A large-span cantilever assembled steel bridge member

By designing the combination of main and secondary stress-bearing components in a large-span cantilever assembly steel bridge, the stress is reduced and uniformly treated in the factory, the damage and stress concentration problems of embedded parts welding to the steel structure are solved, and the safety of the structure is improved and durability.

CN109944168BActive Publication Date: 2024-11-08SHANGHAI MUNICIPAL ENG DESIGN INST (GRP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910190542.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-03-13
Publication Date
2024-11-08
Estimated Expiration
2039-03-13

AI Technical Summary

Technical Problem

Direct welding of embedded parts of large-span steel bridges during construction and operation periods will lead to damage to the steel structure base material, safety hazards during stress concentration and thermal cutting, and affect the durability of the structure.

Method used

Design a large-span cantilever assembly steel bridge member, including the main stressed members and the secondary stressed members. The secondary components are used to weld embedded parts and tracks, reduce the stress of the main components, and complete them in the steel structure processing plant. Connect and paint to avoid on-site welding and rust.

Benefits of technology

It minimizes the damage to the main stressed components by welding embedded parts during construction and operation periods, improves the safety and durability of the structure, and avoids stress concentration and rust problems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109944168B_ABST
    Figure CN109944168B_ABST
Patent Text Reader

Abstract

The present invention is a large-span cantilever assembled steel bridge rod, including a main load-bearing member and a secondary load-bearing member; the main load-bearing member and the secondary load-bearing member are connected by a fixed connection, the main load-bearing part meets the load-bearing requirements of the main structure, the secondary load-bearing part meets the requirements of construction hoisting and operation and maintenance vehicle movement, and at the same time meets the welding requirements of embedded parts. The present invention fully combines design, construction, operation, and management. The main load-bearing part is the load-bearing body of the structure, and the secondary load-bearing member is the functional body during the construction and operation and maintenance period. This design can minimize the damage to the main load-bearing components caused by on-site welding of construction machinery and tools during the construction period and embedded parts such as lighting and guardrails during the operation period. Compared with the prior art, the rod structure of the present invention fully considers the entire life cycle of structural design, construction, and operation management. The increased safety and reliability of the structure improves the durability of the structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge engineering, in particular to a new type of rod for a large-span cantilever assembled steel bridge. Background Art

[0002] Long-span steel arch bridges or steel truss bridges usually adopt the cantilever assembly construction method. During the construction process, the crane usually has to walk on the main arch or main truss chord. After the construction is completed, for the convenience of maintenance, a maintenance vehicle needs to be set up on the main arch or main truss chord. At the same time, in order to meet the requirements of landscape and health monitoring, it is inevitable to weld embedded parts on the structure to install landscape lights or sensors. If these embedded parts during the construction and operation period are directly welded on the main plates of the steel structure, it will inevitably damage the steel structure parent material and cause local stress concentration. In addition, the construction crane track in the past needs to be cut off by thermal cutting technology on the construction site after the construction is completed. The steel plate stress of the long-span steel bridge is relatively large. These stress concentration points and the thermal effects during thermal cutting will become safety hazards of the structure. If the embedded parts are welded at the assembly site, it will also damage the coating of the steel structure parent material and affect the durability of the structure. Summary of the invention

[0003] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and provide a large-span cantilever assembled steel bridge rod structure.

[0004] The purpose of the present invention can be achieved by the following technical solutions:

[0005] A large-span cantilever assembled steel bridge member, characterized in that the large-span cantilever assembled steel bridge member includes a main load-bearing component and a secondary load-bearing component, the main load-bearing component and the secondary load-bearing component are arranged in parallel and both extend along the length direction of the member, and the secondary load-bearing component is connected to the main load-bearing component in a fixed connection manner, the main load-bearing part meets the load requirements of the main structure, the secondary load-bearing part meets the requirements of construction hoisting and operation and maintenance vehicle travel, and at the same time meets the welding requirements of embedded parts.

[0006] Generally, the main load-bearing components are rectangular, polygonal, circular cross-section or truss, and the secondary load-bearing parts are I-shaped, inverted T-shaped, or π-shaped. The connection between the main and secondary components is welded, and the welds should be inspected to ensure the reliable connection between the secondary load-bearing components and the main load-bearing components during bridge operation. The secondary load-bearing components supplement the main load-bearing components and reduce the stress of the main load-bearing components. The cross-sectional area of ​​the secondary load-bearing components is about 3%~7% of the cross-sectional area of ​​the main load-bearing components, so the stress of the main load-bearing components can be reduced by about 3%~7%.

