Boiler system with dual functions of burning kiln mud and providing gas heating and its operation method

By designing a dual-function boiler system, using a fluidized bed form and an adiabatic heat-absorbing structure, the synchronous or separate combustion of pit mud and gas is realized, which solves the problems of stable combustion of pit mud and seasonal heating and ensures stable heating. performance and energy savings.

CN112113229BActive Publication Date: 2024-10-22ZHEJIANG TUFF BOILER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202011103561.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-10-15
Publication Date
2024-10-22
Estimated Expiration
2040-10-15

AI Technical Summary

Technical Problem

Due to the difficulty of stable combustion of pit mud and the demand for seasonal heating, it is difficult for existing boilers to burn pit mud during the pit season and use gas for heating during the season without pit mud, resulting in unstable heating.

Method used

Design a boiler system with dual functions of incineration and gas heating. It adopts a fluidized bed boiler body, including an insulated water-cooled furnace and an absorbent water-cooled furnace, combined with a screw conveyor, a heating burner, and supplementary combustion. The burner and convection evaporation heat exchanger realize the simultaneous or separate combustion of pit mud and gas to ensure stable heating in different seasons.

Benefits of technology

It achieves high-efficiency combustion of pit mud and gas in the same furnace, saves energy, ensures the stability of factory heating in different seasons, solves the insulation and heat absorption requirements of pit mud combustion and gas heating, and achieves the dual-use effect of one furnace.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112113229B_ABST
    Figure CN112113229B_ABST
Patent Text Reader

Abstract

The present invention provides a boiler system with dual functions of burning pit mud and gas heating and its operation method, including a fluidized bed boiler body, a water-cooled air chamber of the boiler body connected to an air inlet pipe, and a top of the boiler body connected to a turning flue, characterized in that the boiler body includes an insulated hot and cold fireplace chamber located at the bottom and a heat-absorbing hot and cold fireplace chamber located at the top, the heat-absorbing hot and cold fireplace chamber and the insulated hot and cold fireplace chamber are connected in an integrated manner from top to bottom, a screw feeder is connected to the front wall or side wall of the insulated hot and cold fireplace chamber, an air distribution plate is arranged at the bottom of the insulated hot and cold fireplace chamber, a heating burner is connected to the side wall of the heat-absorbing hot and cold fireplace chamber, a supplementary combustion burner is connected to the water-cooled air chamber, and a convection evaporation heat exchanger, an SCR denitrification flue, an economizer and an air preheater are connected after the turning flue. The present invention designs the boiler into a two-part structure to correspond to the insulation requirements of pit mud burning and the heat absorption requirements of gas low-nitrogen combustion, so that pit mud burning and gas combustion are combined and burned in one furnace.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of mechanical technology and relates to a boiler application, in particular to a boiler system with dual functions of burning pit mud and providing gas heating and an operation method thereof. Background Art

[0002] The cellar mud has high water content and low calorific value. The stable combustion of the cellar mud has always been a difficulty. In addition, the stacking of the cellar mud pollutes the environment. The combustion of the cellar mud to generate steam can recover a certain amount of heat and achieve energy-saving effects. At the same time, the brewing industry that produces cellar mud is cyclical, and in the months when there is no cellar mud, gas is needed to complete the heating.

[0003] Therefore, there is a need for a boiler that can burn the cellar mud for heating in the season when the cellar mud is produced, and use the existing boiler to burn gas for heating in the season when there is no cellar mud, so as to achieve the effect of one furnace for two purposes. Summary of the invention

[0004] The purpose of the present invention is to address the above-mentioned problems in the existing technology and to propose a boiler system and its operation method which combines pit mud burning and gas heating to achieve combustion of both in the same furnace to improve work efficiency and save energy.

[0005] The object of the present invention can be achieved through the following technical scheme: a boiler system with dual functions of burning pit mud and gas heating, including a fluidized bed boiler body, a water-cooled air chamber of the boiler body connected to an air inlet pipe, and a top opening of the boiler body connected to a turning flue, characterized in that the boiler body includes an insulated water-cooling fireplace chamber located at the bottom and a water-absorbing water-cooling fireplace chamber located at the top, the water-absorbing water-cooling fireplace chamber and the insulated water-cooling fireplace chamber are integrally connected up and down, a screw feeder is connected to the front wall or side wall of the insulated water-cooling fireplace chamber, an air distribution plate is arranged at the bottom opening of the insulated water-cooling fireplace chamber, a heating burner is connected to the side wall of the water-absorbing water-cooling fireplace chamber, a supplementary combustion burner is connected to the water-cooled air chamber, and a convection evaporative heat exchanger, an SCR denitrification flue, an economizer and an air preheater are connected to the back of the turning flue.

