Risk assessment method for distributed voltage control system considering information equipment failure

By using the consistency algorithm and curve clustering model in the distributed voltage control system to evaluate the impact of information equipment failure on voltage risk, the problem of voltage risk assessment caused by information equipment failure in the distributed control system is solved, and the power grid operation is improved. Effective assessment and control of risks.

CN113517701BActive Publication Date: 2024-10-18NORTH CHINA ELECTRIC POWER UNIV
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202110862404.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-07-29
Publication Date
2024-10-18
Estimated Expiration
2041-07-29

AI Technical Summary

Technical Problem

In distributed voltage control systems, there are few studies on the impact of information equipment failures on voltage risks, and existing technologies are difficult to effectively evaluate and control, resulting in increased power grid operation risks.

Method used

A risk assessment method for distributed power distribution cyber-physical voltage control system is proposed. By establishing a distributed system including sensors, controllers, optical fibers, agent nodes, inverters and energy storage devices, photovoltaic inverter reactive power is selected as the consistent Variables, the consistency algorithm is used to update the control variables, and the reachability matrix is ​​generated through the communication network topology, an improved distributed consistency voltage control equation is established, and the risk of voltage out-of-limit is assessed using the curve clustering model.

Benefits of technology

This method can effectively evaluate the dual uncertainties of distributed power output and information equipment failure on voltage risk, improves calculation efficiency and applicability, provides effective technical support for active distribution network planning and operation, and reduces power grid operation risks. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113517701B_ABST
    Figure CN113517701B_ABST
Patent Text Reader

Abstract

The present invention discloses a distributed voltage control system risk assessment method taking into account information equipment failures, which belongs to the technical field of information physical systems. The method comprises step 1: establishing a distributed power distribution information physical voltage control system; step 2: selecting a photovoltaic inverter reactive power Q i (k) As a consistency variable, update the control variable of the local node; Step 3: Determine the photovoltaic grid-connected node set Θ PV Whether the voltage of the first monitored node o exceeds the limit; Step 4: Establish an improved distributed consistency voltage control equation considering information accessibility; Step 5: Establish a photovoltaic time-series daily power generation scenario model based on curve clustering and an information accessibility model under equipment failure, and conduct voltage over-limit risk assessment on the distributed power distribution information physical voltage control system. The present invention is universal for scenarios considering information equipment failure under various communication topologies; it greatly reduces the workload required to modify when changing faulty information equipment, and improves calculation efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of information-physical systems, and in particular to a risk assessment method for a distributed voltage control system taking information equipment failures into account. Background Art

[0002] The rapid development of high-tech industries in modern society has put forward higher requirements for power quality. With the access of a large number of distributed generation (DG) to the distribution network, its uncertain output causes the bidirectional flow of feeder currents, resulting in an increased risk of node voltage exceeding the limit. In order to suppress the negative impact of DG grid connection and improve the grid's ability to accept controllable resources, active control of distribution networks came into being. Through real-time collection and processing of grid information, optimal control of controllable resources such as DG is achieved, reducing grid operation risks and improving operation economy. However, active control is not effective in suppressing grid operation risks. [1] At the same time, due to its deep reliance on information systems, it also brings new security risks to the operation of distribution networks. [2-5] .

[0003] Therefore, conducting research on system operation risks under information equipment failures will provide effective support for the design and risk control of distribution network operation control systems.

[0004] At present, the primary problem caused by DG grid connection is that the voltage at the grid connection point exceeds the limit. In ADN, voltage control is usually used to maintain the voltage deviation of each node within the allowable range. The existing voltage control modes mainly include local, centralized and distributed [6-9] . Due to differences in control mechanisms, the three modes have different requirements for information collection, transmission and processing, and the degree of dependence on information equipment is also quite different. Local control monitors the voltage of local nodes and only uses the local voltage as the control input to achieve regulation. The voltage regulator absorbs or injects power to achieve the purpose of suppressing or raising the voltage. Because the nodes do not need to communicate with each other, there is no dependence on the communication system and they can respond quickly to voltage fluctuations. However, due to the lack of information interaction, the coordination between the global nodes and devices is poor, and the global optimal control cannot be achieved.

[10] Centralized control requires obtaining global data and equipment status information, generating control instructions through optimization algorithms, and sending them to each terminal device through the information system. Centralized control can achieve global coordinated control and has the best control effect, especially in small-scale or non-unidirectional power distribution systems.

[11] However, centralized control requires comprehensive measurement, which requires a well-configured communication system. [12,13]. Reference

[14] established a distribution CPS coordination planning framework, considering the impact of random failures of information systems on the control capability of physical systems, taking economy and DG absorption as multiple objectives, and taking the voltage over-limit probability under information-physical double-sided failure as a constraint, and proposed a coordinated planning method for DG and communication systems to achieve the optimal economy of CPS. Reference

[15] considered a variety of information failure factors and analyzed the impact of different information failures on centralized control voltage fluctuations, laying the foundation for subsequent research. In response to the risks introduced by random information failures, reference [5] proposed an optimization method for the emergency operation strategy of active distribution network DG to reduce the state fluctuation of the power grid under communication failures. The study showed that the injection strategy of distributed energy with a limited output upper limit under communication failures can effectively reduce the system operation risk. It can be seen that the relevant research on random failures of information equipment in centralized control systems has begun to take shape in planning, operation, and risk control.

[0005] As the distribution network will become more and more diverse in the future, considering the economic and multi-agent characteristics, centralized control will be difficult to meet all application scenarios.

[16] Distributed control can achieve global coordination optimization through simple local communication, overcoming the shortcomings of centralized control and decentralized control. [17-19] Multiple proxy nodes are configured in distributed control. These nodes can communicate with each other. Each proxy node makes decisions based on its own collected state information and information from adjacent proxy nodes. The consensus algorithm is usually used to implement [20,21] . Compared with centralized control, it reduces the dependence on the communication system, improves economy and robustness, and has been studied more and more widely in recent years. Reference

[22] studied the voltage distributed control strategy based on the consistency algorithm. Different consistency variables were selected according to the controlled objects. The results showed that the distributed control strategy can effectively suppress voltage over-limit and reduce economic costs. At present, most studies focus on the effects and methods of distributed control, and there are few studies on the impact of information equipment failures in the control process. Compared with centralized control, the impact of information failure is different because the control mechanisms of the two are different. Therefore, studying the impact of information equipment failure on voltage risk under distributed control mode has theoretical value and practical significance.

