A socket-type underground conveying device for filling tailings paste
By designing a socket-type underground conveying device, including drilled casings, slurry filling pipes and underground chambers, the problems of wear and leakage of traditional tailings paste filling slurry conveying pipes and difficulty in drilling replacement have been solved, and the slurry has been realized Non-destructive replacement of filling tubes and permanent use of drilled holes reduces filling costs.
Patent Information
- Application Number
- CN202010463535.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-27
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2040-05-27
AI Technical Summary
Traditional tailings paste filling slurry transportation pipelines are prone to wear and leakage during long-term use, and because they are directly assembled with the boreholes, they cannot be replaced without damaging the boreholes, resulting in high construction costs and easy scrapping of the boreholes.
A socket-type underground conveying device is designed, including a drilling casing, a slurry filling pipe and an underground chamber. It adopts a lifting mechanism and a damping ring, a slurry buffer cavity and a flange connection. The drilling casing and the slurry are connected The filling pipe is fixed through a cement layer, allowing the slurry filling pipe to be replaced without damaging the borehole.
It realizes the non-destructive replacement of the slurry filling pipe, avoids the scrapping of the drilling hole, reduces the filling cost, and protects the drilling hole and pipeline through the cement layer and buffer cavity, extending the service life of the equipment.
Smart Images

Figure CN111456806B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of underground conveying pipelines for filling tailing paste, and in particular to a sleeve-type underground conveying device for filling tailing paste. Background Art
[0002] In the process of development and utilization of mineral resources, a large amount of solid waste is bound to be generated. Mines can reduce the occurrence of underground empty lot collapse accidents and the pollution of waste to the environment by refilling the remaining solid waste into the underground empty lot. Paste filling mainly refers to the technology of mixing one or more solid wastes, cement and water in a certain proportion under certain conditions to prepare a paste-like slurry with certain stability, fluidity and plasticity, and then transporting it to the underground goaf in the form of a plunger flow under the action of external force or gravity through a pipeline to complete the filling operation. Paste filling technology provides the best way to dispose of solid waste. It not only turns solid waste into treasure, but also the filling body provides support for the goaf, ensures the safety of the mining process, reduces the loss and depletion of ore, and improves the utilization rate of mineral resources.
[0003] During the paste filling process, the traditional tailings paste filling slurry underground transportation pipeline structure often adopts a single-layer transportation pipeline structure, that is, after drilling, a slurry filling pipe for slurry transportation is directly laid in the borehole. The disadvantages of this method are: during the slurry filling process, the paste slurry is eroded and cavitated in the slurry filling pipe for a long time, which can easily cause the slurry filling pipe to leak due to wear and damage (generally, when the existing slurry filling pipe is designed with a universal caliber, it can meet the normal flow rate of paste slurry ≤ 300,000 cubic meters. When it exceeds this value, the pipeline will usually experience wear and leakage). Since the existing slurry filling pipe is directly assembled with the borehole, the two are squeezed and fixed to each other. Therefore, the slurry filling pipe cannot be replaced without destroying the borehole, which in turn affects the normal filling of the paste slurry. To restore the paste filling, it is necessary to drill holes again and lay pipelines. However, the drilling construction of tailings paste filling often requires advanced screw directional drilling + drilling measurement technology due to its high construction accuracy requirements (error value ≤ 1°). The construction cost is high, with a unit price of more than 2,500 yuan / meter. Once the drilling is scrapped, it will cause huge losses to the mine, and the losses often exceed one million yuan. Summary of the invention
[0004] In view of this, the purpose of the present invention is to provide a sleeve-type underground conveying device for tailings paste filling, so as to achieve the replacement of the slurry filling pipe without damaging the borehole, ensuring that the borehole can be used permanently, thereby saving filling costs.
[0005] The present invention solves the above-mentioned problem through the following technical means: a socket-type underground conveying device for tailings paste filling, comprising a borehole casing fixedly socketed with a borehole and a slurry filling pipe socketed with the borehole casing, the top of the slurry filling pipe is lifted by a lifting mechanism, an underground chamber is constructed at the lower part of the borehole, a slurry buffer chamber is arranged in the underground chamber, the slurry buffer chamber is connected to the bottom of the slurry filling pipe through a flange, and one side of the slurry buffer chamber is connected to the underground filling pipe through a flange.