[0006] This boiler system uses a fluidized bed to burn the pit mud. The heating system is a prior art, so it will not be described in detail here.

[0007] In the above-mentioned boiler system with dual functions of burning kiln mud and providing gas heating, the port of the air inlet pipe is connected to the air preheater.

[0008] In the above-mentioned boiler system with dual functions of burning kiln mud and providing gas heating, the screw feeder includes an outer shell, a screw feeding rod is arranged inside the outer shell, the screw feeding rod is driven and connected by a feeding motor, a feed port is arranged at one end of the outer shell, and a discharge port is arranged at the other end, and the discharge port is connected to the inner cavity of the insulated hot and cold fireplace hearth.

[0009] In the above-mentioned boiler system with dual functions of burning kiln mud and providing gas heating, the gas combustion injection port of the heating burner extends into the inner cavity of the water-absorbing and cooling hearth.

[0010] In the above-mentioned boiler system with dual functions of burning kiln mud and providing gas heating, the gas combustion injection port of the heating burner is arranged to be inclined downward.

[0011] In the above-mentioned boiler system with dual functions of burning kiln mud and providing gas heating, the gas combustion injection port of the supplementary combustion burner extends into the tube cavity of the air inlet pipe.

[0012] In the above-mentioned boiler system with dual functions of burning pit mud and gas heating, a discharge curved membrane wall is protruded on the side wall of the heat-absorbing and cooling hearth, and the heating burner is fixedly mounted on the discharge curved membrane wall. The protruding structure of the discharge curved membrane wall facilitates the flame of the heating burner to spray downward to ensure the combustion size of the flame.

[0013] The operation method of the boiler system with dual functions of burning kiln mud and gas heating includes the following contents:

[0014] A. Incineration of pit mud and gas heating are carried out simultaneously:

[0015] 1) The cellar mud is transported to the insulated hot and cold firebox of the boiler body through the screw conveyor. At the same time, the air is blown into the insulated hot and cold firebox through the air distribution plate from the air inlet pipe. The synchronous heating burner sprays gas into the boiler body and ignites it, so that the cellar mud and gas burn simultaneously in the boiler body.

[0016] 2) When the calorific value of the pit mud is insufficient, the supplementary combustion burner is turned on to spray gas into the air inlet pipe and ignite it to supplement the burning of the pit mud. The supplementary combustion burner has the functions of ignition and supplementary combustion;

[0017] 3) The flue gas generated by burning pit mud and burning gas enters the convection evaporation heat exchanger through the turning flue. The high-temperature flue gas exchanges heat with the circulating water in the convection evaporation heat exchanger, so that the flue gas temperature is reduced to 380℃, ensuring the temperature entering the denitration catalyst;

[0018] 4) The flue gas with initial cooling then enters the SCR denitrification flue for denitrification operation, and then enters the economizer and air preheater in sequence to continue to reduce the temperature and finally reaches the corresponding exhaust temperature to enter the rear flue gas treatment system to improve the thermal efficiency of the boiler;

[0019] B. Gas heating is carried out separately:

[0020] 1) First, spread a certain thickness of quartz sand or ash on the air distribution plate, turn on the heating burner to spray gas into the boiler body and ignite it;

[0021] 2) After the gas is sprayed downward and burned, it absorbs heat in the hot water cooling hearth area, then rotates upward through the turning flue and enters the convection evaporation heat exchanger. The high-temperature flue gas exchanges heat with the circulating water in the convection evaporation heat exchanger.

[0022] 3) After continuous heat absorption and cooling through the convection evaporative heat exchanger, economizer and air preheater, the high-temperature flue gas is finally discharged to the outside.

[0023] This boiler system solves the two characteristics of pit mud combustion, which requires adiabatic combustion, and gas low-nitrogen combustion, which uses endothermic combustion, to ensure the stability of heating in the plant area in different seasons and achieve the effect of one furnace for two purposes.

