Boiler gas intake system and intake process for semi-coke tail gas and calcium carbide tail gas

Through the combination of liquid sealing structure and water sealing ammonia water tank, the problems of resistance and burner unevenness caused by impurities in ylcon exhaust gas and calcium carbide exhaust gas are solved, and more efficient impurity treatment and burner uniformity are achieved, and more efficient impurity treatment and burner uniformity are achieved. The boiler maintenance cycle is completed.

CN112815351BActive Publication Date: 2024-11-26SHENMU CALCIUM CALCIUM GRP ENERGY DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110184067.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-02-10
Publication Date
2024-11-26
Estimated Expiration
2041-02-10

AI Technical Summary

Technical Problem

Lancharcoal exhaust gas and calcium carbide exhaust gas contain impurities such as moisture, coal tar and ammonia, which leads to large resistance to the conveying pipeline, complex and uneven ignition device of the burner, and easy to block the nozzle, which shortens the boiler maintenance cycle and increases the maintenance workload.

Method used

Use liquid sealing structure and water sealing ammonia tank to collect and clean impurities, reduce the resistance of the conveying pipeline, and treat impurities through the mixed gas ammonia water discharge pipe and drain pipe, and set up multiple burners and flow regulating valves to evenly adjust the burner flow, improving Burner tip is designed to reduce clogging rates.

Benefits of technology

It effectively reduces the resistance of the conveying pipeline, simplifies the burner ignition device, extends the boiler maintenance cycle, improves the uniformity and reliability of the burner, and reduces the maintenance workload.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112815351B_ABST
    Figure CN112815351B_ABST
Patent Text Reader

Abstract

The present invention proposes a boiler gas intake system and intake process for blue coke tail gas and calcium carbide tail gas, and belongs to the field of boiler combustion system and process technology. The system includes a calcium carbide tail gas intake pipe, a blue coke tail gas intake pipe, a first mixed gas intake pipe, a second mixed gas intake pipe, a liquid seal structure, a burner group intake pipe, and a burner group. The calcium carbide tail gas intake pipe and the blue coke tail gas intake pipe are both connected to the first mixed gas intake pipe, the burner group is connected to the burner group intake pipe, and the burner group intake pipe is connected to the second mixed gas intake pipe. The present invention is used for a boiler gas intake system for blue coke tail gas and calcium carbide tail gas, which ensures that the mixed gas can be cleaned and the transportation resistance of the transportation pipeline is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of boiler combustion systems and processes, and specifically relates to a boiler gas intake system and an intake process for blue coke tail gas and calcium carbide tail gas. Background Art

[0002] At present, common boilers generally only burn a single exhaust gas such as lignite tail gas or calcium carbide tail gas, and then transport the single lignite tail gas or calcium carbide tail gas to the boiler burner through a booster fan for combustion. For factories that produce both calcium carbide and lignite, two gases, calcium carbide tail gas and lignite tail gas, will be produced. Lignite tail gas and calcium carbide tail gas contain a large amount of combustible gas and have a very high calorific value. If lignite tail gas and calcium carbide tail gas are directly disposed of, it will waste energy and increase the processing cost. Therefore, the general practice is to mix lignite tail gas and calcium carbide tail gas and send them into a boiler or other combustion equipment for combustion. However, lignite tail gas and calcium carbide tail gas contain a lot of impurities such as moisture, coal tar, ammonia and water vapor, and there are the following problems during combustion:

[0003] 1. There are many impurities such as moisture, coal tar and ammonia in the tail gas of lignite and calcium carbide, which makes the tail gas of lignite and calcium carbide more viscous after mixing, and it is easy to adhere to the wall of the conveying pipeline, resulting in large resistance of the conveying pipeline.

[0004] 2. Existing gas burners need to be equipped with a separate ignition device when igniting. The ignition system is cumbersome, and each burner cannot output power individually and evenly, resulting in uneven load distribution in the boiler and limiting the minimum usage of gas.

[0005] 3. The nozzles on the existing gas burner gun head are arranged around the circumference of the gas nozzle, and the nozzle aperture is small. The mixed gas of blue coke tail gas and calcium carbide tail gas can easily block the nozzle, resulting in a shortened boiler maintenance cycle and an increased workload for maintenance personnel. Summary of the invention

[0006] Aiming at the problem that the existing semi-coke tail gas and calcium carbide tail gas contain a lot of impurities such as moisture, coal tar and ammonia, which leads to large resistance in the transportation pipeline, the present invention proposes a boiler gas intake system and intake process for semi-coke tail gas and calcium carbide tail gas, which adds a liquid seal structure to the boiler gas intake system to collect impurities such as moisture, coal tar and ammonia, thereby reducing the resistance of the transportation pipeline. The specific technical scheme is as follows:

