A tower crane overload control device using spoke-type load sensor for detection

By installing an overload control device with a spoke load sensor and a weight measuring block on the tower crane, the weight of the lifted object is detected in real time and brake control is performed. This solves the problem of the tower crane being difficult to judge overload, and protects the electric motor and Safe operation is ensured.

CN113816274BActive Publication Date: 2024-10-01BENGBU GAOLING SENSOR ENG SYST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111265261.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-28
Publication Date
2024-10-01
Estimated Expiration
2041-10-28

AI Technical Summary

Technical Problem

It is difficult for existing tower cranes to effectively determine whether a heavy object is overweight when lifting heavy objects, resulting in easy damage to the motor and potential safety hazards, and lack of strong braking measures when overloaded.

Method used

A spoke-type load sensor detection device is used, and a spoke-type load sensor and a weight measuring block are installed in the overload control component to detect the weight of the lifted objects in real time, and control the action through the PLC controller to avoid extreme operation of the motor; at the same time, set the upper and lower A brake pad controls the braking of the drive shaft of the electric motor.

Benefits of technology

It achieves accurate weight detection of heavy objects lifted by tower cranes, avoids overload damage to equipment, protects electric motors, ensures safe operation, and reminds operators through alarms to reduce safety accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113816274B_ABST
    Figure CN113816274B_ABST
Patent Text Reader

Abstract

The invention discloses an overload control device for a tower crane using a spoke-type load sensor for detection, comprising an overload control component, wherein the overload control component comprises a slide rail, a rope mounting seat and an electric motor, wherein a spoke-type load sensor is mounted inside the slide rail, a weight measuring block is fixedly connected to the bottom surface of the rope mounting seat, a support seat is fixedly connected to the bottom of the side surface of the rope mounting seat, an electric motor is mounted on the top surface of the support seat, two electric telescopic rods are arranged inside the rope mounting seat, the upper electric telescopic rod is connected to a first brake plate, and the lower electric telescopic rod is connected to a second brake plate, wherein the inner sides of the first brake plate and the second brake plate are both fixedly connected to brake pads; after adopting the above structure, the weight measuring block contacts the spoke-type load sensor during hoisting to accurately detect the weight of the hoisted heavy object, and the transmission shaft of the electric motor is braked and controlled by the cooperation of the upper and lower brake pads.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tower crane control, and in particular to an overload control device for a tower crane detected by a spoke-type load sensor. Background Art

[0002] Tower crane is a kind of rotating crane with boom mounted on the top of a tall tower. It has a large working space and is mainly used for vertical and horizontal transportation of materials and installation of building components in house construction. It consists of three parts: metal structure, working mechanism and electrical system.

[0003] When lifting heavy objects, existing tower cranes mostly rely on observing whether the motor can lift the heavy object to determine whether the heavy object is overweight. During the use of the tower crane, the motor is often put into an extreme operating state, which can easily cause damage to the motor, and it is impossible to effectively determine whether the heavy object is too heavy, which poses a safety hazard. At the same time, when overload occurs, there is no strong braking measure to ensure work safety.

[0004] Therefore, we propose an overload control device for a tower crane using a spoke-type load sensor to detect, in order to solve the above-mentioned problems. Summary of the invention

[0005] In order to overcome the above-mentioned technical problems, the purpose of the present invention is to provide an overload control device for a tower crane using a spoke-type load sensor for detection. By installing a spoke-type load sensor and a measuring block in the overload control component, the measuring block contacts the spoke-type load sensor during lifting, and the weight of the lifted object is accurately detected to determine whether the object is overloaded. The device is controlled by a PLC controller to take action to avoid the motor being in an extreme operating state, which would cause damage to the motor. At the same time, the cooperation of the upper and lower brake pads is provided to perform strong braking control on the drive shaft of the electric motor.

[0006] The purpose of the present invention can be achieved through the following technical solutions:

[0007] The invention discloses an overload control device for a tower crane using a spoke-type load sensor for detection, comprising an overload control component, which is slidably mounted on a boom support of the tower crane. The overload control component can be driven to flexibly move on the boom support of the tower crane through a driving device of the tower crane. The overload control component comprises a slide rail, a rope mounting seat and an electric motor. A spoke-type load sensor is mounted inside the slide rail, a weight measuring block is fixedly connected to the bottom surface of the rope mounting seat, and the weight measuring block contacts the spoke-type load sensor during lifting to accurately detect the weight of the lifted object. A first alarm is fixedly mounted on the top surface of the right side of the rope mounting seat to warn the staff in the tower crane operating room. A support seat is fixedly connected to the bottom of the side surface of the rope mounting seat, and an electric motor is mounted on the top surface of the support seat, wherein a PLC controller is mounted on the front end of the electric motor to control the entire lifting process.

