetry, indoor soil testing, etc. are performed. The results of the various investigations in the preliminary investigation process SA1 are reflected in the analysis conditions in, for example, the shape consideration process SA2 and the structure analysis process SA3. Incidentally, a pre-first manufacturing process SB1a (described later) in the manufacturing flow SB may be started before or after the preliminary inspection process SA1.

[0021] The shape examination process SA2 is a process for examining the shape of the marine structure 1 and creating a model of the marine structure 1. Specifically, for example, in the marine structure 1 which is a monopile foundation, the diameter and thickness of the monopile body 10, the diameter and thickness of the transition piece 20, etc. are examined and a model to be used in the structural analysis process SA3 is created.

[0022] Here, in this embodiment, in the first pre-fabrication process SB1a (described later), materials constituting the monopile body 10 and the transition pieces 20 that are highly versatile may be secured in advance as inventory. That is, for example, multiple types of steel pipes with different diameters, plate thicknesses, and materials may be procured in advance as materials constituting the monopile body 10 and the transition pieces 20. In such a case, the diameters and plate thicknesses of the multiple types of steel pipes vary in predetermined numerical increments. The predetermined numerical values ​​may be, for example, any numerical values ​​as appropriate. The predetermined numerical values ​​are, for example, discrete values. At this time, in this embodiment, a plurality of shapes of the marine structure 1 may be considered in the shape consideration step SA2. In the shape consideration step SA2, the diameters and plate thicknesses of the monopile body 10 and the transition pieces 20 are preferably set in predetermined numerical increments in accordance with the steel pipes secured as inventory. Moreover, the predetermined numerical values ​​are preferably discrete values ​​in accordance with the steel pipes secured as inventory. This makes it easier to perform, for example, the structural analysis step SA3 described below. Also, it makes it easier to prevent excess inventory when procuring materials for the monopile body 10 and the transition pieces 20 (details will be described later). After the shape of the marine structure 1 is considered in the shape consideration step SA2, the first intermediate manufacturing step SB1b (described later) in the manufacturing flow SB is started and the process proceeds to the structural analysis step SA3. However, the start of the first intermediate manufacturing step SB1b is not essential. In other words, whether or not to start the first intermediate manufacturing step SB1b is determined appropriately.

[0023] The structural analysis step SA3 is a step of performing a structural analysis of the model of the marine structure 1. In this embodiment, the structural analysis step SA3 may be performed multiple times. In other words, in this embodiment, the structural analysis step SA3 may be a step in which a computer performs a structural analysis of the model of the marine structure 1 multiple times. The structural analysis process SA3 is performed based on the shape of the marine structure 1 considered in the shape consideration process SA2. As shown in Fig. 5, the structural analysis process SA3 includes an analysis implementation step SA3a, a first confirmation step SA3b, a second confirmation step SA3c, a third confirmation step SA3d, and a review step SA3e.

[0024] The analysis execution step SA3a is a step of performing a structural analysis of the model of the marine structure 1. In this embodiment, the analysis execution step SA3a performs, for example, eigenvalue analysis, wind-wave integrated analysis, earthquake response analysis, etc. The eigenvalue analysis, wind-wave integrated analysis, and earthquake response analysis may be performed by frame structure analysis or finite element analysis. It is also preferable that the wind-wave integrated analysis and earthquake response analysis are performed by time history response analysis. In the analysis execution step SA3a, a static analysis may be performed on the auxiliary equipment 30. In the static analysis, for example, wave load, ship docking load, towing load, etc. may be considered as loads. When multiple shapes of the marine structure 1 are considered in the shape consideration step SA2, for example, an analysis is performed for each shape in the analysis execution step SA3a.

[0025] The first confirmation step SA3b is a step for confirming the results of the analysis performed in the analysis performing step SA3a. Specifically, in the first confirmation step SA3b, it is confirmed whether or not all the members of the marine structure 1 can be finalized based on the overall shape of the model of the marine structure 1 when the analysis performing step SA3a is performed. If it is determined that all components of the marine structure 1 can be finalized based on the overall shape of the model of the marine structure 1 (SA3b: yes), the structural analysis step SA3 is terminated and the shape of the marine structure 1 is finalized. If it is determined that all components of the marine structure 1 cannot be finalized (SA3b: no), the process proceeds to a second confirmation step SA3c.

[0026] The second confirmation step SA3c is a step of confirming whether or not the shape of a part of the model of the marine structure 1, for which it has been determined that not all components are finalizable, is finalizable. Note that the part of the model of the marine structure 1 refers to either the monopile main body 10 or the transition piece 20 in the marine structure 1. In this case, the part of the model of the marine structure 1 may be a part of the monopile main body 10 or a part of the transition piece 20. Among the parts of the model of the marine structure 1, those parts that are determined to be finalizable (SA3c: finalizable parts) start the first manufacturing process SB1c (described later) in the manufacturing flow SB. Among the parts of the model of the marine structure 1, those parts that are determined to be not finalizable (SA3c: non-finalizable parts) move to the third confirmation step SA3d.

[0027] The third confirmation step SA3d is a step of confirming the degree of necessary reinforcement for members that are determined not to be finalizable among parts of the model of the marine structure 1. That is, the third confirmation step SA3d is a step of confirming the degree of need to change the shape of the model of the marine structure 1. For components that are not finalizable, if it is determined that relatively large-scale shape modification is required (SA3d: another shape review step is required), the component moves to the shape review step SA2, where the shape is reconsidered.For components that are not finalizable, if it is determined that large-scale shape modification is not required (SA3d: review of component cross section and material is sufficient), the component moves to the review step SA3e.

[0028] The review step SA3e is a step of reviewing the shape of the model of the relevant member in the marine structure 1 when it is determined that large-scale shape modification is not necessary for the member determined not to be finalizable. In the review step SA3e, for example, the cross-sectional shape of the model of the relevant member and the material used are reviewed. For members for which the review step SA3e has been completed, the analysis execution step SA3a is performed again. In this embodiment, the shape consideration step SA2 and the structure analysis step SA3 may be repeated until the shape of the marine structure 1 is finally determined.

[0029] In this embodiment, for example, when multiple types of steel pipes whose diameters vary in a predetermined numerical increment are secured as stock as materials for constructing the monopile body 10 and the transition piece 20, the structural analysis step SA3 may perform structural analysis of the model of the marine structure 1 only in the predetermined diameter increment. In this case, it is preferable to consider models in the predetermined diameter increment as multiple shapes in the shape consideration step SA2 in accordance with the multiple types of steel pipes secured as stock. In other words, in the structural analysis step SA3, the diameters of the monopile body 10 and the transition piece 20 may be those set in the above-mentioned shape consideration step SA2 in the predetermined numerical increment in accordance with the multiple types of steel pipes secured as stock. Specifically, for example, the predetermined diameter is preferably in the range of 7000 mm to 15000 mm in diameter increments of 500 mm, but may be any other numerical value.

[0030] Also, for example, when multiple types of plate materials or steel pipes whose thicknesses vary in a predetermined numerical increment are secured as materials constituting the monopile body 10 or the transition piece 20, the structural analysis step SA3 may perform the structural analysis of the model of the marine structure 1 only in the predetermined plate thickness increments. In this case, it is preferable to consider models in the predetermined plate thickness increments as multiple shapes in the shape consideration step SA2 in accordance with the multiple types of plate materials and steel pipes secured as inventory. In other words, in the structural analysis step SA3, the plate thicknesses of the monopile body 10 or the transition piece 20 may be set in the above-mentioned shape consideration step SA2 in the predetermined numerical increments in accordance with the multiple types of plate materials and steel pipes secured as inventory. Specifically, for example, the predetermined plate thickness is preferably in the range of 70 mm to 100 mm in 5 mm increments, but may be any other numerical value.

