A coordinated control method and device for peak shaving and valley filling and primary frequency modulation

By calculating the primary frequency regulation target power range corresponding to the frequency of the grid connection point, the target power of the energy storage system is judged and determined, which solves the problem of energy storage equipment being unable to achieve peak shaving and valley filling when meeting primary frequency regulation conditions, and improves the efficiency of peak shaving and valley filling. .

CN113131499BActive Publication Date: 2024-10-18HEFEI SUNGROW RENEWABLE ENERGY SCI & TECH CO LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202110429509.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-04-21
Publication Date
2024-10-18
Estimated Expiration
2041-04-21

AI Technical Summary

Technical Problem

When the energy storage equipment implements the peak shaving and valley filling strategy, once the primary frequency modulation triggering condition is met, the control target of peak shaving and valley filling cannot be achieved, resulting in the energy storage system being unable to achieve the goals of peak shaving and valley filling and primary frequency modulation at the same time.

Method used

By calculating the primary frequency regulation energy storage target power range corresponding to the frequency of the grid connection point, it is judged whether the peak-cutting and valley-filling energy storage adjustment amount is within this range, and the target power of the energy storage system is determined based on the judgment result, so that it can meet the primary frequency regulation target. Basically, it is as close as possible to the target power of peak clipping and valley filling.

Benefits of technology

The peak-shaving and valley-filling efficiency of the energy storage system is improved, so that it can still be close to the peak-shaving and valley-filling target power under primary frequency regulation conditions, and the overall control effect of the system is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113131499B_ABST
    Figure CN113131499B_ABST
Patent Text Reader

Abstract

The present invention provides a coordinated control method and device for peak shaving and valley filling and primary frequency modulation. During the process of an energy storage system executing a peak shaving and valley filling strategy, if the primary frequency modulation triggering condition is met, the primary frequency modulation energy storage target power range corresponding to the grid connection point frequency is calculated, and it is determined whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency modulation energy storage target power range. The target power of the energy storage system is determined based on the judgment result. On the basis of meeting the primary frequency modulation target, the target power of the energy storage system is made as close as possible to the target power of peak shaving and valley filling, thereby improving the peak shaving and valley filling efficiency of the energy storage system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electric power technology, and more specifically, to a coordinated control method and device for peak shaving and valley filling and primary frequency modulation. Background Art

[0002] Peak shaving and valley filling and primary frequency modulation are two commonly used energy storage device control strategies. Peak shaving and valley filling is to use energy storage devices to store electricity when electricity prices are low, and control the energy storage devices to discharge when electricity prices are high, so as to earn the difference in electricity prices and reduce the peak power consumption of the power grid. Primary frequency modulation is to control the energy storage devices to respond to primary frequency modulation when the power grid frequency deviates from the rated range, so as to stabilize the power grid frequency within the rated range and improve the stability of the power grid system.

[0003] At present, when the energy storage device executes the peak shaving and valley filling strategy, once the primary frequency modulation trigger condition is met, the energy storage device no longer executes the peak shaving and valley filling strategy, but only responds to the primary frequency modulation, and the control target of peak shaving and valley filling cannot be achieved. Summary of the invention

[0004] In view of this, the present invention provides a coordinated control method and device for peak shaving and valley filling and primary frequency regulation, which makes the target power of the energy storage system as close as possible to the target power of peak shaving and valley filling on the basis of meeting the primary frequency regulation target.

[0005] In order to achieve the above-mentioned invention object, the specific technical solution provided by the present invention is as follows:

[0006] A coordinated control method for peak shaving and valley filling and primary frequency modulation, comprising:

[0007] When the energy storage system executes the peak shaving and valley filling strategy, if the primary frequency regulation triggering condition is met, the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency is calculated;

[0008] Determine whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range;

[0009] The target power of the energy storage system is determined according to the judgment result.

[0010] Optionally, the calculation of the primary frequency modulation energy storage target power range corresponding to the grid connection point frequency includes:

[0011] Get the frequency of the grid connection point;

[0012] Determine whether the frequency of the grid connection point is within the adjustment range of the system frequency dead zone;

[0013] When the frequency at the grid connection point is less than the downward adjustment boundary of the system frequency dead zone, the target power range of the primary frequency regulation energy storage for upward adjustment is calculated according to the calculation formula of the primary frequency regulation droop curve and the downward adjustment boundary of the system frequency dead zone;

[0014] When the frequency at the grid connection point is greater than the upward adjustment boundary of the system frequency dead zone, the target power range of the primary frequency regulation energy storage for downward adjustment is calculated based on the calculation formula of the primary frequency regulation droop curve and the upward adjustment boundary of the system frequency dead zone.

