Integrated Well Construction System Operation
By integrating the automated control of the well construction system, the problem of lack of communication between well site equipment is solved, efficient and safe operation of the well construction system is achieved, and the degree of automation and operating efficiency are improved.
Patent Information
- Application Number
- CN201980031045.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2018-03-09
- Filing Date
- 2019-03-11
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2039-03-11
AI Technical Summary
The lack of communication between wellsite equipment in existing well construction systems results in operators needing to manually monitor and control various subsystems, increasing costs and reducing operational speed, efficiency and safety.
Using the Integrated Well Construction System (IWCS), automated control of the well construction system is achieved through integrated control devices and communication networks, including fiber optic ring networks, programmable logic controllers and video feeds for real-time monitoring and automated operations.
It improves the automation level of well construction operations, reduces manual intervention, improves operation speed, efficiency and safety, and reduces costs.
Smart Images

Figure CN112105796B_ABST
Abstract
Description
[0001] CROSS-REFERENCE TO RELATED APPLICATIONS
[0002] This application claims priority to and the benefit of U.S. Provisional Application No. 62 / 640,976, filed on March 9, 2018, entitled “SYSTEM AND METHOD FOR CONTROLLING DRILLING OPERATIONS,” and U.S. Provisional Application No. 62 / 641,021, filed on March 9, 2018, entitled “SYSTEM AND METHOD FOR INTEGRATING MULTIPLE DRILLING EQUIPMENT INTO A SINGLE CONTROL NETWORK,” and U.S. Provisional Application No. 62 / 640,999, filed on March 9, 2018, entitled “SYSTEM AND METHOD FOR REAL-TIME ANALYSIS OF DRILLING OPERATIONS,” the entire disclosures of which are hereby incorporated by reference into this document. Background Art
[0003] Wells are typically drilled into the ground or seabed to recover natural deposits of oil, natural gas, and other materials trapped in underground formations. Such wells are drilled into underground formations at the well site using a well construction system having various surface and underground well site equipment operating in a coordinated manner. The well site equipment can be divided into various subsystems, each of which performs different operations controlled by corresponding local and / or remotely located controllers. The subsystems may include, among other examples, a drilling rig control system, a fluid control system, a controlled pressure drilling control system, a gas monitoring system, a closed-circuit television system, a throttling pressure control system, and a well pressure control system.
[0004] Wellsite equipment is monitored and controlled by a control center located at the surface of the wellsite. A typical control center includes a wellsite control station, which is used by several human wellsite operators (e.g., drillers) to monitor and control the wellsite equipment. Although the equipment subsystems can operate in a coordinated manner, there is little communication between the subsystems and their controllers. Therefore, monitoring and control of the wellsite equipment or equipment subsystems can be performed through the corresponding control panel of the wellsite control station. Each control panel includes an associated video output device (e.g., a video monitor) and a plurality of input devices (e.g., buttons, switches, joysticks, etc.).
[0005] Because there is no communication between equipment subsystems, the interaction and coordination between various wellsite equipment is usually initiated by the wellsite operator. For example, the wellsite operator can monitor the equipment subsystems to identify operational and safety events, and manually implement processes to counteract such events. Therefore, a typical wellsite control center may be operated by multiple wellsite operators, each of which monitors and controls different wellsite equipment or equipment subsystems through a corresponding control panel. Relying on multiple wellsite operators to monitor and manually control wellsite equipment increases costs and limits the speed, efficiency and safety of well construction operations. Summary of the invention
[0006] This Summary is provided to introduce a selection of concepts that will be further described in the Detailed Description below. This Summary is neither intended to identify essential features of the claimed subject matter nor to be used to help limit the scope of the claimed subject matter.
[0007] The present disclosure introduces an integrated well construction system (IWCS), which is operable to construct a well through integrated control of integrated control devices that collectively control integrated subsystems of the IWCS. The IWCS includes: an IWCS communication network; the integrated control devices, each of which is directly connected to the IWCS communication network; the integrated subsystems; and a control workstation, which is directly connected to the IWCS communication network and is operable to control each of the integrated control devices, thereby controlling the integrated subsystems.
[0008] The present disclosure also introduces a control workstation, which is directly connected to a communication network and is operable to control each of a plurality of integrated control devices, each of which is directly connected to the communication network. Each integrated control device controls a corresponding component of an IWCS, whereby control of the integrated control device controls the IWCS through operation of the control workstation.
[0009] The present disclosure also introduces a computer program product, which includes a tangible, computer-readable, non-transitory medium on which instructions are stored for: automatically controlling an integrated control device of an integrated subsystem of an IWCS to execute a combination of predetermined operation sequences for constructing a well; receiving a selection of one of the operation sequences to be executed by the IWCS by operation of a control workstation by a human operator; receiving a setting of a first machine of the IWCS to be operated during the selected operation sequence by the human operator through operation of the control workstation; and in response to the human operator receiving a single start input through operation of the control workstation, automatically starting and controlling the first machine and the second machine of the IWCS using the received setting to execute the selected operation sequence.
[0010] The present disclosure also introduces a method, the method comprising operating an IWCS comprising a fiber optic ring network. The nodes of the fiber optic ring network include: programmable logic controllers (PLCs) forming various mechanical pieces of the IWCS; video feeds; drilling operator controls; advanced monitoring; and combinations thereof.
[0011] The present disclosure also introduces an apparatus, the apparatus comprising a communication network and integrated control devices each directly connected to the communication network. Each integrated control device controls a corresponding component of an IWCS. The IWCS is operable to perform well construction without other components that are not controlled by any of the integrated control devices. The apparatus also includes a control workstation that is directly connected to the communication network and is operable to control each of the integrated control devices to control the IWCS.
[0012] The present disclosure also introduces an apparatus, the apparatus comprising a communication network and integrated control devices each directly connected to the communication network. The integrated control devices control corresponding IWCS components. The IWCS components, except for any component not controlled by any of the integrated control devices, can operate together for construction of a well. The apparatus also includes a control workstation, the control workstation being directly connected to the communication network and operable to control each of the integrated control devices and thereby control the IWCS.
[0013] The present disclosure also introduces an apparatus comprising a communication network and integrated control devices each directly connected to the communication network. Each integrated control device controls a corresponding one or more of the integrated well construction components. The integrated well construction components form an integrated well construction system that can be operated to construct a well without any other components. A control workstation is directly connected to the communication network and can be operated to control each integrated control device, thereby controlling the integrated well construction components.
[0014] The present disclosure also introduces a method, which includes: causing a well construction system to perform a well construction operation, thereby automatically collecting and analyzing data associated with the well construction operation in real time to determine parameters based on the data, and at least some of the determined parameters are used to control the well construction operation.
[0015] The present disclosure also introduces a method, which includes: causing a well construction system to perform a well construction operation, thereby automatically collecting and analyzing data associated with the well construction operation in real time to determine parameters based on the data, and at least some of the determined parameters each provide a basis for triggering at least one real-time well construction operation alarm.
[0016] The present disclosure also introduces an apparatus, the apparatus comprising an analysis while drilling (AWD) control system utilized in conjunction with a well construction system during a well construction operation. The inputs to the AWD control system include: an expected configuration of a well to be constructed by the well construction system during the well construction operation; a configuration of a drill string used by the well construction system during the well construction operation; signals from a drilling parameter sensor; and drilling equipment parameters. Outputs of the AWD control system include real-time determinations of: depth and trajectory of the well; depth to bit; number of drill string tubulars and / or standpipes in the well; drill string volumes, displacements and weights; drilling fluid tank volumes and tank selection; drilling fluid losses and / or gains; mud supply tank volume differentials; mud supply tank cumulative volumes; total and / or per-segment strokes and / or strokes to be experienced by the drilling fluid pumping system; total stroke rate of the drilling fluid pumping system; drilling fluid pumping system liner capacity and efficiency; individual and overall drilling fluid flow rates into the well; annular drilling fluid velocity; total and / or per-segment drilling fluid volumes; total minutes per segment and / or minutes to be experienced; drilling fluid return; drill bit run time and revolutions; bit pressure; penetration rate; hook load and standpipe pressure. Outputs from the AWD control system may also include a well overflow calculator and a kill log. Outputs from the AWD control system may also include sensors and calculations for storage in historical data associated with the well construction system. Outputs from the AWD control system may also include well construction operation warnings and alarms.
[0017] The present disclosure also introduces an apparatus, which includes a control workstation, which is directly connected to a communication network and is capable of operating to control a plurality of control devices, each of which is directly connected to the communication network. Each control device controls a corresponding component of an IWCS, whereby control of the control device controls the IWCS through operation of the control workstation. The control workstation includes a display, a processor, and a memory, the memory storing: a construction program that controls each control device when executed by the processor; and an AWD program. The inputs to the AWD system include: an expected configuration of a well constructed by a well construction system during a well construction operation; a configuration of a drill string used by the well construction system during a well construction operation; signals from a drilling parameter sensor; and drilling equipment parameters. The AWD program, when executed by the processor, generates in real time and displays in real time in an AWD screen on the display one or more of the following: a graphical display of the expected and / or actual configuration of the well, including depth; a graphical display of the shoe in the well; an animation of the expected and actual configuration of the well; an animation of the drill string in the well; text and / or graphical displays of values for drilling fluid front tracking and / or depth; annular velocity for each section; open hole volume; total strokes and minutes, strokes and minutes to be experienced, and volume for one or more of the following: surface to drill bit, drill bit to shoe, drill bit to blowout preventer, drill bit to surface; well circulation; full cycle; drill string displacement, open end and closed end; drill string weight; number of tubulars in the well; effective volume; drilling fluid flow rate into the well; drill bit revolutions; and drill bit run time.
[0018] The present disclosure also introduces an apparatus including a control workstation for use with an IWCS. The IWCS is operable to construct a well through integrated control of integrated control devices of integrated subsystems that jointly control the IWCS. The control workstation includes a human-machine interface (HMI), the human-machine interface including a display, a touch screen, a joystick, and a processing system, the processing system including a processor and a memory having a construction program thereon, the construction program, when executed by the processor: presents a setup wizard to a human operator of the control workstation, the setup wizard guiding the operator to input operating parameters for one or more well construction machines of the integrated subsystem to execute a well construction sequence; and controls the integrated control device and thereby controls the integrated subsystem to execute the well construction sequence based on the input operating parameters.
[0019] The present disclosure also introduces an apparatus, the apparatus comprising an IWCS operable to construct a well through integrated control of integrated control devices that collectively control integrated subsystems of the IWCS. The IWCS comprises a processing system, the processing system comprising a processor and a memory having a construction program thereon, the construction program, when executed by the processor: controls each integrated control device, and thus each integrated subsystem, during each of a plurality of predetermined operation sequences; and prevents collisions between machines of the IWCS.
[0020] The present disclosure also introduces a method, which includes: constructing a well using each of a plurality of automatically controlled well construction machines, the plurality of automatically controlled well construction machines including: a drawworks; an iron roughneck; a tongs handling vehicle; a tongs handling arm; a catwalk; a tubular delivery arm; a lower stabilizing arm; an upper tubular restraint; an intermediate tubular restraint; a lower tubular restraint; a top drive; a top drive elevator; a finger beam; a transfer bridge pipe racker; a stand box guide arm; a rat hole; a rat hole; a drilling fluid pumping system; and a drilling fluid readjustment system.
[0021] The present disclosure also introduces a system that is operable to fully control each of a plurality of predetermined operational sequences of well construction operations. The sequences include: lifting a single tubular; making a drilling connection; building a tubular stand; running a drill collar stand; pulling out a drill collar stand; wet pulling; back reaming; moving a single tubular from the center of the well to a catway using a top drive; moving a tubular stand from the center of the well to the catway; moving casing from the catway to the center of the well using a casing tong; moving casing from the catway to the center of the well using a tubular delivery arm and a casing running tool; moving a large diameter casing from the catway to the center of the well using the top drive and the casing running tool; building a casing stand; and running a casing stand without using the casing running tool.
[0022] These and other aspects of the present disclosure are set forth in the following description, and / or may be learned by one of ordinary skill in the art by reading the materials herein and / or practicing the principles described herein.At least some aspects of the present disclosure may be achieved by the means recited in the appended claims. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] This disclosure is in conjunction with the attached Figure 1 The following detailed description will be best understood when read together. It should be emphasized that, according to standard practice in the industry, various features are not drawn to scale. In fact, the size of various features may be arbitrarily increased or reduced for clarity of discussion.
[0024] Figure 1 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure.
[0025] Figure 2 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure.
[0026] Figure 3 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure.
[0027] Figure 4 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure.
[0028] Figure 5 is a perspective view of at least a portion of an exemplary implementation of a device according to one or more aspects of the present disclosure.
[0029] Figure 6 According to one or more aspects of the present disclosure Figure 5 A perspective view of a portion of the device is shown.
[0030] Figure 7 According to one or more aspects of the present disclosure Figure 6 A top view of a portion of an exemplary implementation of a device is shown.
[0031] Figures 8 to 10 According to one or more aspects of the present disclosure, Figure 7 An exemplary implementation of software controls for a device display is shown.
[0032] Figures 11 to 21 According to one or more aspects of the present disclosure, Figure 7 An exemplary implementation of a screen displayed by the device is shown.
[0033] Fig. 22 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure.
[0034] Fig.23 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure.
[0035] Fig.24 is a schematic diagram of at least a portion of an exemplary implementation of a device or system according to one or more aspects of the present disclosure. DETAILED DESCRIPTION
[0036] It should be understood that the following disclosure describes many exemplary implementations of the different aspects presented herein. Specific examples of components and arrangements are described below to simplify the present disclosure. These are merely examples and are not intended to be limiting. In addition, the present disclosure may repeat figure numerals and / or letters in various examples. This repetition is for simplicity and clarity, and does not itself determine the relationship between the various implementations described herein. In addition, in the following description, the formation of a first feature on or on a second feature may include an implementation in which the first feature and the second feature are formed in direct contact, and may also include an implementation in which an additional feature between the first feature and the second feature may be formed so that the first feature and the second feature may not be in direct contact.
[0037] Figure 1 is a schematic diagram of at least a portion of an exemplary implementation of an integrated well construction system 100 (i.e., a drilling rig) according to one or more aspects of the present disclosure. The well construction system 100 represents an exemplary environment in which one or more aspects of the present disclosure described below may be implemented. Although the well construction system 100 is depicted as an onshore implementation, the aspects described below are also applicable to offshore implementations.
[0038] The well construction system 100 is depicted relative to a wellbore 102 formed by rotational and / or directionally drilling from a wellsite surface 104 and extending into a subterranean formation 106. The well construction system 100 includes surface equipment 110 located at the wellsite surface 104 and a drill string 120 suspended within the wellbore 102. The surface equipment 110 may include a mast, a derrick, and / or another support structure 112 disposed above a drill floor 114. The drill string 120 may be suspended from the support structure 112 within the wellbore 102. The support structure 112 and the drill floor 114 are jointly supported above the wellbore 102 by legs and / or other support structures 113.
[0039] The drill string 120 may include a bottom hole assembly (BHA) 124 and a device 122 for conveying the BHA 124 within the wellbore 102. The conveying device 122 may include drill pipe, heavy weight drill pipe (HWDP), wired drill pipe (WDP), and / or other devices for conveying the BHA 124 within the wellbore 102. The downhole end of the BHA 124 may include or be coupled to a drill bit 126. The rotation of the drill bit 126 and the weight of the drill string 120 operate together to form the wellbore 102. The drill bit 126 may be rotated from the wellsite surface 104 and / or by a downhole mud motor (not shown) connected to the drill bit 126.
[0040] The BHA 124 may also include various downhole tools 180, 182, 184. One or more of such downhole tools 180, 182, 184 may be or include an acoustic tool, a density tool, a directional drilling tool, an electromagnetic (EM) tool, a formation sampling tool, a formation testing tool, a gravity tool, a monitoring tool, a neutron tool, a nuclear tool, a photoelectric factor tool, a porosity tool, a reservoir characterization tool, a resistivity tool, a rotational velocity sensing tool, a sampling while drilling (SWD) tool, a seismic tool, a survey tool, a torsion sensing tool, and / or other measurement while drilling (MWD) or logging while drilling (LWD) tools.
[0041] One or more of the downhole tools 180, 182, 184 may be or include a MWD or LWD tool that includes a sensor package 186 operable to collect measurement data related to the BHA 124, the wellbore 102, and / or the formation 106. One or more of the downhole tools 180, 182, 184 and / or another portion of the BHA 124 may also include a telemetry device 187 operable to communicate with the surface equipment 110, such as via mud pulse telemetry. One or more of the downhole tools 180, 182, 184 and / or another portion of the BHA 124 may also include a downhole processing device 188 operable to receive, process, and / or store information received from the surface equipment 110, the sensor package 186, and / or other portions of the BHA 124. The processing device 188 may also store executable computer programs (eg, program code instructions) including instructions for implementing one or more aspects of the operations described herein.
[0042] The support structure 112 may support a drive, such as a top drive 116, which may be operatively connected (perhaps indirectly) to the uphole end of a conveyor 122 and impart a rotary motion 117 to a drill string 120 and a drill bit 126. However, another drive, such as a kelly and a rotary table (neither shown) may be utilized to impart the rotary motion 117 in place of or in addition to the top drive 116. The top drive 116 and the connected drill string 120 may be suspended from the support structure 112 by a lifting device, which may include a traveling block 118, a crown block (not shown), and a drawworks (DW) 119 storing a support cable or line 123. The crown block may be connected to or otherwise supported by the support structure 112, and the traveling block 118 may be coupled to the top drive 116, such as by a hook. The DW 119 may be mounted on or otherwise supported by the drill floor 114. The crown block and traveling block 118 include pulleys or sheaves around which the support line 123 passes to operatively connect the crown block, traveling block 118, and DW 119 (and possibly an anchor). The DW 119 can thus selectively apply tension to the support line 123 to raise and lower the top drive 116, thereby causing vertical movement 135. The DW 119 can include a drum, a frame, and a prime mover (e.g., an engine or motor) (not shown) that is operable to drive the drum to rotate and reel in the support line 123, thereby causing the traveling block 118 and the top drive 116 to move upward. The DW 119 can also be operated to reel out the support line 123 through controlled rotation of the drum, thereby causing the traveling block 118 and the top drive 116 to move downward.
[0043] The top drive 116 may include a grabber, a swivel (neither shown), a tubular handling assembly bail 127 terminating with an elevator 129, and a drive shaft 125 operatively connected to a prime mover (not shown), such as through a gearbox or transmission (not shown). The drill string 120 may be mechanically coupled to the drive shaft 125 with or without a saver joint between the drill string 120 and the drive shaft 125. The prime mover of the top drive 116 may selectively operate to rotate the drive shaft 125 and the drill string 120 coupled to the drive shaft 125. Thus, the top drive 116 and the DW 119 cooperate to advance the drill string 120 into the formation 106 to form the wellbore 102. The tubular handling assembly bail 127 and the elevator 129 of the top drive 116 may handle tubulars (e.g., drill pipes, drill collars, casing joints, etc.) that are not mechanically coupled to the drive shaft 125. For example, when the drill string 120 is lowered into or pulled out of the wellbore 102, the elevator 129 can grip a tubular of the drill string 120 so that the tubular can be raised and / or lowered by a lifting device that is mechanically coupled to the top drive 116. The grabber may include a clamp that clamps onto the tubular when tightening and / or loosening the connection of the tubular to the drive shaft 125. The top drive 116 may have a guide system (not shown), such as rollers that move up and down along guide rails on the support structure 112. The guide system can help align the top drive 116 with the wellbore 102 and prevent the top drive 116 from rotating during drilling by transmitting reaction torque to the support structure 112.
[0044] The well construction system 100 may also include a well control system for maintaining well pressure control. For example, the drill string 120 may be conveyed in the wellbore 102 through various blowout preventer (BOP) equipment, which is on the top of the wellbore 102 and may be set at the well site surface 104 below the drill floor 114. The BOP equipment is operable to control the pressure in the wellbore 102 through a series of pressure barriers (e.g., rams) between the wellbore 102 and the well site surface 104. The BOP equipment may include a BOP stack 130, an annular blowout preventer 132, and / or a rotation control device (RCD) 138 installed above the annular blowout preventer 132. The BOP equipment 130, 132, 138 may be installed on the top of the wellhead 134. The well control system may also include a BOP control unit 137 (i.e., a BOP closing unit) operatively connected to the BOP equipment 130, 132, 138 and operable to actuate, drive, operate, or otherwise control the BOP equipment 130, 132, 138. The BOP control unit 137 may be or include a hydraulic fluid power unit that is fluidly connected to the BOP equipment 130, 132, 138 and selectively operable to hydraulically drive various portions (e.g., gates, valves, seals) of the BOP equipment 130, 132, 138.
[0045] The well construction system 100 may also include a drilling fluid circulation system operable to circulate fluid between the surface equipment 110 and the drill bit 126 during drilling and other operations. For example, the drilling fluid circulation system may be operable to inject drilling fluid from the well site surface 104 into the wellbore 102 through an internal fluid passage 121 extending longitudinally through the drill string 120. The drilling fluid circulation system may include a pit, tank, and / or other fluid container 142 holding drilling fluid (i.e., mud) 140 and a pump 144 operable to move the drilling fluid 140 from the container 142 into the fluid passage 121 of the drill string 120 through a fluid conduit 146 extending from the pump 144 to the top drive 116 and an internal passage extending through the top drive 116. The fluid conduit 146 may include one or more of a pump discharge line, a riser, a rotary hose, and a gooseneck (not shown) connected to a fluid inlet of the top drive 116. The pump 144 and the container 142 may be fluidly connected via a fluid conduit 148, such as a suction line.
[0046] During drilling operations, drilling fluid may continue to flow downhole through the interior passage 121 of the drill string 120, as indicated by directional arrows 158. The drilling fluid may exit the BHA 124 through ports 128 in the drill bit 126 and then circulate uphole through an annular space (annulus) 108 of the wellbore 102 defined between the exterior of the drill string 120 and the wall of the wellbore 102, such flow occurring during the drilling of the wellbore. Figure 1 150 is indicated by directional arrow 159. In this manner, the drilling fluid lubricates the drill bit 126 and carries formation cuttings uphole to the well site surface 104. The returning drilling fluid may exit the annulus 108 through the bell guide nipple 139, the RCD 138, and / or a port adapter 136 (e.g., a sliding valve, a wing valve, etc.) located below one or more portions of the BOP stack 130.
[0047] Drilling fluid exiting the annulus 108 through the bell guide nipple 139 may be directed through a fluid conduit 145 (e.g., a gravity return line) to a drilling fluid reconditioning device 170 for purification and / or reconditioning, as described below, and then returned to the container 142 for recirculation. Drilling fluid exiting the annulus 108 through the RCD 138 may be directed into a fluid conduit 160 (e.g., a drilling pressure control line) and may pass through various wellsite equipment fluidly connected along the conduit 160 and then returned to the container 142 for recirculation. For example, the drilling fluid may pass through a choke manifold 162 (e.g., a drilling pressure control choke manifold) and then through the drilling fluid reconditioning device 170. The choke manifold 162 may include at least one choke valve and a plurality of fluid valves (neither shown) that may operate together to control flow through and out of the choke manifold 162. By variably restricting the flow of drilling fluid or other fluid flowing through the choke manifold 162, back pressure can be applied to the annulus 108. The greater the restriction to the flow through the choke manifold 162, the greater the back pressure applied to the annulus 108. The drilling fluid exiting the annulus 108 through the port adapter 136 can be directed into a fluid conduit 171 (e.g., a rig choke line) and can pass through various equipment fluidly connected along the conduit 171 and then return to the container 142 for recirculation. For example, the drilling fluid can pass through a choke manifold 173 (e.g., a rig choke manifold, a well control choke manifold, etc.) and then through the drilling fluid reconditioning equipment 170. The choke manifold 173 may include at least one choke valve and a plurality of fluid valves (neither shown) that can operate together to control the flow through the choke manifold 173. By variably restricting the flow of drilling fluid or other fluid flowing through the choke manifold 173, back pressure can be applied to the annulus 108.
[0048] Prior to returning to the container 142, the drilling fluid returned to the wellsite surface 104 may be purified and / or reconditioned by drilling fluid reconditioning equipment 170, which may include one or more of a liquid gas separator, a shale shaker, a centrifuge, and other drilling fluid purification equipment. The liquid gas separator may remove formation gas entrained in the drilling fluid discharged from the wellbore 102, and the shale shaker may separate and remove solid particles 141 (e.g., drill cuttings) from the drilling fluid. The drilling fluid reconditioning equipment 170 may also include equipment operable to remove additional gas and finer formation cuttings from the drilling fluid and / or modify the physical properties or characteristics (e.g., rheological properties) of the drilling fluid. For example, the drilling fluid reconditioning equipment 170 may include a degasser, a desander, a desilter, a mud washer, and / or a decanter, among other examples. Intermediate tanks / containers (not shown) may be used to hold the drilling fluid as it progresses through the various stages or portions of the drilling fluid reconditioning equipment 170. The purified / reconditioned drilling fluid may be transferred to a fluid container 142, solid particles 141 removed from the drilling fluid may be transferred to a solids container 143 (e.g., a reserve pit), and the removed gases may be transferred via a conduit 174 (e.g., a flare line) to a flare stack 172 for combustion or to a container (not shown) for storage and removal from the well site.
[0049] The surface equipment 110 may include tubular handling equipment operable to store, move, connect, and disconnect tubulars (e.g., drill pipes) to assemble and disassemble the delivery device 122 of the drill string 120 during drilling operations. For example, the catwalk 131 may be used to deliver tubulars from a ground level, such as along the well site floor 104, to the drill floor 114, allowing the tubular handling assembly lifting ring 127 to grab the tubulars and lift them above the wellbore 102 to connect with previously deployed tubulars. The catwalk 131 may have a horizontal portion 147 and a ramp or inclined portion 149, wherein the inclined portion extends between the horizontal portion and the drill floor 114. The catwalk 131 may include a slide 133 movable along a groove (not shown) that extends longitudinally along the horizontal and inclined portions of the catwalk 131. The slide 133 may be operable to deliver (e.g., push) tubulars along the catwalk 131 to the drill floor 114. The slide 133 may be driven along the groove by a drive system (not shown) such as a pulley system or a hydraulic system. In addition, one or more racks (not shown) may abut the horizontal portion of the catwalk 131. The rack may be a feed station (not shown), such as one that may have a spinner unit and / or other devices for transferring tubulars to the grooves of the catwalk 131.
