A power project contract monitoring system and method
Through the data source, integration, storage and analysis modules of the power project contract monitoring system, the contract payment situation is automatically tracked and analyzed, which solves the problem of payment anomalies in power enterprise contract management, improves the accuracy and rationality of management, and reduces costs. waste.
Patent Information
- Application Number
- CN202010975718.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-16
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2040-09-16
AI Technical Summary
Electric power companies lack effective monitoring and analysis tools in contract management, resulting in untimely contract payments and problems of overpayment, underpayment, early payment, and late payment, which increase costs and fail to effectively control contract performance risks.
A power project contract monitoring system is designed, including a data source module, a data integration module, a data storage module and a project early warning module. It obtains contract information from the ERP system through ETL data extraction technology, performs data integration, storage and analysis, and discovers contract payments. Abnormalities are automatically tracked and fed back to relevant departments.
Without manual intervention, the system can independently and accurately track and analyze power system contracts, solving the problems of heavy manual tracking workload and low accuracy, improving the rationality and accuracy of power grid project management, and reducing cost waste.
Smart Images

Figure CN112100264B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of smart grid informatization, and in particular relates to a power project contract monitoring system and method. Background Art
[0002] Power companies have many types of contracts, with complex classifications, complex contract management, and a lot of monitoring information. Due to the characteristics of power company equipment asset management, conventional power project contract monitoring methods mainly include manual verification and project mileage node monitoring.
[0003] However, these power project contract monitoring methods lack effective monitoring, analysis and management of the entire project life cycle from bidding to execution. In addition, due to the huge system of power enterprises, different management methods and systems used by different branches, inconsistent asset management information data of each system, and the lack of unified analysis and solutions for complex power grid asset data within the enterprise, the monitoring information of the payment of various project contracts of the State Grid Corporation is not timely, and there are problems such as "overpayment, underpayment", "early payment, delayed payment", and "payment when it should not be paid". Due to the delay in discovering problems in the contract payment link, the project management department only monitors the contract based on experience or reported data, which increases costs, causes serious waste, and cannot effectively control the risk of contract performance. Summary of the invention
[0004] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a power project contract monitoring system and method, which, after configuration and setting, can independently and accurately track and analyze power system contracts without human intervention; solve the current bottleneck of manual contract tracking, monitoring, analysis, and troubleshooting, which has a large workload and low accuracy, and improve the rationality and accuracy of power grid project management.
[0005] The technical solution adopted by the present invention to solve its technical problem is:
[0006] It includes data source module, data integration module, data storage module, data analysis module and project early warning module, wherein the data source module is connected with data integration, storage, analysis and early warning modules.
[0007] The data source module is the data source for analyzing and warning contracts. This module obtains contract information related to power projects from the data source (ERP system) through ETL data extraction technology. The information includes contract payment summary information, order payment details, material details, etc. The main functions include data source configuration and source data extraction control.
[0008] The data integration module: uses the data integration tool to integrate the contract payment summary information, order payment details and material details through the purchase order number and the control process of data integration. Integration method: Based on the contract payment summary table, relevant information is obtained by collecting the order number and associating it with the order payment details and material details.
[0009] The data storage module refers to a functional module for storing source detailed data, integration process data and result data. Storage method: using common database storage software for data storage.
[0010] The data analysis module is a process of analyzing and mining the execution of project contracts, providing data support for the business department to conduct root cause analysis. The analysis content includes: execution analysis by unit, execution analysis by project type, execution analysis by stage, execution analysis by time, late payment analysis, early payment analysis, overpayment analysis, underpayment analysis, etc.
[0011] The project early warning module: types of problems found during contract management and control, and how to deal with these problems. According to the monitoring rules, the "overpayment / underpayment" and "early payment / late payment" problems in the four payment links of the contract are found. After discovering the above problems, according to the project type described in the contract, the project contract information is fed back to the finance department and the project-related business department, and the project contract payment information is continuously tracked.
[0012] The present invention has the following beneficial effects and advantages:
[0013] The present invention can accurately track and analyze power system contracts independently and autonomously without human intervention, solving the bottleneck of heavy workload and low accuracy in current manual contract tracking, monitoring, analysis and troubleshooting, and improving the rationality and accuracy of power grid project management. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 A flow chart of a power project contract monitoring system provided by the present invention.
