Prediction device
By designing a prediction device in the online electric discharge processing machine, and using the prediction component consumption rate and display component consumption status, the problem of the wire electric discharge processing machine being difficult to predict the future consumption of components is solved, and reasonable preparations can be made before processing to reduce the risk of interruption. effect.
Patent Information
- Application Number
- CN202010742398.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-29
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2040-07-29
AI Technical Summary
It is difficult for existing wire electric discharge machines to predict the future consumption of components before processing, which may lead to interruptions due to the exhaustion of life of components during processing.
A prediction device is designed. By connecting the wire electric discharge machine, the prediction part is used to predict the consumption rate of components according to the processing conditions, and the prediction results are displayed through the display part. The operator can select appropriate processing conditions or replace them based on the prediction results before processing. components, reducing the risk of disruption.
Effectively predict the consumption of components, help operators make reasonable preparations before processing, reduce the possibility of components being exhausted during processing, and improve the continuity and efficiency of processing.
Smart Images

Figure CN112296460B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a prediction device for managing a wire electrical discharge machine. Background Art
[0002] Japanese Patent Application Laid-Open No. 07-178622 proposes a wire monitor device that displays the current usage of multiple components of a wire feed mechanism for wire electrical discharge machining. Japanese Patent Application Laid-Open No. 07-178622 also describes that the disclosed wire monitor device facilitates life management of the wire feed mechanism. Summary of the invention
[0003] A technique has been proposed for the purpose of understanding how much of the components constituting a wire electrical discharge machine have been consumed so far, but it is difficult to understand how much of the components will be consumed due to machining scheduled to be performed in the future.
[0004] Therefore, an object of the present invention is to provide a prediction device that performs a prediction on the consumption of a component before machining and reports the result.
[0005] One scheme of the invention is a prediction device, which is connected to one or more wire discharge machines, which make the wire electrode move relative to the workpiece along a processing path and process the workpiece according to specified processing conditions. The prediction device comprises: a prediction unit, which predicts a predicted consumption rate based on the processing conditions when the wire electrode moves relative to each other per unit distance for a specified component constituting the wire discharge machine; and a display unit, which displays the predicted consumption rate of the component.
[0006] According to the present invention, there is provided a prediction device for predicting the consumption of a component before machining and reporting the result.
[0007] The above-mentioned objects, features and advantages will be easily understood from the following description of the embodiments with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] Figure 1 This is a schematic diagram of the configuration of a prediction device according to an embodiment.
[0009] Figure 2 This is a flowchart showing an example of the processing operation of the prediction device according to the embodiment.
[0010] Figure 3 This is an example of a display format of the display unit of the embodiment.
[0011] Figure 4 This is a schematic structural diagram of the prediction device of variant example 1.
[0012] Figure 5 This is a schematic structural diagram of the prediction device of variant example 2.
[0013] Figure 6 This is a flowchart showing an example of the processing operation of the prediction device according to the second modification. DETAILED DESCRIPTION
[0014] Hereinafter, the prediction device of the present invention will be described in detail with reference to the accompanying drawings by giving preferred embodiments thereof.
[0015] [Implementation Method]
[0016] Figure 1 It is a schematic structural diagram of the prediction device 10 according to the embodiment.
[0017] The prediction device 10 is a computing device including a computing unit (processor) 12 and a storage unit (memory) 14, and operates by the computing unit 12 executing a predetermined program stored in the storage unit 14. A wire electrical discharge machine that moves a wire electrode relative to a workpiece along a machining path and machines the workpiece according to predetermined machining conditions is connected to the prediction device 10.
[0018] The prediction device 10 includes a prediction unit 16 that predicts a predicted consumption rate indicating a consumption rate of a wire electrode when the wire electrode moves relative to a unit distance based on machining conditions for a predetermined component constituting the wire electric discharge machine, and a display unit 18 that displays the predicted consumption rate.
[0019] The calculation unit 12 includes a prediction unit 16. The prediction unit 16 predicts the predicted consumption rate of a predetermined component based on the predetermined processing conditions as described above. The prediction unit 16 of this embodiment has a table in which the processing conditions and the predicted consumption rates of the components are associated with each other, and predicts the predicted consumption rate by referring to the table. The table is prepared for each type of predetermined component, and the contents of each table can be obtained in advance through experiments.