[0050] An iron roughneck (RN) 151 may be located on the drill floor 114. The RN 151 may include a torque portion 153, which may include, for example, a spinner and a torque wrench including a lower jaw and an upper jaw. The torque portion 153 of the RN 151 may be moved toward and at least partially around the drill string 120, such as to allow the RN 151 to tighten and loosen a connection of the drill string 120. The torque portion 153 may also be moved away from the drill string 120, such as to allow the RN 151 to move away from the drill string 120 during drilling operations. The spinner of the RN 151 may be used to apply a low torque to tighten and loosen a threaded connection between tubulars of the drill string 120, and the torque wrench may be used to apply a higher torque to tighten and loosen a threaded connection. The system 100 may include more than one instance of the RN 151.
[0051] The reciprocating slips 161 may be located on the drill floor 114, such as to accommodate downhole tubulars passing therethrough during make-up and break-out operations and during drilling operations. The reciprocating slips 161 may be in an open position during drilling operations to allow the drill string 120 to be advanced therethrough, and may be in a closed position to clamp about an upper end of a conveying device 122 (e.g., an assembled tubular), such as to suspend the drill string 120 within the wellbore 102 and prevent the drill string 120 from being advanced within the wellbore 102 during make-up and break-out operations.
[0052] During drilling operations, the jacking equipment lowers the drill string 120 while the top drive 116 rotates the drill string 120 to advance the drill string 120 within the wellbore 102 and into the formation 106. During the advancement of the drill string 120, the reciprocating slips 161 are in an open position and the RN 151 moves away from the drill string 120 or otherwise leaves the drill string. When the upper portion of the tubular in the drill string 120 that is buckled to the drive shaft 125 approaches the reciprocating slips 161 and / or the drill floor 114, the top drive 116 stops rotating and the reciprocating slips 161 close to clamp the tubular that is buckled to the drive shaft 125. Then, the grabber of the top drive 116 clamps the upper portion of the tubular that is buckled to the drive shaft 125, and the drive shaft 125 rotates in the opposite direction to the drilling rotation to disconnect the connection between the drive shaft 125 and the buckled tubular. The grabber of the top drive 116 may then release the tubular from the drill string 120 .
[0053] A plurality of tubulars may be loaded on the racks of the catway 131, and each tubular may be transferred from the racks to the trench in the catway 131. The tubular positioned in the trench may be conveyed along the trench by the slide 133 until the end of the tubular protrudes above the drill floor 114. The elevator 129 of the top drive 116 may then grasp the protruding end, and the DW 119 may be operated to lift the top drive 116, the elevator 129, and the new tubular.
[0054] The lifting equipment then raises the top drive 116, elevators 129, and tubular until the tubular is aligned with the upper portion of the drill string 120 gripped by the slips 161. The RN 151 moves toward the drill string 120, and the lower jaws of the torque section 153 grip onto the upper portion of the drill string 120. The spin-down system rotates the new tubular into the upper portion of the drill string 120. The upper jaws then grip onto the new tubular and rotate at high torque to complete the tightening connection with the drill string 120. In this way, the new tubular becomes part of the drill string 120. The RN 151 is then released and moved away from the drill string 120.
[0055] The grabber of the top drive 116 may then be clamped onto the drill string 120. The drive shaft 125 (or a saver sub or other device extending from the drive shaft 125) is brought into contact with the drill string 120 and rotated to tighten the connection between the drill string 120 and the drive shaft 125. The grabber then releases the drill string 120, and the reciprocating slips 161 are moved to the open position. Drilling operations may then be resumed.
[0056] The tubular handling equipment may also include a pipe handling manipulator (PHM) 163 disposed in association with a vertical pipe rack 165 (or a stand of two or three tubulars) for storing tubulars 111. The vertical pipe rack 165 may include or support a finger beam (FIB) 166 defining a plurality of slots configured to support or otherwise retain the tubulars 111 within or on a stand box 164 (e.g., a platform or another area) located adjacent to, along, or below the drill floor 114. The FIB 166 may include a plurality of fingers (not shown), each associated with a corresponding slot and operable to close around and / or otherwise insert the respective tubular 111 therebetween to retain the tubular 111 within the corresponding slot of the stand box 164. The vertical pipe rack 165 may be connected to and supported by the support structure 112 or another portion of the wellsite system 100. The FIB 166 / pivot box 164 provides storage (e.g., temporary storage) of the tubulars 111 during various operations, such as during and between tripping and running down the drill string 120. The PHM 163 is operable to transfer the tubulars 111 between the FIB 166 / pivot box 164 and the drill string 120 (i.e., the space above the suspended drill string 120). For example, the PHM 163 may include an arm 167 terminating in a clamp 169, such as operable to grasp and / or clamp onto one of the tubulars 111. The arm 167 of the PHM 163 may extend and retract, and / or at least a portion of the PHM 163 may be capable of rotating and / or moving toward and away from the drill string 120, such as to allow the PHM 163 to transfer the tubulars 111 between the FIB 166 / pivot box 164 and the drill string 120.
[0057] The surface equipment 110 of the well construction system 100 may also include a control center 190, through which various parts of the well construction system 100, such as the top drive 116, the crane system, the tubular handling system, the drilling fluid circulation system, the well control system, and other examples of the BHA 124, may be monitored and controlled. The control center 190 may be located on the drilling floor 114 or at another location of the well construction system 100 (such as the well site surface 104). The control center 190 may include a facility 191 (e.g., a room, a cabin, a trailer, etc.) containing a control workstation 197, which may be operated by a human well site operator 195 to monitor and control various well site equipment or parts of the well construction system 100. The control workstation 197 may include or be communicatively connected to a processing device 192 (e.g., a controller, a computer, etc.), such as being operable to receive, process, and output information to monitor and / or control the operation of one or more parts of the well construction system 100. For example, the processing device 192 may be communicatively connected to the various surface and downhole equipment described herein, and may be operable to receive signals from such equipment or transmit signals to the equipment to perform the various operations described herein. The processing device 192 may store executable program code, instructions, and / or operating parameters or set points, including for implementing one or more aspects of the methods and operations described herein. The processing device 192 may be located within and / or outside the facility 191.
[0058] The control workstation 197 may be operable for inputting or otherwise communicating control commands to the processing device 192 by the wellsite operator 195, and for displaying or otherwise communicating information from the processing device 192 to the wellsite operator 195. The control workstation 197 may include a plurality of human-machine interface (HMI) devices, including one or more input devices 194 (e.g., keyboard, mouse, joystick, touch screen, etc.) and one or more output devices 196 (e.g., video monitor, touch screen, printer, audio speaker, etc.). Communication between the processing device 192, the input device 194, and the output device 196 and various wellsite equipment may be performed via wired communication devices and / or wireless communication devices. However, for clarity and ease of understanding, such communication devices are not depicted, and those of ordinary skill in the art will understand that such communication devices are within the scope of the present disclosure.
[0059] Well construction systems within the scope of the present disclosure may include, for example, those described above and Figure 1 More or fewer components than depicted. In addition, Figure 1 The various equipment and / or subsystems of the oil well construction system 100 shown may include, for example, those described above and Figure 1More or fewer components than depicted. For example, various engines, motors, hydraulics, actuators, valves, and / or other components not expressly described herein may be included in the well construction system 100 and be within the scope of the present disclosure.
[0060] Figure 2 is a schematic diagram of an exemplary implementation of a wellsite system 200, the wellsite system including a plurality of pipe handling equipment, each pipe handling equipment including or carrying one or more sensors operable to generate sensor measurements indicative of corresponding operating parameters (e.g., position, velocity, acceleration, etc.) of such equipment. According to one or more aspects of the present disclosure, various equipment pieces of the wellsite system 200 are operable to move the pipe 111 between various locations in the wellsite system 200 to perform the processes described herein, including the assembly and disassembly of the drill string 120. The wellsite system 200 may be formed Figure 1 A portion of the well construction system 100 shown and / or may be combined with Figure 1 The well construction system 100 is shown to operate as shown, including where indicated by the same numerals. Therefore, the following description collectively refers to Figure 1 and Figure 2 .
[0061] The wellsite system 200 may include a support structure 112 that supports various automated pipe handling equipment operable to transport tubulars 111 (e.g., drill pipe, stands of drill pipe, casing joints) between different areas of the wellsite system 200. The wellsite system 200 may also include a catwalk 131 operable to transport tubulars 111 from a storage area (not shown) at ground level (e.g., wellsite floor 104) to the drill floor 114.
[0062] The support structure 112 or another portion of the wellsite system 200 may support a tubular delivery arm (TDA) 202 that is operable to grab tubulars 111 from the FIB 166 and / or catwalk 131 one at a time and lift or otherwise move the tubulars 111 to a predetermined location. For example, the TDA 202 may move the tubulars 111 over the wellbore 102 so that the tubulars 111 are aligned with the wellbore center 203 over the reciprocating slips 161 and the fluid control equipment 213 (e.g., BOP equipment 130, 132, 138, etc. mounted on top of the wellhead 134) located below the drill floor 114. The TDA 202 may also move the tubulars 111 over a mousehole (MOH) 204 so that the tubulars 111 are aligned with the mousehole center 205, thereby allowing one or more tubulars 111 to be disposed therein so that two or more tubulars 111 may be coupled together to form a stand.
[0063] The TDA 202 may also move the tubular 111 to a thread oil application station or area 206 so that the tubular 111 may be prepared for a make-up operation by a cleaner / thread oil applicator device (thread oil applicator) 209. For example, the thread oil applicator 209 may apply thread oil to the pin end of the tubular 111 in preparation for make-up and / or may clean the pin end of the tubular 111 prior to transfer to the FIB 166 / pipe box 164. Thus, the thread oil applicator 209 may be positioned in conjunction with the thread oil application area 206, the MOH 204, and / or other areas, such as for performing a cleaning / thread oil application operation on the tubular 111 while it is being engaged by the TDA 202. The thread oil applicator 209 may also be positioned in conjunction with the TDA 202.
[0064] Portions of the TDA 202 may be operable to move horizontally and / or vertically, as indicated by arrows 208, such as to allow a gripper or clamp 210 of the TDA 202 to grip or otherwise receive a tubular 111 delivered to the drill floor 114 via the catwalk 131. The DW 119 may be operable to move the TDA 202 vertically along the support structure 112, as indicated by arrows 212. The DW 119 may be operatively connected to the TDA 202 via a support line 214 extending between the TDA 202 and a drum 216 of the DW 119.
[0065] One or more sensors 211 may be provided in association with the clamp 210, such as to allow the sensor 211 to generate a sensor signal indicating the presence or proximity of the tubular 111 received by the clamp 210. One or more sensors 218 may be provided in association with the DW 119, such as to allow the sensor 218 to generate a sensor measurement (e.g., an electrical sensor signal or data) indicating the rotational position of the reel 216. Such sensor measurements may also indicate the vertical position of the TDA 202 along the support structure 112. The TDA 202 may carry or include one or more sensors 220 operable to generate sensor measurements indicating the tension applied to the TDA 202 and, therefore, the weight supported by the TDA 202. The support structure 112 may also support a plurality of sensors 226, each located at a predetermined or other known reference position 221-224 (i.e., height) along the support structure 112. Such known reference positions 221-224 may be referred to as landmarks or targets in the oil and gas industry. Each sensor 226 is operable to generate a sensor signal indicative of the presence or proximity of the TDA 202 when the TDA 202 passes the sensor 226 , thereby indicating the corresponding known position 221 - 224 of the TDA 202 at such times.
[0066] The support structure 112 or another portion of the wellsite system 200 may also support a lower stabilizing arm (LSA) 228 operable to receive (e.g., snap) and stabilize a tubular 111 through a retaining device 230, which is supported by the TDA 202 and swung toward the support structure 112 after the tubular 111 is lifted from the catwalk 131. The LSA 228 may then pivot 231 to horizontally move 233 the tubular 111 to align the tubular 111 with the rathole center 205 or the thread compound application area 206. The retaining device 230 may extend (at least partially) around the tubular 111 to provide additional stability, such as during straightening prior to a make-up operation. The LSA 228 may carry or include one or more sensors 232 operable to generate sensor measurements indicating the stabilizing arm extension (i.e., length) and / or the angle 234 between the LSA 228 and the support structure 112 or a reference plane.
[0067] The support structure 112 or another portion of the wellsite system 200 may support a vertical frame 165 that includes or supports a FIB 166 that defines a plurality of slots configured to support or otherwise retain the tubular 111 within or on a stand box 164 that is located adjacent to, along, or below the drill floor 114. The support structure 112, vertical frame 165, or another portion of the wellsite system 200, such as a PHM 163, may support an upper tubular restraint (UTC) 242 and a lower tubular restraint (LTC) 244, each of which is operable to grasp a respective upper portion and lower portion of the tubular 111 via respective grabbers or clamps 246, 248. UTC 242 and LTC 244 may stabilize tubular 111 and / or horizontally move corresponding upper and / or lower portions of tubular 111 (as indicated by arrows 247 , 249 ) to align tubular 111 with rathole center 205 or thread compound application area 206 . The UTC 242 and the LTC 244 may also horizontally move corresponding upper and / or lower portions of the tubular 111 (as indicated by arrows 247, 249) to position the tubular 111 along a tubular transfer position (THP) 207, at which the TDA 202 may grab the tubular 111 and align it with the wellbore center 203 for connection to the drill string 120, or align the tubular 111 with a portion of a catwalk 131, thereby allowing the tubular 111 to be lowered onto the catwalk 131, which then moves the tubular 111 from the drill floor 114 to ground level (e.g., the wellsite floor 104). The THP 207 may be horizontally aligned with the thread compound application area 206, such as to allow the tubular 111 to be thread compounded and / or cleaned by the thread compound applicator 209 before the TDA 202 aligns the tubular along the wellbore center 203 for connection with the drill string 120 or positions the tubular 111 for lowering through the catwalk 131. The UTC 242 and LTC 244 may each carry or include one or more corresponding sensors 250, 252 operable to generate sensor measurements indicative of the extension or horizontal position 247, 249 of the corresponding clamp 246, 248.
[0068] The support structure 112, the vertical frame 165, or another portion of the wellsite system 200 may also support an intermediate tubular restraint (ITC) 236 operable to grasp the tubular 111 supported by the TDA 202 via a gripper or clamp 238, stabilize the tubular 111, and / or horizontally move 235 the tubular 111 to align the tubular 111 with the rathole center 205 or the thread compound application area 206. The ITC 236 may carry or include one or more sensors 240 operable to generate sensor measurements indicative of an extension or horizontal position 235 of the clamp 238.
[0069] The support structure 112, vertical rack 165, or another portion of the wellsite system 200 may also support a transfer bridge racker (TBR) 254 and a stand box guide arm (SGA) 262 that may operate together to store (e.g., hang, rack) tubulars 111 in the FIB 166 of the vertical rack 165 within or on the stand box 164. For example, the TBR 254 may be operable to grab an upper portion of the tubular 111 via a grabber or clamp 256 and move the tubular 111 horizontally and / or vertically between the FIB 166 and the THP 207, as indicated by arrows 258. The TBR 254 may carry or include one or more corresponding sensors 260 that may be operable to generate sensor measurements indicative of a horizontal and / or vertical position 258 of the clamp 256. The SGA 262 may be operable to grab a lower portion of the tubular 111 via a grabber or clamp 264 and guide the lower portion of the tubular 111 horizontally and / or vertically between the pipe box 164 and the THP 207, as indicated by arrow 266, in unison (i.e., synchronously) with the TBR 254. The SGA 262 may carry or include one or more corresponding sensors 268 operable to generate sensor measurements indicative of the horizontal and / or vertical position 266 of the clamp 264. When the tubular 111 is aligned with the THP 207, the TDA 202 may grab the tubular 111 and align it with the wellbore center 203 for connection with the drill string 120, or align the tubular with a portion of the catwalk 131, thereby allowing the tubular 111 to be lowered onto the catwalk 131.
[0070] The UTC 242, ITC 236, and LTC 244 may temporarily grasp tubulars 111 in the THP 207, such as while the TBR 254, SGA 262, and TDA 202 are performing other operations. One or more of the UTC 242, ITC 236, and LTC 244 may also be capable of extending to grasp tubulars 111 in the MOH 204 (or move tubulars 111 to the MOH 204). For example, tubulars 111 may be temporarily stored in the MOH 204 while waiting to be added to the drill string 120 or waiting to be transferred to the THP 207 and / or FIB 166 / stand box 164.
[0071] The catwalk 131 may include a slide 133 movable along a groove (not shown) extending longitudinally along the catwalk 131. The slide 133 may be driven along the groove by a drive system 270, such as a winch system including a reel 272 driven by a motor (not shown). The drive system 270 may be selectively operable to pull the slide 133 in opposite directions along the catwalk 131 via a line 274 extending between the reel 272 and the slide 133. Actuated by the drive system 270, the slide 133 may be operable to convey (e.g., push) the tubular 111 along the catwalk 131 to the drill floor 114. The slide 133 may move the box end of the tubular 111 into the clamp 210 of the TDA 202 so that the tubular 111 may be lifted by the TDA 202. The drive system 270 may carry or include one or more corresponding sensors 276 operable to generate sensor measurements indicative of the rotational position of the reel 272 and, therefore, the position of the slider 133 along the catwalk 131 .
[0072] Sensors 218, 276 may be or include, for example, encoders, rotary potentiometers, and / or rotary variable differential transformers (RVDTs). Sensor 220 may be or include, for example, strain gauges and / or load sensors. Sensors 211, 226 may be or include, for example, proximity sensors and Hall effect sensors. Sensors 232, 240, 250, 252, 260, 268 may be or include, for example, encoders, rotary potentiometers, linear potentiometers, or rotary variable differential transformers (RVDTs).
[0073] The present disclosure also provides various implementations of systems and / or methods for controlling one or more parts of the well construction system 100 and the wellsite system 200. Because the wellsite system 200 may form a part of the well construction system 100 and / or operate in conjunction with the well construction system 100, the well construction system 100 and the wellsite system 200 are collectively referred to as the well construction systems 100, 200 below. Figure 3is a schematic diagram of at least a portion of an exemplary implementation of a monitoring and control system 300 for monitoring and controlling various equipment, parts, and subsystems of a well construction system 100, 200 according to one or more aspects of the present disclosure. Figures 1 to 3 .
[0074] The control system 300 can communicate with the well construction system 100, 200 in real time and can be used to monitor and / or control the various parts, components and equipment of the well construction system 100, 200. The equipment of the well construction system 100, 200 can be grouped into several subsystems, each of which can be operated to perform a corresponding operation and / or a part of the well construction operation described herein. The subsystems can include, among other examples, a rig control (RC) system 311, a fluid circulation (FC) system 312, a managed pressure drilling control (MPDC) system 313, a choke pressure control (CPC) system 314, a well pressure control (WC) system 315, and a closed circuit television (CCTV) system 316. The control workstation 197 can be used to monitor, configure, control and / or otherwise operate one or more of the well construction subsystems 311-316.
[0075] The RC system 311 may include a support structure 112, a drill string hoisting system or equipment (e.g., DW 119), a drill string rotation system (e.g., top drive 116 and / or rotary table and kelly), a reciprocating slip 161, a drill pipe handling system or equipment (e.g., catwalk 131, TDA 202, stand box 164, FIB 166, TBR 254, SGA 262, LTC 244, ITC 236, UTC 242, LSA 228, and RN 151), a generator, and other equipment. Thus, the RC system 311 may perform power generation and / or distribution, and may control the handling, hoisting, and rotation operations of the drill pipe. The RC system 311 may also serve as a support platform for drilling equipment and a scaffolding work platform for drilling rig operations (such as the above-mentioned connection tightening and unfastening operations).
[0076] The FC system 312 may include the drilling fluid 140 , a pump 144 , drilling fluid loading and / or mixing equipment, drilling fluid reconditioning equipment 170 , a flare stack 172 , and / or other fluid control equipment. Thus, the FC system 312 may perform fluid operations of the well construction system 100 .
[0077] The MPDC system 313 may include the RCD 138, the throttle manifold 162, the downhole pressure sensor 186, and / or other equipment. The CPC system 314 may include the throttle manifold 173 and / or other equipment. The WC system 315 may include the BOP equipment 130, 132, 138, the BOP control unit 137, and a BOP control station (not shown) for controlling the BOP control unit 137.
[0078] The CCTV system 316 may include a camera 198 and a corresponding actuator (e.g., a motor) for moving or otherwise controlling the direction of the camera 198. The CCTV system 316 may be used to capture real-time video of the various portions or subsystems 311-315 of the well construction system 100 and display the video signal from the camera 198 on the video output device 196 to display the various portions or subsystems 311-315 in real time.
[0079] Each of the well construction subsystems 311-316 may also include various communication equipment (e.g., modems, network interface cards / circuits, etc.) and communication conductors (e.g., cables) that communicatively connect the equipment (e.g., sensors and actuators) of each subsystem 311-316 with the control workstation 197 and / or other equipment. Figure 1 and Figure 2 The wellsite equipment shown in FIG. 1 is associated with certain wellsite subsystems 311 - 316 , but such association is merely an example, and the example is not intended to limit or prevent such wellsite equipment from being associated with two or more wellsite subsystems 311 - 316 and / or different wellsite subsystems 311 - 316 .
[0080] The control system 300 may include a wellsite computing resource environment 305, which may be located at the wellsite 104 as part of the well construction system 100, 200. The control system 300 may also include a remote computing resource environment 306, which may be off-site (i.e., not at the wellsite 104). The control system 300 may also include various local controllers (e.g., Figure 4 As described above, each subsystem 311-316 of the well construction system 100, 200 may include an actuator (e.g., a controller 341-346) for performing operations of the well construction system 100, 200. Figure 4 Actuators 331-336) and sensors (e.g., Figure 4 321-326). These actuators and sensors may be monitored and / or controlled by the wellsite computing resource environment 305, the remote computing resource environment 306, and / or the corresponding local controller. For example, the wellsite computing resource environment 305 and / or the local controller may be operable to monitor the sensors of the wellsite subsystems 311-316 in real time and provide real-time control commands to the subsystems 311-316 based on the received sensor data. Data may be generated by sensors and / or computing and may be used for coordinated control between two or more of the subsystems 311-316.
[0081] The control system 300 may communicate in real time with various components of the well construction system 100, 200. For example, the local controller may communicate with various sensors and actuators of the corresponding subsystems 311-316 via a local communication network (not shown), and the wellsite computing resource environment 305 may communicate with the subsystems 311-316 via a data bus or network 309. As described below, the data or sensor signals generated by the sensors of the subsystems 311-316 may be used by the processes of the wellsite computing resource environment 305 (e.g., Figure 4 Similarly, data or control signals generated by the processes and / or devices of the wellsite computing resource environment 305 may be automatically communicated to the various actuators of the subsystems 311-316, perhaps according to predetermined programming, such as to facilitate well construction operations and / or other operations described herein.
[0082] The remote computing resource environment 306, the wellsite computing resource environment 305, and the subsystems 311-316 of the well construction system 100, 200 may be communicatively connected to each other via a network connection, such as via a wide area network (WAN), a local area network (LAN), and / or other networks that are also within the scope of the present disclosure. A "cloud" computing environment is an example of a remote computing resource environment 306. The wellsite computing resource environment 305 may be or form at least a portion of the processing device 192, and may therefore form a portion of or be communicatively connected to the control workstation 197.
[0083] Figure 4 It is connected to the subsystems 311-316 of the well construction system 100 and 200 in a communicative manner. Figure 3 The schematic diagram of an exemplary implementation of the control system 300 shown in FIG. 1 includes a RC system 311, a FC system 312, a MPDC system 313, a CPC system 314, a WC system 315, and a CCTV system 316. Figures 1 to 4 .
[0084] The well construction system 100, 200 may include one or more on-site user devices (OUDs) 302 communicatively connected to a wellsite computing resource environment 305. The on-site user devices 302 may be or include fixed user devices and / or portable user devices intended to be placed at the well construction system 100, 200. For example, the on-site user devices 302 may include desktop computers, laptop computers, smart phones and / or other portable smart devices, personal digital assistants (PDAs), tablet / touch screen computers, wearable computers, and / or other devices. The on-site user devices 302 are operable to communicate with the wellsite computing resource environment 305 and / or the remote computing resource environment 306 of the well construction system 100, 200. At least one of the on-site user devices 302 may be or include Figure 1 The control workstation 197 shown and / or Figure 1 and Figure 3 At least a portion of processing equipment 192 is shown, which may be located within facility 191.
[0085] The wellsite computing resource environment 305 and / or other portions of the well construction system 100, 200 may also include an information technology (IT) system 319 that is operable to communicatively interconnect the various portions of the wellsite computing resource environment 305 and / or communicatively connect the wellsite computing resource environment 305 with other portions of the well construction system 100, 200. The IT system 319 may include communication conduits, software, computers, and / or other IT equipment that facilitates communication between one or more portions of the wellsite computing resource environment 305 and / or between the wellsite computing resource environment 305 and another portion of the well construction system 100, 200 (such as the remote computing resource environment 306, the on-site user device 302, and the subsystems 311-316).
[0086] The control system 300 may include one or more off-site user devices 303 (or be used in combination therewith in other ways). The off-site user device 303 may be or include a desktop computer, a laptop computer, a smart phone and / or other portable smart device, a PDA, a tablet / touch screen computer, a wearable computer and / or other device. The off-site user device 303 may be operable to receive and / or transmit information (e.g., for monitoring functions) from and / or to the well construction system 100, 200, such as by communicating with the well site computing resource environment 305 through a network 308. The off-site user device 303 may be used only for monitoring functions. However, one or more of the off-site user devices 303 may be used to provide a control process for controlling the operation of the various subsystems 311-316 of the well construction system 100, 200. The off-site user device 303 and / or the well site computing resource environment 305 may also be operable to communicate with the remote computing resource environment 306 through a network 308. The network 308 may be a WAN, such as the Internet, a cellular network, a satellite network, other WANs, and / or combinations thereof.
[0087] The subsystems 311-316 of the well construction system 100, 200 and the control system 300 may include sensors 321-326, actuators 331-336 and local controllers 341-346. The controllers 341-346 may be programmable logic controllers (PLCs) and / or have functions similar to Fig.231000. The RC system 311 may include one or more sensors 321, one or more actuators 331, and one or more controllers 341. The FC system 312 may include one or more sensors 322, one or more actuators 332, and one or more controllers 342. The MPDC system 313 may include one or more sensors 323, one or more actuators 333, and one or more controllers 343. The CPC system 314 may include one or more sensors 324, one or more actuators 334, and one or more controllers 344 (e.g., Figure 6 The WC system 315 may include one or more sensors 325, one or more actuators 335, and one or more controllers 345. The CCTV system 316 may include one or more sensors 326, one or more actuators 336, and one or more controllers 346.