[0007] A boiler gas intake system for semi-coke tail gas and calcium carbide tail gas, comprising a calcium carbide tail gas intake pipe, a semi-coke tail gas intake pipe, a first mixed gas intake pipe, a second mixed gas intake pipe, a liquid seal structure, a burner group intake pipe and a burner group, wherein the calcium carbide tail gas intake pipe and the semi-coke tail gas intake pipe are both connected to the first mixed gas intake pipe, the burner group is connected to the burner group intake pipe, and the burner group intake pipe is connected to the second mixed gas intake pipe;

[0008] The liquid-sealing structure comprises a liquid-sealing box, a liquid-sealing structure air inlet pipe, a liquid-sealing structure air outlet pipe, a liquid-sealing structure overflow pipe and a liquid-sealing structure liquid injection pipe. The liquid-sealing structure air inlet pipe, the liquid-sealing structure air outlet pipe, the liquid-sealing structure overflow pipe and the liquid-sealing structure liquid injection pipe are all connected to the inner cavity of the liquid-sealing box. The liquid-sealing structure air inlet pipe is connected to the first mixed gas inlet pipe, and the liquid-sealing structure air outlet pipe is connected to the second mixed gas inlet pipe. The inner cavity of the liquid-sealing box contains liquid-sealing liquid. The liquid-sealing structure air inlet pipe extends below the liquid level of the liquid-sealing liquid, the liquid-sealing structure air outlet pipe is arranged above the liquid level of the liquid-sealing liquid, and the liquid-sealing structure overflow pipe is arranged between the liquid-sealing structure air inlet pipe and the liquid-sealing structure air outlet pipe.

[0009] It is further defined that the liquid sealing structure also includes a liquid sealing structure discharge pipe, the liquid sealing structure discharge pipe is communicated with the inner cavity of the liquid sealing box, and the liquid sealing structure discharge pipe is arranged at the bottom of the liquid sealing box.

[0010] The above-mentioned boiler gas intake system for lignite tail gas and calcium carbide tail gas also includes a water-sealed ammonia water tank, and the liquid-sealed structure overflow pipe and the liquid-sealed structure discharge pipe are both connected to the water-sealed ammonia water tank.

[0011] The above-mentioned boiler gas intake system for lignite exhaust gas and calcium carbide exhaust gas also includes a mixed gas ammonia water discharge pipe, which is connected to the second mixed gas intake pipe, and the mixed gas ammonia water discharge pipe is connected to the lower end of the second mixed gas intake pipe, and the mixed gas ammonia water discharge pipe is connected to the water-sealed ammonia water pool, and the mixed gas ammonia water discharge pipe is arranged between the liquid seal structure and the burner group intake pipe.

[0012] It is further defined that a mixed gas regulating valve is provided on the second mixed gas intake pipe, and the mixed gas regulating valve is provided between the burner group intake pipe and the mixed gas ammonia discharge pipe.

[0013] The above-mentioned boiler gas intake system for lignite tail gas and calcium carbide tail gas also includes a mixed gas discharge pipe and a discharge pipe. The burner group is connected to the mixed gas discharge pipe, and the mixed gas discharge pipe and the second mixed gas intake pipe are both connected to the discharge pipe.

[0014] The above-mentioned boiler gas intake system for lignite tail gas and calcium carbide tail gas also includes a gas cabinet, and the calcium carbide tail gas intake pipe and the lignite tail gas intake pipe are both connected to the gas cabinet, and the first mixed gas intake pipe is connected to the gas cabinet.

[0015] It is further defined that the burner group includes a plurality of burners, and the plurality of burners are all connected to the burner group air inlet pipe, and the plurality of burners are also all connected to the mixed gas discharge pipe, and a burner gun head is provided on the burner, and a plurality of side jet holes and a central jet hole are provided on the burner gun head, and the center point of the central jet hole coincides with the center line axis of the burner gun head, and the side jet holes are arranged on the outside of the central jet hole along the radial direction of the central jet hole.

[0016] The boiler gas intake process for semi-coke tail gas and calcium carbide tail gas comprises the following steps: semi-coke tail gas and calcium carbide tail gas enter the gas cabinet respectively, and are pressure balanced, cooled and mixed in the gas cabinet to form a mixed gas; the mixed gas is discharged from the gas cabinet and enters the first mixed gas intake pipe, and enters the liquid sealing liquid in the liquid sealing box through the first mixed gas intake pipe, and the coal tar, moisture and ammonia in the mixed gas are washed away in the liquid sealing liquid, and then the mixed gas is discharged from the liquid sealing box and enters the second mixed gas intake pipe; The sealing liquid is in a dynamic equilibrium state, and the excess sealing liquid flows along the overflow pipe of the liquid sealing structure to the water-sealed ammonia water pool. The sealing liquid containing coal tar and ammonia deposited at the bottom of the liquid sealing box flows along the discharge pipe of the liquid sealing structure to the water-sealed ammonia water pool; the ammonia water in the mixed gas in the second mixed gas inlet pipe is deposited at the bottom of the second mixed gas inlet pipe and flows along the mixed gas ammonia water discharge pipe to the water-sealed ammonia water pool; the mixed gas flows to the burner group inlet pipe through the mixed gas regulating valve, and enters the burner group through the burner group inlet pipe for combustion.