[0006] Furthermore, a vibration damping ring is provided between the drilling casing and the slurry filling pipe.
[0007] Furthermore, the vibration damping ring is a wear-resistant rubber vibration damping ring.
[0008] Furthermore, a lifting mechanism is provided on both sides of the slurry filling pipe, and the lifting mechanism includes a lifting cylinder, a support plate connected to the piston rod of the lifting cylinder, and a support screw horizontally passing through the support plate. The support screw is rotatably sleeved with the support plate. Both sides of the slurry filling pipe are provided with a plurality of threaded holes spaced apart in parallel along the vertical direction. The threaded holes do not penetrate the side wall of the slurry filling pipe, and the support screws on both sides are respectively threadedly connected to one of the threaded holes on the corresponding side.
[0009] Furthermore, the lifting cylinder is a lifting oil cylinder or a lifting air cylinder.
[0010] Furthermore, a cement layer is filled between the inner wall of the borehole and the outer wall of the borehole casing.
[0011] Furthermore, a protruding structure is formed at the threaded hole to increase the wall thickness of the slurry filling tube.
[0012] Furthermore, the drilling casing, slurry filling pipe and downhole filling pipe are all welded by multiple pipe sections.
[0013] Beneficial effects of the present invention:
[0014] The present invention provides a sleeve-type underground conveying device for tailing paste filling, comprising a borehole casing fixedly sleeved with a borehole and a slurry filling pipe sleeved with the borehole casing, the top of the slurry filling pipe is lifted by a lifting mechanism, an underground chamber is constructed at the lower part of the borehole, a slurry buffer chamber is arranged in the underground chamber, the slurry buffer chamber is connected with the bottom of the slurry filling pipe through a flange, and one side of the slurry buffer chamber is connected with the underground filling pipe through a flange. The sleeve-type underground conveying device for tailing paste filling of the present application adopts a structural form in which the borehole casing and the slurry filling pipe are sleeved, the slurry filling pipe is not directly assembled with the borehole, when the slurry filling pipe is worn and leaked, the slurry filling pipe can be replaced without damaging the borehole, during the entire filling process, the borehole and the borehole casing are in an intact state, avoiding the risk of scrapping the borehole, no need to construct a spare borehole, the filled borehole can be used permanently, and the filling cost is greatly saved.
[0015] In addition, the advantages of this application are as follows:
[0016] 1. A cement layer is filled between the outer wall of the borehole casing and the inner wall of the borehole. The cement layer can not only reliably fix the borehole casing, but also play a good role in protecting the borehole wall and preventing the collapse of the borehole. 2. The slurry buffer chamber can buffer the flow of the paste slurry, avoiding the impact and wear of the slurry on the downhole filling pipe. 3. The filling pipe lifting device can remove and replace the worn slurry filling pipe from the borehole casing. During the removal process, the borehole will not be damaged under the protection of the borehole casing and the cement layer, avoiding the scrapping of the borehole. 4. The vibration damping ring avoids the rigid friction between the borehole casing and the slurry filling pipe caused by vibration. 5. The borehole casing, slurry filling pipe and downhole filling pipe are all welded by multiple sections of pipes. The welding method is full welding after beveling, which is safer and has a longer service life than the traditional threaded connection. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0018] Figure 1 It is a structural schematic diagram of the present invention. DETAILED DESCRIPTION
[0019] The present invention will be described in detail below with reference to the accompanying drawings. Figure 1As shown: a sleeve-type underground conveying device for tailing paste filling, including a borehole casing 1 fixedly sleeved with a borehole and a slurry filling pipe 3 sleeved with the borehole casing 1, a cement layer 2 is filled between the inner wall of the borehole and the outer wall of the borehole casing, the cement layer 2 can not only reliably fix the borehole casing 1, but also play a good wall protection role for the borehole to prevent the inside of the borehole from collapsing. A vibration damping ring 4 is arranged between the borehole casing 1 and the slurry filling pipe 3, the vibration damping ring is a wear-resistant rubber vibration damping ring, the vibration damping ring 4 is sleeved on the slurry filling pipe 3, and the vibration damping ring avoids the rigid friction between the borehole casing and the slurry filling pipe caused by vibration.