[0088] Sensors 321-326 may include sensors for operation of the various subsystems 311-316 of the well construction systems 100, 200. For example, sensors 321-326 may include cameras, position sensors, pressure sensors, temperature sensors, flow sensors, vibration sensors, current sensors, voltage sensors, resistance sensors, gesture detection sensors or devices, voice actuation or recognition devices or sensors, and / or other examples.
[0089] The sensors 321-326 may be operable to provide sensor data to the wellsite computing resource environment 305, such as to the coordination control device 304. For example, the sensors 321-326 may provide sensor data 351-356, respectively. The sensor data 351-356 may include signals or information indicating equipment operating status (e.g., on or off, up or down, set or released, etc.), drilling parameters (e.g., depth, hook load, torque, etc.), auxiliary parameters (e.g., vibration data of a pump), flow rate, temperature, operating speed, position, and pressure, among other examples. The collected sensor data 351-356 may include or be associated with a timestamp (e.g., date and / or time) indicating when the sensor data 351-356 was collected. The sensor data 351-356 may also or alternatively be aligned with depth, time, and / or other drilling parameters.
[0090] The collection of sensor data 351-356 at the coordination control device 304 can facilitate the measurement of the same physical property at different locations of the well construction system 100, 200, where the sensor data 351-356 can be used for measurement redundancy to allow continuous well construction operations. The measurement of the same physical property at different locations can also be used to detect the condition of equipment at different physical locations at the well site surface 104 or within the wellbore 102. Changes in measurements over time at different well site locations can be used to determine equipment performance, system performance, scheduled maintenance due dates, etc. For example, a slip state (e.g., set or not set) can be collected from the sensor 321 and the slip state can be communicated to the well site computing resource environment 305. The collection of fluid samples can be measured by sensors such as sensors 186, 323 and related to drill bit depth and time measured by other sensors. The collection of data from the camera 198, 325 can facilitate the detection of the arrival and / or installation of materials or equipment at the well construction system 100, 200. The arrival and / or installation time of materials or equipment may be used to assess material degradation, scheduled maintenance of equipment, and other assessments.
[0091] The coordination control device 304 may facilitate control of one or more of the subsystems 311-316 at the level of each individual subsystem 311-316. For example, in the FC system 312, the sensor data 352 may be fed into the controller 342, which may respond to control the actuator 332. However, for control operations involving multiple systems, the control may be coordinated by the coordination control device 304. For example, the coordinated control operation may include downhole pressure control during tripping. The downhole pressure may be affected by each of the FC system 312 (e.g., pump speed), the MPDC 313 (e.g., the throttling position of the MPDC), and the RC system 311 (e.g., tripping speed). Therefore, when it is intended to maintain a certain downhole pressure during tripping, the coordination control device 304 may be used to direct appropriate control commands to two or more (or each) of the participating subsystems.
[0092] Control of the subsystems 311-316 of the well construction system 100, 200 may be provided by a three-tier control system including a first-tier local controller 341-346, a second-tier coordination control device 304, and a third-tier monitoring system 307. Coordination control may also be provided by one or more controllers 341-346 of one or more of the subsystems 311-316 without using the coordination control device 304. In this implementation of the control system 300, the wellsite computing resource environment 305 may provide control processes directly to these controllers 341-346 for coordinated control.
[0093] The sensor data 351-356 may be received by the coordination control device 304 and used for control of the subsystems 311-316. The sensor data 351-356 may be encrypted to produce encrypted sensor data 371. For example, the wellsite computing resource environment 305 may encrypt sensor data from different types of sensors and systems to produce a set of encrypted sensor data 371. Therefore, if an unauthorized user device (either an off-site user device 303 or an on-site user device 302) is able to access one or more networks of the well construction system 100, 200, such a device may not be able to view the encrypted sensor data 371. As described above, the encrypted sensor data 371 may include a timestamp and aligned drilling parameters (e.g., depth). The encrypted sensor data 371 may be communicated to the remote computing resource environment 306 via the network 308 and stored as encrypted sensor data 372.
[0094] The wellsite computing resource environment 305 may provide encrypted sensor data 371, 372 that may be used for off-site viewing and processing, such as by an off-site user device 303. Access to the encrypted sensor data 371, 372 may be limited by access controls implemented in the wellsite computing resource environment 305. The encrypted sensor data 371, 372 may be provided to the off-site user device 303 in real time, so that off-site personnel may view the real-time status of the well construction system 100, 200 and provide feedback based on the real-time sensor data. For example, different portions of the encrypted sensor data 371, 372 may be sent to the off-site user device 303. The encrypted sensor data 371, 372 may be decrypted by the wellsite computing resource environment 305 before transmission and / or decrypted on the off-site user device 303 after receiving the encrypted sensor data. The off-site user device 303 may include a thin client (not shown) configured to display data received from the wellsite computing resource environment 305 and / or the remote computing resource environment 306. For example, various types of thin clients (eg, devices with display capabilities and minimal processing capabilities) may be used for certain functions or for viewing various sensor data 351 - 356 .
[0095] The wellsite computing resource environment 305 may include various computing resources for monitoring and controlling operations, such as one or more computers with processors and memory. For example, the coordination control device 304 may include a processing device (e.g., Fig.23The processing device 1000 shown in the figure is used to process sensor data, store sensor data, and issue control commands in response to sensor data. As described above, the coordination control device 304 can control the various operations of the subsystems 311-316 by analyzing the sensor data 351-356 from one or more of the well site subsystems 311-316 to facilitate coordinated control between the subsystems 311-316. The coordination control device 304 can generate control data 373 (e.g., signals, commands, coded instructions) to perform control of the subsystems 311-316. The coordination control device 304 can transmit the control data 373 to one or more subsystems 311-316. For example, control data 361 can be sent to the RC system 311, control data 362 can be sent to the FC system 312, control data 363 can be sent to the MPDC system 313, control data 364 can be sent to the CPC system 314, control data 365 can be sent to the WC system 315, and control data 366 can be sent to the CCTV system 316. The control data 361-366 may include, for example, wellsite operator commands (e.g., turning a pump on or off, opening or closing a valve, updating a physical property set point, etc.). The coordinated control device 304 may include a fast control loop that directly obtains the sensor data 351-356 and executes, for example, a control algorithm. The coordinated control device 304 may include a slow control loop that obtains data through the wellsite computing resource environment 305 to generate control commands.
[0096] The coordination control device 304 may be in an intermediate position between the monitoring system 307 and the local controllers 341-346 of the subsystems 311-316, such as to allow the monitoring system 307 to control the subsystems 311-316. The monitoring system 307 may include, for example, a device for inputting control commands to perform operations of the subsystems 311-316. The coordination control device 304 may receive commands from the monitoring system 307, process such commands according to rules (e.g., algorithms based on physical laws for drilling operations), and provide control data to one or more subsystems 311-316. The monitoring system 307 may be provided by the wellsite operator 195 and / or a process monitoring and control program. In such an implementation, the coordination control device 304 may coordinate control between the discrete monitoring systems and the subsystems 311-316 while utilizing control data 361-366 that may be generated based on sensor data 351-356 received from the subsystems 311-316 and analyzed by the wellsite computing resource environment 305. Coordinating control device 304 may receive control data 351-356 and then dispatch control data 361 including interlock commands to each subsystem 311-316. Coordinating control device 304 may also or alternatively monitor only control data 351-356 being dispatched to each subsystem 321-326 and then initiate machine interlock commands to the associated local controllers 341-346.
[0097] The coordinated control device 304 can operate at different levels of autonomy. For example, the coordinated control device 304 can operate in an advisory mode to notify the wellsite operator 195 to perform specific tasks or take specific corrective actions based on the sensor data 351-356 received from the various subsystems 311-316. When in the advisory mode, the coordinated control device 304 can, for example, advise or instruct the wellsite operator 195 to perform a standard work sequence when gas is detected on the rig floor 114, such as to close the annular BOP 132. In addition, if the wellbore 102 is gaining or losing drilling fluid 140, the coordinated control device 304 can, for example, advise or instruct the wellsite operator 195 to modify the density of the drilling fluid 140, modify the pumping rate of the drilling fluid 140, and / or modify the pressure of the drilling fluid within the wellbore 102.
[0098] The coordination control device 304 may also operate in a system / equipment interlock mode, whereby certain operations or sequences of operations are prevented based on the received sensor data 351-356. When operating in the interlock mode, the coordination control device 304 may manage the interlock operations between the various equipment of the subsystems 311-316. For example, if a pipe ram of the BOP stack 130 is activated, the coordination control device 304 may issue an interlock command to the RC system controller 341 to stop the DW 119 from moving the drill string 120. However, if a shear ram of the BOP stack 130 is activated, the coordination control device 304 may issue an interlock command to the controller 341 to operate the DW 119 to adjust the position of the drill string 120 within the BOP stack 130 before activating the shear ram so that the shear ram is not aligned with the shoulder of the tubular forming the drill string 120.
[0099] The coordination control device 304 may also operate in an automatic sequence mode, whereby certain operations or sequences of operations are automatically performed based on the received sensor data 351-356. For example, the coordination control device 304 may automatically activate an alarm and / or stop or reduce the operating speed of the pipe handling equipment when a wellsite operator 195 is detected near a mobile RN 151, TDA 202, LSA 228, LTC 244, or catwalk 131. As another example, if the wellbore pressure increases rapidly, the coordination control device 304 may automatically close the annular BOP 132, close one or more gates of the BOP stack 130, and / or adjust the throttle manifold 162.
[0100] The wellsite computing resource environment 305 may include or execute a monitoring process 374 (e.g., an event detection process) that may utilize the sensor data 351-356 to determine information about the state of the well construction system 100, 200 and automatically initiate an operational action, process, and / or sequence of one or more of the subsystems 311-316. The monitoring process 374 may initiate an operational action to be caused by the coordination control device 304. Depending on the type and scope of the received sensor data 351-356, the operational action may be performed in an advisory mode, an interlocking mode, or an automatic sequence mode.
[0101] For example, the monitoring process 374 may determine the drilling status, equipment health, system health, maintenance plan, or a combination thereof, and initiate recommendations to be generated. The monitoring process 374 may also detect abnormal drilling events (such as wellbore fluid loss and gain, wellbore erosion, fluid quality issues, or equipment events) based on job design and execution parameters (e.g., wellbore, drilling fluid, and drill string parameters), current drilling status, and real-time sensor information from the surface equipment 110 (e.g., the presence of hazardous gases at the rig floor, the presence of well site operators in close proximity to mobile pipe handling equipment, etc.) and real-time sensor information from the BHA 124 to initiate operational actions in an automatic mode. The monitoring process 374 may be connected to the real-time communication network 309. The coordination control device 304 may initiate countermeasures (e.g., predetermined actions, processes, or operations) based on events detected by the monitoring process 374.
[0102] The term "event" as used herein may include, but is not limited to, the operational and / or safety-related events described herein and / or another operational and safety-related event that may occur at the well construction system 100, 200. The events described herein may be detected by the monitoring process 374 based on the sensor data 351-356 (e.g., sensor signals or information) received and analyzed by the monitoring process 374.
[0103] The wellsite computing resource environment 305 may also include or execute a control process 375 that may utilize the sensor data 351-356 to optimize drilling operations, such as control of drilling equipment for improving drilling efficiency, equipment reliability, etc. For example, the acquired sensor data 352 may be used to derive a noise cancellation scheme to improve electromagnetic and / or mud pulse telemetry signal processing. The remote computing resource environment 306 may include or execute a control process 376 that is substantially similar to the control process 375 that may be provided to the wellsite computing resource environment 305. The monitoring and control processes 374, 375, 376 may be implemented, for example, by a control algorithm, a computer program, firmware, or other hardware and / or software.
[0104] The wellsite computing resource environment 305 may include various computing resources, such as a single computer or multiple computers. The wellsite computing resource environment 305 may also include a virtual computer system and a virtual database or other virtual structures for the collected data, such as one or more resource interfaces (e.g., network interfaces) that facilitate the submission of application programming interface (API) calls to various resources by request. In addition, each of the resources may include one or more resource interfaces that facilitate resources to access each other (e.g., to facilitate the virtual computer system of the computing resource environment to store data in a database or other structure for the collected data or to retrieve data from it). The virtual computer system may include a collection of computing resources configured to instantiate virtual machine instances. The wellsite operator 195 may interact with the virtual computer system through an off-site user device 303 or an on-site user device 302. Other computer systems or computer system services may be utilized in the wellsite computing resource environment 305, such as computer systems or computer system services that provide computing resources on dedicated or shared computers / servers and / or other physical devices. The wellsite computing resource environment 305 may include a single server (in discrete hardware components or as virtual servers) or multiple servers (eg, web servers, application servers, or other servers). A server may be, for example, a computer arranged in a physical and / or virtual configuration.
[0105] The wellsite computing resource environment 305 may also include a database, which may be or include a collection of computing resources that run one or more data sets. Such data sets may be operated and managed by utilizing API calls. Data sets such as sensor data 351-356 may be used by other resources in the wellsite computing resource environment 305 or by user devices (e.g., on-site user devices 302 and / or off-site user devices 303) accessing the wellsite computing resource environment 305. The remote computing resource environment 306 may include computing resources similar to those described above, such as a single computer or multiple computers (in discrete hardware components or virtual computer systems).
[0106] Figure 5 and Figure 6 is a perspective view and a cross-sectional view of at least a portion of an exemplary implementation of a control center 400 according to one or more aspects of the present disclosure. The control center 400 may be or form Figure 1 At least a portion of the control center 190 shown. The following description is commonly referred to as Figures 1 to 6 .
[0107] The control center 400 includes a facility 405 (e.g., a room, a cabin, a trailer, etc.) that contains various control devices for monitoring and controlling the subsystems 311-316 and other parts of the well construction system 100, 200. The facility 405 may include a front side 401 and a rear side 403. The front side 401 may be positioned toward or closest to the drill string 120 constructed by the well construction system 100, 200. The rear side 403 may face away from the drill string 120. The facility 405 may include a floor 402, a front wall 404, a left wall 406, a right wall 408, a rear wall 410, and a roof 412. The facility 405 may also have a side door 414, a rear door 416, and a plurality of windows 421-428 in one or more of the walls 404, 406, 408, 410, and / or the roof 412. Each of the windows 421-428 may be surrounded by a structural frame 430 that is connected to the wall and supports a window security guard 432 (eg, bars, grilles) in front of or along the windows 421-428.
[0108] The facility 405 may have an observation area 440 at the front side 401 of the facility 405 from which the wellsite operator 195 may directly observe the drill string 120, the drill floor 114, and / or other portions of the well construction system 100, 200. The observation area 440 may be surrounded or defined by windows 423-428 on several sides to increase the horizontal and vertical viewing angles of the well construction system 100 for the wellsite operator 195. A portion 442 of the observation area 440 (e.g., windows 423-427) may protrude or extend beyond other portions of the facility 405 (e.g., the front wall 404) to facilitate viewing of the well construction system 100, 200 by the wellsite operator 195. The observation area 440 may be located on one side of the facility 405. The viewing area 440 may be surrounded by or at least partially defined by: a front window 424 that allows the wellsite operator 195 to look forward; two side windows 423, 425 that allow the wellsite operator 195 to look to the sides (i.e., to the left and to the right); a lower window 426 that allows the wellsite operator 195 to look downward; and one or more upper windows 427, 428 that allow the wellsite operator 195 to look upward. The lower window 426 and / or at least one upper window 427 may extend diagonally relative to the front window 424.
[0109] The control center 400 may include one or more wellsite operator control workstations within the facility 405. The workstations may be used by the wellsite operator 195 to monitor and control the subsystems 311-316 and other portions of the well construction system 100, 200. For example, the observation area 440 may include a first control workstation 450 located adjacent to the windows 423, 424, 425, 426, 428 and at least partially within an extended portion 442 of the observation area 440, such as to allow the wellsite operator 195 to utilize the control workstation 450 to have an unobstructed view of the drill string 120, the drill floor 114, and / or other portions of the well construction system 100, 200. The observation area 440 may also include a second control workstation 452 located adjacent to the first control workstation 450 (e.g., behind it) and adjacent to the window 425, but may not be located within the extended portion 442 of the observation area 440. The control workstation 452 can be raised at least partially above the control workstation 450 to reduce the view obstruction caused by the control workstation 450 and thus allow the well site operator 195 to use the control workstation 452 to observe the drill string 120, the drill floor 114 and / or other parts of the well construction system 100, 200 through the front window 424 at a position above the control workstation 450. The control center 400 may also include a third control workstation 454, which is located adjacent to the control workstations 450, 452 and adjacent to the windows 421, 422, but is not located within the observation area 440.
[0110] The control center 400 may also include a processing device 456 (e.g., a controller, a computer, a server, etc.) that is operable to provide control of one or more portions of the well construction system 100, 200 and / or operable to monitor the operation of one or more portions of the well construction system 100, 200. For example, the processing device 456 may be communicatively connected to various surface and downhole equipment described herein, and may be operable to receive signals from such equipment or transmit signals to the equipment to perform various operations described herein or otherwise within the scope of the present disclosure. The processing device 456 may store executable programs, instructions, and / or operating parameters or set points, including for implementing one or more aspects of the operations described herein. The processing device 456 may be communicatively connected to the control workstations 450, 452, 454. Although the processing device 456 is shown as being located within the facility 405, the processing device 456 may be located outside the facility 405. In addition, although the processing device 456 is shown as a single device that is separate and distinct from the control workstations 450, 452, 454, one or more of the control workstations 450, 452, 454 may include a corresponding processing device 456 that is configured in association with or forms at least a portion of such corresponding processing device 456.
[0111] The control workstations 450, 452, 454 may be operable to input or otherwise communicate commands to the processing device 456 by the wellsite operator 195, and to display or otherwise communicate information from the processing device 456 to the wellsite operator 195. One or more of the control workstations 450, 452, 454 may include an operator chair 460 and an HMI system including one or more input devices 462 (e.g., keyboard, mouse, joystick, touch screen, microphone, etc.) and one or more output devices 464 (e.g., video monitor, printer, audio speaker, touch screen, etc.). The input devices 462 and the output devices 464 may be arranged and / or integrated in association with the operator chair 460 to allow the wellsite operator 195 to input commands or other information to the processing device 456, and to view, hear and / or otherwise receive information from the processing device 456 and other portions of the well construction system 100, 200. One or more of the control workstations 450, 452, 454 may be or form a Figure 1 At least a portion of the control workstation 197 shown, and the processing device 456 may be or form Figure 1 At least a portion of the processing device 192 is shown.
[0112] The control center 400 may also include a BOP control station 470 (e.g., a control panel) of the WC system 315, which is operable to monitor and control one or more portions of the WC system 315. For example, the BOP control station 470 may be communicatively coupled to the BOP control unit 137 and the BOP equipment 130, 132, and may be operable to monitor and control the operation of the BOP control unit 137 and the BOP equipment 130, 132.
[0113] The BOP control station 470 may be operable to communicate control commands to the BOP control unit 137, which are input by the wellsite operator 195 for controlling the BOP equipment 130, 132, and to display or otherwise communicate information indicating the operating status of the BOP equipment 130, 132 and the BOP control unit 137 to the wellsite operator 195. The BOP control station 470 may include a processing device (e.g., Fig.23The BOP control station 470 may further include an HMI system including one or more input devices 472 (e.g., buttons, keys, touch screens, etc.) and one or more output devices 474 (e.g., video monitors, gauges, audio speakers, touch screens, etc.). The input devices 472 and the output devices 474 may be disposed and / or integrated in association with a housing or casing of the BOP control station 470 to allow the wellsite operator 195 to input commands or other information to the BOP control station 470 to control the BOP equipment 130, 132 and to receive information from the BOP control station 470 to monitor the operating status of the BOP equipment 130, 132.
[0114] The BOP control unit 470 may be communicatively connected to one or more of the control stations 450, 452, 454, such as to allow one or more portions of the WC system 315 to be monitored and controlled through the control stations 450, 452, 454. For example, one or more of the control stations 450, 452, 454 or the processing device 456 may be communicatively connected directly to the processing device of the BOP control station 470, or indirectly to it, such as through an input device 472 and an output device 474 of the BOP control station 470. Such connection may allow the control station 450, 452, 454 to receive information indicating the operating status of the BOP control unit 137 and the BOP equipment 130, 132 through the BOP control station 470. Such connection may also allow the control station 450, 452, 454 to transmit control commands to the BOP control unit 137 and the BOP equipment 130, 132 through the BOP control station 470. Such connection may also or alternatively facilitate control of the BOP control station 470 by the control workstations 450 , 452 , 454 , such as may cause the BOP control station 470 to be directed by or through the control workstations 450 , 452 , 454 to control the BOP control unit 137 and the BOP equipment 130 , 132 .
[0115] The control workstations 450, 452, 454 may be operable to display information indicative of the operating status of the BOP control unit 137 and the BOP equipment 130, 132 to the wellsite operator 195 via an output device 464 to allow the wellsite operator to monitor the operating status of the BOP control unit 137 and the BOP equipment 130, 132 while seated in the corresponding operator chair 460. The control workstations 450, 452, 454 may also be operable to receive control commands from the wellsite operator 195 via an input device 462 while seated in the corresponding operator chair 460 for transmission to the BOP control station 470 to control the BOP control unit 137 and the BOP equipment 130, 132.
[0116] Figure 7 is a top view of a portion of an exemplary implementation of a wellsite operator control workstation 500 communicatively coupled to and operable to control a well construction system 100 , 200 according to one or more aspects of the present disclosure. Figure 7 The depicted control workstation 500 is an exemplary implementation of the control workstations 450, 452, 454 described above. The control workstation 500 can facilitate receiving and displaying various information, such as sensor signals or information (e.g., sensor data 351-356), control commands (e.g., control data 361-366), processes occurring, events being detected, and operating states of various equipment of the subsystems 311-316 of the well construction system 100, 200. The following description collectively refers to Figures 1 to 7 .
[0117] The control workstation 500 includes an operator chair 502 (e.g., a driller's chair) and an HMI system that includes a plurality of input and output devices integrated with, supported by, or otherwise provided in association with the operator chair 502. The input devices allow the wellsite operator 195 to input commands or other information to control the wellsite equipment of the well construction system 100, 200, and the output devices allow the wellsite operator 195 to receive sensor signals and other information indicating the operating status of the wellsite equipment. The operator chair 502 may include a seat 504, a left armrest 506, and a right armrest 508.
[0118] The input devices of the control workstation 500 may include a plurality of physical controls, such as a left joystick 510, a right joystick 512, and / or other physical controls 514, 515, 516, 518, such as buttons, keys, switches, knobs, dials, sliders, mice, keyboards, and microphones. One or more of the joysticks 510, 512 and / or physical controls 514, 515, 516 may be integrated into or otherwise supported by corresponding armrests 506, 508 of the operator chair 502 to allow the wellsite operator 195 to operate these input devices through the operator chair 502. In addition, one or more physical controls 518 may be integrated into corresponding joysticks 510, 512 to allow the wellsite operator 195 to operate these physical controls 518 while operating the joysticks 510, 512. The physical controls may include an emergency stop (E-stop) button 515, which may be electrically connected to the E-stop relays of one or more wellsite equipment items (e.g., RN 151, TDA 202, DW 119, LSA 228, LTC 244, SGA 262, top drive 116, etc.) so that the wellsite operator 195 can shut down the wellsite equipment during emergencies and other situations.
[0119] The output devices of the control workstation 500 may include one or more video output devices 526 (e.g., video monitors), printers, speakers, and other output devices disposed in association with the operator chair 502 and operable to display sensor signals and other information indicative of the operational status of the well construction system 100, 200 to the wellsite operator 195. The video output device 526 may be implemented as one or more LCD displays, LED displays, plasma displays, cathode ray tube displays, and / or other types of displays.
[0120] The video output device 526 may be disposed in front of or otherwise adjacent to the operator chair 502. The video output device 526 may include a plurality of video output devices 532, 534, 536, each dedicated to displaying predetermined information in a predetermined (e.g., programmed) manner. Although the video output device 526 is shown as including three video output devices 532, 534, 536, the video output device 526 may be or include one, two, four, or more video output devices.
[0121] The video output devices 532, 534, 536 may each display in a predetermined manner selected sensor signals or information indicative of the operating status of the selected portion of the well construction system 100, 200. For example, the video output devices 534, 536 may display sensor signals or information 540 (e.g., sensor data 351-356) generated by various sensors (e.g., sensors 321-326) of the well construction system 100, 200 to allow the wellsite operator 195 to monitor the operating status of the subsystems 311-316. The information 540 may be displayed in the form of virtual or computer-generated lists, menus, tables, charts, bars, meters, lights, and schematic diagrams, among other examples.
[0122] One or more of the video output devices 526 may be configured to display video signals (i.e., video feeds) generated by one or more of the cameras 198. For example, the video output device 532 may be dedicated to displaying video signals generated by one or more of the cameras 198. When displaying video signals from multiple cameras 198, the video output device 532 may display multiple video windows, each video window displaying a corresponding video signal. In addition, one or more of the other video output devices 534, 536 may also display video signals from one or more of the cameras 198. For example, one or both of the video output devices 534, 536 may display one or more picture-in-picture (PIP) video windows 544, each PIP video window displaying a video signal from a corresponding camera in the cameras 198. The PIP video windows 544 may be embedded or inserted along or adjacent to the sensor information 540. The search (i.e., selection) of the camera 198 whose video signal is to be displayed on the video output device 526 can be manually selected by the well site operator 195 or automatically operated by the control system 300, such as based on an operational event at the well construction system 100, 200 (e.g., a drilling event, a well construction operation phase, etc.), so that a video signal related to the currently occurring event is displayed.
[0123] The control workstation 500 may also include a combination device that is operable as both an input device and an output device to display information to the wellsite operator 195 and receive commands or information from the wellsite operator 195. Such a device may be or include a touch screen 522, 524 that is operable to display a plurality of software (e.g., virtual, computer-generated) buttons, switches, knobs, dials, icons, and / or other software controls 530, thereby allowing the wellsite operator 195 to operate (e.g., click, select, move) the software controls 530 through finger contact with the touch screen 522, 524 to control various wellsite equipment of the subsystems 311-316. The software controls 530 may also be operated by physical controls 514, 516, joysticks 510, 512, or other input devices of the control workstation 500. The software controls 530 and / or other features displayed on the touch screens 522, 524 may also display sensor signals or information (e.g., sensor data 351-356), operational settings, set points, and / or the status of selected wellsite equipment for viewing by the wellsite operator 195. For example, the software controls 530 may change color, move in position or direction, and / or display sensor information, set points, and / or operational values (e.g., temperature, pressure, position). The touch screens 522, 524 may be disposed on, supported by, or integrated into the armrests 506, 508 or other portions of the operator's chair 502 to allow the wellsite operator 195 to operate the software controls 530 displayed on the touch screens 522, 524 through the operator's chair 502.
