A four-stage throttling precooling concrete production system

By designing a four-stage throttling pre-cooled concrete production system and utilizing a series-connected compressor and throttle valve structure, the problems of high energy consumption and complex equipment in the existing technology are solved, achieving high energy consumption ratio and good stability. Cooling effect.

CN113635453BActive Publication Date: 2024-10-29SINOHYDRO BUREAU 8 CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202110863851.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-07-29
Publication Date
2024-10-29
Estimated Expiration
2041-07-29

AI Technical Summary

Technical Problem

The existing concrete pre-cooling system has high energy consumption, complex equipment, and low stability. The large temperature difference between various working conditions results in low cooling efficiency, short equipment life, and high failure rate.

Method used

Design a four-stage throttling pre-cooled concrete production system, which is connected to each other through cold water refrigeration compressor, primary air-cooling refrigeration compressor, secondary air-cooling refrigeration compressor, flake ice refrigeration compressor and other components to form a series structure, and utilizes energy-saving The flow valve performs four-stage temperature and pressure reduction, and the refrigeration system is merged to reduce the number of equipment and refrigerant charge.

Benefits of technology

It improves the refrigeration efficiency and energy consumption ratio, reduces the compressor exhaust temperature and pressure, simplifies the process, enhances the stability and safety of the system, and reduces the number of equipment and environmental risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113635453B_ABST
    Figure CN113635453B_ABST
Patent Text Reader

Abstract

The invention discloses a four-stage throttling precooling concrete production system, wherein a cold water refrigeration compressor, a primary air-cooling refrigeration compressor, a secondary air-cooling refrigeration compressor and a flake ice refrigeration compressor are all connected to a condenser, the condenser is connected to a high-pressure liquid reservoir, the high-pressure liquid reservoir is connected to a cold water gravity circulation liquid reservoir through a second liquid pipeline, the cold water gravity circulation liquid reservoir is connected to a primary air-cooling low-pressure circulation liquid reservoir through a fourth liquid pipeline, the primary air-cooling low-pressure circulation liquid reservoir is connected to a secondary air-cooling low-pressure circulation liquid reservoir through a sixth liquid pipeline, the secondary air-cooling low-pressure circulation liquid reservoir is connected to a flake ice low-pressure circulation liquid reservoir through an eighth liquid pipeline, the flake ice low-pressure circulation liquid reservoir is connected to a flake ice refrigeration compressor through a ninth gas pipeline, and a throttle valve is provided on the second liquid pipeline, the fourth liquid pipeline, the sixth liquid pipeline and the eighth liquid pipeline. The invention has the advantages of high energy consumption ratio, high fault tolerance, good stability, less equipment and structures, and simple process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the feeding or proportioning of ingredients when clay or cement is mixed with other materials, and in particular to a four-stage throttling precooling concrete production system. Background Art

[0002] When concrete has low tensile strength and small elastic modulus and a large temperature difference between the inside and outside, temperature cracks are very likely to occur, affecting structural safety and normal use. Therefore, the maximum temperature inside large-volume concrete must be strictly controlled. Controlling the temperature of the concrete outlet is currently one of the most effective and common measures to control the maximum temperature of concrete. The main way to control the temperature of the concrete outlet is to pre-cool its raw materials, that is, to cool its raw materials before mixing the concrete.