[0006] In view of the above technical problems, the present invention proposes a risk assessment method for a distributed power distribution cyber-physical voltage control system, targeting a power distribution cyber-physical system under distributed control, taking into account the dual uncertainties of photovoltaic output and information equipment failure.

[0007] References:

[0008] [1] Wang Haotian. Research on Optimal Dispatching of Active Distribution Network Considering Over-limit Risk[D]. Dalian University of Technology, 2019.

[0009] [2] Zhang Tianyu, Luo Fengzhang, Wang Chengshan, Wang Xiaoyu, Jin Zikai, Liu Yanzhang. Analysis of the impact of information system on microgrid operation reliability[J]. Automation of Electric Power Systems, 2016, 40(23): 28-35.

[0010] [3] Liu Wenxia, ​​Lin Zijian, Ma Tie, Wang Zhiqiang, Gong Qi. Reliability modeling and evaluation of active distribution system considering the impact of information failure[J]. Automation of Electric Power Systems, 2019, 43(19): 94-102.

[0011] [4] An Yu, Liu Dong, Chen Fei, Xu Weiwei. Risk analysis of cyber-physical operation of distribution network considering information attacks[J]. Power System Technology, 2019, 43(07): 2345-2352.

[0012] [5] Liu Wenxia, ​​Ma Tie, Yang Mengyao, Huang Yuchen. Optimization of emergency operation strategy of distributed power generation in active distribution system under severe communication failure[J]. Proceedings of the CSEE, 2020, 40(03): 754-765.

[0013] [6] Zhang Bo, Tang Wei, Cai Yongxiang, Wang Zhaoqi, Li Tianrui, Zhang Han. Distributed control strategy for household photovoltaic inverter and energy storage based on consensus algorithm[J]. Automation of Electric Power Systems, 2020, 44(02): 86-94.

[0014] [7] 2014,doi:10.1109 / TSTE.2014.2313862.

[0015] [8]K.Turitsyn,P.Sulc,S.Backhaus,et al."Options for Control ofReactive Power by Distributed Photovoltaic Generators,"in Proceedings of theIEEE,vol.99,no.6,pp.1063-1073,June 2011,doi:10.1109 / JPROC.2011.2116750.

[0016] [9]Y.Wang,K.T.Tan,X.Y.Peng,et al."Coordinated Control of DistributedEnergy-Storage Systems for Voltage Regulation in Distribution Networks,"inIEEE Transactions on Power Delivery,vol.31,no.3,pp.1132-1141,June 2016,doi:10.1109 / TPWRD.2015.2462723.

[0017]

[10] F.Olivier,P.Aristidou,D.Ernst,et al."Active Management of Low-Voltage Networks for Mitigating Overvoltages Due to Photovoltaic Units,"inIEEE Transactions on Smart Grid,vol.7,no.2,pp.926-936,March 2016,doi:10.1109 / TSG.2015.2410171.

[0018]

[11] Review of control strategies for voltage regulation of the smartdistribution network with high penetration of renewable distributedgeneration

[0019]

[12] A.Kulmala,S.Repo an,P. "Coordinated Voltage Control in Distribution Networks Including Several Distributed Energy Resources," in IEEETransactions on Smart Grid, vol.5, no.4, pp.2010-2020, July 2014, doi:10.1109 / TSG.2014.2297971.

[0020]

[13] E.Dall'Anese, SVDhople, GGBGiannakis. "Optimal dispatch of photovoltaic inverters in residential distribution systems," 2014IEEE PESGeneral Meeting|Conference&Exposition, National Harbor, MD, USA, 2014, pp.1-1, doi:10.1109 / PESGM.2014.6939035.

[0021]

[14] Liu Wenxia, ​​Xu Huiting, Chen Ye, Liu Zongqi. Optimal planning method for power distribution cyber-physical system considering multi-dimensional uncertainty[J]. Proceedings of the CSEE, 2017, 37(24): 7205-7215+7434.

[0022]

[15] Liu Wenxia, ​​Han Hui. Evaluation of voltage fluctuation in distribution network under multiple control information failures[J]. Automation of Electric Power Systems, 2020, 44(09): 69-77.

[0023]

[16] Zhang Jin, Geng Guangchao, Jiang Quanyuan, Yang Yong, Zhou Ziqiang. Distributed adaptive control of distribution network with flexible multi-state switches[J]. Power System Technology, 2020, 44(07): 2649-2656.

[0024]

[17] M.Zeraati, MEHamedani Golshan, JMGuerrero. "Distributed Control of Battery Energy Storage Systems for Voltage Regulation in DistributionNetworks With High PV Penetration," in IEEE Transactions on Smart Grid, vol.9, no.4, pp.3582-3593, July 2018,doi:10.1109 / TSG.2016.2636217.

[0025]

[18] Cai Yongxiang, Tang Wei, Xu Ouyang, Zhang Lu. A review of voltage control research for low-voltage distribution networks with a high proportion of household photovoltaics[J]. Power System Technology, 2018, 42(01): 220-229.

[0026]

[19] Pu Tianjiao, Liu Wei, Chen Naishi, Wang Xiaohui, Dong Lei. Distributed Optimal Scheduling of Active Distribution Networks Based on Consensus Algorithm[J]. Proceedings of the CSEE, 2017, 37(06): 1579-1590.

[0027]

[20] Wang Zhengang, Chen Yuanrui, Zeng Jun, Chen Jianlong, Liu Junfeng. Modeling and reliability assessment of microgrid cyber-physical system for fully distributed control[J]. Power System Technology, 2019, 43(07): 2413-2421.

[0028]

[21] Le Jian, Zhou Qian, Wang Cao, Li Xingrui. Research on voltage and power optimization control method of distribution network based on distributed coordination[J]. Proceedings of the CSEE, 2020, 40(04): 1249-1257+1415.