[0124] Each video output device 526 and touch screens 522, 524 may display (i.e., generate) a plurality of display screens (i.e., an integrated display system), each display screen displaying selected sensor signals or information 540 and software controls 530 indicating the operating status of the well construction system 100, 200 to the well site operator 195 for controlling selected portions of the well construction system, respectively. Each display screen may integrate software controls 530 and / or sensor information 540 from one or more well site equipment items (e.g., subsystems 311-316) with information generated by the control system 300 (e.g., monitoring processes 374, control processes 375, and control data 361-366, 373) for viewing and / or operation by the well site operator 195. The display screens may be alternately shown or displayed on one or more of the video output device 526 and / or the touch screens 522, 524, or simultaneously shown or displayed on one or more of these devices. The display screens intended to be displayed on the video output device 526 and / or the touch screens 522, 524 may be selected by the wellsite operator 195 via the physical controls 514, 516, 518 and / or the software controls 530. The display screens intended to be displayed on the video output device 526 and / or the touch screens 522, 524 may also or alternatively be automatically selected by the control system 300 based on an operational event (e.g., equipment failure, hazardous drilling conditions) detected at the well construction system 100, 200 or a planned operational event (e.g., a changed period or phase of a well construction operation) so that information related to the currently occurring event is displayed. Each display screen generated by the touch screens 522, 524 may display a software control 530 that may be operated by the wellsite operator 195 to control the wellsite equipment associated with the software control 530, and each display screen generated by the video output device 526 may display information 540 indicating the operational status of the wellsite equipment associated with the information 540. Therefore, the display screen displayed on the touch screens 522 , 524 may be referred to as a control screen hereinafter, and the display screen displayed on the video output device 526 may be referred to as a status screen hereinafter.
[0125] The touch screens 522, 524 may be operable to display one or more control screens (e.g., configuration screens) that may be used to operate, set, adjust, configure, or otherwise control the subsystems 311-316 or other wellsite equipment. Each control screen may display one or more software controls 530, such as may allow the wellsite operator 195 to operate, set, adjust, configure, or otherwise control the subsystems 311-316 or other wellsite equipment by finger contact with the touch screens 522, 524 from the operator chair 502. Figures 8 to 10552, 554, 556, which may be displayed on the touch screen 522, 524 and operated by the wellsite operator 195 to operate, set, adjust, configure, or otherwise control the subsystems 311-316 or other wellsite equipment of the well construction system 100, 200. Figures 7 to 10 .
[0126] The software controls 552, 554, 556 may be pressed, clicked, selected, moved, or otherwise manipulated through the physical controls 514, 516 and / or through finger contact by the wellsite operator 195 to increase, decrease, modify, or otherwise input operating parameters, set points, and / or instructions for controlling one or more wellsite equipment items of the well construction system 100, 200. The software controls 552, 554, 556 may also display the inputted and / or current operating parameters on or associated with the software controls 552, 554, 556 for viewing by the wellsite operator 195. The operating parameters, set points, and / or instructions associated with the software controls 552, 554, 556 may include equipment operating states (e.g., on or off, up or down, set or released, position, speed, temperature, etc.), drilling parameters (e.g., depth, hook load, torque, etc.), auxiliary parameters (e.g., vibration data of a pump), and fluid parameters (e.g., flow, pressure, temperature, etc.), among other examples.
[0127] The software control 552 may be or include a software button that may be operated to increase, decrease, change, or otherwise input different operating parameters, set points, and / or instructions for controlling one or more parts of the well construction system 100, 200 associated with the software control 552. The software control 554 may be or include a list or menu of items related to one or more aspects of the well construction system 100, 200 (e.g., equipment, processes, operating stages, equipment subsystems, etc.) that may be operated to select one or more items on the list. The selected items may be highlighted, colored differently, or otherwise indicated, such as by a check mark, circle, dot, or other character / icon that appears in association with the selected item. The software control 556 may be or include a combination of different software controls that may be operated to increase, decrease, change, or otherwise input different operating parameters, set points, and / or instructions for controlling one or more parts of the well construction system 100, 200 associated with the software control 556 (such as a pump of the well construction system 100, 200). The software controls 556 may include a slider 553 that may be moved along a scale bar or otherwise operated to increase, decrease, or otherwise change the pump speed or another operating parameter associated with the slider 553. The input pump speed may be shown in the display window 555. The software controls 556 may also include a software button 557, such as one that may be operated to start, pause, and stop the operation of a pump or another portion of the well construction system 100, 200 associated with the software button 557.
[0128] Figures 11 to 15 601-605 (e.g., configuration screens or menus) that may be displayed on the touch screen 522, 524 according to one or more aspects of the present disclosure. Each control screen 601-605 may be operated by the wellsite operator 195 through finger contact with the touch screen 522, 524 (and / or other input devices) to operate, set, adjust, configure, or otherwise control the subsystems 311-316 or other wellsite equipment of the well construction system 100, 200 associated with or displayed on the control screen 601-605. The following description collectively refers to Figures 11 to 15 .
[0129] Each control screen (including control screens 601-605) may display a selection bar 610 for switching between or selecting which control screen is to be displayed on the corresponding touch screen 522, 524 and / or which status screen is to be displayed on each of the video output devices 526. Each control screen may also include an equipment control area 618 for displaying software controls for controlling well construction operations and / or wellsite equipment associated with the control screen. The selection bar 610 may include an equipment menu button 612, which, when operated by the wellsite operator 195, may cause a control screen selection menu 614 (e.g., a drop-down menu or a pop-up menu) to appear. The selection menu 614 may include a plurality of buttons 616, each button being associated with and listing a corresponding well construction operation or wellsite equipment to be controlled. The wellsite operator 195 may operate (eg, click, touch, and / or otherwise select) one of the buttons 616 to select a well construction operation or wellsite equipment, thereby causing display of a corresponding control screen for controlling the associated well construction operation or wellsite equipment.
[0130] After selecting one of the buttons 616, ( Figures 12 to 15 A plurality of software controls 630 (shown in FIG. 6A ) may appear in the equipment control area 618 and the selected well construction operation or wellsite equipment may be listed or otherwise identified in the control screen identification area 620. As the wellsite operator 195 switches between various control screens by selecting different buttons 616, the software controls 630 or other information displayed in the equipment control area 618 will change. Fig.11As shown, exemplary control screens that may be selected for display on touch screens 522, 524 may include: a tripping control screen displaying software controls for controlling automatic operation of wellsite equipment that may operate together to perform tripping operations; a drilling control screen displaying software controls for controlling automatic operation of wellsite equipment that may operate together to perform drilling operations; a drill pipe handling control screen displaying software controls for controlling automatic operation of wellsite equipment that may operate together to move drill pipe at the wellsite; and a plurality of separate equipment control screens, each separate equipment control screen displaying software controls for automatically and / or manually controlling the operation of separate wellsite equipment, the separate wellsite equipment such as catwalk 131, TDA 202, standpipe box 164, FIB 166, TBR 254, SGA 262, LTC 244, ITC 236, UTC 242, LSA 228, pipe box 164, catwalk 131, top drive 116, RN 151, choke 162, and fluid reconditioning equipment 170. Although not described herein, control screens within the scope of the present disclosure may include control screens that display software controls for other individual wellsite equipment and / or wellsite equipment subsystems (e.g., subsystems 311-316).
[0131] Each control screen, including control screens 601-605, may also be used to switch between or select which status screen is to be displayed on which video output device 532, 534, 536. For example, selection bar 610 may include status screen selection buttons 622, each of which is associated with a corresponding one of video output devices 532, 534, 536 and is operable to cause a corresponding status screen selection menu 624 (e.g., a drop-down menu or a pop-up menu) to appear when operated by wellsite operator 195. Each selection menu 624 may include a plurality of buttons 626, each of which is associated with and lists a corresponding well construction operation, wellsite equipment, and / or subsystem (e.g., subsystems 311-316) of well construction system 100, 200 to be displayed. The wellsite operator 195 may operate (e.g., click, touch, and / or otherwise select) one of the buttons 622 and 626 to select one of the video output devices 532, 534, 536 and a well construction operation, wellsite equipment, or subsystem, thereby causing a corresponding status screen displaying sensor signals or information 540 indicating the operating status of the selected well construction operation, wellsite equipment, or subsystem to be displayed on the selected video output device 532, 534, 536. The status screens that may be displayed on the video output devices 532, 534, 536 are described in more detail below.
[0132] When operated, the software controls 630 may activate, deactivate, start, stop, configure, or otherwise control the operation of the wellsite equipment associated with the software controls 630. The software controls 630 may initiate automatic operation of the wellsite equipment associated with the control screen, such as by operating an "auto" software button. The software controls 630 may also cause manual control of the wellsite equipment associated with the control screen to be given to the wellsite operator 195, such as by operating a "manual" software button. The software controls 630 may be grouped by related equipment and / or related operations, which may be identified by text 632 associated with each group of software controls 632.
[0133] Additionally, each software control 630 may list or otherwise identify an item of equipment or operation controlled by or otherwise associated with the software control 630. One or more of the software controls 630 may list or otherwise indicate the operational status (i.e., feedback) of the wellsite equipment or operation associated with the software control 630. For example, one or more of the software controls 630 may change color, text, shape, or otherwise change to indicate that the item of wellsite equipment associated with the software control 630 is activated, deactivated, or in a predetermined position, or that the operation associated with the software control 630 has started, stopped, or is in a particular stage.
[0134] Fig.12 6 is an exemplary implementation of a "Drilling" control screen 602 that can be used to control automatic, semi-automatic, and / or manual operation of wellsite equipment associated with a drilling operation and / or operating together to perform a drilling operation according to one or more aspects of the present disclosure. The control screen 602 can display various software controls 630 in the equipment control area 618 for controlling various wellsite equipment and / or operating parameters of the drilling operation performed by the well construction system 100, 200. For example, when operated, the software controls 630 can activate, deactivate, start, stop, configure, or otherwise control the automatic, semi-automatic, and / or manual operation of wellsite equipment associated with the drilling operation. Such wellsite equipment may include top drive 116, DW 119, pump 144, and BOP equipment 130, 132, among other examples.
[0135] Fig.136 is an exemplary implementation of a "pipe handling" control screen 603 that may be used to control automatic, semi-automatic, and / or manual operations of wellsite equipment associated with drill pipe handling (e.g., moving, storing) operations and / or that operate together to perform drill pipe handling operations according to one or more aspects of the present disclosure. The control screen 603 may display various software controls 630 in the equipment control area 618 for controlling various wellsite equipment and / or operating parameters of the drill pipe handling operations performed by the well construction system 100, 200. For example, when operated, the software controls 630 may activate, deactivate, start, stop, configure, or otherwise control automatic, semi-automatic, and / or manual operations of wellsite equipment associated with drill pipe handling operations. Such wellsite equipment may include catwalk 131 , TDA 202 , pipe box 164 , FIB 166 , TBR 254 , SGA 262 , LTC 244 , ITC 236 , UTC 242 , LSA 228 , RN 151 , and reciprocating slips 161 , among other examples.
[0136] Fig.14 6 is an exemplary implementation of a "Top Drive" control screen 604 that may be used to control automatic, semi-automatic, and / or manual operations of a top drive 116 according to one or more aspects of the present disclosure. The control screen 604 may display various software controls 630 in an equipment control area 618 for configuring and / or controlling automatic, semi-automatic, and / or manual operations performed by the top drive 116 and / or operating parameters associated with the top drive 116. For example, when operating, the software controls 630 may activate, deactivate, start, stop, configure, or otherwise control the operation of one or more portions of the top drive 116, such as the drive shaft 125, grabber, swivel, tubular handling assembly 127, and other portions of the top drive 116. The software controls 630 may also be used to control other wellsite equipment that may be directly or closely associated with the top drive 116 or operate in close association with the top drive, such as the RN 151.
[0137] Fig.15 6 is an exemplary implementation of a "Driller 1" control screen 605 that can be used to control automatic, semi-automatic, and / or manual operations of one of the RNs 151 according to one or more aspects of the present disclosure. The control screen 605 can display various software controls 630 in the equipment control area 618 for configuring or controlling automatic, semi-automatic, and / or manual operations performed by the RN 151 and / or operating parameters associated with the RN 151. For example, when operating, the software controls 630 can activate, deactivate, start, stop, configure, or otherwise control the operation of one or more parts of the RN 151 (such as a spinner and a torque wrench, including upper and lower jaws and associated clamps). The software controls 630 can also be used to control other wellsite equipment that can be directly or closely associated with the RN 151 or operate in close association with the RN.
[0138] The video output device 126 and / or the touch screen 522, 524 may also display a manual control guide menu or screen used by the wellsite operator 195 to guide or assist the wellsite operator 195 in manually controlling a selected operation or a single wellsite equipment item of the well construction system 100, 200. The guide screen may display the control function of a selected one of the joysticks 510, 512, the associated physical controls 518, and / or the other physical controls 514, 516 with respect to the selected operation or single wellsite equipment item. For example, manual control may be initiated when a "manual" software control 630 button is selected on one of the control screens displayed on one of the touch screens 522, 524. The control system 300 may then suspend the automatic operation of the associated wellsite equipment, hand over the operational control to the predetermined joystick 510, 512 and / or the other physical controls 514, 516, and display a corresponding manual control guide listing the control functions for manually controlling the wellsite equipment associated with the control screen.
[0139] Fig.16 6 is an exemplary implementation of a manual control guide screen 606 for displaying control functions for controlling drilling operations via the left joystick 510 and physical controls 514. The guide screen 606 may display a title bar 640 identifying the operation or wellsite equipment to be controlled and the joystick 510 and / or physical controls 514 for controlling such operation or wellsite equipment. The guide screen 606 may include a joystick control area 642 displaying a schematic diagram 644 of the joystick 510 and a schematic diagram 646 of associated physical controls 518 (e.g., joystick buttons and thumbstick). Each schematic button 646 is associated with text 638 describing the control function of each corresponding physical button 518 of the joystick 510. The joystick control area 642 may also display arrows 648 and corresponding text 650 describing the control function associated with movement of the joystick 510 and arrows 652 and corresponding text 654 describing the control function associated with movement of the joystick thumbstick 518. The tutorial screen 606 may also include a button control area 656 that displays a schematic diagram 658 of the corresponding physical controls 514. The button control area 656 may also display text 660 describing the control function associated with the operation of each of the corresponding physical controls 514. The tutorial screen 606 may also display an "Exit" software control 662 that may be operated to terminate manual control of the drilling operation and close the tutorial screen 606.
[0140] As mentioned above about Figure 7As described, an operator workstation within the scope of the present disclosure may display multiple status screens on one or more of the video output devices 526, each status screen displaying selected sensor signals or information (e.g., sensor data 351-356) generated by various sensors (e.g., sensors 321-326) of the wellsite construction system 100, such as to allow a wellsite operator to monitor operations, wellsite equipment, and / or equipment subsystems described herein (e.g., subsystems 311-316). Figures 17 to 21 is a diagram of an exemplary implementation of status screens 701-706 displayed on one or more of the video output devices 526 according to one or more aspects of the present disclosure. Figures 1 to 4 , Figure 7 and Figures 17 to 21 .
[0141] Status screens including status screens 701-706 may be alternately displayed on one of the video output devices 526. Some status screens may display the operational status of a well construction operation (e.g., tripping, drilling, pipe handling, etc.) that involves multiple wellsite equipment pieces operating in a coordinated manner to perform such operations, which may allow the wellsite operator 195 to monitor the operational status or parameters of such operations on a single status screen. Some status screens may display the operational status of a single wellsite equipment piece or a subsystem of the wellsite equipment (e.g., subsystems 311-316), such as may also allow the wellsite operator 195 to monitor the operational status or parameters of a single equipment piece or equipment subsystem. As described above, the status screens and corresponding operations, wellsite equipment, or equipment subsystems may be selected via the touch screens 522, 524. As Fig.11 As shown, exemplary status screens that may be selected for display may include: a tripping status screen that displays information indicating the operational status of a tripping operation; a drilling status screen that displays information indicating the operational status of a drilling operation; a pipe handling status screen that displays information indicating the operational status of a drill pipe handling operation; and a plurality of subsystem status screens, each of which displays information indicating the operational status of a corresponding subsystem of the well construction system 100, 200. Although not described herein, status screens within the scope of the present disclosure may also or alternatively include status screens that display information indicating the operational status of individual wellsite equipment items described herein.
[0142] The status screens including the status screens 701-706 may include a wellsite status screen indicator and an alarm window or area 710 that may visually indicate which operation or wellsite equipment is being displayed on the selected video output device 526 and whether a safety alarm or operational alarm associated with the operation or wellsite equipment is active. For example, the area 710 may include a plurality of indicators 712 (e.g., text, icons, graphics, etc.) that list the operations, wellsite equipment, and / or equipment subsystems that may be displayed via the corresponding status screen. The indicator 712 corresponding to the operation, wellsite equipment, or equipment subsystem of the currently displayed status screen may appear or lighten, highlight, or otherwise mark to indicate to the wellsite operator 195 which status screen is being displayed. The area 710 may also include a plurality of alarm or event indicators 714 (e.g., lights), each associated with a corresponding operation, wellsite equipment, or equipment subsystem indicator 712. One or more of the indicators 714 may be displayed, such as by ( Figure 4 The event indicator 714 may be activated (e.g., illuminated, changed color, etc.) by operation of the control system 300 (shown) to visually notify the wellsite operator 195 of an alarm or operational event occurring at or associated with the corresponding operation, wellsite equipment, or equipment subsystem. In response to the event indicator 714 being activated, the wellsite operator 195 may switch to a status screen corresponding to the activated event indicator 714 to evaluate the event and / or implement appropriate countermeasures or actions. Instead of manually changing between status screens, the status screen may automatically change to show a status screen corresponding to the operation, wellsite equipment, or equipment subsystem that experienced the event.
[0143] The status screens including the status screens 701-706 may also include a main operating status window or area 716 that displays selected sensor signals or information indicating the operating status of the operation, wellsite equipment, or equipment subsystem associated with the displayed status screen. The information displayed in the main operating status area 716 may be generated by actual wellsite equipment that performs the operation or forms the equipment subsystem associated with the displayed status screen. The information displayed in the main operating status area 716 may change when different display screens are displayed. The information in the main operating status area 716 may be displayed in the form of a list, menu, table, graph, bar, meter, light, and / or schematic diagram, among other examples.
[0144] The status screens including the status screens 701-706 may also include a secondary operating status window or area 718 that displays selected sensor signals or information indicating the operating status of the drilling operation and / or the general status of the well construction operation, such as to allow the wellsite operator to monitor the progress of the drilling operation and / or other well construction operations while monitoring the specific operation, wellsite equipment, or equipment subsystem displayed in the primary operating status area 716. The secondary operating status area 718 may also display sensor signals or information indicating the operating status of other wellsite equipment related to the drilling operation but not necessarily performing the drilling operation. When different status screens are displayed, the information displayed in the secondary operating status area 718 may remain unchanged or partially changed, such as to allow the wellsite operator 195 to monitor the progress of the drilling operation and / or other well construction operations while monitoring different operations, wellsite equipment, or equipment subsystems associated with different status screens.
[0145] However, when a different status screen is displayed, the information displayed in the secondary operating status area 718 may change. The changing information may allow the wellsite operator 195 to monitor the operating status of other wellsite equipment related to the operation displayed in the primary operating status area 716 but not necessarily directly performing the operation, and / or monitor the operating status of other wellsite equipment related to the wellsite equipment or equipment subsystems displayed in the secondary operating status area 716. The information in the secondary operating status area 718 may be displayed in the form of a list, menu, table, graph, bar, meter, light, and / or schematic diagram, among other examples.
[0146] Each status screen, including status screens 701-706, may also include a detailed description window or area 720 that lists and / or describes one or more aspects related to the operation, wellsite equipment or equipment subsystems displayed in the main operating status area 716, or another aspect of the well operation operation. Fig.17 and Fig.18 As shown, the description area 720 may display a general and / or detailed description of the work or activities (e.g., construction or work plans) that the wellsite operator 195 has, is, or will perform or supervise at the wellsite. The description area 720 may display proactive information about the work and / or a call to action to guide future work. The work description may include a title or name of a project phase or period, an estimated completion date (i.e., a deadline) for completing the project phase, and / or a list of operational steps or actions that the wellsite operator 195 will implement during the project phase. However, the control system 300 may automatically operate the wellsite equipment or subsystems to automatically implement such steps or actions according to the construction or work plan, such as by transmitting predetermined control commands to the corresponding wellsite equipment or subsystems. As described above, such automatic operation may be initiated, for example, by operating the "automatic" software button 630 on the associated control screen.
[0147] like Figures 19 to 21 As shown, the description area 720 may also or alternatively display a detailed description or information related to an event detected or otherwise occurring at the well construction system 100, 200. The description area 720 may also list and / or describe one or more countermeasures (e.g., corrective actions, sequences of operations) related to the event that may be executed or otherwise implemented in response to the event. Depending on the event and / or mode (e.g., advisory, interlocked, automatic) in which the control system 300 (e.g., computing resource environment 305) is operating, the description area 720 may describe the corrective actions to be initiated or otherwise implemented by the well site operator 195. However, the control system 300 may automatically implement the corrective actions, or cause the corrective actions to be automatically implemented, such as by transmitting predetermined control commands to corresponding well site equipment pieces or subsystems. The information displayed in the description area 720 may only display events and / or corrective actions related to the operation, well site equipment, or equipment subsystems shown in the main operating status area 716, and therefore may change when switching between status screens. However, when switching between status screens, the information displayed in the description area 720 may not change, and may list each detected event and / or corresponding corrective action, such as in chronological order or order of importance. As described above, the control system 300 may automatically change the status screen to show the operation, wellsite equipment, or equipment subsystem experiencing the event.
[0148] Each status screen including status screens 701-706 may also include ( Fig. 20 and Fig.21 The PIP video windows 722 may be configured to display one or more PIP video windows 722 (shown), each of which displays a video signal from a predetermined camera 198 in real time to display wellsite equipment associated with the operation, wellsite equipment, or equipment subsystem displayed in the main operating status area 716. The PIP video windows 722 may be embedded or inserted into a corresponding status screen, such as within the main operating status area 716. The views shown in the PIP video windows 722 may be switched manually or automatically between different cameras 198 to display different wellsite equipment or different views of wellsite equipment.
[0149] As described above, the status screen to be displayed on the video output device 526 may be selected via the touch screens 522, 524. However, the status screen including the sensor signals or information displayed in the indicator and alarm area 710, the primary operating status area 716, the secondary operating status area 718, the detailed description area 720, and / or the PIP window 722 may automatically change based on the successive stages of the well construction operation. For example, as the well construction operation progresses through the successive stages (e.g., tripping, drilling, pipe handling, etc.), the control system 300 may cause the video output device 526 to automatically change and display a status screen including information indicating the operational status of the wellsite equipment performing the current stage of the well construction operation or otherwise associated with the current stage of the well construction operation.
[0150] The wellsite operator 195 may adjust or otherwise configure each status screen, including status screens 701-706, to display one or more of the various information areas 710, 716, 718, 720 in a selected location on each status screen. For example, the indicator and alarm area 710 may be displayed at the top of the status screen, the detailed description area 720 may be displayed at the bottom of the status screen, the primary operating status area 716 may be displayed in the middle of the left side of the status screen, and the secondary operating status area 718 may be displayed on the right side of the status screen. In addition, the position and / or size (i.e., dimensions) of the PIP video window 722 displayed on each status screen may also be adjusted or otherwise selected. The relative positions of the information areas 710, 716, 718, 720 and the PIP video window 722 on the status screen may also be selected, for example, via one or more of the physical controls 514, 516, 518, such as by dragging and dropping the information areas 710, 716, 718, 720 and / or the PIP video window 722 to a selected location on the status screen.
[0151] Fig.17is an exemplary implementation of a status screen 701 that displays sensor signals or information indicative of operational status of various wellsite equipment associated with and operable together to perform drill pipe tripping operations in accordance with one or more aspects of the present disclosure. When the wellsite operator 195 or the control system 300 causes the tripping operations status screen 701 to be displayed on one of the video output devices 526, an indicator 712 associated with the tripping operations (such as the letters "TR") may appear or become highlighted to visually indicate to the wellsite operator 195 that the tripping operations status screen is being displayed. The main operating status area 716 may display information such as hook load, bit weight, traveling block position, driller torque, mud supply tank accumulation or volume, and return flow, among other examples. The secondary operational status area 718 may display information related to the drilling operation, such as hook load, traveling block position, drill bit depth, wellbore depth, number of pipe stands or tubulars in the wellbore, riser pressure, top drive trolley position, internal BOP position, top drive pipe connection status, elevator status, extension connection status, and slip status, among other examples. The description area 720 may display a work plan (i.e., a well construction plan) related to the tripping operation, including actions or steps that the wellsite operator 195 will perform or supervise at the wellsite during the tripping operation. However, as described above, the description area 720 may also or alternatively display information indicating operational events.
[0152] Fig.18 702 is an exemplary implementation of a status screen 702 that displays sensor signals or information indicating the operating status of various wellsite equipment associated with drilling operations and that can be operated together to perform drilling operations in accordance with one or more aspects of the present disclosure. When the wellsite operator 195 or the control system 300 causes the drilling operation status screen 702 to be displayed on one of the video output devices 526, an indicator 712 associated with the drilling operation (such as the letters "DR") may appear or become highlighted to visually indicate to the wellsite operator 195 that the drilling operation status screen is being displayed. The primary operating status area 716 may display information such as hook load, traveling block speed, bit weight, penetration rate, standpipe pressure, top drive torque, torque wrench torque, top drive rotation speed, drilling fluid loss / gain, and drilling fluid return flow, among other examples. The secondary operating status area 718 may display information related to the drilling operation, such as information related to or indicating the drilling fluid (i.e., mud) operating status and / or the operating status of the tank in use. The description area 720 may display a work plan related to the drilling operation (ie, a well construction plan), including actions or steps that the wellsite operator 195 will perform or supervise at the wellsite during the drilling operation. However, as described above, the description area 720 may also or alternatively display information indicating operational events.
