A method for lifting, pushing and erecting a truss-type emergency bridge

By using a general-purpose crane to carry out hoisting and suspension pushing combined erection methods in emergency bridges, the long-span truss structure can be quickly assembled and pushed, which solves the problem of low erection efficiency of long-span bridges in the existing technology and achieves a fast, economical and efficient emergency bridge erection.

CN109098088BActive Publication Date: 2024-10-29赵启林
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN201810849152.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-07-28
Publication Date
2024-10-29
Estimated Expiration
2038-07-28

AI Technical Summary

Technical Problem

The existing cantilever push frame and hoisting frame methods of emergency bridges are difficult to quickly meet the needs of large-span bridges. Especially in mountainous areas where the site is small and the geological conditions are unstable, the emergency rush time is increased, and the existing hoisting equipment is adaptable. insufficient.

Method used

A general-purpose crane is used for hoisting and suspension push combination, and the guide beams and truss bridge sections are quickly assembled to achieve one-time hoisting of the large-span truss structure, and the crane is used to push the bridge sections to complete the erection section by section, reducing ancillary facilities and site requirements.

Benefits of technology

It realizes the rapid erection of large-span emergency bridges under limited conditions, reduces erection time and equipment configuration, improves erection efficiency and span adaptability, and meets the need for rapid rush-through.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0001747208340000011
    Figure HDA0001747208340000011
  • Figure HDA0001747208340000012
    Figure HDA0001747208340000012
  • Figure HDA0001747208340000013
    Figure HDA0001747208340000013
Patent Text Reader

Abstract

The present invention provides a method for lifting and pushing a combined erection of a truss-type emergency bridge, which is erected by a combination of lifting and hanging and pushing, and the steps are as follows: quickly assemble a guide beam of a certain length and an assembled truss bridge section into a truss structure of a certain span; use a crane to lift and erect the assembled truss structure of a certain span to the opposite bank at one time, so that one end of the guide beam is erected on the opposite bank, and the assembled truss bridge section is erected on my bank; level the ground on the opposite bank and set rollers; the assembled bridge section is hoisted by a crane, and the erection personnel on my bank cooperate to assemble the truss bridge section at the rear end of the erected truss structure; the crane arm is extended forward to provide horizontal thrust to push the bridge section to the opposite bank. This method not only reduces the configuration and installation of auxiliary facilities and equipment, reduces site requirements, but also reduces the occurrence of possible difficult-to-control situations; without increasing the number of emergency repair personnel, the erection time is greatly reduced, and the purpose of rapid emergency repair is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of emergency bridge construction and erection, and in particular to a hoisting, pushing and combined erection method for a truss type emergency bridge. Background Art

[0002] In recent years, geological and hydrological disasters have occurred frequently in some parts of my country, causing huge losses to the people. After the disaster, roads and bridges were severely damaged, which not only blocked the escape of the people in the disaster area, but also blocked the entry of disaster relief personnel and materials. Therefore, the rapid opening of roads and bridges is very urgent. However, the existing cantilever push erection method and hoisting erection method of emergency bridges cannot well meet the needs of rapid opening. The cantilever push erection method relies on the guide beam to gradually push the emergency bridge unit to the opposite bank, and has high requirements on the length and flatness of our bank; disasters usually occur in mountainous areas, the rear site is small, and the geological conditions are unstable. It is usually necessary to further clean up and organize the site, which greatly increases the time for emergency opening; most of the existing emergency bridges are made of steel and are heavy. Combined with the existing hoisting equipment, the existing hoisting method can only adapt to the hoisting of emergency bridges with smaller spans, and the adaptability is difficult to meet the requirements. Summary of the invention

[0003] Technical problem: In order to solve the defects of the prior art, the present invention provides a method for quickly erecting a large-span emergency bridge during emergency rescue. By adopting this erection method, a large-span truss emergency bridge can be quickly erected to the opposite bank under limited conditions.

[0004] Technical solution: The present invention provides a method for erecting a truss-type emergency bridge by hoisting and pushing. The method uses a general-purpose crane and adopts a combination of hoisting and hanging and pushing to erect the bridge. The method comprises the following steps:

[0005] (1) The crane is placed near the shore. A certain length of guide beam and assembled truss bridge sections are quickly assembled into a truss structure with a certain span at the side and rear of the crane or along the shore.

[0006] (2) Use a crane to hoist and erect the assembled truss structure of a certain span to the opposite bank at one time, so that one end of the guide beam is erected on the opposite bank and the assembled truss bridge section is erected on our bank;

[0007] (3) The truss bridge erection personnel on our bank carry equipment through the erected truss structure to the other side, level the ground on the other side and set up rollers;

[0008] (4) The crane moves backward to create a certain space between the crane and the erected truss structure. The crane is used to lift the assembled bridge section, and the erection personnel on our shore cooperate to assemble the truss bridge section at the rear end of the erected truss structure.

[0009] (5) The crane lifts the rear end of the assembled bridge section to a certain height, and the crane arm extends forward to provide horizontal thrust to push the bridge section to the other side, completing the erection of the simply supported truss bridge.