[0020] The predetermined component constituting the wire electric discharge machine is not particularly limited as long as it is a component that is considered to be consumed by machining, and it is, for example, an electrode pin, a filter, or an ion resin. The prediction unit 16 may predict the predicted consumption rate for a plurality of components or for only one component.
[0021] The predetermined machining conditions are a combination of a plurality of control parameters created before machining is performed. The control parameters include, for example, the relative moving speed of the wire electrode relative to the workpiece, the magnitude of the voltage applied to the wire electrode, or the stop time of the voltage application. In addition, the specific method for determining the content of the machining conditions is not the main content of this embodiment, so it is omitted.
[0022] The wire electrical discharge machine has machining conditions, which are stored in, for example, a control device (CNC) included in the wire electrical discharge machine. The prediction device 10 acquires information on the machining conditions of the wire electrical discharge machine from the wire electrical discharge machine connected to the prediction device 10 .
[0023] The wire discharge machine of this embodiment has a plurality of processing conditions, namely, "emphasis on speed", "emphasis on precision" and "emphasis on surface roughness". "Emphasis on speed" is a processing condition set for the purpose of completing processing in the shortest possible time. "Emphasis on precision" is a processing condition set for the purpose of obtaining a shape that conforms to the processing path as much as possible. "Emphasis on surface roughness" is a processing condition set for the purpose of making the processing surface of the workpiece as smooth as possible. In this way, a plurality of processing conditions are prepared so that the operator can appropriately select the desired processing condition.
[0024] In addition, the prediction unit 16 can predict the predicted consumption rate for multiple machining conditions or only for one machining condition selected by the operator. As an example, the prediction unit 16 of this embodiment predicts the predicted consumption rate for each of the speed-focused, accuracy-focused, and surface roughness-focused conditions.
[0025] The display unit 18 has a screen that displays the predicted consumption rate predicted by the prediction unit 16. Thus, the operator can operate the wire discharge machine in consideration of the predicted consumption rate displayed on the display unit 18. The display unit 18 may display not only the predicted consumption rate but also information related to the machining conditions used as the basis for the prediction by the prediction unit 16.
[0026] For example, assuming that the predicted consumption rate of the filter for the important speed is greater than the predicted consumption rate of the filter for other processing conditions, the operator initially intends to perform processing at the important speed, but can determine before performing the processing that if the processing is started directly at the important speed, the life of the filter is likely to be exhausted in the middle of the processing.
[0027] In this case, the operator can start processing after replacing the filter with a new product. Alternatively, the operator can also select other processing conditions in which the predicted consumption rate of the filter is relatively small to perform processing.
[0028] The above is an example of the configuration of the prediction device 10 of the present embodiment. According to the prediction device 10, the possibility of interruption of machining due to the wear of the components constituting the wire electrical discharge machine is reduced.
[0029] In addition, the prediction device 10 of the embodiment is not limited to the above. For example, the prediction unit 16 may predict the predicted consumption rate and then predict the predicted consumption amount indicating the consumption amount of the component when the machining is performed. In this case, the display unit 18 may also display the predicted consumption amount.
[0030] The predicted consumption is a value calculated based on the machining path and the predicted consumption rate. By displaying the predicted consumption on the display unit 18, the operator can operate the wire electrical discharge machine in consideration of not only the predicted consumption rate displayed on the display unit 18 but also the predicted consumption.
[0031] In addition, when predicting the predicted consumption, the calculation unit 12 may further include: a consumption acquisition unit 20 that acquires the consumption of the component so far; and a determination unit 22 that determines whether the total value of the consumption of the component so far and the predicted consumption predicted by the prediction unit 16 is greater than a threshold value ( Figure 1 ).
[0032] The consumption of the component so far can be obtained, for example, by installing a sensor capable of detecting the state of the component in the wire discharge machine, comparing the state of the component before and after processing, thereby obtaining the consumption of the processing, and accumulating and storing the obtained result in the storage unit 14. In this case, the consumption acquisition unit 20 can obtain the consumption of the component so far by referring to the storage unit 14. The method of obtaining the consumption so far is not limited to this. For example, the state of the component as a new product can be pre-stored in the storage unit 14, the state of the component after processing can be obtained by the sensor, and the state of the component as a new product and the state after processing can be compared to obtain the consumption so far. The threshold value can be appropriately set and changed, for example, the level of consumption recommended by the component manufacturer for replacing the component.