[0031] As described above, by setting the diameter and plate thickness in the structural analysis process SA3 in predetermined numerical increments in accordance with the multiple types of plate materials and steel pipes secured as inventory, it is possible to prevent excess inventory from occurring and also to reduce the number of analyses performed at one time in the structural analysis process SA3. This makes it easier to perform the structural analysis process SA3. In this manner, the design review flow SA is performed.

[0032] Here, in the structural analysis step SA3, the various analyses described above may take several months. Also, the shape of the marine structure 1 (e.g., component cross-sections, materials, etc.) is often roughly determined at the time of the first structural analysis step SA3. In this case, if the structural analysis step SA3 is performed several times and the manufacture of the marine structure 1 is started after the shape of the marine structure 1 is finally determined, there is room to shorten the process of the construction project for the marine structure 1. Therefore, in this embodiment, the production flow SB is carried out as follows, which contributes to shortening the process of a construction project.

[0033] The fabrication flow SB is a flow for fabricating the marine structure 1. Specifically, the fabrication flow SB is a flow for procuring materials for constructing the marine structure 1 and processing the procured materials. As shown in Fig. 5, the fabrication flow SB includes a first fabrication process SB1, a second fabrication process SB2, and an assembly process SB3.

[0034] The first fabrication process SB1 is, for example, the structural analysis process SA3 described above, which is started after the completion of the earthquake response analysis included in the first structural analysis process SA3 and before the completion of the earthquake response analysis included in the second structural analysis process SA3. The first fabrication process SB1 is a process for fabricating at least a part of the members constituting the marine structure 1. Since the analysis results of each component affect each other, normally production (procurement) would not begin until all of the above-mentioned structural analysis process SA3 was completed. However, in this embodiment, the first production process SB1 contributes to accelerating the completion of the marine structure 1 by, for example, starting the production of components that are deemed to be finalizable in the above-mentioned structural analysis process SA3 in advance. In this embodiment, the first manufacturing process SB1 may, for example, manufacture a part of the members constituting the marine structure 1. An example of the part manufactured in the first manufacturing process SB1 will be described later. Alternatively, the first manufacturing process SB1 may manufacture all of the members constituting the marine structure 1.

[0035] In this embodiment, the first manufacturing process SB1 has a front first manufacturing process SB1a, a middle first manufacturing process SB1b, and a rear first manufacturing process SB1c. In this embodiment, the first manufacturing process SB1 may have only one or two of these processes. In this embodiment, performing the first manufacturing process SB1 means performing at least one of these processes.

[0036] The pre-first manufacturing process SB1a is a process that is started before or after the preliminary investigation process SA1 during the first manufacturing process SB1. The pre-first manufacturing process SB1a is a process for securing in advance as inventory materials that are highly versatile among those that constitute the monopile body 10 and the transition pieces 20. In the pre-first manufacturing process SB1a, for example, an order is placed for multiple types of steel pipes with different diameters, plate thicknesses, and materials as materials that constitute the monopile body 10 and the transition pieces 20. In this case, the diameters and wall thicknesses of the multiple types of steel pipes may be changed in increments of a predetermined value. The predetermined value may be, for example, any value that is appropriately determined. The predetermined value may be, for example, a discrete value.

[0037] The first intermediate manufacturing process SB1b is a process in the first manufacturing process SB1 that is started before the start of the structural analysis process SA3. In this embodiment, the first intermediate manufacturing process SB1b is started after the shape of the marine structure 1 is considered in the shape consideration process SA2. In the first intermediate manufacturing process SB1b, for example, materials that are not procured in the first previous manufacturing process SB1a are procured. Specifically, in the first intermediate manufacturing process SB1b, for example, an order is placed for materials constituting the monopile body 10 or the transition piece 20, the shapes of which have been finalized in the shape review process SA2.

[0038] As described above, in the shape examination step SA2 and the structural analysis step SA3, the diameters and plate thicknesses of the monopile body 10 and the transition pieces 20 of the marine structure 1 are set in predetermined numerical increments in accordance with the plates and steel pipes procured in the first fabrication step SB1a. This makes it possible to start processing the components using appropriate materials as soon as the diameters and plate thicknesses of the monopile body 10 and the transition pieces 20 are determined as the structural analysis step SA3 progresses.

[0039] Furthermore, by setting the diameters and plate thicknesses of the monopile body 10 and the transition pieces 20 as described above, it is possible to reduce the types of materials that need to be prepared in the first front manufacturing process SB1a and the first intermediate manufacturing process SB1b. This makes it easier to prevent excess inventory. In addition, among the materials having a plurality of diameters and plate thicknesses procured as described above, it is preferable that those not used for the monopile body 10 or the transition piece 20 are diverted to other members, structures, etc. This also makes it possible to more reliably prevent excess inventory from occurring. In addition, in the first intermediate fabrication process SB1b, materials used for the auxiliary equipment 30 of the marine structure 1 may be procured. However, the materials used for the auxiliary equipment 30 of the marine structure 1 may be procured in the first front fabrication process SB1a or the first rear fabrication process SB1c. The first intermediate manufacturing process SB1b can contribute to hastening the completion of the marine structure 1 by procuring materials in advance as described above.

[0040] The post-first manufacturing process SB1c is a process in the first manufacturing process SB1 that is started after the start of the structural analysis process SA3. In this embodiment, the post-first manufacturing process SB1c, for example, manufactures a component (SA3c: possible component) that is determined to be finalizable among a part of the model of the marine structure 1 in the second confirmation step SA3c of the structural analysis process SA3. As described above, the part of the model of the marine structure 1 in the second confirmation step SA3c refers to either the monopile body 10 or the transition piece 20 of the marine structure 1. In the post-first manufacturing process SB1c, it is preferable to manufacture one of these that is determined to be finalizable and for which manufacturing can be started.

[0041] In the post-first fabrication process SB1c, materials are mainly processed to form various components of the marine structure 1. In this embodiment, the start time of the post-first fabrication process SB1c is preferably set appropriately depending on, for example, the design difficulty of each component, the fabrication process, the offshore construction process, etc. Alternatively, the post-first fabrication process SB1c may be started as soon as the shapes of each component are determined with the progress of the structural analysis process SA3.

[0042] In this embodiment, performing the above-mentioned first manufacturing process SB1 contributes to early completion of the offshore wind turbine WM. Note that it is preferable that the members to be manufactured in the first manufacturing process SB1 are appropriately determined after careful consideration. In this embodiment, the first manufacturing process SB1 manufactures, for example, components that are rate-limiting in the manufacturing process of the marine structure 1. In this embodiment, being rate-limiting means that there is room to shorten the manufacturing process of the marine structure 1, for example, because it takes a long time to procure materials or to process and assemble materials. Below, there will be described several examples of members that are rate-limiting in the process of manufacturing the marine structure 1. In this embodiment, it is preferable to appropriately select any of the members described below and manufacture them in the first manufacturing process SB1.