[0003] Commonly used precooling processes mainly include air cooling of coarse aggregate and mixing with flake ice and cold water. Coarse aggregate air cooling is divided into primary air cooling and secondary air cooling. In the prior art, primary air cooling, secondary air cooling, cold water production and flake ice production use four different design evaporation temperature conditions: primary air cooling -15°C, secondary air cooling -20°C, cold water 0~2°C, flake ice -25°C. At present, all precooling processes generally use single-stage compression refrigeration. The temperature difference between the various working conditions is large, especially the secondary air cooling and flake ice production conditions, which deviate greatly from the economic operation range of the single-stage system, resulting in more flash steam from the liquid supply, higher compressor exhaust temperature, lower refrigeration efficiency, lower energy consumption, shortened equipment service life, high failure rate, and uneconomical. Each working condition generally has a separate refrigeration system, with a large number of equipment, pipelines and valve accessories, and a large number of corresponding refrigeration workshops and other structures. The system is complex, the capacity tolerance range of the main equipment of the system is small, the stability is low, and the fault tolerance rate and risk resistance rate are low. A few pre-cooling systems use screw compressors with economizers, or simply combine the primary air cooling with the high-pressure part of the chilled water, which simplifies the system process to a certain extent, but is far from solving the problem fundamentally. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a four-stage throttling precooling concrete production system with high energy consumption ratio, high fault tolerance, good stability, fewer equipment and structures, and simple process and structure.

[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0006] A four-stage throttling precooling concrete production system comprises a cold water refrigeration compressor, a primary air-cooled refrigeration compressor, a secondary air-cooled refrigeration compressor, a flake ice refrigeration compressor, a condenser, a high-pressure liquid reservoir, a cold water gravity circulation liquid reservoir, a cold water evaporator, a primary air-cooled low-pressure circulation liquid reservoir, a primary air-cooled air cooler, a secondary air-cooled low-pressure circulation liquid reservoir, a secondary air-cooled air cooler, a flake ice low-pressure circulation liquid reservoir and a flake ice machine, wherein the cold water refrigeration compressor, the primary air-cooled refrigeration compressor, the secondary air-cooled refrigeration compressor and the flake ice refrigeration compressor are all connected to the condenser through a first gas pipeline, the condenser is connected to the high-pressure liquid reservoir through a first liquid pipeline, the high-pressure liquid reservoir is connected to the cold water gravity circulation liquid reservoir through a second liquid pipeline, the cold water gravity circulation liquid reservoir is connected to the cold water evaporator through a third liquid pipeline, is connected to the primary air-cooled low-pressure circulation liquid reservoir through a fourth liquid pipeline, is connected to the cold water refrigeration compressor through a third gas pipeline, and the cold water evaporator is connected to the cold water gravity circulation liquid reservoir through a second gas pipeline. The first air-cooled low-pressure circulation reservoir is connected with the first air-cooled air cooler through the fifth liquid pipeline, is connected with the second air-cooled low-pressure circulation reservoir through the sixth liquid pipeline, and is connected with the first air-cooled refrigeration compressor through the fifth gas pipeline. The first air-cooled air cooler is connected with the first air-cooled low-pressure circulation reservoir through the fourth gas pipeline. The second air-cooled low-pressure circulation reservoir is connected with the second air-cooled air cooler through the seventh liquid pipeline, is connected with the flake ice low-pressure circulation reservoir through the eighth liquid pipeline, and is connected with the second air-cooled refrigeration compressor through the seventh gas pipeline. The second air-cooled air cooler is connected with the second air-cooled low-pressure circulation reservoir through the sixth gas pipeline. The flake ice low-pressure circulation reservoir is connected with the flake ice machine through the ninth liquid pipeline and is connected with the flake ice refrigeration compressor through the ninth gas pipeline. The flake ice machine is connected with the flake ice low-pressure circulation reservoir through the eighth gas pipeline. Throttle valves are provided on the second liquid pipeline, the fourth liquid pipeline, the sixth liquid pipeline and the eighth liquid pipeline.

[0007] As a further improvement of the above technical solution, a primary air-cooled refrigerant pump is provided on the fifth liquid pipeline.

[0008] As a further improvement of the above technical solution, a secondary air-cooled refrigerant pump is provided on the seventh liquid pipeline.

[0009] As a further improvement of the above technical solution, a flake ice refrigerant pump is provided on the ninth liquid pipeline.

