A multi-tube mixing pile drilling rig
Through the multi-channel pipeline system and oblique correction technology of the multi-pipe mixing pile drilling rig, the problem of insufficient cement slurry is solved, and the uniform stirring of soil and cement slurry is achieved, ensuring consistency of pile body strength and improvement of construction efficiency.
Patent Information
- Application Number
- CN202110282771.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-03-16
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2041-03-16
AI Technical Summary
During the drilling process of existing cement mixing pile drilling rigs, as the drilling depth increases, the slurry jet resistance increases, resulting in insufficient cement slurry, making it difficult to ensure uniform stirring of soil and cement slurry, affecting the homogeneous performance and quality of piles. sex.
Design a multi-pipe mixing pile drilling rig, adopting a multi-channel pipeline system, and the slurry gas swing joint and slurry line swing joint realizes the injection of cement slurry and compressed gas to the soil at the same time. Combined with the inclination measuring device and the computing control system, real-time monitoring and correct the skewness of the drill pipe to ensure uniformity of stirring and vertical accuracy.
Effectively promote the full mixing of soil and cement slurry, ensure the consistency of pile body strength, improve the construction quality and efficiency of mixing piles, shorten the construction cycle, and reduce costs.
Smart Images

Figure CN112854207B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of foundation construction, and in particular relates to a multi-tube mixing pile drilling rig for underground water-stop curtain wall construction, foundation pit excavation and enclosure, dam anti-seepage treatment and foundation reinforcement and improvement. Background Art
[0002] At present, cement mixing pile construction technology is widely used in industrial construction and urban construction foundation construction. Through a special multi-axis soil mixing drill, during the drilling and lifting process of the drill rod, cement slurry curing agent is sprayed from the front end of the drill bit, and forcedly mixed with loose soil, sand and gravel and curing agent to form a cement soil mixing reinforced foundation with integrity, water stability and certain strength. A large number of construction cases show that the internal homogeneity of the pile body varies greatly during the formation process, and the quality of the upper part of the cement soil mixing pile is better than that of the lower part.
[0003] The existing cement soil mixing pile drilling rig generally adopts the method of grouting and jetting at the bottom of the drill bit. As the drilling depth increases, the drill bit is subjected to a large soil pressure, and the slurry jetting resistance is large, resulting in insufficient cement slurry in the surrounding soil, making it difficult to ensure uniform mixing of cement slurry and soil, thereby affecting the homogeneous performance of the pile body. In order to improve the homogeneous performance of the upper and lower piles after drilling and mixing of cement soil mixing piles, ensure the consistency of the quality of the upper and lower piles, and improve the vertical accuracy requirements of the wall after the pile is formed, it is necessary to make necessary technical improvements to the drill rod and drill tool structure, set up multi-channel pipelines in the inner cavity of the drill rod and its drill tool, ensure that grouting and jetting are simultaneously performed on the surrounding soil during the mixing process, and realize grouting on the surrounding soil at different stages when the drill rod and its drill tool are drilled and lifted to promote the mixing of the surrounding soil and cement slurry components. By setting up a drill rod inclinometer to monitor the inclination of the drill rod and its drilling tools during rotational drilling, the operator is prompted to take timely corrective measures to ensure the vertical accuracy of the mixing pile wall and the homogeneity of the upper and lower pile bodies of the mixing pile, effectively improving the construction quality and efficiency of the mixing pile and reducing the construction cost of the mixing pile. Summary of the invention
[0004] The main purpose of the present invention is to overcome the shortcomings of the existing mixing drill rigs, and to provide a multi-tube mixing pile drilling rig that can meet the requirements of rotating and conveying slurry and compressed gas to the drill rod assembly and adapt to the wiring of monitoring cables, so as to meet the functional requirements of the mixing pile drilling rig to spray and jet air to the surrounding soil at different stages when the drill rod assembly is drilling down and lifting up, promote the full mixing of the surrounding soil and cement slurry, achieve the consistency of the pile body strength after the pile is formed, and improve the construction quality of the mixing pile; through the inclinometer, azimuth detection device, depth detection device and operation control system, the deflection of the drill rod during rotation is displayed on the control screen, prompting the operator to take corresponding correction measures, thereby ensuring the upper and lower vertical accuracy of the mixing pile wall, improving the operating efficiency of the mixing pile drilling rig, shortening the construction period and saving construction costs.
[0005] The present invention is achieved through the following technical solutions:
[0006] A multi-tube mixing pile drilling rig, comprising: a power head with a top drive mechanism, a frame including a guide plate and a lifting pulley block, and a reduction box, three slurry-air swivel joints, a slurry-line swivel joint, an azimuth detection device including an encoder, a pinion, a mounting frame and a cover; a set of first drill rod assemblies, three sets of second drill rod assemblies, a sealing gasket including a sealing gasket body and three upper convex lip rings with an upper steel sleeve, a plurality of drill rod support frames, a guide bracket, a depth sensor and an operation control system, wherein:
[0007] The reduction box includes a box body and a cover, four hollow spindles with a first spindle grouting channel, a second spindle grouting channel, a spindle air injection channel and a spindle countersink, two input shafts, a spindle flange connected to the lower end of each hollow spindle, a female joint, a first flange grouting pipe, a second flange grouting pipe, a first flange air pipe, a measuring gear and a flange countersink; wherein the female joint includes a female fixing plate located at the bottom of its inner groove and having a female plate through hole;
[0008] The slurry-gas rotary joint comprises a support frame, a lower rotating shaft, an upper rotating shaft including an upper shaft air supply hole located therein and an upper shaft shoulder at the lower end, a rotating shaft jacket, an upper sleeve cover, a lower sleeve cover, an upper connecting shaft, an upper bracket, a transition joint, a rotary air injection joint, an air supply pipe and a diverter block; wherein: the lower rotating shaft comprises a first lower shaft grouting hole, a second lower shaft grouting hole, a lower shaft air injection hole, a first lower shaft transverse grouting hole and a second lower shaft transverse grouting hole respectively connected with the first lower shaft grouting hole and the second lower shaft grouting hole, and also comprises a lower shaft countersunk hole located at its upper end and a lower shaft docking cover located at its outer wall; the rotating shaft jacket comprises a first grouting annular groove and a second grouting annular groove located on its inner wall, a plurality of outer sleeve annular grooves and outer sleeve grooves with oil supply nozzles, an outer sleeve countersunk hole located at its upper end, a first grouting hole and a second grouting hole located on its outer wall respectively connected with the first grouting annular groove and the second grouting annular groove, and also comprises a first locking hole and a second locking hole located on its outer wall;
[0009] The slurry line rotary joint comprises a support frame including a first stop claw, a first stop claw and a support flange located at the bottom, a lower rotating shaft, an upper rotating shaft, a rotating shaft outer sleeve, an upper cover including a first upper cover countersunk hole and a second upper cover countersunk hole, a lower cover including a first lower cover countersunk hole and a second lower cover countersunk hole, an upper connecting shaft, an upper bracket including a bracket ring, an upper bracket of a fixed vertical plate located on one side of the bracket ring, a transition joint and a slip electric ring; wherein: the slip electric ring comprises an outer cable connected to the outer ring of the slip electric ring, an inner cable led out from the inner ring of the slip electric ring and a pressure plate;
[0010] The first drill pipe assembly includes a multi-section unit drill pipe, an inclination drill pipe and a drilling tool; wherein the unit drill pipe includes a male joint, a female joint and a third built-in pipeline including a fifth slurry pipe, a sixth slurry pipe, a third air pipe and a plurality of third pipeline racks; the inclination drill pipe includes a male joint, a female joint, an upper shotcrete port, a first inclination measuring device including an arc plate, a plate support and a first sensor, and a first built-in pipeline including a first slurry pipe, a second slurry pipe, a first air pipe and a plurality of first pipeline racks; the drilling tool includes a male joint, a lower shotcrete port, a second built-in pipeline including a third slurry pipe, a second air pipe and a plurality of second pipeline racks, an air jet port, and a plurality of groups of stirring blades and cutting blades including blades and blade seats;
[0011] The second drill rod assembly includes a multi-section unit drill rod, a bare drill rod and a drilling tool; wherein the unit drill rod includes a male joint, a female joint and a third internal pipeline including a fifth slurry pipe, a sixth slurry pipe, a third air pipe and a plurality of third pipeline racks; the bare drill rod includes a male joint, a female joint, an upper shotcrete port including a first slurry pipe, a second slurry pipe, a first air pipe and a plurality of first pipeline racks; the drilling tool includes a male joint, a lower shotcrete port, a second internal pipeline including a third slurry pipe, a second air pipe and a plurality of second pipeline racks, an air jet port, a plurality of groups of stirring blades and cutting blades including blades and blade seats; wherein:
[0012] The frame of the power head is fixed on the cover of the gear box. It is placed on the column guide rail of the external pile frame through its guide plate, and its lifting pulley group is connected to the wire rope led out by the external pile frame winch; the four hollow main shafts of the reduction box are arranged in a straight line along the transverse direction of the reduction box body, and are arranged in a way that both ends extend out of the reduction box, and their upper ends extend out of the box cover and are located in each end ring, and their lower ends extend out of the box body and are fitted with the main shaft flange and then installed with the docking flange; the first main shaft grouting channel, the second main shaft grouting channel, and the main shaft air injection channel of the hollow main shaft are arranged in a way that their cross-sectional directions are equilateral triangle symmetrical and axially parallel to each other, and their upper end faces are all located at the main shaft countersunk holes of the hollow main shaft; the two input shafts are arranged on the gear box on one side of the four hollow main shafts, and they are respectively meshed with the four hollow main shafts through gear transmission in the inner cavity of the gear box and then output power; the top drive mechanism is respectively arranged at the upper end of each input shaft;