[0043] In the first manufacturing process SB1, for example, a member with a shear key is manufactured. Since a shear key requires a relatively large amount of welding, it takes a long time to manufacture. For this reason, a member with a shear key may be manufactured in the first manufacturing process SB1.

[0044] In the first manufacturing process SB1, for example, the auxiliary equipment 30 may be manufactured. The auxiliary equipment 30 is at least one of the mooring equipment 31, the ladder 32, the landing 33, the work platform 34, and the passageway 35. These auxiliary equipment 30 require a relatively large amount of welding, and therefore require a long period of time to manufacture. For this reason, these auxiliary equipment 30 may be manufactured in the first manufacturing process SB1.

[0045] In the first manufacturing process SB1, for example, the interface flange IF may be manufactured. The interface flange IF requires a long period of time to manufacture because it requires time-consuming anticorrosive processing. For this reason, the interface flange IF may be manufactured in the first manufacturing process SB1.

[0046] In the first manufacturing process SB1, for example, the monopile body 10 may be manufactured. As described above, the monopile body 10 is formed by connecting a plurality of unit cylindrical bodies 11 in the longitudinal direction, and therefore a relatively large amount of welding is required. Also, in the first manufacturing process SB1, at least one of the inner and outer surfaces of the monopile body 10 may be coated with anti-corrosion coating. For this reason, it takes a long period of time to manufacture the monopile body 10. For this reason, the monopile body 10 may be manufactured in the first manufacturing process SB1.

[0047] Also, in the first manufacturing process SB1, for example, the portion of the monopile body 10 that is to be installed underground may be manufactured. As described above, the portion of the monopile body 10 that is to be installed underground, and particularly the portion close to the surface (seabed surface) of the seabed OF, may be subjected to a relatively large bending moment compared to other portions, and therefore a material with a relatively large plate thickness may be used. Such materials require a large amount of welding compared to materials with normal plate thicknesses, and therefore may require a long period of time for processing. For this reason, in the first manufacturing process SB1, the portion of the monopile body 10 that is to be installed underground may be manufactured. More specifically, for example, the material to be used for the portion of the monopile body 10 that is to be installed underground may be procured in advance. In addition, in the first manufacturing process SB1, a connection portion of the monopile body 10 that is connected to the transition piece 20 in a state where it overlaps with the transition piece 20 when viewed horizontally may be manufactured, and no portion of the monopile body 10 other than the connection portion may be manufactured.

[0048] In this embodiment, in the first manufacturing process SB1, in addition to the rate-limiting components described above, a component whose shape is unlikely to change before and after the structural analysis process SA3 may be manufactured. Specifically, for example, the following is performed. That is, in the first manufacturing process SB1, for example, the transition piece 20 may be manufactured. As described above, the transition piece 20 is arranged so as to overlap the upper part of the monopile body 10. Therefore, the transition piece 20 has a relatively high strength, and is unlikely to change in shape before and after the structural analysis process SA3. Therefore, the transition piece 20 may be manufactured in the first manufacturing process SB1. In addition, in the first manufacturing process SB1, the interface flange IF of the transition piece 20 may not be manufactured, and a portion of the transition piece 20 other than the interface flange IF may be manufactured. The portion of the transition piece 20 other than the interface flange IF may be, for example, a side wall portion of the transition piece 20.

[0049] In this embodiment, in the first manufacturing process SB1, at least one of the above-mentioned members is manufactured. Also, in the first manufacturing process SB1, a plurality of the above-mentioned members may be manufactured. Specifically, for example, in the latter first manufacturing process SB1c, at least one of the monopile body 10, the transition piece 20, and the auxiliary equipment 30 may be manufactured. Alternatively, in the first manufacturing process SB1, all of the above-mentioned various members may be manufactured.

[0050] Here, the multiple marine structures 1 present at the same installation site A may be installed one by one in order. Therefore, in this embodiment, it is preferable that the first fabrication process SB1 is performed for at least one of the multiple marine structures 1 present at the same installation site A. In other words, it is preferable that the first fabrication process SB1 is performed only for the first one of the multiple marine structures 1 to be installed or for some of the marine structures to be installed in the early stages. For the marine structures 1 whose turn comes to be fabricated after the structural analysis process SA3 is completed, it is preferable to start fabrication after the structural analysis process SA3 is completed without performing the first fabrication process SB1. This can prevent the need to redo the fabrication of the marine structure 1, for example, when it becomes necessary to change the shape of the marine structure 1 due to the results of the structural analysis process SA3.

[0051] The second manufacturing process SB2 is a process for manufacturing the components constituting the marine structure 1 that are not manufactured in the first manufacturing process SB1 after the structural analysis process SA3 is completed. In the second manufacturing process SB2, for example, it is preferable to manufacture components that do not require a long time for material procurement and manufacturing. In addition, in the second manufacturing process SB2, for example, it is possible to manufacture components whose shapes are determined relatively late in the structural analysis process SA3. This is preferable to prevent the need to redo the manufacturing of components due to changes in shape, and to reduce costs.

[0052] The assembly process SB3 is a process for assembling the various members produced in the first production process SB1 and the second production process SB2 described above. The assembly process SB3 may be performed, for example, at a location such as a factory where the first fabrication process SB1 and the second fabrication process SB2 are performed. In this case, the marine structure 1 may be transported to the installation site A and installed there after the assembly process SB3 is completed. Alternatively, the assembly process SB3 may be performed at the installation site of the marine structure 1. In this case, the marine structure 1 may be installed at the installation site A at the same time as it is assembled in the assembly process SB3. The process planning method according to this embodiment is carried out through the above-mentioned steps.

[0053] The process planning method according to the present embodiment may be implemented, for example, by a computer executing a program. In this case, all or part of the functions of the computer may be realized using hardware such as an ASIC (Application Specific Integrated Circuit), a PLD (Programmable Logic Device), or an FPGA (Field Programmable Gate Array). The program may be recorded on a computer-readable recording medium. Examples of the computer-readable recording medium include portable media such as a flexible disk, a magneto-optical disk, a ROM, and a CD-ROM, and storage devices such as a hard disk built into a computer system. The program may be transmitted via an electric communication line.

[0054] As described above, the process planning method according to this embodiment includes a first fabrication process SB1 that is started after completion of the earthquake response analysis included in the first structural analysis process SA3 and before completion of the earthquake response analysis included in the second structural analysis process SA3, and that fabricates at least some of the members that constitute the marine structure 1 (monopile foundation). This allows the fabrication of the members to be started in advance in the first fabrication process SB1. Therefore, for example, the process of the construction project for the marine structure 1 can be shortened compared to a case in which fabrication of the marine structure 1 is started after completion of the structural analysis process SA3. Therefore, the operation of the offshore wind turbine WM can be started earlier. Moreover, the first manufacturing process SB1 manufactures the transition piece 20. The first manufacturing process SB1 does not manufacture the interface flange IF of the transition piece 20, but manufactures the portion of the transition piece 20 other than the interface flange IF. This shortens the waiting period for completion of the portion of the transition piece 20 other than the interface flange IF, and shortens the process of the construction project for the offshore structure 1. Furthermore, the interface flange IF of the transition piece 20 can easily and flexibly respond to changes in shape that occur in the structural analysis process SA3. In addition, the first manufacturing process SB1 manufactures the monopile body 10. In the first manufacturing process SB1, the connection portion of the monopile body 10 that is connected to the transition piece 20 in a state where it overlaps with the transition piece 20 in a horizontal view is manufactured, and the portion of the monopile body 10 other than the connection portion is not manufactured. This shortens the waiting period for the completion of the connection portion of the monopile body 10, and shortens the process of the construction project for the marine structure 1. In addition, the portion of the monopile body 10 other than the connection portion can be easily and flexibly adapted to changes in shape that occur in the structural analysis process SA3.