[0033] When the total value of the component's consumption so far and the predicted consumption predicted by the prediction unit 16 is greater than the threshold value, it means that the component is likely to run out of life in the middle of the next processing. In addition, when the total value is less than the threshold value, it means that the component is unlikely to run out of life in the middle of the next processing. Therefore, by reporting the judgment result to the operator, the operator can easily and appropriately judge whether the component replacement operation is required before the processing is performed.
[0034] In addition, a plurality of wire electrical discharge machines may be connected to the prediction device 10. Thus, a system including the prediction device 10 and a plurality of wire electrical discharge machines connected to the prediction device 10 is constructed. In this system, the prediction device 10 may predict the predicted consumption rate of a predetermined component based on predetermined machining conditions for each of the plurality of wire electrical discharge machines.
[0035] In addition, the prediction device 10 connected to the wire EDM includes a mode in which the prediction device 10 is integrated with the wire EDM as a device as long as the functional connection is made. For example, the CNC of the wire EDM may include the prediction unit 16, the display unit 18, the consumption acquisition unit 20, and the determination unit 22.
[0036] Next, a description will be given of the flow of processing operations of the above-mentioned prediction device 10. In addition, the following description will be given of a case where the prediction device 10 predicts not only the predicted consumption rate but also the predicted consumption amount.
[0037] Figure 2 This is a flowchart showing an example of the processing operation of the prediction device 10 according to the embodiment.
[0038] First, the prediction device 10 acquires one or more predetermined machining conditions from the wire electric discharge machine connected to itself (step S1 ). It is assumed that the prediction device 10 of this embodiment acquires three machining conditions of emphasizing speed, emphasizing accuracy, and emphasizing surface roughness.
[0039] Next, the prediction unit 16 of the prediction device 10 predicts the predicted consumption rate of the specified component based on the processing conditions acquired in step S1 (step S2). It is assumed that the prediction unit 16 of this embodiment predicts the predicted consumption rate of each of the electrode pin, the filter, and the ion resin based on the three processing conditions acquired in step S1.
[0040] Next, the display unit 18 displays the prediction result in step S2 (the predicted consumption rate based on the processing conditions of the specified component) (step S3). Thus, the operator can select the desired processing conditions in consideration of the predicted consumption rate displayed on the display unit 18. In addition, the operator can also perform the replacement operation of any component among the three specified components when the predicted consumption rate based on the processing conditions desired by the operator is large.
[0041] Figure 3 This is an example of the display format of the display unit 18 according to the embodiment.
[0042] The display format of the display unit 18 in step S3 is not limited, but in this embodiment, it is assumed that Figure 3 Like that. Figure 3In the example, for each icon A to C representing the processing conditions, the item name D of the information in the icons A to C is displayed, and a bar graph E representing the information of the item name D is displayed on the right. Icons A, B, and C represent processing conditions that emphasize speed, emphasize accuracy, and emphasize surface roughness in this order. For each icon A to C, the length of the bar graph E shown on the right side of the figure for the speed, accuracy, and surface roughness of the item name D respectively indicates how much importance is attached to the item shown on the left. In addition, the length of the bar graph E shown on the right side of the figure for the electrode pin, filter, and ion resin in the item name D respectively indicates the size of the predicted consumption rate of the item shown on the left based on the corresponding processing conditions.
[0043] When the operator selects the machining conditions, the prediction unit 16 predicts the predicted consumption (step S4). At this time, the prediction unit 16 obtains information related to the machining path (e.g., machining program) from the wire EDM connected to itself before predicting the predicted consumption. Thus, the prediction unit 16 can predict the predicted consumption based on the predicted consumption rate and the machining path.
[0044] Next, the consumption acquisition unit 20 acquires the consumption of the predetermined component up to now (step S5). In addition to the method described above, the consumption of the predetermined component up to now may be acquired based on, for example, a general technique related to the remaining life management of machine tool components.
[0045] Next, the determination unit 22 calculates the total of the predicted consumption of the predetermined component and the consumption so far, and determines whether the total is equal to or greater than a threshold value (step S6). The threshold value is assumed to be "the consumption of the component manufacturer's recommended replacement component."