[0013] The three slurry-gas rotary joints and one slurry-line rotary joint are respectively arranged above the four hollow main shafts of the reduction box, and they all pass through the end ring of the reduction box through the lower rotating shaft to reach the upper end of the hollow main shaft; the first lower shaft grouting hole, the second lower shaft grouting hole and the lower shaft air injection hole of the lower rotating shaft are arranged in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other; the first lower shaft grouting hole and the second lower shaft grouting hole are respectively connected with the first lower shaft transverse slurry channel and the second lower shaft transverse slurry channel in the lower rotating shaft, and the first lower shaft transverse slurry channel and the second lower shaft transverse slurry channel are respectively connected with the first grouting ring groove and the second grouting ring groove of the rotating shaft outer sleeve; the lower end of the lower rotating shaft is placed in the main shaft countersunk hole of the hollow main shaft, and its first lower shaft grouting hole, the second lower shaft grouting hole The hole and the lower shaft air injection hole are respectively connected with the first main shaft grouting channel, the second main shaft grouting channel and the main shaft air injection channel of the hollow main shaft; the lower shaft docking cover is fixed on the hollow main shaft by screws to connect the lower rotating shaft and the hollow main shaft into one; the first lower sleeve hole groove and the second lower sleeve hole groove of the lower cover are respectively installed with bearings and skeleton oil seals, and then are sleeved on the installation position on the lower rotating shaft; the rotating shaft outer sleeve is sleeved on the lower rotating shaft and is tightly connected with the lower sleeve cover; the outer sleeve ring groove and the outer sleeve groove are respectively installed with O-rings and grease; the first grouting hole and the second grouting hole of the rotating shaft outer sleeve are respectively connected with the first grouting ring groove and the second grouting ring groove in the rotating shaft outer sleeve, and the other ends are respectively connected to external slurry delivery pipelines, and the proportioned cement slurry is pumped in by the external grouting system; the upper The rotating shaft is placed in the lower shaft countersunk hole of the lower rotating shaft through its upper shaft shoulder, and its upper shaft air supply hole is obliquely set and connected with the lower shaft air injection hole of the lower rotating shaft; the upper end face of the upper rotating shaft is fixed with a transition joint; the upper connecting shaft is placed on the upper end face of the transition joint through the upper shaft hole shoulder located at its bottom and is fixed to the upper rotating shaft by screws, thereby connecting the upper connecting shaft, the transition joint and the upper rotating shaft into one; the through hole of the upper connecting shaft is connected with the through hole of the transition joint and the upper shaft air supply hole of the upper rotating shaft; the first lower upper sleeve hole groove and the second upper sleeve hole groove of the upper sleeve cover are respectively installed with bearings and skeleton oil seals, and then pass through the upper connecting shaft and the transition joint and are fixed to the upper end face of the rotating shaft outer sleeve; the upper bracket is fixed to the upper sleeve cover through the bracket ring; the fixed vertical plate is fixed to one side of the bracket ring; The support frame is respectively arranged on the left and right sides of each slurry-gas rotary joint and the slurry-line rotary joint, and the first stop claw and the first stop claw of the support frame are respectively placed in the first locking hole and the second locking hole on the outer wall of the rotating shaft sleeve of each slurry-gas rotary joint and the slurry-line rotary joint; the support frame flange is fixedly mounted on each installation position of the box cover of the reduction box, so that the slurry-gas rotary joint and the slurry-line rotary joint are fixedly mounted on the upper end of the hollow output shaft; the rotary air injection joint of the slurry-gas rotary joint is fixedly mounted on the upper connecting shaft; the diverter block is fixedly mounted on the fixed vertical plate; the air supply pipe connects the rotary air injection joint and the diverter block; the slipping electric ring of the slurry-line rotary joint is sleeved on the upper cover through its inner ring, and the pressure plate is fixed on the end face of the slipping electric ring, and the other end is fastened to the fixed vertical plate;The inner cable passes through the through hole of the upper connecting shaft, the through hole of the transition joint, the upper shaft air supply hole of the upper rotating shaft, the lower shaft air injection hole of the lower rotating shaft, and the main shaft air injection channel of the hollow main shaft, and then enters the multi-section unit drill rod and the inclination drill rod of the first drill rod assembly in sequence, and then connects to the first inclination measuring device;
[0014] The first set of drill rod assemblies and the three sets of second drill rod assemblies are respectively inserted into the female joints of the docking flanges fixed at the lower ends of the hollow main shafts of the reduction box to complete the assembly of the drill rods and drilling tools;
[0015] The first drill pipe assembly is formed by connecting a plurality of unit drill pipes, an inclinometer drill pipe and a drill tool; the male plate through holes of the male fixing plate of the male joint of the unit drill pipe are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate; the female plate through holes of the female fixing plate of the female joint are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the female fixing plate; the third built-in pipeline is arranged in the inner cavity of the unit drill pipe through a plurality of third pipeline racks, and the fifth slurry pipe, the sixth slurry pipe and the third air pipe of the third built-in pipeline are arranged in the inner cavity of the unit drill pipe in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other; the third pipeline rack is provided with three third pipe rack through holes arranged in an equilateral triangle symmetrical manner in the radial direction; The fifth slurry pipe, the sixth slurry pipe and the third air pipe are respectively passed through the three third pipe rack through holes of the third pipeline rack and are fixed in the inner cavity of the unit drill pipe; the upper ends of the fifth slurry pipe, the sixth slurry pipe and the third air pipe are respectively placed in the three male plate through holes of the male fixing plate of the male joint and are welded and fixed, and the male fixing plate is welded and fixed to the end face of the male joint; the lower ends of the fifth slurry pipe, the sixth slurry pipe and the third air pipe are respectively placed in the three female plate through holes of the female fixing plate of the female joint and are welded and fixed, and the female fixing plate is welded and fixed to the bottom of the inner groove of the female joint; the male fixing plate of the male joint of the inclinometer drill pipe is provided with three male plate through holes, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate; the female fixing plate of the female joint is provided with three female plate through holes, which are equilaterally arranged in the radial direction of the female fixing plate The first slurry pipe is symmetrically arranged in an equilateral triangle; the upper grouting port of the inclinometer drill pipe is arranged on its outer wall; the first built-in pipeline of the inclinometer drill pipe is arranged in the inner cavity of the bare drill pipe through a plurality of first pipeline racks, and the first slurry pipe, the second slurry pipe and the first air pipe of the first built-in pipeline are arranged in the inner cavity of the bare drill pipe in a manner that their cross-sectional directions are symmetrical in an equilateral triangle and their axes are parallel to each other; the first slurry pipe is connected to the upper grouting port in the inner cavity of the inclinometer drill pipe through a short elbow pipe; the first pipeline rack is provided with three first pipe rack through holes arranged in an equilateral triangle symmetrical manner in their radial direction; the first slurry pipe, the second slurry pipe and the first air pipe are respectively fixed to the inner cavity of the inclinometer drill pipe after passing through the three first pipe rack through holes of the first pipeline rack; the upper ends of the first slurry pipe, the second slurry pipe and the first air pipe are respectively The first inclinometer 104 is fixed on the outer wall of the inclinometer drill pipe below the upper grouting port through an arc plate; the plate support is located on the inner side of the arc plate; the sensor 1043 of the first inclinometer 104 is fixed on the plate support 1042, and is connected to the inner cable 2111 of the sliding electric ring 211 of each air pipe passing through the inner cavity of the first drill pipe assembly 1; the male plate through holes of the male fixing plate of the male connector of the drilling tool are provided with three, which are arranged symmetrically in an equilateral triangle in the radial direction of the male fixing plate;The lower grouting port is arranged at the bottom end of the outer wall of the drill pipe body of the drill tool; the air jet port is arranged at the bottom of the drill pipe body of the drill tool; the second built-in pipeline of the drill tool is arranged in the inner cavity of the drill tool through a plurality of second pipeline racks; the second pipeline rack is provided with three second pipe rack through holes arranged symmetrically in an equilateral triangle in its radial direction; the third slurry pipe and the second air pipe of the second built-in pipeline are respectively fixed in the inner cavity of the stirring drill tool through two second pipe rack through holes of the plurality of second pipeline racks; the upper ends of the third slurry pipe and the second air pipe are respectively placed on two male fixing plates of the male fixing plate The plate is welded and fixed after being through-holed, and the male fixing plate is welded and fixed to the end face of the male joint; the lower end of the third slurry pipe is connected to the lower grouting port through the lower curved slurry pipe; the lower end of the second air pipe is connected to the air jet port; the multiple groups of stirring blades of the drill tool are symmetrically arranged on the outer wall of the drill tool body of the drill tool in an upper and lower spaced and crossed manner; the blades of each group of stirring blades are installed on the blade seat through a pin shaft; the cutting wings of the drill tool are symmetrically arranged on the bottom outer wall of the drill tool body of the drill tool; the lower grouting port is arranged at the bottom end of the outer wall of the drill tool body; the air jet port is arranged at the bottom of the drill tool body;