[0015] Optionally, the calculation of the primary frequency modulation energy storage target power range for upward adjustment according to the droop curve calculation formula of the primary frequency modulation and the downward adjustment boundary of the system frequency dead zone includes:

[0016] The first and second FM components of the up-regulation are calculated according to the following formula:

[0017] ΔP1=(fL-f)*P e / (f N *δ)

[0018] ΔP2=(fn-f)*P e / (f N *δ)

[0019] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fL is the downward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0020] The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted upward is determined as the first target power of the primary frequency modulation energy storage adjusted upward, and the first target power of the primary frequency modulation energy storage adjusted upward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted upward;

[0021] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted upward is determined as the second target power of the primary frequency modulation energy storage adjusted upward. The second target power of the primary frequency modulation energy storage adjusted upward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted upward.

[0022] Optionally, the calculation of the primary frequency modulation energy storage target power range for downward adjustment according to the droop curve calculation formula of the primary frequency modulation and the upward adjustment boundary of the system frequency dead zone includes:

[0023] The first FM component and the second FM component of the down-regulation are calculated according to the following formula:

[0024] ΔP1=(fn-f)*P e / (f N *δ)

[0025] ΔP2=(fH-f)*P e / (fN *δ)

[0026] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fH is the upward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0027] The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted downward is determined as the first target power of the primary frequency modulation energy storage adjusted downward, and the first target power of the primary frequency modulation energy storage adjusted downward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted downward;

[0028] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted downward is determined as the second target power of the primary frequency modulation energy storage adjusted downward. The second target power of the primary frequency modulation energy storage adjusted downward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted downward.

[0029] Optionally, the lower limit of the primary frequency modulation energy storage target power range is the first target power, and the upper limit is the second target power, and determining the target power of the energy storage system according to the judgment result includes:

[0030] When the peak-shaving and valley-filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range, the peak-shaving and valley-filling target power is determined as the target power of the energy storage system;

[0031] When the peak shaving and valley filling energy storage adjustment amount is less than the first target power, the first target power is determined as the target power of the energy storage system;

[0032] When the peak shaving and valley filling energy storage adjustment amount is greater than the second target power, the second target power is determined as the target power of the energy storage system.

[0033] Optionally, after determining the target power of the energy storage system according to the judgment result, the method further includes:

[0034] Determine whether the target power for peak shaving and valley filling is the discharge power;

[0035] If it is discharge power, the minimum value between the target power of the energy storage system and the maximum dischargeable power is determined as the final target power of the energy storage system;

[0036] If it is charging power, the maximum value between the target power of the energy storage system and the maximum chargeable power is determined as the final target power of the energy storage system.

[0037] A coordinated control device for peak shaving and valley filling and primary frequency modulation, comprising:

[0038] A power range calculation unit, used to calculate the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency if the primary frequency regulation triggering condition is met during the process of the energy storage system executing the peak shaving and valley filling strategy;

[0039] A judging unit, used to judge whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range;

[0040] The target power determination unit is used to determine the target power of the energy storage system according to the judgment result.

[0041] Optionally, the power range calculation unit includes:

[0042] A grid connection point frequency acquisition subunit, used to acquire the grid connection point frequency;

[0043] A judgment subunit, used to judge whether the frequency of the grid connection point is within the adjustment range of the system frequency dead zone;

[0044] The upper regulation power range calculation subunit is used to calculate the upper regulation primary frequency regulation energy storage target power range according to the droop curve calculation formula of the primary frequency regulation and the lower regulation boundary of the system frequency dead zone when the grid connection point frequency is less than the lower regulation boundary of the system frequency dead zone;

[0045] The downward regulation power range calculation subunit is used to calculate the downward regulation primary frequency regulation energy storage target power range according to the primary frequency regulation droop curve calculation formula and the system frequency dead zone's upward boundary when the grid connection point frequency is greater than the system frequency dead zone's upward boundary.

[0046] Optionally, the upper adjustment power range calculation subunit is specifically used to:

[0047] The first and second FM components of the up-regulation are calculated according to the following formula:

[0048] ΔP1=(fL-f)*P e / (f N *δ)

[0049] ΔP2=(fn-f)*P e / (f N *δ)

[0050] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fL is the downward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0051] The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted upward is determined as the first target power of the primary frequency modulation energy storage adjusted upward, and the first target power of the primary frequency modulation energy storage adjusted upward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted upward;

[0052] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted upward is determined as the second target power of the primary frequency modulation energy storage adjusted upward. The second target power of the primary frequency modulation energy storage adjusted upward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted upward.

