A steel pipe pile structure of a steel box beam and a construction method thereof
By arranging triangular stiffening plates around the steel box girder steel pipe piles and welding them to the concrete foundation layer, combined with small mechanical excavation and brick slag replacement, the problem of steel pipe piles sinking in clayey soil has been solved, and a low-cost, cost-effective solution has been achieved. Good suitability for steel box girder installation.
Patent Information
- Application Number
- CN202110181567.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-02-09
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-02-09
AI Technical Summary
During the installation process of the steel box girder, when the steel pipe piles are under special adverse conditions (such as floods, long-term local erosion, weak geology, etc.), the friction between the steel pipe piles and the soil is insufficient, causing the steel pipe piles to sink slowly. The existing The cement-water glass grouting process does not work well in clayey soils and is costly and complex to operate.
The steel pipe pile structure using steel box beams includes a concrete base layer, reinforcement area and stiffening plate. Triangular stiffening plates are set around the steel pipe pile and welded to the concrete base layer, combined with small mechanical excavation and replacement of brick slag or crushed materials. stone to form a stable foundation and prevent the steel pipe piles from sinking.
This method does not require special equipment, has low construction cost, is suitable for different geological conditions, can effectively prevent the steel pipe piles from sinking, improve the foundation strength, and ensure the installation accuracy of the steel box beams.
Smart Images

Figure CN112814008B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of bridges, and in particular to a steel pipe pile structure of a steel box girder and a construction method thereof. Background Art
[0002] The support method is a common process for installing steel box girders. When constructing near riverbanks or weak foundations, steel pipe piles are often used for force support, mainly using the friction between the side walls of the steel pipe piles and the soil to offset the upper load. However, during the installation of steel box girders, when the steel pipe pile support is subjected to special adverse conditions, such as floods, long-term local scouring, and local geology is weak, resulting in insufficient friction between the steel pipe column and the soil, the steel pipe piles will slowly sink, and the steel pipe piles need to be strengthened.
[0003] The process often used in engineering is cement-water glass grouting process, that is, first drill grouting holes around the soil, prepare the grouting solution according to the mix ratio, use a grouting machine to grout, and seal the grouting holes. This process can quickly fill the caves and other unfavorable geological conditions in the foundation under certain conditions to improve the bearing capacity of the foundation. However, this process has the following disadvantages: (1) The grouting process is suitable for reinforcing shallow concrete strip foundations. The depth of the steel pipe pile foundation is large, and it is impossible to reasonably judge the effect of grouting. (2) The grouting process is suitable for sandy or silty soil with large porosity, and its solution has good fluidity. However, the geology of this project is clay soil, the soil porosity is small, and the solution fluidity is poor. (3) It takes a long time for the grouting machine to enter the site, and a dedicated person is required to operate the machine, which is expensive. Summary of the invention
[0004] The main purpose of the present application is to provide a steel pipe pile structure for a steel box girder, which can utilize the soil around the steel pipe piles to bear the load and prevent the steel pipe piles from sinking.
[0005] On the one hand, the main purpose of the present application is to provide a steel pipe pile structure of a steel box beam, comprising:
[0006] Steel box girder;
[0007] A concrete base layer, located below the surface layer;
[0008] a reinforcement zone located below the concrete foundation layer;
[0009] The steel pipe pile has one end located below the steel box girder and connected to the steel box girder, and the other end inserted into the ground layer and passes through the concrete foundation layer and the reinforcement area.
[0010] Preferably, it also includes a plurality of stiffening plates, which are distributed around the steel pipe piles on the surface layer.
[0011] Preferably, it also includes connecting steel bars, which are located below the stiffening plate and are in an inverted "U" shape. The connecting steel bars are connected to the lower surface of the stiffening plate, and both ends of the connecting steel bars penetrate into the concrete foundation layer.
[0012] Preferably, the connecting steel bars and the stiffening plates are fixed by welding.
[0013] Preferably, both ends of the connecting steel bar are provided with hooks extending to the concrete foundation layer.