[0008] Two electric telescopic rods are arranged inside the lifting rope mounting seat, the upper electric telescopic rod is connected to the first brake plate, and the lower electric telescopic rod is connected to the second brake plate, wherein the inner sides of the first brake plate and the second brake plate are fixedly connected with brake pads, and the transmission shaft of the electric motor is braked and controlled by the cooperation of the upper and lower brake pads.

[0009] As a further solution of the present invention: two slide rails are provided, and the overload control component is slidably installed on the tower crane boom bracket through the two slide rails, thereby maintaining the stability of the movement and avoiding instability caused by a single sliding. A movement groove is opened in the middle of the top surface of each slide rail, and the movement grooves are all in an inverted T shape, thereby ensuring the stability of the installation of the lifting rope mounting seat.

[0010] As a further solution of the present invention: a plurality of spoke-type load sensors are installed in the middle of the two moving grooves, and the plurality of spoke-type load sensors are distributed at equal intervals, and the positions of the spoke-type load sensors in the two moving grooves correspond one to one. By using the spoke-type load sensors, real-time detection is performed on the lifting rope mounting seat when lifting heavy objects, thereby avoiding overloading and damage to equipment.

[0011] As a further solution of the present invention: the connector end of each spoke-type load sensor passes through the motion slot and extends to the outside, so as to facilitate connection with equipment.

[0012] As a further solution of the present invention: an installation groove is opened in the middle of the lifting rope mounting seat, and the installation groove is open upward, and the winding shaft is rotatably installed through the installation groove. Two weighing blocks are fixedly connected to the bottom surface of the lifting rope mounting seat, and the two weighing blocks are symmetrically distributed about the center of the bottom surface of the lifting rope mounting seat, and the positions of the two weighing blocks correspond to the positions of the two moving grooves. The lifting rope mounting seat is installed in the moving groove in the slide rail through the two weighing blocks.

[0013] As a further solution of the present invention: a plurality of support springs are fixedly connected to the bottom of each weight block, and the plurality of support springs are linearly and evenly spaced, wherein the plurality of support springs are alternately arranged with a plurality of spoke-type load sensors during actual installation.

[0014] As a further solution of the present invention: the first brake plate and the second brake plate are both semicircular.

[0015] As a further solution of the present invention: positioning guide pillars are symmetrically arranged on both sides of the bottom surface of the first brake plate, and positioning circular grooves are symmetrically opened on both sides of the top surface of the second brake plate, and the positioning guide pillars are adapted to the positioning circular grooves. Through the assembly of the positioning guide pillars and the positioning circular grooves, the precise fit between the first brake plate and the second brake plate is ensured to avoid offset and affect braking.

[0016] Beneficial effects of the present invention:

[0017] 1. The present invention installs a first alarm and a second alarm on the suspension rope mounting seat and the suspension hook respectively, so as to further warn the staff in the tower crane operating room and the staff at the bottom to avoid the occurrence of safety accidents.

[0018] 2. The present invention installs a plurality of spoke-type load sensors in the slide rail. The spoke-type load sensors are used to perform real-time detection on the lifting rope mounting seat when lifting heavy objects, so as to determine whether it is overloaded, thereby avoiding overload during lifting and damage to the equipment. Moreover, the joint end of each spoke-type load sensor extends through the motion groove to the outside to facilitate connection with the equipment. At the same time, the spoke-type load sensor has outstanding advantages such as low height, high precision, good linearity, and resistance to deflection loads and lateral forces.

[0019] 3. The present invention ensures the precise fit of the first brake plate and the second brake plate to avoid offset that affects braking through the assembly of the positioning guide column and the positioning circular groove, wherein the inner sides of the first brake plate and the second brake plate are fixedly connected with brake pads, and the cooperation of the upper and lower brake pads performs braking control on the drive shaft of the electric motor, thereby protecting the electric motor and preventing the electric motor from being in an extreme operating state that causes damage to the electric motor. In addition, when overloaded, strong braking is performed to avoid safety accidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention will be further described below in conjunction with the accompanying drawings.