[0053] Optionally, the down-regulating power range calculation subunit is specifically used to:

[0054] The first FM component and the second FM component of the down-regulation are calculated according to the following formula:

[0055] ΔP1=(fn-f)*P e / (f N *δ)

[0056] ΔP2=(fH-f)*P e / (f N *δ)

[0057] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fH is the upward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0058] The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted downward is determined as the first target power of the primary frequency modulation energy storage adjusted downward, and the first target power of the primary frequency modulation energy storage adjusted downward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted downward;

[0059] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted downward is determined as the second target power of the primary frequency modulation energy storage adjusted downward. The second target power of the primary frequency modulation energy storage adjusted downward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted downward.

[0060] Optionally, the lower limit of the primary frequency modulation energy storage target power range is the first target power, and the upper limit is the second target power, and the target power determination unit is specifically used to:

[0061] When the peak-shaving and valley-filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range, the peak-shaving and valley-filling target power is determined as the target power of the energy storage system;

[0062] When the peak shaving and valley filling energy storage adjustment amount is less than the first target power, the first target power is determined as the target power of the energy storage system;

[0063] When the peak shaving and valley filling energy storage adjustment amount is greater than the second target power, the second target power is determined as the target power of the energy storage system.

[0064] Optionally, the target power determination unit is further used to:

[0065] After determining the target power of the energy storage system according to the judgment result, judging whether the target power of peak shaving and valley filling is the discharge power;

[0066] If it is discharge power, the minimum value between the target power of the energy storage system and the maximum dischargeable power is determined as the final target power of the energy storage system;

[0067] If it is charging power, the maximum value between the target power of the energy storage system and the maximum chargeable power is determined as the final target power of the energy storage system.

[0068] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0069] The present invention discloses a coordinated control method for peak shaving and valley filling and primary frequency modulation. During the process of an energy storage system executing a peak shaving and valley filling strategy, if the primary frequency modulation triggering condition is met, the primary frequency modulation energy storage target power range corresponding to the grid connection point frequency is calculated, and it is judged whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency modulation energy storage target power range. The target power of the energy storage system is determined according to the judgment result. On the basis of meeting the primary frequency modulation target, the target power of the energy storage system is made as close as possible to the target power of peak shaving and valley filling, thereby improving the peak shaving and valley filling efficiency of the energy storage system. BRIEF DESCRIPTION OF THE DRAWINGS

[0070] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0071] Figure 1 A schematic diagram of the structure of a photovoltaic storage system disclosed in an embodiment of the present invention;

[0072] Figure 2 A schematic flow chart of a coordinated control method for peak shaving and valley filling and primary frequency modulation disclosed in an embodiment of the present invention;

[0073] Figure 3A flow chart of a method for calculating a primary frequency modulation energy storage target power range corresponding to a grid connection point frequency disclosed in an embodiment of the present invention;

[0074] Figure 4 It is a schematic structural diagram of a coordinated control device for peak shaving and valley filling and primary frequency modulation disclosed in an embodiment of the present invention. DETAILED DESCRIPTION

[0075] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0076] The present invention discloses a coordinated control method of peak shaving and valley filling and primary frequency modulation, which is applied to a control device or control system of an energy storage system and is used to coordinately control peak shaving and valley filling and primary frequency modulation of the energy storage system. The energy storage system can be Figure 1 The energy storage system in the photovoltaic storage system shown can also be an energy storage system in a wind power generation system, or an energy storage system in other types of power generation systems, which are not specifically limited here. When the energy storage system implements the peak shaving and valley filling strategy, once the primary frequency regulation triggering condition is met, the energy storage system implements the coordinated control strategy of peak shaving and valley filling and primary frequency regulation. On the basis of the primary frequency regulation target, the target power of the energy storage system is made as close as possible to the target power of peak shaving and valley filling, thereby improving the peak shaving and valley filling efficiency of the energy storage system.

[0077] For details, please refer to Figure 2 This embodiment discloses a coordinated control method for peak shaving and valley filling and primary frequency modulation, comprising the following steps:

[0078] S101: Determine whether a frequency modulation trigger condition is met.

[0079] During the operation of the energy storage system, the grid connection point frequency is monitored in real time to see if it is within the rated range. If the grid connection point frequency deviates from the rated range, the primary frequency regulation trigger condition is met.