[0153] As described above, the status screen may display sensor signals or information indicative of the operational status of the wellsite equipment subsystems (eg, subsystems 311 - 316 ). Fig.19 7 is an exemplary implementation of an RC system status screen 703 that displays sensor signals or information indicative of an operational status of the RC system 311 in accordance with one or more aspects of the present disclosure. When the wellsite operator 195 or the control system 300 causes the RC system status screen 703 to be displayed on one of the video output devices 526, an indicator 712 associated with the RC system 311, such as the letters "RC", may appear or become highlighted to visually indicate to the wellsite operator 195 that the RC system status screen 703 is being displayed. The main operational status area 716 may display sensor signals or information related to various wellsite equipment pieces that form the RC system 311, such as the catwalk 131, TDA 202, pipe box 164, FIB 166, TBR 254, SGA 262, LTC 244, ITC 236, UTC 242, LSA 228, and RN 151, among other examples. The main operating status area 716 may also display a schematic diagram 730 of such wellsite equipment to visually display the operating status (e.g., position) of such wellsite equipment to the wellsite operator 195. For example, a schematic diagram 730 of the drill floor 114, catwalk 131, pipe box 164, FIB 166, RN 151, and TDA 202 may visually indicate the movement and position of various parts of such wellsite equipment to the wellsite operator 195 in real time. The RC system status screen 703 may include a schematic diagram 730 of the slider 133 of the catwalk 131, TDA 202, LSA 228, SGA 262, ITC 236, and LTC 244, and other examples of the vertical pipe rack assembly 165 (e.g., pipe box 164 and FIB 166) containing the tubulars 111. Portions of the schematic 730 (e.g., the various arms of the TDA 202) may change position and / or color to visually indicate to the wellsite operator 195 the various positions and movements of the wellsite equipment represented. The primary operating status area 716 may also display sensor signals or information indicating the operating status of the wellsite equipment within a text box 732 positioned in association with the schematic 730 of the wellsite equipment. The secondary operating status area 718 may display information related to the drilling operation and / or additional information related to the operating status of the RC system 311, such as additional information not displayed in the primary operating status area 716. As described above, the description area 720 may display information indicating operational events. However, the description area 720 may also or alternatively display a work plan related to tripping, drilling, or other wellsite construction operations.
[0154] Fig. 207 is an exemplary implementation of a CPC system status screen 705 that displays sensor signals or information indicative of an operational status of a CPC system 314 in accordance with one or more aspects of the present disclosure. When a wellsite operator 195 or the control system 300 causes the CPC system status screen 705 to be displayed on one of the video output devices 526, an indicator 712 associated with the CPC system 314, such as the letters "CPC," may appear or become highlighted to visually indicate to the wellsite operator 195 that the CPC system status screen 705 is being displayed. A primary operational status area 716 may display sensor signals or information related to various wellsite equipment pieces that form the CPC system 314, such as the choke manifold 162 and associated wellsite equipment. The primary operational status area 716 may also display a schematic diagram 730 of the wellsite equipment to visually display the operational status of such wellsite equipment to the wellsite operator 195. The schematic diagram 730 may include, for example, various fluid control valves (e.g., ball valves, adjustable throttle valves) of the throttle manifold 162 and a plurality of fluid control valves in fluid connection with the throttle manifold 162. The primary operating status area 716 may visually indicate to the wellsite operator 195 in real time the operating status, fluid flow rate, fluid pressure, and valve position of the wellsite equipment forming the CPC system 314. Portions of the schematic diagram 730 (e.g., fluid valves) may change position and / or color to indicate the operating status (e.g., position) of such wellsite equipment to the wellsite operator 195. The primary operating status area 716 may also display sensor signals or information indicating the operating status of the wellsite equipment in a text box 732 positioned in association with the schematic diagram 730 of the wellsite equipment. The secondary operating status area 718 may display information related to the drilling operation and / or additional information related to the operating status of the CPC system 314, such as additional information not displayed in the primary operating status area 716. As described above, the description area 720 may display information indicating an operational event. However, the description area 720 may also or alternatively display a work plan related to tripping, drilling, or other wellsite construction operations. A PIP video window 722 showing a real-time view of the throttle manifold 162 or another portion of the CPC system 314 may be displayed in the main operating status area 716 or another area of the CPC system status screen 705.
[0155] Fig.217 is an exemplary implementation of a WC system status screen 706 that displays sensor signals or information indicating an operational status of a WC system 315 in accordance with one or more aspects of the present disclosure. When a wellsite operator 195 or the control system 300 causes the WC system status screen 706 to be displayed on one of the video output devices 526, an indicator 712 associated with the WC system 315 (such as the letters "WC") may appear or become highlighted to visually indicate to the wellsite operator 195 that the WC system status screen 706 is being displayed. A primary operating status area 716 may display sensor signals or information related to various wellsite equipment pieces (such as BOP equipment 130, 132) that form the WC system 315. Information displayed in the primary operating status area 716 may include, for example, information related to: risers / re-injectors, POD controls, POD regulators, analog sensor values (e.g., pressure, position), BOP event alarm signals, and tilt sensors. The main operating status area 716 may visually indicate to the wellsite operator 195 in real time the operating status, fluid pressure, and operating position of the wellsite equipment forming the CPC system 314. The main operating status area 716 may also display a schematic diagram 730 of the wellsite equipment to visually display the operating status of such wellsite equipment to the wellsite operator 195. The schematic diagram 730 may include, for example, a BOP stack 130 and annular fluid control device 132, and visually indicate to the wellsite operator 195 the operating status (e.g., position) of various gates and valves of the BOP stack 130 and annular fluid control device 132. Various portions of the schematic diagram 730 (e.g., fluid valves, gates) may change position and / or color to indicate to the wellsite operator 195 the operating status (e.g., position) of such wellsite equipment. The main operating status area 716 may also display sensor signals or information indicating the operating status of the wellsite equipment within a text box 732 positioned in association with the schematic diagram 730 of the wellsite equipment. The secondary operating status area 718 may display information related to the drilling operation and / or additional information related to the operating status of the WC system 315, such as additional information not displayed in the primary operating status area 716. As described above, the description area 720 may display information indicating an operational event. However, the description area 720 may also or alternatively display a work plan related to tripping, drilling, or other well site construction operations. A PIP video window 722 showing a real-time view of another portion of the BOP equipment 130, 132 or the WC system 315 may be displayed in the primary operating status area 716 or another area of the WC system status screen 706.
[0156] Fig. 22is a schematic diagram of at least a portion of an exemplary implementation of a system (or processing device) 800 according to one or more aspects of the present disclosure. The system 800 may form at least a portion of one or more electronic devices used at the well construction system 100, 200. For example, the system 800 may be or form at least a portion of the processing device 188, 192, 456 and the control workstation 450, 452, 454, 500. The system 800 may form at least a portion of the control system 300, including the wellsite computing resource environment 305, the coordination control device 304, the monitoring system 307, the local controllers 341-346, the on-site user device 302 and the off-site user device 303. The following description collectively refers to Figures 1 to 7 and Fig. 22 .
[0157] The well construction system 100, 200 also includes fixed and / or mobile cameras 198 disposed or used at various locations of the well construction system 100, 200. The cameras 198 capture video of various portions, equipment, or subsystems of the well construction system 100, 200, and may capture wellsite operators 195 and the actions they perform during or otherwise in connection with wellsite operations, including actions performed when performing maintenance on the well construction system 100, 200. For example, the cameras 198 may capture digital images (or video frames) of the entire well construction system 100, 200 and / or specific portions of the well construction system 100, 200, such as the top drive 116, RN 151, TDA 202, FIB 166, pipe box 164, catwalk 131, and / or areas through which tubulars 111 are passed between components of the well construction system 100, 200, among other examples. The camera 198 generates a corresponding video signal (i.e., feedback) that includes or otherwise indicates the captured digital image. The camera 198 may be in signal communication with the processing device 192, such as to allow the video signal to be processed and transmitted to the control workstation 197, and thus allow the wellsite operator 195 to view various portions or components of the well construction system 100, 200 on one or more of the output devices 196. Another portion of the processing device 192 or the control workstation 197 may be operable to record the video signal generated by the camera 198.
[0158] The system 800 may include a network ring 900 that electronically interconnects a plurality of drilling / analysis equipment and / or a control mechanism for at least partially automating such equipment. On the network ring 900, there may be a plurality of ring network nodes 801 that electrically connect the various elements of the well construction system 100, 200 or the control system 300 to each other. For example, a first control workstation 850 (e.g., which may include or may be Figure 5 and Figure 6 The first control station 450 and / or Figure 7 The wellsite operator control workstation 500 shown) and optionally a second control workstation 852 (e.g., which may include or may be Figure 5 and Figure 6 The second control workstation 452 and / or Figure 7 The well site operator control workstation 500 shown in the figure can be electrically connected to the network ring 900 through one or more of the plurality of ring network nodes 801. Optionally, the network ring 900 can be electrically interconnected with a telephone system including one or more telephone lines through one or more ring network nodes 801. For example, in Fig. 22 Five VOIP (Voice over Internet Protocol) lines 881-885 are shown, but there may be more or fewer telephone lines to accommodate various numbers of users, workstations, etc.
[0159] Programmable logic controllers (PLCs) 901, 911, 921, 931, 941, 951, 961, 971, 981, 991 are also each connected to the network ring 900 via a corresponding ring network node 801, thereby facilitating communication between the first control workstation 850 and the second control workstation 852 and the well construction and / or control subsystems (for example, in particular the RC subsystem 311, the FC subsystem 312, the MPDC subsystem 313, the CPC subsystem 314, the WC subsystem 315 and the CCTV subsystem 316). Each PLC 901, 911, 921, 931, 941, 951, 961, 971, 981, 991 may be electrically connected to its own subsystem network ring 909, 919, 929, 939, 949, 959, 969, 979, 989, 999, each of which is electrically connected to its corresponding PLC and / or electrically connected to one or more other equipment pieces through a subsystem ring network node 809, 819, 829, 839, 849, 859, 869, 879, 889, 899. For example, a programmable logic subsystem controller, a processing device and / or a sensor 902, 903, 904, 905 may each be electrically connected to a subsystem network ring 909 through a corresponding subsystem ring network node 809, and the subsystem network ring is also electrically connected to the PLC 901 through its own subsystem ring network node 809, thereby forming a ring network subsystem. Although four PLC / sensor / processing devices 902-905 are shown as Fig. 22 The subsystem network ring 909 in FIG. 1 is connected to the PLC 901, but it should be understood that more or fewer such devices may be electrically connected thereto and / or that there may be more than one type of such device electrically connected thereto in a given ring network subsystem. Similar ring network subsystems are shown in FIG. Fig. 22900, each ring network subsystem is electrically connected to additional PLCs 911, 921, 931, 941, 951, 961, 971, 981, 991 and additional PLC / sensor / processing devices 912-915, 922-925, 932-935, 942-945, 952-955, 962-965, 972-975, 982-924, 992-995 via corresponding subsystem network rings 919, 929, 939, 949, 959, 969, 979, 989, 999 via corresponding ring network nodes 801. Again, although in Fig. 22 Although four workstations 992-995 are shown as being connected to PLC 991 via subsystem network ring 999, and although three cameras 982-984 are shown as being connected to PLC 981 via subsystem network ring 989, it will be understood that more or fewer such devices may be electrically connected thereto and / or that there may be more than one type of such device electrically connected thereto in any given ring network subsystem.
[0160] Fig.23 1 is a schematic diagram of at least a portion of an exemplary implementation of a processing device 1000 according to one or more aspects of the present disclosure. One or more electronic devices utilized at the well construction system 100, 200 may each be, include, or be formed by at least a portion of the processing device 1000. For example, the processing devices 188, 192, 456, the BOP control station 470, the control workstations 450, 452, 454, 500, 850, 852, 992, and the CPUs 901-981 may each be, include, or be formed by at least a portion of an instance of the processing device 1000. An instance of the processing device 1000 or a portion thereof may form at least a portion of the control system 300, including the wellsite computing resource environment 305, the coordination control device 304, the monitoring system 307, the local controllers 341-346, the on-site user devices 302, and the off-site user devices 303.
[0161] The processing device 1000 may communicate with various sensors, actuators, controllers, and other devices of the subsystems 311-316 and / or other parts of the well construction system 100, 200. The processing device 1000 may be operable to receive coded instructions 1032 and sensor data 351-356 generated by sensors 321-326 from the wellsite operator 195 via the wellsite control workstation 500, 850, 852, process the coded instructions 1032 and sensor data 351-356, and communicate control data 361-366 to the local controllers 341-346 and / or actuators 331-336 of the subsystems 311-316 to execute the coded instructions 1032 to implement at least a portion of one or more of the exemplary methods and / or operations described herein and / or to implement at least a portion of one or more of the exemplary systems described herein.
[0162] The processing device 1000 may be or include, for example, one or more processors, a dedicated computing device, a server, a personal computer (e.g., a desktop computer, a laptop computer, and / or a tablet computer), a personal digital assistant, a smart phone, an Internet appliance, and / or other types of computing devices. The processing device 1000 may include a processor 1012, such as a general-purpose programmable processor. The processor 1012 may include a local memory 1014 and may execute coded instructions 1032 present in the local memory 1014 and / or another memory device. The processor 1012 may, among other things, execute machine-readable coded instructions 1032 and / or other instructions and / or programs for implementing the exemplary methods and / or operations described herein. The programs stored in the local memory 1014 may include program instructions or computer program code, which, when executed by the processor 1012 of the processing device 1000, may cause the subsystems 311-316 of the well construction system 100, 200 and / or individual wellsite equipment items to perform the exemplary methods and / or operations described herein. The processor 1012 may be, include or be implemented by one or more processors of various types suitable for the local application environment, and may include, as non-limiting examples, one or more of a general-purpose computer, a special-purpose computer, a microprocessor, a digital signal processor (DSP), a field programmable gate array (FPGA), an application-specific integrated circuit (ASIC), and a processor based on a multi-core processor architecture. Of course, other processors from other families are also applicable.
[0163] The processor 1012 may communicate with the main memory 1016 (such as may include volatile memory 1018 and non-volatile memory 1020), possibly through a bus 1022 and / or other communication means. The volatile memory 1018 may be, include, or be implemented by a random access memory (RAM), a static random access memory (SRAM), a synchronous dynamic random access memory (SDRAM), a dynamic random access memory (DRAM), a RAMBUS dynamic random access memory (RDRAM), and / or other types of random access memory devices. The non-volatile memory 1020 may be, include, or be implemented by a read-only memory, a flash memory, and / or other types of memory devices. One or more memory controllers (not shown) may control access to the volatile memory 1018 and / or the non-volatile memory 1020.
[0164] The processing device 1000 may also include an interface circuit 1024. The interface circuit 1024 may be, include, or be implemented by various types of standard interfaces, such as an Ethernet interface, a universal serial bus (USB), a third generation input / output (3GIO) interface, a wireless interface, a cellular interface, and / or a satellite interface, etc. The interface circuit 1024 may also include a graphics driver card. The interface circuit 1024 may also include a communication device, such as a modem or a network interface card for facilitating data exchange with an external computing device through a network (e.g., an Ethernet connection, a digital subscriber line (DSL), a telephone line, a coaxial cable, a cellular telephone system, a satellite, etc.). One or more of the local controllers 341-346, the sensors 321-326, and the actuators 331-336 may be connected to the processing device 1000 through the interface circuit 1024, such as to facilitate communication between the processing device 1000 and the local controllers 341-346, the sensors 321-326, and / or the actuators 331-336.
[0165] One or more input devices 1026 may also be connected to the interface circuit 1024. The input device 1026 may allow the well site operator 195 to enter coded instructions 1032, such as control commands, processing routines, and / or operating settings and set points. The input device 1026 may be, include, or be implemented by a keyboard, a mouse, a joystick, a touch screen, a track pad, a trackball, an isopoint, and / or a voice recognition system, among other examples. One or more output devices 1028 may also be connected to the interface circuit 1024. The output device 1028 may be, include, or be implemented by a video output device (e.g., an LCD, LED display, a touch screen, etc.), a printer, and / or a speaker, among other examples. The processing device 1000 may also communicate with one or more mass storage devices 1030 and / or removable storage media 1034, such as may be or include a floppy disk drive, a hard drive, a compact disk (CD) drive, a digital versatile disk (DVD) drive, and / or a USB and / or other flash drive, among other examples.
[0166] The coded instructions 1032 may be stored in the mass storage device 1030, the main memory 1016, the local memory 1014, and / or the removable storage medium 1034. Thus, the processing device 1000 may be implemented in hardware (perhaps in one or more chips including an integrated circuit (such as an ASIC)), or may be implemented as software or firmware for execution by the processor 1012. In the case of firmware or software, the implementation may be provided as a computer program product including a non-transitory computer-readable medium or storage structure on which computer program code (i.e., software or firmware) is embodied for execution by the processor 1012. The coded instructions 1032 may include program instructions or computer program code that, when executed by the processor 1012, may cause the various subsystems 311-316 of the well construction system 100, 200 or individual wellsite equipment items to perform the intended methods, processes, and / or operations disclosed herein.
[0167] In the exemplary operational sequence described below, among other matters within the scope of the present disclosure, the pipe handling equipment may be automatically operated by the construction program, and the step execution of the pipe handling equipment may be automatically controlled by one or two operators 195 at one or more associated workstations 450, 452, 454. The construction program may also have a configurable step confirmation feature. Each sequence controlled by the construction program may be stopped or interrupted at any time, and some or all functions may be manually operated by one or two operators 195 at one or more associated workstations 450, 452, 454.
[0168] Various well construction operations may be performed using different combinations of the above aspects. For example, when a downhole operation is to be performed, an operator 195 on the rig floor 114 may confirm that various equipment pieces have been properly closed and locked, and then may perform other preparations, such as the examples listed below in Table 1A.
[0169]
[0170] Table 1A: Drilling Preparation
[0171] The well construction system 100, 200 may then be set up for a downhole sequence. An example of such a setup may be as listed below in Table 1B.
[0172]
[0173]
[0174] Table 1B: Drill-down settings
[0175] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). The run-in sequence begins with the top drive 116 in a lowered position, with the elevators 129 closed, the slips 161 closed, and a portion (e.g., about one meter) of the drill string 120 (referred to as the "extended portion") protruding above the slips 161. The TDA 202 (and possibly the LSA 228) has lifted the tubular 111 from the THP 207 to an extended level above the MOH 204. The THP 207 is empty, and the UTC 242 and LTC 244 are open and retracted. The TBR 254 and SGA 262 may also be empty and may be moving to lift new tubulars 111 from the vertical pipe rack assembly 165. The top drive elevators 129 are then opened and retracted from the extended height.
[0176] The top drive 116 is then moved to top dead center by operation of the DW 119. The TDA 202 (possibly in coordination with the LSA 228) then moves a new tubular 111 above the well center 203 (WC). The RN 151 also moves toward the WC 203. During this time, the TBR 254 and SGA 262 operate to remove another tubular 111 from the pipe box 164 and FIB 166. The location from which this additional tubular 111 is removed may be selected automatically or by input from the operator 195 at the control workstation 450, 452, 454. For example, a "pipe handler" operator 195 seated at a control workstation 450 may typically control / monitor pipe handling equipment (e.g., equipment that manipulates tubulars 111 that are not connected to a drill string 120), while a "driller" operator 195 seated at a control workstation 452 may typically control / monitor the remaining equipment (or at least the equipment that manipulates the drill string 120).
[0177] The TBR 254 and SGA 262 then cooperate to move the currently held tubular 111 to the THP 207. The UTC 242 and LTC 244 then close to hold the new tubular 111. The thread compound applicator 209, which may be integrated into or otherwise associated with the THP 207, may then clean and compound the pin end of the new tubular 111. The TBR 254 and SGA 262 may then return to select the next tubular 111 from the vertical pipe rack assembly.
[0178] The stab shoe and / or backup tongs (BUT) of the RN 151 may then be closed to assist in stab. The TDA 202 then lowers the new tubular 111 to stab into the extension, possibly continuing a short distance (e.g., about one meter) after stab to provide space for the top drive elevator 129. The LSA 228 may then be opened and retracted from the WC 203. The RN 151 then performs a low torque spin and then a high torque "wrench" to make the tubular 111 up to the drill string 120.
[0179] The top drive 116, which has been hoisted to a height generally near the top of the new tubular 111 during this time, then extends to the WC 203 and closes the elevators 129 around the new tubular 111. At the same time, the TDA 202 and (perhaps) the LSA 228 move to the THP 207 for the next tubular 111, and the RN 151 opens and retracts away from the WC 203 to a standby position.
[0180] The DW 119 then raises the top drive 116 to lift the now extended drill string 120 and opens the slips 161, then lowers the top 116 to lower the drill string 120 into the wellbore 102. The slips 161 are closed again to leave the extension ready for the next tubular 111. During this time when the drill string 120 is lowered into the wellbore, the TDA 202 and (perhaps) the LSA 228 are extended and latched onto another new tubular 111 currently in the THP 207, and then the UTC 242 and LTC 244 are opened and retracted. Possibly guided by the LSA 228, the new tubular 111 is lifted from the root box level to the drilling (rig) floor level (e.g., about 9 meters). The box (top) end of the new tubular 111 can be threaded by another cleaning / threading oiling device (if selected).
[0181] This drill-down sequence is summarized in Table 1C listed below.
[0182]
[0183]
[0184]
[0185]
[0186] Table 1C: Drill-down Operations
[0187] When the pull-out operation is to be performed, the operator 195 on the drill floor 114 can confirm that the various equipment pieces have been properly closed and locked, and then may perform other preparations, such as the examples listed above in Table 1A. The well construction system 100, 200 can then be set up for the pull-out sequence. An example of such a setup may be as listed below in Table 2A.
[0188]
[0189] Table 2A: Drilling setup
[0190] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). An exemplary pull-up sequence may begin with the TD 116 in a lower position above the WC 203, with the slips 161 and elevators 129 closed, and with an extension of approximately one meter. The TDA 202 and LSA 228 are opened at the THP location 207 (the tubular 111 delivered from the WC 203 to the THP 207). The UTC 242 and LTC 244 are closed on the tubular 111 in the THP 207. The TBR 254 and SGA 262 are empty on the way from the FIB 166 to obtain the new tubular 111 in the THP 207. Exemplary steps of the pull-up sequence may be as listed below in Table 2B.
[0191]
[0192]
[0193]
[0194]
[0195] Table 2B: Tripping Operations
[0196] When a drilling connection is to be made, an operator 195 on the rig floor 114 may confirm that the various pieces of equipment have been properly closed and locked, and may then perform other preparations, such as the examples listed above in Table 1A. The well construction system 100, 200 may then be set up for making a drilling connection. Examples of such a setup may be as listed below in Table 3A.
[0197]
[0198]
[0199] Table 3A: Drilling connection settings
[0200] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured to be ready for remote control (e.g., by deactivating the emergency stop function). According to the drilling program execution, an exemplary drilling connection sequence may begin with the drill string 120 drilling all the way down, reaming, surveying, raising / lowering weights, etc. The tubulars 111 to be added to the drill string 120 and the TDA 202 / LSA 228 are lifted from the extended level to above the MOH 204. The THP 207 is empty, and the UTC 242 and LTC 244 are opened and retracted. The TBR 254 and SGA 262 are empty on the way from the FIB 166 to obtain the new tubular 111. The exemplary steps of the drilling connection sequence may be as listed below in Table 3B.
[0201]
[0202]
[0203]
[0204]
[0205]
[0206]
[0207] Table 3B: Drilling Connection Operations
[0208] Note that the exemplary drilling connection sequence listed above describes the RN 151 and THT used as BUT for the TD 116 during make-up and the option of tightening the lower connection with the RN 151 and tightening the lower connection with the TD 116 .
[0209] Various combinations of the above aspects may also be used to build stands of two or more tubulars 111. Such stand building may be performed during drilling and other operations performed at the WC 203. However, such simultaneous operations are coordinated to avoid conflicts and obstructions between different machines and systems. For example, the elevators of the TDA 202 may have two different sized inserts to allow for the construction of casing stands while drilling. The change in head size may be accomplished at a workstation 450 (or 452 or 454) remote from the pipe manipulator. When the stand building operation is to be performed, the operator 195 on the rig floor 114 may confirm that the various pieces of equipment are properly closed and locked, and may then perform other preparations, such as the examples listed below in Table 4A.
[0210]
[0211]
[0212] Table 4A: Preparation for stand construction
[0213] The well construction system 100, 200 may then be set up for stand pipe construction operations. An example of such a setup may be as listed below in Table 4B.
[0214]
[0215] Table 4B: Stand Construction Settings
[0216] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating an emergency stop function). An exemplary pipe build sequence may begin with the MOH 204 and THP 207 empty, the ITC 236 retracted, and the CW 131 feed station preloaded with tubulars (which may have been cleaned and thread compounded). Exemplary steps of the pipe build sequence may be as listed below in Table 4C. In such an example, the pipe handling equipment may be automatically operated by the construction program, and the execution of the steps of the pipe handling equipment may be automatically controlled by one or two operators 195 at one or more associated workstations 450, 452, 454, among other matters within the scope of the present disclosure. The construction program may also have a configurable step confirmation feature. The pipe build sequence controlled by the construction program may be stopped or interrupted at any time, and some or all functions may be manually operated by one or two operators 195 at one or more associated workstations 450, 452, 454.
[0217]
[0218]
[0219]
[0220]
[0221]
[0222]
[0223]
[0224] Table 4C: Stand Construction Operations
[0225] To drop the pipe stand (offline), the operator 195 on the rig floor 114 may confirm that the various pieces of equipment have been properly closed and locked, and then may perform other preparations, such as the examples listed above in Table 4A. The well construction system 100, 200 may then be set up for performing the drop operation. Examples of such a setup may be as listed below in Table 5A.
[0226]
[0227] Table 5A: Stand Setting Settings
[0228] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating an emergency stop function). An exemplary pipe stand drop sequence may begin with all machines empty, the ITC 236 retracted, and the CW 131FT empty and ready to receive a single tubular 111. Exemplary steps of a pipe stand drop sequence may be as listed below in Table 5B.
[0229]
[0230]
[0231]
[0232]
[0233]
[0234]
[0235]
[0236]
[0237]
[0238] Table 5B: Stand-off Operation
[0239] Various combinations of the above aspects may also be used to lift a single tubular 111 prior to assembling a stand of two or more tubulars. Such operations may be performed during drilling and other operations performed at the WC 203. However, such simultaneous operations are coordinated to avoid conflicts and obstructions between different machines and systems. Preparations for lifting a single tubular 111 may include the examples listed below in Table 6A.
[0240]
[0241]
[0242] Table 6A: Single Wire Lift Preparation
[0243] The well construction system 100, 200 may then be set up for a pull-up operation. An example of such a set-up may be as listed below in Table 6B.