[0010] As a further improvement of the above technical solution, the third gas pipeline is divided into four branches, namely a main air intake branch and three air supply branches. The main air intake branch is connected to the cold water refrigeration compressor, and the three air supply branches are respectively connected to the primary air-cooled refrigeration compressor, the secondary air-cooled refrigeration compressor, and the flake ice refrigeration compressor.

[0011] As a further improvement of the above technical solution, the outlets of the four first gas pipelines are merged into a tenth main gas pipeline, and the tenth main gas pipeline is connected to the condenser.

[0012] As a further improvement of the above technical solution, the inlet of the third liquid pipeline and the inlet of the fourth liquid pipeline are combined into one inlet on the cold water gravity circulation reservoir.

[0013] As a further improvement of the above technical solution, the inlet of the fifth liquid pipeline and the inlet of the sixth liquid pipeline are combined into one inlet on the primary air-cooled low-pressure circulation liquid reservoir.

[0014] As a further improvement of the above technical solution, the inlet of the seventh liquid pipeline and the inlet of the eighth liquid pipeline are combined into one inlet on the secondary air-cooled low-pressure circulation reservoir.

[0015] Compared with the prior art, the advantages of the present invention are:

[0016] (1) The four-stage throttling pre-cooling concrete production system of the present invention connects the cold water gravity circulation reservoir, the primary air-cooled low-pressure circulation reservoir, the secondary air-cooled low-pressure circulation reservoir, and the flake ice low-pressure circulation reservoir in series. The lower-stage container can also serve as a flash economizer for the upper-stage container. The four throttling valves perform four-stage temperature and pressure reduction, which greatly reduces throttling flash steam and improves refrigeration efficiency and energy consumption ratio; the four systems of primary air cooling, secondary air cooling, cold water and flake ice production are combined into one system to simplify the process flow and reduce the number of equipment and the refrigerant filling amount to the greatest extent: for ammonia refrigeration systems, the safety is greatly improved and the number of major hazardous sources is reduced; for Freon systems, the risk probability and scope of environmental damage are reduced, and the system has the advantages of high energy consumption ratio, high fault tolerance, good stability, less equipment and structures, and simple process and structure.

[0017] (2) In the four-stage throttling pre-cooling concrete production system of the present invention, part of the gas in the cold water gravity circulation reservoir flows to the gas supply ports of the primary air-cooled refrigeration compressor, the secondary air-cooled refrigeration compressor, and the flake ice refrigeration compressor through the gas supply branch, and the other part of the gas flows to the air inlet of the cold water refrigeration compressor and enters the next cycle after being compressed. The relationship between the evaporation temperature under cold water conditions and the evaporation temperature and condensation temperature of the primary air-cooled, secondary air-cooled, and flake ice production is fully utilized, and the gas in the cold water gravity circulation reservoir is used as the gas supply for the primary air-cooled refrigeration compressor, the secondary air-cooled refrigeration compressor, and the flake ice refrigeration compressor, which greatly reduces the exhaust temperature and pressure of the compressor, and further improves the refrigeration efficiency and energy consumption ratio. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of the present invention.

[0019] The symbols in the figure represent:

[0020] 1. Cold water refrigeration compressor; 2. Primary air-cooled refrigeration compressor; 3. Secondary air-cooled refrigeration compressor; 4. Flake ice refrigeration compressor; 5. Condenser; 6. High-pressure liquid storage tank; 7. Cold water gravity circulation liquid storage tank; 8. Cold water evaporator; 9. Primary air-cooled low-pressure circulation liquid storage tank; 10. Primary air-cooled air cooler; 11. Secondary air-cooled low-pressure circulation liquid storage tank; 12. Secondary air-cooled air cooler; 13. Flake ice low-pressure circulation liquid storage tank; 14. Flake ice machine; 15. First gas pipeline; 16. First liquid pipeline; 17. Second liquid pipeline; 18. Third liquid pipeline; 19. Fourth liquid pipeline 1. The third gas pipeline; 20. The third gas pipeline; 21. The second gas pipeline; 22. The fifth liquid pipeline; 23. The sixth liquid pipeline; 24. The fifth gas pipeline; 25. The fourth gas pipeline; 26. The seventh liquid pipeline; 27. The eighth liquid pipeline; 28. The seventh gas pipeline; 29. ​​The sixth gas pipeline; 30. The ninth liquid pipeline; 31. The ninth gas pipeline; 32. The eighth gas pipeline; 33. The throttle valve; 34. The primary air-cooled refrigerant pump; 35. The secondary air-cooled refrigerant pump; 36. The flake ice refrigerant pump; 37. The main air intake branch; 38. The air supply branch; 39. The tenth main gas pipeline. DETAILED DESCRIPTION

