Lifting construction displacement control system and displacement control method in jacking construction
By setting up a combined structure of through-holes, guide columns and limit beams in building hoisting construction, the horizontal displacement of the hoisting floor slab is limited, and the construction damage problem caused by deviation in hoisting construction is solved, and construction safety is improved. Structural stability.
Patent Information
- Application Number
- CN201911078539.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-06
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2039-11-06
AI Technical Summary
During the construction of building lifting, the floor is prone to deviation after being affected by horizontal load, resulting in the misalignment of the partition joints, which in turn leads to the inability to transfer the building's self-weight load. In severe cases, it may cause the collapse of the stress system and the construction damage.
Design a lift construction displacement control system. By setting through openings and guiding columns on the lifting floor slab, the lower end of the guide column is firmly connected to the fixed floor slab, and a limit beam is set on the upper surface of the lifting floor slab to form a limit port, and the limit port is formed. A lubricating layer is provided between the guide column and the limit beam to limit the horizontal displacement of the lifting floor slab and avoid building offset.
Effectively constrain the horizontal displacement of the floor, ensure that the building does not have offset during the lifting process, improve construction safety, and facilitate on-site splicing through I-steel and channel steel structures, enhancing structural stability and strength.
Smart Images

Figure CN110792285B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building reconstruction, and in particular to a jacking construction displacement control system and a jacking construction process. Background Art
[0002] In construction, jacking construction between floors is a renovation construction that increases the height between two floor slabs.
[0003] like Figure 5 The specific construction steps are as follows:
[0004] Step 1: Arrange corbels 2 on two opposite sides of the structural column 1, and one corbel 2 is arranged on each of the two sides of the structural column 1;
[0005] Step 2: Install the CNC hydraulic cylinder 3 between the two bull legs 2;
[0006] Step 3: Cut the structural column 1 on the horizontal plane between the upper and lower corbels 2 to form a separation seam 4, and destroy the wall between the upper and lower floors;
[0007] Step 4: Corbels 2 are arranged on the remaining two sides of the structural column 1, and a manual follower hydraulic cylinder 5 is arranged between the corbels 2;
[0008] In this way, the four sides of each structural column 1 are provided with corbels 2, wherein the four higher corbels 2 are located above the partition 4, and the four lower corbels 2 are located below the partition 4, and the heights of the four higher corbels 2 and the four lower corbels 2 are uniform;
[0009] Step 5: The numerically controlled hydraulic cylinder 3 starts the jacking bracket 2, so that the building structure above the separation gap 4 is lifted as a whole, and the size of the separation gap 4 is enlarged;
[0010] Step 6: Follow the manual operation of the hydraulic cylinder 5 to follow the lifting process to prevent the lifted building structure from falling back due to the failure of the CNC hydraulic cylinder 3;
[0011] Step 7: Repeat steps 5 and 6 until the building structure above the separation joint 4 reaches a preset height;
[0012] Step 8: After the structural column 1 is lifted, high-strength concrete is filled in the separation joint 4, and the follower hydraulic cylinder 5, CNC hydraulic cylinder 3 and corbel 2 are removed after the concrete is cured and reaches the designed strength.
[0013] The above-mentioned prior art has the following defects: during the jacking process, the floors will be offset due to the horizontal load such as wind load, which will cause the upper and lower parts of the separation joint to be unable to be aligned, and then the deadweight load of the jacked part of the building cannot be transmitted downward. In severe cases, the force system will collapse and the building will be damaged during the jacking construction process. Summary of the invention
[0014] In view of the shortcomings of the prior art, the present invention provides a jacking construction displacement control system, which has the advantage of constraining the horizontal displacement of the floor when jacking the floor slab through the device.
[0015] The first technical objective of the present invention is achieved through the following technical solutions: a jacking construction displacement control system, arranged on two adjacent upper and lower floor slabs, wherein the upper floor slab is a jacking floor slab and the lower floor slab is a fixed floor slab, comprising a through-hole opened on the jacking floor slab, at least two through-holes, a guide column arranged in the through-hole, the lower end of the guide column is fixedly connected to the fixed floor slab, and the upper end of the guide column passes through the through-hole; a plurality of limit beams are fixed horizontally and vertically on the upper surface of the jacking floor slab, and the plurality of limit beams are staggered to form a limit opening, and the opening range of the limit opening is within the opening range of the through-hole.
