A force-balanced embankment width structure of an existing high-speed railway on a rock foundation and a construction method thereof
By using grouting anchors and reinforced concrete frame structures in the construction of high-speed railway support networks, combined with cantilever plates and fill bodies, the problem of difficult control of deformation of rock foundation embankments is solved, and the protection of existing high-speed railways and the construction of new roadbeds are achieved. It has excellent stability, good deformation control effect and construction characteristics.
Patent Information
- Application Number
- CN201911232399.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-04
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2039-12-04
AI Technical Summary
In the construction of high-speed railway branch networks, when the new high-speed railway needs to run parallel or widen the existing high-speed railway, it is difficult to control the deformation of the rock foundation embankment, affecting the stability of the existing high-speed railway.
It uses several grouting anchors and reinforced concrete frame structures, combined with cantilever plates and filling bodies, and uses the high bearing capacity and anchoring force of the rock foundation to resist the train load through the tensile force of the grouting anchors and the weight of the filling body. Avoid vertical deformation and ensure that the new roadbed does not cause adverse loads on the existing high-speed railway.
It effectively avoids the adverse impact of the new roadbed on the existing high-speed railway, achieves deformation control, and is fast, safe, economical, reliable, environmentally friendly, and suitable for popularization and application.
Smart Images

Figure CN110761127B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of high-speed railway engineering, and in particular to a force-balanced embankment width structure of an existing high-speed railway on a rock foundation and a construction method thereof. Background Art
[0002] High-speed railways are developing rapidly in my country. At present, my country's large high-speed railway network has been basically completed. However, with the continuous increase in local demand, the construction of high-speed railway branch networks is increasing. In the construction of high-speed railway branch networks, many new high-speed railways need to be built in parallel with existing high-speed railways, and even need to be built adjacent to existing high-speed railways or the existing high-speed railways need to be widened.
[0003] High-speed railways have strict requirements on deformation. Ballastless track high-speed railways have millimeter-level deformation control. Increasing loads near existing high-speed railways will undoubtedly cause adverse deformation of the existing high-speed railways. When the existing high-speed railway is an embankment project, the impact of this later adverse deformation is particularly obvious and becomes a key control point for the implementation of new high-speed railways. Summary of the invention
[0004] The purpose of the present invention is to provide a force-balanced width structure and construction method for an existing high-speed railway embankment on a rock foundation in response to the problems existing in the prior art, which can effectively solve the technical problem of difficult control of width deformation of an existing high-speed railway embankment on a rock foundation.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] A force-balanced embankment width structure for an existing high-speed railway on a rock foundation, comprising:
[0007] A number of grouting anchors are used to be installed at intervals in the rock foundation outside the slope foot of the existing embankment;
[0008] A reinforced concrete frame structure is used to be installed on the rock foundation outside the slope foot of the existing embankment, and all the grouting anchor rods are connected to the bottom of the frame structure;
[0009] A reinforced concrete cantilever plate, one end of which is connected to the top of the frame structure, and the other end is placed on the existing embankment shoulder structure, and the top surface of the frame structure, the top surface of the cantilever plate and the top surface of the existing embankment are flush;
[0010] The filling body fills the inner cavity of the frame structure.
[0011] The width of the frame structure is determined according to the width requirement of the roadbed, the cantilever plate meets the vertical deformation requirement under the dynamic stress of the train, and the grouting anchor rod can provide a large favorable pulling force for the frame structure; the frame structure serves as the bearing body of the newly-built roadbed, and is used as the fixed force-bearing end of the cantilever plate, while providing a restraint space for the compacted body; the weight of the compacted body is provided for the roadbed of the roadbed by economical and local materials; the cantilever plate is used as a part of the bearing structure of the roadbed of the roadbed of the roadbed, and the cantilever structure does not contact the existing high-speed railway compacted body, and does not cause adverse deformation to the existing high-speed railway.
[0012] The force-balancing widening structure of an existing high-speed railway embankment on a rock foundation described in the present invention is adopted to fully utilize the high bearing capacity and anchoring force of the rock foundation. The weight of the frame structure and the filling body inside it, combined with the tension generated by the grouting anchor rods, is used to resist the load of the train on the cantilever plate, and has a very high safety reserve, thereby avoiding adverse vertical deformation when the train passes through the cantilever plate. The widening roadbed does not generate adverse loads on the existing high-speed railway foundation, thereby not affecting the existing high-speed railway. The structure completely avoids the impact on the filling body of the existing high-speed railway, so it will not have an adverse impact on the existing high-speed railway.