[0046] Next, the display unit 18 displays the determination result in step S6 (step S7). The display format of the determination result in step S7 is not particularly limited. For example, if the above-mentioned total value is greater than the threshold value, it is considered to display a message such as "The life of the specified component may be exhausted in the middle of the next processing, so maintenance work is recommended." In this way, the operator can easily and appropriately determine whether maintenance work is required for the specified component before performing processing.
[0047] The above is an example of the processing operation of the prediction device 10 according to the embodiment.
[0048] In addition, the processing actions of the prediction device 10 are not limited to the above. For example, in the above, it is described that after predicting the predicted consumption rate based on each of a plurality of processing conditions, the operator can select the processing conditions in consideration of the predicted consumption rate. Not limited to this, the prediction device 10 may also predict the predicted consumption rate based on the selected processing condition after allowing the operator to select the processing condition. The operator may also change the processing condition after confirming the predicted consumption rate based on the processing condition selected by himself using the display unit 18. In addition, for example, steps S4 to S7 may also be omitted.
[0049] [Modifications]
[0050] Although the embodiment is described above as an example of the present invention, various changes or improvements can be made to the above-mentioned embodiment. It is clear from the description of the claims that the form to which such changes or improvements are added is also included in the technical scope of the present invention.
[0051] (Variant 1)
[0052] Figure 4 This is a schematic diagram of the structure of the prediction device 10 according to the first modification.
[0053] The prediction device 10 may further include: a consumption rate acquisition unit 24 that acquires the consumption rate of the component based on the execution result of the machining; and a table update unit 26 that updates the table based on the consumption rate acquired by the consumption rate acquisition unit 24. Figure 4 In the example, the computing unit 12 includes a consumption rate acquisition unit 24 and a table update unit 26. For example, a sensor for observing the state of a component is provided in the wire discharge machine, and the consumption rate acquisition unit 24 acquires the consumption rate of the component based on a comparison of the states of the component before and after machining and the machining path.
[0054] As described in the embodiment, the table that the prediction unit 16 refers to when predicting the predicted consumption rate is obtained in advance by experiments. However, the consumption rate of a predetermined component constituting the wire electrical discharge machine may change depending on how the wire electrical discharge machine is used or the environment in which it is installed.
[0055] Therefore, in this modification, as described above, the table referenced by the prediction unit 16 is updated based on the execution result of machining. This can improve the accuracy of the prediction by the prediction unit 16 in accordance with the method of use or the environment in which the wire electrical discharge machine is installed.
[0056] (Variant 2)
[0057] Figure 5 This is a schematic structural diagram of the prediction device 10 according to the second modification.
[0058] In the above description, the prediction unit 16 has a table in which machining conditions and predicted consumption rates are associated with each other, and the prediction unit 16 predicts the predicted consumption rate by referring to the table. This is not limited to this, and the prediction unit 16 may predict the predicted consumption rate based on a model function that takes the machining conditions as input and outputs the predicted consumption rate.
[0059] Here, the model function is explained. The model function of this modification has a structure that is generally also conceptually referred to as a "multilayer neural network (neural network)". That is, the model function of this modification adds weights to each component of the vector as input and adds them, and then applies a specified activation function to the result, thereby generating a new value (neuron). The generation of neurons is performed multiple times with changing weights for the same vector. Thus, multiple neurons based on the same vector are generated, and new vectors with the multiple neurons as components are generated. The model function repeats the above-mentioned weighting and addition on the generated vector, and finally generates (outputs) 1 neuron.
[0060] In the case of this variation, the vector initially input to the model function is the processing condition. The components of the vector are the multiple control parameters included in the processing condition. In addition, the neuron finally output by the model function is a neuron representing the predicted consumption rate. The activation function of the model function is not particularly limited as long as it is a function generally known as an activation function, for example, a ramp function.
[0061] Regarding the model function, the model function obtained by experiment is stored in the memory in advance, and the prediction unit 16 can refer to it appropriately. In this way, the prediction device 10 can predict the predicted consumption rate based on the processing conditions. In this modified example, when the prediction unit 16 predicts the predicted consumption rate, a table corresponding to the processing conditions and the predicted consumption rate is not required.