[0021] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0022] Figure 2 It is a front view schematic diagram of the overall structure of the present invention;

[0023] Figure 3 It is a side view schematic diagram of the overall structure of the present invention;

[0024] Figure 4 yes Figure 3 A schematic diagram of the enlarged structure of the middle A area;

[0025] Figure 5 It is a schematic diagram of the connection between the suspension rope mounting seat and the slide rail in the present invention;

[0026] Figure 6 It is a schematic diagram of the internal structure of the suspension rope mounting seat of the present invention;

[0027] Figure 7 It is a schematic diagram of the connection between the first brake plate, the second brake plate and the brake pad in the present invention.

[0028] In the figure: 2, overload control component; 20, slide rail; 201, moving groove; 202, spoke load sensor; 21, rope mounting seat; 211, weighing block; 212, support spring; 213, mounting cavity; 214, heat dissipation hole; 215, electric telescopic rod; 216, first brake plate; 217, brake pad; 218, second brake plate; 22, reel; 221, wire rope; 222, hook; 23, first alarm; 24, electric motor; 25, support seat; 26, PLC controller. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0030] Embodiment 1:

[0031] like Figure 1-7 As shown, an overload control device for a tower crane using a spoke-type load sensor for detection includes an overload control component 2, and the overload control component 2 is slidably mounted on a tower crane boom support, and the tower crane boom support is mounted on the tower crane, and the overload control component 2 can be driven by a driving device of the tower crane to flexibly move on the tower crane boom support to lift heavy objects;

[0032] like Figure 1-2As shown, the overload control component 2 is provided with two slide rails 20, and the overload control component 2 is slidably installed on the tower crane boom bracket through the two slide rails 20, so as to maintain the stability of the movement and avoid instability caused by a single sliding. A rope mounting seat 21 is installed on the top of the two slide rails 20, a winding shaft 22 is installed in the rope mounting seat 21, and a steel wire rope 221 is wound in the winding shaft 22 for lifting heavy objects. A first alarm 23 is fixedly installed on the top surface of the right side of the rope mounting seat 21 for alerting the staff in the tower crane operating room. A support seat 25 is fixedly connected to the bottom of the side of the rope mounting seat 21, and an electric motor 24 is installed on the top surface of the support seat 25, wherein a PLC controller 26 is installed on the front end of the electric motor 24 for controlling the entire lifting process.

[0033] like Figure 3 , Figure 4 and Figure 5 As shown, the two slide rails 20 are symmetrically arranged with each other, and a movement groove 201 is opened in the middle of the top surface of each slide rail 20, and the movement grooves 201 are inverted T-shaped to ensure the stable installation of the rope mounting seat 21. A plurality of spoke-type load sensors 202 are installed in the middle of the two movement grooves 201, and the plurality of spoke-type load sensors 202 are distributed at equal intervals. The positions of the spoke-type load sensors 202 in the two movement grooves 201 correspond one to one. By using the spoke-type load sensors 202, real-time detection is performed on the rope mounting seat 21 when hoisting heavy objects to avoid overloading and damage to the equipment. In addition, the connector end of each spoke-type load sensor 202 passes through the movement groove 201 and extends to the outside to facilitate the connection of equipment.

[0034] Further Figure 1-7 As shown, a mounting groove is provided in the middle of the rope mounting seat 21, and the mounting groove is open upward, and the winding shaft 22 is rotatably installed through the mounting groove, and the length of the mounting groove is greater than the length of the winding shaft 22 to avoid jamming, and two measuring weights 211 are fixedly connected to the bottom surface of the rope mounting seat 21, and the two measuring weights 211 are symmetrically distributed about the transverse center line of the bottom surface of the rope mounting seat 21, and the positions of the two measuring weights 211 correspond to the positions of the two moving grooves 201, and the rope mounting seat 21 is installed in the moving groove 201 in the slide rail 20 through the two measuring weights 211, wherein each measuring weight 211 is fixedly connected to a plurality of supporting springs 212 at the bottom, and the plurality of supporting springs 212 are linearly and evenly spaced on the bottom surface of the measuring weight 211, wherein the plurality of supporting springs 212 are alternately arranged with the plurality of spoke-type load sensors 202 during actual installation, and the bottom end of each supporting spring 212 at the bottom of the two measuring weights 211 is fixedly connected to the inner bottom surface of the moving groove 201;