[0244]
[0245]
[0246] Table 6B: Single lift settings
[0247] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). An exemplary single-stand pull sequence may begin with the extension at WC 203, and CW 131FT pre-loaded with tubulars 111 (which may have been cleaned and thread compounded). Exemplary steps of a stand build sequence may be as listed below in Table 6C.
[0248]
[0249]
[0250]
[0251]
[0252] Table 6C: Single Wire Lifting Operation
[0253] Different combinations of the above aspects can also be used to lower a single tubular 111 from the WC 203 using the top drive 116. Such an operation can be performed during drilling and other operations performed at the WC 203. However, such simultaneous operations are coordinated to avoid conflicts and obstacles between different machines and systems. Preparation for this lowering operation can include the examples listed below in Table 7A.
[0254]
[0255] Table 7A: Preparation for a single laydown from WC to CW using TD
[0256] The well construction system 100, 200 may then be set up for a pull-up operation. An example of such a setup may be as listed below in Table 7B.
[0257]
[0258] Table 7B: Settings for a single drop from WC to CW using TD
[0259] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). This sequence may begin with the top drive 116 in a lowered position at the WC 203, with the elevators 129 closed, with the slips 161 closed, and with the catwalk ramp 149 empty and in a drill floor 114 loading position (ready to move to the drill floor 114). The catwalk feed station may be unloaded and ready to receive the tubular 111, and the TDA 202 may be parked outside of a potential collision zone. Exemplary steps of the sequence may be as listed below in Table 7C.
[0260]
[0261]
[0262]
[0263]
[0264] Table 7C: Setup sequence for single laydown from WC to CW using TD
[0265] Various combinations of the above aspects may also be used to run casing from CW 131 with a casing tong (CTO). Preparation for such an operation may include the examples listed below in Table 8A.
[0266]
[0267] Table 8A: Preparation for running the cannula from CW using CTO
[0268] The well construction system 100, 200 may then be set up for operation. An example of such a setup may be as listed below in Table 8B.
[0269]
[0270] Table 8B: Settings for running the cannula from CW using CTO
[0271] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). An example of this sequence may begin with the casing extended at the WC 203, with the slips 161 and TD 116 elevators 129 closed. The casing may be arranged on the casing side of the CW 131 (e.g., the driller's side), cleaned, thread compounded, and counted, and the protector removed. The catwalk ramp 149 may be empty and in a loading position. Exemplary steps of the sequence may be as listed below in Table 8C.
[0272]
[0273]
[0274]
[0275] Table 8C: Sequence for running the cannula from CW using CTO
[0276] When a "wet" (when the drill string 120 is full of mud) tripping operation is to be performed, the operator 195 on the rig floor 114 may confirm that the various pieces of equipment are properly closed and locked, and then may perform other preparations, such as the examples listed below in Table 9A.
[0277]
[0278] Table 9A: Wet Drilling Preparation
[0279] The well construction system 100, 200 may then be set up for a wet pull-out sequence. An example of such a setup may be as listed below in Table 9B.
[0280]
[0281]
[0282] Table 9B: Wet Drilling Settings
[0283] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). An exemplary wet pull-out sequence may begin with the TD 116 in a lower position above the WC 203, with the slips 161 and elevators 129 closed, and with an extension of approximately one meter. The TDA 202 and LSA 228 are opened at the THP 207 location (the tubular 111 delivered from the WC 203 to the THP 207). The UTC 242 and LTC 244 are closed on the tubular 111 in the THP 207, and the ITC 236 is opened and retracted. The TBR 254 and SGA 262 are empty on their way from the FIB 166 to acquire the new tubular 111 in the THP 207. Exemplary steps of a wet pull-out sequence may be as listed below in Table 9C.
[0284]
[0285]
[0286]
[0287]
[0288] Table 9C: Wet Drilling Operations
[0289] When a back-reaming operation is to be performed, the operator 195 on the rig floor 114 may confirm that the various pieces of equipment have been properly closed and locked, and may then perform other preparations, such as the examples listed above in Table 9A. The well construction system 100, 200 may then be set up for the back-reaming sequence. Examples of such a setup may be as listed below in Table 10A.
[0290]
[0291] Table 10A: Back scribe settings
[0292] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). An exemplary back-ream sequence may begin with the top drive 116 in a lowered position and retracted (elevator bail vertical), the slips 161 closed, and the TDA 202 and LSA 228 open in the THP 207. The UTC 242 and LTC 244 may be closed on the tubular 111 in the THP 207, with the ITC 236 open and retracted, and the TBR 254 and SGA 262 (on their way from the FIB 166 to retrieve the next tubular 111 in the THP 207) empty. Exemplary steps of a back-ream sequence may be as listed below in Table 10B.
[0293]
[0294]
[0295]
[0296]
[0297]
[0298] Table 10B: Back-marking operation
[0299] For running the drill collar stand, the operator 195 on the drill floor 114 may confirm that the various pieces of equipment have been properly closed and locked, and then may perform other preparations, such as the examples listed below in Table 11A.
[0300]
[0301] Table 11A: Preparation for pulling out drill collar stand
[0302] The well construction system 100, 200 may then be set up for a downhole sequence. An example of such a setup may be as listed below in Table 11B.
[0303]
[0304]
[0305] Table 11B: Drill collar stand settings
[0306] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating an emergency stop function). The sequence for running a drill collar stand may begin with the drill collar stand 111 extended at the WC 203, with the top drive 116 elevators 129 closed on the extended portion and the slips 161 closed. The UTC 242 and LTC 244 may be closed on another drill collar stand 111 in the THP 207, with the cleaning and thread compounding of the pins completed. The TDA 202, LSA 228, TBR 254, and SGA 262 may each be empty. Exemplary steps of a drill collar stand running sequence may be as listed below in Table 11C.
[0307]
[0308]
[0309]
[0310]
[0311]
[0312] Table 11C: Drill collar stand operation
[0313] Various combinations of the above aspects may also be used to run casing from CW 131 using TDA 202 and casing running tool (CRT). Preparation for such an operation may include the examples listed below in Table 12A.
[0314]
[0315] Table 12A: Preparation of bushing to run from CW using TDA and CRT
[0316] The well construction system 100, 200 may then be set up for operation. An example of such a setup may be as listed below in Table 12B.
[0317]
[0318] Table 12B: Settings for running the bushing from CW using TDA and CRT
[0319] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). An example of this sequence may begin with the casing extended at the WC 203, with the slips 161 closed and the CRT engaged. The casing, which has been cleaned, thread compounded, and counted, may be arranged on the casing side of the CW 131 (e.g., the driller's side), and the protector removed. The TDA 202 and LSA 228 may hold the casing 111 in a standby position on the drill floor 114. Exemplary steps of the sequence may be as listed below in Table 12C.
[0320]
[0321]
[0322]
[0323]
[0324] Table 12C: Sequence for running the cannula from CW using CTO
[0325] Different combinations of the above aspects may also be used to build two or more casing stand pipes. Such casing stand construction may be performed during drilling and other operations performed at the WC 203. However, such simultaneous operations are coordinated to avoid conflicts and obstructions between different machines and systems. For example, the elevator of the TDA 202 may have two different sized inserts to allow casing stands to be built while drilling. The change in head size may be accomplished at a workstation 450 (or 452 or 454) remote from the pipe manipulator. When the casing stand construction operation is to be performed, the operator 195 on the rig floor 114 may confirm that the various equipment pieces are properly closed and locked, and may then perform other preparations, such as the examples listed below in Table 13A.
[0326]
[0327]
[0328] Table 13A: Casing stand construction preparation
[0329] The well construction system 100, 200 may then be set up for a casing stand construction operation. An example of such a setup may be as listed below in Table 13B.
[0330]
[0331] Table 13B: Casing stand construction settings
[0332] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating an emergency stop function). An exemplary casing stand construction sequence may begin with the MOH 204 and THP 207 empty, the ITC 236 retracted, and the CW 131 feed station preloaded with casing singles (which may have been cleaned and threaded with thread compound). Exemplary steps of the casing stand construction sequence may be as listed below in Table 13C. In such an example, among other matters within the scope of the present disclosure, the pipe handling equipment may be automatically operated by the construction program, and the execution of the steps of the pipe handling equipment may be automatically controlled by one or two operators 195 at one or more associated workstations 450, 452, 454. The construction program may also have a configurable step confirmation feature. The casing stand construction sequence controlled by the construction program may be stopped or interrupted at any time, and some or all functions may be manually operated by one or two operators 195 at one or more associated workstations 450, 452, 454.
[0333]
[0334]
[0335]
[0336]
[0337]
[0338]
[0339] Table 13C: Casing Stand Construction Operations
[0340] For running a casing stand without a CRT, an operator 195 on the rig floor 114 may confirm that the various pieces of equipment are properly closed and locked, and then may perform other preparations, such as the examples listed below in Table 14A.
[0341]
[0342]
[0343] Table 14A: Preparation for running casing stand without CRT
[0344] The well construction system 100, 200 may then be set up for a non-CRT casing stand run-in sequence. An example of such a setup may be as listed below in Table 14B.
[0345]
[0346]
[0347] Table 14B: Casing stand settings without CRT
[0348] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating the emergency stop function). The sequence for non-CRT running a casing stand may begin with the top drive 116 in the lower position at the WC 203, with the slips 161 closed around the approximately one meter of casing extension. Another casing stand 111 may be in the TDA 202 / LSA 228, lifted from the THP 207 to an extended level above the MOH 204, with the TDA 202 elevators facing the top drive 116. The THP 207, UTC 242, and LTC 244 may have been opened and retracted. The TBR 254 and SGA 262 may be empty (e.g., on the way from the FIB 166 to lift a new casing stand). Exemplary steps of a sequence for non-CRT drilling a casing stand may be as listed below in Table 14C.
[0349]
[0350]
[0351]
[0352]
[0353]
[0354] Table 14C: Running casing stand without CRT operation
[0355] Various combinations of the above aspects may also be used to run large diameter casing (LDC) from CW 131 using top drive 116 and CRT. For example, the LDC may have an outer diameter of about 13.375 inches (about 34 centimeters) or more. Preparations for such an operation may include the examples listed below in Table 15A.
[0356]
[0357]
[0358] Table 15A: Preparation for LDC operation from CW using TD and CRT
[0359] The well construction system 100, 200 may then be set up for operation. An example of such a setup may be as listed below in Table 8B.
[0360]
[0361]
[0362] Table 15B: Settings for LDC operation from CW using TD and CRT
[0363] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured to be ready for remote control (e.g., by deactivating the emergency stop function). An example of this sequence may begin with the casing extended at the WC 203 (e.g., about 1.5 meters), with the slips 161 closed and the CRT engaged. The casing, which has been cleaned, thread oiled, and counted, may be arranged on the casing side of the CW 131 (e.g., the driller's side), and the protector removed. The catwalk ramp 149 may be loaded with casing. The TDA 202 may be parked outside the collision zone (e.g., the top of the mast), and the LSA 228 may be ready. Exemplary steps of the sequence may be as listed below in Table 15C.
[0364]
[0365]
[0366]
[0367]
[0368] Table 15C: Sequence for LDC operation from CW using TD and CRT
[0369] For pulling out the drill collar stand, the operator 195 on the rig floor 114 can confirm that the various equipment pieces have been properly closed and locked, and then possibly perform other preparations, such as the examples listed above in Table 11A. The well construction system 100, 200 can then be set up for the drill collar stand pulling sequence. An example of such a setup can be as listed below in Table 16A.
[0370]
[0371]
[0372] Table 16A: Drill collar stand settings
[0373] After such preparation and setup, the operator 195 may vacate the drill floor 114, and the equipment may be configured ready for remote control (e.g., by deactivating an emergency stop function). The sequence for pulling out a drill collar stand may begin with the drill collar stand 111 extended at the WC 203, with the top drive 116 elevators 129 closed on the extended portion and the slips 161 closed. The UTC 242 and LTC 244 may be closed on another drill collar stand 111 in the THP 207, with the cleaning and thread compounding of the pins completed. The TDA 202 may be parked outside the collision zone, and the LSA 228, TBR 254, and SGA 262 may each be empty. Exemplary steps of a drill collar stand pulling out sequence may be as listed below in Table 16B.
[0374]
[0375]
[0376]
[0377]
[0378] Table 16B: Pulling out drill collar stand operation
[0379] The zone management system (ZMS) mentioned in the above sequence defines zones for each physical component of the IWCS where collisions will be avoided. The zones are three-dimensional spaces defined according to the common coordinate system of the IWCS. Each zone is associated with one or more different pieces of equipment, including those structures or components that are fixed as part of the IWCS. The zones are attached to the equipment and travel with the equipment. The size of the zone can be changed (expanded or reduced) depending on the transportation speed of the relevant equipment or the transportation speed of the surrounding equipment. Some machinery and equipment are complex enough that it is necessary to use multiple zones within the machinery, and the ZMS maintains information related to the zones of different sub-components. The ZMS monitors the zones to prevent collisions.
[0380] Fig.24 Component 1140 is depicted as the subject of a ZMS. Component 1140 may be any component of an IWCS. Component 1140 has a region 1141 that at least partially encloses component 1140. Region 1141 may be larger than component 1140 such that a buffer zone is formed between an end of component 1140 and region 1141 to further help avoid collisions between components. Database 1142 stores characteristics of components tracked by the ZMS. Database 1142 may store information related to location, size, shape, weight, motion path, tolerances, impact sensitivity, reference points, center of mass 1143, and attachment points. A processing system 1144 of the ZMS may perform logic and calculations. Processing system 1144 may be Fig.23 An example of a processing system 1000 is shown in FIG.
[0381] The position of the component 1140 can be expressed in terms of coordinates relative to one or more coordinate systems. Each coordinate system can be an xyz system, a polar coordinate system, or another type of coordinate system. A coordinate system can be centered at any arbitrary point, such as the drill floor 114 ( Figure 1 ) or the intersection of the center of the well with the rig floor 114, among other examples. The location of the component 1140 is monitored and continuously compared with the locations of other related components of the IWCS. The location information of the component and the size and / or shape information of the component can be used to describe the equipment and its associated zone in the three-dimensional coordinate system space in relation to other components of the IWCS. The ZMS system can detect when a collision between two or more components is imminent and, accordingly, issue a warning or take action to prevent the collision.
[0382] The component sizes are stored by database 1142 to assist in calculating area 1141. Database 1142 may be Fig.23 1000 . Database 1142 may store the size of component 1140 according to coordinates at each end of component 1140. If component 1140 has a generally cubic shape, the size may be described by the edges and orientation of the cube or other coordinate system. If the shape of component 1140 is more complex, more coordinates may be used to define the size and shape. The size and / or shape information of each component 1140 is used to define the corresponding size and / or shape of the associated zone 1141. Zone 1141 may completely enclose physical component 1140, or may only cover a portion of physical component 1140 that may collide with other components 1140. The size of zone 1141 may also expand in a direction aligned with the movement of the component 1140 and / or in another direction approaching component 1140. The extent of this expansion may depend on the speed of one or more moving components 1140.
[0383] The database 1142 also tracks the weight of the component 1140, which the ZMS can use to determine the amount of force required to move or stop the motion of the component 1140. The weight of the component 1140 may be known, such as when entered during sequence setup, while in other cases, the IWCS may include a sensor configured to determine the weight of the component 140. For example, if the component 1140 is a top drive 116 connected to a drill string 120, the weight of the component 1140 varies depending on the length of the drill string 120 and other parameters. The sensor may perform a weight measurement to determine the required weight.
[0384] The positions of the various components 1140 of the IWCS change from time to time. The movement path of each component 1140 may also be stored by the database 1142. The movement path of the component 1140 may be a complete path, such as when the component 1140 can travel from one position to another. Alternatively, the movement path of the component 1140 may be only the direction in which the component 1140 can travel, without a defined endpoint. The database 1142 may store routine movement paths of the components 1140. For example, the iron roughneck 151 has a movement path between the retracted position and the deployed position. The trajectory of the path may be known in advance. The ZMS processing system 1144 may be informed of the proposed movement path of a given component 1140, and may calculate whether the component 1140 can make the proposed movement at the proposed time without intersecting with the zone of another component of the IWCS. If so, the ZMS processing system 1144 approves the movement. Alternatively, when the component 1140 is commanded to move in a specific direction, the zone 1141 associated with the component 1140 may be expanded in the direction of the expected movement. The extent to which the zone 1141 is enlarged may depend on the speed of the associated component 1140. Using the enlarged zone 1141 of the component 1140, the ZMS processing system 1144 can calculate whether the enlarged zone 1141 may intersect with the zone 1141 of another component 1140 of the IWCS. If not, the ZMS processing system 1144 approves the movement. In addition, when the component 1140 is commanded to move in a particular direction, the zones 1141 associated with the surrounding components 1140 that may come into contact with the moving component 1140 may be enlarged in the direction of the incoming component 1140. The extent to which the zone 1141 is enlarged may depend on the speed of the incoming component 1140. The ZMS processing system 1144 may perform similar calculations to evaluate whether a zone 1141 intersection may occur and react accordingly. The movement of the component 1140 may be performed under the guidance and control of the construction program, so the actions controlled by the construction program may be approved by the ZMS processing system 1144 to prevent collisions between components 1140.
[0385] The movement of one or more portable components may be unplanned. A portable component is an object that is not part of the IWCS equipment, but may exist during operation. For example, a human operator 195 on the drilling floor 114 may be a portable object. The ZMS processing system 1144 is equipped to detect and monitor the unplanned movement of portable components. For example, the various cameras, sensors and other measurement equipment described above can be used to identify portable components and detect their movement. The ZMS processing system 1144 can establish a zone associated with a portable component, assess the risk of collision with surrounding equipment, and issue a warning and / or take action to prevent a collision. The ZMS processing system 1144 can move other components 1140 away, or can stop the movement of other components 1140 to avoid a collision. The ZMS processing system 1144 can also calculate the expected damage of a given collision, and may include logic for allowing the ZMS processing system 1144 to determine a course of action under a given set of circumstances. For example, if the ZMS processing system 1144 detects that the top drive 116 is moving downward toward the drill floor 114 when the operator 195 is walking toward the center of the well, the ZMS processing system 1144 may immediately establish a zone 1141 around the operator 195 and evaluate whether this zone 1141 will intersect with a zone 1141 associated with the top drive 116. Based on the safety policy established for the operation, the ZMS processing system 1144 may take a variety of actions to avoid a collision between the top drive 116 and the operator 195, such as triggering an alarm, slowing the movement of the top drive 116, and / or emergency stopping of the top drive 116, among other examples.
[0386] Database 1142 can store information related to the tolerance of a given component 1140. The tolerance can be defined as the distance from the edge of the physical structure of the component 1140 to the corresponding edge of the defined area 1141. The properties of the component 1140 and the environment in which this component is used can be taken into account when determining the tolerance. Generally, the faster the speed of the component 1140, the greater the tolerance in the direction of movement. Alternatively, the faster the speed of the incoming component 1140, the greater the tolerance in the direction of the incoming component 1140. It is also possible that the more sensitive the component 1140 is, the greater the tolerance may be. The constraints of the environment may also determine what the tolerance is. For example, if the component 1140 is to be installed in a predetermined space next to another component, the tolerance can be adjusted accordingly to avoid triggering an alarm or corrective action when installed in the desired position. The tolerance can also be changed during movement, so that when a given component 1140 is stationary, the tolerance can be smaller, and when the component 1140 moves, the tolerance (and therefore the area 1141) can be temporarily increased.
[0387] Various components are made of different materials, and some components are more fragile than others. The impact resistance of the component can be taken into account in the calculation of the zone 1141. The concept of impact sensitivity may not only be physical impact, but also may include chemical, thermal, vibration, and electromagnetic contact. Therefore, the zone 1141 of the component 1140 can be increased or decreased according to the impact, chemical, thermal, vibration, electromagnetic, and other sensitivities of the component 1140.
[0388] Components 1140 typically each have a physical body, and in order to correctly resolve the position of component 1140 and its proximity to other components, a reference point can be given to component 1140, and the size of component 1140 can be defined with reference to the reference point. The reference point can be selected arbitrarily, or it can have a certain importance. For example, the reference point can coincide with the center of mass 1143, an important angle, an edge, or another important point on component 1140. If component 1140 is routinely rotated, the reference point and geometry of component 1140 can be updated when it is rotated during maintenance. The area 1141 associated with the component can also be updated accordingly. Some components 1140 have attachment points, such as hooks, rails, slides, eyes, bolt forms, or other physical connection points. This information can also be stored in a database 1142 to allow manipulation of components. In the event of an impending collision, information about the location of the attachment point may prove useful, and it can be determined what course of action was taken to prevent or mitigate the collision. Another type of attachment point is a port, such as a valve, an electrical socket / port, etc. Knowing the location and existence of these attachment points and ports may also prove useful and determine actions taken by the systems and methods of the present disclosure.
[0389] Different priorities may be associated with different components 1140. Each component 1140 may be given a priority relative to the other components, and if there are two competing move proposals, the higher priority component may be given the green light, while the lower priority component will have to wait or find another move path. The higher priority component may be referred to as the command component, while the lower component may be referred to as the lower component or slave component.
[0390] According to the drilling rig control system of the present disclosure (which can be used with Fig. 22 The system 800 shown in FIG. 8 may include: a communication network (e.g., from Fig. 22 Ring network 900); control workstations directly connected to the communication network (e.g., from Fig. 22 One or more control workstations 850 and / or 852); a plurality of control devices, each directly connected to the communication network, at least some (possibly each) of which may include or may be a computer (PC or IPC) and / or a programmable logic controller (PLC) (e.g., from Fig. 22PLC 901, 911, 921, 931, 941, 951, 961, 971, 981, 991); each of the plurality of local control networks connected to the communication network through a corresponding control device in the plurality of control devices (e.g., from Fig. 22 and a plurality of local control devices, at least some (and possibly each) of which may include or may be a computer (PC or IPC) and / or a programmable logic controller (PLC) (e.g., from Fig. 22 The plurality of local control devices may be connected to a corresponding local control network in the plurality of local control networks (e.g., directly) and each of the local control devices may be connected to a corresponding local control network in the plurality of local control networks (in which case each local control network may be indirectly connected to a larger communication network). The communication network may include or may be a single ring, star, or daisy chain network, and / or may be fiber optic. Each of the plurality of control devices may perform, be caused to perform, sense, measure, monitor, record actions (e.g., mechanical, software, or other actions) of a surface or downhole component (or group thereof), subsystem (or group thereof), and / or system (or group thereof), and / or similarly perform the actions. Each of the plurality of control devices may communicate directly or indirectly with each other with the plurality of control devices by virtue of their connection through the communication network. In an advantageous embodiment, the communications network is configured such that a plurality of control devices (and / or a plurality of local control devices) can (and in some embodiments do) execute substantially all of the control logic included in the direct operation of the various tools / equipment and / or array of subsystems controlled by the rig control system, while the control workstation, for example, exchanges data including, as, and / or derived from, user input data with the plurality of control devices (and / or via a plurality of local control networks), with the plurality of local control devices, and therefore ultimately with the various tools / equipment / subsystems controlled by the rig control system, by, essentially consisting of, or as operating parameters and / or user input data for multi-tool / multi-subsystem tasks.
[0391] In this or another embodiment, or as an independent embodiment, an analysis while drilling (AWD) control system according to the present disclosure (which can be used with Fig. 22The AWD control system may be operable to display and / or utilize a plurality of drilling-related parameters that may be and / or have been input by a user and / or that may be and / or have been calculated by one or more algorithms (e.g., based on parameters that may be or have been input by a user). The AWD control system may utilize as input data drilling-related parameters relating to well configuration, drill string (including BHA) configuration, drilling-related sensor data / parameters (e.g., mud pit level sensor, riser pressure sensor, mud flow sensor, etc.), and drilling equipment data / parameters (e.g., directly from corresponding equipment, such as drill string revolutions per minute (RPM), make-up torque, mud pump SPM, etc.). The AWD control system may provide output data that may be delivered to and / or used by: one or more workstation displays (e.g., including an AWD display); a historical logging system (e.g., which may include, for example, a log from a well); Figure 3 and Figure 4 206), a mud logging system (e.g., which may include a remote computing resource environment such as from Figure 3 and Figure 4 AWD control system output data may include: drilling operation warnings and alarms, well overflow calculators and kill logs; sensor data and sensor data calculations stored in historical trending / logging systems, dynamic tracking of data / parameters related to / indicative of a predetermined set of operating parameters, parameters and / or other information indicating well configuration, and / or parameters and / or other information indicating drill string (e.g., including BHA) configuration. A predetermined set of operating parameters may include, but are not necessarily limited to: well depth / shape; bit depth; wellbore standoffs; mud volumes in segments; drill string volumes, displacements and weights; mud tank volumes, including in-use tank selection and loss / gain calculation information; mud supply tank volume differential; mud supply tank cumulative volume; mud pump total stroke counter (individual stroke counts tracked by / representing each mud pump); mud pump SPM total; mud pump liner capacity and efficiency settings; mud flow into the wellbore, individual and total; annular mud velocity per segment; mud volume per segment; total strokes per segment; strokes to be experienced by each segment; total minutes per segment; minutes experienced by each segment; mud return flow; bit run time and revolutions; WOB; ROP; hook load; and pressure; among other items.
[0392] The AWD system is operable to deliver high-quality calculations for real-time monitoring and alarming of complex drilling and tripping parameters. Inputs from the following sources can be the basis for AWD calculations: well and drill string configuration; and drilling parameter sensors, such as mud pit level sensors, riser pressure sensors, and mud flow sensors; directly from drilling equipment (such as drill string RPM, make-up torque, and mud pump SPM). The AWD system can output results to a workstation display (e.g., an AWD display screen that the operator can view on the control workstation display), a historical logging system, and a mud logging instrument system. The AWD system has direct access to all necessary sensor signals and can allow the operator to gain further insight and understanding.
[0393] The AWD system can provide determination and / or confirmation of the following: well and drill string configuration; dynamic tracking of well and drill bit depth; well mid-stand; dynamic calculation of segmented mud volume, drill string volume, displacement and weight; mud tank volume, including tank selection and loss / gain calculation; mud supply tank volume difference; mud supply tank cumulative volume; mud pump total stroke counter (individual counts can be performed by each mud pump); total mud pump strokes per minute; mud pump cylinder capacity and efficiency settings; mud flow into the wellbore, individual and total; annulus per segment Dynamic calculation of mud velocity; dynamic calculation of mud volume per section; dynamic calculation of total stroke per section; dynamic calculation of stroke to be experienced per section; dynamic calculation of total minutes per section; dynamic calculation of minutes experienced per section; mud return flow; drill bit operating time and number of revolutions; WOB; ROP; hook load; standpipe pressure; casing pressure, cement pressure, sensors and calculations for well overflow calculator and well kill log (e.g., following the "Driller's Method") stored in the historical trending system; and operational warnings and alarms.
