Critical chain buffer area arrangement method based on production uncertainty
An uncertainty and buffer technology, applied in the critical chain field, to achieve the effect of improving accuracy
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2018-04-20
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the technical field of critical chains, in particular to an improved buffer setting method for critical chains facing production uncertainty. Background technique
[0002] Researching scientific and effective production scheduling control algorithms and developing a practical and stable production scheduling management system have become the urgent needs of manufacturing enterprises. Traditional production scheduling methods have insufficient research on the impact of variability on the production process. Most of the research results focus on scheduling strategies, bottleneck control, equipment load allocation, and task assignment. The production line is used as a whole to evaluate the production cycle and production rate. And the overall performance of the WIP, and then quantify the uncertainties and study their impact on the performance of the manufacturing system.
[0003] Critical chain has been widely used in the field o...
Examples
Embodiment Construction
[0026] In order to make the purpose, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the implementation methods and accompanying drawings.
[0027] The present invention adopts the CARVER matrix and the system evaluation method to design the priority rules, then uses the heuristic algorithm to identify the critical chain based on the designed priority rules, and finally completes the buffer setting through the factory physics variability theory and resource utilization measurement. On the premise of ensuring the accuracy of the buffer setting, the multi-objective critical chain production scheduling is realized. Its specific implementation steps are as follows:
[0028] Step 1. Design priority rules.
[0029] 1.1 Set customer importance:
[0030]For the production scheduling of multiple orders, in the case of the same order, the orders of more important customers should be...