[0035] Furthermore, a mounting cavity 213 is provided on the mounting wall at the right end of the sling mounting seat 21, and the transmission shaft of the electric motor 24 is arranged through the middle of the mounting cavity 213, and the transmission shaft of the electric motor 24 is connected to the winding shaft 22, and electric telescopic rods 215 are installed at both ends of the mounting cavity 213, and the two electric telescopic rods 215 are arranged opposite to each other and are located in the middle position, the upper electric telescopic rod 215 moves downward, and its telescopic rod is connected to a first brake plate 216, and the first brake plate 216 is semicircular, and positioning guide pillars are symmetrically arranged on both sides of the bottom surface of the first brake plate 216, and the electric The telescopic rod 215 moves upward, and the telescopic rod is connected to a second brake plate 218. The second brake plate 218 is semicircular, and positioning circular grooves are symmetrically provided on both sides of the top surface of the second brake plate 218. The positioning guide column is adapted to the positioning circular groove. Through the assembly of the positioning guide column and the positioning circular groove, the first brake plate 216 and the second brake plate 218 are ensured to be accurately fitted to avoid offset and affect braking. The inner side surfaces of the first brake plate 216 and the second brake plate 218 are fixedly connected with brake pads 217. The cooperation of the upper and lower brake pads 217 controls the transmission shaft of the electric motor 24.

[0036] Among them Figure 7 As shown, a plurality of heat dissipation holes 214 are provided on one side of the installation cavity 213 close to the electric motor 24 for dissipating the heat generated by braking.

[0037] like Figure 2 As shown, a wire rope 221 is orderly wound around the middle of the winding shaft 22, a hook 222 is connected to the other end of the wire rope 221, and a second alarm is arranged on the front of the hook 222 to warn the bottom staff and avoid safety accidents, wherein the hook 222 is also provided with a buckle to prevent the heavy objects from falling off during the lifting process.

[0038] The PLC controller 26 in the entire overload control assembly 2 is electrically connected to the electric motor 24, the electric telescopic rod 215, the spoke-type load sensor 202, the first alarm 23 and the second alarm.

[0039] Furthermore, if Figure 2 As shown, a certain gap is left between the bottom surface of the support seat 25 and the top surface of the slide rail 20 to avoid affecting the vertical movement of the suspension rope mounting seat 21.

[0040] Embodiment 2:

[0041] The working method of the overload control device is:

[0042] When heavy objects need to be hoisted, the PLC controller 26 first starts the electric motor 24, drives the reel 22 to rotate, releases the wire rope 221, and the hook 222 falls vertically. When the height reaches the set position from the ground, the PLC controller 26 stops the electric motor 24 and waits for the bottom staff to install the heavy objects.

[0043] When the installation of the heavy object is completed, the PLC controller 26 activates the second alarm to remind the bottom workers to stay away, and then the PLC controller 26 activates the electric motor 24 to drive the reel 22 to rotate, tighten the wire rope 221, and lift the heavy object;

[0044] When the weight is overloaded, the wire rope 221 pulls the rope mounting seat 21 to squeeze the spoke load sensor 202. The spoke load sensor 202 transmits an overload weight signal to the PLC controller 26. The PLC controller 26 disconnects the power supply of the electric motor 24 and starts the two electric telescopic rods 215 at the same time, driving the first brake plate 216 and the second brake plate 218 to enclose the drive shaft of the electric motor 24 for braking to prevent the electric motor 24 from being in an extreme motion state and causing damage to the electric motor 24. At the same time, it prevents the weight from falling rapidly and causing damage. When the PLC controller 26 disconnects the power supply of the electric motor 24, it starts the first alarm 23 to remind the staff in the tower crane operating room that it is overloaded and to stop operating.