[0007] Furthermore, secondary load-bearing components are used for the running tracks of construction cranes, the running tracks of operation and maintenance vehicles, and are also used for welding of embedded parts of auxiliary facilities. The main load-bearing components and secondary load-bearing components should be connected into a whole at the steel structure processing plant and uniformly painted in the factory. After the on-site hoisting construction and the welding of auxiliary facilities during the operation period, the damaged parts of the paint of the secondary load-bearing components need to be repaired. For the secondary components used as the maintenance vehicle tracks during the operation period, reliable measures (such as oiling, etc.) need to be adopted to prevent the secondary load-bearing components from rusting.

[0008] The primary load-bearing components mentioned above should ensure the safety of the structure during construction and operation periods under the premise that the secondary load-bearing components are regarded as loads without taking into account their contribution to the bearing capacity of the primary load-bearing components.

[0009] The secondary load-bearing components mentioned above should ensure their safety under the effects of construction and operation loads.

[0010] The main load-bearing components and secondary load-bearing components should be welded together in the steel structure processing plant to ensure the connection quality.

[0011] The main load-bearing components and secondary load-bearing components mentioned above shall be uniformly painted in the factory after the connection is completed. The damaged parts of the paint on the secondary components shall be repaired after the on-site hoisting construction and the welding of the ancillary facilities during the operation period. Reliable measures (such as oiling, etc.) shall be adopted to prevent the secondary components from rusting when they are used as the maintenance vehicle tracks during the operation period.

[0012] Specifically, the rod is the upper chord of the main truss of the steel truss bridge. The main load-bearing component has a rectangular cross-section and is welded from four stiffening plates. The secondary load-bearing component adopts a π-shaped cross-section and is welded to the top plate of the main load-bearing component. The crane used during the construction process uses the secondary load-bearing component of the rod as a track and travels on the rod. The safety guardrails and construction monitoring strain gauges during the construction process are all welded to the secondary load-bearing components.

[0013] Furthermore, after all construction is completed and all auxiliary components are welded, the secondary load-bearing components will be repaired by painting to ensure that they will not rust during the operation period.

[0014] Furthermore, during operation, the maintenance vehicle uses the secondary load-bearing components as tracks to travel along the longitudinal direction of the bridge to complete the maintenance of the upper chord and upper parallel joint of the bridge; the health monitoring equipment and embedded parts during operation are all welded to the secondary load-bearing components; the landscape lighting equipment and embedded parts during the operation period are all welded to the secondary load-bearing components.

[0015] The present invention fully combines design, construction, operation and management. The main load-bearing part is the load-bearing body of the structure, and the secondary load-bearing components are the functional bodies during the construction and operation and maintenance period. This design can minimize the damage to the main load-bearing components caused by on-site welding of construction machinery and tools during the construction period and embedded parts such as lighting and guardrails during the operation period. At the same time, the secondary load-bearing part can serve as a supplement to the main load-bearing part to reduce the stress of the main load-bearing part. This structural system can maximize factory prefabrication and avoid the impact of on-site welding or bolting on the main load-bearing rods, thereby improving the reliability of the structure and having a high promotion value in cantilever assembled steel arch bridges and steel truss bridges. Compared with the prior art, the rod structure of the present invention fully considers the entire life cycle of structural design, construction, and operation management. The increased safety and reliability of the structure improves the durability of the structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the bridge structure and cantilever construction method in Example 1 of the present invention;

[0017] Figure 2 It is a schematic elevation view of the upper chord segment in Embodiment 1 of the present invention;

[0018] Figure 3 The figure is a schematic diagram of the cross section of the upper chord in the embodiment 1 of the present invention;

[0019] Figure 4 The figure is a schematic diagram of the cross section of the main force-bearing component of the upper chord in the embodiment 1 of the present invention;

[0020] Figure 5 The figure is a schematic diagram of the cross section of the secondary load-bearing member of the upper chord in the embodiment 1 of the present invention;

[0021] Figure 6 It is a schematic diagram of the construction crane in Example 1 of the present invention walking on the secondary load-bearing member;

[0022] In the figure, 1-bridge upper chord segment, 2-upper chord main load-bearing member, 3-upper chord secondary load-bearing member, 4-truss crane support leg, 5-truss crane. DETAILED DESCRIPTION

[0023] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0024] Example 1

[0025] A long-span cantilever assembly steel bridge rod, which is used as the upper chord of a particularly long-span steel truss bridge. The bridge uses a truss crane for large-segment cantilever assembly, as shown in the attached figure. Figure 1 During the operation period, a maintenance vehicle is installed on the main truss to inspect and maintain the upper chord and parallel joint.

[0026] The main truss upper chord adopts the rod structure of the present invention. The main load-bearing member is a rectangular cross-section, welded by four stiffened plates, the four stiffened plates are the top plate, the bottom plate and two side plates. The secondary load-bearing member adopts a π-shaped cross-section, and the two secondary load-bearing members are welded on both sides of the top plate of the main load-bearing member. Both are painted in the factory.