[0017] It is further defined that the step also includes: when the burner group fails, the mixer in the burner group discharges the mixed gas into the discharge pipe along the mixed gas discharge pipe.

[0018] Compared with the prior art, the present invention has the following beneficial effects:

[0019] 1. The present invention is used for a boiler gas intake system for semi-coke tail gas and calcium carbide tail gas, which comprises a calcium carbide tail gas intake pipe, a semi-coke tail gas intake pipe, a first mixed gas intake pipe, a second mixed gas intake pipe, a liquid seal structure, a burner group intake pipe, and a burner group. The calcium carbide tail gas intake pipe and the semi-coke tail gas intake pipe are both connected to the first mixed gas intake pipe, the burner group is connected to the burner group intake pipe, the burner group intake pipe is connected to the second mixed gas intake pipe, the liquid seal structure comprises a liquid seal box, a liquid seal structure intake pipe, a liquid seal structure outlet pipe, and a liquid seal structure. The liquid-sealed structure overflow pipe and the liquid-sealed structure injection pipe are all connected with the inner cavity of the liquid-sealed box. The liquid-sealed structure air inlet pipe is connected with the first mixed gas inlet pipe, and the liquid-sealed structure air outlet pipe is connected with the second mixed gas inlet pipe. The inner cavity of the liquid-sealed box is filled with liquid-sealing liquid. The liquid-sealed structure air inlet pipe extends below the liquid level of the liquid-sealing liquid. The liquid-sealed structure air outlet pipe is arranged above the liquid level of the liquid-sealing liquid. The liquid-sealed structure overflow pipe is arranged between the liquid-sealed structure air inlet pipe and the liquid-sealed structure air outlet pipe. The mixed gas of the semi-coke tail gas and the calcium carbide tail gas is cleaned in the liquid sealing liquid in the liquid sealing box, and impurities such as coal tar, ammonia, water and water vapor in the mixed gas are cleaned. The cleaned coal tar is deposited at the bottom of the liquid sealing box, and the cleaned mixed gas is discharged from the liquid sealing box. The overflow pipe of the liquid sealing structure can ensure that the liquid level of the liquid sealing liquid is always below the liquid sealing structure inlet pipe and above the liquid sealing structure outlet pipe, and the liquid is continuously introduced into the liquid sealing box through the liquid sealing structure injection pipe. The liquid is continuously discharged through the overflow pipe of the liquid sealing structure to ensure that the liquid sealing liquid in the liquid sealing box is always in a dynamic equilibrium state, ensuring that the mixed gas can be cleaned and the transportation resistance of the conveying pipeline is reduced. Another function of the liquid sealing structure is that when the burner or boiler fails, the mixed gas entering the liquid sealing box from the liquid sealing structure outlet pipe cannot flow out from the liquid sealing structure inlet pipe, which plays the role of closing the pipeline, and the sealing effect will not cause leakage, which is much better than the sealing effect of the valve.

[0020] 2. The boiler gas intake system for lignite tail gas and calcium carbide tail gas of the present invention also includes a water-sealed ammonia water tank and a liquid-sealed structure discharge pipe. The liquid-sealed liquid containing coal tar and ammonia water deposited at the bottom of the liquid-sealed box is promptly discharged into the water-sealed ammonia water tank through the liquid-sealed structure discharge pipe, further ensuring that the mixed gas can be cleaned.

[0021] 3. The boiler gas intake system for lignite tail gas and calcium carbide tail gas of the present invention also includes a mixed gas ammonia water discharge pipe, through which the ammonia water at the bottom of the second mixed gas intake pipe is promptly discharged to the water-sealed ammonia water pool, thereby reducing the flow resistance of the mixed gas in the second mixed gas intake pipe.

[0022] 4. The boiler gas intake system for lignite tail gas and calcium carbide tail gas of the present invention also includes a mixed gas ammonia discharge pipe, a mixed gas vent pipe and a vent pipe. The burner group is connected to the mixed gas vent pipe, and the mixed gas vent pipe and the second mixed gas intake pipe are both connected to the vent pipe. When the boiler or burner fails or is under maintenance, the mixed gas in the burner group and the second mixed gas intake pipe is discharged through the vent pipe to ensure the safety of maintenance personnel.

[0023] 5. The boiler gas intake system for lignite tail gas and calcium carbide tail gas of the present invention also includes a gas holder, which is connected to the cooling tower. The gas holder can balance the pressure of the lignite tail gas intake pipe and the calcium carbide tail gas intake pipe, and mix and cool the lignite tail gas and the calcium carbide tail gas.

[0024] 6. The burner group of the present invention includes multiple burners, and a burner group flow regulating valve is provided on the burner group air inlet pipe. The burner group flow regulating valve can be used to synchronously and evenly adjust the flow of each burner, so that the load distribution in the boiler is uniform, and the minimum usage of gas is not limited.