[0016] The second drill pipe assembly is formed by connecting a multi-section unit drill pipe, a bare drill pipe and a drill tool; the first built-in pipeline of the bare drill pipe is arranged in the inner cavity of the bare drill pipe through a plurality of first pipeline racks, and the first slurry pipe, the second slurry pipe and the first air pipe of the first built-in pipeline are arranged in the inner cavity of the bare drill pipe in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axes are parallel to each other; the first pipeline rack is provided with three first pipe rack through holes arranged in an equilateral triangle symmetrical manner in their radial directions; the first slurry pipe, the second slurry pipe and the first air pipe are respectively fixed in the inner cavity of the bare drill pipe after passing through the three first pipe rack through holes of the first pipeline rack; the first slurry pipe is connected to the upper grouting port in the inner cavity of the bare drill pipe through a short bend pipe; the upper ends of the first slurry pipe, the second slurry pipe and the first air pipe are respectively placed in the three male plate through holes of the male fixing plate of the male joint and then welded and fixed, and the male fixing plate is welded and fixed to the end face of the male joint; the lower ends of the second slurry pipe and the first air pipe are placed in the two female plate through holes of the female fixing plate of the female joint and then welded and fixed, and the female fixing plate is welded and fixed to the bottom of the inner groove of the female joint;
[0017] The three upper convex lip rings of the sealing gasket are arranged on the upper end surface of the sealing gasket body in an equilateral triangle symmetrical manner, and the upper steel sleeve is arranged in the hole of the upper convex lip ring; the sealing gaskets are respectively arranged between the lower rotating shaft of each slurry-gas swivel joint and the slurry line swivel joint and the main shaft countersunk hole of the hollow main shaft of the reduction box, and between each hollow main shaft and the docking flange, and their three upper convex lip rings respectively enter the first lower shaft grouting hole, the second lower shaft grouting hole and the lower shaft air injection hole at the lower end of each lower rotating shaft, and the first main shaft grouting channel, the second main shaft grouting channel and the main shaft air injection channel at the lower end of each hollow main shaft; the first drill pipe assembly and each second drill pipe assembly are connected at the female joints of each docking flange of the reduction box When the drill pipe is assembled, the sealing gasket is respectively arranged between each docking flange and the unit drill pipe, between the unit drill pipe and the inclinometer drill pipe, and between each unit drill pipe and the bare drill pipe, and its three upper convex lip rings are respectively in the holes of the first flange slurry pipe, the second flange slurry pipe, and the first flange air pipe at the flange sink of each docking flange, and in the holes of the fifth slurry pipe, the sixth slurry pipe, and the third air pipe at the end face of the female fixing plate of the female joint of each unit drill pipe; the sealing gasket is also respectively arranged between the inclinometer drill pipe and the drilling tool, and between each bare drill pipe and the drilling tool, and two of its three upper convex lip rings are respectively entered into the holes of the second slurry pipe and the first air pipe at the outer end face of the female fixing plate of the female joint of the inclinometer drill pipe and each bare drill pipe;
[0018] The groups of stirring blades of the drill tools between the first drill rod assembly and the second drill rod assembly, and between adjacent second drill rod assemblies, are arranged in an up-and-down staggered manner, so that the arc trajectories formed by the groups of stirring blades of the drill tools have a certain overlap during the rotation of the drill tools; the unit drill rods of the first drill rod assembly and the second drill rod assembly are supported by a plurality of guide brackets arranged vertically therewith, the side ends of the guide brackets are placed on the column guide rails of the external pile frame, and are connected and hung under the reduction box of the power head by iron chains; the drill tools of the first drill rod assembly and the second drill rod assembly are supported by a plurality of drill rod support brackets arranged vertically therewith;
[0019] The azimuth detection device is arranged at a docking flange below the reduction box, and the docking flange is fixedly mounted with the first drill pipe assembly; the encoder is fixedly mounted on the mounting frame, and a pinion is fixedly mounted on the rotating shaft of the encoder; after the mounting frame and the enclosure are fixedly mounted below the reduction box, the spindle flange and the docking flange of the reduction box which are mounted on the hollow spindle are enclosed therein; the pinion is meshed with the measuring gear of the docking flange, and the horizontal azimuth angle of the first drill pipe assembly during rotation is transmitted to the operation control system through a cable;
[0020] The depth sensor is installed on the external pile frame column of the suspended mixing pile drilling rig to detect the drilling depth in real time and transmit it to the operation control system through an external data line;
[0021] The operation control system displays the drill rod inclination on a display screen by performing software operation, superposition and compensation on the drilling depth collected by the depth sensor, the upper and lower end deflection angles of the first drill rod assembly collected by the first inclinometer and the second inclinometer, and the horizontal azimuth of the first drill rod assembly detected by the azimuth detection device.
[0022] The present invention may be that the verticality deviations of the outer end surface of the male fixing plate of the male joint and the hollow main shaft of the reduction box, the unit drill rod, the inclinometer drill rod, the smooth drill rod and the axial center line of the drill tool are less than or equal to 0.08-0.10mm.
[0023] The present invention may also be that the verticality deviation of the outer end surface of the female fixing plate of the female joint and the axial center line of the docking flange of the reduction box, the unit drill rod, the inclinometer drill rod, and the smooth drill rod is less than or equal to 0.08-0.10mm.
[0024] The present invention may also be that the verticality deviation between the outer end surface of the flange sink hole of the docking flange of the reduction box and the axial center line of the docking flange is less than or equal to 0.08-0.10 mm. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the structure of the multi-tube mixing pile drilling rig of the present invention;
[0026] Figure 2 yes Figure 1 Left view of;
[0027] Figure 3 yes Figure 1 A top view of
[0028] Figure 4 yes Figure 1 Bottom view of
[0029] Figure 5 It is a schematic diagram of the drilling tool structure of the first drill rod assembly and the second drill rod assembly in the present invention;
[0030] Figure 6 yes Figure 5 A top view of
[0031] Figure 7 yes Figure 5 Bottom view of
[0032] Figure 8 yes Figure 6 Middle HH section view;
[0033] Fig. 9 yes Figure 5 Middle JJ section view;
[0034] Fig.10 yes Figure 6A partial enlarged view of the middle S part;
[0035] Fig.11 It is a schematic diagram of the monitoring drill rod structure of the first drill rod assembly in the present invention;
[0036] Fig.12 yes Fig.11 A top view of
[0037] Fig.13 yes Fig.11 Bottom view of
[0038] Fig.14 yes Fig.12 Middle AA section view;
[0039] Fig.15 It is a schematic diagram of the sealing gasket structure of the present invention;
[0040] Fig.16 yes Fig.15 Middle BB section view;
[0041] Fig.17 It is a schematic diagram of the bare drill rod structure of the second drill rod assembly in the present invention;
[0042] Fig.18 yes Fig.17 A top view of
[0043] Fig.19 yes Fig.17 Bottom view of
[0044] Fig. 20 yes Fig.18 Middle PP section view;
[0045] Fig.21 It is a schematic diagram of the unit drill rod structure of the first drill rod assembly and the second drill rod assembly in the present invention;
[0046] Fig. 22 yes Fig.21 A top view of
[0047] Fig.23 yes Fig.21 Bottom view of
[0048] Fig.24 yes Fig. 22 Middle DD section view;
[0049] Fig.25 It is a schematic diagram of the structure of the first drill pipe assembly and the azimuth detection device in the present invention;
[0050] Fig.26 yes Fig.25 Middle CC section view;
[0051] Fig. 27 yes Fig.26 A partial enlarged view of the middle H part;
[0052] Fig.28 yes Fig.25 Cross-sectional view in the middle XX direction;
[0053] Fig.29 yes Fig.25 Middle YY section view;
[0054] Fig.30 yes Fig.25 ZZ-axis sectional view;
[0055] Fig.31 It is the schematic diagram of the structure of the power head, the slurry gas rotary joint and the slurry line rotary joint in the present invention;
[0056] Fig.32 yes Fig.31 Left view of
[0057] Fig.33 yes Fig.31 A top view of
[0058] Fig.34 yes Fig.33 Middle SS section view;
[0059] Fig.35 It is a schematic diagram of the structure of the slurry-gas rotary joint in the present invention;
[0060] Fig.36 yes Fig.35 Middle EE section view;
[0061] Fig.37 yes Fig.36 Middle MM section view;
[0062] Fig.38 It is a schematic diagram of the structure of the pulp line rotary joint in the present invention;
[0063] Fig.39 yes Fig.38 Middle FF section view;
[0064] Fig.40 It is the NN section view in 39. DETAILED DESCRIPTION
[0065] The multiple-tube mixing pile drilling rig of the present invention will be further described below in conjunction with the accompanying drawings.
[0066] A multi-tube mixing pile drilling rig, comprising: a power head 3 having a top drive mechanism 31, a frame 32 including a guide plate 321 and a lifting pulley block 322 and a reduction box 30, three slurry-gas rotary joints 20, a slurry-line rotary joint 20', an orientation detection device 80 including an encoder 801, a pinion 805, a mounting frame 803 and a cover 804; a set of first drill pipe assemblies 1, three sets of second drill pipe assemblies 1', a sealing gasket 50 including a sealing gasket body 500 and three upper convex lip rings 501 with upper steel sleeves 5011, a plurality of drill pipe support frames 7, a guide bracket 7', a depth sensor and an operation control system;
[0067] The reduction box 30 includes a box body 300, a box cover 301, four hollow main shafts 302 with a first main shaft grouting channel 3021, a second main shaft grouting channel 3022, a main shaft air injection channel 3023 and a main shaft counterbore 3026, two input shafts 301, a main shaft flange 304 connected to the lower end of each hollow main shaft 302, a docking flange 305 including a female joint 102, a first flange grouting pipe 3051, a second flange grouting pipe 3052, a first flange air pipe 3053, a measuring gear 2055 and a flange counterbore 3056; wherein the female joint 102 includes a female fixing plate 1021 located at the bottom of its inner groove and having a female plate through hole 1022;
[0068] The slurry gas rotary joint 20 includes a support frame 200, a lower rotating shaft 201, an upper rotating shaft 202 including an upper shaft air supply hole 2023 located therein and an upper shaft shoulder 2024 at the lower end, a rotating shaft jacket 204, an upper sleeve cover 205, a lower sleeve cover 206, an upper connecting shaft 207, an upper bracket 208, a transition joint 209, a rotary gas injection joint 210, an air supply pipe 2101 and a diverter block 2102; wherein: The lower shaft 201 includes a first lower shaft grouting hole 2011, a second lower shaft grouting hole 2012, a lower shaft air injection hole 2013, a first lower shaft transverse grouting hole 20111 and a second lower shaft transverse grouting hole 20121 which are respectively connected to the first lower shaft grouting hole 2011 and the second lower shaft grouting hole 2012, and also includes a lower shaft countersunk hole 2014 located at its upper end and a lower shaft docking cover 2015 located on its outer wall; the shaft sleeve 204 includes a lower shaft countersunk hole 2014 located at its inner wall A first grouting annular groove 2041, a second grouting annular groove 2042, a plurality of outer sleeve annular grooves 2043 and outer sleeve grooves 2044 with oil supply nozzles, an outer sleeve countersunk hole 2045 located at the upper end thereof, a first grouting hole 20411 and a second grouting hole 20421 located on the outer wall thereof and connected to the first grouting annular groove 2041 and the second grouting annular groove 2042 respectively, and also includes a first locking hole 2046 and a second locking hole 2047 located on the outer wall thereof;