[0029]

[22] Zhang Bo, Tang Wei, Cai Yongxiang, Wang Yue, Chen Lu. Coordinated planning of energy storage system and communication network for high proportion of household photovoltaic consumption[J]. Power System Technology, 2018, 42(10): 3161-3169. Summary of the invention

[0030] The purpose of the present invention is to provide a distributed voltage control system risk assessment method taking into account information equipment failures, characterized in that it comprises the following steps:

[0031] Step 1: Establish a distributed power distribution cyber-physical voltage control system including sensors, controllers, optical fibers, proxy nodes, inverters, and energy storage devices;

[0032] Step 2: Select the PV inverter reactive Qi (k) As a consistency variable, the consistency algorithm is used to update the control variable of the local node;

[0033] Step 3: Determine the photovoltaic grid-connected node set Θ PV Whether the voltage of the node o detected first in the process exceeds the limit; if the voltage exceeds the upper limit, a reactive absorption signal is transmitted to suppress overvoltage; if the voltage exceeds the lower limit, a reactive injection signal is transmitted to support undervoltage;

[0034] Step 4: Generate the reachability matrix P through the adjacency matrix A and the transfer coefficient matrix D of the communication network topology, and establish the improved distributed consistency voltage control equation considering information reachability;

[0035] Step 5: Establish a photovoltaic time-series daily power generation scenario model based on curve clustering and an information accessibility model under equipment failure, and conduct voltage over-limit risk assessment on the distributed distribution information-physical voltage control system.

[0036] The consistency algorithm in step 2 is as follows:

[0037]

[0038] Where: d ij is the transfer coefficient from proxy node j to node i, calculated as follows

[0039]

[0040] Where: n i and n j Represents the number of adjacent nodes between node i and node j.

[0041] The reactive power of the photovoltaic inverter at node o in step 3 is as follows

[0042]

[0043] In the formula, is the voltage-reactive sensitivity of node o to node j; is the actual voltage at node o; V max and V min are the upper and lower limits of the node voltage respectively.

[0044] The element a of the adjacency matrix A in step 4 ij and the element d of the transfer coefficient matrix D ij The relationship is as follows:

[0045]

[0046] Where N c is a set of proxy nodes;

[0047] The improved distributed consensus voltage control equation considering information accessibility is:

[0048]

[0049] Where C i is the state of the i-th controller, 1 for normal operation and 0 for failure; p ji is the element of the reachability matrix; Q j (k) is the output of controller j.

[0050] The steps to improve distributed consistent voltage control are as follows:

[0051] Step D1: The sensor collects the local voltage and uploads it to the proxy node;

[0052] Step D2: Node o, as a voltage regulating node, detects that the voltage exceeds the limit;

[0053] Step D3: Set the initial value of the control variable of node o and transmit it to other proxy nodes;

[0054] Step D4: Each proxy node updates the control quantity setting value based on the improved consistency algorithm and transmits it to other proxy nodes;

[0055] Step D5: Determine whether the setting values ​​of each voltage regulation node are consistent; if so, the proxy node sends the control quantity to the local controller to complete the voltage regulation; if not, go to step D4.

[0056] The step 5 of establishing a photovoltaic time-series daily power generation scenario model based on curve clustering specifically includes:

[0057] Step 51: Based on the historical data of photovoltaic output in a certain area for n days, the sampling interval is t, and the photovoltaic output sample X on the i-th day is set i =[x i1 ,x i2 ,…,x iu ], where x iu is the output at the uth moment on the i-th day, and the photovoltaic output sample set matrix is ​​obtained:

[0058]

[0059] Step 52: Select k photovoltaic daily power samples As the initial clustering center, the n photovoltaic daily power samples are divided into k classes C1, C2, ..., Ck. The number of samples in each class α1, α2, ..., αk satisfies α1+α2+ ...+αk=n; where is the i-th sample of class Cr, For class C r The cluster center of and are u-dimensional vectors, and the sum of squared deviations of samples of class Cr is

[0060]

[0061] Step 53: Calculate the Euclidean distance from each cluster center to each photovoltaic day power generation sample, and divide all samples into the class with the smallest Euclidean distance from it; wherein, the Euclidean distance is calculated as follows:

[0062]

[0063] In the formula: x it 、x jt Represents the tth data in the i-th and j-th samples;

[0064] Step 54: Calculate the arithmetic mean of all samples in each category as the new cluster center after clustering And determine whether the cluster center does not change before and after the update, that is, the square error criterion function E is stable within the minimum value range; if so, go to step 55; if not, go to step 53; wherein the new cluster center for

[0065]

[0066] In the formula, To classify the former class C p The cluster center, x (qu) Photovoltaic day power sample X q Data at each moment;

[0067] The square error criterion function E is

[0068]

[0069] In the formula, C r is the rth class, is the photovoltaic daily power sample in the rth class, is the cluster center of the rth class;

[0070] Step 55: Subtract 1 from the number of cluster centers k and assign it to k;

[0071] Step 56: Calculate the statistic ξ 2 and increase amplitude γ, and determine whether the number of cluster centers k is 1 or whether the increase amplitude γ is greater than 10. If so, take the value before k minus 1 as the ideal number of cluster centers; if not, go to step 53; where the statistic ξ 2 for

[0072]

[0073] Where W s ,W z ,W r They are the new classes C after the merger s , Class C before the merger z and C r The sum of squares of the intra-class deviations, a z and a r are the number of samples of class z and class r respectively;

[0074] The increase before and after each merger is expressed as

[0075]

[0076] The establishment of the information accessibility model under equipment failure in step 5 specifically includes:

[0077] The component status change is simulated through the cycle of "run-stop-run", and the available status S(y) of information component y is:

[0078]

[0079] The interruption of information transmission in the communication transmission path between nodes is regarded as the disappearance of directed edges in the directed graph, which is equivalent to setting the corresponding elements in the adjacency matrix to 0; the failure and aging of sensor, controller, and proxy node equipment are regarded as the disappearance of vertices in the directed graph, which is equivalent to the disappearance of all directed edges connected to the node, which is equivalent to setting the corresponding elements in the adjacency matrix to 0;

[0080] The probability calculation of information equipment failure scenarios is expressed using the following full probability model:

[0081]

[0082] Where t represents the tth information equipment failure scenario, P it is the probability that the i-th information device is in the corresponding state in the t-th information device failure scenario, P t is the probability of scenario t, and Ω is the number of information device components.