[0013] Preferably, the top surface of the width structure formed by the top surface of the frame structure and the top surface of the cantilever plate is used to set the track structure.
[0014] Preferably, a chamfer structure is provided between the cantilever plate and the side wall of the frame structure.
[0015] The spacing and depth of the grouting anchor rods are determined according to the force balance safety reserve requirement. Preferably, the depth of the grouting anchor rods inserted into the rock foundation is equal to or greater than 4 m.
[0016] Preferably, the landfill is a layered fill structure.
[0017] Preferably, the frame structure comprises a bottom plate, two vertical walls and a top plate, the bottom plate, the two vertical walls and the top plate enclose a cubic pipe gallery structure, and the filling body is arranged inside the pipes of the cubic pipe gallery.
[0018] Preferably, the cantilever plate and the top plate are integrally formed structural parts.
[0019] The present invention also provides a method for constructing the force-balanced width-supporting structure of an existing high-speed railway embankment on a rock foundation as described above, comprising the following steps:
[0020] A. Leveling the rock foundation of the new high-speed railway;
[0021] B. constructing all the grouting anchor rods on the rock foundation, wherein the grouting anchor rods are embedded in the rock foundation and the tops thereof are exposed from the surface of the rock foundation;
[0022] C. constructing the bottom plate and the vertical wall on the rock foundation, the exposed section of the grouting anchor is fixedly connected to the steel bars of the bottom plate, and the vertical force-bearing steel bars of the vertical wall are exposed at their tops;
[0023] D. After the bottom plate and the vertical wall are formed, the cavity of the frame structure is filled with the compacted material;
[0024] E. The top plate and the cantilever plate are constructed as one piece, and the exposed steel bars of the vertical wall are fixedly connected to the steel bars of the top plate.
[0025] The method for constructing a force-balanced widening structure of an existing high-speed railway embankment on a rock foundation described in the present invention fully utilizes the high bearing capacity and anchoring force of the rock foundation, and uses the weight of the frame structure and the filling body inside it, combined with the tension generated by the grouting anchor rods, to resist the load of the train on the cantilever plate, and has a very high safety reserve, thereby avoiding adverse vertical deformation when the train passes through the cantilever plate, and the widening roadbed does not generate adverse loads on the existing high-speed railway foundation, thereby not affecting the existing high-speed railway; the construction method has the characteristics of good deformation control effect, fast and convenient construction, safety, economic reliability and environmental protection, and is conducive to promotion and application.
[0026] Preferably, in step B, the exposed section of the grouting anchor is equal to or greater than 30 cm.
[0027] Preferably, in step C, the exposed section of the vertical stress-bearing steel bars of the vertical wall is equal to or greater than 30 cm.
[0028] Preferably, in the step D, after the concrete strength of the bottom plate and the vertical wall reaches 80% of the design strength, the cavity of the frame structure is filled with the filling body.
[0029] Preferably, in the step D, the filling soil layers are constructed in layers to form the built body.
[0030] Preferably, after step E, the track structure on the top plate and the cantilever plate is constructed.
[0031] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0032] 1. The force-balanced widening structure of an existing high-speed railway embankment on a rock foundation described in the present invention is used to fully utilize the high bearing capacity and anchoring force of the rock foundation. The weight of the frame structure and the filling body inside it, combined with the tension generated by the grouting anchor rods, is used to resist the load of the train on the cantilever plate, and has a high safety reserve, thereby avoiding adverse vertical deformation when the train passes through the cantilever plate. The widening roadbed does not generate adverse loads on the existing high-speed railway foundation, thereby not affecting the existing high-speed railway; the structure completely avoids the impact on the filling body of the existing high-speed railway, so it will not have an adverse impact on the existing high-speed railway;
[0033] 2. The method for constructing a force-balanced widening structure of an existing high-speed railway embankment on a rock foundation described in the present invention is used to fully utilize the high bearing capacity and anchoring force of the rock foundation. The weight of the frame structure and the filling body inside it, combined with the tension generated by the grouting anchor rods, is used to resist the load of the train on the cantilever plate, and has a high safety reserve, thereby avoiding adverse vertical deformation when the train passes through the cantilever plate. The widening roadbed does not generate adverse loads on the existing high-speed railway foundation, thereby not affecting the existing high-speed railway. The construction method has the characteristics of good deformation control effect, fast and convenient construction, safety, economic reliability and environmental protection, and is conducive to promotion and application. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a schematic diagram of the force balance dam width structure of an existing high-speed railway embankment on a rock foundation described in the present invention.