[0069] The pulp line rotary joint 20' comprises a support frame 200 including a first stop claw 2006, a first stop claw 2007 and a support flange 2008 at the bottom, a lower rotating shaft 201, an upper rotating shaft 202, a rotating shaft outer sleeve 204, an upper cover 205 including a first upper cover countersunk hole 2051 and a second upper cover countersunk hole 2052, a lower cover 206 including a first lower cover countersunk hole 2061 and a second lower cover countersunk hole 2062, an upper connecting shaft 207, an upper bracket 208 including a bracket ring 2081 and a fixed vertical plate 2082 located on one side of the bracket ring, a transition joint 209 and a slipping electric ring 211; wherein: the slipping electric ring 211 comprises an outer cable 2112 connected to the outer ring of the slipping electric ring, an inner cable 2111 led out from the inner ring of the slipping electric ring 211, and a pressing plate 2113;
[0070] The first drill pipe assembly 1 includes a multi-section unit drill pipe 10', an inclination drill pipe 10 and a drilling tool 60; wherein the unit drill pipe 10' includes a male joint 101, a female joint 102 and a third built-in pipeline 105' including a fifth slurry pipe 1051', a sixth slurry pipe 1052', a third air pipe 1053' and a plurality of third pipeline racks 1054', and the inclination drill pipe 10 includes a male joint 101, a female joint 102, an upper grouting port 103, an arc plate 1041, a plate support 1042 and a first sensor 1 043, a first inclinometer 104, a first built-in pipeline 105 including a first slurry pipe 1051, a second slurry pipe 1052, a first air pipe 1053 and a plurality of first pipeline racks 1054; the drilling tool 60 includes a male connector 101, a lower shotcrete port 603, a second built-in pipeline 605 including a third slurry pipe 6052, a second air pipe 6053 and a plurality of second pipeline racks 6054, an air jet port 609, a plurality of stirring blades 606 including blades 6061 and blade seats 6062, and a cutting blade 607;
[0071] The second drill pipe assembly 1' comprises a multi-section unit drill pipe 10', a bare drill pipe 10" and a drilling tool 60; wherein the unit drill pipe 10' comprises a male joint 101, a female joint 102 and a third internal pipeline 105' including a fifth slurry pipe 1051', a sixth slurry pipe 1052', a third air pipe 1053' and a plurality of third pipeline racks 1054'; the bare drill pipe 10" comprises a male joint 101, a female joint 102, an upper grouting port 103 including a first slurry pipe 1051', a sixth slurry pipe 1052', a third air pipe 1053' and a plurality of third pipeline racks 1054' 051, a second slurry pipe 1052, a first air pipe 1053 and a first built-in pipeline 105 of a plurality of first pipeline racks 1054; the drilling tool 60 includes a male joint 101, a lower shotcrete port 603, a second built-in pipeline 605 including a third slurry pipe 6052, a second air pipe 6053 and a plurality of second pipeline racks 6054, an air jet port 609, a plurality of stirring blades 606 and cutting blades 607 including blades 6061 and blade seats 6062; wherein:
[0072] The frame 32 of the power head 3 is fixed to the cover 301 of the gear box 30, and is placed on the column guide rail of the external pile frame through its guide plate 321. Its lifting pulley group 322 is connected to the wire rope led out by the external pile frame winch; the four hollow main shafts 302 of the reduction box 30 are arranged in a straight line along the transverse direction of the box body 300 of the reduction box 30, and are arranged in a manner that both ends extend out of the reduction box 30, and the upper end thereof extends out of the box cover 301 and is located in each end ring 306, and the lower end thereof extends out of the box body 300 and is fitted with the main shaft flange 304 and then the docking flange 305 is installed. The first spindle grouting channel 3021, the second spindle grouting channel 3022, and the spindle air injection channel 3023 of the hollow spindle 302 are arranged in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other, and their upper end faces are all located at the spindle counterbore 3026 of the hollow spindle 302; the two input shafts 301 are arranged on the gear box 30 on one side of the four hollow spindles, and they output power after respectively meshing with the four hollow spindles 302 through gear transmission in the inner cavity of the gear box 30; the top drive mechanism 31 is respectively arranged at the upper end of each input shaft 301.
[0073] The three slurry-gas rotary joints 20 and one slurry-line rotary joint 20' are arranged above the four hollow main shafts 302 of the reduction box 30, and they all pass through the end ring 306 of the reduction box 30 through their lower rotating shafts 201 to reach the upper end of the hollow main shafts 302; the first lower shaft grouting hole 2011, the second lower shaft grouting hole 2012 and the lower shaft gas injection hole 2013 of the lower rotating shaft 201 are arranged in a manner that their cross-sectional directions are equilateral triangles and their axes are parallel to each other; The first lower shaft grouting hole 2011 and the second lower shaft grouting hole 2012 are connected to the first lower shaft transverse grouting channel 20111 and the second lower shaft transverse grouting channel 20121 in the lower shaft 201, respectively. The first lower shaft transverse grouting channel 20111 and the second lower shaft transverse grouting channel 20121 are connected to the first grouting ring groove 2041 and the second grouting ring groove 2042 of the shaft sleeve 204, respectively. The lower end of the lower shaft 201 is placed in the main shaft counterbore 3026 of the hollow main shaft 302. The first lower shaft grouting hole 2011, the second lower shaft grouting hole 2012 and the lower shaft air injection hole 2013 are respectively connected with the first main shaft grouting channel 3021, the second main shaft grouting channel 3022 and the main shaft air injection channel 3023 of the hollow main shaft 302; the lower shaft docking cover 2015 is fixed on the hollow main shaft 302 by screws to connect the lower rotating shaft 201 and the hollow main shaft into one; the first lower sleeve hole groove 2061 and the second lower sleeve hole groove 206 of the lower sleeve cover 206 ... 62 are respectively installed with bearings and skeleton oil seals and then mounted on the mounting position on the lower rotating shaft 201; the rotating shaft sleeve 204 is mounted on the lower rotating shaft 201 and is tightly connected with the lower sleeve cover 206; the sleeve ring groove 2043 and the sleeve groove 2044 are respectively installed with O-rings and grease; in this way, the upper and lower slurries can be effectively isolated to prevent the upper and lower slurries from flowing into each other, avoid leakage of slurry from between the rotating shaft sleeve 204 and the lower rotating shaft 201, and improve its sealing performance. The first grouting hole 20411 and the second grouting hole 20421 of the shaft sleeve 204 are respectively connected with the first grouting annular groove 2041 and the second grouting annular groove 2042 in the shaft sleeve 204, and the other ends are respectively connected to external grouting pipelines, and the proportioned cement slurry is pumped into by the external grouting system; it is ensured that the cement slurry sprayed out by the mixing pile drilling rig at different stages of drilling and lifting is fully mixed with the surrounding soil, ensuring that the quality of the pile body of the mixing pile after the pile is formed meets the technical requirements.The upper rotating shaft 202 is placed in the lower shaft counterbore 2014 of the lower rotating shaft 201 through its upper shaft shoulder 2024, and its upper shaft air supply hole 2023 is obliquely set and connected with the lower shaft air injection hole 2013 of the lower rotating shaft 201; the upper end face of the upper rotating shaft 202 is fixed with a transition joint 209; the upper connecting shaft 207 is placed on the upper end face of the transition joint 209 through the upper shaft hole shoulder 2071 located at the bottom and then fixed to the upper rotating shaft 202 by screws, so that the upper connecting shaft 207, the transition joint 209 and the upper rotating shaft 202 are connected as a whole; the through hole of the upper connecting shaft 207 is connected with the through hole of the transition joint 209 and the upper shaft air supply hole 2023 of the upper rotating shaft 202; the first lower upper sleeve hole groove 2061 and the second upper sleeve hole groove 2062 of the upper sleeve cover 205 are respectively installed with bearings and skeleton oil seals and then pass through the upper connecting shaft The connecting shaft 207 and the transition joint 209 are fixed to the upper end surface of the rotating shaft sleeve 204; the upper bracket 208 is fixed to the upper sleeve cover 205 through the bracket ring 2081; the fixed vertical plate 2082 is fixed to one side of the bracket ring 2081; the support frame 200 is respectively arranged on the left and right sides of each slurry-gas rotary joint 20 and the slurry-line rotary joint 20', and the first stop claw 2006 and the first stop claw 2007 of the support frame are respectively placed in the first locking hole 2046 and the second locking hole 2047 on the outer wall of the rotating shaft sleeve 204 of each slurry-gas rotary joint 20 and the slurry-line rotary joint 20'; the support flange 2008 is fixed to each installation position of the box cover 301 of the reduction box 30, so as to fix the slurry-gas rotary joint 20 and the slurry-line rotary joint 20' to the upper end of the hollow output shaft 302.
[0074] The rotary air injection joint 210 of the slurry-gas rotary joint 20 is fixed on the upper connecting shaft 207; the diverter block 2102 is fixed on the fixed vertical plate 2082; the air supply pipe 2101 connects the rotary air injection joint 210 and the diverter block 2102. After the external air pipe is connected to the diverter block, compressed air is pumped in to meet the functional requirements of the mixing pile drilling rig to spray compressed air to the surrounding soil at different stages when the drill rod is drilled down and lifted up, promote the full mixing of the surrounding soil and cement slurry, and ensure that the strength of the pile body is consistent from top to bottom.
[0075] The slipping electric ring 211 of the slurry line rotary joint 20' is sleeved on the upper cover 205 through its inner ring, the pressure plate 2083 is fixed on the end face of the slipping electric ring 211, and the other end is fastened to the fixed vertical plate 2082; the inner cable 2111 passes through the through hole of the upper connecting shaft 207, the through hole of the transition joint 209, the upper shaft air supply hole 2023 of the upper rotating shaft 202, the lower shaft air injection hole 2013 of the lower rotating shaft 201, and the main shaft air injection channel 3023 of the hollow main shaft 302, and then enters the multi-section unit drill rod 10' and the inclinometer drill rod 10 of the first drill rod assembly 1 in sequence, and then connects to the first inclinometer device 104. When the mixing pile drilling rig rotates and drills, the outer ring of the slipping electric ring 211 does not rotate, but the inner ring rotates with the upper connecting shaft 207, the upper rotating shaft 202, the lower rotating shaft 201 and the hollow main shaft 302 of the reduction gearbox 30 connected thereto, and the first drill rod assembly 1. The inner cable 2111 led out from the inner ring of the slipping electric ring 211 rotates in the air pipe of the inner cavity of the first drill rod assembly 1 without getting entangled, thereby ensuring that the first inclinometer sensor 1043 connected thereto and located on the outer wall of the inclinometer drill rod 10 transmits the monitored drill rod deflection to the control screen, which is convenient for the operator to take corresponding correction measures and effectively ensure the normal construction of the mixing pile drilling rig.
