Oil-air cooler cleanliness treatment system and oil-air cooler cleaning method

Through the circulation flushing system of clean water and cleaning fluid and the high-pressure and high-temperature fan drying technology, the problem of difficult cleaning of impurities and dirt inside the oil air cooler is solved, the cleaning efficiency and equipment lifespan are improved, and the cost is reduced.

CN113936890BActive Publication Date: 2024-10-11ZHEJIANG ERG TECH
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202111207070.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-15
Publication Date
2024-10-11
Estimated Expiration
2041-10-15

AI Technical Summary

Technical Problem

During the operation of the existing oil air cooler, it is difficult to thoroughly clean the internal impurities and pipe wall dirt, which affects the cooling effect, and the hot oil flushing cost is high and takes a long time.

Method used

An oil air cooler cleanliness treatment system including a clean water flushing tank and a cleaning fluid flushing tank is designed. It is flushed through the cleaning fluid and clean water circulation, combined with the drying system, using high-pressure and high-temperature fans for drying, and setting up liquid level gauges, temperature sensors and Flow meters control the cleaning process automatically.

Benefits of technology

It achieves thorough cleaning of impurities and dirt inside the oil air cooler, shortens cleaning time, reduces costs, and extends the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113936890B_ABST
    Figure CN113936890B_ABST
Patent Text Reader

Abstract

The present invention discloses a cleanliness treatment system for an oil-air cooler with thorough cleaning, good cleanliness and high cleaning efficiency, which comprises a flushing system and a drying system; the flushing system comprises a clean water flushing tank and a cleaning liquid flushing tank; an A water pump connected to an A flushing pipeline is provided at the inlet of the clean water flushing tank, and the outlet is connected to a B flushing pipeline; an A heater, an A thermometer and an A filter are provided in the clean water flushing tank; a B water pump connected to an A flushing pipeline is provided at the inlet of the cleaning liquid flushing tank, and the outlet is connected to a B flushing pipeline; a B heater, a B thermometer and a B filter are provided in the cleaning liquid flushing tank; the A flushing pipeline and the B flushing pipeline are used to connect the oil-air cooler to be cleaned; the A water pump and the B water pump are electrically connected to a control system; the drying system is used to dry the cleaned oil-air cooler. Correspondingly, the present invention also provides a cleaning method for an oil-air cooler.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of oil-air coolers, and in particular to an oil-air cooler cleanliness processing system and an oil-air cooler cleaning method. Background Art

[0002] As one of the most core electrical equipment in the power system, the safe operation of the transformer is directly related to the safety and stability of the power grid. When the transformer is running, the loss in the winding and the core will generate a lot of heat. The generated heat must be dissipated in time to avoid overheating and insulation damage. Therefore, the cooler has become an indispensable auxiliary facility in the operation of the transformer. The cooler is a type of heat exchange equipment used to cool the fluid, usually using water or air as a coolant to remove heat; it can be mainly divided into shell and tube coolers, plate coolers and air-cooled coolers. Among them, the oil-air cooler is widely used in large transformers, and its cooling performance maintains the normal working oil temperature of the transformer, so that the transformer can maintain normal operation. However, during the operation of the existing oil-air cooler, impurities and dirt will be generated inside. Once these impurities and dirt are too much, they will cause internal blockage and affect the cooling effect. For this reason, we need to clean the inside of the oil-air cooler from time to time, and its cleanliness is the key to affecting the normal operation of the transformer.

[0003] At present, the conventional transformer oil-air cooler in the industry is flushed with 35KV transformer oil. The cleanliness treatment process is as follows: the transformer oil is heated to about 70 degrees, and the hot oil is pumped out by the oil pump to flush the cooler. The return oil after flushing is filtered by a vacuum filter and a plate oil filter and then recycled (such as Figure 1 The oil cooler is cleaned by hot oil, which is expensive and time-consuming, and the oil is viscous and difficult to clean. Summary of the invention

[0004] The purpose of the present application is to provide an oil-air cooler cleanliness processing system to overcome the above-mentioned problems existing in the prior art. The oil-air cooler cleanliness processing system of the present application can effectively flush away impurities inside the oil-air cooler and dirt on the pipe wall, and the cleaning is thorough, the cleanliness is good, and the cleaning efficiency is high. Correspondingly, the present application also provides an oil-air cooler cleaning method.

[0005] As for the treatment system, the technical solution of the present application is: an oil-air cooler cleanliness treatment system, including a flushing system and a drying system; the flushing system includes a clean water flushing tank and a cleaning liquid flushing tank; an A water pump is provided at the inlet of the clean water flushing tank, the A water pump is connected to the A flushing pipeline, the outlet of the clean water flushing tank is connected to the B flushing pipeline, and the clean water flushing tank is provided with an A heater, an A thermometer and an A filter; a B water pump is provided at the inlet of the cleaning liquid flushing tank, the B water pump is connected to the A flushing pipeline, the outlet of the cleaning liquid flushing tank is connected to the B flushing pipeline, and the cleaning liquid flushing tank is provided with a B heater, a B thermometer and a B filter; the A flushing pipeline and the B flushing pipeline are used to connect the oil-air cooler to be cleaned; the A water pump and the B water pump are electrically connected to the control system; the drying system is used to dry the cleaned oil-air cooler.