[0016] By adopting the above technical scheme, a guide column is fixed to the fixed floor slab, the guide column passes through and extends out of the jacking floor slab, and a limit beam for limiting the displacement of the guide column is arranged at one end extending out of the jacking floor slab. Several guide columns limited by the limit beam can guide the jacking floor slab during the jacking process, and limit the horizontal displacement of the jacking floor slab during the jacking process, thereby avoiding horizontal offset between the jacked part and the non-jacked part of the building, which may lead to damage to the jacking construction system and the building.
[0017] The present invention is further configured as follows: a floor beam is arranged on the lower surface of the fixed floor slab, the limiting beam and the floor beam are arranged alternately, and the intersecting positions of the floor beam and the limiting beam are fixedly connected by a limiting hoop; the limiting hoop surrounds the limiting beam and passes through the fixed floor slab to be fixed to the limiting beam.
[0018] By adopting the above technical solution, a limiting hoop is arranged at the staggered position of the limiting beam and the floor beam, and the limiting hoop is used to firmly fix the limiting beam on the floor beam, thereby improving the restraining effect of the limiting beam on the guide column.
[0019] The present invention is further configured as follows: the guide column is a frame structure including a plurality of vertical poles and cross poles, the vertical poles are four and distributed in a rectangular shape, and the cross poles connect adjacent vertical poles.
[0020] By adopting the above technical solution, the guide column is spliced by multiple vertical rods and horizontal rods, so the guide column can be conveniently spliced on site.
[0021] The present invention is further configured as follows: the vertical poles and the limit beams are I-beams; and the horizontal poles are channel steels.
[0022] By adopting the above technical solution, the I-beam is used as the vertical pole, which has good bending resistance, and the cross bar is a channel steel structure, which has good weldability and bending resistance, so that the guide rod has better structural strength.
[0023] The present invention is further configured as follows: a plurality of oblique rods are arranged in the guide column, and the diagonal vertical rods at both ends of the oblique rods are connected.
[0024] By adopting the above technical solution, the two ends of the oblique rod are connected to the diagonal vertical rods, so that the oblique rod, the vertical rod and the horizontal rod form a triangular structure, thereby improving the overall structural stability of the guide column.
[0025] The present invention is further configured as follows: a pad is provided at the lower end of the vertical pole, bolts are provided at intervals on the upper surface of the pad around the pad, and the bolts pass through the pad to be connected with the fixed floor slab.
[0026] By adopting the above technical solution, the bolts surrounding the pad are connected to the fixed floor, so that the pad can be firmly fixed on the fixed floor, and further the guide column can be firmly fixed on the fixed floor.
[0027] The present invention is further configured such that: a protrusion extending into the fixed floor slab is provided at the bottom of the pad.
[0028] By adopting the above technical solution, the protrusion extends into the fixed floor slab, which can prevent the pad from slipping.
[0029] The present invention is further configured as follows: a gap is provided between the guide column and the limiting beam, and a lubricating layer is provided on the outer surface of the guide column.
[0030] By adopting the above technical solution, a lubricating layer is provided on the guide column, and when the limiting beam contacts the guide column during the jacking process, the friction force generated by the contact between the limiting beam and the guide column can be effectively reduced.
[0031] The present invention is further configured as follows: a fixing plate is provided on the pad, one end of the fixing plate is connected to the vertical pole, and the other end of the fixing plate is connected to the pad.
[0032] By adopting the above technical solution, the fixing plate connects the upright pole and the pad, thereby improving the stability of the connection between the upright pole and the pad, thereby improving the structural stability of the guide column.
[0033] The first technical purpose of the present invention is achieved through the following technical solution: a displacement control method in jacking construction, comprising the following construction steps:
[0034] Step 1: Open four through openings on the jacking floor;
[0035] Step 2: Setting a limit beam on the upper surface of the jacking floor and forming a limit opening;
[0036] Step 3: Set the limit hoop to fix the limit beam;
[0037] Step 4: Splice to form a guide column, and fix the lower end of the guide column on the fixed floor slab, and let the upper end of the guide column pass through the through opening and the limit opening;
[0038] Step 5: Apply a lubricating layer on the surface of the guide column;
[0039] Step 6: Carry out jacking construction on the fixed floor slab.