[0076] The first drill rod assembly 1 and the three second drill rod assemblies 1' are respectively inserted into the female joints 102 of the docking flanges 305 fixed at the lower ends of the hollow main shafts 302 of the reduction box 30 to complete the assembly of the drill rods and drilling tools.
[0077] The first drill pipe assembly 1 is formed by connecting a multi-section unit drill pipe 10', an inclinometer drill pipe 10 and a drilling tool 60; the male plate through holes 1012 of the male fixing plate 1011 of the male joint 101 of the unit drill pipe 10' are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate 1011; the female plate through holes 1022 of the female fixing plate 1021 of the female joint 102 are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the female fixing plate 1021; the third built-in pipeline 105' is arranged in the inner cavity of the unit drill pipe 10' through a plurality of third pipeline racks 1054', and the fifth slurry pipe 1051', the sixth slurry pipe 1052', and the third air pipe 1053' of the third built-in pipeline are arranged in the inner cavity of the unit drill pipe 10' in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other; the third pipeline rack 1054' is provided There are three third pipe rack through holes 10541' arranged symmetrically in an equilateral triangle in its radial direction; the fifth slurry pipe 1051', the sixth slurry pipe 1052', and the third air pipe 1053' are respectively passed through the three third pipe rack through holes 10541' of the third pipeline rack 1054' and then fixed in the inner cavity of the unit drill pipe 10'; the upper ends of the fifth slurry pipe 1051', the sixth slurry pipe 1052', and the third air pipe 1053' are respectively placed in the three male plate through holes 1012 of the male fixing plate 1011 of the male connector 101 and then welded and fixed, and the male fixing plate is welded and fixed to the end face of the male connector 101; the lower ends of the fifth slurry pipe 1051', the sixth slurry pipe 1052', and the third air pipe 1053' are placed in the three female plate through holes 1022 of the female fixing plate 1021 of the female connector 102 and then welded and fixed, and the female fixing plate is welded and fixed to the bottom of the inner groove of the female connector 102.The male plate through holes 1012 of the male fixing plate 1011 of the male joint 101 of the inclination drill pipe 10 are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate 1011; the female plate through holes 1022 of the female fixing plate 1021 of the female joint 102 are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the female fixing plate 1021; the upper grouting port 103 of the inclination drill pipe 10 is provided on its outer wall; the first built-in pipeline 105 of the inclination drill pipe 10 is connected through a plurality of first pipeline racks 1054 is arranged in the inner cavity of the inclination drill pipe 10, and the first slurry pipe 1051, the second slurry pipe 1052, and the first air pipe 1053 of the first built-in pipeline are arranged in the inner cavity of the inclination drill pipe 10 in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axes are parallel to each other; the first slurry pipe 1051 is connected to the upper grouting port 103 in the inner cavity of the inclination drill pipe 10 through a short bend pipe 10511; the first pipeline rack 1054 is provided with three first pipe rack through holes 10541 arranged in an equilateral triangle symmetrical manner in its radial direction; The first slurry pipe 1051, the second slurry pipe 1052, and the first air pipe 1053 are respectively passed through the three first pipe rack through holes 10541 of the first pipeline rack 1054 and are fixed to the inner cavity of the inclination drilling rod 10; the upper ends of the first slurry pipe 1051, the second slurry pipe 1052, and the first air pipe 1053 are respectively placed on the three male plate through holes 1012 of the male fixing plate 1011 and are welded and fixed, and the male fixing plate is welded and fixed to the end face of the male joint 101; the lower ends of the second slurry pipe 1052 and the first air pipe 1053 are placed on the female fixing plate 1011 and the male fixing plate 1012. The two mother plate through holes 1022 of the plate 1021 are welded and fixed, and the mother fixing plate is welded and fixed to the bottom of the inner groove of the female joint 102; the first inclinometer 104 is fixedly mounted on the outer wall of the inclinometer drill pipe 10 below the upper shotcrete port 103 through the arc plate 1041; the plate support 1042 is located on the inner side of the arc plate 1041; the sensor 1043 of the first inclinometer 104 is fixedly mounted on the plate support 1042, and is connected to the inner cable 2111 of the sliding electric ring 211 of each air pipe passing through the inner cavity of the first drill pipe assembly 1.The male plate through holes 1012 of the male fixing plate 1011 of the male joint 101 of the drilling tool 60 are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate 1011; the lower grouting port 603 is arranged at the bottom end of the outer wall of the drilling tool tube 608 of the drilling tool 60; the air jet port 609 is arranged at the bottom of the drilling tool tube 608 of the drilling tool 60; the second built-in pipeline 605 of the drilling tool 60 is arranged in the inner cavity of the drilling tool 60 through a plurality of second pipeline racks 6054; the second pipeline rack 6054 is provided with three second pipe rack through holes 60541 arranged in an equilateral triangle symmetrical manner in its radial direction; the third slurry pipe 6052 and the second air pipe 6053 of the second built-in pipeline 605 are respectively fixed to the inner cavity of the stirring drilling tool 60 through two second pipe rack through holes 60541 of a plurality of second pipeline racks 6054; the third slurry pipe The upper ends of the first and second air pipes 6052 and 6053 are respectively placed in the two male plate through holes 1012 of the male fixing plate 1011 and then welded and fixed. The male fixing plate is welded and fixed to the end face of the male joint 101; the lower end of the third slurry pipe 6052 is connected to the lower grouting port 603 through the lower bent slurry pipe 60521; the lower end of the second air pipe 6053 is connected to the air jet port 609; the multiple groups of stirring blades 606 of the drilling tool 60 are symmetrically arranged on the outer wall of the drilling tool body 608 of the drilling tool 60 in an upper and lower spaced and crossed manner; the blades 6061 of each group of stirring blades 606 are installed on the blade seat 6062 through a pin shaft; the cutting wings 660 of the drilling tool 60 are symmetrically arranged on the bottom outer wall of the drilling tool body 608 of the drilling tool 60; the lower grouting port 603 is arranged at the bottom end of the outer wall of the drilling tool body 608; the air jet port 609 is arranged at the bottom of the drilling tool body 608.
[0078] The second drill pipe assembly 1' is formed by connecting a multi-section unit drill pipe 10', a bare drill pipe 10" and a drilling tool 60; the first built-in pipeline 105 of the bare drill pipe 10" is arranged in the inner cavity of the bare drill pipe 10" through a plurality of first pipeline racks 1054, and the first slurry pipe 1051, the second slurry pipe 1052, and the first air pipe 1053 of the first built-in pipeline are arranged in the inner cavity of the bare drill pipe 10" in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other; the first pipeline rack 1054 is provided with three first pipe rack through holes 10541 arranged in an equilateral triangle symmetrical manner in their radial direction; the first slurry pipe 1051, the second slurry pipe 1052, and the first air pipe 1053 pass through the first pipeline rack 1054 respectively. 054 is fixed in the inner cavity of the bare drill rod 10" after being inserted into the three first pipe rack through holes 10541; the first slurry pipe 1051 is connected to the upper grouting port 103 in the inner cavity of the bare drill rod 10" through a short bend pipe 10511; the upper ends of the first slurry pipe 1051, the second slurry pipe 1052 and the first air pipe 1053 are respectively placed in the three male plate through holes 1012 of the male fixing plate 1011 of the male joint 101 and then welded and fixed, and the male fixing plate is welded and fixed to the end face of the male joint 101; the lower ends of the second slurry pipe 1052 and the first air pipe 1053 are placed in the two female plate through holes 1022 of the female fixing plate 1021 of the female joint 102 and then welded and fixed, and the female fixing plate is welded and fixed to the bottom of the inner groove of the female joint 102.
[0079] The three upper convex lip rings 501 of the sealing gasket 50 are arranged in an equilateral triangle symmetrical manner on the upper end surface of the sealing gasket body 500, and the upper steel sleeve 5011 is set in the hole of the upper convex lip ring 501; the sealing gasket 50 is respectively arranged between the lower rotating shaft 201 of each slurry-gas rotary joint 20, the slurry line rotary joint 20' and the main shaft countersunk hole 3026 of the hollow main shaft 302 of the reduction box 30, and between each hollow main shaft 302 and the docking flange 305, and their three upper convex lip rings 501 respectively enter the first lower shaft grouting hole 2011, the second lower shaft grouting hole 2012 and the lower shaft air injection hole 2013 at the lower end of each lower rotating shaft 201 and the first main shaft grouting channel 3021, the second main shaft grouting channel 3022 and the main shaft air injection channel 3023 at the lower end of each hollow main shaft 302. When the first drill pipe assembly 1 and each second drill pipe assembly 1' are connected at the female joint 102 of each docking flange 305 of the reduction box 30, the sealing gasket 50 is respectively arranged between each docking flange 305 and the unit drill pipe 10', between the unit drill pipe 10' and the inclinometer drill pipe 10, and between each unit drill pipe 10' and the bare drill pipe 10", and its three upper convex lip rings 501 are respectively in the first flange slurry pipe 3051 at the flange sink 3056 of each docking flange 305, the second flange slurry pipe 3052, the first flange air pipe 3053, and the fifth slurry pipe 1 at the end face of the female fixing plate 1021 of the female joint 102 of each unit drill pipe 10'. 051', the sixth slurry pipe 1052', and the third air pipe 1053'; the sealing gasket 50 is also respectively arranged between the inclination drill rod 10 and the drilling tool 60, and between each bare drill rod 10" and the drilling tool 60, and two of its three upper convex lip rings 501 respectively enter the second slurry pipe 1052 and the first air pipe 1053 located at the outer end surface of the female fixing plate 1021 of the female joint 102 of the inclination drill rod 10 and each bare drill rod 10". The various pipelines in the inner cavity of the first drill rod assembly 1 and the second drill rod assembly 1' are connected, effectively avoiding the problems of slurry string movement, gas leakage, etc., improving the pipeline sealing performance, and effectively improving the safety performance of the mixing pile construction.