[0394] The AWD system may contain specific WITS (Wellsite Information Transfer Standard) calculations and triggers that are used to populate serial communications using the WITS0 protocol. The AWD system may calculate data for the WITS records "Record 1 - General Time Based" and "Record 11 - Mud Tank Volume - Time Based". The WITS record "Record 19 - Hole and Drill String" is available for configuration.
[0395] The AWD system can calculate the mud effective volume based on the level measured by the mud pit level instrument. The level sensor can be wired to the AWD system, or the AWD system can receive the level sensor data from the drilling fluid control system. The operator can select the tanks in use to be included as part of the effective volume. Any combination of tanks can achieve the effective volume. Once selected, the tanks will automatically be added to the effective volume. All calculations involving the effective volume will be updated with the new value. The AWD screen can indicate the status of those tanks that contribute to the mud effective volume determination, and the operator can always view these status.
[0396] The AWD system calculates data for a mud balance volume indicator that shows lost / gained volume with arrows for increasing / decreasing trends. System loss / gain is calculated as the change between the effective volume and the reset value.
[0397] The AWD system automatically calculates the drill bit and well depth by using the jacking position, hook load and slips status. The AWD system automatically calculates the well and bit depth each time the drill bit is moved in the well or the well is lengthened. The update depends on the specific weight of the drill string, i.e. the ability to measure the hook load. If the weight of the drill string is too low to get a reliable signal, it can be decided manually when the drill bit depth should be updated. The drill bit and well depth calculator also includes an automatic wellbore stand counter based on the input average stand length.
[0398] The AWD system may have two options for depth calculations: "Slips", which are used to take effect for depth calculations when slips are not set; and "Hook Load", which is used to perform depth calculations when the load is in the elevator.
[0399] The AWD system may include a separate SPM and stroke counter for each mud pump. In addition, there may be multiple (e.g., four) independent total stroke counters and total SPM for active mud pumps. The operator may select the pumps to be counted in the active mud pumps for the total counter.
[0400] The AWD system can include monitoring of the mud flow rate pumped into the drill string and the mud return flow rate. The calculation of the inflow depends on the configuration of the cylinder capacity and efficiency factor set for each mud pump. By using this data and the SPM, the AWD system can calculate the mud flow rate in each pump in addition to the total flow pumped into the well.
[0401] The mud return flow can be read directly from the mud return sensor, which can be selected by the operator through the sensor selection pop-up menu.
[0402] As the well or drill bit depth increases over time, the ROP can be calculated. The operator can select whether the ROP calculation will be done based on drill bit depth or well depth.
[0403] WOB can be calculated as the change in hook load from a reset value.
[0404] The AWD system may include counters for drill bit revolutions and run time. These counters may depend on the RPM of the top drive and the calculated mud inflow. Updating of the counters may be done when the drill bit is at the bottom.
[0405] The AWD system may display a well configuration for configuring well and drill string parameters as well as giving an overview view of the current configuration being used.
[0406] Well designs entered into the AWD system include the number of well sections and the well diameter and planned length of each section. Choke and kill line designs entered into the AWD system may include choke line ID, choke line joint ID, choke line joint section, choke line length, kill line ID, kill line joint ID, kill line joint section, and kill line length. Drill string designs entered into the AWD system may include the dimensions and length of each drill string section, including the number of drill string sections, planned length, drill string capacity, drill string steel displacement, drill string closure displacement, average length of pipe tool joints, average stand length, and number of tool joints per stand, among other examples.
[0407] If a well overflow occurs and the well must be shut in and the overflow must be circulated out to regain control of the well, the well overflow calculator can be used. The well overflow calculator does not initiate any equipment, sequence or process and can be used at any time or any point in the well. The inputs to the well overflow calculator may include measured depth, true vertical depth, measured shoe depth (e.g., second lowest well section), vertical shoe depth, original mud weight, leak test mud weight, leak test pressure, shut-in casing pressure, shut-in drill pipe pressure, well overflow increase volume, kill pump selection, kill pump capacity (e.g., calculated based on mud pump configuration), kill pump speed, slow circulation rate pressure, safety margin and other examples of choke / kill lines selected to be used. The well overflow calculator may also use previously entered and / or measured parameters as column and well characteristics, riser size, and kill and choke line characteristics. Volume, shoe and pump data can be collected from mud pump and well configuration settings. The Well Flow Calculator can output Initial Circulating Pressure, Temporary Circulating Pressure, Final Circulating Pressure, Kill Mud Weight, Maximum Mud Weight, Pressure Drop per 100 Strokes, Inflow Gradient, Inflow Height, Surface to Bit Strokes and Minutes, Bit to Shoe Strokes and Minutes, Shoe to BOP Strokes and Minutes, BOP to Choke Strokes and Minutes, and Total Circulating Strokes and Minutes among other examples.
[0408] The AWD system can determine the difference in the mud supply tank by comparing the expected drill string displacement in the well with the actual volume measured in the mud supply tank. The drill string displacement may depend on the drill string configuration and the drill bit depth.
[0409] The AWD system can determine the cumulative volume of the mud supply tank as the total volume of mud during the run-in or run-out period. The reservoir may freeze while filling or emptying, thereby filling or emptying the mud supply tank without reflecting the cumulative value.
[0410] The AWD display screen can dynamically display the configured and drilled wells and drill strings in a graphical manner. The AWD display screen can also dynamically display the mud volume, stroke and speed of different well sections. The AWD system can also track the mud front depth, which can be displayed in the form of text (e.g., numbers) and graphics on the well animation. The AWD display screen may include a graphical display of the well configuration and well section depth, a graphical display of the shoe, an animation of the drilled well relative to the well configuration, an animation of the drill string in the well, mud front tracking (e.g., mud front depth value and graphical display), annular velocity of each well section, open hole volume, and other examples such as the total stroke and minutes for the surface to the drill bit, the drill bit to the shoe, the drill bit to the BOP and the drill bit to the surface, the well cycle and the full cycle, the stroke and minutes to be experienced, and the dynamic determination of the volume. The AWS display screen may also display other AWD parameters that the AWD system has determined, such as drill string displacement – open end, drill string displacement – closed end, drill string weight, well stand, effective volume, mud inflow, drill bit revolutions, and drill bit run time, among other examples. The AWD display screen may also outline the configured well section lengths and display the depth of each section in addition to indicating the shoe depth graphically. If the actual well depth exceeds the configured well depth, the length of the deepest well section may automatically update so that the volume, time, and travel calculations are correct. The well and drill string animations may also update to reflect the exceeded well depth.
[0411] When a well configuration is input into the AWD system, the well may be filled with a first color, and as drilling progresses, the well animation may be filled with a second color accordingly based on the calculated well depth. The drill string may be graphically displayed in the configured well in either the second or third color. The depth of the drill string will indicate the drill bit depth.
[0412] The mud front tracking position may be calculated relative to the mud pump total stroke counter and the drill string and well configuration. The mud front may be tracked from the surface or the drill bit. When the operator selects to track the mud front from the surface, and the selected total stroke counter is set to zero, a graphical symbol may indicate that the mud front position moves from the surface toward the drill bit within the drill string as mud is pumped into the well. When the stroke counter exceeds the number of strokes from the surface to the drill bit, another graphical symbol may indicate the mud front position in the annular volume from the bottom to the surface. When the mud front indication reaches the surface, it may stay at the surface until the selected total stroke counter is reset. When the operator selects to track the mud front from the drill bit (or bottom), and the selected total stroke counter is set to zero, a graphical symbol may indicate the mud front position in the annular volume starting from the drill bit and moving toward the surface. When the mud front indication reaches the surface, it may stay at the surface until the selected total stroke counter is reset. In addition to the graphical display of the mud front depth, there may also be a digital display showing the depth. For example, the value may be positive if the mud front is moving in the annulus volume toward the drill bit inside the drill string or toward the surface.
[0413] The AWD system can calculate and display the annular velocity with a digital display for each of the well sections. If the drill string has several outer diameters within the same well section, the calculated velocity can be an average value in the specific well section.
[0414] The AWD system can calculate the open hole volume based on the well configuration at the current well depth.
[0415] The AWD system can dynamically calculate the volume, total strokes, total minutes, and number of strokes and minutes to be experienced for one or more of the following: surface to drill bit (drill string volume); drill bit to shoe (drill bit to shoe annulus volume); drill bit to surface (total annulus volume); well cycle (drill string + annulus volume); and full cycle (drill string + annulus volume + effective volume). The strokes and minutes to be experienced can be calculated based on the last reset of the selected total stroke counter. If the operator chooses to track from the surface, the strokes and minutes to be experienced can be calculated starting from counting the strokes from the surface. If the operator chooses to track from the bottom, the strokes and minutes to be experienced can be calculated starting from the drill bit position. When the operator chooses to track from the bottom, the strokes and time to be experienced from the surface to the drill bit can be set to zero.
[0416] The volume calculation may be related to the well and drill string configuration and the calculated bit depth. The trip calculation may depend on the calculated volume and the effective mud pump capacity setting. The minutes to elapse calculation may depend on the calculated volume, the effective mud pump capacity setting, and the mud pump total SPM.
[0417] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22 The system 800 shown in (similar or identical to) may be operable to monitor and at least partially (e.g., completely) control the drilling operations of the drilling rig and one or more of the following modules: running drill pipe in drill (with and / or without drill collar stands); pulling drill pipe out of drill pipe (with and / or without drill collar stands); drill pipe connection; drill pipe stand construction (offline); drill pipe drop station (offline); casing stand construction; running casing in drill pipe; stand shackle; running casing from a catwalk; lifting singles from a catwalk; placing singles from the center of the well on a catwalk; back reaming; wet tripping; normal drilling shutdown; and emergency drilling shutdown (based on alarm conditions). One such exemplary module involves running 13-3 / 8" casing from a catwalk using a top drive and casing running tool. This module sequence may begin with the top drive in a lowered position, the casing running tool engaged, the slips closed (e.g., approximately 1.5 meters of extension), the catwalk machine feed table loaded with (cleaned) tubulars, the catwalk machine ramp loaded with casing (e.g., in an upward direction), the tubular delivery arm parked in / near the top of the mast, and the lower stabilizing arm ready. The module sequence may then include: (i) releasing the casing running tool from the extension and hoisting the top drive to the raised position; (ii) latching the top drive and the casing running tool; and (iii) resetting the casing running tool. (iii) the top drive / lower stabilizing arm hoists the casing to the center of the well and the catwalk machine moves to the loading position; (iv) buckles the casing; (v) loads another (e.g., next) casing on the catwalk machine ramp; (vi) runs the catwalk to the rig floor; (vii) engages the casing running tool and tightens the casing connection; (viii) opens the backup tongs and retracts the tongs handling vehicle; (ix) lowers the casing string and opens the elevators; (x) tilts out one or more elevator bail and sets slips; and (xi) optionally repeats some or all of these steps as needed for additional (e.g., next) casing.
[0418] A drilling system according to one or more aspects of the present disclosure (which may be used with Fig. 22 The system 800 shown in (similar to or identical to) may include at least partially (e.g., fully) automatic control of equipment including, consisting essentially of, or consisting of each of the following: a drawworks; a top drive; an iron roughneck; a mud bucket; one or more catheads; a mousehole; a mud system including a mud pump; a catway; a fingerboard; a vertical pipe manipulator; a CCTV system; a riser tensioning system; a top-mounted compensator; and an optional bottom hole assembly (BHA).
[0419] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22The system 800 shown in the drawings may be similar or identical to the system 800 shown in the drawings) may be operable to control drilling operations, wherein the automatic drilling and / or automatic pulling out modules may advantageously be more efficient than manual drilling and / or pulling out modules for ordinary human work teams. The control system may achieve one, some, or all of the following: an automatic average drilling and / or pulling out speed [in standpipes per hour] that is at least 5% (e.g., at least 6%, at least 7%, at least 8%, at least 9%, or at least 10%) better / more than the average drilling and / or pulling out speed of an ordinary human work team; an automatic standard deviation from the average drilling and / or pulling out speed that is at least 50% (e.g., at least 55%, at least 60%, at least 65%, at least 70%, at least 75%, or at least 80%) better / lower than the standard deviation from the average drilling and / or pulling out speed of an ordinary human work team. Deviation; an automated average drill down and / or pull out slip-to-slip connection time [in seconds] that is at least 4% (e.g., at least 5%, at least 6%, or at least 7%) better / lower than the average drill down and / or pull out slip-to-slip connection time for an average human work team; and an automated standard deviation from the average drill down and / or pull out slip-to-slip connection time that is at least 50% (e.g., at least 55%, at least 60%, at least 65%, at least 70%, at least 75%, or at least 80%) better / lower than the standard deviation of the average drill down and / or pull out slip-to-slip connection time for an average human work team.
[0420] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22800) may be operable to control drilling operations in which collisions may be avoided between: (a) a drawworks and one or more of an iron roughneck, a tongs handling vehicle, a tongs handling arm, a catwalk, a tubular delivery arm, a lower stabilizing arm, and an upper tubular restraint; (b) a top drive and one or more of an iron roughneck, a tongs handling vehicle, a tongs handling arm, a catwalk, a tubular delivery arm, a lower stabilizing arm, and an upper tubular restraint; (c) an iron roughneck and one or more of a drawworks, a top drive, a catwalk, a tubular delivery arm, a lower stabilizing arm, an intermediate tubular restraint, a rotary table, a power slip, a well center connection, and a rat hole connection; (d) a tongs handling vehicle and one or more of a drawworks, a top drive, a catwalk, a tubular delivery arm, a lower stabilizing arm, and an upper tubular restraint; (e) a clamp manipulator arm and one or more of a winch, a top drive, a catwalk, a tubular delivery arm, a lower stabilizing arm, an intermediate tubular restraint, a rotating table, a power slip, a well center connection, and a mouse hole connection; (f) a catwalk and one or more of a winch, a top drive, an iron roughneck, a clamp manipulator vehicle, a clamp manipulator arm, a tubular delivery arm, a lower stabilizing arm, a pipe near the transfer position, and a pipe in a mouse hole; (g) a tubular delivery arm and one or more of a winch, a top drive, an iron roughneck, a clamp manipulator vehicle, a clamp manipulator arm, a catwalk, a lower stabilizing arm, a transfer bridge pipe racker, an upper tubular restraint, an intermediate tubular restraint, a lower tubular restraint, one or more stand box guide arms, a stand (h) a lower stabilizing arm and one or more of a winch, a top drive, an iron roughneck, a tongs manipulator, a tongs manipulator arm, a catwalk, a tubular delivery arm, and an intermediate tubular restraint; (i) a transfer bridge pipe racker and one or more of a tubular delivery arm, an upper tubular restraint, a lower tubular restraint, one or more stand box guide arms, a stand transfer position, and a finger beam; (j) an upper tubular restraint and one or more of a winch, a top drive, a tubular delivery arm, a transfer bridge pipe racker, a lower tubular restraint, and one or more stand box guide arms; (k) an intermediate tubular restraint and one or more of an iron roughneck, a tongs manipulator arm, a tubular delivery arm, a lower stabilizing arm, and a mouse hole connection (i) one or more pipe box guide arms and one or more of a pipe delivery arm, a lower stabilizing arm, a transfer bridge racker, an upper pipe restraint, and a lower pipe restraint; (m) multiple pipe box guide arms; (n) a finger beam and a transfer bridge racker; (o) a lower pipe restraint and one or more of a pipe delivery arm, a lower stabilizing arm, a transfer bridge racker, an upper stabilizing arm, and one or more pipe box guide arms; (p) a pipe transfer position and one or both of a pipe delivery arm and a transfer bridge racker; and / or (q) a rotary table / power slip and one or more of a drawworks, a top drive, an iron roughneck, a tongs manipulator, a tongs manipulator arm, a pipe delivery arm, a lower stabilizing arm, and a well center connection.
[0421] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22) may be operable to control drilling operations, wherein the level of automation for various drilling operations may be selected by: generating a control screen to facilitate selection of the level of automation; and facilitating selection of full (i.e., substantially complete) automation, semi-automation (e.g., via driller / operator confirmation to begin a particular sequence of operations, automation of the first portion of a larger sequence of operations, such as waiting for driller / operator authorization for completion and / or a second portion of a larger sequence of operations, etc.), or manual control (e.g., via a joystick).
[0422] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22 ) may be operable for controlling a drilling operation and may include a customizable display screen on which a control screen is generated, and the control screen may be operable to facilitate selection of scales and / or limits (e.g., one or more pie charts, one or more linear bar charts, one or more spider charts, and / or the like, and combinations thereof) for an indicator graph that may graphically represent one or more aspects of a drilling operation. Selection of scales and / or limits may include, but are not necessarily limited to: minimum and maximum graphical values; warning value limits; and graphical scales.
[0423] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22 ) may be operable to control drilling operations and may include the display of software objects (e.g., symbols, icons, buttons, and / or the like) that: may be displayed on a monitor or touch screen; may indicate equipment / tool / device status by changing colors, localized background colors, adjacent or localized background symbols (e.g., check marks or Xs), flashing colors, filled / unfilled objects, and / or the like; may display operating status (e.g., high value, open, closed, running, idle, error, and / or the like); may display communication status (e.g., feedback error, communication error, and / or the like); may display control status (e.g., automatic, manual, local, and / or the like); and may be displayed in association with displayed numerical values; and other items.
[0424] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22) may include an AWD display screen showing one, some, or all of the following information: (a) a graphical display of well configuration and well section depths; (b) a graphical display of the shoe; (c) an animation of the planned well versus the actual well; (d) an animation of the drill string in the well; (e) values and graphical display of mud front tracking / depth; (f) annular velocity per section; (g) open hole volume; (h) a dynamic calculation of the total number of strokes and minutes, the number of strokes and minutes to be experienced, and the volume for at least the following: (i) surface to drill bit; (ii) drill bit to shoe; (iii) drill bit to BOP; (iv) drill bit to surface; (v) well circulation; (vi) total circulation; (j) drill string displacement, open end and closed end; (k) drill string weight; (l) roots in the wellbore; (m) effective volume; (n) mud inflow; (o) drill bit revolutions; and (p) drill bit running time.
[0425] A control system according to one or more aspects of the present disclosure (which may be used with Fig. 22 ) may include an alarm system that can assist an equipment operator / resource producer in operating equipment (e.g., drilling equipment) in an efficient and safe manner. The alarm system may be operable to: attract operator attention to alarms by using colors, symbols, flashing, sounds, and other symbols with different meanings; present descriptive and easy to understand alarm text; use alarm priorities with different meanings; logically group alarms; and keep the alarm rate as low as possible. The alarm system may additionally or alternatively utilize screen objects / symbols that indicate equipment or devices and can display status by changing colors, localized background colors, adjacent or localized background symbols, flashing colors, filled or unfilled objects, and / or the like. The alarm system may additionally or alternatively be configured to: enable a driller / operator to respond to all alarms; for intuitive navigation and alarm confirmation; automatically log each alarm and alarm state change; and for high system availability and robustness.
[0426] A method of at least partially automating drilling operations according to one or more aspects of the present disclosure, which may be employed using one, some, or all of the (control) systems described herein, may include: using data indicative of the operation or capability of a first piece of drilling equipment as an input parameter for controlling the operation of a second piece of drilling equipment, wherein the effect of the data indicative of the operation / capability of the first piece of drilling equipment is not intuitively connected to or is counter-intuitive to the operation / capability of the second piece of drilling equipment. For example, an output parameter relating to drilling equipment piece A may be used as an input parameter for the operation of drilling equipment piece B, and an output parameter relating to drilling equipment piece B (e.g., similar to or different from the input parameter) may be used as an input parameter for the operation of drilling equipment piece C. In this example, one or more effects of the operation / capability of the parameter relating to piece A are not intuitively connected to or are counter-intuitive in their applicability to the operation / capability of piece C. In this example, "drilling equipment item B" may represent a single drilling equipment item or a series of drilling equipment items, in which the output parameters of each of the drilling equipment items are used as input parameters of the next drilling equipment item in the entire series (it is worth noting that they may but do not have to be the same output and / or input parameters in the entire drilling equipment series).
[0427] In view of the entirety of the present disclosure including the drawings and claims, a person skilled in the art will readily recognize that the present disclosure introduces an apparatus comprising: an integrated well construction system (IWCS), the IWCS being operable to construct a well through integrated control of a plurality of integrated control devices that jointly control a plurality of integrated subsystems of the IWCS, wherein the IWCS comprises: an IWCS communication network; the integrated control devices, each of which is directly connected to the IWCS communication network; the integrated subsystems; and a control workstation, the control workstation being directly connected to the IWCS communication network and operable to control each of the integrated control devices, thereby controlling the integrated subsystems.
[0428] Each integrated control device may control a corresponding integrated subsystem among the integrated subsystems.
[0429] The IWCS communication network may be a single optical fiber ring topology network.
[0430] The integrated subsystem may include at least: a drilling rig control subsystem, which includes a drawworks, a top drive, an iron roughneck, automatic slips and automatic pipe handling equipment; a fluid circulation subsystem, which includes a drilling fluid pump and drilling fluid readjustment equipment; a controlled pressure drilling control subsystem; a throttling pressure control subsystem; a well pressure control subsystem; and a closed-circuit television subsystem.
[0431] Each subsystem may include: a subsystem network directly connected to the integrated control device of the subsystem; and a plurality of subsystem components each directly connected to the subsystem network. The subsystem components may each control, execute, sense, measure and / or monitor aspects of well construction performed in association with the subsystem including the subsystem component.
[0432] The control workstation may include a processor and a memory storing a service program that, when executed by the processor, controls each integrated control device at least in part in response to data received from at least another of the integrated control devices.
[0433] The control workstation may include a processor and a memory storing an operation program, which when executed by the processor controls each integrated control device during each of a plurality of predetermined operation sequences. The plurality of predetermined operation sequences may include: lifting a single tubular; making a drilling connection; building a tubular stand; running a drill collar stand; pulling out a drill collar stand; wet pulling; back reaming; moving a single tubular from the center of the well to a catway using a top drive; moving a tubular stand from the center of the well to the catway; moving casing from the catway to the center of the well using a casing tong; moving casing from the catway to the center of the well using a tubular delivery arm and a casing running tool; moving large diameter casing from the catway to the center of the well using the top drive and the casing running tool; building a casing stand; and running a casing stand without using the casing running tool. The construction program, when executed by the processor, may control a top drive, a drawworks, an automatic slip, a top drive elevator, an iron roughneck, a drilling fluid pumping system, a catwalk, an automatic pipe racker, an automatic fingerboard, and a tubular delivery arm by controlling an integrated control device during execution of a predetermined sequence of operations. The construction program may be configured by a human operator to allow the operator to select a level of human interaction during execution of a predetermined sequence of operations. The construction program may be configured by a human operator to allow the operator to select a level of automation of the IWCS during execution of a predetermined sequence of operations. The construction program may be configured by a human operator to allow the operator to select which machines of the IWCS will be controlled by the construction program during execution of each predetermined sequence of operations. The construction program may be configured by a human operator to allow the operator to select which machines of the IWCS will be controlled by the construction program and which operator will supervise which machines of the IWCS during execution of each predetermined sequence of operations. The construction program may be configured by a human operator to allow the operator to select which steps of each predetermined sequence of operations will be manually performed and / or confirmed and which operator will manually perform and / or confirm the steps.
[0434] The IWCS may be operable for constructing a well without operation of other components that are not controlled, monitored, or otherwise in communication with any of the integrated control devices.
[0435] The IWCS may be operable for constructing a well without operation of other components not controlled by any of the integrated controls.
[0436] The present disclosure also introduces a device, which includes: a control workstation, which is directly connected to a communication network and can be operated to control each of a plurality of integrated control devices that are directly connected to the communication network, wherein each integrated control device controls a corresponding component of an integrated well construction system, thereby controlling the integrated control device to control the integrated well construction system through the operation of the control workstation.
[0437] The integrated well construction system, excluding any components not controlled by any of the integrated control devices, may be operable for construction of a well through operation of a control workstation.
[0438] The present disclosure also introduces a computer program product, which includes a tangible, computer-readable, non-transitory medium on which instructions are stored for: automatically controlling multiple integrated control devices of an integrated subsystem of an integrated well construction system (IWCS) to execute a combination of multiple predetermined operation sequences for constructing a well; receiving a selection of one of the operation sequences to be executed by the IWCS through operation of a control workstation by a human operator; receiving settings of a first machine of the IWCS to be operated during the selected operation sequence by the human operator through operation of the control workstation; and in response to the human operator receiving a single start input through operation of the control workstation, automatically starting and controlling the first machine and the second machine of the IWCS using the received settings to execute the selected operation sequence.
[0439] Automatic activation and control of the first machine and the second machine may execute the selected operating sequence without further manual action.
[0440] The present disclosure also introduces a method, which includes: operating an integrated well construction system (IWCS) including a fiber optic ring network, wherein the fiber optic ring network includes multiple nodes, which include: programmable logic controllers (PLCs) of various mechanical parts forming the IWCS; video feeds; drilling operator controls; advanced monitoring; and combinations thereof.
[0441] The IWCS mechanical PLC may include: a drilling fluid pumping system PLC; a top drive PLC; a drawworks PLC; an automatic slip PLC; an iron roughneck PLC; a catwalk PLC; an automatic pipe racker PLC; an automatic fingerboard PLC; and a pipe delivery arm PLC.
[0442] A fiber optic ring network exchanges data between PLCs for coordinated control of machinery.
[0443] A fiber optic ring network may exchange data between one or more of the PLCs and the drilling operator for manual or semi-automatic control of the IWCS.
[0444] The fiber optic ring network can exchange data between one or more of the PLCs and the supervisory controller for automatic and optimized control of the IWCS.
[0445] The present disclosure also introduces an apparatus, which includes: a communication network; a plurality of integrated control devices, each of which is directly connected to the communication network, wherein each integrated control device controls a corresponding component of an integrated well construction system, and wherein the integrated well construction system is operable to construct a well without requiring other components that are not controlled by any of the integrated control devices; and a control workstation, which is directly connected to the communication network and is operable to control each of the integrated control devices, thereby controlling the integrated well construction system.