[0040] In summary, the present invention has the following beneficial effects: due to the cooperation between the guide column and the limit opening, if the jacking floor slab undergoes horizontal displacement during the jacking construction process, since the distance of the gap between the limit opening and the guide column is smaller than the displacement distance allowed by the jacking floor slab, the displacement of the jacking floor slab can be limited by this system, thereby making the building jacking construction safer.
[0041] In addition, the guide columns, limit beams, limit hoops and other structures in the system are all formed by splicing I-beams or channel steels, so the system can be conveniently spliced at the construction site.
[0042] 1. A guide column is fixed on the fixed floor slab. The guide column passes through and extends out of the jacking floor slab, and a limit beam for limiting the displacement of the guide column is arranged at one end extending out of the jacking floor slab. Several guide columns limited by the limit beam can guide the jacking floor slab during the jacking process and limit the horizontal displacement of the jacking floor slab during the jacking process, thereby avoiding horizontal deviation between the jacked part and the non-jacked part of the building, which may lead to damage to the jacking construction system and the building.
[0043] 2. Apply lubricant between the guide column and the limit beam to form a lubricating layer, which can effectively reduce the friction generated by the contact between the limit beam and the guide column.
[0044] 3. The fixing plate connects the upright pole and the pad to improve the stability of the connection between the upright pole and the pad, thereby improving the structural stability of the guide column. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 It is a schematic diagram of the overall structure in the first embodiment;
[0046] Figure 2 for Figure 1 Schematic diagram of the cross-sectional structure of AA;
[0047] Figure 3 for Figure 2Schematic diagram of the cross-sectional structure of the middle BB;
[0048] Figure 4 This is a schematic structural diagram of the lower end of the vertical pole in the first embodiment;
[0049] Figure 5 It is a structural schematic diagram of the background technology.
[0050] Figure numerals: 1. structural column; 2. corbel; 3. CNC hydraulic cylinder; 4. partition joint; 5. follower hydraulic cylinder; 6. lifting floor; 7. fixed floor; 8. through-hole; 9. guide column; 10. limit beam; 11. limit hole; 12. web one; 13. flange plate one; 14. floor beam; 15. limit hoop; 16. web two; 17. flange plate two; 18. vertical pole; 19. horizontal pole; 20. diagonal pole; 21. web three; 22. flange plate three; 23. pad; 24. bump; 25. bolt; 26. fixing plate. DETAILED DESCRIPTION
[0051] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0052] like Figure 1 , 2 As shown, a jacking construction displacement control system disclosed by the present invention is arranged on two adjacent upper and lower floors, wherein the upper floor is a jacking floor 6, and the lower floor is a fixed floor 7, including four through holes 8 opened on the jacking floor 6, and guide columns 9 are arranged in the through holes 8. The lower ends of the guide columns 9 are fixedly connected to the fixed floor 7, and the upper ends of the guide columns 9 pass through the through holes 8; a plurality of limit beams 10 are fixed horizontally and vertically on the upper surface of the jacking floor 6, and the plurality of limit beams 10 are staggered to form limit holes 11, and the opening range of the limit holes 11 is within the opening range of the through holes 8.
[0053] like Figure 1 , 2 As shown, in this embodiment, the number of the limiting beams 10 is 8, including 4 horizontal ones and 4 vertical ones. The 4 horizontal limiting beams 10 are in direct contact with the upper surface of the fixed floor slab 7, while the 4 vertical limiting beams 10 are arranged on the horizontal limiting beams 10. The four through-holes 8 are rectangular and distributed in a rectangular shape, and the staggered positions of the two horizontal and two vertical limiting beams 10 form the limiting openings 11. The cross-section of the guide column 9 along its length direction is rectangular as a whole, and there is a gap between the guide column 9 and the limiting opening 11, and the gap is smaller than the horizontal displacement distance allowed by the jacking floor slab 6. In addition, by adjusting the number of horizontal and vertical limiting beams 10, an even number of through-holes 8 can be formed, for example, two, six, or eight.