[0021] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0022] like Figure 1 As shown, the four-stage throttling pre-cooling concrete production system of this embodiment includes a cold water refrigeration compressor 1, a primary air-cooled refrigeration compressor 2, a secondary air-cooled refrigeration compressor 3, a flake ice refrigeration compressor 4, a condenser 5, a high-pressure liquid reservoir 6, a cold water gravity circulation liquid reservoir 7, a cold water evaporator 8, a primary air-cooled low-pressure circulation liquid reservoir 9, a primary air-cooled air cooler 10, a secondary air-cooled low-pressure circulation liquid reservoir 11, a secondary air-cooled air cooler 12, a flake ice low-pressure circulation liquid reservoir 13 and a flake ice machine 14.

[0023] The cold water refrigeration compressor 1, the primary air-cooled refrigeration compressor 2, the secondary air-cooled refrigeration compressor 3 and the flake ice refrigeration compressor 4 are all connected to the condenser 5 through the first gas pipeline 15, the condenser 5 is connected to the high-pressure liquid reservoir 6 through the first liquid pipeline 16, and the high-pressure liquid reservoir 6 is connected to the cold water gravity circulation liquid reservoir 7 through the second liquid pipeline 17.

[0024] The cold water gravity circulation reservoir 7 is connected to the cold water evaporator 8 through the third liquid pipeline 18, connected to the primary air-cooled low-pressure circulation reservoir 9 through the fourth liquid pipeline 19, and connected to the cold water refrigeration compressor 1 through the third gas pipeline 20. The cold water evaporator 8 is connected to the cold water gravity circulation reservoir 7 through the second gas pipeline 21.

[0025] The primary air-cooled low-pressure circulation liquid reservoir 9 is connected to the primary air-cooled air cooler 10 through the fifth liquid pipeline 22, connected to the secondary air-cooled low-pressure circulation liquid reservoir 11 through the sixth liquid pipeline 23, and connected to the primary air-cooled refrigeration compressor 2 through the fifth gas pipeline 24. The primary air-cooled air cooler 10 is connected to the primary air-cooled low-pressure circulation liquid reservoir 9 through the fourth gas pipeline 25.

[0026] The secondary air-cooled low-pressure circulation reservoir 11 is connected to the secondary air-cooled air cooler 12 through the seventh liquid pipeline 26, connected to the flake ice low-pressure circulation reservoir 13 through the eighth liquid pipeline 27, and connected to the secondary air-cooled refrigeration compressor 3 through the seventh gas pipeline 28. The secondary air-cooled air cooler 12 is connected to the secondary air-cooled low-pressure circulation reservoir 11 through the sixth gas pipeline 29.

[0027] The flake ice low pressure circulation liquid storage device 13 is connected to the flake ice machine 14 through the ninth liquid pipeline 30 and to the flake ice refrigeration compressor 4 through the ninth gas pipeline 31. The flake ice machine 14 is connected to the flake ice low pressure circulation liquid storage device 13 through the eighth gas pipeline 32.