[0025] 7. The burner gun head of the present invention is provided with a plurality of side jet holes and a central jet hole, the center point of the central jet hole coincides with the centerline axis of the burner gun head, the side jet holes are arranged on the outside of the central jet hole along the radial direction of the central jet hole, the aperture of the central jet hole is larger than the aperture of the side jet hole, larger impurities can be ejected through the central jet hole, and the blockage rate of the side jet holes is effectively reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a connection schematic diagram of the boiler gas intake system for blue coke tail gas and calcium carbide tail gas of the present invention;

[0027] Figure 2 It is a connection diagram of the gas burner group and the gas ignition station group;

[0028] Figure 3 is a schematic diagram of the structure of a gas burner;

[0029] Figure 4 for Figure 3 Side view of

[0030] Among them, 1-calcium carbide tail gas inlet pipe, 2-lignite tail gas inlet pipe, 3-gas cabinet, 41-first mixed gas inlet pipe, 42-second mixed gas inlet pipe, 5-liquid seal structure, 51-liquid seal structure inlet pipe, 52-liquid seal structure outlet pipe, 53-liquid seal structure overflow pipe, 54-liquid seal structure discharge pipe, 55-liquid seal structure injection pipe, 6-water seal ammonia tank, 7-mixed gas ammonia discharge pipe, 8-vent pipe, 9-mixed gas regulating valve, 10-burner group inlet pipe, 11-burner group, 111-burner, 112-burner gun head, 1121-center jet hole, 1122-side jet hole, 12-mixed gas vent pipe. DETAILED DESCRIPTION

[0031] The technical solution of the invention is further explained below in conjunction with the accompanying drawings and embodiments, but the present invention is not limited to the implementation modes described below.

[0032] The present invention is used for a boiler gas intake system for semi-coke tail gas and calcium carbide tail gas, comprising a calcium carbide tail gas intake pipe 1, a semi-coke tail gas intake pipe 2, a first mixed gas intake pipe 41, a second mixed gas intake pipe 42, a liquid seal structure 5, a burner group intake pipe 10 and a burner group 11, wherein the calcium carbide tail gas intake pipe 1 and the semi-coke tail gas intake pipe 2 are both connected to the first mixed gas intake pipe 41, the burner group 11 is connected to the burner group intake pipe 10, and the burner group intake pipe 10 is connected to the second mixed gas intake pipe 42; the liquid seal structure 5 comprises a liquid seal box, a liquid seal structure intake pipe 51, a liquid seal structure outlet pipe 52, a liquid seal structure overflow pipe 53, a liquid seal structure outlet pipe 54, a liquid seal structure outlet pipe 55, a liquid seal structure outlet pipe 56, a liquid seal structure outlet pipe 57, a liquid seal structure outlet pipe 58, a liquid seal structure outlet pipe 59, a liquid seal structure outlet pipe 60, a liquid seal structure outlet pipe 61, a liquid seal structure outlet pipe 62, a liquid seal structure outlet pipe 63, a liquid seal structure outlet pipe 64, a liquid seal structure outlet pipe 65, a liquid seal structure outlet pipe 66, a liquid seal structure outlet pipe 67, a liquid seal structure outlet pipe 68, a liquid seal structure outlet pipe 69, a liquid seal structure outlet pipe 70, a liquid seal structure outlet pipe 71, a liquid seal structure outlet pipe 72, a liquid seal structure outlet pipe 73, a liquid seal structure outlet pipe 74, a liquid seal structure outlet pipe 75, a liquid seal structure outlet pipe 76, a liquid seal structure outlet pipe 77, a liquid seal structure outlet pipe 78, a liquid seal structure outlet pipe 79, a liquid seal structure outlet pipe 80, a liquid seal structure outlet pipe 81, a liquid seal structure outlet pipe 82, a liquid The flow pipe 53 and the liquid-sealing structure injection pipe 55, the liquid-sealing structure air inlet pipe 51, the liquid-sealing structure air outlet pipe 52, the liquid-sealing structure overflow pipe 53 and the liquid-sealing structure injection pipe 55 are all connected to the inner cavity of the liquid-sealing box. The liquid-sealing structure air inlet pipe 51 is connected to the first mixed gas air inlet pipe 41, and the liquid-sealing structure air outlet pipe 52 is connected to the second mixed gas air inlet pipe 42. The inner cavity of the liquid-sealing box contains liquid sealing liquid. The liquid-sealing structure air inlet pipe 51 extends below the liquid level of the liquid sealing liquid. The liquid-sealing structure air outlet pipe 52 is arranged above the liquid level of the liquid sealing liquid. The liquid-sealing structure overflow pipe 53 is arranged between the liquid-sealing structure air inlet pipe 51 and the liquid-sealing structure air outlet pipe 52. The liquid-sealing structure 5 also includes a liquid-sealing structure discharge pipe 55, a liquid-sealing structure discharge pipe 54 is connected to the inner cavity of the liquid-sealing box, and the liquid-sealing structure discharge pipe 54 is arranged at the bottom of the liquid-sealing box.