[0062] In addition, the accuracy of the predicted consumption rate output by the model function changes due to the number of layers of the neural network (how many times the vector is generated), the type of activation function of the model function, and the setting of the weight multiplied by the components of the vector. In connection with this, the prediction device 10 may also include a consumption rate acquisition unit 24, an error acquisition unit 28, and a function update unit 30 in order to obtain the best model function for predicting the predicted consumption rate through regression learning. Below, it is also explained in order based on the flow of the processing action.
[0063] Figure 6 is a flowchart showing an example of the processing operation of the prediction device 10 according to the second modification. Figure 6 The "start" is after the wire EDM performs machining.
[0064] The consumption rate acquisition unit 24 is as described in Modification 1. That is, after executing machining, the consumption rate acquisition unit 24 acquires the consumption rate of a predetermined component based on the execution result of the machining (step S11).
[0065] The error acquisition unit 28 acquires the error between the predicted consumption rate predicted by the prediction unit 16 and the consumption rate acquired by the consumption rate acquisition unit 24 (step S12). The predicted consumption rate and the acquired consumption rate used for error acquisition are predictions and acquisitions of the same processing. Thus, the accuracy of the prediction of the prediction unit 16 relative to the actual processing result is expressed by a numerical value. The error is not limited to a simple "difference" between the predicted consumption rate and the acquired consumption rate, and can also be obtained as a value obtained by squaring the "difference", for example.
[0066] The function updating unit 30 optimizes the model function in a manner that minimizes the error acquired by the error acquiring unit 28 (step S13). The optimization of the model function is performed by changing at least one of the weights, the number of layers of the multilayer neural network, and the activation function. At this time, in order to efficiently optimize the model function, the techniques and algorithms for solving optimization problems known in the field of mathematical programming may also be applied to the function updating unit 30.
[0067] Thereby, the prediction device 10 can learn a model function that can predict the predicted consumption rate with high accuracy.
[0068] [Inventions from Embodiments]
[0069] Hereinafter, the invention that can be grasped from the above-mentioned embodiment and modified examples will be described.
[0070] A prediction device (10) is connected to one or more wire discharge machines, wherein the wire discharge machines move a wire electrode relative to a workpiece along a processing path and process the workpiece according to specified processing conditions. The prediction device (10) comprises: a prediction unit (16) which predicts a predicted consumption rate representing a consumption rate of the wire electrode when the wire electrode moves relative to the workpiece for a unit distance based on the processing conditions for a specified component constituting the wire discharge machine; and a display unit (18) which displays the predicted consumption rate of the component.
[0071] Thus, a prediction device (10) is provided which predicts the consumption of components before machining and reports the result.
[0072] The prediction unit (16) may predict a predicted consumption amount indicating the consumption amount of the component when the machining is performed based on the machining path and the predicted consumption rate, and the display unit (18) may display the predicted consumption amount. Thus, it becomes easy for the operator to operate the wire discharge machining machine in consideration of not only the predicted consumption rate but also the predicted consumption amount.
[0073] The invention may further include: a consumption acquisition unit (20) for acquiring the consumption of the component so far; and a determination unit (22) for determining whether the total value of the consumption of the component so far and the predicted consumption predicted by the prediction unit (16) is greater than a threshold value, and the display unit (18) displays the determination result determined by the determination unit (22). Thus, it becomes easy for an operator to easily and appropriately determine whether maintenance work is required for a predetermined component before executing processing.
[0074] The prediction unit (16) may also have a table in which the processing conditions and the predicted consumption rates of the components are associated with each other, and the predicted consumption rate is predicted by referring to the table. Thus, the prediction unit (16) can predict the predicted consumption rate of a predetermined component based on predetermined processing conditions by referring to the table.
[0075] The invention may further include: a consumption rate acquisition unit (24) for acquiring the consumption rate of the component based on the result of the machining; and a table updating unit (26) for updating the table based on the consumption rate acquired by the consumption rate acquisition unit (24). Thus, the prediction accuracy of the prediction unit (16) can be improved to adapt to the usage method or installation environment of the wire electric discharge machine.