[0080] by Figure 1 Taking the photovoltaic storage system shown in the figure as an example, the above-mentioned grid connection point frequency is the total grid connection point frequency of the photovoltaic storage.

[0081] If the primary frequency regulation triggering condition is not met, execute S102: determine the target power of peak shaving and valley filling as the target power of the energy storage system.

[0082] That is to say, when the primary frequency regulation triggering conditions are not met, the energy storage system only implements the peak shaving and valley filling strategy.

[0083] If the primary frequency modulation triggering condition is met, execute S103: calculate the primary frequency modulation energy storage target power range corresponding to the grid connection point frequency.

[0084] The target power range of primary frequency regulation energy storage corresponding to the grid connection point frequency can be calculated based on the system frequency dead zone range in the existing primary frequency regulation strategy, and the grid connection point frequency can be stabilized within the system frequency dead zone range by controlling the target power of the energy storage system.

[0085] Preferably, the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency can also be calculated based on the upper and lower regulation boundaries of the system frequency dead zone, and the grid connection point frequency can be stabilized within the upper and lower regulation boundaries of the system frequency dead zone by controlling the target power of the energy storage system.

[0086] S104: Determine whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range.

[0087] Among them, the peak shaving and valley filling energy storage adjustment amount ΔP=Ps-Ps0, Ps is the target power of peak shaving and valley filling, and Ps0 is the active power of the energy storage system grid connection point.

[0088] S105: Determine the target power of the energy storage system according to the judgment result.

[0089] It should be noted that, since the peak shaving and valley filling energy storage regulation amount and the primary frequency regulation energy storage target power range are comprehensively considered in the process of determining the target power of the energy storage system, the target power of the determined energy storage system is as close to the peak shaving and valley filling target power as possible on the basis of meeting the primary frequency regulation target.

[0090] Specifically, when the peak-shaving and valley-filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range, the peak-shaving and valley-filling target power is determined as the target power of the energy storage system;

[0091] When the peak shaving and valley filling energy storage adjustment amount is less than the first target power, the first target power is determined as the target power of the energy storage system;

[0092] When the peak shaving and valley filling energy storage adjustment amount is greater than the second target power, the second target power is determined as the target power of the energy storage system.

[0093] Furthermore, after determining the target power Pt of the energy storage system according to the judgment result, considering the maximum charge and discharge power of the energy storage system, it is necessary to enter the boundary judgment, with Pmax_discharge representing the maximum dischargeable power as a value > 0, and Pmax_charge representing the maximum chargeable power as a value < 0, then:

[0094] When the target power for peak shaving and valley filling is the discharge power, that is, when Ps>0, the final target power of the energy storage system is Ptt=min(Pt,Pmax_discharge).

[0095] When the target power for peak shaving and valley filling is the charging power, that is, when Ps<0, the final target power of the energy storage system Ptt=max(Pt,Pmax_charge).

[0096] Furthermore, after the final target power of the energy storage system is output, if the primary frequency regulation target is not met due to insufficient capacity of the energy storage system itself, the power of the power generation unit should be limited or increased to achieve the purpose of primary frequency regulation.

[0097] by Figure 1 Taking the photovoltaic storage system shown as an example, when the primary frequency regulation target is not met, the power of the photovoltaic power generation unit in the photovoltaic system should be limited or increased to achieve the purpose of primary frequency regulation.

[0098] The present embodiment discloses a coordinated control method for peak shaving and valley filling and primary frequency regulation. During the process of the energy storage system executing the peak shaving and valley filling strategy, if the primary frequency regulation triggering condition is met, the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency is calculated, and it is determined whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range. The target power of the energy storage system is determined according to the judgment result. On the basis of meeting the primary frequency regulation target, the target power of the energy storage system is made as close as possible to the target power of peak shaving and valley filling, thereby improving the peak shaving and valley filling efficiency of the energy storage system.

[0099] This embodiment provides a specific preferred implementation method of the above embodiment S103: calculating the target power range of primary frequency regulation energy storage corresponding to the grid connection point frequency. It not only stabilizes the grid connection point frequency within the system frequency dead zone by controlling the target power of the energy storage system, but also calculates the target power range of primary frequency regulation energy storage corresponding to the grid connection point frequency by taking into account the upper and lower regulation boundaries. For details, please refer to Figure 3 , a method for calculating the primary frequency modulation energy storage target power range corresponding to the grid connection point frequency disclosed in this embodiment is as follows:

[0100] S201: Obtain the frequency of the grid connection point.