[0033] The boiler gas intake system for the semi-coke tail gas and calcium carbide tail gas also includes a water-sealed ammonia water tank 6 , and the liquid-sealed structure overflow pipe 53 and the liquid-sealed structure discharge pipe 54 are both connected to the water-sealed ammonia water tank 6 .

[0034] The boiler gas intake system for blue coke tail gas and calcium carbide tail gas also includes a mixed gas ammonia water discharge pipe 7, which is connected to the second mixed gas intake pipe 42, and the mixed gas ammonia water discharge pipe 7 is connected to the lower end of the second mixed gas intake pipe 42, and the mixed gas ammonia water discharge pipe 7 is connected to the water-sealed ammonia water tank 6, and the mixed gas ammonia water discharge pipe 7 is arranged between the liquid seal structure 5 and the burner group intake pipe 10. A mixed gas regulating valve 9 is arranged on the second mixed gas intake pipe 42, and the mixed gas regulating valve 9 is arranged between the burner group intake pipe 10 and the mixed gas ammonia water discharge pipe 7.

[0035] The boiler gas intake system for semi-coke tail gas and calcium carbide tail gas also includes a mixed gas discharge pipe 12 and a discharge pipe 8, the burner group 11 is connected to the mixed gas discharge pipe 12, and the mixed gas discharge pipe 12 and the second mixed gas intake pipe 42 are both connected to the discharge pipe 8. The boiler gas intake system for semi-coke tail gas and calcium carbide tail gas also includes a gas tank 3, the calcium carbide tail gas intake pipe 1 and the semi-coke tail gas intake pipe 2 are both connected to the gas tank 3, and the first mixed gas intake pipe 41 is connected to the gas tank 3. The burner group 11 includes multiple burners 111, and the multiple burners 111 are all connected to the burner group air inlet pipe 10, and the multiple burners 111 are also connected to the mixed gas diffusion pipe 12. The burner 111 is provided with a burner gun head 112, and the burner gun head 112 is provided with multiple side jet holes 1122 and a central jet hole 1121. The center point of the central jet hole 1121 coincides with the centerline axis of the burner gun head 112, and the side jet holes 1122 are arranged on the outside of the central jet hole 1121 along the radial direction of the central jet hole 1121.

[0036] The present invention is used for a boiler gas intake process for blue coke tail gas and calcium carbide tail gas, and comprises the following steps: blue coke tail gas and calcium carbide tail gas enter a gas tank 3 respectively, and are pressure balanced, cooled and mixed in the gas tank 3 to form a mixed gas; the mixed gas is discharged from the gas tank 3 and enters a first mixed gas intake pipe 41, and enters a liquid sealing liquid in a liquid sealing box through the first mixed gas intake pipe 41, and coal tar, moisture and ammonia in the mixed gas are washed away in the liquid sealing liquid, and then the mixed gas is discharged from the liquid sealing box and enters a second mixed gas intake pipe 42; the liquid sealing liquid in the liquid sealing box It is in a dynamic equilibrium state, and the excess liquid sealing liquid flows along the liquid sealing structure overflow pipe 53 to the water sealing ammonia water pool 6, and the liquid sealing liquid containing coal tar and ammonia deposited at the bottom of the liquid sealing box flows along the liquid sealing structure discharge pipe 54 to the water sealing ammonia water pool 6; the ammonia water in the mixed gas in the second mixed gas inlet pipe 42 is deposited at the bottom of the second mixed gas inlet pipe 42 and flows along the mixed gas ammonia water discharge pipe 7 to the water sealing ammonia water pool 6; the mixed gas flows to the burner group inlet pipe 10 through the mixed gas regulating valve 9, and enters the burner group 11 through the burner group inlet pipe 10 for combustion.

[0037] The above steps also include: when the burner group fails, the mixer in the burner group 11 discharges the mixed gas along the mixed gas discharge pipe 12 into the second mixed gas intake pipe 42 .