[0055] Furthermore, in a structural analysis process SA3, a structural analysis is performed using a model of the marine structure 1. Then, in a first manufacturing process SB1, at least some of the members constituting the marine structure 1 are manufactured before the completion of the structural analysis process SA3. This makes it possible to shorten the process of the construction project for the marine structure 1, for example, compared to a case in which manufacturing of the marine structure 1 is started after the completion of the structural analysis process SA3. Therefore, it is possible to hasten the start of operation of the offshore wind turbine WM.

[0056] Furthermore, the first manufacturing process SB1 manufactures some of the components that make up the marine structure 1. In this way, by manufacturing some of the components that make up the marine structure 1 in the first manufacturing process SB1 before the structural analysis process SA3 is performed, the process of the construction project for the marine structure 1 can be shortened.

[0057] Moreover, the structural analysis step SA3 performs structural analysis of the model of the marine structure 1 only at a predetermined diameter increment. In this way, by managing the diameter of the pipes used in the production of the marine structure 1 at a predetermined diameter increment in accordance with the diameter for which the structural analysis is performed, it is possible to easily manage the inventory of pipes. Specifically, for example, it is possible to prevent the occurrence of pipes of a diameter that are procured in advance and then not used in the production of the marine structure 1 due to the results of the structural analysis, thereby preventing the occurrence of surplus inventory. Furthermore, for example, the number of times the structural analysis is performed can be reduced compared to when the structural analysis of the model of the marine structure 1 is performed for all possible diameters, and therefore the structural analysis step SA3 can be shortened.

[0058] Moreover, the structural analysis step SA3 performs structural analysis of the model of the marine structure 1 only in predetermined plate thickness increments. In this way, by managing the thickness of the plates used in the production of the marine structure 1 in predetermined plate thickness increments in accordance with the plate thickness for which the structural analysis is performed, it is possible to easily manage the inventory of plates. Specifically, for example, it is possible to prevent the occurrence of plates of a plate thickness that have been procured in advance and are not used in the production of the marine structure 1 due to the results of the structural analysis, and thus to prevent the occurrence of excess inventory. Furthermore, for example, the number of times the structural analysis is performed can be reduced compared to when the structural analysis of the model of the marine structure 1 is performed using all possible plate thicknesses, and therefore the structural analysis step SA3 can be shortened.

[0059] Moreover, the first manufacturing process SB1 manufactures rate-limiting members in the manufacturing process of the marine structure 1. In this way, by manufacturing the rate-limiting members in advance in the first manufacturing process SB1, the process of the construction project for the marine structure 1 can be shortened.

[0060] Here, the shear key requires a relatively large amount of welding and can be a rate-limiting factor in the production of the marine structure 1. Therefore, in the first production process SB1, a member with a shear key is produced. In this way, by producing a member with a shear key in the first production process SB1, which is carried out before the structural analysis process SA3, the waiting period for the completion of the member with the shear key can be shortened (or eliminated), and the process of the construction project for the marine structure 1 can be shortened.

[0061] The marine structure 1 also has auxiliary equipment 30. If the auxiliary equipment 30 requires a large amount of welding, this may become a rate-limiting factor in the manufacture of the marine structure 1. Therefore, the first manufacture process SB1 manufactures the auxiliary equipment 30. This shortens (or eliminates) the waiting period for the completion of the auxiliary equipment 30, and shortens the process of the construction project for the marine structure 1.

[0062] The auxiliary facilities 30 are at least any one of the mooring facilities 31, ladders 32, landings 33, work platforms 34, and passageways 35. This makes it possible to shorten (or eliminate) the waiting period for the completion of any one of the mooring facilities 31, ladders 32, landings 33, work platforms 34, and passageways 35, and shorten the process of the construction project for the marine structure 1.

[0063] The marine structure 1 also has a transition piece 20. The transition piece 20 is arranged so as to overlap the upper part of the marine structure 1, which makes it relatively strong. For this reason, the transition piece 20 is relatively unlikely to have its shape changed due to the analysis results of the marine structure 1. Therefore, the first manufacturing process SB1 manufactures the transition piece 20. This makes it easier to shorten the manufacturing period of the marine structure 1. Alternatively, the waiting period for the completion of the transition piece 20 can be shortened (or eliminated), thereby shortening the process of the construction project for the marine structure 1.

[0064] The transition piece 20 also has an interface flange IF. The interface flange IF requires anti-corrosion processing, and therefore may be a rate-limiting step in the production of the marine structure 1. Therefore, the first production process SB1 produces the interface flange IF. This shortens (or eliminates) the waiting period for the completion of the interface flange IF, and shortens the process of the construction project for the marine structure 1.

[0065] Moreover, the marine structure 1 is a monopile foundation. The monopile foundation has a monopile body 10, and the first manufacturing process SB1 manufactures the monopile body 10. This shortens (or eliminates) the waiting period for the completion of the monopile body 10, and shortens the process of the construction project of the marine structure 1.

[0066] Here, a relatively large bending moment may act on the portion of the monopile body 10 that is installed underground, and on the portion of that portion that is particularly close to the surface (seabed surface) of the seabed OF. For this reason, the portion of the monopile body 10 that is installed underground may need to have a large plate thickness. This may lengthen the time required for welding the materials used in that portion, which may become a rate-limiting step in the manufacture of the marine structure 1. Therefore, the first manufacturing process SB1 manufactures the portion of the monopile body 10 that is installed underground. This shortens (or eliminates) the waiting period for the completion of the portion of the monopile body 10 that is installed underground, and shortens the process of the construction project for the marine structure 1.

[0067] Furthermore, among the members constituting the marine structure 1, those not produced in the first production process SB1 are produced in the second production process SB2 after the completion of the structural analysis process SA3. This makes it easier to prevent, for example, changes in shape occurring during the production of the members, which results in the need to redo the production. Also, for example, it makes it easier to prevent excess inventory, which occurs when materials procured in advance before the structural analysis process SA3 are not used in the production of the marine structure 1. This therefore makes it possible to reduce the amount of material used and the production costs of the marine structure 1.

[0068] Moreover, the first manufacturing process SB1 manufactures all of the components that make up the marine structure 1. This makes it possible to more reliably shorten the process of the construction project for the marine structure 1. Also, for example, compared to a case in which only some of the components that make up the marine structure 1 are manufactured in the first manufacturing process SB1, it is easier to adjust the order in which each component is manufactured. This makes it easier to carry out the first manufacturing process SB1 efficiently.

[0069] Here, multiple marine structures 1 at the same installation location A may be installed one by one in sequence. Thus, the first fabrication process SB1 is performed for at least one of the multiple marine structures 1 at the same installation location A. This allows, for example, early fabrication of the marine structure 1 that is to be installed first among the multiple marine structures 1 to be started by the first fabrication process SB1. This makes it easier to shorten the period from the start of a construction project for the marine structure 1 to the start of installation of the marine structure 1.