[0101] S202: Determine whether the grid connection point frequency is within the adjustment range of the system frequency dead zone.

[0102] The adjustment range of the system frequency dead zone is [fn-fd, fn+fd], fL=fn-fd, fH=fn+fd.

[0103] fL is the lower adjustment boundary of the system frequency dead zone, fH is the upper adjustment boundary of the system frequency dead zone, fd is the primary frequency modulation dead zone, and fn is 50Hz.

[0104] When the frequency at the grid connection point is less than the downward adjustment boundary of the system frequency dead zone, execute S203: calculate the primary frequency regulation energy storage target power range for upward adjustment according to the droop curve calculation formula of the primary frequency regulation and the downward adjustment boundary of the system frequency dead zone.

[0105] When the frequency of the grid connection point is in the dead zone of the system frequency, S204 is executed: the energy storage system does not respond to the primary frequency modulation.

[0106] When the grid connection point frequency is greater than the upward adjustment boundary of the system frequency dead zone, execute S205: calculate the downward adjustment primary frequency regulation energy storage target power range according to the droop curve calculation formula of the primary frequency regulation and the upward adjustment boundary of the system frequency dead zone.

[0107] The traditional droop curve calculation formula is:

[0108] P=P0-P N (ff d ) / (f N *δ)

[0109] Among them, P is the target power, P0 is the initial value of active power, P N is the startup capacity, f is the grid connection frequency, f d is the primary frequency modulation dead zone, f N is the rated frequency of the system, and δ is the regulation rate of the new energy fast frequency response.

[0110] The power regulation amount is represented by ΔP=P0-P, then ΔP=P N (ff d ) / (f N *δ)

[0111] It can be seen that the traditional droop curve calculation formula only considers that the target power of the energy storage system is controlled to stabilize the grid connection point frequency within the system frequency dead zone. This embodiment provides a droop curve calculation formula based on the primary frequency modulation and the upper adjustment boundary of the system frequency dead zone to calculate the primary frequency modulation energy storage target power range for upper / lower adjustment. The traditional droop curve calculation formula is improved, such as replacing (ff d ), or by adding an adjustment coefficient or adjustment margin to the formula, the target power of the energy storage system can be controlled to stabilize the grid connection point frequency within the upper and lower adjustment boundaries of the system frequency dead zone.

[0112] Specifically, this embodiment provides a method for calculating the primary frequency modulation energy storage target power range for the upper adjustment according to the droop curve calculation formula of the primary frequency modulation and the upper adjustment boundary of the system frequency dead zone:

[0113] The first and second FM components of the up-regulation are calculated according to the following formula:

[0114] ΔP1=(fL-f)*P e / (f N *δ)

[0115] ΔP2=(fn-f)*P e / (f N *δ)

[0116] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fL is the downward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, and δ is the rapid frequency response modulation rate of the new energy.

[0117] The sum of the active power of the energy storage system grid-connected point and the first frequency modulation component of the upward adjustment is determined as the first target power of the primary frequency modulation energy storage of the upward adjustment, that is, Pd1=Ps0+ΔP1, Ps0 is the active power of the energy storage system grid-connected point, and the first target power of the primary frequency modulation energy storage of the upward adjustment is the lower limit of the target power range of the primary frequency modulation energy storage of the upward adjustment.

[0118] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component of the upward adjustment is determined as the second target power of the primary frequency modulation energy storage of the upward adjustment, that is, Pd2=Ps0+ΔP2, Ps0 is the active power of the energy storage system grid-connected point, and the second target power of the primary frequency modulation energy storage of the upward adjustment is the upper limit of the target power range of the primary frequency modulation energy storage of the upward adjustment.

[0119] Accordingly, the following is a method for calculating the target power range of the primary frequency regulation energy storage for the upper adjustment based on the calculation formula of the primary frequency regulation droop curve and the upper adjustment boundary of the system frequency dead zone:

[0120] Specifically, the first frequency modulation component and the second frequency modulation component of the down-regulation are calculated according to the following formula:

[0121] ΔP1=(fn-f)*P e / (f N *δ)

[0122] ΔP2=(fH-f)*P e / (f N *δ)

[0123] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fH is the upward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, Pe is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0124] The sum of the active power of the energy storage system grid-connected point and the first frequency modulation component adjusted downward is determined as the first target power of the primary frequency modulation energy storage adjusted downward, that is, Pd1=Ps0+ΔP1, Ps0 is the active power of the energy storage system grid-connected point, and the first target power of the primary frequency modulation energy storage adjusted downward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted downward;

[0125] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted downward is determined as the second target power of the primary frequency modulation energy storage adjusted downward, that is, Pd2=Ps0+ΔP2, Ps0 is the active power of the energy storage system grid-connected point, and the second target power of the primary frequency modulation energy storage adjusted downward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted downward.