[0010] Wherein, in step (1), the guide beam is connected to the assembled truss bridge segment by single or double ears.

[0011] Beneficial effects: The hoisting and pushing combined erection method of the truss type emergency bridge provided by the present invention solves the problem of rapid erection of the emergency bridge in a comprehensive, economical and efficient manner. Compared with the suspended push method, the weighted push method and the traditional hoisting method, this method not only reduces the configuration and installation of auxiliary facilities and equipment, reduces site requirements, but also reduces the occurrence of possible uncontrollable situations; without increasing the number of repair personnel, the erection time is greatly reduced, thereby achieving the purpose of rapid emergency repair.

[0012] The characteristics of this combined lifting and pushing erection method are: some bridge span modules are spliced ​​with lightweight guide beams to form a whole, so as to ensure that a structure that can cross obstacles can be lifted at a time with a lighter weight; and then the bridge span is assembled and pushed section by section, thus avoiding the problems that a single lifting scheme is difficult to lift a longer bridge span, and a single pushing scheme requires a longer site leveling on our bank.

[0013] The erection method relies on a combination of light guide beams and bridge sections. Under the condition of meeting the crane lifting requirements, a large-span bridge structure can be erected at one time. After that, the bridge sections can be further suspended and pushed by relying on the structure and using a crane. The erection efficiency is extremely high and the span adaptability is relatively strong. The crane equipment used is an existing general equipment that is generally equipped by emergency repair forces. That is to say, the lifting, pushing and combined erection method of a truss-type emergency bridge provided by the present invention can be realized by utilizing known equipment in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is the hoisting, pushing and combined erection step 1 of the 54m-long-span lightweight composite material emergency bridge of the present invention;

[0015] Figure 2 This is step 2 of the hoisting, pushing and assembly erection of the 54m-long-span lightweight composite material emergency bridge of the present invention;

[0016] Figure 3 This is step 4 of the hoisting, pushing and assembly erection of the 54m-long-span lightweight composite material emergency bridge of the present invention;

[0017] Figure 4 This is step 5 of the hoisting, pushing and assembly erection of the 54m-long-span lightweight composite material emergency bridge of the present invention;

[0018] Figure 5This is step 5 of the hoisting, pushing and combined erection of the 54m-long-span lightweight composite material emergency bridge of the present invention. DETAILED DESCRIPTION

[0019] The scheme of the present invention is further described below in conjunction with the erection of a 54m-long-span lightweight composite emergency bridge.

[0020] The 54m-long-span lightweight composite emergency bridge is assembled from 9 6m-long modular bridge sections, with a modular bridge section weight of 1.8T; the matching 36m guide beam is also assembled from modular units, with a total weight of 2T. Using the erection method of this invention, the steps are as follows:

[0021] (1) At the rear side of the crane or along the shore, assemble the 36m guide beam and the 18m truss bridge section into a 54m truss structure, as shown in Figure (1);

[0022] (2) The crane is placed near the shore, and a 25-ton crane is used to lift and erect the assembled 54m truss structure to the opposite shore at one time. The crane only needs to operate within 180°, as shown in Figure (2).

[0023] (3) Through the erected 54m truss structure, our shore personnel carried equipment to the other side, leveled the ground on the other side and set up rollers;

[0024] (4) The crane moves backward, providing a certain space between the crane and the erected truss structure, and the crane hoists the bridge section, while manual labor quickly assembles the truss bridge section at the rear end of the erected truss structure, as shown in Figure (3);

[0025] (5) The crane slightly lifts the rear section of the assembled bridge, as shown in Figure (4); the crane arm extends forward to provide horizontal thrust to gradually push the bridge section to the other side, completing the erection of the simply supported truss bridge, as shown in Figure (5).

Claims

1. A method for lifting, pushing and erecting a truss-type emergency bridge. Features: Using a general-purpose crane, the installation is carried out by a combination of hoisting and hanging pushing, which includes the following steps: (1) The crane is placed near the shore. A certain length of guide beam and assembled truss bridge sections are quickly assembled into a truss structure with a certain span at the side and rear of the crane or along the shore. (2) Use a crane to hoist and erect the assembled truss structure of a certain span to the opposite bank at one time, so that one end of the guide beam is erected on the opposite bank and the assembled truss bridge section is erected on our bank; (3) The truss bridge erection personnel on our bank carry equipment through the erected truss structure to the other side, level the ground on the other side and set up rollers; (4) The crane moves backward to create a certain space between the crane and the erected truss structure. The crane is used to lift the assembled bridge section, and the erection personnel on our shore cooperate to assemble the truss bridge section at the rear end of the erected truss structure. (5) The crane lifts the rear end of the assembled bridge section to a certain height, and the crane arm extends forward to provide horizontal thrust to push the bridge section to the other side, completing the erection of the simply supported truss bridge.

2. A method for lifting, pushing and erecting a truss-type emergency bridge according to claim 1, Features: In step (1), the guide beam is connected to the assembled truss bridge segment by single or double ears.

Citation Information

Patent Citations

  • Modular assembly type emergency bridge and erection method thereof

    CN108179695A