[0070] In addition, the first manufacturing process SB1 has a first pre-manufacturing process SB1a and a first intermediate manufacturing process SB1b that are started before the start of the structural analysis process SA3, and a first post-manufacturing process SB1c that is started after the start of the structural analysis process SA3. As a result, for example, in the marine structure 1, for members whose shapes have been determined before the start of the structural analysis process SA3, manufacturing can be started by the first pre-manufacturing process SB1a and the first intermediate manufacturing process SB1b, and manufacturing can be started for other members in the first post-manufacturing process SB1c. Therefore, it is possible to prevent the start of manufacturing of members including uncertain elements before the structural analysis process SA3. Therefore, it is possible to easily prevent the occurrence of redoing the manufacturing of members due to a change in the shape of the marine structure 1. Therefore, it is possible to optimize the process plan. Also, it is possible to easily prevent an increase in costs.

[0071] The marine structure 1 is a monopile foundation. The monopile foundation has a transition piece 20 and an auxiliary facility 30, and the first subsequent manufacturing process SB1c manufactures at least one of the transition piece 20 and the auxiliary facility 30. In this manner, by manufacturing at least one of the transition piece 20 and the auxiliary facility 30 in the first subsequent manufacturing process SB1c that is started after the start of the structural analysis process SA3, it is possible to easily prevent the need to redo the manufacturing of either the transition piece 20 or the auxiliary facility 30.

[0072] The marine structure 1 is a monopile foundation. The monopile foundation has a monopile body 10, and in a first manufacturing process SB1, at least one of the inner and outer surfaces of the monopile body 10 is coated and protected from corrosion. This shortens the waiting period for the completion of the work of coating and protecting the monopile body 10 from corrosion, and shortens the process of the construction project for the marine structure 1.

[0073] In addition, a construction planning method according to the present disclosure is applied to the marine structure 1. This makes it possible to shorten the construction project schedule for the marine structure 1. As a result, it is possible to accelerate the start of operation of the offshore wind turbine WM.

[0074] Second embodiment Next, a process planning method according to a second embodiment of the present disclosure will be described. In the second embodiment, the same components as those in the first embodiment are denoted by the same reference numerals, and their description will be omitted, with only the differences being described.

[0075] In the second embodiment, in the first fabrication process SB1, for example, no components are fabricated that are not rate-limiting in the process of fabricating the marine structure 1. In this embodiment, not being rate-limiting means, for example, that there is little room to shorten the fabrication process of the marine structure 1 because procuring materials and processing and assembling the materials do not require a long period of time, and there is a relatively high possibility that changes to the shape will occur in the structural analysis process SA3, so it is more preferable to start fabrication after the shape is determined. In this way, for non-rate-limiting members, by not manufacturing them in the first manufacturing process SB1, which is performed before the completion of the structural analysis process SA3, manufacturing can be started after the shape is determined. This helps prevent changes to the shape during manufacturing, thereby reducing the need to redo manufacturing. Below, we will explain several examples of members that are not rate-limiting in the process of manufacturing the marine structure 1. In this embodiment, it is preferable to appropriately select any of the members described below and not manufacture them in the first manufacturing process SB1.

[0076] In the second embodiment, for example, the transition piece 20 is not manufactured in the first manufacturing process SB1. The transition piece 20 is a component that accounts for a large proportion of the processing cost and the weight of the materials (e.g., steel) used in the marine structure 1. For this reason, the transition piece 20 may not be manufactured in the first manufacturing process SB1, but rather manufactured after the shape has been determined, thereby further reducing costs incurred by reworking the manufacturing process.

[0077] In the second embodiment, for example, the monopile body 10 may not be manufactured in the first manufacturing process SB1. The monopile body 10 is a component that accounts for a large proportion of the weight of the material (e.g., steel) used in the marine structure 1. For this reason, the monopile body 10 may not be manufactured in the first manufacturing process SB1, but may be manufactured after the shape is determined, thereby further reducing costs incurred by redoing the manufacturing process.

[0078] In the second embodiment, for example, at least one of both ends of the monopile body 10 may not be manufactured in the first manufacturing process SB1. As described above, the monopile body 10 is formed by connecting a plurality of unit tubular bodies 11 in the longitudinal direction. At this time, the unit tubular bodies 11 located at other than both ends of the monopile body 10 are welded at both ends, whereas the unit tubular bodies 11 located at both ends of the monopile body 10 are welded only at one end. Therefore, the amount of welding at both ends of the monopile body 10 is small, and it is unlikely to be a rate-limiting factor in the manufacturing process. For this reason, by not manufacturing at least one of both ends of the monopile body 10 in the first manufacturing process SB1, it may be possible to easily and flexibly respond to changes in shape in the structural analysis process SA3.

[0079] In the second embodiment, for example, the auxiliary facilities 30 may not be fabricated in the first fabrication process SB1. The auxiliary facilities 30 are at least any of the mooring facilities 31, ladders 32, landings 33, working platforms 34, and passageways 35. These auxiliary facilities 30 are easily affected by the design results of the main components (e.g., the transition piece 20) in the marine structure 1, and therefore their shapes are likely to change in the structural analysis process SA3. For this reason, the auxiliary facilities 30 may not be fabricated in the first fabrication process SB1, but may be fabricated after the shape has been determined, thereby further reducing costs incurred by re-fabrication.

[0080] In the second embodiment, at least one of the above-mentioned members is not manufactured in the first manufacturing process SB1. Also, a plurality of the above-mentioned members may not be manufactured in the first manufacturing process SB1. Alternatively, all of the above-mentioned various members may not be manufactured in the first manufacturing process SB1.

[0081] As described above, according to the process planning method of the second embodiment, the first manufacturing process SB1 does not manufacture members that are not rate-limiting in the manufacturing process of the marine structure 1. This makes it easier to flexibly respond to changes in shape for members that are not manufactured.

[0082] The marine structure 1 also has a transition piece 20. The transition piece 20 requires a relatively large amount of material and processing effort. Therefore, the first manufacturing process SB1 does not manufacture the transition piece 20. This allows the manufacturing of the transition piece 20 to start after the shape of the transition piece 20 has been optimized. Therefore, it is possible to prevent changes to the shape of the transition piece 20 during manufacturing, and to easily reduce the manufacturing cost of the marine structure 1.

[0083] Furthermore, the marine structure 1 is a monopile foundation, and the monopile foundation has a monopile body 10. The monopile body 10 uses a relatively large amount of material. Therefore, the first manufacturing process SB1 does not manufacture the monopile body 10. This allows the manufacturing of the monopile body 10 to start after the shape of the monopile body 10 has been optimized. This prevents the shape of the monopile body 10 from being changed during manufacturing, and makes it easier to reduce the manufacturing costs of the marine structure 1.

[0084] Here, the monopile body 10 is constructed by welding a plurality of unit tubular bodies 11 in the longitudinal direction. At this time, the unit tubular bodies 11 located at positions other than both ends of the monopile body 10 are welded at both ends, whereas the unit tubular bodies 11 located at both ends of the monopile body 10 are welded at only one end. Therefore, the amount of welding at both ends of the monopile body 10 is small, and it is relatively unlikely to be a rate-limiting step in the manufacture of the marine structure 1. Therefore, in the first manufacturing process SB1, at least one of the both ends of the monopile body 10 is not manufactured. This makes it easier to flexibly respond to shape changes that occur in the member.