[0028] The second liquid pipeline 17 , the fourth liquid pipeline 19 , the sixth liquid pipeline 23 and the eighth liquid pipeline 27 are all provided with a throttle valve 33 .

[0029] The specific working process is as follows: the cold water refrigeration compressor 1, the primary air-cooled refrigeration compressor 2, the secondary air-cooled refrigeration compressor 3, and the flake ice refrigeration compressor 4 discharge the high-temperature and high-pressure refrigerant gas into the condenser 5, and the condenser 5 condenses the high-temperature and high-pressure gas into a high-temperature and high-pressure liquid, and the high-temperature and high-pressure liquid flows into the high-pressure liquid reservoir 6. The high-temperature and high-pressure liquid in the high-pressure liquid reservoir 6 is cooled and depressurized by the throttle valve 33 on the second liquid pipeline 17 and flows into the cold water gravity circulation liquid reservoir 7. Most of the liquid is reduced to about 0°C and the saturated liquid falls into the lower part of the cold water gravity circulation liquid reservoir 7, and a small part of the liquid becomes flash steam in the upper part of the cold water gravity circulation liquid reservoir 7;

[0030] A portion of the saturated liquid at about 0°C in the cold water gravity circulation reservoir 7 flows into the cold water evaporator 8 through the third liquid pipeline 18, and performs heat exchange with the normal temperature water in the cold water evaporator 8, reducing the normal temperature water to cold water at 2-6°C (the cold water is used for concrete mixing). A portion of the saturated liquid at about 0°C absorbs heat and evaporates to become a gas-liquid mixture, and flows back to the cold water gravity circulation reservoir 7 through the second gas pipeline 21 for gas-liquid separation. The liquid falls into the lower part of the cold water gravity circulation reservoir 7, and the gas flows to the air inlet of the cold water refrigeration compressor 1 through the fifth gas pipeline 24 at the upper part of the cold water gravity circulation reservoir 7, and becomes a high-temperature and high-pressure refrigerant gas after compression to enter the next cycle;

[0031] Another part of the saturated liquid at about 0°C in the cold water gravity circulation reservoir 7 is cooled and depressurized by the throttle valve 33 on the fourth liquid pipeline 19 and then flows to the primary air-cooled low-pressure circulation reservoir 9. Most of the liquid is reduced to about -15°C and the saturated liquid falls into the lower part of the primary air-cooled low-pressure circulation reservoir 9. A small part of the liquid turns into flash steam in the upper part of the primary air-cooled low-pressure circulation reservoir 9. A part of the saturated liquid at about -15°C passes through the fifth liquid pipeline 22 and enters the primary air-cooled air cooler 10, absorbs heat and evaporates in the primary air-cooled air cooler 10, thereby reducing the temperature of the air flowing through the primary air-cooled air cooler 10 and cooling the air. The air after passing through the blower (not shown in the figure) enters the primary air-cooled aggregate bin (not shown in the figure) connected to the primary air-cooled air cooler 10, and cools the aggregate in the primary air-cooled aggregate bin. The saturated liquid at about -15°C absorbs heat and evaporates to become a gas-liquid mixture, which flows back to the primary air-cooled low-pressure circulation reservoir 9 through the fourth gas pipeline 25 for gas-liquid separation. The liquid falls into the lower part of the primary air-cooled low-pressure circulation reservoir 9, and the gas flows to the air inlet of the primary air-cooled refrigeration compressor 2 through the fifth gas pipeline 24 at the upper part of the primary air-cooled low-pressure circulation reservoir 9, and becomes a high-temperature and high-pressure refrigerant gas after being compressed to enter the next cycle;