[0083] The risk index of voltage over-limit risk assessment in step 5 is:

[0084]

[0085] Where Risk represents the comprehensive risk of voltage exceeding the limit of distribution network; P i is the probability of information failure scenario i; P j is the probability of running scenario j; represents the voltage over-limit degree of node t in operation scenario j and information fault scenario i; m, n, and k are the number of distribution network nodes, the number of information fault scenarios, and the number of operation scenarios, respectively; where,

[0086]

[0087]

[0088]

[0089] In the formula, p l is the probability that information device l is in the available state; Θ i is the available state set of all devices under information device state i; n j is the number of samples in the typical scenario class of the photovoltaic output; is the voltage value of node t.

[0090] The beneficial effects of the present invention are:

[0091] 1. The present invention fully considers the dual uncertainty of distributed power output and information equipment failure to evaluate voltage risk, and is universal for scenarios considering information equipment failure under various communication topologies;

[0092] 2. Based on the information accessibility matrix, the distributed control algorithm that reflects the impact of information equipment failures only needs to modify the corresponding elements in the adjacency matrix when different information equipment fails, and the control quantity in the scenario can be directly obtained, which greatly reduces the workload required to modify when changing the faulty information equipment and improves the calculation efficiency;

[0093] 3. The present invention fully considers the uncertainty, seasonal characteristics and time series correlation of photovoltaic output, selects the extreme daily output in various categories as the operation scenario, and has stronger applicability for voltage risk assessment;

[0094] 4. The present invention can provide effective technical support for active distribution network planning, operation and risk control. BRIEF DESCRIPTION OF THE DRAWINGS

[0095] Figure 1 It is a schematic diagram of the distributed voltage control system;

[0096] Figure 2 It is the IEEE33 node power distribution system diagram;

[0097] Figure 3 The overall flow chart of the risk assessment method for distributed voltage control system considering information equipment failure;

[0098] Figure 4 A flow chart for establishing a photovoltaic time-series daily power generation scenario model based on curve clustering;

[0099] Figure 5 Flowchart for improving distributed consistent voltage control;

[0100] Figure 6 Solve the flow chart for voltage risk assessment indicators;

[0101] Figure 7 This is the clustering result diagram of the sample curve of photovoltaic output historical data;

[0102] Figure 8 The simulation results of voltage exceeding the limit when different information equipment fails are shown in the figure;

[0103] Fig. 9 This is a simulation result diagram comparing the impact of faults at different locations on the same device;

[0104] Fig.10 This is the simulation result diagram of information equipment failure under different voltage regulation point configurations. DETAILED DESCRIPTION

[0105] The present invention proposes a distributed voltage control system risk assessment method taking information equipment failure into account. The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0106] 1 Distributed voltage control system model

[0107] 1.1 System composition and operation mode

[0108] Distributed voltage control system (DVCS), its system structure is as follows Figure 1 As shown. DVCS is mainly composed of sensors, controllers, optical fibers, proxy nodes, inverters and energy storage devices. Among them, the proxy node refers to a workstation composed of equipment with information relay and task processing capabilities. The sensor collects the voltage status of the local physical node and uploads it to the local proxy node. The local proxy node receives the voltage information from the local and other neighboring proxy nodes through the optical fiber, and transmits the local voltage information to other neighboring proxy nodes. Each proxy node determines whether control is required based on whether the local voltage information exceeds the limit, and performs decision calculations according to a certain algorithm to obtain the decision amount and send it to the local controller. The controller drives the photovoltaic inverter, energy storage and other physical devices according to the control instructions, thereby achieving the adjustment of the physical domain. The control of distributed systems mostly adopts consistency algorithms, which have the advantages of simple modeling, fast convergence speed and low requirements for information system configuration.

[0109] 1.2 Consistency Algorithm of Traditional Distributed Voltage Control

[0110] The consensus algorithm updates the control variables of the local node through information interaction between the local node and the adjacent nodes, so that the control variables of the node converge to a stable common value. Let the control variable of node i be x i (k) , where k is the number of iterations. In distributed control, the control amount of each node is adjusted according to the control amount of its adjacent nodes. As the number of iterations increases, the control amount of the node tends to be consistent. When the control amounts of all nodes are consistent within the convergence condition range, the system converges. The present invention selects the photovoltaic inverter reactive power as the consistency variable Q i (k) , the consistency algorithm can be described by formula (1):

[0111]

[0112] Where: d ij is the transfer coefficient of proxy node j to i, and its value can be calculated according to the following formula.

[0113]

[0114] Where: n i and n j represents the number of adjacent nodes between node i and node j, v c A collection of nodes.

[0115] When the consistency variables of different control nodes are close to each other, that is, |Q i (k) -Q j (k) |≤0.0001, the consistency algorithm can be considered to have converged. When the communication topology is a strongly connected graph, the consistency algorithm can achieve convergence, and the convergence result is a constant that is independent of the communication topology. The example used in the present invention is a strongly connected graph.

[0116] The set of photovoltaic grid-connected points is denoted as Θ PV ,When the voltage of these nodes exceeds the limit, the node that first detects the voltage exceeding the limit is recorded as o, o∈Θ PV According to the consistency algorithm, the sensor will sense that the node voltage exceeds the limit and transmit the voltage value to the local proxy node. If the voltage exceeds the upper limit, the reactive absorption signal is transmitted to suppress the overvoltage; if it exceeds the lower limit, the reactive injection signal is transmitted to support the undervoltage.