[0024] In the operating method of the above-mentioned boiler system with dual functions of incinerating kiln mud and providing gas heating, before step A, the air is first heated by an air preheater and then enters the boiler body through the air distribution plate; before step B, the air is first heated by an air preheater and then directly enters the boiler body.

[0025] In the operating method of the above-mentioned boiler system with dual functions of burning pit mud and providing gas heating, a certain thickness of castable is coated on the furnace wall of the insulated hot and cold fireplace hearth, and the castable forms an insulating layer to reduce the degree of absorption of the heat of the pit mud combustion by the insulated hot and cold fireplace hearth.

[0026] Compared with the prior art, the boiler system with dual functions of incinerating kiln mud and providing gas heating and its operation method have the following advantages:

[0027] The integrated boiler is designed with a lower insulation and upper heat absorption structure to meet the insulation requirements of pit mud firing and the heat absorption requirements of gas low-nitrogen combustion, so that pit mud firing and gas combustion are combined in one furnace. In the pit mud production season, both are used for joint heating to achieve waste heat reuse while disposing of pit mud; in the season when pit mud is not produced, gas is used for heating alone to ensure the stability of heating in the plant area in different seasons. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a structural diagram of a boiler system with dual functions of incinerating kiln mud and providing gas heating.

[0029] In the figure, 1. Insulated hot and cold water hearth; 2. Screw feeder; 3. Absorbent hot and cold water hearth; 4. Heating burner; 5. Air inlet pipe; 6. Air distribution plate; 7. Supplementary combustion burner; 8. Turning flue; 9. Convection evaporation heat exchanger; 10. SCR denitrification flue; 11. Economizer; 12. Air preheater. DETAILED DESCRIPTION

[0030] The following are specific embodiments of the present invention and the accompanying drawings to further describe the technical solution of the present invention, but the present invention is not limited to these embodiments.

[0031] like Figure 1 As shown, the boiler system with dual functions of incinerating kiln mud and gas heating includes a boiler body, a water-cooling air chamber of the boiler body connected to an air inlet pipe 5, a top of the boiler body connected to a turning flue 8, the boiler body includes an insulated hot and cold fireplace hearth 1 located at the bottom and a heat-absorbing hot and cold fireplace hearth 3 located at the top, the heat-absorbing hot and cold fireplace hearth 3 and the insulated hot and cold fireplace hearth 1 are integrally connected from top to bottom, a screw feeder 2 is connected to the front wall or side wall of the insulated hot and cold fireplace hearth 1, an air distribution plate 6 is arranged at the bottom of the insulated hot and cold fireplace hearth 1, a heating burner 4 is connected to the side wall of the heat-absorbing hot and cold fireplace hearth 3, a supplementary combustion burner 7 is connected to the water-cooling air chamber, and a convection evaporative heat exchanger 9, an SCR denitrification flue 10, an economizer 11 and an air preheater 12 are connected behind the turning flue 8.

[0032] This boiler system uses a fluidized bed to burn the pit mud. The heating system is a prior art, so it will not be described in detail here.

[0033] The port of the air inlet pipe 5 is connected to the air preheater 12 .

[0034] The screw feeder 2 comprises a shell, in which a screw feeding rod is arranged, the screw feeding rod is connected by a feeding motor, a feed port is arranged at one end of the shell, and a discharge port is arranged at the other end, and the discharge port is connected to the inner cavity of the insulated hot and cold fireplace chamber 1.

[0035] The gas combustion injection port of the heating burner 4 extends into the inner cavity of the hot water cooling fireplace 3 .

[0036] The gas combustion injection port of the heating burner 4 is arranged to be inclined downward.

[0037] The gas combustion injection port of the supplementary combustion burner 7 extends into the tube cavity of the air inlet pipe 5.

[0038] The side wall of the heat-absorbing and cooling fireplace 3 is convexly provided with a row of curved membrane walls, and the heating burner 4 is fixedly mounted on the row of curved membrane walls. The convex structure of the row of curved membrane walls is conducive to the flame of the heating burner 4 to spray downward to ensure the combustion size of the flame.