[0045] In the description of the present invention, it should be understood that the terms "upper", "lower", "left", "right", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, and a specific direction structure and operation, and therefore, cannot be understood as a limitation on the present invention. In addition, "first" and "second" are only for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0046] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0047] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. An overload control device for a tower crane using a spoke-type load sensor, comprising an overload control component (2), the overload control component (2) being slidably mounted on a tower crane boom support, characterized in that: The overload control assembly (2) comprises a slide rail (20), a rope mounting seat (21) and an electric motor (24). The two slide rails (20) are matched with the rope mounting seat (21) on the top. A reel (22) is installed in the rope mounting seat (21). A steel wire rope (221) is reeled in the reel (22) for lifting heavy objects. A first alarm (23) is fixedly installed on the top surface of the right side of the rope mounting seat (21) for alerting the staff in the tower crane operating room. A support seat (25) is fixedly connected to the bottom of the side of the rope mounting seat (21). A An electric motor (24) is installed, wherein a PLC controller (26) is installed at the front end of the electric motor (24) for controlling the entire lifting process; a hook (222) is connected to the other end of the steel wire rope (221), and a second alarm is arranged on the front of the hook (222) for alerting the bottom staff; a spoke-type load sensor (202) is installed inside the slide rail (20), and a weight measuring block (211) is fixedly connected to the bottom surface of the rope mounting seat (21), and the weight measuring block (211) contacts the spoke-type load sensor (202) during lifting, so as to accurately detect the weight of the lifted heavy object; Two electric telescopic rods (215) are arranged inside the suspension rope mounting seat (21), the upper electric telescopic rod (215) is connected to a first brake plate (216), and the lower electric telescopic rod (215) is connected to a second brake plate (218), wherein the inner sides of the first brake plate (216) and the second brake plate (218) are fixedly connected to brake pads (217), and the transmission shaft of the electric motor (24) is braked and controlled by the cooperation of the upper and lower brake pads (217); The slide rails (20) are provided with two, each of which has a movement groove (201) in the middle of the top surface thereof, and the movement grooves (201) are in an inverted T-shape; The first brake plate (216) and the second brake plate (218) are both semicircular; The PLC controller (26) in the entire overload control assembly (2) is electrically connected to the electric motor (24), the electric telescopic rod (215), the spoke-type load sensor (202), the first alarm (23) and the second alarm; The working method of the overload control device is: When a heavy object needs to be hoisted, the PLC controller (26) starts the electric motor (24), drives the reel (22) to rotate, releases the wire rope (221), and causes the hook (222) to fall vertically. When the height reaches a set position above the ground, the PLC controller (26) stops the electric motor (24) and waits for the bottom staff to install the heavy object. When the installation of the heavy object is completed, the PLC controller (26) activates the second alarm to remind the bottom workers to stay away, and then the PLC controller (26) activates the electric motor (24) to drive the reel (22) to rotate, tighten the wire rope (221), and lift the heavy object; When the weight is overloaded, the steel wire rope (221) pulls the rope mounting seat (21) to squeeze the spoke-type load sensor (202), and the spoke-type load sensor (202) transmits an overload weight signal to the PLC controller (26). The PLC controller (26) disconnects the power supply of the electric motor (24) and simultaneously starts the two electric telescopic rods (215), driving the first brake plate (216) and the second brake plate (218) to enclose the transmission shaft of the electric motor (24) to brake, thereby preventing the electric motor (24) from being in an extreme motion state and causing damage to the electric motor (24), and at the same time preventing the weight from falling rapidly and causing damage. When the PLC controller (26) disconnects the power supply of the electric motor (24), the first alarm (23) is started to remind the staff in the tower crane operation room that the tower crane is overloaded and stops the operation.

2. The tower crane overload control device using a spoke-type load sensor as described in claim 1 is characterized in that: A plurality of spoke-type load sensors (202) are installed in the middle of each of the two movement slots (201), and the plurality of spoke-type load sensors (202) are distributed at equal intervals.

3. The tower crane overload control device using a spoke-type load sensor as described in claim 2 is characterized in that: The joint end of each spoke-type load sensor (202) passes through the movement slot (201) and extends to the outside.

4. The tower crane overload control device using a spoke-type load sensor as described in claim 3 is characterized in that: Two weight measuring blocks (211) are fixedly connected to the bottom surface of the suspension rope mounting seat (21), and the positions of the two weight measuring blocks (211) correspond to the positions of the two movement slots (201).

5. The tower crane overload control device using a spoke-type load sensor as described in claim 4 is characterized in that: A plurality of support springs (212) are fixedly connected to the bottom of each weight measuring block (211), and the plurality of support springs (212) are linearly and evenly spaced.

6. The overload control device for a tower crane using a spoke-type load sensor as described in claim 1, characterized in that: Positioning guide pillars are symmetrically arranged on both sides of the bottom surface of the first brake plate (216), and positioning circular grooves are symmetrically opened on both sides of the top surface of the second brake plate (218), and the positioning guide pillars are adapted to the positioning circular grooves.