[0015] Figure 2 A flow chart of a power project contract monitoring method provided by the present invention.
[0016] Figure 3 A flow chart of a power project contract execution monitoring and analysis method provided by the present invention. DETAILED DESCRIPTION
[0017] The present invention is further described in detail below in conjunction with the embodiments.
[0018] The present invention provides a power project contract monitoring system, which comprises a data source module, a data integration module, a data storage module, a data analysis module and a project early warning module, wherein the data source module is connected with the data integration, storage, analysis and early warning modules.
[0019] The data source module is the data source for analyzing and warning contracts. This module obtains contract information related to power projects from the data source (ERP system) through ETL data extraction technology. The information includes contract payment summary information, order payment details, material details, etc. The main functions include data source configuration and source data extraction control.
[0020] The data integration module: uses the data integration tool to integrate the contract payment summary information, order payment details and material details through the purchase order number and the control process of data integration. Integration method: Based on the contract payment summary table, relevant information is obtained by collecting the order number and associating it with the order payment details and material details.
[0021] The data storage module refers to a functional module for storing source detailed data, integration process data and result data. Storage method: using common database storage software for data storage.
[0022] The data analysis module is a process of analyzing and mining the execution of project contracts, providing data support for the business department to conduct root cause analysis. The analysis content includes: execution analysis by unit, execution analysis by project type, execution analysis by stage, execution analysis by time, late payment analysis, early payment analysis, overpayment analysis, underpayment analysis, etc.
[0023] The project early warning module: types of problems found during contract management and control, and how to deal with these problems. According to the monitoring rules, the "overpayment / underpayment" and "early payment / late payment" problems in the four payment links of the contract are found. After discovering the above problems, according to the project type described in the contract, the project contract information is fed back to the finance department and the project-related business department, and the project contract payment information is continuously tracked.
[0024] In order to achieve the above object, another aspect of the present invention provides a power project contract monitoring system, the method comprising the following steps:
[0025] Step 1: Store basic contract information and contract execution information through the ERP system through business flow, data entry, etc. Basic contract information: provincial company name, provincial company code, municipal company code, municipal company name, project code, project name, project type, project category, purchase order number, supplier number, supplier name, payment terms, contract amount, contract payment ratio, production date, contract effective date, WBS code, WBS description, etc.
[0026] Contract payment information: provincial company name, provincial company code, project code, project name, fiscal year, accounting document number, accounting document line item, debit and credit identification, purchase order number, payment type, payment amount, payment date, WBS code, WBS description, line item, arrival date, arrival amount, material code, material name, receipt quantity, etc.
[0027] Step 2: Use the data extraction tool KETTLE to extract the contract payment summary table, order payment details table and material details table in the ERP system into the contract execution monitoring database.
[0028] Step 3: Through the data extraction tool KETTLE, the contract payment summary table, order payment detail table and material detail table in the contract execution monitoring database are integrated according to the wide table integration rules to form the contract payment summary wide table, order payment detail wide table and material detail wide table. The database table is associated through KETTLE software to query and merge data.
[0029] Based on the contract payment summary wide table, relevant information is obtained by collecting order numbers and associating them with the order payment detail table and the material detail table. The material detail table and the material code table are associated through the material code to form a material detail wide table.
[0030] Step 4: Store the integrated wide table data in the Oracle database.
[0031] Step 5: Use Tableau tools to monitor and analyze data based on the contract payment summary table, order payment detail table, and material detail table. Monitor contract non-compliance ("overpayment / underpayment" and "early payment / late payment"), and if there are any problems with the contract payment, promptly inform the business department to pay attention and make corrections.
[0032] The analysis methods include: execution analysis by unit, execution analysis by project type, execution analysis by link, execution analysis by time, late payment analysis, early payment analysis, overpayment analysis, underpayment analysis, etc., and it is concluded that the project contract should be given special attention, the corresponding links of the project should be given special attention, the project unit should be given special attention, etc.