[0039] The operation method of the boiler system with dual functions of burning kiln mud and gas heating includes the following contents:

[0040] A. Incineration of pit mud and gas heating are carried out simultaneously:

[0041] 1) The cellar mud is transported to the insulated hot and cold fire hearth 1 of the boiler body through the screw conveyor 2, and at the same time, the air is blown into the insulated hot and cold fire hearth 1 through the air inlet pipe 5 and the air distribution plate 6, and the synchronous heating burner 4 sprays gas into the boiler body and ignites it, so that the cellar mud and the gas are burned simultaneously in the boiler body;

[0042] 2) When the calorific value of the pit mud is insufficient, the supplementary combustion burner 7 is turned on to spray gas into the air inlet pipe 5 and ignite it, so as to supplement the burning of the pit mud. The supplementary combustion burner 7 has the functions of both ignition and supplementary combustion;

[0043] 3) Flue gas generated by burning pit mud and burning gas enters the convection evaporation heat exchanger 9 through the turning flue 8. The high-temperature flue gas exchanges heat with circulating water in the convection evaporation heat exchanger 9, so that the flue gas temperature is reduced to 380°C to ensure the temperature entering the denitration catalyst;

[0044] 4) The flue gas with initial cooling then enters the SCR denitrification flue 10 for denitrification operation, and then enters the economizer 11 and the air preheater 12 in sequence to continue to reduce the temperature and finally reaches the corresponding exhaust temperature to enter the rear flue gas treatment system, thereby improving the thermal efficiency of the boiler;

[0045] B. Gas heating is carried out separately:

[0046] 1) First, a certain thickness of quartz sand or ash is laid on the air distribution plate 6, and the heating burner 4 is turned on to spray gas into the boiler body and ignite it;

[0047] 2) After the gas is sprayed downward and burned, it absorbs heat in the hot water cooling hearth 3, and then rotates upward through the turning flue 8 to enter the convection evaporation heat exchanger 9, where the high-temperature flue gas exchanges heat with the circulating water;

[0048] 3) After continuous heat absorption and cooling in the convection evaporation heat exchanger 9, the economizer 11 and the air preheater 12, the high-temperature flue gas is finally discharged to the outside.

[0049] This boiler system solves the two characteristics of pit mud combustion, which requires adiabatic combustion, and gas low-nitrogen combustion, which uses endothermic combustion, to ensure the stability of heating in the plant area in different seasons and achieve the effect of one furnace for two purposes.

[0050] Before step A, the air is first heated by the air preheater 12 and then enters the boiler body through the air distribution plate 6; before step B, the air is first heated by the air preheater 12 and then directly enters the boiler body.

[0051] The furnace wall of the insulated hot and cold fireplace hearth 1 is coated with a castable of a certain thickness, and the castable forms an insulating layer to reduce the absorption degree of the heat of the burning pit mud by the insulated hot and cold fireplace hearth 1.

[0052] Compared with the prior art, the boiler system with dual functions of incinerating kiln mud and providing gas heating and its operation method have the following advantages:

[0053] The integrated boiler is designed with a lower insulation and upper heat absorption structure to meet the insulation requirements of pit mud firing and the heat absorption requirements of gas low-nitrogen combustion, so that pit mud firing and gas combustion are combined in one furnace. In the pit mud production season, both are used for joint heating to achieve waste heat reuse while disposing of pit mud; in the season when pit mud is not produced, gas is used for heating alone to ensure the stability of heating in the plant area in different seasons.

[0054] The specific embodiments described herein are merely examples of the spirit of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.

[0055] Although the terminology such as insulated hot and cold hearth 1; screw conveyor 2; hot and cold hearth 3; heating burner 4; air inlet pipe 5; air distribution plate 6; supplementary combustion burner 7; turning flue 8; convection evaporation heat exchanger 9; SCR denitrification flue 10; economizer 11; air preheater 12 is used more frequently in this article, the possibility of using other terms is not excluded. The use of these terms is only for more convenient description and explanation of the essence of the present invention; interpreting them as any additional limitation is contrary to the spirit of the present invention.