[0117] Since the control signal is transmitted from node o to other nodes, the calculation of the reactive power of the photovoltaic inverter at node o is crucial. It can be calculated according to formula (3):

[0118]

[0119] In the formula, is the actual voltage at node O; V max and V min are the upper and lower limits of node voltage respectively; is the voltage-reactive power sensitivity of node o to node j, that is, the voltage change of node o caused by the unit reactive power change of node j.

[0120] 1.3 Improved distributed control algorithm model considering information accessibility

[0121] The calculation of the control quantity of the traditional distributed consistency algorithm is based on a sound communication network. However, random failures of equipment may cause problems such as the inability to transmit and iterate information between some nodes, the inability to collect the physical domain status of some nodes, and the inability to execute control instructions. At the same time, the breakage of the optical fiber will also cause the number of adjacent nodes of the node to change. At this time, the conventional consistency algorithm is no longer applicable to the scenario of information equipment failure. For this reason, the present invention takes into account information equipment failures and establishes an improved distributed consistency control algorithm based on the information reachability matrix.

[0122] 1.3.1 Information accessibility analysis based on accessibility matrix

[0123] Most of the existing information system devices use full-duplex communication. The information system topology can be regarded as a generalized directed graph. The accessibility of information between devices can be studied through directed graph theory. The information devices in the network can be regarded as nodes, and the optical fibers can be regarded as edges. Whether the devices can communicate is then converted into the question of whether the nodes of the directed graph are reachable.

[0124] (1) Overview of Graph Theory

[0125] Suppose the directed graph topology is D = (v, ε), where the vertex set V = {v1, v2, …, v n}, edge set E = {e1,e2,…,e n}. Each edge has a direction, that is, starting from an element a in the vertex set and ending at another element b, it is called a directed edge from a to b. ij Represents vertex v i With vertex v j The connection relationship between them is calculated by formula (4). The resulting matrix A=A(D) is called the adjacency matrix of the directed graph D.

[0126]

[0127] (2) Directed graph reachability matrix calculation method

[0128] Suppose there is a directed graph D = (v, ε), and a vertex set V = {v1, v2, …, v n}. Define the matrix P = (p ij ) n×n , is called the reachability matrix of the directed graph D. Among them,

[0129]

[0130] For an n-order directed graph adjacency matrix A, the reachability matrix of the graph can be obtained from A. Let it be P. The steps to obtain it are as follows: First, find B n =A+A 2 +…+A n , then, transform the matrix B n Change the non-zero elements in the graph to 1, and keep the zero elements unchanged. The resulting matrix is ​​the reachable matrix P of graph D.

[0131] 1.3.2 Improved Consensus Algorithm Model Considering Information Accessibility

[0132] First, write out the adjacency matrix of the communication network topology and generate the reachability matrix at this time. ij and the transfer coefficient matrix element d ij The definition of , we can get the following relationship:

[0133]

[0134] Where N c A collection of proxy nodes.

[0135] At this time, when an information system fails, it can be equivalent by modifying the corresponding elements of the adjacency matrix. The specific modification method is shown in 2.2.2. Then, the transfer coefficient matrix in the distributed control consistency algorithm can be directly derived through the modified adjacency matrix.

[0136] According to the transfer coefficient matrix D and the reachability matrix P, the improved distributed consistency voltage control equation considering information reachability can be obtained. According to the principle of the consistency algorithm described in 3.1, the output calculation method of each controller is as follows:

[0137]

[0138] In the formula, C i is the state of the i-th controller, 1 for normal operation and 0 for failure; p ij and d ij are the corresponding elements in the reachability matrix and transfer coefficient matrix of the information system topology; Q j (k) is the output of controller j. The algorithm convergence conditions and the calculation method of the output of the starting node are as described above. The specific control process is shown in Figure 5 .

[0139] 2 Voltage over-limit risk assessment

[0140] The distribution network is connected to a large number of photovoltaics. On the one hand, the uncertainty of photovoltaic output has an impact on the voltage quality of the distribution network, which in turn brings voltage risks; on the other hand, due to the strong dependence of distributed voltage control on the information system, the uncertain failure of information equipment has further increased the risk of voltage exceeding the limit. Therefore, in order to evaluate the voltage risk of the distributed voltage control system, it is necessary to analyze and model the uncertainty of photovoltaic output and the uncertainty of information equipment failure.

[0141] 2.1 Operation scenario modeling based on curve clustering

[0142] Modeling the uncertainty of photovoltaic output is a prerequisite for risk assessment of information-physical voltage control systems. The greater the uncertainty of photovoltaic output, the more severe the voltage fluctuation, the greater the necessity of voltage regulation, and the greater the dependence on the information system. In addition, there is a certain continuous downtime for information equipment failure. When evaluating its impact, the timing correlation of photovoltaic output should be fully considered. Therefore, the present invention proposes a method for generating photovoltaic time-series daily output scenarios based on a curve clustering algorithm, clusters the historical data of photovoltaic daily output throughout the year, generates several representative photovoltaic daily output curves as typical operating scenarios, and calculates the probability of the operating scenario.

[0143] 2.1.1 Photovoltaic output scenario generation

[0144] For the historical data of photovoltaic output in a certain area for n days, the sampling interval is t, and the photovoltaic output sample X on the i-th day is i =[x i1 ,x i2 ,…,x iu ], where x iu is the output data at the uth moment of the i-th day, so there is a photovoltaic output sample set matrix:

[0145]

[0146] The Euclidean distance is used to measure the difference between any two samples. The Euclidean distance calculation method is as follows:

[0147]

[0148] In the formula, x it Represents the tth data in the i-th sample. ij The smaller the sample size, the smaller the i and X j The better the similarity, the worse it is. By calculating the Euclidean distance from the initial cluster center to each photovoltaic day power sample, all samples are divided into the class with the smallest Euclidean distance.

[0149] Calculate the arithmetic mean of all samples in each category as the new cluster center after this clustering

[0150]

[0151] In the formula, To classify the former class C p The cluster center, x (qu) Photovoltaic day power sample X q The Euclidean distance between the new cluster center and each sample is calculated, and then the above steps are repeated until the cluster center does not change before and after the update, that is, the square error criterion function E is stable within the minimum value range, and the clustering is completed. The calculation formula of the square error criterion function is shown in formula (7).