[0446] The present disclosure also introduces an apparatus, which includes: a communication network; a plurality of integrated control devices, each of which is directly connected to the communication network, wherein each integrated control device controls a corresponding component of a plurality of integrated well construction components, and wherein the integrated well construction components except any component not controlled by any of the integrated control devices can be operated together for constructing a well; and a control workstation, which is directly connected to the communication network and can be operated to control each of the integrated control devices, thereby controlling the integrated well construction system.
[0447] The present disclosure also introduces an apparatus, which includes: a communication network; a plurality of integrated control devices, each of which is directly connected to the communication network, wherein each integrated control device controls a corresponding component of a plurality of integrated well construction components, and wherein the integrated well construction components form an integrated well construction system that can be operated for constructing a well without any other components; and a control workstation, which is directly connected to the communication network and can be operated to control each of the integrated control devices, thereby controlling the integrated well construction system.
[0448] The present disclosure also introduces a method, which includes: causing a well construction system to perform a well construction operation, thereby automatically collecting and analyzing data associated with the well construction operation in real time to determine multiple parameters based on the data, and wherein at least some of the determined parameters are used to control the well construction operation.
[0449] The data may be selected from: human operator input; equipment control, feedback and interlock signals; surface sensor signals; and downhole sensor signals.
[0450] The well construction system may include a processing system including a processor and a memory having instructions recorded thereon, the instructions being used, when executed by the processor, to: automatically determine parameters; and automatically control at least a portion of a well construction operation based at least in part on the determined parameters.
[0451] The well construction system may include a processing system including a processor and a memory having recorded thereon instructions for, when executed by the processor: automatically determining parameters; and automatically displaying at least some of the determined parameters to a human operator substantially in real time. The method may also include at least partially controlling, by the human operator, at least a portion of the well construction operation based at least in part on the displayed parameters. The display may include numbers, pictures, animations, or combinations thereof.
[0452] The determined parameters may include one or more of the following: drilling fluid effective volume, drilling fluid loss and / or gain, drill bit depth, wellbore depth, hook load weight and friction, drilling fluid pump stroke, drilling fluid stroke rate, penetration rate, bit pressure, drill bit revolutions, drill bit running time, well configuration, drill string configuration, choke valve configuration, well kill line configuration, well overflow calculator, mud supply tank volume, mud supply tank difference determination, and mud supply tank cumulative volume.
[0453] One of the determined parameters can be a well overflow determination based on the following: measured depth; true vertical depth; measured shoe depth; vertical shoe depth; original drilling fluid weight; leak test drilling fluid weight; leak test pressure; shut-in casing pressure; shut-in drill pipe pressure; well overflow gain volume; kill pump selection; kill pump capacity; kill pump speed; slow circulation rate pressure; safety margin and selected choke / kill line.
[0454] The present disclosure also introduces a method, which includes: causing a well construction system to perform a well construction operation, thereby automatically collecting and analyzing data associated with the well construction operation in real time to determine multiple parameters based on the data, and wherein at least some of the determined parameters each provide a basis for triggering at least one real-time well construction operation alarm.
[0455] The data may be selected from: human operator input; equipment control, feedback and interlock signals; surface sensor signals; and downhole sensor signals.
[0456] The at least one real-time alarm may be a plurality of alarms, including: high mud make-up tank volume; low mud make-up tank volume; high effective drilling fluid volume; low effective drilling fluid volume; high drilling fluid loss; low drilling fluid loss; high drilling fluid gain; low drilling fluid gain; high drilling fluid return; low drilling fluid return; high standpipe pressure; low standpipe pressure; drilling fluid pumping system total stroke rate; and drilling fluid pumping system total stroke.
[0457] The well construction system may include a processing system including a processor and a memory having instructions recorded thereon for, when executed by the processor: automatically determining parameters; and automatically triggering at least one real-time alarm based on at least one of the determined parameters.
[0458] The determined parameters may include one or more of the following: drilling fluid effective volume, drilling fluid loss and / or gain, drill bit depth, wellbore depth, hook load weight and friction, drilling fluid pump stroke, drilling fluid stroke rate, penetration rate, bit pressure, drill bit revolutions, drill bit running time, well configuration, drill string configuration, choke valve configuration, well kill line configuration, well overflow calculator, mud supply tank volume, mud supply tank difference determination, and mud supply tank cumulative volume.
[0459] The present disclosure also introduces a device, which includes an analysis while drilling (AWD) control system used in conjunction with a well construction system during well construction operations, wherein inputs for the AWD control system include: the expected configuration of the well constructed by the well construction system during the well construction operation; the configuration of the drill string used by the well construction system during the well construction operation; signals from drilling parameter sensors; and drilling equipment parameters. Outputs of the AWD control system include real-time determinations of: depth and trajectory of the well; depth to bit; number of drill string tubulars and / or standpipes in the well; drill string volumes, displacements and weights; drilling fluid tank volumes and tank selection; drilling fluid losses and / or gains; mud supply tank volume differentials; mud supply tank cumulative volumes; total and / or per-segment strokes and / or strokes to be experienced by the drilling fluid pumping system; total stroke rate of the drilling fluid pumping system; drilling fluid pumping system liner capacity and efficiency; individual and overall drilling fluid flow rates into the well; annular drilling fluid velocity; total and / or per-segment drilling fluid volumes; total minutes per segment and / or minutes to be experienced; drilling fluid return; drill bit run time and revolutions; bit pressure; penetration rate; hook load and standpipe pressure. Outputs from the AWD control system may also include a well overflow calculator and a kill log. Outputs from the AWD control system may also include sensors and calculations for storage in historical data associated with the well construction system. Outputs from the AWD control system may also include well construction operation warnings and alarms.
[0460] The drilling parameter sensors may include a drilling fluid tank level sensor, a riser pressure sensor, a cement manifold pressure sensor, and a drilling fluid flow sensor.
[0461] Drilling equipment parameters may include drill string revolutions per minute, make-up torque, lifting position, hook load, slip status, average stand length, average pipe length, cylinder liner capacity and efficiency of a single drilling fluid system pump, top drive revolutions per minute, choke line parameters, kill line parameters, number of drill string sections, drill string capacity, drill string steel displacement, and drill string closure displacement.
[0462] The present disclosure also introduces an apparatus, the apparatus comprising: a control workstation, which is directly connected to a communication network and is operable to control each of a plurality of control devices, each of which is directly connected to the communication network, wherein each control device controls a corresponding component of an integrated well construction system, whereby the control of the control device controls the integrated well construction system through the operation of the control workstation, wherein the control workstation comprises a display, a processor and a memory, the memory storing: a construction program that controls each control device when executed by the processor; and an analysis while drilling (AWD) program. The inputs to the AWD system include: an expected configuration of a well to be constructed by the well construction system during a well construction operation; a configuration of a drill string used by the well construction system during a well construction operation; a signal from a drilling parameter sensor; and drilling equipment parameters. The AWD program, when executed by the processor, generates in real time and displays in real time in an AWD screen on the display one or more of the following: a graphical display of the expected and / or actual configuration of the well, including depth; a graphical display of the shoe in the well; an animation of the expected and actual configuration of the well; an animation of the drill string in the well; text and / or graphical displays of values for drilling fluid front tracking and / or depth; annular velocity for each section; open hole volume; total strokes and minutes, strokes and minutes to be experienced, and volume for one or more of the following: surface to drill bit, drill bit to shoe, drill bit to blowout preventer, drill bit to surface; well circulation; full cycle; drill string displacement, open end and closed end; drill string weight; number of tubulars in the well; effective volume; drilling fluid flow rate into the well; drill bit revolutions; and drill bit run time.
[0463] The present disclosure also introduces a device, which includes a control workstation for use with an integrated well construction system (IWCS), wherein the IWCS is operable to construct a well by integrated control of multiple integrated control devices that jointly control multiple integrated subsystems of the IWCS, and wherein the control workstation includes a human-machine interface (HMI), the human-machine interface including a display, a touch screen, a joystick, and a processing system, the processing system including a processor and a memory having a construction program thereon, and the construction program, when executed by the processor: presents a setup wizard to a human operator of the control workstation, the setup wizard guiding the operator to input operating parameters for one or more well construction machines of the integrated subsystem to execute a well construction sequence; and controls the integrated control device and thereby controls the integrated subsystem to execute the well construction sequence based on the input operating parameters.
[0464] The well construction sequence can be selected from: lifting a single tubular; making drilling connections; building a tubular stand; running in a drill collar stand; pulling out the drill collar stand; wet pulling out; back-marking; using a top drive to move a single tubular from the center of the well to a catway; moving a tubular stand from the center of the well to the catway; using a casing tong to move casing from the catway to the center of the well; using a tubular delivery arm and a casing running tool to move casing from the catway to the center of the well; using the top drive and the casing running tool to move a large diameter casing from the catway to the center of the well; building a casing stand; and running in a casing stand without using the casing running tool.
[0465] The input operating parameters may be used for one or more of the following: top drive, drawworks, automatic slips, top drive elevators, iron roughnecks, drilling fluid pumping systems, catwalks, automatic pipe rackers, automatic fingerboards, and tubular delivery arms.
[0466] The input operating parameters may include a speed limit for at least one of the well construction machines.
[0467] The input operating parameters may include travel stops for at least one of the well-constructing machines.
[0468] The input operating parameters may include a maximum limit of at least one of the well-constructing machines.
[0469] The input operating parameters may include target settings for at least one of the well-constructing machines.
[0470] The input operating parameters may include target settings for the well construction sequence.
[0471] The input operation parameters may include an automation level. The automation level may be selected from: automatic control by the construction program; automatic control by the construction program after confirmation by the human operator; and manual operation by the human operator.
[0472] The human operator may cause the initiation of the well construction sequence by actuating a button on the touch screen.
[0473] The human operator may cause initiation of the well construction sequence by actuating the joystick to ramp up the speed of the well construction machine.
[0474] The construction program may allow the human operator to manually control one or more of the well construction machines during the well construction sequence.
[0475] The construction program may allow the human operator to modify operating parameters of one or more of the well construction machines during the well construction sequence.
[0476] The well construction sequence may be a running or pulling-out sequence that may be executed at an average running or pulling-out rate of at least five percent faster than a rate that a normal human crew could achieve without the use of the IWCS.
[0477] The well construction sequence may be a run-in or run-out sequence that may be executed with a standard deviation at least fifty percent lower than the standard deviation from a mean run-in or run-out rate that a normal human crew could achieve without the IWCS.
[0478] The well construction sequence may be a run-in sequence that may be executed with an average slip-to-slip connection time that is at least four percent faster than a connection time that an ordinary human crew could achieve without the IWCS.
[0479] The well construction sequence may be a drilling sequence that may be executed with a standard deviation from an average slip-to-slip connection time that is at least fifty percent lower than a standard deviation that an ordinary human crew could achieve without using the IWCS.
[0480] The present disclosure also introduces a device, which includes: an integrated well construction system (IWCS), which is capable of operating to construct a well through integrated control of multiple integrated control devices that jointly control multiple integrated subsystems of the IWCS, wherein the IWCS includes a processing system, which includes a processor and a memory with a construction program thereon, and the construction program, when executed by the processor: controls each integrated control device during each of a plurality of predetermined operation sequences, and thereby controls each integrated subsystem; and prevents collisions between machines of the IWCS.
[0481] The IWCS machines that are prevented from colliding by the construction procedure may include: a drawworks; an iron roughneck; a tongs handling vehicle; a tongs handling arm; a catwalk; a tubular delivery arm; a lower stabilizing arm; an upper tubular restraint; an intermediate tubular restraint; a lower tubular restraint; a top drive; a top drive elevator; a finger beam; a transfer bridge pipe racker; and a stand box guide arm. The construction procedure may also prevent collisions between: the IWCS machines; tubulars being transported by any of the IWCS machines; tubulars extending from the well; tubulars in a rat hole of the IWCS; and tubulars in a transfer position of the IWCS. The construction procedure can prevent collisions between: the winch and one or more of the catwalk, the iron roughneck, the lower stabilizing arm, the clamp operating arm, the clamp operating vehicle, the tubular delivery arm and the upper tubular restraint; and / or the top drive and one or more of the iron roughneck, the clamp operating vehicle, the clamp operating arm, the catwalk, the tubular delivery arm, the lower stabilizing arm and the upper tubular restraint; and / or the iron roughneck and the winch, the top drive, the catwalk, the tubular delivery arm, the lower stabilizing arm, the intermediate tubular restraint, the rotary table, the automatic Slips, one or more of tubulars extending from the well and from the rathole of the IWCS; and / or the clamp handling vehicle and the winch, the top drive, the catway, the tubular delivery arm, the lower stabilizing arm, the rotating table, the automatic slips and one or more of tubulars extending from the well; and / or the clamp handling arm and the winch, the top drive, the catway, the tubular delivery arm, the lower stabilizing arm, the intermediate tubular restraint, the rotating table, the automatic slips, the tubulars extending from the well and from one or more of the tubulars extending from the rathole; and / or the catwalk and the drawworks, the top drive, the iron roughneck, the clamp manipulator, the clamp manipulator arm, the tubular delivery arm, the lower stabilizing arm, the tubulars in the transfer position of the IWCS and one or more of the tubulars extending from the rathole; and / or the tubular delivery arm and the drawworks, the top drive, the iron roughneck, the clamp manipulator, the clamp manipulator arm, the catwalk, the lower stabilizing arm, the transfer bridge pipe racker, the upper tubular restraint, the intermediate tubular restraint, the lower one or more of the upper tubular restraint, the pipe box guide arm, the tubular in the transfer position, the rotary table and the automatic slips; and / or the lower stabilizing arm and the drawworks, the top drive, the iron roughneck, the clamp manipulator, the clamp manipulator arm, the catwalk, the tubular delivery arm and the intermediate tubular restraint; and / or the transfer bridge pipe racker and the tubular delivery arm, the upper tubular restraint, the lower tubular restraint, the pipe box guide arm, the tubular in the transfer position and the finger beam;and / or the upper tubular restraint and one or more of the drawworks, the top drive, the tubular delivery arm, the transfer bridge pipe racker, the lower tubular restraint and the pipe stand box guide arm; and / or the intermediate tubular restraint and one or more of the iron roughneck, the tongs operating arm, the tubular delivery arm, the lower stabilizing arm and the pipe in the mouse hole; and / or the pipe stand box guide arm and one of the tubular delivery arm, the lower stabilizing arm, the transfer bridge pipe racker, the upper tubular restraint and the lower tubular restraint or more; and / or the finger beam and the transfer bridge pipe racker; and / or the lower tubular restraint and one or more of the tubular delivery arm, the lower stabilizing arm, the transfer bridge pipe racker, the upper stabilizing arm and the stand box guide arm; and / or the tubular in the transfer position and one or both of the tubular delivery arm and the transfer bridge pipe racker; and / or the automatic slip and one or more of the drawworks, the top drive, the iron roughneck, the tongs handling vehicle, the tongs handling arm, the tubular delivery arm and the lower stabilizing arm. ;
[0482] The present disclosure also introduces a method, which includes: constructing a well using each of a plurality of automatically controlled well construction machines, the plurality of automatically controlled well construction machines including: a drawworks; an iron roughneck; a tongs handling vehicle; a tongs handling arm; a catwalk; a tubular delivery arm; a lower stabilizing arm; an upper tubular restraint; an intermediate tubular restraint; a lower tubular restraint; a top drive; a top drive elevator; a finger beam; a transfer bridge pipe racker; a stand box guide arm; a rat hole; a rat hole; a drilling fluid pumping system; and a drilling fluid readjustment system.
[0483] The present disclosure also introduces a system that can be operated to fully control each of multiple predetermined operation sequences of well construction operations, wherein the sequence includes: lifting a single tubular; making a drilling connection; building a tubular stand; running a drill collar stand; pulling out a drill collar stand; wet drilling; back-marking; using a top drive to move a single tubular from the center of the well to a catway; moving a tubular stand from the center of the well to the catway; using a casing tong to move casing from the catway to the center of the well; using a tubular delivery arm and a casing running tool to move casing from the catway to the center of the well; using the top drive and the casing running tool to move a large diameter casing from the catway to the center of the well; building a casing stand; and running a casing stand without using the casing running tool.
[0484] The present disclosure also introduces a control system for controlling drilling operations in which the level of automation for various operations can be selected. It can generate a control screen that facilitates the selection of the level of automation. It can facilitate the selection of full automation, semi-automation (e.g., by driller confirmation to start a specific sequence), or manual control (e.g., by a joystick).
[0485] The present disclosure also introduces a control system for controlling drilling operations, the control system comprising: a customizable display; a control screen that facilitates selection of scales and limits for indicator graphs (e.g., circular bar graphs, linear bar graphs); and customizable selections that include minimum and maximum graph values, warning value limits, and scales.
[0486] The present disclosure also introduces a control system for controlling drilling operations, which includes the display of software objects (symbols, icons, buttons, etc.), which are: displayed on a monitor or touch screen; indicate the status of equipment or devices through changing colors, localized background colors, adjacent or localized background symbols (e.g., check marks or Xs), flashing colors, filled or unfilled objects, etc.; display operating status (e.g., high value, open, closed, running, idle, error, etc.); display communication status (e.g., feedback error, communication error, etc.); display control status (e.g., automatic, manual, local, etc.); and / or can be displayed in association with a displayed numerical value.
[0487] The present disclosure also introduces a drilling rig control system including a communication network. The communication network can be a single ring, star or daisy chain network. The communication network can be optical fiber. The drilling rig control system also includes a control workstation directly connected to the network. The drilling rig control system also includes a plurality of different control devices. Each control device can execute, cause execution, sense, measure, monitor and / or record mechanical, software or other actions of a surface or downhole component (or group thereof), subsystem (or group thereof) or system (or group thereof). Each control device can be directly connected to the communication network. Each control device can communicate with each other control device (directly or indirectly). Each control device can function at least partially in response to or at least partially based on or otherwise using data from at least one other control device. For example, each control device can have input from another drilling rig component (or group thereof), drilling rig subsystem (or group thereof) or drilling rig system (or group thereof) (one or more control devices). Each control device can be a computer (PC or IPC) or PLC. The drilling rig control system can also include a plurality of local control networks. Each local control network can be connected to the communication network, such as through a corresponding control device in the control device. The drilling rig control system may also include a plurality of local control devices. Each local control device may be directly connected to a corresponding local control network. Each local control device may be a computer (PC or IPC) or a PLC. The control device directly connected to the communication network may execute all control logic, and the control workstation may be (at least primarily) a data exchanger.
[0488] The present disclosure also introduces an alarm system that helps operators operate equipment and processes in an efficient and safe manner. The alarm system can utilize screen objects / symbols that: indicate equipment or devices; display status through changing colors, localized background colors, adjacent or localized background symbols, flashing colors, filled or unfilled objects, etc.; are designed to attract operator attention to alarms by using colors, symbols, flashing, sounds, and other symbols with different meanings; present descriptive and easy-to-understand alarm text; use alarm priorities with different meanings; logically group alarms; keep the alarm rate as low as possible; ensure that operators respond to all alarms; allow intuitive navigation and alarm confirmation; allow all alarms and alarm state changes to be recorded; and provide high system availability and robustness.
[0489] The present disclosure also introduces an analysis while drilling (AWD) control system that is operable to display a large number of drilling related parameters determined by complex algorithms. The AWD inputs may include: well configuration; drill string (including BHA) configuration; drilling parameter sensors (e.g., mud pit level sensor, riser pressure sensor, mud flow sensor); and drilling equipment parameters (e.g., directly from equipment, such as drill string RPM, make-up torque, mud pump SPM). The AWD outputs may be delivered to and / or used by: one or more workstation displays, including an AWD display; a historical logging system; and / or a mud logging instrument system. The AWD outputs may include well configuration, drill string (including BHA) configuration, and dynamic tracking of: well; bit depth; wellbore stand; mud volumes by segment; drill string volumes, displacements, and weights; mud tank volumes, including in-use tank selection and loss / gain calculations; mud supply tank volume differential; mud supply tank cumulative volume; mud pump total stroke counter (single count may be done in mud pump); mud pump SPM total; mud pump liner capacity and efficiency; mud flow into the wellbore, individual and total; annular mud velocity per segment; mud volume per segment; total strokes per segment; strokes to be experienced per segment; total minutes per segment; minutes experienced per segment; mud return flow; bit run time and revolutions; WOB; ROP; hook load; and standpipe pressure. The AWD outputs may also include: well overflow calculator and kill log; sensors and calculations for storage in the historical trending system; drilling operation warnings and alarms.
[0490] The present disclosure also introduces an AWD display screen, which displays: a graphical display of well configuration and well section depth; a graphical display of the shoe; an animation of the planned well and the actual well; an animation of the drill string in the well; values and graphical displays of mud front tracking / depth; annular velocity for each section; open hole volume; dynamic calculations of the total strokes and minutes, the strokes and minutes to be experienced, and the volume for the following: surface to drill bit, drill bit to shoe, drill bit to BOP, drill bit to surface; well cycle; full cycle; drill string displacement (open end and closed end); drill string weight; roots in the wellbore; effective volume; mud inflow; drill bit revolutions; and drill bit operation time.
[0491] The present disclosure also introduces automatic drilling down (or pulling out of the drill) which results in: an automatic average drilling down speed (e.g., in terms of standpipes per hour) that is at least 5% faster than that of an ordinary human work team; and / or an automatic standard deviation from the average drilling down speed that is at least 50% lower than that of an ordinary human work team; and / or an automatic average drilling down slip-to-slip connection time that is at least 4% faster than that of an ordinary human work team; and / or an automatic standard deviation from the average drilling down slip-to-slip connection time that is at least 50% lower than that of an ordinary human work team.
[0492] The present disclosure also introduces a method for automatic drilling operation, which requires input of at least a given set of input parameters and requires the ability to automatically control at least a given set of equipment related to the drilling operation.
[0493] The present disclosure also introduces a control system for controlling drilling operations in which the level of automation for various operations can be selected. It can generate a control screen that facilitates the selection of the level of automation. It can facilitate the selection of full automation, semi-automation (e.g., by driller confirmation to start a specific sequence), or manual control (e.g., by a joystick).
[0494] The present disclosure also introduces a control system for controlling drilling operations, the control system comprising: a customizable display; a control screen that facilitates selection of scales and limits for an indicator graph (e.g., a circular bar graph, a linear bar graph); and customizable selections that include minimum and maximum graph values, warning value limits, and scales.
[0495] The present disclosure also introduces a control system for controlling drilling operations, which includes the display of software objects (symbols, icons, buttons, etc.), which are: displayed on a monitor or touch screen; indicate the status of equipment or devices through changing colors, localized background colors, adjacent or localized background symbols (e.g., check marks or Xs), flashing colors, filled or unfilled objects, etc.; display operating status (e.g., high value, open, closed, running, idle, error, etc.); display communication status (e.g., feedback error, communication error, etc.); display control status (e.g., automatic, manual, local, etc.); and / or can be displayed in association with a displayed numerical value.
[0496] The foregoing lists the features of several embodiments so that those of ordinary skill in the art can better understand aspects of the present disclosure. Those of ordinary skill in the art should understand that they can easily use the present disclosure as a basis for designing or modifying other processes and structures for achieving the same purpose and / or obtaining the same advantages as the embodiments described herein. Those of ordinary skill in the art should also recognize that such equivalent constructions do not depart from the scope of the present disclosure, and that various changes, substitutions and modifications can be made herein without departing from the spirit and scope of the present disclosure.
[0497] The abstract at the end of this disclosure is provided to allow readers to quickly ascertain the nature of the technical disclosure. It should be understood that it should not be used to interpret or limit the scope or meaning of the claims.
Claims
1. An integrated well construction device, comprising: A control workstation for use with an integrated well construction system IWCS, wherein the integrated well construction system IWCS is operable for constructing a well by integrated control of a plurality of integrated control devices that collectively control a plurality of integrated subsystems of the integrated well construction system IWCS, wherein the plurality of integrated subsystems include: a top drive, a drawworks, an automatic slip, a top drive elevator, an iron roughneck, a drilling fluid pumping system, a catwalk, an automatic pipe racker, an automatic fingerboard, and a tubular delivery arm, and wherein the control workstation includes: one or more sensors configured to monitor the plurality of integrated subsystems to obtain sensor feedback; and A human-machine interface (HMI) comprising a display, one or more input devices and a processing system, wherein the one or more input devices comprise a keyboard, a mouse, a touch screen, a joystick, or any combination thereof, and wherein the processing system comprises a processor and a memory having a construction program thereon, wherein the construction program, when executed by the processor: displaying sensor feedback from the one or more sensors; Receiving, through the one or more input devices, operating parameters for one or more well construction machines of the plurality of integrated subsystems to execute a well construction sequence, wherein the operating parameters include an automation level and are used for each of the plurality of integrated subsystems, and wherein the automation level is selected based on: automatic control by the construction program; automatic control by the construction program after confirmation by a human operator; and manual operation by the human operator; and sending one or more control signals to the plurality of integrated control devices to cause the plurality of integrated subsystems to execute the well construction sequence based on the operating parameters and the sensor feedback, wherein the well construction sequence is selected from at least one of the following: Lift up a single pipe fitting; Make drilling connections; Construction of pipe stands; Insert the drill collar to set the roots; Pull out the drill collar stand; Wet drilling; Reverse eye; Use a top drive to move individual tubulars from the center of the well to the catwalk; moving a tubular stand from the well center to the catwalk; moving casing from the catwalk to the center of the well using a casing tong; moving casing from the catwalk to the center of the well using a tubular delivery arm and a casing running tool; Using the top drive and the casing running tool to move a large diameter casing from the catwalk to the center of the well; construct casing stands; or The casing stand is run without using the casing running tool.
2. The apparatus of claim 1, wherein the operating parameters include a speed limit for at least one of the one or more well construction machines.
3. The apparatus of claim 1, wherein the operating parameter comprises a travel stop of at least one of the one or more well construction machines.
4. The apparatus of claim 1, wherein the operating parameters include a maximum limit of at least one of the one or more well construction machines.
5. The apparatus of claim 1, wherein the operating parameters include target settings for at least one of the one or more well construction machines.
6. The apparatus of claim 1, wherein the operating parameters include target settings for the well construction sequence.
7. The apparatus of claim 1, wherein the human operator causes initiation of the well construction sequence by actuating a button on the touch screen.
8. The apparatus of claim 1, wherein the human operator causes initiation of the well construction sequence by actuating the one or more input devices to ramp up a speed of the one or more well construction machines.
9. The apparatus of claim 1, wherein the construction program allows the human operator to manually control one or more of the well construction machines during the well construction sequence.
10. The apparatus of claim 1, wherein the construction program allows the human operator to modify operating parameters of one or more of the well construction machines during the well construction sequence.