[0126] Based on the peak shaving and valley filling and primary frequency modulation coordinated control method disclosed in the above embodiment, this embodiment correspondingly discloses a peak shaving and valley filling and primary frequency modulation coordinated control device, please refer to Figure 4 , the device comprises:

[0127] The power range calculation unit 100 is used to calculate the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency if the primary frequency regulation triggering condition is met during the process of the energy storage system executing the peak shaving and valley filling strategy;

[0128] A judging unit 200, used to judge whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range;

[0129] The target power determination unit 300 is used to determine the target power of the energy storage system according to the judgment result.

[0130] Optionally, the power range calculation unit 100 includes:

[0131] A grid connection point frequency acquisition subunit, used to acquire the grid connection point frequency;

[0132] A judgment subunit, used to judge whether the frequency of the grid connection point is within the adjustment range of the system frequency dead zone;

[0133] The upper regulation power range calculation subunit is used to calculate the upper regulation primary frequency regulation energy storage target power range according to the droop curve calculation formula of the primary frequency regulation and the lower regulation boundary of the system frequency dead zone when the grid connection point frequency is less than the lower regulation boundary of the system frequency dead zone;

[0134] The downward regulation power range calculation subunit is used to calculate the downward regulation primary frequency regulation energy storage target power range according to the primary frequency regulation droop curve calculation formula and the system frequency dead zone's upward boundary when the grid connection point frequency is greater than the system frequency dead zone's upward boundary.

[0135] Optionally, the upper adjustment power range calculation subunit is specifically used to:

[0136] The first and second FM components of the up-regulation are calculated according to the following formula:

[0137] ΔP1=(fL-f)*P e / (f N *δ)

[0138] ΔP2=(fn-f)*P e / (f N *δ)

[0139] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fL is the downward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0140] The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted upward is determined as the first target power of the primary frequency modulation energy storage adjusted upward, and the first target power of the primary frequency modulation energy storage adjusted upward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted upward;

[0141] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted upward is determined as the second target power of the primary frequency modulation energy storage adjusted upward. The second target power of the primary frequency modulation energy storage adjusted upward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted upward.

[0142] Optionally, the down-regulating power range calculation subunit is specifically used to:

[0143] The first FM component and the second FM component of the down-regulation are calculated according to the following formula:

[0144] ΔP1=(fn-f)*P e / (f N *δ)

[0145] ΔP2=(fH-f)*P e / (f N *δ)

[0146] Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fH is the upward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response;

[0147] The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted downward is determined as the first target power of the primary frequency modulation energy storage adjusted downward, and the first target power of the primary frequency modulation energy storage adjusted downward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted downward;

[0148] The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted downward is determined as the second target power of the primary frequency modulation energy storage adjusted downward. The second target power of the primary frequency modulation energy storage adjusted downward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted downward.

[0149] Optionally, the lower limit of the primary frequency modulation energy storage target power range is the first target power, and the upper limit is the second target power. The target power determination unit 300 is specifically used to:

[0150] When the peak-shaving and valley-filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range, the peak-shaving and valley-filling target power is determined as the target power of the energy storage system;

[0151] When the peak shaving and valley filling energy storage adjustment amount is less than the first target power, the first target power is determined as the target power of the energy storage system;

[0152] When the peak shaving and valley filling energy storage adjustment amount is greater than the second target power, the second target power is determined as the target power of the energy storage system.

[0153] Optionally, the target power determination unit 300 is further configured to:

[0154] After determining the target power of the energy storage system according to the judgment result, judging whether the target power of peak shaving and valley filling is the discharge power;

[0155] If it is discharge power, the minimum value between the target power of the energy storage system and the maximum dischargeable power is determined as the final target power of the energy storage system;

[0156] If it is charging power, the maximum value between the target power of the energy storage system and the maximum chargeable power is determined as the final target power of the energy storage system.

[0157] The present embodiment discloses a coordinated control device for peak shaving and valley filling and primary frequency modulation. During the process of the energy storage system executing the peak shaving and valley filling strategy, if the primary frequency modulation triggering condition is met, the primary frequency modulation energy storage target power range corresponding to the grid connection point frequency is calculated, and it is judged whether the target power of peak shaving and valley filling is within the primary frequency modulation energy storage target power range. The target power of the energy storage system is determined according to the judgment result. On the basis of meeting the primary frequency modulation target, the target power of the energy storage system is made as close as possible to the target power of peak shaving and valley filling, thereby improving the peak shaving and valley filling efficiency of the energy storage system.