[0152]

[0153] Among them, C r is the rth class, is the photovoltaic daily power sample in the rth class, is the cluster center of the rth class.

[0154] Assume that k photovoltaic daily power samples are selected as cluster centers, denoted as The n photovoltaic daily power samples are divided into k classes, each of which is denoted as C1, C2, ..., C k , the number of samples in each class is recorded as a, there are a1+a2+…+a k =n, For class C r The i-th sample of For class C r The cluster center of and All are u-dimensional vectors, class C r The sum of squared deviations within a class is:

[0155]

[0156] Define the statistic ξ 2 It is used to measure the increase in the sum of squares of deviations within a class after two classes are merged into a new class, and then to determine the difference between the two merged classes and whether they should be merged.

[0157]

[0158] Where W s ,W z ,W r They are the new classes C after the merger s , Class C before the merger z and C r The sum of squares of the intra-class deviations, a z and a rare the number of samples of class z and class r respectively.

[0159] Starting from the initial cluster center number k, we continue to merge clusters until k equals 1, and then count the difference between k and ξ 2 and calculate the relationship between each merge 2 The increase amplitude γ can be calculated according to formula (14):

[0160]

[0161] Different scenarios have different requirements for clustering accuracy. Different γ values ​​can be selected as the standard for judging whether to merge. In the present invention, it is considered that when γ is greater than 10, the difference between the two categories merged this time is significant, and k before the merger is taken as the ideal number of cluster centers.

[0162] 2.2 Information equipment failure modeling

[0163] The information system components of the existing typical distributed power distribution information control system mainly include proxy nodes, optical fibers, sensors, controllers, etc. The uncertainty of information equipment failure refers to the fact that during the operation of the above equipment, with the increase of service life and the deterioration of the operating environment, the information equipment will fail with a certain probability and stop running within a certain repair time. Therefore, modeling the impact of uncertain information equipment failures on distribution network voltage regulation is the key to evaluating the voltage over-limit risk of cyber-physical voltage control systems.

[0164] 2.2.1 Analysis of the impact of information equipment failure

[0165] Different information devices play different roles in the voltage regulation process. The sensor is responsible for collecting information in the physical domain and uploading it to the proxy node; the proxy node is responsible for determining whether the voltage needs to be adjusted and calculating the control amount; the controller is responsible for receiving and executing the control instructions of the proxy node; the transmission of collected information and control instructions is completed through optical fiber.

[0166] For faulty information equipment, the equipment is always in a stopped state during its repair time, and the information that the equipment participates in transmitting or processing during this period is invalid information. Sensors are information uplink devices. If they fail, local status information cannot be collected before repair, and the node information cannot participate in optimization decisions. This situation not only affects the control effect of this node, but also causes inaccurate scheduling strategies due to missing decision data, and affects the control effects of other nodes. Controllers are information downlink devices. If control instructions cannot be issued due to a fault, the physical node maintains the previous state unchanged before the fault is repaired. This situation only affects the control effect of this node. The proxy node is a hub device. If it fails, not only will the local control instructions be unable to be issued, but it will also cause the proxy node decision information of other nodes to be missing, making the scheduling strategy inaccurate.

[0167] In the case of a fiber failure, the information transmitted through this fiber fails. The analysis of the impact on the uplink and downlink of information is the same as above and will not be repeated here. 2.2.2 Information accessibility modeling under equipment failure

[0168] Information device availability status:

[0169] Without considering aging failures, most faults and outages in the information domain are repairable, and their component state changes can be simulated through the "run-out-run" cycle. Therefore, the available state S(k) of information component k is:

[0170]

[0171] Wherein, S(k) is the available status of the kth device.

[0172] For the communication transmission paths between nodes, the interruption of information transmission caused by optical fiber compression breakage, aging failure, etc. can be regarded as the disappearance of directed edges in the directed graph, which is equivalent to setting the corresponding elements in the adjacency matrix to 0; for node equipment failures, aging failures, etc. such as sensors, controllers, and proxy nodes, they can be regarded as the disappearance of vertices in the directed graph, and their impact is equivalent to the disappearance of all directed edges connected to the node, which is equivalent to setting the corresponding elements in the adjacency matrix to 0. Then, the improved consistency algorithm in 1.3.2 can be used to calculate the control quantity under the failure of the corresponding information equipment.

[0173] 2.2.3 Probability calculation of information equipment failure scenarios

[0174] The probability calculation of information equipment failure scenarios is expressed using a full probability model, which can be described by the following formula:

[0175]

[0176] Where t represents the tth information equipment failure scenario, P it is the probability that the i-th information device is in the corresponding state in the t-th information device failure scenario, P t is the probability of scenario t, and Ω is the number of information device components.

[0177] 2.3 Voltage over-limit risk assessment indicators and algorithms

[0178] The risk of voltage over-limit in the distribution network refers to a comprehensive measure of the probability of voltage over-limit events occurring in the system and the severity of the consequences caused. After a large number of photovoltaics are connected, the structure and operation mode of the distribution network will change. Due to its uncertainty and the failure of the information system, voltage control cannot be carried out normally, resulting in node voltage fluctuations and even increased risk of over-limit. According to the "National Standard for Power Quality", the sum of the absolute values ​​of the positive and negative deviations of the distribution network voltage should not exceed 10% of the rated value. The present invention uses an analytical method to evaluate the risk of voltage over-limit in the distribution network, and the risk index can be calculated using the following formula:

[0179]

[0180] Where Risk represents the comprehensive risk of voltage exceeding the limit of distribution network; P i is the probability of information failure scenario i; P j is the probability of running scenario j; It represents the voltage over-limit degree of node t in operation scenario j and information fault scenario i; m, n, and k are the number of distribution network nodes, the number of information fault scenarios, and the number of operation scenarios, respectively.

[0181] Each term in the above formula can be calculated according to formula (18-20):

[0182]

[0183]

[0184]

[0185] In the formula, p l is the probability that information device l is in the available state; Θ i is the available state set of all devices under information device state i; n j is the number of samples in the typical scenario of photovoltaic output; V t is the voltage value of node t. The voltage risk assessment index solution process is shown in Figure 6 .