[0033] The monitored data include: contract amount, contract payment ratio (advance payment ratio, delivery payment ratio, operation payment ratio, warranty payment ratio), actual amount of advance payment, actual amount of delivery payment, actual amount of operation payment, actual amount of operation payment, quantity of goods received, contract effective time, payment date;
[0034] When the payment type is "prepayment", if the payment amount is not equal to the contract amount * prepayment payment ratio, it is an "overpayment / underpayment" exception;
[0035] When the payment type is "Payment on Delivery", if the payment amount is not equal to the contract amount * payment ratio on delivery, it is an "Overpayment / Underpayment" exception;
[0036] When the payment type is "operation payment", if the payment amount is not equal to the contract amount * operation payment ratio, it is an "overpayment / underpayment" exception;
[0037] When the payment type is "warranty payment", if the payment amount is not equal to the contract amount * warranty payment ratio, it is an "overpayment / underpayment" exception;
[0038] For a project contract with materials, when the received quantity is blank, and the payment amount is greater than the contract amount*(advance payment ratio + delivery payment ratio), it is an "overpayment / underpayment" exception;
[0039] When the commissioning date is blank, and the payment amount is greater than the contract amount*(advance payment ratio + delivery payment ratio), it is an "overpayment / underpayment" exception;
[0040] When the commissioning date and the last payment date are in the same year, if the payment amount is greater than the contract amount*(advance payment ratio + delivery payment ratio + delivery payment ratio), it is an "overpayment / underpayment" exception;
[0041] When the advance payment is made before the effective date of the contract, it is considered early payment;
[0042] When the payment time is earlier than the arrival time of the goods, it is considered early payment;
[0043] When the payment time of commissioning payment is earlier than the project commissioning time, it is considered early payment;
[0044] When the warranty payment is made earlier than the warranty period, it is considered early payment.
[0045] Step 6: The alarm information generated by the monitoring is transmitted to the monitoring alarm display screen through the data interface, and the alarm instruction is issued. The on-duty personnel will report the non-compliance of the contract execution to each business department based on the alarm prompt information.
[0046] like Figure 1 As shown, the present invention provides a power project contract monitoring system and method, the system includes a data source module, a data integration module, a data storage module, a data analysis module, and a project early warning module, wherein the data source module is connected to the data integration, storage, analysis, and early warning modules.
[0047] The data source module is the data source for analyzing and warning contracts. This module obtains contract information related to power projects from the data source (ERP system) through ETL data extraction technology. The information includes contract payment summary information, order payment details, material details, etc. The main functions include data source configuration and source data extraction control.
[0048] The data integration module: The data integration module: Use the data integration tool to integrate the contract payment summary information, order payment details and material details through the purchase order number and the control process of data integration. Integration method: Based on the contract payment summary table, relevant information is obtained by collecting the order number and associating it with the order payment details and material details.
[0049] The data storage module refers to a functional module for storing source detailed data, integration process data and result data. Storage method: using common database storage software for data storage.
[0050] The data analysis module is a process of analyzing and mining the execution of project contracts, providing data support for the business department to conduct root cause analysis. The analysis content includes: execution analysis by unit, execution analysis by project type, execution analysis by stage, execution analysis by time, late payment analysis, early payment analysis, overpayment analysis, underpayment analysis, etc.
[0051] The project early warning module: types of problems found during contract management and control, and how to deal with these problems. According to the monitoring rules, the "overpayment / underpayment" and "early payment / late payment" problems in the four payment links of each contract are found. After discovering the above problems, according to the project type described in the contract, the project contract information is fed back to the financial department and the project-related business department, and the project contract payment information is continuously tracked.
[0052] like Figure 2 Another aspect of the present invention provides a method for monitoring a power project contract, the method comprising the following steps:
[0053] Step 1: Store basic contract information and contract execution information through business flow and data entry in the ERP system. Basic contract information: provincial company name, provincial company code, prefecture-level company code, prefecture-level company name, project code, project name, project type, project category, purchase order number, supplier number, supplier name, payment terms, contract amount, contract payment ratio, commissioning date, contract effective date, WBS code, WBS description, etc. Contract payment information:
[0054] Provincial company name, provincial company code, project code, project name, fiscal year, accounting document number, accounting document line item, debit and credit identification, purchase order number, payment type, payment amount, payment date, WBS code, WBS description, line item, arrival date, arrival amount, material code, material name, receipt quantity, etc.
[0055] Step 2: Use the data extraction tool KETTLE to extract the contract payment summary table, order payment details table and material details table in the ERP system into the contract execution monitoring database.