[0035] Icons: 01- rock foundation, 02- existing embankment, 1- grouting anchor, 2- frame structure, 21- bottom plate, 22- vertical wall, 23- top plate, 3- cantilever plate, 4- fill, 5- track structure. DETAILED DESCRIPTION
[0036] The present invention will be described in detail below in conjunction with the accompanying drawings.
[0037] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0038] Example 1
[0039] like Figure 1 As shown, the force-balanced dam structure of an existing high-speed railway embankment on a rock foundation according to the present invention comprises:
[0040] A plurality of grouting anchor rods 1 are used to be arranged at intervals in the rock foundation 01 outside the slope foot of the existing embankment 02. The spacing and depth of the grouting anchor rods 1 are determined according to the force balance safety reserve requirements. Specifically, the depth of the grouting anchor rods 1 inserted into the rock foundation 01 is equal to or greater than 4m.
[0041] A reinforced concrete frame structure 2 is used to be arranged on a rock foundation 01 outside the slope foot of an existing embankment 02, all of the grouting anchor rods 1 are connected to the bottom of the frame structure 2, and the frame structure 2 includes a bottom plate 21, two vertical walls 22 and a top plate 23, and the bottom plate 21, the two vertical walls 22 and the top plate 23 enclose a cubic pipe gallery structure;
[0042] A reinforced concrete cantilever plate 3, one end of which is connected to the top of the frame structure 2, and the other end is placed on the shoulder structure of the existing embankment 02. The top surface of the frame structure 2, the top surface of the cantilever plate 3 and the top surface of the existing embankment 02 are flush. The cantilever plate 3 and the top plate 23 are integrally formed structural parts. A chamfer structure is provided between the cantilever plate 3 and the adjacent vertical wall 22.
[0043] The filling body 4 is made of general earth materials and fills the inner cavity of the frame structure 2 in layers;
[0044] The track structure 5 is used to be arranged on the top surface of the width structure formed by the top surface of the frame structure 2 and the top surface of the cantilever plate 3.
[0045] The width of the frame structure 2 is determined according to the width requirement of the roadbed, the cantilever plate 3 meets the vertical deformation requirement under the dynamic stress of the train, and the grouting anchor rod 1 can provide a large favorable pulling force for the frame structure 2; the frame structure 2 serves as the bearing body of the newly-built roadbed, and is used as the fixed force-bearing end of the cantilever plate 3, while providing a restraint space for the compacted body 4; the weight of the compacted body 4 is economically and locally made to provide favorable pressure for the roadbed; the cantilever plate 3 is used as a part of the bearing structure of the roadbed, and the cantilever structure does not contact the existing high-speed railway compacted body, and does not cause adverse deformation to the existing high-speed railway.
[0046] By using the force-balancing widening structure of an existing high-speed railway embankment on a rock foundation described in the present invention, the high bearing capacity and anchoring force of the rock foundation 01 are fully utilized, and the weight of the frame structure 2 and the filling body 4 inside it, combined with the tension generated by the grouting anchor rod 1, is used to resist the load of the train on the cantilever plate 3, and has a very high safety reserve, thereby avoiding adverse vertical deformation when the train passes through the cantilever plate 3. The widening roadbed does not generate adverse loads on the existing high-speed railway foundation, thereby not affecting the existing high-speed railway; this structure completely avoids the impact on the filling body of the existing high-speed railway, so it will not have an adverse impact on the existing high-speed railway.
[0047] Example 2
[0048] like Figure 1 As shown, the method for constructing a force-balanced width-supporting structure of an existing high-speed railway embankment on a rock foundation described in the present invention is used to construct the force-balanced width-supporting structure of an existing high-speed railway embankment on a rock foundation as described in Example 1, and the method comprises the following steps:
[0049] A. Leveling the rock foundation 01 foundation of the new high-speed railway;
[0050] B. constructing all the grouting anchor rods 1 on the rock foundation 01, wherein the grouting anchor rods 1 are embedded in the rock foundation 01, and the tops thereof are exposed from the surface of the rock foundation 01, and the exposed sections of the grouting anchor rods 1 are equal to or greater than 30 cm;
[0051] C. The bottom plate 21 and the vertical wall 22 are constructed on the rock foundation 01. The exposed section of the grouting anchor rod 1 is fixedly connected to the steel bars of the bottom plate 21 by welding. The vertical stress-bearing steel bars of the vertical wall 22 are exposed at their tops. The exposed section of the vertical stress-bearing steel bars of the vertical wall 22 is equal to or greater than 30 cm.