[0186] 3 Example Analysis

[0187] 3.1 Example model and parameter setting

[0188] The example of the present invention adopts the IEEE 33-node power distribution system, where distributed photovoltaics are connected at 15, 18, 21, 22, 24, 25, 32, and 33, and nodes 18, 22, 25, and 33 are set as voltage regulation nodes, such as Figure 2As shown. Since the photovoltaic grid-connected points of the distribution network are not far apart, it can be considered that the output values ​​of each photovoltaic power station are approximately equal. The present invention collects the historical data of photovoltaic output in a certain area, with a sampling period of 365 days and a sampling interval of 15 minutes. The information equipment of each photovoltaic node includes sensors, controllers, and corresponding proxy nodes and optical fibers of the communication layer. The failure rate and fault repair time of each device are shown in Table 1:

[0189] Table 1 Information equipment failure parameters

[0190]

[0191] Since the probability of multiple equipment failures occurring simultaneously in an information system is very low, this example only considers single failure of information equipment.

[0192] 3.2 Analysis of photovoltaic curve clustering results

[0193] according to Figure 3 The overall flow chart and the risk assessment method of distributed voltage control system considering information equipment failure Figure 4 A flow chart of establishing a photovoltaic time-series daily output scenario model based on curve clustering; through the curve clustering and operation scenario selection method described in the present invention, the photovoltaic output historical data samples are clustered, and the cluster centers in each category are selected as the operation scenarios for voltage risk assessment. The results are as follows Figure 7 shown.

[0194] 3.3 Voltage over-limit risk assessment and comparative analysis

[0195] According to the improved consistency algorithm considering information accessibility proposed in the present invention, the voltage over-limit situation when different information devices fail is simulated under the operation scenarios listed in 3.2. The results are as follows: Figure 8 ,According to the operation scenario and fault scenario generation methods in 3.1 and 3.2 and the voltage risk assessment method in 3.3, it can be obtained that the comprehensive voltage risk of the distribution network is 4.19%.

[0196] It can be seen that the failure of the proxy node has the most serious impact on the voltage control effect, followed by the controller failure. However, since the failure rate of the proxy node is usually low, the voltage risk it brings is not high. Analysis shows that the proxy node is the transmitter of information and the decision maker of the control quantity. Its failure not only causes the information to be unable to be transmitted, but also causes the control quantity to be unable to be adjusted. The controller failure only has a greater impact on the voltage of the local and nearby nodes because its control instructions cannot be executed, causing the local node to lose control. On the other hand, although the voltage of some nodes exceeds the limit due to sensor failure and fiber breakage, its severity is very small. This is because, whether it is a sensor failure or a fiber breakage, it only affects part of the observed values ​​participating in the setting calculation of the control quantity, but it can still be adjusted to a relatively ideal value. Therefore, although there is a voltage limit, it is not serious.

[0197] 3.4 Comparative analysis of the impact of failures at different locations on the same equipment

[0198] In order to analyze the difference in the impact of the same type of information equipment when it fails in different locations, this section sets up scenarios of single failures at different locations for comparative analysis for the proxy node with the most serious failure impact. The simulation results are shown in the figure. Fig. 9 :

[0199] The failure of proxy node 22 has a great impact on the voltage control effect. Analysis shows that: as the hub node among the proxy nodes, the failure of proxy node 22 will cause the two sides to completely lose contact, causing the voltage control mode of 18 nodes to degenerate into local control. However, the initial value of distributed control is used as the control quantity of local control without cyclic iteration, causing it to greatly exceed the power required for local control, and the node voltage is seriously out of limit.

[0200] 3.5 Comparison of voltage risks under different voltage regulation point configurations

[0201] To study the impact of changes in information system access points on voltage risk, this section reconfigures the information system, changes the location of the voltage regulation point, performs information equipment failure simulation analysis, and recalculates the voltage risk index.

[0202] Change the voltage regulating nodes in the calculation model described in 3.1 to 15, 21, 24, and 32, and keep other parameters unchanged. Re-simulate the information equipment failure, and the results are as follows: Fig.10 .

[0203] The calculated comprehensive voltage risk of the distribution network is 9.44%. Compared with the communication network planning scheme in 3.1, its voltage risk has greatly increased. This is because the change of the voltage regulation point sets the node with serious source-load imbalance as the voltage regulation point. Although this has good economy and robustness, it requires the information system to be strong and reliable. Once a failure occurs, the photovoltaic power output is uncontrolled and random, causing the node voltage to exceed the limit significantly. Therefore, when selecting the voltage regulation point, the node with a moderate degree of matching between the photovoltaic output and the node load should be selected as the voltage regulation point based on the historical level of the node load and combined with the load and photovoltaic output forecast. On the one hand, it can achieve good economy under normal conditions, and on the other hand, it can ensure that the voltage risk is within an acceptable range when considering information equipment failures.

[0204] In summary, when the information system is fully online, the voltage control effect of centralized control is better than that of distributed control. However, when the information system failure factor is considered, distributed control is better than centralized control. The results show that although centralized control based on a fully observable and robust information system has the best control effect, for medium and low voltage distribution networks with relatively poor communication levels and considering information equipment failures, distributed voltage control is obviously a better choice.