[0080] The outer end surface of the male fixing plate 1011 of the male connector 101 has a verticality deviation of less than or equal to 0.08-0.10 mm with the hollow main shaft 302 of the reduction box 30, the unit drill rod 10', the inclinometer drill rod 10, the light drill rod 10" and the axial center line of the drilling tool 60. The outer end surface of the female fixing plate 1021 of the female connector 102 has a verticality deviation of less than or equal to 0.08-0.10 mm with the docking flange 305 of the reduction box 30, the unit drill rod 10', the inclinometer drill rod 10, and the light drill rod 10" axial center line. The outer end surface of the flange sink 3056 of the docking flange 305 of the reduction box 30 has a verticality deviation of less than or equal to 0.08-0.10 mm with the axial center line of the docking flange 305. This makes it easier to install the sealing gaskets when the upper and lower drill pipes and drill pipes and drill tools are connected, ensuring that the force is evenly distributed under compression, effectively improving the sealing performance at the joints between the drill pipes and drill pipes and drill tools, preventing cement slurry leakage and compressed gas leakage, and improving the safety performance of drilling and excavation construction.
[0081] The groups of stirring blades 606 of the drilling tools between the first drill rod assembly 1 and the second drill rod assembly 1', and between the adjacent second drill rod assemblies 1' are arranged in an up-down staggered manner, so that the circular arc trajectories formed by the groups of stirring blades 606 of the drilling tools 60 have a certain overlap during the rotation of the drilling tools 60. In this way, it is ensured that the mixing pile drilling rig sprays grout to the surrounding soil through the upper and lower grouting ports and the bottom jets air at different stages when the drilling rod is lowered and lifted, further promoting the full mixing of the surrounding soil and cement slurry, and ensuring that the pile body homogeneity and strength are consistent from top to bottom after drilling and mixing. The unit drill rods 10' of the first drill rod assembly 1 and the second drill rod assembly 1' are supported by multiple guide brackets 7' arranged vertically therewith, and the side ends of the guide brackets 7' are placed on the column guide rails of the external pile frame and are suspended below the reduction box 30 of the power head 3 through iron chain connection; the drilling tools 60 of the first drill rod assembly 1 and the second drill rod assembly 1' are supported by multiple drill rod support brackets 7 arranged vertically therewith. In this way, it is effectively ensured that the rotation of each drill rod assembly is always stable and the guidance is reliable during the drilling and mixing operations of the mixing pile drilling rig, thereby ensuring the quality of the pile wall formed by the mixing pile drilling rig.
[0082] The azimuth detection device 80 is arranged at a docking flange 305 below the reduction box 30, and the docking flange is fixedly mounted on the first drill rod assembly 1; the encoder 801 is fixedly mounted on the mounting frame 803, and a pinion 805 is fixedly mounted on its rotating shaft; after the mounting frame 803 and the enclosure 804 are fixedly mounted below the reduction box 30, the main shaft flange 304 and the docking flange 305 of the reduction box 30 which are mounted on the hollow main shaft 302 are enclosed therein; the pinion 805 is meshed with the measuring gear 2055 of the docking flange 305, and the horizontal azimuth angle of the first drill rod assembly 1 during rotation is transmitted to the operation control system through a cable.
[0083] The depth sensor is installed on the external pile frame column of the suspended mixing pile drilling rig to detect the drilling depth in real time and transmit it to the operation control system through an external data line.
[0084] The operation control system displays the drill rod inclination on the display screen by performing software operation, superposition and compensation on the drilling depth collected by the depth sensor, the upper and lower end deflection angles of the first drill rod assembly 1 collected by the first inclinometer 104 and the second inclinometer 104', and the horizontal azimuth of the first drill rod assembly 1 detected by the azimuth detection device 80. In this way, the operator can monitor the drill rod deflection of the mixing pile drilling rig in real time. If the deviation value exceeds the design requirement, the operator can take corresponding measures to correct the deviation in time, thereby ensuring the pile forming accuracy requirement of the mixing pile drilling rig.
[0085] The present invention can improve the sealing performance of each slurry pipe and air pipe in the inner cavity of each drill rod assembly of the mixing pile drilling rig, and prevent the problems of slurry leakage and gas leakage after each drill rod assembly is docked with the hollow main shaft of the reduction box. The deflection of the drill rod assembly during rotation is effectively monitored and transmitted by the inclinometer, which is convenient for the operator to take correction measures to meet the vertical accuracy of the mixing pile drilling rig after drilling and excavating the pile. Multiple slurry pipes, air pipes and grouting ports are arranged in the inner cavity of each drill rod assembly. The operator can operate the grouting system through the external construction control system, and the lower grouting port is used to spray grout to the surrounding soil when each drill rod assembly is drilled down with the power head, and the upper grouting port is used to spray grout to the surrounding soil when it is lifted up, and compressed air is sprayed through the bottom jet port of each drill rod assembly, which further promotes the surrounding soil and cement slurry to be fully and evenly mixed, and ensures that the pile body homogeneity and strength are consistent after mixing, effectively improves the construction efficiency of the mixing pile, and greatly reduces the construction cost.
[0086] Various changes and improvements may be made to the present invention without departing from the overall concept of the present invention. However, as long as they are identical or equivalent to the present invention, they also fall within the protection scope of the present invention.
Claims
1. A multi-tube mixing pile drilling rig, comprising: A power head (3) having a top drive mechanism (31), a frame (32) including a guide plate (321) and a lifting pulley block (322), and a reduction box (30), three slurry-gas rotary joints (20), a slurry-line rotary joint (20'), an orientation detection device (80) including an encoder (801), a pinion (805), a mounting frame (803) and a cover (804); a set of first drill pipe assemblies (1), three sets of second drill pipe assemblies (1'), a sealing gasket (50) including a sealing gasket body (500) and three upper convex lip rings (501) with upper steel sleeves (5011), a plurality of drill pipe support frames (7), a guide bracket (7'), a depth sensor and an operation control system, wherein: The reduction box (30) comprises a box body (300), a box cover (301), four hollow main shafts (302) having a first main shaft grouting channel (3021), a second main shaft grouting channel (3022), a main shaft air injection channel (3023) and a main shaft counterbore (3026), two input shafts, a main shaft flange (304) connected to the lower end of each hollow main shaft (302), a docking flange (305) comprising a female joint (102), a first flange grouting pipe (3051), a second flange grouting pipe (3052), a first flange air pipe (3053), a measuring gear (2055) and a flange counterbore (3056); wherein the female joint (102) comprises a female fixing plate (1021) located at the bottom of its inner groove and having a female plate through hole (1022); The slurry-gas rotary joint (20) comprises a support frame (200), a lower rotating shaft (201), an upper rotating shaft (202) including an upper shaft air supply hole (2023) located therein and an upper shaft shoulder (2024) at the lower end, a rotating shaft outer sleeve (204), an upper sleeve cover (205), a lower sleeve cover (206), an upper connecting shaft (207), an upper bracket (208), a transition joint (209), a rotary air injection joint (210), an air supply pipe (2101) and a diverter block (2102); wherein: the lower rotating shaft (201) comprises a first lower shaft grouting hole (2011), a second lower shaft grouting hole (2012), a lower shaft air injection hole (2013), a first lower shaft grouting hole (2011) and a second lower shaft grouting hole (2012) respectively connected to each other; The shaft cross grout channel (20111) and the second lower shaft cross grout channel (20121) also include a lower shaft countersunk hole (2014) located at the upper end thereof and a lower shaft docking cover (2015) located at the outer wall thereof; the shaft sleeve (204) includes a first grouting ring groove (2041) and a second grouting ring groove (2042) located at the inner wall thereof, a plurality of sleeve ring grooves (2043) and sleeve grooves (2044) with oil supply nozzles, a sleeve countersunk hole (2045) located at the upper end thereof, a first grouting hole (20411) and a second grouting hole (20421) located at the outer wall thereof and respectively connected to the first grouting ring groove (2041) and the second grouting ring groove (2042), and also includes a first locking hole (2046) and a second locking hole (2047) located at the outer wall thereof; The pulp line rotary joint (20') comprises a support frame (200) including a first stop claw (2006), a first stop claw (2007) and a support frame flange (2008) located at the bottom, a lower rotating shaft (201), an upper rotating shaft (202), a rotating shaft sleeve (204), an upper cover (205) including a first upper cover countersunk hole (2051) and a second upper cover countersunk hole (2052), and a lower cover (2061) including a first lower cover countersunk hole (2062) and a second lower cover countersunk hole (2063). 2062), an upper connecting shaft (207), an upper bracket (208) including a bracket ring (2081), a fixed vertical plate (2082) located on one side of the bracket ring, a transition joint (209) and a slipping electric ring (211); wherein the slipping electric ring (211) comprises an outer cable (2112) connected to the outer ring of the slipping electric ring, an inner cable (2111) led out from the inner ring of the slipping electric ring (211), and a pressing plate (2113); The first drill rod assembly (1) comprises a plurality of unit drill rods (10'), an inclination drill rod (10) and a drilling tool (60); wherein the unit drill rod (10') comprises a male joint (101), a female joint (102) and a third internal pipeline (105') comprising a fifth slurry pipe (1051'), a sixth slurry pipe (1052'), a third air pipe (1053') and a plurality of third pipeline racks (1054'); and the inclination drill rod (10) comprises a male joint (101), a female joint (102), an upper grouting port (103), a curved plate (1041), a plate support (1042) and a first sensor (1054'). 