[0032] Another part of the saturated liquid at about -15°C in the primary air-cooled low-pressure circulation reservoir 9 is cooled and depressurized by the throttle valve 33 on the sixth liquid pipeline 23 and then flows into the secondary air-cooled low-pressure circulation reservoir 11. Most of the liquid is reduced to about -20°C and the saturated liquid falls into the lower part of the secondary air-cooled low-pressure circulation reservoir 11, and a small part of the liquid turns into flash steam in the upper part of the secondary air-cooled low-pressure circulation reservoir 11. A part of the saturated liquid at about -20°C passes through the seventh liquid pipeline 26 and enters the secondary air-cooled air cooler 12, where it absorbs heat and evaporates, thereby reducing the liquid flowing through the secondary air-cooled air cooler 12. Air temperature, the cooled air enters the secondary air-cooled aggregate bin (not shown in the figure) connected to the secondary air-cooled air cooler 12 through a fan (not shown in the figure), and cools the aggregate in the secondary air-cooled aggregate bin. The saturated liquid at about -20°C absorbs heat and evaporates to become a gas-liquid mixture, which flows back to the secondary air-cooled circulating reservoir 11 through the sixth gas pipeline 29 for gas-liquid separation. The liquid falls into the lower part of the secondary air-cooled circulating reservoir 11, and the gas flows to the air inlet of the secondary air-cooled refrigeration compressor 3 through the seventh gas pipeline 28 at the upper part of the secondary air-cooled circulating reservoir 11, and becomes a high-temperature and high-pressure refrigerant gas after being compressed to enter the next cycle;

[0033] Another part of the saturated liquid at about -20°C in the secondary air-cooled low-pressure circulation reservoir 11 is cooled and depressurized by the throttle valve 33 on the eighth liquid pipeline 27 and then flows into the flake ice low-pressure circulation reservoir 13. Most of the liquid is cooled to about -25°C and falls into the lower part of the flake ice low-pressure circulation reservoir 13. A small part of the liquid turns into flash steam in the upper part of the flake ice low-pressure circulation reservoir 13. The saturated liquid at about -25°C passes through the ninth liquid pipeline 30 and enters the flake ice machine 14, where it absorbs heat and evaporates, thereby reducing The temperature of the water flowing into the flake ice machine 14 causes the water to freeze into ice (the ice is used to replace part of the water used for mixing concrete). The saturated liquid at about -25°C absorbs heat and evaporates to become a gas-liquid mixture, which flows back to the flake ice low-pressure circulation reservoir 13 through the eighth gas pipeline 32 for gas-liquid separation. The liquid falls into the lower part of the flake ice low-pressure circulation reservoir 13, and the gas flows from the upper part of the flake ice low-pressure circulation reservoir 13 through the ninth gas pipeline 31 to the air inlet of the flake ice refrigeration compressor 4, where it is compressed and becomes a high-temperature and high-pressure refrigerant gas to enter the next cycle.

[0034] The four-stage throttling pre-cooling concrete production system of the present invention connects the cold water gravity circulation reservoir, the primary air-cooled low-pressure circulation reservoir, the secondary air-cooled low-pressure circulation reservoir, and the flake ice low-pressure circulation reservoir in series, and the lower-stage container can also serve as a flash economizer for the upper-stage container. The four throttling valves 33 perform four-stage temperature and pressure reduction, which greatly reduces throttling flash steam and improves refrigeration efficiency and energy consumption ratio; the four systems of primary air cooling, secondary air cooling, cold water and flake ice production are combined into one system, which simplifies the process flow and reduces the number of equipment and the refrigerant charge to the greatest extent: for ammonia refrigeration systems, the safety is greatly improved and the number of major hazardous sources is reduced; for Freon systems, the risk probability and scope of environmental damage are reduced, and it has the advantages of high energy consumption ratio, high fault tolerance, good stability, less equipment and structures, and simple process and structure.

[0035] In this embodiment, a primary air-cooled refrigerant pump 34 is provided on the fifth liquid pipeline 22. A secondary air-cooled refrigerant pump 35 is provided on the seventh liquid pipeline 26. A flake ice refrigerant pump 36 is provided on the ninth liquid pipeline 30. Since the four-stage system uses the primary air-cooled low-pressure circulation accumulator 9, the secondary air-cooled low-pressure circulation accumulator 11, and the flake ice low-pressure circulation accumulator 13, the refrigerant charge amount of the system increases, and a refrigerant pump is required to pump the refrigerant liquid.