[0085] The marine structure 1 also has auxiliary equipment 30. The auxiliary equipment 30 is easily affected by the design results of major components in the marine structure 1 (e.g., the transition piece 20), and so changes in shape are likely to occur. Therefore, the first manufacturing process SB1 does not manufacture the auxiliary equipment 30. This allows the manufacturing of the auxiliary equipment 30 to begin after the shape of the auxiliary equipment 30 has been optimized. This prevents the auxiliary equipment 30 from being subject to shape changes during manufacturing, making it easier to reduce the manufacturing costs of the marine structure 1.

[0086] The auxiliary equipment 30 is at least any one of the mooring equipment 31, the ladder 32, the landing 33, the work floor 34, and the passageway 35. This makes it possible to suppress changes in shape of any one of the mooring equipment 31, the ladder 32, the landing 33, the work floor 34, and the passageway 35 during fabrication, and makes it easier to suppress the fabrication costs of the marine structure 1.

[0087] The technical scope of the present disclosure is not limited to the above-described embodiments, and various modifications can be made without departing from the spirit of the present disclosure. For example, the process planning method according to this embodiment may be applied to structures other than the marine structure 1. Furthermore, in the structural analysis step SA3, the structural analysis of the model of the marine structure 1 may be performed not in predetermined diameter increments or predetermined plate thickness increments, but in any diameter or plate thickness. Also, the first manufacturing process SB1 may be configured not to manufacture a member having a shear key. Furthermore, the marine structure 1 does not necessarily need to be equipped with a transition piece 20. Furthermore, the marine structure 1 does not have to have a monopile foundation. In addition, in the first manufacturing process SB1, the portion of the monopile body 10 that is to be placed underground may not be manufactured. In addition, in the first manufacturing process SB1, one or both of the two end portions of the monopile body 10 may be manufactured. Furthermore, in the first manufacturing process SB1, not all of the members constituting the marine structure 1 may be manufactured. Moreover, the first fabrication process SB1 may be performed for two or more of the multiple marine structures 1 present at the same installation site A, or may be performed for all of them. Moreover, the first manufacturing process SB1 does not necessarily have to include the intermediate first manufacturing process SB1b and the subsequent first manufacturing process SB1c. Furthermore, in the first manufacturing process SB1, at least one of the inner and outer surfaces of the monopile body 10 does not need to be coated with corrosion protection.

[0088] In addition, within the scope of the present disclosure, the components in the above-described embodiments may be replaced with well-known components as appropriate, and the above-described modified examples may be combined as appropriate.

[0089] (Additional Note) The process planning method and the marine structure according to the embodiment can be understood, for example, as follows.

[0090] <1> A process planning method according to one embodiment of the present disclosure is a process planning method for planning the process of a construction project of a monopile foundation having a monopile body and a transition piece and supporting the tower of an offshore wind turbine, the process comprising: a structural analysis process in which a computer performs a structural analysis of a model of the monopile foundation multiple times; and a first fabrication process that is started after completion of an earthquake response analysis included in a first structural analysis process and before completion of an earthquake response analysis included in a second structural analysis process, the first fabrication process fabricating at least a part of the components that constitute the monopile foundation, wherein the first fabrication process fabricates the transition piece, the first fabrication process does not fabricate an interface flange of the transition piece, and fabricates a portion of the transition piece other than the interface flange, the first fabrication process fabricates the monopile body, the first fabrication process fabricates a connection portion of the monopile body that is connected in a state that overlaps with the transition piece in a horizontal view, and does not fabricate a portion of the monopile body other than the connection portion.

[0091] According to the above process planning method, a first fabrication process is started after completion of an earthquake response analysis included in a first structural analysis process and before completion of an earthquake response analysis included in a second structural analysis process, and includes a first fabrication process for fabricating at least some of the components that constitute the monopile foundation. This allows fabrication of the components to be started in advance in the first fabrication process. Therefore, for example, the process of a construction project for an offshore structure can be shortened compared to a case in which fabrication of the offshore structure is started after completion of the structural analysis process. Therefore, the operation of the offshore wind turbine can be started earlier. In addition, the first manufacturing process manufactures the transition piece. In the first manufacturing process, the interface flange of the transition piece is not manufactured, but the portion of the transition piece other than the interface flange is manufactured. This shortens the waiting period for the completion of the portion of the transition piece other than the interface flange, and shortens the process of the offshore structure construction project. In addition, the interface flange of the transition piece can easily and flexibly respond to changes in shape that occur in the structural analysis process. In addition, the first manufacturing process manufactures the monopile body. In the first manufacturing process, the connection part of the monopile body that is connected to the transition piece in a state where it overlaps with the transition piece in a horizontal view is manufactured, and the part of the monopile body other than the connection part is not manufactured. This shortens the waiting period for the completion of the connection part of the monopile body, and shortens the process of the marine structure construction project. In addition, the part of the monopile body other than the connection part can be easily and flexibly adapted to changes in shape that occur in the structural analysis process.

[0092] <2> A process planning method according to one embodiment of the present disclosure is a process planning method for planning the process of a construction project of an marine structure that supports the tower of an offshore wind turbine, and is characterized by comprising a structural analysis process for performing a structural analysis of a model of the marine structure, and a first manufacturing process for manufacturing at least some of the components that constitute the marine structure before completion of the structural analysis process.

[0093] According to the above process planning method, in the structural analysis step, a structural analysis is performed using a model of the offshore structure. Then, in the first manufacturing step, at least some of the members constituting the offshore structure are manufactured before the structural analysis step is completed. This makes it possible to shorten the process of a construction project for the offshore structure, for example, compared to a case in which the manufacturing of the offshore structure is started after the structural analysis step is completed. Therefore, it is possible to start operation of the offshore wind turbine earlier.

[0094] <3> the above <2> In the process planning method according to the above, the first manufacturing process may be configured to manufacture a part of a member that constitutes the marine structure.

[0095] In addition, the first manufacturing process manufactures some of the components that make up the marine structure. In this way, by manufacturing some of the components that make up the marine structure in the first manufacturing process before the structural analysis process is performed, the process of the marine structure construction project can be shortened.

[0096] <4> the above <2> or <3> In the process planning method according to the above, the structural analysis step may be configured to perform structural analysis of the model of the marine structure only at predetermined diameter intervals.

[0097] In addition, the structural analysis step performs structural analysis of the marine structure model only at a predetermined diameter interval. In this way, by managing the diameter of the pipes used in the manufacture of the marine structure at a predetermined diameter interval in accordance with the diameter for which the structural analysis is performed, it is possible to easily manage the inventory of pipes. Specifically, for example, it is possible to prevent the occurrence of pipes of a diameter that are procured in advance and then not used in the manufacture of the marine structure due to the results of the structural analysis, and thus prevent the occurrence of surplus inventory. In addition, for example, the number of times the structural analysis is performed can be reduced compared to when the structural analysis of the marine structure model is performed for all possible diameters, thereby shortening the structural analysis process.

[0098] <5> the above <2> from <4> In the process planning method according to any one of the above aspects, the structural analysis step may adopt a configuration characterized in that structural analysis of the model of the marine structure is performed only at predetermined plate thickness increments.

[0099] In addition, the structural analysis step performs structural analysis of the marine structure model only in predetermined plate thickness increments. In this way, by managing the plate thickness of the plate used in the production of the marine structure in predetermined plate thickness increments according to the plate thickness for which the structural analysis is performed, it is possible to easily manage the plate inventory. Specifically, for example, it is possible to prevent the occurrence of plates of a plate thickness that are procured in advance and then not used in the production of the marine structure due to the results of the structural analysis, and thus prevent the occurrence of excess inventory. In addition, for example, the number of times the structural analysis is performed can be reduced compared to when the structural analysis of the marine structure model is performed using all possible plate thicknesses, thereby shortening the structural analysis process.