[0076] Alternatively, the prediction unit (16) predicts the predicted consumption rate by using a model function that takes the machining conditions as input and takes the predicted consumption rate as output, and the prediction device (10) further comprises: a consumption rate acquisition unit (24) that acquires the consumption rate of the component based on the execution result of the machining; an error acquisition unit (28) that acquires the error between the predicted consumption rate predicted by the prediction unit (16) and the consumption rate acquired by the consumption rate acquisition unit (24); and a function updating unit (30) that optimizes the model function in a manner that minimizes the error. Thus, the prediction device (10) can predict the predicted consumption rate of a specified component based on specified machining conditions by using a model function. In addition, the prediction device (10) can learn a model function that can predict the predicted consumption rate with high accuracy.
[0077] The wire electrical discharge machine may be composed of a plurality of the components, and the prediction unit (16) may perform prediction for the plurality of components. Thus, the predicted consumption rate and the predicted consumption amount may be predicted for a plurality of predetermined components constituting the wire electrical discharge machine.
[0078] The wire electrical discharge machine may have a plurality of machining conditions, and the prediction unit (16) may perform prediction for the plurality of machining conditions. Thus, the predicted consumption rate and the predicted consumption amount may be predicted for the plurality of predetermined machining conditions of the wire electrical discharge machine.
Claims
1. A prediction device connected to one or more wire electrical discharge machines, wherein the wire electrical discharge machines move a wire electrode relative to a workpiece along a processing path and perform processing of the workpiece according to predetermined processing conditions, the prediction device comprising: a prediction unit that predicts a predicted consumption rate indicating a consumption rate based on the machining conditions when the wire electrode relatively moves a unit distance for a predetermined component constituting the wire electrical discharge machine; and a display unit for displaying the predicted consumption rate of the component, The wire electrical discharge machine has a plurality of machining conditions, and the machining conditions include: Focus on speed, precision, and surface roughness. The prediction unit predicts a plurality of predicted consumption rates, the plurality of predicted consumption rates including: a predicted consumption rate when the processing is started according to the emphasis on speed, a predicted consumption rate when the processing is started according to the emphasis on accuracy, and a predicted consumption rate when the processing is started according to the emphasis on surface roughness. The display unit displays the plurality of predicted consumption rates corresponding to the plurality of machining conditions before the machining starts.
2. The prediction device according to claim 1, characterized in that The prediction unit predicts a predicted consumption amount indicating a consumption amount of the component when the machining is performed based on the machining path and the predicted consumption rate. The display unit displays the predicted consumption.
3. The prediction device according to claim 2, characterized in that Also available: a consumption amount acquisition unit that acquires the consumption amount of the component to date; and a determination unit configured to determine whether a total value of the consumption of the component up to now and the predicted consumption predicted by the prediction unit is equal to or greater than a threshold value, The display unit displays a determination result determined by the determination unit.
4. The prediction device according to any one of claims 1 to 3, characterized in that: The prediction unit has a table in which the machining conditions and the predicted consumption rate of the component are associated with each other, and predicts the predicted consumption rate by referring to the table.
5. The prediction device according to claim 4, characterized in that Also available: a consumption rate acquisition section that acquires a consumption rate of the component based on a result of execution of the processing; and A table updating unit updates the table based on the consumption rate acquired by the consumption rate acquiring unit.
6. The prediction device according to any one of claims 1 to 3, characterized in that: The prediction unit predicts the predicted consumption rate by using a model function that takes the processing condition as an input and takes the predicted consumption rate as an output, The prediction device further comprises: a consumption rate acquisition unit that acquires a consumption rate of the component based on an execution result of the processing; an error obtaining unit, which obtains an error between the predicted consumption rate predicted by the prediction unit and the consumption rate obtained by the consumption rate obtaining unit; as well as A function updating unit optimizes the model function in such a way as to minimize the error.
7. The prediction device according to any one of claims 1 to 3, characterized in that: The wire discharge machine is composed of a plurality of the above components. The prediction unit performs prediction on the plurality of components.
Citation Information
Patent Citations
Wire monitor for wire cut electric discharge machine
JP1995178622A
Electrical Discharge Machining Machine
JP5595559B1
Wire discharge machining apparatus
US20150202701A1
Wire electric discharge machine having estimation function for filter replacement timing
US20160096231A1
Self-learning filter lifetime estimation method
US20180266935A1