[0056] Step 3: Through the data extraction tool KETTLE, the contract payment summary table, order payment detail table and material detail table in the contract execution monitoring database are integrated according to the wide table integration rules to form the contract payment summary wide table, order payment detail wide table and material detail wide table. The database table is associated through KETTLE software to query and merge data.
[0057] Based on the contract payment summary table, relevant information is obtained by collecting the order number and associating it with the order payment details table and the material details table.
[0058] Table 1 Contract payment summary table
[0059]
[0060]
[0061]
[0062] 2. Order payment details wide table
[0063] Direct correspondence.
[0064] Table 2 Order payment details wide table
[0065]
[0066]
[0067] 3. Material details table
[0068] The material details table and the material coding table are associated through material coding to form a wide material details table.
[0069] Table 3 Material Details Wide Table
[0070]
[0071] Step 4: Store the integrated wide table data in the Oracle database.
[0072] Step 5: Based on the contract payment summary wide table, order payment detail wide table and material detail wide table, use the Tableau tool to carry out data monitoring and analysis.
[0073] Monitor contract non-compliance ("overpayment / underpayment" and "early payment / late payment"), identify contracts that currently have payment problems, and promptly inform the business department for attention and rectification.
[0074] Analysis: analysis of execution by unit, analysis of execution by project type, analysis of execution by link, analysis of execution by time, analysis of late payment, analysis of early payment, analysis of overpayment, analysis of underpayment, etc., to determine which project contracts should receive special attention, which links should receive special attention, which units should receive special attention, etc.
[0075] The monitored data include: contract amount, contract payment ratio (advance payment ratio, delivery payment ratio, operation payment ratio, warranty payment ratio), actual amount of advance payment, actual amount of delivery payment, actual amount of operation payment, actual amount of operation payment, quantity of goods received, contract effective time, payment date;
[0076] When the payment type is "prepayment", if the payment amount is not equal to the contract amount * prepayment payment ratio, it is an "overpayment / underpayment" exception;
[0077] When the payment type is "Payment on Delivery", if the payment amount is not equal to the contract amount * payment ratio on delivery, it is an "Overpayment / Underpayment" exception;
[0078] When the payment type is "operation payment", if the payment amount is not equal to the contract amount * operation payment ratio, it is an "overpayment / underpayment" exception;
[0079] When the payment type is "warranty payment", if the payment amount is not equal to the contract amount * warranty payment ratio, it is an "overpayment / underpayment" exception;
[0080] For a project contract with materials, when the received quantity is blank, and the payment amount is greater than the contract amount*(advance payment ratio + delivery payment ratio), it is an "overpayment / underpayment" exception;
[0081] When the commissioning date is blank, and the payment amount is greater than the contract amount*(advance payment ratio + delivery payment ratio), it is an "overpayment / underpayment" exception;
[0082] When the commissioning date and the last payment date are in the same year, if the payment amount is greater than the contract amount*(advance payment ratio + delivery payment ratio + delivery payment ratio), it is an "overpayment / underpayment" exception;
[0083] When the advance payment is made before the effective date of the contract, it is considered early payment;
[0084] When the payment time is earlier than the arrival time of the goods, it is considered early payment;
[0085] When the payment time of commissioning payment is earlier than the project commissioning time, it is early payment;
[0086] When the warranty payment time is earlier than the warranty period, it is considered early payment.
[0087] Step 6: The alarm information generated by the monitoring is transmitted to the monitoring alarm display screen through the data interface, and the alarm instruction is issued. The on-duty personnel will report the non-compliance of the contract execution to each business department based on the alarm prompt information.