043), a first inclinometer (104) including a first slurry pipe (1051), a second slurry pipe (1052), a first air pipe (1053) and a plurality of first pipeline racks (1054); the drilling tool (60) includes a male joint (101), a lower shotcrete outlet (603), a second inclinometer (605) including a third slurry pipe (6052), a second air pipe (6053) and a plurality of second pipeline racks (6054), an air jet outlet (609), a plurality of stirring blades (606) including blades (6061) and blade seats (6062), and a cutting blade (607); The second drill rod assembly (1') comprises a multi-section unit drill rod (10'), a bare drill rod (10") and a drilling tool (60); wherein the unit drill rod (10') comprises a male joint (101), a female joint (102) and a third internal pipeline (105') comprising a fifth slurry pipe (1051'), a sixth slurry pipe (1052'), a third air pipe (1053') and a plurality of third pipeline racks (1054'); the bare drill rod (10") comprises a male joint (101), a female joint (102), an upper grouting port (103) comprising a first slurry pipe The drilling tool (60) comprises a first internal pipeline (105) including a third slurry pipe (1051), a second slurry pipe (1052), a first air pipe (1053) and a plurality of first pipeline racks (1054); the drilling tool (60) comprises a male joint (101), a lower shotcrete port (603), a second internal pipeline (605) including a third slurry pipe (6052), a second air pipe (6053) and a plurality of second pipeline racks (6054), an air jet port (609), a plurality of groups of stirring blades (606) including blades (6061) and blade seats (6062), and a cutting blade (607); Features: The frame (32) of the power head (3) is fixed to the cover (301) of the gear box (30), and is placed on the column guide rail of the external pile frame through its guide plate (321). Its lifting pulley group (322) is connected to the wire rope led out of the external pile frame winch; the four hollow main shafts (302) of the reduction box (30) are arranged in a straight line along the transverse direction of the box body (300) of the reduction box (30), and are arranged in a manner that both ends extend out of the reduction box (30), the upper end of which extends out of the box cover (301) and is located in each end ring (306), and the lower end of which extends out of the box body (300) and is installed after being fitted with the main shaft flange (304). The first main shaft grouting channel (3021), the second main shaft grouting channel (3022), and the main shaft air injection channel (3023) of the hollow main shaft (302) are arranged in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other, and their upper end faces are all located at the main shaft counterbore (3026) of the hollow main shaft (302); the two input shafts are arranged on the gear box (30) on one side of the four hollow main shafts, and they are respectively meshed with the four hollow main shafts (302) through gear transmission in the inner cavity of the gear box (30) to output power; the top drive mechanism (31) is respectively arranged at the upper end of each input shaft; The three slurry-gas rotary joints (20) and one slurry-line rotary joint (20') are arranged above the four hollow main shafts (302) of the reduction box (30); they all pass through the end ring (306) of the reduction box (30) through their lower rotating shafts (201) to reach the upper end of the hollow main shafts (302); the first lower shaft grouting hole (2011), the second lower shaft grouting hole (2012) and the lower shaft gas injection hole (2013) of the lower rotating shaft (201) are arranged in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axes are parallel to each other; the first lower shaft grouting hole (2011) and the second lower shaft grouting hole (2012) are respectively arranged in the lower rotating shaft (201) and are connected to the first lower shaft transverse slurry channel (20111) and the second lower shaft transverse slurry channel (20112). The first lower shaft transverse grouting channel (20111) and the second lower shaft transverse grouting channel (20121) are connected with the first grouting ring groove (2041) and the second grouting ring groove (2042) of the shaft sleeve (204) respectively; the lower end of the lower shaft (201) is placed in the main shaft counterbore (3026) of the hollow main shaft (302); its first lower shaft grouting hole (2011), the second lower shaft grouting hole (2012) and the lower shaft air injection hole (2013) are respectively connected with the first main shaft grouting channel (3021), the second main shaft grouting channel (3022) and the main shaft air injection channel (3023) of the hollow main shaft (302); the lower shaft docking cover (2015) is fixed to the hollow main shaft (3026) by screws. 302), the lower rotating shaft (201) and the hollow main shaft are connected as one; the first lower sleeve hole groove (2061) and the second lower sleeve hole groove (2062) of the lower sleeve cover (206) are respectively installed with bearings and skeleton oil seals, and then sleeved on the installation position on the lower rotating shaft (201); the rotating shaft outer sleeve (204) is sleeved on the lower rotating shaft (201) and is tightly connected with the lower sleeve cover (206); the outer sleeve ring groove (2043) and the outer sleeve groove (2044) are respectively installed with O-type sealing rings and lubricating grease; the first grouting hole (20411) and the second grouting hole (20421) of the rotating shaft outer sleeve (204) are respectively connected with the first grouting ring groove (2041) and the second grouting ring groove (2042) in the rotating shaft outer sleeve (204). The upper end of the upper rotating shaft (202) is connected to the upper end of the lower rotating shaft (201), and the other end is connected to the external slurry delivery pipeline, and the proportioned cement slurry is pumped into the upper rotating shaft (201) by the external grouting system; the upper rotating shaft (202) is placed in the lower shaft counterbore (2014) of the lower rotating shaft (201) through its upper shaft shoulder (2024), and its upper shaft air delivery hole (2023) is arranged obliquely and is connected with the lower shaft air injection hole (2013) of the lower rotating shaft (201); the upper end surface of the upper rotating shaft (202) is fixed with a transition joint (209); the upper connecting shaft (207) is placed on the upper end surface of the transition joint (209) through the upper shaft hole shoulder (2071) located at the bottom thereof, and then fixed to the upper rotating shaft (202) by screws, so that the upper connecting shaft (207), the transition joint (209) and the upper rotating shaft (202) are connected as a whole;The through hole of the upper connecting shaft (207) is connected with the through hole of the transition joint (209) and the upper shaft air supply hole (2023) of the upper rotating shaft (202); the first lower upper sleeve hole groove (2061) and the second upper sleeve hole groove (2062) of the upper sleeve cover (205) are respectively installed with bearings and skeleton oil seals, and then pass through the upper connecting shaft (207) and the transition joint (209) and are fixed to the upper end surface of the rotating shaft sleeve (204); the upper bracket (208) is fixed to the upper sleeve cover (205) through the bracket ring (2081); the fixed vertical plate (2082) is fixed to The support frame (200) is respectively arranged on the left and right sides of each pulp-gas rotary joint (20) and pulp-line rotary joint (20'), and the first stop claw (2006) and the first stop claw (2007) of the support frame are respectively placed in the first locking hole (2046) and the second locking hole (2047) on the outer wall of the rotating shaft sleeve (204) of each pulp-gas rotary joint (20) and the pulp-line rotary joint (20'); the support frame flange (2008) is fixedly mounted on each installation of the box cover (301) of the reduction box (30). The slurry-gas rotary joint (20) and the slurry-line rotary joint (20') are fixedly mounted on the upper end of the hollow output shaft (302); the rotary gas injection joint (210) of the slurry-gas rotary joint (20) is fixedly mounted on the upper connecting shaft (207); the diverter block (2102) is fixedly mounted on the fixed vertical plate (2082); the air supply pipe (2101) connects the rotary gas injection joint (210) and the diverter block (2102); the sliding electric ring (211) of the slurry-line rotary joint (20') is sleeved on the upper cover (205) through its inner ring; the pressure The plate (2083) is fixed on the end surface of the sliding electric ring (211), and the other end is fastened to the fixed vertical plate (2082); the inner cable (2111) passes through the through hole of the upper connecting shaft (207), the through hole of the transition joint (209), the upper shaft air supply hole (2023) of the upper rotating shaft (202), the lower shaft air injection hole (2013) of the lower rotating shaft (201), and the main shaft air injection channel (3023) of the hollow main shaft (302), and then enters the multi-section unit drill rod (10') of the first drill rod assembly (1), the inclination drill rod (10) in turn, and then connects to the first inclination measuring device (104); The first set of drill rod assemblies (1) and the three sets of second drill rod assemblies (1') are respectively inserted into the female joints (102) of the docking flanges (305) fixed at the lower ends of the hollow main shafts (302) of the reduction box (30) to complete the assembly of the drill rods and drilling tools; The first drill pipe assembly (1) is formed by butt-jointing a plurality of unit drill pipes (10'), an inclinometer drill pipe (10) and a drilling tool (60); the male plate through holes (1012) of the male fixing plate (1011) of the male joint (101) of the unit drill pipe (10') are provided with three male plate through holes (1012), which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate (1011); the female plate through holes (1022) of the female fixing plate (1021) of the female joint (102) are provided with three female plate through holes (1022), which are arranged in an equilateral triangle symmetrical manner in the radial direction of the female fixing plate (1021); the third built-in pipeline (105') is arranged in the inner cavity of the unit drill pipe (10') through a plurality of third pipeline racks (1054'); the third built-in pipeline (105') is provided ... The fifth slurry pipe (1051'), the sixth slurry pipe (1052'), and the third air pipe (1053') are arranged in the inner cavity of the unit drill pipe (10') in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other; the third pipeline rack (1054') is provided with three third pipe rack through holes (10541') arranged in a manner that their radial directions are equilateral triangle symmetrical; the fifth slurry pipe (1051'), the sixth slurry pipe (1052'), and the third air pipe (1053') are respectively passed through the three third pipe rack through holes (10541') of the third pipeline rack (1054') and then fixed in the inner cavity of the unit drill pipe (10'); the fifth slurry pipe (1051'), the sixth slurry pipe (1052'), and the third air pipe (1053') are respectively passed through the three third pipe rack through holes (10541') of the third pipeline rack (1054') and fixed in the inner cavity of the unit drill pipe (10'); The upper end of the third air pipe (1053') is respectively placed in three male plate through holes (1012) of the male fixing plate (1011) of the male joint (101) and then welded and fixed. The male fixing plate is welded and fixed to the end surface of the male joint (101); the lower ends of the fifth slurry pipe (1051'), the sixth slurry pipe (1052') and the third air pipe (1053') are placed in three female plate through holes (1022) of the female fixing plate (1021) of the female joint (102) and then welded and fixed. The female fixing plate is welded and fixed to the bottom of the inner groove of the female joint (102); the male fixing plate (1011) of the male joint (101) of the inclination measuring drill pipe (10) is provided with three male plate through holes (1012), which are located in the male fixing plate (1011). The female fixing plate (1021) of the female joint (102) is arranged in an equilateral triangle symmetrical manner in the radial direction; the female plate through holes (1022) of the female fixing plate (1021) are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the female fixing plate (1021); the upper grouting port (103) of the inclination measuring drill rod (10) is arranged on its outer wall; the first built-in pipeline (105) of the inclination measuring drill rod (10) is arranged in the inner cavity of the inclination measuring drill rod (10) through a plurality of first pipeline racks (1054); the first