[0020] A downhole chamber 6 is constructed at the lower part of the borehole to facilitate maintenance, inspection and disassembly of downhole pipelines; a slurry buffer chamber 8 is arranged in the downhole chamber 6, and the slurry buffer chamber 8 is connected to the bottom of the slurry filling pipe 3 through a flange 5, and one side of the slurry buffer chamber 8 is connected to the downhole filling pipe 7 through a flange. The slurry buffer chamber 8 is an enlarged cavity structure. When the slurry is vertically poured, its flow rate is relatively large under the action of gravity, and the slurry buffer chamber can buffer the flow of the paste slurry, slow down its flow rate, and avoid the impact and wear of the slurry on the downhole filling pipe.
[0021] The top of the slurry filling pipe 3 is lifted by a lifting mechanism. During the slurry filling process, the lifting mechanism lifts, supports and bears the weight of the slurry filling pipe. When the slurry filling pipe needs to be replaced, the lifting mechanism can lift and remove the slurry filling pipe. In this embodiment, a lifting mechanism is provided on both sides of the slurry filling pipe, and the lifting mechanism includes a lifting cylinder 9, a support plate 11 connected to the piston rod of the lifting cylinder 9, and a support screw 10 passing through the support plate 11 horizontally. The lifting cylinder 9 is a lifting oil cylinder or a lifting air cylinder, and the support screw 10 is rotatably sleeved with the support plate 11; a plurality of threaded holes are arranged in parallel and spaced apart along the vertical direction on both sides of the slurry filling pipe 3, and preferably, the threaded holes on both sides correspond to each other in the height direction; the threaded holes do not penetrate the side wall of the slurry filling pipe to avoid leakage at the threaded holes during the slurry filling process, and a protruding structure 13 is formed at the threaded holes to increase the wall thickness of the slurry filling pipe to ensure the strength of the slurry filling pipe; the support screws 10 on both sides are respectively threadedly connected to one of the threaded holes on the corresponding side. In the specific design, the size of the support screw is reasonably designed so that it can bear the weight of the slurry filling pipe. During the specific lifting, after the slurry filling pipe 3 is inserted into the drilling casing 1 to a suitable height by a crane, the supporting screws 10 on both sides are rotated to be threadedly connected with the threaded holes at the corresponding heights respectively, and the slurry filling pipe 3 can be firmly supported by the supporting screws 10, the support plate 11 and the lifting cylinder 9; when the slurry filling pipe 3 is worn and leaks and needs to be replaced, the flange between the slurry filling pipe 3 and the slurry buffer chamber 8 is first disconnected, and then the lifting cylinders 9 on both sides are extended to make the slurry filling pipe rise a certain distance, and then the supporting screw 10 on one side is separated from the corresponding threaded hole (the slurry filling pipe is only supported by the supporting screw on the other side), and The corresponding lifting cylinder 9 drives the support screw to move downward so that it is threadedly connected with the corresponding threaded hole on the lower side, and then adjusts the support screw 10 on the other side so that it is also threadedly connected with the corresponding threaded hole on the lower side (similarly, during the adjustment process, the slurry filling pipe 3 is also supported by the support screw on the other side). After the support screws on both sides are adjusted to be threadedly connected with the threaded holes corresponding to the lower side, the next round of lifting of the slurry filling pipe can be driven by the lifting cylinder 9. Each round of lifting causes the slurry filling pipe 3 to rise by the spacing distance of adjacent threaded holes. In this way, after multiple rounds of adjustment and lifting, the slurry filling pipe can be lifted out of the drilling casing. Compared with the winch lifting mechanism, the lifting mechanism has a simple structure and low cost. It can not only ensure the stability of the lifting process, but also realize the lifting of a longer slurry filling pipe in a single small stroke, which is conducive to improving the convenience of disassembly after lifting, so it has great creativity and practical value.
[0022] The drilling casing 1, slurry filling pipe 3 and downhole filling pipe 7 are all welded from multiple sections of pipes, and the welding method is a full welding method after beveling, which is safer and has a longer service life than traditional threaded connections.