[0158] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0159] It should also be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0160] The steps of the method or algorithm described in conjunction with the embodiments disclosed herein may be implemented directly using hardware, a software module executed by a processor, or a combination of the two. The software module may be placed in a random access memory (RAM), a memory, a read-only memory (ROM), an electrically programmable ROM, an electrically erasable programmable ROM, a register, a hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.

[0161] The above-mentioned embodiments may be combined arbitrarily. For the above description of the disclosed embodiments, the features recorded in the embodiments in this specification may be replaced or combined with each other, so that professional and technical personnel in this field can implement or use the present application.

[0162] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A coordinated control method for peak shaving and valley filling and primary frequency modulation, characterized in that: include: When the energy storage system executes the peak shaving and valley filling strategy, if the primary frequency regulation triggering condition is met, the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency is calculated; Determine whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range; Determine the target power of the energy storage system according to the judgment result; The lower limit of the primary frequency modulation energy storage target power range is the first target power, and the upper limit is the second target power. The target power of the energy storage system is determined according to the judgment result, including: When the peak-shaving and valley-filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range, the peak-shaving and valley-filling target power is determined as the target power of the energy storage system; When the peak shaving and valley filling energy storage adjustment amount is less than the first target power, the first target power is determined as the target power of the energy storage system; When the peak shaving and valley filling energy storage adjustment amount is greater than the second target power, the second target power is determined as the target power of the energy storage system.

2. The method according to claim 1, characterized in that The calculation of the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency includes: Get the frequency of the grid connection point; Determine whether the frequency of the grid connection point is within the adjustment range of the system frequency dead zone; When the frequency at the grid connection point is less than the downward adjustment boundary of the system frequency dead zone, the target power range of the primary frequency regulation energy storage for upward adjustment is calculated according to the calculation formula of the primary frequency regulation droop curve and the downward adjustment boundary of the system frequency dead zone; When the frequency at the grid connection point is greater than the upward adjustment boundary of the system frequency dead zone, the target power range of the primary frequency regulation energy storage for downward adjustment is calculated based on the calculation formula of the primary frequency regulation droop curve and the upward adjustment boundary of the system frequency dead zone.

3. The method according to claim 2, characterized in that The calculation of the primary frequency regulation energy storage target power range for upward adjustment based on the droop curve calculation formula of the primary frequency regulation and the downward adjustment boundary of the system frequency dead zone includes: The first and second FM components of the up-regulation are calculated according to the following formula: ΔP1=(fL-f)*P e / (f N *d) ΔP2=(fn-f)*P e / (f N *d) Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fL is the downward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response; The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted upward is determined as the first target power of the primary frequency modulation energy storage adjusted upward, and the first target power of the primary frequency modulation energy storage adjusted upward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted upward; The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted upward is determined as the second target power of the primary frequency modulation energy storage adjusted upward. The second target power of the primary frequency modulation energy storage adjusted upward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted upward.

4. The method according to claim 2, characterized in that: The calculation of the primary frequency regulation energy storage target power range for downward adjustment based on the droop curve calculation formula of the primary frequency regulation and the upward adjustment boundary of the system frequency dead zone includes: The first FM component and the second FM component of the down-regulation are calculated according to the following formula: ΔP1=(fn-f)*P e / (f N *d) ΔP2=(fH-f)*P e / (f N *δ) Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fH is the upward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response; The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted downward is determined as the first target power of the primary frequency modulation energy storage adjusted downward, and the first target power of the primary frequency modulation energy storage adjusted downward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted downward; The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted downward is determined as the second target power of the primary frequency modulation energy storage adjusted downward. The second target power of the primary frequency modulation energy storage adjusted downward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted downward.

5. The method according to claim 1, characterized in that After determining the target power of the energy storage system according to the judgment result, the method further includes: Determine whether the target power for peak shaving and valley filling is the discharge power; If it is discharge power, the minimum value between the target power of the energy storage system and the maximum dischargeable power is determined as the final target power of the energy storage system; If it is charging power, the maximum value between the target power of the energy storage system and the maximum chargeable power is determined as the final target power of the energy storage system.