Claims

1. An operation method of a boiler system with dual functions of burning pit mud and gas heating, adopting a boiler system with dual functions of burning pit mud and gas heating, the boiler system comprising a boiler body, a water-cooling air chamber of the boiler body connected to an air inlet pipe, a top opening of the boiler body connected to a turning flue, the boiler body comprising an insulated hot and cold fireplace chamber located at the bottom and a water-absorbing hot and cold fireplace chamber located at the top, the water-absorbing hot and cold fireplace chamber and the insulated hot and cold fireplace chamber being integrally connected from top to bottom, a screw feeder connected to the side wall of the insulated hot and cold fireplace chamber, an air distribution plate arranged at the bottom opening of the insulated hot and cold fireplace chamber, a heating burner connected to the front wall or side wall of the water-absorbing hot and cold fireplace chamber, a post-combustion burner connected to the water-cooling air chamber, a convection evaporation heat exchanger, an SCR denitrification flue, an economizer and an air preheater connected to the back of the turning flue; It is characterized in that The operation method of the boiler system with dual functions of burning kiln mud and gas heating includes the following: A. Incineration of pit mud and gas heating are carried out simultaneously: 1) The cellar mud is transported to the insulated hot and cold firebox of the boiler body through the screw conveyor. At the same time, the air is blown into the insulated hot and cold firebox through the air distribution plate from the air inlet pipe. The synchronous heating burner sprays gas into the boiler body and ignites it, so that the cellar mud and gas burn simultaneously in the boiler body. 2) When the calorific value of the pit mud is insufficient, the supplementary combustion burner is turned on to spray gas into the air inlet pipe and ignite it to supplement the burning of the pit mud. The supplementary combustion burner has the functions of ignition and supplementary combustion; 3) The flue gas generated by burning pit mud and burning gas enters the convection evaporation heat exchanger through the turning flue. The high-temperature flue gas exchanges heat with the circulating water in the convection evaporation heat exchanger, reducing the flue gas temperature to 380°C to ensure the temperature entering the denitration catalyst; 4) The flue gas with initial cooling then enters the SCR denitrification flue for denitrification operation, and then enters the economizer and air preheater in sequence to continue to reduce the temperature and finally reach the corresponding exhaust temperature to enter the rear flue gas treatment system to improve the thermal efficiency of the boiler; the furnace wall of the insulated hot and cold firebox is coated with a certain thickness of castable, which forms an insulating layer to reduce the absorption of the heat of the pit mud combustion by the insulated hot and cold firebox; B. Gas heating is carried out separately: 1) First, spread a certain thickness of quartz sand or ash on the air distribution plate, turn on the heating burner to spray gas into the boiler body and ignite it; 2) After the gas is sprayed downward and burned, it absorbs heat in the hot water cooling hearth area, then rotates upward and passes through the turning flue into the convection evaporation heat exchanger. The high-temperature flue gas exchanges heat with the circulating water in the convection evaporation heat exchanger. 3) After continuous heat absorption and cooling through the convection evaporative heat exchanger, economizer and air preheater, the high-temperature flue gas is finally discharged to the outside.

2. The method for operating the boiler system with dual functions of burning kiln mud and providing gas heating according to claim 1, characterized in that: The port of the air inlet pipe is connected to the air preheater.

3. The operating method of the boiler system with dual functions of incinerating kiln mud and providing gas heating according to claim 1 is characterized in that: The screw feeder comprises a shell, a screw feeding rod is arranged inside the shell, the screw feeding rod is connected by a feeding motor, a feed port is arranged at one end of the shell, a discharge port is arranged at the other end, and the discharge port is connected to the inner cavity of the insulated hot and cold fireplace.

4. The method for operating the boiler system with dual functions of incinerating kiln mud and providing gas heating according to claim 1, characterized in that: The gas combustion injection port of the heating burner extends into the inner cavity of the heat-absorbing and cooling fireplace.

5. The method for operating the boiler system with dual functions of burning kiln mud and providing gas heating according to claim 4 is characterized in that: The gas combustion injection port of the heating burner is arranged to be inclined downward.

6. The method for operating the boiler system with dual functions of burning kiln mud and providing gas heating according to claim 1, characterized in that: The gas combustion injection port of the supplementary combustion burner extends into the tube cavity of the air inlet pipe.

7. The method for operating the boiler system with dual functions of burning kiln mud and providing gas heating according to claim 1, characterized in that: A discharge curved membrane wall is protruded on the side wall of the hot water absorbing and cooling fireplace, and the heating burner is fixedly mounted on the discharge curved membrane wall.

8. The method for operating the boiler system with dual functions of burning kiln mud and providing gas heating according to claim 1, characterized in that: Before step A, the air is first heated by the air preheater and then enters the boiler body through the air distribution plate; before step B, the air is first heated by the air preheater and then directly enters the boiler body.