slurry pipe (1051), the second slurry pipe (1052), and the first air pipe (1053) of the first built-in pipeline are arranged in the inner cavity of the inclination measuring drill rod (10) in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other;The first slurry pipe (1051) is connected to the grouting port (103) in the inner cavity of the inclination measuring drill pipe (10) through a short curved pipe (10511); the first pipeline rack (1054) is provided with three first pipeline rack through holes (10541) arranged symmetrically in an equilateral triangle in its radial direction; the first slurry pipe (1051), the second slurry pipe (1052) and the first air pipe (1053) are respectively passed through the three first pipeline rack through holes (10541) of the first pipeline rack (1054) and then fixed in the inner cavity of the inclination measuring drill pipe (10); the upper ends of the first slurry pipe (1051), the second slurry pipe (1052) and the first air pipe (1053) are respectively placed in the three male plate through holes (1012) of the male fixing plate (1011) and then The male fixing plate is welded and fixed to the end face of the male connector (101); the lower ends of the second slurry pipe (1052) and the first air pipe (1053) are placed in two mother plate through holes (1022) of the female fixing plate (1021) and then welded and fixed; the female fixing plate is welded and fixed to the bottom of the inner groove of the female connector (102); the first inclinometer (104) is fixed to the outer wall of the inclinometer drill rod (10) below the upper grouting port (103) through the arc plate (1041); the plate support (1042) is located on the inner side of the arc plate (1041); the sensor (1043) of the first inclinometer (104) is fixed to the plate support (1042) and is connected to the sliding electric ring of each air pipe passing through the inner cavity of the first drill rod assembly (1). The inner cable (2111) of the drilling tool (211) is connected; the male plate through holes (1012) of the male fixing plate (1011) of the male connector (101) of the drilling tool (60) are provided with three, which are arranged in an equilateral triangle symmetrical manner in the radial direction of the male fixing plate (1011); the lower shotcrete port (603) is provided at the bottom end of the outer wall of the drilling tool tube (608) of the drilling tool (60); the jet port (609) is provided at the bottom of the drilling tool tube (608) of the drilling tool (60); the second built-in pipeline (605) of the drilling tool (60) is provided in the inner cavity of the drilling tool (60) through a plurality of second pipeline racks (6054); the second pipeline rack (6054) is provided with three arranged in an equilateral triangle symmetrical manner in its radial direction. The third slurry pipe (6052) and the second air pipe (6053) of the second built-in pipeline (605) respectively pass through two second pipe rack through holes (60541) of the plurality of second pipeline racks (6054) and are fixed to the inner cavity of the stirring drill (60); the upper ends of the third slurry pipe (6052) and the second air pipe (6053) are respectively placed in two male plate through holes (1012) of the male fixing plate (1011) and then welded and fixed, and the male fixing plate is welded and fixed to the end surface of the male joint (101); the lower end of the third slurry pipe (6052) is connected to the lower grouting port (603) through the lower bent slurry pipe (60521); the lower end of the second air pipe (6053) is connected to the air jet port (609);The multiple groups of stirring blades (606) of the drilling tool (60) are symmetrically arranged on the outer wall of the drilling tool tube (608) of the drilling tool (60) in an interlaced manner in an upper and lower manner; the blades (6061) of each group of the stirring blades (606) are installed on the blade seat (6062) through a pin shaft; the cutting blades (660) of the drilling tool (60) are symmetrically arranged on the bottom outer wall of the drilling tool tube (608) of the drilling tool (60); the lower grouting port (603) is arranged at the bottom end of the outer wall of the drilling tool tube (608); and the air jet port (609) is arranged at the bottom of the drilling tool tube (608); The second drill rod assembly (1') is formed by butt-jointing a multi-section drill rod (10'), a bare drill rod (10") and a drilling tool (60); the first built-in pipeline (105) of the bare drill rod (10") is arranged in the inner cavity of the bare drill rod (10") through a plurality of first pipeline racks (1054); the first slurry pipe (1051), the second slurry pipe (1052) and the first air pipe (1053) of the first built-in pipeline are arranged in the inner cavity of the bare drill rod (10") in a manner that their cross-sectional directions are equilateral triangle symmetrical and their axial directions are parallel to each other; the first pipeline rack (1054) is provided with three first pipe rack through holes (10541) arranged in a manner that their radial directions are equilateral triangle symmetrical; the first slurry pipe (1051), the second slurry pipe (1052) and the first air pipe (1053) respectively pass through the first pipeline rack (1054); 4) and then fixed in the inner cavity of the bare drill rod (10”); the first slurry pipe (1051) is connected to the upper grouting port (103) in the inner cavity of the bare drill rod (10”) through a short curved pipe (10511); the upper ends of the first slurry pipe (1051), the second slurry pipe (1052) and the first air pipe (1053) are respectively placed in the three male plate through holes (1012) of the male fixing plate (1011) of the male joint (101) and then welded and fixed, and the male fixing plate is welded and fixed to the end surface of the male joint (101); the lower ends of the second slurry pipe (1052) and the first air pipe (1053) are placed in the two female plate through holes (1022) of the female fixing plate (1021) of the female joint (102) and then welded and fixed, and the female fixing plate is welded and fixed to the bottom of the inner groove of the female joint (102); The three upper convex lip rings (501) of the sealing gasket (50) are arranged in an equilateral triangle symmetrical manner on the upper end surface of the sealing gasket body (500), and the upper steel sleeve (5011) is arranged in the hole of the upper convex lip ring (501); the sealing gasket (50) is respectively arranged between the lower rotating shaft (201) of each slurry-gas rotary joint (20) and the slurry-line rotary joint (20') and the main shaft counterbore (3026) of the hollow main shaft (302) of the reduction box (30) and between each hollow main shaft (302) and the docking flange (305), and their three upper convex lip rings (501) respectively enters into the first lower shaft grouting hole (2011), the second lower shaft grouting hole (2012) and the lower shaft air injection hole (2013) at the lower end of each lower rotating shaft (201) and into the first main shaft grouting channel (3021), the second main shaft grouting channel (3022) and the main shaft air injection channel (3023) at the lower end of each hollow main shaft (302); when the first drill rod assembly (1) and each second drill rod assembly (1') are connected at the female joint (102) of each docking flange (305) of the reduction box (30), the sealing gasket (50) are respectively arranged between each docking flange (305) and the unit drill rod (10'), between the unit drill rod (10') and the inclination drill rod (10), and between each unit drill rod (10') and the bare drill rod (10"), and the three upper convex lip rings (501) are respectively arranged in the holes of the first flange slurry pipe (3051), the second flange slurry pipe (3052), and the first flange air pipe (3053) at the flange sink (3056) of each docking flange (305), and the female fixing plate (1021) of the female joint (102) of each unit drill rod (10'). ) in the holes of the fifth slurry pipe (1051'), the sixth slurry pipe (1052'), and the third air pipe (1053') at the end surface of the inclination drill rod (10) and the drilling tool (60), and between each bare drill rod (10") and the drilling tool (60), and two of the three upper convex lip rings (501) thereof respectively enter the holes of the second slurry pipe (1052) and the first air pipe (1053) at the outer end surface of the female fixing plate (1021) of the female joint (102) of the inclination drill rod (10) and each bare drill rod (10"); The verticality deviation between the outer end surface of the flange sink (3056) of the docking flange (305) of the reduction box (30) and the axial center line of the docking flange (305) is less than or equal to 0.08-0.10 mm; The groups of stirring blades (606) of the drilling tools between the first drilling rod assembly (1) and the second drilling rod assembly (1'), and between adjacent second drilling rod assemblies (1') are arranged in an up-down staggered manner, so that the circular arc trajectories formed by the groups of stirring blades (606) of the drilling tools (60) have a certain overlap during the rotation of the drilling tools (60); the unit drilling rods (10') of the first drilling rod assembly (1) and the second drilling rod assembly (1') are supported by a plurality of guide brackets (7') arranged vertically therewith, the side ends of the guide brackets (7') are placed on the column guide rails of the external pile frame, and are connected and suspended below the reduction box (30) of the power head (3) by an iron chain; the drilling tools (60) of the first drilling rod assembly (1) and the second drilling rod assembly (1') are supported by a plurality of drill rod support brackets (7) arranged vertically therewith; The outer end surface of the male fixing plate (1011) of the male joint (101) has a verticality deviation of less than or equal to 0.08-0.10 mm with the hollow main shaft (302) of the reduction box (30), the unit drill rod (10'), the inclination drill rod (10), the bare drill rod (10") and the axial center line of the drilling tool (60); The verticality deviations of the outer end surface of the female fixing plate (1021) of the female joint (102) and the axial center lines of the docking flange (305) of the reduction box (30), the unit drill rod (10'), the inclination drill rod (10), and the smooth drill rod (10") are all less than or equal to 0.08-0.10 mm; The azimuth detection device (80) is arranged at a docking flange (305) below the reduction box (30), and the docking flange is fixedly mounted on the first drill pipe assembly (1); the encoder (801) is fixedly mounted on a mounting frame (803), and a pinion (805) is fixedly mounted on the rotating shaft of the encoder (801); the mounting frame (803) and the enclosure (804) are fixedly mounted below the reduction box (30), and the main shaft flange (304) and the docking flange (305) of the reduction box (30) are enclosed therein; the pinion (805) is meshed with a measuring gear (2055) of the docking flange (305), and the horizontal azimuth angle of the first drill pipe assembly (1) during rotation is transmitted to the operation control system through a cable; The depth sensor is installed on the external pile frame column of the suspended mixing pile drilling rig to detect the drilling depth in real time and transmit it to the operation control system through an external data line; The operation control system displays the drill rod inclination on a display screen by performing software operation, superposition and compensation on the drilling depth collected by the depth sensor, the upper and lower end deflection angles of the first drill rod assembly (1) collected by the first inclinometer (104) and the second inclinometer (104'), and the horizontal azimuth of the first drill rod assembly (1) detected by the azimuth detection device (80).
Citation Information
Patent Citations
Deep cement stirring processor
CN106320321A
Stirring stake drilling machine
CN207062940U
Multi-pipe mixing pile drilling machine
CN215165521U
LU43672A1