6. A coordinated control device for peak shaving and valley filling and primary frequency modulation, characterized in that: include: A power range calculation unit, used to calculate the primary frequency regulation energy storage target power range corresponding to the grid connection point frequency if the primary frequency regulation triggering condition is met during the process of the energy storage system executing the peak shaving and valley filling strategy; A judging unit, used to judge whether the peak shaving and valley filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range; A target power determination unit, used to determine the target power of the energy storage system according to the judgment result; The lower limit of the primary frequency modulation energy storage target power range is the first target power, and the upper limit is the second target power. The target power determination unit is specifically used to: When the peak-shaving and valley-filling energy storage adjustment amount is within the primary frequency regulation energy storage target power range, the peak-shaving and valley-filling target power is determined as the target power of the energy storage system; When the peak shaving and valley filling energy storage adjustment amount is less than the first target power, the first target power is determined as the target power of the energy storage system; When the peak shaving and valley filling energy storage adjustment amount is greater than the second target power, the second target power is determined as the target power of the energy storage system.

7. The device according to claim 6, characterized in that The power range calculation unit comprises: A grid connection point frequency acquisition subunit, used to acquire the grid connection point frequency; A judgment subunit, used to judge whether the frequency of the grid connection point is within the adjustment range of the system frequency dead zone; The upper regulation power range calculation subunit is used to calculate the upper regulation primary frequency regulation energy storage target power range according to the droop curve calculation formula of the primary frequency regulation and the lower regulation boundary of the system frequency dead zone when the grid connection point frequency is less than the lower regulation boundary of the system frequency dead zone; The downward regulation power range calculation subunit is used to calculate the downward regulation primary frequency regulation energy storage target power range according to the primary frequency regulation droop curve calculation formula and the system frequency dead zone's upward boundary when the grid connection point frequency is greater than the system frequency dead zone's upward boundary.

8. The device according to claim 7, characterized in that The upper adjustment power range calculation subunit is specifically used for: The first and second FM components of the up-regulation are calculated according to the following formula: ΔP1=(fL-f)*P e / (f N *d) ΔP2=(fn-f)*P e / (f N *d) Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fL is the downward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response; The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted upward is determined as the first target power of the primary frequency modulation energy storage adjusted upward, and the first target power of the primary frequency modulation energy storage adjusted upward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted upward; The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted upward is determined as the second target power of the primary frequency modulation energy storage adjusted upward. The second target power of the primary frequency modulation energy storage adjusted upward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted upward.

9. The device according to claim 7, characterized in that The down-regulation power range calculation subunit is specifically used for: The first FM component and the second FM component of the down-regulation are calculated according to the following formula: ΔP1=(fn-f)*P e / (f N *d) ΔP2=(fH-f)*P e / (f N *δ) Among them, ΔP1 is the first frequency modulation component of the upward adjustment, ΔP2 is the second frequency modulation component of the upward adjustment, fH is the upward adjustment boundary of the system frequency dead zone, fn is 50Hz, f N is the rated frequency of the system, f is the grid connection point frequency, P e is the rated installed power of the photovoltaic system, δ is the regulation rate of the new energy fast frequency response; The sum of the active power of the energy storage system grid connection point and the first frequency modulation component adjusted downward is determined as the first target power of the primary frequency modulation energy storage adjusted downward, and the first target power of the primary frequency modulation energy storage adjusted downward is the lower limit of the target power range of the primary frequency modulation energy storage adjusted downward; The sum of the active power of the energy storage system grid-connected point and the second frequency modulation component adjusted downward is determined as the second target power of the primary frequency modulation energy storage adjusted downward. The second target power of the primary frequency modulation energy storage adjusted downward is the upper limit of the target power range of the primary frequency modulation energy storage adjusted downward.

10. The device according to claim 6, characterized in that The target power determination unit is further used for: After determining the target power of the energy storage system according to the judgment result, judging whether the target power of peak shaving and valley filling is the discharge power; If it is discharge power, the minimum value between the target power of the energy storage system and the maximum dischargeable power is determined as the final target power of the energy storage system; If it is charging power, the maximum value between the target power of the energy storage system and the maximum chargeable power is determined as the final target power of the energy storage system.

Citation Information

Patent Citations

  • Wind power limit grid-connected capacity calculating method under constraint of frequency modulation and peak-load regulation adequacy

    CN105281358A

  • Method for controlling frequency modulation or peak regulation mode in optical-storage combined system

    CN110492512A

  • Multipurpose energy storage integrated device

    CN110676864A

  • Primary frequency modulation control method, device and system for new energy station

    CN110994640A

  • Power system load power prediction method and energy storage power station power distribution method

    CN111401604A