[0100] <6> the above <2> from <5> In the process planning method according to any one of the above aspects, the first manufacturing process may be configured to manufacture a component that is rate-limiting in the process of manufacturing the marine structure.

[0101] In addition, the first manufacturing process is for manufacturing the rate-limiting components in the manufacturing process of the marine structure. By manufacturing the rate-limiting components in advance in the first manufacturing process, the process of the marine structure construction project can be shortened.

[0102] <7> the above <2> from <6> In the process planning method according to any one of the above aspects, the first manufacturing process may be configured to manufacture a member having a shear key.

[0103] Here, the shear key requires a relatively large amount of welding, which can be a rate-limiting factor in the production of marine structures. Therefore, in the first production process, the components with the shear key are produced. In this way, by producing the components with the shear key in the first production process, which is carried out before the structural analysis process, the waiting period for the completion of the components with the shear key can be shortened, and the process of the marine structure construction project can be shortened.

[0104] <8> the above <2> from <7> In the process planning method according to any one of the above aspects, the marine structure may have auxiliary equipment, and the first manufacturing process may be configured to manufacture the auxiliary equipment.

[0105] In addition, the marine structure has auxiliary equipment. If the auxiliary equipment requires a large amount of welding, this can become a rate-limiting step in the manufacture of the marine structure. Therefore, the first manufacturing process is to manufacture the auxiliary equipment. This shortens the waiting period for the completion of the auxiliary equipment, and shortens the process of the marine structure construction project.

[0106] <9> the above <8> In the process planning method according to the above, the auxiliary equipment may be at least one of a mooring facility, a ladder, a landing, a work platform, and a passageway.

[0107] The auxiliary facilities are at least any one of a mooring facility, a ladder, a landing and a work platform, and a gangway. This shortens the waiting period for the completion of any one of the mooring facility, the ladder, the landing and a work platform, and the gangway, and shortens the process of the marine structure construction project.

[0108] <10> the above <2> from <9> In the process planning method according to any one of the above aspects, the marine structure may have a transition piece, and the first manufacturing process may be configured to manufacture the transition piece.

[0109] The marine structure also has a transition piece. The transition piece is arranged so as to overlap the upper part of the marine structure, which makes it relatively strong. For this reason, the transition piece is relatively unlikely to undergo changes in shape due to the analysis results of the marine structure. Therefore, the first manufacturing process manufactures the transition piece. This makes it easier to shorten the manufacturing period of the marine structure. Alternatively, it is possible to shorten the period of waiting for the completion of the transition piece and shorten the process of the construction project of the marine structure.

[0110] <11> the above <10> In the process planning method according to the above, the transition piece may have an interface flange, and the first manufacturing process may be configured to manufacture the interface flange.

[0111] The transition piece also has an interface flange. The interface flange requires corrosion protection, which can be a time-limiting step in the manufacture of offshore structures. Therefore, the first manufacturing process is to manufacture the interface flange. This shortens the waiting period for the completion of the interface flange, and shortens the process of the offshore structure construction project.

[0112] <12> the above <2> from <11> In the process planning method according to any one of the above aspects, the marine structure may be a monopile foundation, the monopile foundation having a monopile body, and the first manufacturing process may be characterized by manufacturing the monopile body.

[0113] In addition, the marine structure is a monopile foundation. The monopile foundation has a monopile body, and the first manufacturing process is to manufacture the monopile body. This shortens the waiting period for the completion of the monopile body, and shortens the process of the marine structure construction project.

[0114] <13> the above <12> In the process planning method according to the above, the first manufacturing process may be configured to manufacture a portion of the monopile body that is to be installed underground.

[0115] Here, a relatively large bending moment may act on the portion of the monopile body that is installed underground, and particularly on the portion of that portion that is close to the seabed. For this reason, the portion of the monopile body that is installed underground may need to have a larger plate thickness. This may lengthen the time required for welding the material used in that portion, which may become a rate-limiting factor in the manufacture of the marine structure. Therefore, the first manufacturing process manufactures the portion of the monopile body that is installed underground. This shortens the waiting period for the completion of the portion of the monopile body that is installed underground, and shortens the process of the marine structure construction project.

[0116] <14> the above <2> from <13> In the process planning method according to any one of the above embodiments, a configuration may be adopted which is characterized by including a second manufacturing process in which components constituting the marine structure that are not manufactured by the first manufacturing process are manufactured after completion of the structural analysis process.

[0117] In addition, among the components constituting the marine structure, those that are not produced in the first production process are produced in the second production process after the structural analysis process is completed. This makes it easier to prevent, for example, changes in the shape of the components occurring during production, which may result in redoing the production. In addition, for example, it makes it easier to prevent excess inventory from occurring, which may occur when materials procured in advance before the structural analysis process are not used in the production of the marine structure. This therefore makes it possible to reduce the amount of material used and the production costs of the marine structure.

[0118] <15> the above <2> from <14> In the process planning method according to any one of the above aspects, the first manufacturing process may be configured not to manufacture any components that are not rate-limiting in the manufacturing process of the marine structure.

[0119] In addition, the first manufacturing process does not manufacture any members that are not rate-limiting in the manufacturing process of the marine structure. This makes it easier to flexibly respond to changes in the shape of the members that are not manufactured.

[0120] <16> the above <2> from <15> In the process planning method according to any one of the above aspects, the marine structure may have a transition piece, and the first manufacturing process may be configured not to manufacture the transition piece.

[0121] The marine structure also has a transition piece. The transition piece requires a relatively large amount of material and a relatively large amount of processing effort. Therefore, the first manufacturing process does not manufacture the transition piece. This allows the manufacturing of the transition piece to begin after the shape of the transition piece has been optimized. This prevents the transition piece from being subjected to shape changes during manufacturing, making it easier to reduce the manufacturing costs of the marine structure.

[0122] <17> the above <2> from <16> In the process planning method according to any one of the above aspects, the marine structure may be a monopile foundation, the monopile foundation having a monopile body, and the first manufacturing process may be configured to not manufacture the monopile body.

[0123] Furthermore, the marine structure is a monopile foundation, and the monopile foundation has a monopile body. The monopile body uses a relatively large amount of material. Therefore, the first manufacturing process does not manufacture the monopile body. This allows the manufacturing of the monopile body to start after the shape of the monopile body has been optimized. This prevents the shape of the monopile body from being changed during manufacturing, and makes it easier to reduce the manufacturing costs of the marine structure.

[0124] <18> the above <17> In the process planning method according to the above, the first manufacturing process may adopt a configuration characterized in that at least one of both end portions of the monopile body is not manufactured.

[0125] Here, the monopile body is constructed by welding multiple raw pipes (blank pipes) in the longitudinal direction. In this case, the blank pipes located at the ends other than those of the monopile body are welded at both ends, whereas the blank pipes located at both ends of the monopile body are welded at only one end. Therefore, the amount of welding at both ends of the monopile body is small, and it is relatively unlikely to be a rate-limiting step in the manufacture of marine structures. Therefore, in the first manufacturing process, at least one of the ends of the monopile body is not manufactured. This makes it easier to flexibly respond to shape changes that occur in the member.