[0205] This embodiment is only a preferred specific implementation of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A distributed voltage control system risk assessment method taking into account information equipment failures, characterized in that: The following steps are involved: Step 1: Establish a distributed power distribution cyber-physical voltage control system including sensors, controllers, optical fibers, proxy nodes, inverters, and energy storage devices; Step 2: Select the PV inverter reactive Q i (k) As a consistency variable, the consistency algorithm is used to update the control variable of the local node; Step 3: Determine the photovoltaic grid-connected node set Θ PV Whether the voltage of the node o detected first exceeds the limit; if the voltage exceeds the upper limit, a reactive absorption signal is transmitted to suppress the overvoltage; If the lower limit is exceeded, a reactive injection signal is transmitted to support the undervoltage; Step 4: Generate the reachability matrix P through the adjacency matrix A and the transfer coefficient matrix D of the communication network topology, and establish the improved distributed consistency voltage control equation considering information reachability; The element a of the adjacency matrix A in step 4 ij and the element d of the transfer coefficient matrix D ij The relationship is as follows: Where N c is a set of proxy nodes; The improved distributed consensus voltage control equation considering information accessibility is: Where C i is the state of the i-th controller, 1 for normal operation and 0 for failure; p ji is the element of the reachability matrix; Q j (k) is the output of controller j; The steps to improve distributed consistent voltage control are as follows: Step D1: The sensor collects the local voltage and uploads it to the proxy node; Step D2: Node o, as a voltage regulating node, detects that the voltage exceeds the limit; Step D3: Set the initial value of the control variable of node o and transmit it to other proxy nodes; Step D4: Each proxy node updates the control variable setting value based on the improved consistency algorithm and transmits it to other proxy nodes; Step D5: Determine whether the setting values ​​of each voltage regulating node are consistent; if so, the proxy node sends the control quantity to the local controller to complete the voltage regulation; if not, go to step D4; Step 5: Establish a photovoltaic time-series daily power generation scenario model based on curve clustering and an information accessibility model under equipment failure, and conduct voltage over-limit risk assessment on the distributed distribution information-physical voltage control system.

2. The distributed voltage control system risk assessment method taking into account information equipment failure according to claim 1 is characterized in that: The consistency algorithm in step 2 is as follows: Where: d ij is the transfer coefficient from proxy node j to node i, calculated as follows Where: n i and n j Represents the number of adjacent nodes between node i and node j.

3. The distributed voltage control system risk assessment method taking into account information equipment failure according to claim 1 is characterized in that: The reactive power of the photovoltaic inverter at node o in step 3 is as follows In the formula, is the voltage-reactive sensitivity of node o to node j; is the actual voltage at node o; V max and V min are the upper and lower limits of the node voltage respectively.

4. The distributed voltage control system risk assessment method taking into account information equipment failure according to claim 1 is characterized in that: The step 5 of establishing a photovoltaic time-series daily power generation scenario model based on curve clustering specifically includes: Step 51: Based on the historical data of photovoltaic output in a certain area for n days, the sampling interval is t, and the photovoltaic output sample X on the i-th day is set i =[x i1 ,x i2 ,…,x iu ], where x iu is the output at the uth moment on the i-th day, and the photovoltaic output sample set matrix is ​​obtained: Step 52: Select K photovoltaic daily power generation samples As the initial clustering center, the n photovoltaic daily power samples are divided into K classes C1, C2, ..., CK. The number of samples in each class α1, α2, ..., αK satisfies α1+α2+ ...+αK=n; where is the i-th sample of class Cr, For class C r The cluster center of and are u-dimensional vectors, and the sum of squared deviations of samples of class Cr is Step 53: Calculate the Euclidean distance from each cluster center to each photovoltaic day power generation sample, and divide all samples into the class with the smallest Euclidean distance from it; wherein, the Euclidean distance is calculated as follows: In the formula: x it 、x jt Represents the tth data in the i-th and j-th samples; Step 54: Calculate the arithmetic mean of all samples in each category as the new cluster center after this clustering And determine whether the cluster center does not change before and after the update, that is, the square error criterion function E is stable within the minimum value range; if so, go to step 55; if not, go to step 53; wherein the new cluster center for In the formula, To classify the former class C p The cluster center, x (qu) Photovoltaic day power sample X q Data at each moment; The square error criterion function E is In the formula, C r is the rth class, is the photovoltaic daily power sample in the rth class, is the cluster center of the rth class; Step 55: Subtract 1 from the number of cluster centers K and assign it to K; Step 56: Calculate the statistic ξ 2 and increase amplitude γ, and determine whether the number of cluster centers K is 1 or whether the increase amplitude γ is greater than 10. If so, take the value before K minus 1 as the ideal number of cluster centers; if not, go to step 53; where the statistic ξ 2 for Where W s ,W z ,W r They are the new classes C after the merger s 、Class C before the merger z and C r The sum of squares of the intra-class deviations, a z and a r are the number of samples of class z and class r respectively; The increase before and after each merger is expressed as 5. The distributed voltage control system risk assessment method taking into account information equipment failures according to claim 1 is characterized in that: The establishment of the information accessibility model under equipment failure in step 5 specifically includes: The component status change is simulated through the "run-stop-run" cycle. The available status S(y) of information component y is: The interruption of information transmission in the communication transmission path between nodes is regarded as the disappearance of directed edges in the directed graph, which is equivalent to setting the corresponding elements in the adjacency matrix to 0; the failure and aging of sensor, controller, and proxy node equipment are regarded as the disappearance of vertices in the directed graph, which is equivalent to the disappearance of all directed edges connected to the node, which is equivalent to setting the corresponding elements in the adjacency matrix to 0; The probability calculation of information equipment failure scenarios is expressed using the following full probability model: Where t represents the tth information equipment failure scenario, P it is the probability that the i-th information device is in the corresponding state in the t-th information device failure scenario, P t is the probability of scenario t, and Ω is the number of information device components.

6. The distributed voltage control system risk assessment method taking into account information equipment failure according to claim 1 is characterized in that: The risk index of voltage over-limit risk assessment in step 5 is: Where Risk represents the comprehensive risk of voltage exceeding the limit of distribution network; P i is the probability of information failure scenario i; P j is the probability of running scenario j; represents the voltage over-limit degree of node t in operation scenario j and information fault scenario i; m, n, and H are the number of distribution network nodes, the number of information fault scenarios, and the number of operation scenarios, respectively; where, In the formula, p l is the probability that information device l is in an available state; Θ i is the available state set of all devices under information device state i; n j is the number of samples in the typical photovoltaic output scenario; is the voltage value of node t.

Citation Information

Patent Citations

  • Power distribution network single photovoltaic digestion capability evaluation method in consideration of voltage out-of -limit risk

    CN108233416A

  • Power distribution network overvoltage suppression method and system based on active power limit value algorithm

    CN108539801A