[0054] The limiting beam 10 is an I-beam, and the limiting beam 10 includes a web 12 and flange plates 13 vertically arranged on both sides of the width of the web 12. The flange plates 13 of the horizontally arranged and longitudinally arranged limiting beams 10 are both vertically fixed to the floor slab 7.
[0055] The lower surface of the fixed floor slab 7 is provided with a floor beam 14, and a limiting hoop 15 is provided at the intersection of the limiting beam 10 and the floor beam 14 to connect the floor beam 14 and the limiting beam 10, and a pair of limiting hoops 15 are provided on both sides of the width of the limiting beam 10. The limiting hoop 15 is formed by splicing three channel steels, two of which pass through the fixed floor slab 7 at two layers of the width of the floor beam 14 and are welded and fixed on one side of the width of the limiting beam 10, and the lower ends of the two aforementioned channel steels are located below the lower end surface of the floor beam 14 and are welded with another channel steel. The channel steel of the limiting hoop 15 includes a web plate 16 and a flange plate 17, and the flange plate 17 is vertically fixed on both sides of the width of the web plate 16, and the upper end of the web plate 16 is fitted and welded to the flange plate 13. Because the limiting hoop 15 is provided to fix the floor beam 14 and the limiting beam 10 together, the stability of the limiting beam 10 on the fixed floor slab 7 is enhanced.
[0056] like Figure 2 , 3 As shown, the guide column 9 is a frame structure as a whole, and the guide column 9 includes a vertical rod 18, a horizontal rod 19 and an oblique rod 20. Among them, there are four vertical rods 18 and they are distributed in a rectangular form, and the vertical rods 18 are perpendicular to the fixed floor 7. The horizontal rod 19 is horizontally arranged between two adjacent vertical rods 18, and the two ends of the horizontal rod 19 are welded and fixed to the corresponding vertical rods 18. The vertical rod 18 is an I-beam, which includes a web three 21 and a flange plate three 22, and the flange plate three 22 is fixed on both sides of the width of the web three 21. The horizontal rod 19 is welded to the middle of the web three 21 or the flange plate three 22 of the vertical rod 18. An oblique rod 20 is also arranged at the same height position as the horizontal rod 19, and the two ends of the oblique rod 20 are welded and fixed to the two vertical rods 18 at diagonal positions. Among them, the horizontal rod 19 and the oblique rod 20 are both channel steel structures.
[0057] A lubricating layer (not shown) is formed on the surface of the guide column 9. If displacement occurs during the lifting process of the jacking floor 6, the guide column 9 will contact the limit beam 10. Because a lubricating layer is brushed on the surface of the guide column 9, the friction between the guide column 9 and the limit beam 10 can be reduced when they contact, thereby allowing the fixed floor 7 to be lifted smoothly.
[0058] like Figure 4As shown, a square pad 23 is vertically fixed on the lower end surface of the vertical rod 18, and the lower end of the vertical rod 18 is welded and fixed to the middle of the pad 23. A protrusion 24 extending into the fixed floor 7 is fixed in the middle of the lower surface of the pad 23. A plurality of bolts 25 surrounding the edge of the pad 23 are arranged at intervals on the pad 23, and the bolts 25 pass through the pad 23 and are fixed to the fixed floor 7, so that the guide column 9 can be firmly connected to the fixed floor 7.
[0059] A fixing plate 26 is arranged on the opposite sides of the two flange plates 22 on the same vertical rod 18. The fixing plate 26 is vertical and fixed on the pad 23 and the flange plate 22, and the fixing plate 26, the vertical rod 18, and the pad 23 form a triangular structure to enhance the connection strength between the vertical rod 18 and the pad 23.
[0060] Embodiment 2.
[0061] like Figure 1 , 2 As shown, a displacement control method in jacking construction includes the following construction steps:
[0062] Step 1: Open four through openings 8 on the jacking floor 6 by static cutting method;
[0063] Step 2: Arrange a limit beam 10 on the upper surface of the jacking floor 6 and form a limit opening 11;
[0064] Step 3: holes are set on both sides of the width of the limiting beam 10, and then limiting hoops 15 are set in the holes to fix the limiting beam 10;
[0065] Step 4: Splice to form a guide column 9, and fix the lower end of the guide column 9 on the fixed floor slab 7, and let the upper end of the guide column 9 pass through the through opening 8 and the limit opening 11;
[0066] Step 5: brushing to form a lubricating layer on the surface of the guide column 9;
[0067] Step 6: Perform jacking construction on the fixed floor slab 7 according to the jacking construction method in the background technology.