[0036] In this embodiment, the third gas pipeline 20 is divided into four branches, namely, a main air intake branch 37 and three air supply branches 38. The main air intake branch 37 is connected to the cold water refrigeration compressor 1, and the three air supply branches 38 are respectively connected to the primary air cooling refrigeration compressor 2, the secondary air cooling refrigeration compressor 3, and the flake ice refrigeration compressor 4. A part of the gas in the cold water gravity circulation reservoir 7 flows to the air supply ports of the primary air cooling refrigeration compressor 2, the secondary air cooling refrigeration compressor 3, and the flake ice refrigeration compressor 4 through the air supply branch 38, and the other part of the gas flows to the air intake of the cold water refrigeration compressor 1 and enters the next cycle after being compressed. The relationship between the evaporation temperature under the cold water working condition and the evaporation temperature and condensation temperature of the primary air cooling, secondary air cooling, and flake ice production is fully utilized, and the gas in the cold water gravity circulation reservoir 7 is used as the air supply of the primary air cooling refrigeration compressor 2, the secondary air cooling refrigeration compressor 3, and the flake ice refrigeration compressor 4, which greatly reduces the exhaust temperature and pressure of the compressor, and further improves the refrigeration efficiency and energy consumption ratio.

[0037] In this embodiment, the outlets of the four first gas pipelines 15 are combined into a tenth main gas pipeline 39 , and the tenth main gas pipeline 39 is connected to the condenser 5 .

[0038] In this embodiment, the inlet of the third liquid pipeline 18 and the inlet of the fourth liquid pipeline 19 are two separate inlets on the cold water gravity circulation reservoir 7. It should be noted that, except for this embodiment, the inlet of the third liquid pipeline 18 and the inlet of the fourth liquid pipeline 19 are combined into one inlet on the cold water gravity circulation reservoir 7.

[0039] In this embodiment, the inlet of the fifth liquid pipeline 22 and the inlet of the sixth liquid pipeline 23 are combined into one inlet on the primary air-cooled low-pressure circulation reservoir 9. The inlet of the seventh liquid pipeline 26 and the inlet of the eighth liquid pipeline 27 are combined into one inlet on the secondary air-cooled low-pressure circulation reservoir 11.

[0040] Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention. Any technician familiar with the art can make many possible changes and modifications to the technical solution of the present invention by using the technical content disclosed above without departing from the scope of the technical solution of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention should fall within the scope of protection of the technical solution of the present invention.