[0038] Example 1

[0039] See also Figure 1 The present invention is used for a boiler gas intake system for semi-coke tail gas and calcium carbide tail gas, which comprises a calcium carbide tail gas intake pipe 1, a semi-coke tail gas intake pipe 2, a gas cabinet 3, a first mixed gas intake pipe 41, a second mixed gas intake pipe 42, a liquid seal structure 5, a water-sealed ammonia water tank 6, a mixed gas ammonia water discharge pipe 7, a burner group intake pipe 10, a burner group 11 and a mixed gas discharge pipe 12; the liquid seal structure 5 comprises a liquid seal box, a liquid seal structure intake pipe 51, a liquid seal structure outlet pipe 52, a liquid seal structure overflow pipe 53, a liquid seal structure injection pipe 55 and a liquid seal structure discharge pipe 54; the calcium carbide tail gas intake pipe 1 and The semi-coke tail gas inlet pipe 2 is connected to the air inlet of the gas tank 3, and the gas tank 3 is connected to a cooling tower, which is used to cool the mixed gas in the gas tank 3. The first mixed gas inlet pipe 41 is connected to the gas outlet of the gas tank 3, and the liquid seal structure inlet pipe 51 is connected to the first mixed gas inlet pipe 41. The liquid seal structure inlet pipe 51 is connected to the inner cavity of the liquid seal box. The liquid seal box contains a liquid seal liquid for liquid sealing, and the liquid seal liquid is water. The outlet of the liquid seal structure inlet pipe 51 extends below the liquid level of the liquid seal liquid. The liquid seal structure outlet pipe 52 is connected to the inner cavity of the liquid seal box. The gas port is arranged above the liquid level of the liquid sealing liquid, the liquid sealing structure gas outlet pipe 52 is communicated with the second mixed gas inlet pipe 42, the liquid sealing structure overflow pipe 53 is communicated with the inner cavity of the liquid sealing box, the outlet of the liquid sealing structure overflow pipe 53 is arranged between the gas outlet of the liquid sealing structure inlet pipe 51 and the gas inlet of the liquid sealing structure gas outlet pipe 52, the liquid sealing structure overflow pipe 53 is communicated with the water seal ammonia water tank 6, the liquid sealing structure injection pipe 55 is communicated with the inner cavity of the liquid sealing box, the liquid sealing liquid is passed into the liquid sealing box through the liquid sealing structure injection pipe 55, and a liquid sealing structure discharge pipe 54 is arranged at the bottom of the liquid sealing box, and the liquid sealing structure discharge pipe 54 is connected to the water seal. The second mixed gas inlet pipe 42 is connected to the ammonia water tank 6; a mixed gas ammonia water discharge pipe 7, a mixed gas regulating valve 9 and a mixed gas release pipe 12 are arranged in sequence from front to back, the second mixed gas inlet pipe 42 is connected to the water-sealed ammonia water tank 6 through the mixed gas ammonia water discharge pipe 7, and the air inlet of the mixed gas ammonia water discharge pipe 7 is connected to the lower end of the second mixed gas inlet pipe 42; the mixed gas regulating valve 8 is installed on the second mixed gas inlet pipe 42, and the flow rate of the second mixed gas inlet pipe 42 is adjusted by the mixed gas regulating valve 9, and the second mixed gas inlet pipe 42 is connected to the burner group inlet pipe 10; Figure 2-Figure 4, 8 burners 111 are arranged on the burner group, and the 8 burners 111 are all connected to the burner group air inlet pipe 10, and the 8 burners 111 are all connected to the second mixed gas inlet pipe 42 through the mixed gas discharge pipe 12, the mixed gas discharge pipe 12 is connected to the discharge pipe 8, and the discharge pipe 8 is also connected to the second mixed gas inlet pipe 42; a burner gun head 112 is arranged on the burner 111, and a central jet hole 1121 and 6 side jet holes 1122 are arranged on the burner gun head 112, the diameter of the central jet hole 1121 is 120 mm, the diameter of the side jet hole 1122 is 25 mm, the center of the central jet hole 1121 coincides with the centerline axis of the burner gun head 112, the 6 side jet holes 1122 are arranged on the outside of the central jet hole 1121 along the radial direction of the central jet hole 1121, and the 6 side jet holes 1122 are evenly distributed along the radial direction of the central jet hole 1121.

[0040] The mixed gas of the semi-coke tail gas and the calcium carbide tail gas is cleaned in the liquid sealing liquid in the liquid sealing box, and impurities such as coal tar, ammonia, water and water vapor in the mixed gas are cleaned. The cleaned coal tar is deposited at the bottom of the liquid sealing box, and the cleaned mixed gas is discharged from the liquid sealing box. The overflow pipe 53 of the liquid sealing structure can ensure that the liquid level of the liquid sealing liquid is always below the liquid sealing structure air inlet pipe 51 and above the liquid sealing structure air outlet pipe 52, and the liquid is continuously introduced into the liquid sealing box through the liquid sealing structure injection pipe 55. The liquid is continuously discharged through the overflow pipe 53 of the liquid sealing structure to ensure that the liquid sealing liquid in the liquid sealing box is always in a dynamic equilibrium state, ensuring that the mixed gas can be cleaned and the transportation resistance of the transportation pipeline is reduced. Another function of the liquid sealing structure 5 is that when the burner 111 or the boiler fails, the mixed gas entering the liquid sealing box from the liquid sealing structure air outlet pipe 52 cannot flow out from the liquid sealing structure air inlet pipe 51, which plays the role of closing the pipeline, and the sealing effect will not have the situation of air leakage, which is much better than the sealing effect of the valve.