[0014] Preferably, the reinforcement area is composed of brick slag or crushed stone, and the thickness of the reinforcement area is 70-90 cm, more preferably 60 cm, which can stabilize the foundation soil.
[0015] Preferably, the concrete foundation layer has a thickness of 10-30 cm, more preferably 20 cm, and is made of C20 concrete.
[0016] Preferably, the stiffening plates are triangular stiffening plates, and there are four of them, which are evenly distributed around the steel pipe piles.
[0017] On the other hand, the present application also provides a construction method of a steel pipe pile structure of a steel box beam, comprising the following steps:
[0018] S1, foundation pit excavation: small machinery cooperates with manual labor to excavate the soil within a certain range around the steel pipe piles, with a depth of 0.5-1.5m, to remove the silt and impurities on the original ground. Preferably, the excavation depth is 1m;
[0019] S2, replacement and reinforcement area: Brick slag or crushed stone are placed within 70-90cm from the original ground to stabilize the foundation soil;
[0020] S3, pouring concrete foundation layer and pre-embedded connecting steel bars: pour a layer of C20 concrete with a thickness of 10-30cm on the replaced brick slag or gravel, and pre-embed connecting steel bars matching the size of the stiffening plate near the steel pipe piles to ensure accurate positioning;
[0021] S4, welding stiffening plates: when the strength of the concrete foundation layer reaches the required level, four stiffening plates are evenly arranged around the steel pipe piles and welded tightly to the embedded connecting steel bars.
[0022] The beneficial effects of the present application are: by evenly arranging and welding 4 triangular pressure plates around the steel pipe piles, by replacing the foundation around the steel pipe piles, pouring concrete, and setting embedded plates and welding the steel pipe pile pressure plates at the corresponding positions of the concrete foundation. The structure is simple and feasible, does not require special grouting machines and other professional equipment, and has low construction costs. It is not affected by geological porosity and has good applicability. When the foundation strength reaches the requirement, the triangular pressure plates are welded at the corresponding positions to withstand the force and prevent the steel pipe piles from continuing to sink. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:
[0024] Figure 1 It is a schematic diagram of the overall structure of a steel pipe pile structure of a steel box beam;
[0025] Figure 2 It is a partial schematic diagram of a steel pipe pile structure of a steel box girder.
[0026] 1—Steel box girder; 2—Connecting steel bars; 3—Stiffening plate; 4—Concrete foundation layer; 5—Reinforcement area; 6—Steel pipe piles. DETAILED DESCRIPTION
[0027] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0028] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0029] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.
[0030] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.
[0031] In addition, the term "plurality" shall mean two or more.
[0032] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0033] Example 1
[0034] See also Figure 1-2 , the present application provides a steel pipe pile structure of a steel box beam, comprising:
[0035] Steel box girder 1;
[0036] a concrete foundation layer 4, located below the surface layer;
[0037] A reinforcement area 5, located below the concrete foundation layer 4;
[0038] The steel pipe pile 6 has one end located below the steel box girder 1 and connected to the steel box girder 1 , and the other end inserted into the ground layer and passes through the concrete foundation layer 4 and the reinforcement area 5 .
[0039] In this embodiment, a plurality of stiffening plates 3 are further included, and the stiffening plates 3 are distributed around the steel pipe piles 6 on the surface layer.
[0040] In this embodiment, it also includes connecting steel bars 2, which are located below the stiffening plate 3. The connecting steel bars 2 are in an inverted "U" shape. The connecting steel bars 2 are connected to the lower surface of the stiffening plate 3, and both ends of the connecting steel bars 2 penetrate into the concrete foundation layer 4.
[0041] In this embodiment, the connecting steel bars 2 and the stiffening plates 3 are fixed by welding.
[0042] In this embodiment, hooks extending to the concrete foundation layer 4 are provided at both ends of the connecting steel bar 2 .