[0027] When designing primary load-bearing components, secondary load-bearing components are treated as loads without considering their contribution to the strength of the primary load-bearing components.

[0028] The crane used in the construction process uses the secondary load-bearing components of the rod as a track and moves on top of the rod.

[0029] The safety guardrails and construction monitoring strain gauges used during the construction process are all welded to secondary load-bearing components.

[0030] During operation, the maintenance vehicle also uses the secondary load-bearing components as tracks to move along the longitudinal direction of the bridge to complete the maintenance of the bridge's upper chord and upper parallel joint.

[0031] The health monitoring equipment and embedded parts during operation are welded to the secondary load-bearing components.

[0032] During the operation period, the landscape lighting equipment and embedded parts are welded to the secondary load-bearing components.

[0033] After all construction is completed and all auxiliary components are welded, the secondary load-bearing components will be painted and repaired to ensure that they will not rust during the operation period.

[0034] The above description of the embodiments is to facilitate the understanding and use of the invention by those skilled in the art. It is obvious that those skilled in the art can easily make various modifications to the embodiments and apply the general principles described herein to other embodiments without creative work. Therefore, the present invention is not limited to the above embodiments, and improvements and modifications made by those skilled in the art based on the disclosure of the present invention without departing from the scope of the present invention should be within the scope of protection of the present invention.

Claims

1. A long-span cantilever assembled steel bridge member, characterized in that The large-span cantilever assembled steel bridge rods include main load-bearing components and secondary load-bearing components. The main load-bearing components and the secondary load-bearing components extend along the length direction of the rods, and the secondary load-bearing components are connected to the main load-bearing components in a fixed connection manner. The main load-bearing components meet the load-bearing requirements of the main structure, and the secondary load-bearing components meet the requirements of construction hoisting and operation and maintenance vehicle travel, and at the same time meet the welding requirements of embedded parts. The main load-bearing components are rectangular, polygonal, circular cross-sections or trusses, and the secondary load-bearing parts are I-shaped, inverted T-shaped or π-shaped cross-sections. The connection between the main load-bearing components and the secondary load-bearing components is welded, and the welds should be inspected to ensure that the secondary load-bearing components are reliably connected to the main load-bearing components during the operation of the bridge. The secondary load-bearing components serve as a supplement to the main load-bearing components to reduce the stress of the main load-bearing components. The cross-sectional area of ​​the secondary load-bearing components is 3% to 7% of the cross-sectional area of ​​the main load-bearing components.

2. A long-span cantilever assembled steel bridge member according to claim 1, characterized in that The secondary load-bearing components are used for the running tracks of construction cranes, the running tracks of operation and maintenance vehicles, and are also used for welding of embedded parts for ancillary facilities.

3. The long-span cantilever assembled steel bridge member according to claim 1, characterized in that The main load-bearing components and secondary load-bearing components are connected into a whole at the steel structure processing plant and uniformly painted in the factory. After the on-site hoisting construction and the welding of ancillary facilities during the operation period are completed, the damaged parts of the paint on the secondary load-bearing components need to be repaired. For the secondary load-bearing components that serve as the maintenance vehicle tracks during the operation period, reliable measures must be taken to prevent the secondary load-bearing components from rusting.

4. The long-span cantilever assembled steel bridge member according to claim 1, characterized in that The large-span cantilever assembled steel bridge rod can be used as a chord of a large-span continuous steel truss bridge of cantilever construction and a main arch of a large-span steel arch bridge.

5. The long-span cantilever assembled steel bridge member according to claim 1, characterized in that The rod is the upper chord of the main truss of the steel truss bridge. The main load-bearing component has a rectangular cross-section and is welded from four stiffening plates. The secondary load-bearing component has a π-shaped cross-section and is welded to the top plate of the main load-bearing component. The crane used during the construction process uses the secondary load-bearing component of the rod as a track and travels on the rod. The safety guardrails and construction monitoring strain gauges during the construction process are all welded to the secondary load-bearing components.

6. A long-span cantilever assembled steel bridge member according to claim 5, characterized in that After all construction is completed and all auxiliary components are welded, the secondary load-bearing components will be painted and repaired to ensure that they will not rust during the operation period.

7. The long-span cantilever assembled steel bridge member according to claim 5, characterized in that During operation, the maintenance vehicle uses the secondary load-bearing components as tracks and moves along the longitudinal direction of the bridge to complete the maintenance of the upper chord and upper parallel joint of the bridge; the health monitoring equipment and embedded parts during operation are all welded to the secondary load-bearing components; the landscape lighting equipment and embedded parts during the operation period are all welded to the secondary load-bearing components.