[0023] During specific filling, the slurry filling pipe 3 is connected with the surface filling pipe 12, and the slurry flows into the slurry filling pipe 3 through the surface filling pipe 12, and then flows through the slurry buffer chamber 8 and the downhole filling pipe 7 in sequence before flowing into the area to be filled.
[0024] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A method for lifting a slurry filling pipe of an underground conveying device for filling tailing paste, characterized in that: The underground conveying device includes a borehole casing fixedly sleeved with the borehole and a slurry filling pipe sleeved with the borehole casing, the top of the slurry filling pipe is lifted by a lifting mechanism, an underground chamber is constructed at the lower part of the borehole, a slurry buffer chamber is arranged in the underground chamber, the slurry buffer chamber is connected to the bottom of the slurry filling pipe through a flange, and one side of the slurry buffer chamber is connected to the underground filling pipe through a flange; A vibration damping ring is provided between the drilling casing and the slurry filling pipe; The vibration damping ring is a wear-resistant rubber vibration damping ring; Both sides of the slurry filling pipe are provided with a lifting mechanism, the lifting mechanism includes a lifting cylinder, a support plate connected to the piston rod of the lifting cylinder, and a support screw rod horizontally passing through the support plate, the support screw rod is rotatably sleeved with the support plate, and both sides of the slurry filling pipe are provided with a plurality of threaded holes spaced in parallel along the vertical direction, the threaded holes do not penetrate the side wall of the slurry filling pipe, and the support screw rods on both sides are respectively threadedly connected with one of the threaded holes on the corresponding side; The lifting process of the slurry filling pipe is as follows: the top of the slurry filling pipe is lifted by a lifting mechanism. Specifically, when lifting, the slurry filling pipe is inserted into the drilling casing to a suitable height by a crane, and then the supporting screws on both sides are rotated to make them threadedly connected with the threaded holes of corresponding heights respectively, so that the slurry filling pipe can be firmly supported by the supporting screws, the supporting plate and the lifting cylinder; when the slurry filling pipe is worn and leaks and needs to be replaced, the flange between the slurry filling pipe and the slurry buffer chamber is first disconnected, and then the lifting cylinders on both sides are extended to make the slurry filling pipe rise a certain distance, and then the supporting screw on one side is separated from the corresponding threaded hole, and the slurry filling pipe only relies on the other side to fill the slurry. The support screw on one side is supported and driven downward by the corresponding lifting cylinder to be threadedly connected with the corresponding threaded hole on the lower side. Then the support screw on the other side is adjusted to be threadedly connected with the corresponding threaded hole on the lower side. Similarly, during the adjustment process, the slurry filling pipe is also supported by the support screw on the other side. After the support screws on both sides are adjusted to be threadedly connected with the corresponding threaded holes on the lower side, the next round of lifting of the slurry filling pipe can be achieved by driving the lifting cylinder. Each round of lifting makes the slurry filling pipe rise the interval distance between adjacent threaded holes. In this way, after multiple rounds of adjustment and lifting, all the slurry filling pipes can be lifted out of the drilling casing.
2. The method for lifting a slurry filling pipe of an underground conveying device for filling tailing paste according to claim 1, characterized in that: The lifting cylinder is a lifting oil cylinder or a lifting air cylinder.
3. The method for lifting a slurry filling pipe of an underground conveying device for filling tailing paste according to claim 2, characterized in that: A cement layer is filled between the inner wall of the borehole and the outer wall of the borehole casing.
4. The method for lifting a slurry filling pipe of an underground conveying device for filling tailing paste according to claim 3, characterized in that: A protruding structure is formed at the threaded hole to increase the wall thickness of the slurry filling pipe.
5. The method for lifting a slurry filling pipe of an underground conveying device for filling tailing paste according to claim 4, characterized in that: The drilling casing, slurry filling pipe and downhole filling pipe are all welded by multiple pipe sections.
Citation Information
Patent Citations
Pressure relief device and method for underground filling and pipe plugging and underground filling system
CN108643963A
Novel wire feeder lifting mechanism
CN210596145U
Sleeving type underground conveying device for tailing paste filling
CN212154858U