[0041] Example 2

[0042] The boiler gas intake system for semi-coke tail gas and calcium carbide tail gas in this embodiment 1 realizes the boiler gas intake process for semi-coke tail gas and calcium carbide tail gas, and the steps are as follows: the semi-coke tail gas and calcium carbide tail gas enter the gas tank 3 respectively, and are pressure balanced, cooled and mixed in the gas tank 3 to form a mixed gas; after the mixed gas is discharged from the gas tank 3, it enters the first mixed gas intake pipe 41, enters the liquid sealing liquid in the liquid sealing box through the first mixed gas intake pipe 41, and washes the mixed gas in the liquid sealing liquid. The coal tar, moisture, ammonia and other impurities in the liquid seal box are removed, and then the mixed gas is discharged from the liquid seal box and enters the second mixed gas inlet pipe 42; the liquid seal liquid in the liquid seal box is always in a dynamic equilibrium state when the liquid inlet is continuously fed and the liquid seal structure overflow pipe 53 is continuously discharged, and the excess liquid seal liquid flows along the liquid seal structure overflow pipe 53 to the water seal ammonia pool 6, and the liquid seal liquid containing coal tar and ammonia deposited at the bottom of the liquid seal box flows along the liquid seal structure discharge pipe 54 to the water seal ammonia pool 6, and the second mixed gas is discharged from the second mixed gas inlet pipe 42; the liquid seal liquid in the liquid seal box is ... second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas inlet pipe 42; the second mixed gas is discharged from the second mixed gas The ammonia water in the mixed gas in the air intake pipe 42 is deposited at the bottom of the second mixed gas inlet pipe 42 and flows along the mixed gas ammonia water discharge pipe 7 to the water-sealed ammonia water pool 6, and the liquid sealing liquid and the liquid sealing liquid containing coal tar and ammonia and the ammonia water are recovered through the water-sealed ammonia water pool 6 to prevent the liquid sealing liquid and the ammonia water from turbulently polluting the environment; the mixed gas in the second mixed gas inlet pipe 42 flows to the burner group inlet pipe 10 through the mixed gas regulating valve 9, and the mixed gas in the burner group inlet pipe 10 enters the burner group 11 through the burner group flow regulating valve, that is, enters each burner 111, and is burned in the burner 111; when the burner 111 or the boiler fails or needs to be repaired, the mixer in the burner 111 enters the vent pipe 8 along the mixed gas vent pipe 12, and the mixed gas in the second mixed gas inlet pipe 42 enters the vent pipe 8, and the mixed gas is emptied through the vent pipe 8 to prevent a large amount of mixed gas from accumulating in the burner 111 and causing physical harm to the maintenance personnel.

[0043] The liquid sealing liquid of the present invention is not limited to water, and any liquid that can recover coal tar, ammonia and water vapor can be used; the number of burners 111 is not limited to the above description, and it can be increased or decreased according to the actual situation of the boiler; the diameter of the central jet hole 1121 and the diameter of the side jet hole 1122 on the burner gun head 112 can be opened according to actual conditions and are not limited to the above-mentioned limited values.

Claims

1. The gas intake process of the boiler gas intake system for blue coke tail gas and calcium carbide tail gas is characterized in that: The boiler gas intake system for semi-coke tail gas and calcium carbide tail gas comprises a calcium carbide tail gas intake pipe (1), a semi-coke tail gas intake pipe (2), a first mixed gas intake pipe (41), a second mixed gas intake pipe (42), a liquid seal structure (5), a burner group intake pipe (10) and a burner group (11); the calcium carbide tail gas intake pipe (1) and the semi-coke tail gas intake pipe (2) are both in communication with the first mixed gas intake pipe (41); the burner group (11) is in communication with the burner group intake pipe (10); and the burner group intake pipe (10) is in communication with the second mixed gas intake pipe (42); The liquid-sealing structure (5) comprises a liquid-sealing box, a liquid-sealing structure air inlet pipe (51), a liquid-sealing structure air outlet pipe (52), a liquid-sealing structure overflow pipe (53) and a liquid-sealing structure liquid injection pipe (55); the liquid-sealing structure air inlet pipe (51), the liquid-sealing structure air outlet pipe (52), the liquid-sealing structure overflow pipe (53) and the liquid-sealing structure liquid injection pipe (55) are all in communication with the inner cavity of the liquid-sealing box; the liquid-sealing structure air inlet pipe (51) is in communication with the first mixed gas inlet pipe (41); the liquid-sealing structure air outlet pipe (52) is in communication with the second mixed gas inlet pipe (42); the inner cavity of the liquid-sealing box contains liquid-sealing liquid; the liquid-sealing structure air inlet pipe (51) extends below the liquid level of the liquid-sealing liquid; the liquid-sealing structure air outlet pipe (52) is arranged above the liquid level of the liquid-sealing liquid; and the liquid-sealing structure overflow pipe (53) is arranged between the liquid-sealing structure air inlet pipe (51) and the liquid-sealing structure air outlet pipe (52); The liquid sealing structure (5) further comprises a liquid sealing structure discharge pipe (54), the liquid sealing structure discharge pipe (54) being in communication with the inner cavity of the liquid sealing box, and the liquid sealing structure discharge pipe (54) being arranged at the bottom of the liquid sealing box; The boiler gas intake system for blue coke tail gas and calcium carbide tail gas also includes a water-sealed ammonia water pool (6), and the liquid-sealed structure overflow pipe (53) and the liquid-sealed structure discharge pipe (54) are both in communication with the water-sealed ammonia water pool (6); The gas intake process of the boiler gas intake system for semi-coke tail gas and calcium carbide tail gas comprises the following steps: the semi-coke tail gas and calcium carbide tail gas enter the gas holder (3) respectively, are pressure balanced, cooled and mixed in the gas holder (3) to form a mixed gas, the mixed gas is discharged from the gas holder (3) and enters the first mixed gas intake pipe (41), enters the liquid sealing liquid in the liquid sealing box through the first mixed gas intake pipe (41), and cleans the coal tar, moisture and ammonia in the mixed gas in the liquid sealing liquid, and then the mixed gas is discharged from the liquid sealing box and enters the second mixed gas intake pipe (42); the liquid sealing liquid in the liquid sealing box is in a dynamic state; In a balanced state, excess sealing liquid flows along the liquid sealing structure overflow pipe (53) into the water sealing ammonia water pool (6), and the sealing liquid containing coal tar and ammonia gas deposited at the bottom of the liquid sealing box flows along the liquid sealing structure discharge pipe (54) into the water sealing ammonia water pool (6); ammonia water in the mixed gas in the second mixed gas inlet pipe (42) is deposited at the bottom of the second mixed gas inlet pipe (42) and flows along the mixed gas ammonia water discharge pipe (7) into the water sealing ammonia water pool (6); the mixed gas flows through the mixed gas regulating valve (9) into the burner group inlet pipe (10), and enters the burner group (11) through the burner group inlet pipe (10) for combustion.