Claims
1. A power project contract monitoring method, characterized in that: The method comprises the following steps: Obtain basic contract information and contract payment information through business flow and data entry in the ERP system; The contract payment summary table, order payment detail table and material detail table in the ERP system are extracted into the contract execution monitoring database through the data extraction tool KETTLE, and the contract payment summary table, order payment detail table and material detail table in the contract execution monitoring database are integrated according to the wide table integration rules to form a contract payment summary wide table, an order payment detail wide table and a material detail wide table, and the database tables are associated through the KETTLE software to perform data query and merging; based on the contract payment summary wide table, relevant information is obtained by collecting order numbers and associating them with the order payment detail table and the material detail table; Store the integrated wide table data in the Oracle database; Based on the contract payment summary table, order payment detail table and material detail table, use Tableau to monitor and analyze data; Inform other departments of any non-compliance in contract execution detected; The data monitored by using the tableau tool specifically include: contract amount, contract payment ratio, actual amount of advance payment, actual amount of delivery payment, actual amount of commissioning payment, actual amount of commissioning payment, quantity of goods received, contract effective time, payment date; among which, the contract payment ratio includes: advance payment ratio, delivery payment ratio, commissioning payment ratio, and warranty payment ratio; Use tableau tools to conduct analysis, including: execution analysis by unit, execution analysis by project type, execution analysis by stage, execution analysis by time, late payment analysis, early payment analysis, overpayment analysis, and underpayment analysis; The basic contract information includes: provincial company name, provincial company code, prefecture-level company code, prefecture-level company name, project code, project name, project type, project category, purchase order number, supplier number, supplier name, payment terms, contract amount, contract payment ratio, commissioning date, contract effective date, WBS code, and WBS description; The contract payment information: provincial company name, provincial company code, project code, project name, fiscal year, accounting document number, accounting document line item, debit and credit identification, purchase order number, payment type, payment amount, payment date, WBS code, WBS description, line item, arrival date, arrival amount, material code, material name, and receipt quantity; The contract payment summary broad table includes a broad table, a contract payment summary table, an order payment detail table, a material detail table, and a payment ratio description; wherein the broad table includes company information, project information, payment type, quantity received, payment amount, commissioning date, advance payment payment time, arrival payment time, commissioning payment time, and warranty payment time; The order payment details wide table includes a wide table and an order payment details table; wherein each attribute in the order payment details table corresponds to each attribute of the wide table in the contract payment summary wide table; the material details wide table includes a wide table, a material details table, and a material coding table; the material details table and the material coding table are associated through material coding to form a material details wide table; The data monitoring and analysis based on the contract payment summary wide table, the order payment detail wide table and the material detail wide table specifically includes the following steps: When the payment type is "Prepayment", if the payment amount is not equal to (Contract Amount * Prepayment Payment Ratio), it is an "Overpayment / Underpayment" exception; When the payment type is "Payment on Delivery", if the payment amount is not equal to (Contract Amount * Payment Ratio on Delivery), it is an "Overpayment / Underpayment" exception; When the payment type is "Operation payment", if the payment amount is not equal to (contract amount * operation payment ratio), it is an "overpayment / underpayment" exception; When the payment type is "Warranty Payment", if the payment amount is not equal to (Contract Amount * Warranty Payment Ratio), it is an "Overpayment / Underpayment" exception; For a project contract with materials, when the received quantity is blank, if the payment amount is greater than {contract amount*(advance payment ratio+delivery payment ratio)}, it will be an overpayment / underpayment exception; When the commissioning date is blank, and the payment amount is greater than {contract amount*(advance payment ratio+delivery payment ratio)}, it is an "overpayment / underpayment" exception; When the commissioning date and the last payment date are in the same year, if the payment amount is greater than {contract amount*(advance payment ratio + delivery payment ratio + delivery payment ratio)}, it is an "overpayment / underpayment" exception; When the advance payment is made before the effective date of the contract, it is considered early payment; When the payment time is earlier than the arrival time of the goods, it is considered early payment; When the payment time of commissioning payment is earlier than the project commissioning time, it is considered early payment; When the warranty payment is made earlier than the warranty period, it is considered early payment.
2. A power project contract monitoring system, characterized in that: The power project contract monitoring method according to claim 1 comprises: The data source module is used to obtain the contract information related to the power project from the data source; The data integration module is used to obtain the contract payment summary table, the order payment detail table and the material detail table based on the contract payment summary table by collecting the order number and associating it with the order payment detail table and the material detail table; The data storage module is used to store the contract information obtained from the data source, the integration process data and the result data of the data integration module; Data analysis module, used to analyze the execution of project contracts and provide data support for business departments to conduct root cause analysis; The project early warning module is used to find problems in the contract payment process and feedback the project contract information to other departments according to the project type described in the contract; The contract information includes contract payment summary information, order payment detail information, and material detail information.