[0126] <19> the above <2> from <18> In the process planning method according to any one of the above aspects, the marine structure may have auxiliary equipment, and the first manufacturing process may be configured to not manufacture the auxiliary equipment.

[0127] Furthermore, the marine structure has auxiliary equipment. The auxiliary equipment is easily affected by the design results of major components of the marine structure (e.g., transition pieces), and so changes in shape are likely to occur. Therefore, the first manufacturing process does not manufacture the auxiliary equipment. This allows the manufacturing of the auxiliary equipment to begin after the shape of the auxiliary equipment has been optimized. This prevents the auxiliary equipment from changing in shape during manufacturing, making it easier to reduce the manufacturing costs of the marine structure.

[0128] <20> the above <19> In the process planning method according to the above, the auxiliary equipment may be at least one of a mooring facility, a ladder, a landing, a work platform, and a passageway.

[0129] The auxiliary equipment is at least one of the mooring equipment, ladders, landings and work platforms, and passageways. This makes it possible to suppress changes in shape of the mooring equipment, ladders, landings and work platforms, and passageways during fabrication, and makes it easier to suppress the fabrication costs of the marine structure.

[0130] <21> the above <2> from <20> In the process planning method according to any one of the above aspects, the first manufacturing process may be configured to manufacture all of the members that constitute the marine structure.

[0131] In addition, the first manufacturing process manufactures all of the components that make up the marine structure. This makes it possible to more reliably shorten the process of the marine structure construction project. Also, for example, compared to a case in which only some of the components that make up the marine structure are manufactured in the first manufacturing process, it is easier to adjust the order in which each component is manufactured. This makes it easier to carry out the first manufacturing process efficiently.

[0132] <22> the above <2> from <21> In the process planning method according to any one of the above aspects, a configuration may be adopted in which the first manufacturing process is performed on at least one of a plurality of the marine structures located in the same wind farm or sea area.

[0133] Here, multiple marine structures existing in the same wind farm or sea area may be installed one by one in sequence. Thus, the first fabrication process is performed for at least one of the multiple marine structures existing in the same wind farm or sea area. This allows, for example, early fabrication of an marine structure that is to be installed first among the multiple marine structures to be started by the first fabrication process. This makes it easier to shorten the period from the start of a construction project for the marine structure to the start of installation of the marine structure.

[0134] <23> the above <2> from <22> In the process planning method according to any one of the above aspects, the first production process may be characterized in that it includes a pre-first production process and an intermediate first production process that are started before the structural analysis process begins, and a post-first production process that is started after the structural analysis process begins.

[0135] Moreover, the first manufacturing process includes a first pre-manufacturing process and a first intermediate manufacturing process that are started before the start of the structural analysis process, and a first post-manufacturing process that is started after the start of the structural analysis process. As a result, for example, in an offshore structure, for members whose shapes have been determined before the start of the structural analysis process, manufacturing can be started in the first pre-manufacturing process and the first intermediate manufacturing process, and manufacturing can be started for other members in the first post-manufacturing process. Therefore, it is possible to prevent the manufacturing of members including uncertain elements from being started before the structural analysis process. Therefore, it is possible to easily prevent the need to redo the manufacturing of members due to changes in the shape of the offshore structure. Therefore, it is possible to optimize the process plan. Also, it is possible to easily prevent increases in costs.

[0136] <24> the above <23> In the process planning method according to the above, the marine structure may be a monopile foundation, the monopile foundation having a transition piece and auxiliary equipment, and the first subsequent manufacturing process may be configured to manufacture at least one of the transition piece and the auxiliary equipment.

[0137] Moreover, the marine structure is a monopile foundation. The monopile foundation has a transition piece and an auxiliary equipment, and at least one of the transition piece and the auxiliary equipment is manufactured in the first subsequent manufacturing process. In this manner, by manufacturing at least one of the transition piece and the auxiliary equipment in the first subsequent manufacturing process that is started after the start of the structural analysis process, it is possible to easily prevent the need to redo the manufacturing of either the transition piece or the auxiliary equipment.

[0138] <25> the above <2> from <24> In the process planning method according to any one of the above aspects, the marine structure may be a monopile foundation, the monopile foundation having a monopile body, and in the first production process, at least one of the inner and outer surfaces of the monopile body may be coated and corrosion-protected.

[0139] The marine structure is a monopile foundation. The monopile foundation has a monopile body, and in the first manufacturing process, at least one of the inner and outer surfaces of the monopile body is coated and protected against corrosion. This shortens the waiting period for the completion of the work of coating and protecting the monopile body, and shortens the process of the marine structure construction project.

[0140] <26> The marine structure according to one embodiment of the present disclosure is <1> from <25> The process planning method according to any one of the above aspects is applied.

[0141] In addition, the process planning method according to the present disclosure is applied to the marine structure according to the present disclosure. This makes it possible to shorten the process of the construction project of the marine structure. Therefore, it is possible to start the operation of the offshore wind turbine earlier. [Explanation of symbols]

[0142] 1 Marine structures 10 Monopile body 11 Unit cylinder 11A board 20 Transition Piece 30 Ancillary Equipment 31 Mooring equipment 32 Ladder 33 Landing 34 Working Floor 35 Passage A. Installation location B Bolt C Cable DC Davit Crane G Grout H hole IF Interface Flange OF ocean floor SA design review flow SA1 Preliminary investigation process SA2 Shape review process SA3 Structural analysis process SA3a Analysis Implementation Steps SA3b 1st confirmation step SA3c 2nd verification step SA3d 3rd confirmation step SA3e Review Steps SB production flow SB1 1st production process SB1a first production process SB1b Middle 1st production process SB1c 1st production process SB2 2nd production process SB3 Assembly Process T Tower WM Offshore Wind Turbine

Claims

[Claim 1] A process planning method for planning a process for a construction project of a monopile foundation that supports a tower of an offshore wind turbine, the monopile foundation having a monopile body and a transition piece, comprising: a structural analysis step in which a computer performs a structural analysis of the monopile foundation model multiple times; a first fabrication process that is started after completion of an earthquake response analysis included in a first structural analysis process and before completion of an earthquake response analysis included in a second structural analysis process, the first fabrication process fabricating at least a part of the members that constitute the monopile foundation; Equipped with The first manufacturing step includes manufacturing the transition piece, The first manufacturing step does not manufacture an interface flange of the transition piece, and manufactures a portion of the transition piece other than the interface flange, The first manufacturing step includes manufacturing the monopile body, The first manufacturing process is a process planning method in which a connection portion of the monopile body is manufactured so as to be connected to the transition piece in a state where it overlaps with the transition piece when viewed horizontally, and no portion of the monopile body other than the connection portion is manufactured.

Citation Information

Patent Citations

  • Construction mode of vertical structure using prefabricated unit structure

    JP1987086273A

  • Reinforcement structure of underwater installation cylindrical body, and reinforcement method

    JP2023139586A

  • Offshore foundation

    WO2015071634A1

Cited By

  • Steel pipe manufacturing method, tower, and foundation

    JP2026170638A

  • Product manufacturing method, steel pipe pile foundation, and wall using steel pipe piles

    JP2026173635A

  • A method for designing a tower structure, a method for manufacturing a tower structure, and a tower structure

    JP7878621B1

  • Design method for tower structure, manufacturing method for tower structure, and tower structure

    WO2026168209A1