[0006] Compared with the prior art, the oil-air cooler cleanliness processing system of the present application can use cleaning liquid to flush the oil-air cooler by setting a cleaning liquid flushing pool and a clean water flushing pool, flushing away impurities inside the cooler and dirt on the pipe wall, and after the cleaning liquid flushing is completed, use clean water to flush away the cleaning liquid remaining inside the cooler, thereby improving the cleaning quality, achieving good cleaning effect, and shortening the cleaning operation time; by setting a filter net inside the clean water flushing pool and the cleaning liquid flushing pool to filter out impurities in the cleaning liquid and clean water, the cleaning liquid and clean water can be recycled, which helps to reduce the cleaning cost; by setting a drying system to dry the inside of the cooler, it can prevent the accumulation of water inside the oil-air cooler after cleaning from damaging it, thereby ensuring the service life of the oil-air cooler.

[0007] As an optimization, the drying system includes a high-pressure and high-temperature fan, and the air outlet of the high-pressure and high-temperature fan is connected to a ventilation pipeline, and the ventilation pipeline is used to connect the oil-air cooler to be dried after cleaning. The high-temperature and high-pressure fan operates with little or no oil, and the output air is clean. Using a high-pressure and high-temperature fan to dry the oil-air cooler will not cause pollution to the inside of the cooler, and it is easy to install and easy to operate.

[0008] As an optimization, the clean water flushing pool is provided with a liquid level gauge A, and the cleaning liquid flushing pool is provided with a liquid level gauge B. Therefore, the staff can observe the liquid level in the clean water flushing pool and the cleaning liquid flushing pool through the liquid level gauge. When the liquid level is lower than a certain height, the cleaning is stopped, and the staff adds clean water or cleaning liquid to the clean water flushing pool and the cleaning liquid flushing pool to ensure the smooth cleaning of the cooler.

[0009] As an optimization, three A filters are provided in the clean water flushing tank, and three B filters are provided in the cleaning liquid flushing tank. Furthermore, the three A filters separate the clean water flushing tank into A liquid inlet chamber, A liquid outlet chamber and A intermediate chamber; the three B filters separate the cleaning liquid flushing tank into B liquid inlet chamber, B liquid outlet chamber and B intermediate chamber. At this time, the cleaning liquid and clean water after flushing the cooler can be filtered three times to avoid impurities in the liquid, thereby further ensuring the cleaning quality of the oil-air cooler.

[0010] As an optimization, the A water pump is connected to the A flushing pipeline through the A connecting pipeline, and the A electric valve is provided on the A connecting pipeline. The outlet of the clean water flushing pool is connected to the B flushing pipeline through the B connecting pipeline, and the B electric valve is provided on the B connecting pipeline; the B water pump is connected to the A flushing pipeline through the C connecting pipeline, and the C electric valve is provided on the C connecting pipeline. The outlet of the cleaning liquid flushing pool is connected to the B flushing pipeline through the D connecting pipeline, and the D electric valve is provided on the D connecting pipeline; the A electric valve, B electric valve, C electric valve, and D electric valve are all electrically connected to the control system.

[0011] As an optimization, a flow meter is provided on the A flushing pipeline to detect the flow rate of clean water or cleaning liquid flowing through the A flushing pipeline. When the detected flow rate does not meet the requirements, the control system sends a signal to adjust the A electric valve or the C electric valve to increase the flow rate, so that cleaning can proceed smoothly and ensure the cleaning effect.

[0012] As an optimization, a liquid level sensor is provided in the clean water rinsing tank and the cleaning liquid rinsing tank, and the liquid level sensor is electrically connected to the control system. The liquid level sensor monitors the liquid level in the clean water rinsing tank and the cleaning liquid rinsing tank in real time. When the liquid level drops below the set value, the control system sends a command to stop cleaning and issues an alarm to remind the staff to add clean water or cleaning liquid in time. At this time, the degree of automation is high and the labor intensity of the staff can be reduced.

[0013] As an optimization, a temperature sensor is provided in the clean water rinsing pool and the cleaning liquid rinsing pool, and the temperature sensor is electrically connected to the control system. At this time, the temperature sensor can be used to detect whether the liquid temperature in the clean water rinsing pool and the cleaning liquid rinsing pool reaches the set value, without the need for the staff to stare at the thermometer in real time, which greatly saves the staff's time.