[0068] Because of the coordination between the guide column 9 and the limit opening 11, if the jacking slab 6 undergoes horizontal displacement during the jacking construction, since the gap between the limit opening 11 and the guide column 9 is smaller than the displacement distance allowed by the jacking slab 6, the displacement of the jacking slab 6 can be limited through this system, making the building jacking construction safer.
[0069] In addition, the guide column 9, the limiting beam 10, the limiting hoop 15 and other structures in the system are all formed by splicing I-beams or channel steels, so the system can be conveniently spliced and formed at the construction site.
[0070] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A displacement control system for jacking construction, arranged on two adjacent floors, wherein the upper floor is a jacking floor (6) and the lower floor is a fixed floor (7), characterized in that: The invention comprises a through hole (8) opened on a jacking floor (6), wherein the through holes (8) are at least two, and a guide column (9) is arranged in the through hole (8), wherein the lower end of the guide column (9) is fixedly connected to the fixed floor (7), and the upper end of the guide column (9) passes through the through hole (8); a plurality of limit beams (10) are fixed to the upper surface of the jacking floor (6) in the horizontal and vertical directions, and the plurality of limit beams (10) are staggered to form a limit hole (11), and the opening range of the limit hole (11) is within the opening range of the through hole (8); The guide column (9) is a frame structure including a plurality of vertical poles (18) and a cross bar (19), wherein the vertical poles (18) are four and are distributed in a rectangular shape, and the cross bar (19) connects adjacent vertical poles (18); A plurality of inclined rods (20) are arranged inside the guide column (9), and the diagonal vertical rods (18) at both ends of the inclined rods (20) are connected; There is a gap between the guide column (9) and the limiting beam (10), and a lubricating layer is provided on the outer surface of the guide column (9); A pad (23) is provided at the lower end of the vertical rod (18), and bolts (25) are provided on the upper surface of the pad (23) at intervals around the pad (23), and the bolts (25) pass through the pad (23) and are connected to the fixed floor slab (7); A fixing plate (26) is arranged on the pad (23); one end of the fixing plate (26) is connected to the vertical rod (18), and the other end is connected to the pad (23).
2. A jacking construction displacement control system according to claim 1, characterized in that: The lower surface of the lifting floor (6) is provided with a floor beam (14); the limiting beam (10) and the floor beam (14) are arranged in an alternating manner, and the intersecting positions of the floor beam (14) and the limiting beam (10) are fixedly connected by a limiting hoop (15); the limiting hoop (15) surrounds the limiting beam (10) and passes through the lifting floor (6) to be fixed to the limiting beam (10).
3. A jacking construction displacement control system according to claim 1, characterized in that: The vertical pole (18) and the limiting beam (10) are I-beams; and the horizontal pole (19) is a channel steel.
4. A jacking construction displacement control system according to claim 3, characterized in that: The lower surface of the pad (23) is provided with a protrusion (24) extending into the fixed floor slab (7).
5. A displacement control method in jacking construction, using a jacking construction displacement control system according to any one of claims 1 to 4, characterized in that: The construction steps include the following: Step 1: Open four through openings (8) on the jacking floor (6); Step 2: Arranging a limiting beam (10) on the upper surface of the jacking floor (6) and forming a limiting opening (11); Step 3: Setting a limiting hoop (15) to fix the limiting beam (10); Step 4: Splice to form a guide column (9), and fix the lower end of the guide column (9) on the fixed floor slab (7), and let the upper end of the guide column (9) pass through the through opening (8) and the limit opening (11); Step 5: brushing the surface of the guide post (9) to form a lubricating layer; Step 6: Perform jacking construction on the jacking floor (6).
Citation Information
Patent Citations
Construction method for carrying out pile sinking based on floating walking platform
CN105625425A
Liftable construction platform and assembly type building and construction method of liftable construction platform
CN106869473A
Method and device for transforming first floor into shopping mall by wholly jacking building
CN109930858A
Lateral limiting method for brick-concrete structure house jacking inclination rectification
CN110107114A
Jacking guide device of top formwork system
CN204356905U