[0052] It also includes the processes of setting up formwork and pouring concrete;
[0053] D. After the concrete strength of the bottom plate 21 and the vertical wall 22 reaches 80% of the design strength, fill the cavity of the frame structure 2 with soil layers in layers to fill the built-up body 4;
[0054] E. The top plate 23 and the cantilever plate 3 are constructed as one piece, and the exposed steel bars of the vertical wall 22 are fixedly connected to the steel bars of the top plate 23, specifically by welding;
[0055] It also includes the steps of setting the formwork and pouring concrete, and the steel cage of the top plate 23 and the steel cage of the cantilever plate 3 are tied into a whole;
[0056] F. Construct the track structure 5 on the top plate 23 and the cantilever plate 3.
[0057] The method for constructing a force-balanced widening structure of an existing high-speed railway embankment on a rock foundation described in the present invention fully utilizes the high bearing capacity and anchoring force of the rock foundation 01, and uses the weight of the frame structure 2 and the filling body 4 inside it, combined with the tension generated by the grouting anchor rod 1, to resist the load of the train on the cantilever plate 3, and has a very high safety reserve, thereby avoiding adverse vertical deformation when the train passes through the cantilever plate 3, and the widening roadbed does not generate adverse loads on the existing high-speed railway foundation, thereby not affecting the existing high-speed railway; the construction method has the characteristics of good deformation control effect, fast and convenient construction, safety, economic reliability and environmental protection, and is conducive to promotion and application.
[0058] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for constructing a force-balanced embankment width structure of an existing high-speed railway on a rock foundation, characterized in that: The force balance dam structure of the existing high-speed railway embankment on rock foundation includes: A plurality of grouting anchor rods (1) are arranged at intervals in a rock foundation (01) outside the slope foot of an existing embankment (02); A reinforced concrete frame structure (2) is used to be arranged on a rock foundation (01) outside the slope foot of an existing embankment (02), and all the grouting anchor rods (1) are connected to the bottom of the frame structure (2); the frame structure (2) comprises a bottom plate (21), two vertical walls (22) and a top plate (23), and the bottom plate (21), the two vertical walls (22) and the top plate (23) enclose a cubic pipe gallery structure; A reinforced concrete cantilever plate (3) is connected at one end to the top of the frame structure (2) and at the other end is placed on the shoulder structure of the existing embankment (02); the top surface of the frame structure (2), the top surface of the cantilever plate (3) and the top surface of the existing embankment (02) are flush; the top surface of the width structure formed by the top surface of the frame structure (2) and the top surface of the cantilever plate (3) is used to set the track structure (5); the cantilever plate (3) and the top plate (23) are integrally formed structural parts; A filling body (4) is used to fill the internal cavity of the frame structure (2); The method comprises the following steps: A. Leveling the rock foundation (01) of the new high-speed railway; B. constructing all the grouting anchor rods (1) on the rock foundation (01), wherein the grouting anchor rods (1) are embedded in the rock foundation (01) and the tops thereof are exposed from the surface of the rock foundation (01); C. constructing the base plate (21) and the vertical wall (22) on the rock foundation (01), wherein the exposed section of the grouting anchor rod (1) is fixedly connected to the steel bars of the base plate (21), and the vertical force-bearing steel bars of the vertical wall (22) are exposed at their tops; D. After the bottom plate (21) and the vertical wall (22) are formed, the cavity of the frame structure (2) is filled with the filling material (4); E. The top plate (23) and the cantilever plate (3) are constructed as one piece, and the exposed steel bars of the vertical wall (22) are fixedly connected to the steel bars of the top plate (23).
2. The construction method according to claim 1, characterized in that: A chamfer structure is provided between the cantilever plate (3) and the side wall of the frame structure (2).
3. The construction method according to claim 1, characterized in that: The grouting anchor rod (1) is inserted into the rock foundation (01) to a depth equal to or greater than 4 m.
4. The construction method according to claim 1, characterized in that: The filling body (4) is a layered filling structure.
5. The construction method according to claim 1, characterized in that: In the step D, the soil layers are filled in layers to form the fill body (4).
6. The construction method according to any one of claims 1 to 5, characterized in that: After step E, the track structure (5) on the top plate (23) and the cantilever plate (3) is constructed.