Claims

1. A four-stage throttling precooling concrete production system, characterized by: The invention comprises a cold water refrigeration compressor (1), a primary air-cooled refrigeration compressor (2), a secondary air-cooled refrigeration compressor (3), a flake ice refrigeration compressor (4), a condenser (5), a high-pressure liquid storage device (6), a cold water gravity circulation liquid storage device (7), a cold water evaporator (8), a primary air-cooled low-pressure circulation liquid storage device (9), a primary air-cooled air cooler (10), a secondary air-cooled low-pressure circulation liquid storage device (11), a secondary air-cooled air cooler (12), a flake ice low-pressure circulation liquid storage device (13) and a flake ice machine (14), wherein the cold water refrigeration compressor (1), the primary air-cooled refrigeration compressor (2), the secondary air-cooled refrigeration compressor (3) and the flake ice refrigeration compressor (4) are all connected to the condenser (5) via a first gas pipeline (15). The condenser (5) is connected to the high-pressure liquid reservoir (6) through a first liquid pipeline (16), the high-pressure liquid reservoir (6) is connected to the cold water gravity circulation liquid reservoir (7) through a second liquid pipeline (17), the cold water gravity circulation liquid reservoir (7) is connected to the cold water evaporator (8) through a third liquid pipeline (18), is connected to the primary air-cooled low-pressure circulation liquid reservoir (9) through a fourth liquid pipeline (19), and is connected to the cold water refrigeration compressor (1) through a third gas pipeline (20), the cold water evaporator (8) is connected to the cold water gravity circulation liquid reservoir (7) through a second gas pipeline (21), and the primary air-cooled low-pressure circulation liquid reservoir (9) is connected to the primary air-cooled air compressor (1) through a fifth liquid pipeline (22). The primary air-cooled air cooler (10) is connected to the secondary air-cooled low-pressure circulation liquid reservoir (11) through a sixth liquid pipeline (23), and is connected to the primary air-cooled refrigeration compressor (2) through a fifth gas pipeline (24); the primary air-cooled air cooler (10) is connected to the primary air-cooled low-pressure circulation liquid reservoir (9) through a fourth gas pipeline (25); the secondary air-cooled low-pressure circulation liquid reservoir (11) is connected to the secondary air-cooled air cooler (12) through a seventh liquid pipeline (26), is connected to the flake ice low-pressure circulation liquid reservoir (13) through an eighth liquid pipeline (27), and is connected to the secondary air-cooled refrigeration compressor (3) through a seventh gas pipeline (28); the secondary air-cooled air cooler (12 ... The flake ice low-pressure circulation liquid reservoir (11) is connected to the secondary air-cooled low-pressure circulation liquid reservoir (11) through a ninth liquid pipeline (30), and is connected to the flake ice machine (14) through a ninth gas pipeline (31); the flake ice machine (14) is connected to the flake ice low-pressure circulation liquid reservoir (13) through an eighth gas pipeline (32); a throttle valve (33) is provided on the second liquid pipeline (17), the fourth liquid pipeline (19), the sixth liquid pipeline (23) and the eighth liquid pipeline (27); a primary air-cooled refrigerant pump (34) is provided on the fifth liquid pipeline (22); and a secondary air-cooled refrigerant pump (35) is provided on the seventh liquid pipeline (26).

2. The four-stage throttling precooling concrete production system according to claim 1 is characterized in that: The ninth liquid pipeline (30) is provided with a flake ice refrigerant pump (36).

3. The four-stage throttling precooling concrete production system according to claim 1 or 2, characterized in that: The third gas pipeline (20) is divided into four branches, namely a main air intake branch (37) and three air supply branches (38). The main air intake branch (37) is connected to the cold water refrigeration compressor (1), and the three air supply branches (38) are respectively connected to the primary air-cooled refrigeration compressor (2), the secondary air-cooled refrigeration compressor (3), and the flake ice refrigeration compressor (4).

4. The four-stage throttling precooling concrete production system according to claim 1 or 2, characterized in that: The outlets of the four first gas pipelines (15) are combined into a tenth main gas pipeline (39), and the tenth main gas pipeline (39) is connected to the condenser (5).

5. The four-stage throttling precooling concrete production system according to claim 1 or 2, characterized in that: The inlet of the third liquid pipeline (18) and the inlet of the fourth liquid pipeline (19) are combined into one inlet on the cold water gravity circulation reservoir (7).

6. The four-stage throttling precooling concrete production system according to claim 1 or 2, characterized in that: The inlet of the fifth liquid pipeline (22) and the inlet of the sixth liquid pipeline (23) are combined into one inlet on the primary air-cooled low-pressure circulation liquid storage tank (9).

7. The four-stage throttling precooling concrete production system according to claim 1 or 2, characterized in that: The inlet of the seventh liquid pipeline (26) and the inlet of the eighth liquid pipeline (27) are combined into one inlet on the secondary air-cooled low-pressure circulation liquid storage tank (11).

Citation Information

Patent Citations

  • Four-stage throttling precooling concrete production system

    CN215882083U