[0043] In this embodiment, the reinforcement area 5 is composed of brick slag or crushed stone, and the thickness of the reinforcement area 5 is 70-90 cm, more preferably 60 cm, which can stabilize the foundation soil.
[0044] In this embodiment, the thickness of the concrete foundation layer 4 is 10-30 cm, more preferably 20 cm, and is made of C20 concrete.
[0045] In this embodiment, the stiffening plates 3 are triangular stiffening plates, and there are four of them, which are evenly distributed around the steel pipe piles 6 .
[0046] On the other hand, the present application also provides a construction method of a steel pipe pile structure of a steel box beam, comprising the following steps:
[0047] S1, foundation pit excavation: small machinery cooperates with manual labor to excavate the soil within a certain range around the steel pipe piles, with a depth of 0.5-1.5m, and remove the silt and impurities on the original ground;
[0048] S2, replacement and reinforcement area: Brick slag or crushed stone are placed within 70-90cm from the original ground to stabilize the foundation soil;
[0049] S3, pouring concrete foundation layer and pre-embedded connecting steel bars: pour a layer of C20 concrete with a thickness of 10-30cm on the replaced brick slag or gravel, and pre-embed connecting steel bars matching the size of the stiffening plate near the steel pipe piles to ensure accurate positioning;
[0050] S4, welding stiffening plates: when the strength of the concrete foundation layer reaches the required level, four stiffening plates are evenly arranged around the steel pipe piles and welded tightly to the embedded connecting steel bars.
[0051] This method makes full use of the principle of caisson foundation. After the foundation strength meets the requirements, it can be quickly connected to the concrete foundation layer by welding stiffening plates, thereby preventing the steel pipe piles from continuing to sink, thereby ensuring the installation accuracy of the steel box girder.
[0052] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A steel pipe pile structure of a steel box beam, characterized in that: include: Steel box girder; A concrete base layer, located below the surface layer; a reinforcement zone located below the concrete foundation layer; A steel pipe pile, one end of which is located below the steel box girder and connected to the steel box girder, and the other end of which is inserted into the ground layer and passes through the concrete foundation layer and the reinforcement area; Also included are a plurality of stiffening plates, which are distributed around the steel pipe piles of the surface layer; It also includes connecting steel bars, which are located below the stiffening plate, are in an inverted "U" shape, are connected to the lower surface of the stiffening plate, and have two ends of the connecting steel bars extending deep into the concrete foundation layer; The connecting steel bars are fixed to the stiffening plates by welding; Both ends of the connecting steel bars are provided with hooks extending to the concrete foundation layer; The reinforcement area is composed of brick slag or crushed stone, and the thickness of the reinforcement area is 70-90 cm; The thickness of the concrete foundation layer is 10-30 cm and is made of C20 concrete; The stiffening plates are triangular stiffening plates, and there are four of them, which are evenly distributed around the steel pipe piles.
2. A construction method for a steel pipe pile structure applied to a steel box girder as claimed in claim 1, comprising the following steps: S1, foundation pit excavation: small machinery cooperates with manual labor to excavate the soil within a certain range around the steel pipe piles, with a depth of 0.5-1.5m, and remove the silt and impurities on the original ground; S2, replacement and reinforcement area: Brick slag or crushed stone are placed within 70-90cm from the original ground to stabilize the foundation soil; S3, pouring concrete foundation layer and pre-embedded connecting steel bars: pour a layer of C20 concrete with a thickness of 10-30cm on the replaced brick slag or gravel, and pre-embed connecting steel bars matching the size of the stiffening plate near the steel pipe piles to ensure accurate positioning; S4, welding stiffening plates: when the strength of the concrete foundation layer reaches the required level, four stiffening plates are evenly arranged around the steel pipe piles and welded tightly to the embedded connecting steel bars.
Citation Information
Patent Citations
Underwater foundation spreading supporting structure for temporary steel trestle
CN105569043A
Concrete filled steel tube column base joint and construction method thereof
CN109457868A
Photovoltaic power generation is reinforced concrete reinforcement steel pipe pile foundation for support
CN206887984U