2. The gas intake process for the boiler gas intake system for blue coke tail gas and calcium carbide tail gas according to claim 1, characterized in that: The boiler gas intake system for semi-coke tail gas and calcium carbide tail gas further comprises a mixed gas ammonia water discharge pipe (7), the mixed gas ammonia water discharge pipe (7) is in communication with a second mixed gas intake pipe (42), and the mixed gas ammonia water discharge pipe (7) is connected to the lower end of the second mixed gas intake pipe (42), the mixed gas ammonia water discharge pipe (7) is in communication with a water-sealed ammonia water pool (6), and the mixed gas ammonia water discharge pipe (7) is arranged between the liquid seal structure (5) and the burner group intake pipe (10).

3. The gas intake process for the boiler gas intake system for blue coke tail gas and calcium carbide tail gas as claimed in claim 2, characterized in that: The second mixed gas intake pipe (42) is provided with a mixed gas regulating valve (9), and the mixed gas regulating valve (9) is arranged between the burner group intake pipe (10) and the mixed gas and ammonia discharge pipe (7).

4. The gas intake process for the boiler gas intake system for blue coke tail gas and calcium carbide tail gas according to any one of claims 1 to 3, characterized in that: The boiler gas intake system for blue coke tail gas and calcium carbide tail gas also includes a mixed gas discharge pipe (12) and a discharge pipe (8), the burner group (11) is connected to the mixed gas discharge pipe (12), and the mixed gas discharge pipe (12) and the second mixed gas intake pipe (42) are both connected to the discharge pipe (8).

5. The gas intake process for the boiler gas intake system for blue coke tail gas and calcium carbide tail gas as claimed in claim 4, characterized in that: The boiler gas intake system for semi-coke tail gas and calcium carbide tail gas further comprises a gas cabinet (3), the calcium carbide tail gas intake pipe (1) and the semi-coke tail gas intake pipe (2) are both connected to the gas cabinet (3), and the first mixed gas intake pipe (41) is connected to the gas cabinet (3).

6. The gas intake process for the boiler gas intake system for blue coke tail gas and calcium carbide tail gas as claimed in claim 5, characterized in that: The burner group (11) comprises a plurality of burners (111), and the plurality of burners (111) are all in communication with a burner group air inlet pipe (10), and the plurality of burners (111) are also all in communication with a mixed gas discharge pipe (12); a burner gun head (112) is provided on the burner (111), and the burner gun head (112) is provided with a plurality of side jet holes (1122) and a central jet hole (1121); the center point of the central jet hole (1121) coincides with the centerline axis of the burner gun head (112); the side jet holes (1122) are arranged on the outside of the central jet hole (1121) along the radial direction of the central jet hole (1121); and the aperture of the central jet hole (1121) is larger than the aperture of the side jet hole (1122).

7. The gas intake process for the boiler gas intake system for blue coke tail gas and calcium carbide tail gas according to claim 1, characterized in that: The steps also include: when a burner group fails, the mixer in the burner group (11) discharges the mixed gas along the mixed gas discharge pipe (12) into the discharge pipe (8).