[0014] As for the method, the technical solution of the present application is: an oil-air cooler cleaning method, which uses the aforementioned oil-air cooler cleanliness processing system of the present application to flush and dry the oil-air cooler, and the cleaning process is as follows: connect the A flushing pipeline and the B flushing pipeline to the inlet and outlet of the oil-air cooler to be cleaned respectively, and set the flushing time and drying time in the control system; when flushing, start the B heater, heat the cleaning liquid in the cleaning liquid flushing pool to 60℃±5 (observe the temperature value on the B thermometer), and the control system controls the B water pump to turn on to flush the oil-air cooler. Wash; after flushing for T1 hour, the control system controls the B water pump to turn off, and at the same time turns off the B heater, starts the A heater, heats the clean water in the clean water flushing pool to 60℃±5, and the control system controls the A water pump to open, and flushes the oil-air cooler; after flushing for T2 hours, the control system controls the A water pump to turn off, and at the same time turns off the A heater; after the flushing is completed, the oil-air cooler is removed and connected to the drying system, and the drying system dries the inside of the oil-air cooler until all the accumulated water inside it is vaporized and dried; after drying is completed, the oil-air cooler is removed, and the entire cleaning process is completed.

[0015] Compared with the prior art, the oil-air cooler cleaning method of the present application first uses a cleaning liquid to circulate and flush the oil-air cooler for a period of time to flush away impurities inside the cooler and dirt on the tube wall; after the flushing with the cleaning liquid is completed, the oil-air cooler is circulated and flushed with clean water for a period of time to flush away the cleaning liquid remaining inside the cooler; finally, the oil-air cooler is dried by a drying system to blow dry the accumulated water inside the cooler, and the cleaning is completed; this method can effectively and thoroughly clean the interior of the oil-air cooler, and the cleaning effect is good. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 is a schematic diagram of a cooler hot oil flushing system in the prior art;

[0017] Figure 2 is a schematic diagram of the flushing system in the present application;

[0018] Figure 3 is a schematic diagram of the drying system in this application.

[0019] The markings in the attached figure are: 1-clean water flushing tank, 101-A liquid inlet chamber, 102-A liquid outlet chamber, 103-A intermediate chamber; 2-clean liquid flushing tank, 101-B liquid inlet chamber, 102-B liquid outlet chamber, 103-B intermediate chamber; 3-A water pump; 4-A flushing pipeline; 5-B flushing pipeline; 6-A heater; 7-A thermometer; 8-A filter; 9-B water pump; 10-B heater; 11-B thermometer; 12-B filter; 13-oil-air cooling device; 14-control system; 15-high temperature and high pressure fan; 16-ventilation pipeline; 17-A liquid level gauge; 18-B liquid level gauge; 19-flow meter; 20-A connecting pipeline; 21-A electric valve; 22-B connecting pipeline; 23-B electric valve; 24-C connecting pipeline; 25-C electric valve; 26-D connecting pipeline; 27-D electric valve; 28-control system; 29-oil pump; 30-oil storage cabinet; 31-vacuum filter; 32-plate filter; 33-filter screen. DETAILED DESCRIPTION

[0020] The present application is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present application.

[0021] Example:

[0022] See also Figure 2 and Figure 3 The oil-air cooler cleanliness treatment system of the present application includes a flushing system and a drying system; the flushing system includes a clean water flushing tank 1 and a cleaning liquid flushing tank 2; an A water pump 3 is provided at the outlet of the clean water flushing tank, the A water pump 3 is connected to the A flushing pipeline 4, the inlet of the clean water flushing tank 1 is connected to the B flushing pipeline 5, and the clean water flushing tank 1 is provided with an A heater 6, an A thermometer 7 and an A filter 8; a B water pump 9 is provided at the outlet of the cleaning liquid flushing tank 2, the B water pump 9 is connected to the A flushing pipeline 4, the inlet of the cleaning liquid flushing tank 2 is connected to the B flushing pipeline 5, and the cleaning liquid flushing tank 2 is provided with a B heater 10, a B thermometer 11 and a B filter 12; the A flushing pipeline 4 and the B flushing pipeline 5 are used to connect the oil-air cooler 13 to be cleaned; the A water pump 3 and the B water pump 9 are electrically connected to the control system 14; the drying system is used to dry the cleaned oil-air cooler.

[0023] In this embodiment, the drying system includes a high-pressure and high-temperature fan 15, and the air outlet of the high-pressure and high-temperature fan 15 is connected to a ventilation pipeline 16, and the ventilation pipeline 16 is used to connect the oil-air cooler 13 to be dried after cleaning. The high-temperature and high-pressure fan 15 is operated with little or no oil, and the output air is clean. The high-pressure and high-temperature fan 15 is used to dry the oil-air cooler 13 without polluting the inside of the cooler, and is easy to install and easy to operate.

[0024] In this embodiment, the clean water flushing pool 1 is provided with a liquid level gauge A 17, and the clean liquid flushing pool 2 is provided with a liquid level gauge B 18. Therefore, the staff can observe the liquid levels in the clean water flushing pool 1 and the clean liquid flushing pool 2 through the liquid level gauges. When the liquid levels are lower than a certain height, the cleaning is stopped, and the staff adds clean water or clean liquid to the clean water flushing pool 1 or the clean liquid flushing pool 2 to ensure the smooth cleaning of the cooler.

[0025] In this embodiment, liquid level sensors are provided in the clean water washing pool 1 and the cleaning liquid washing pool 2, and the liquid level sensors are electrically connected to the control system 14. The liquid level sensors monitor the liquid levels in the clean water washing pool 1 and the cleaning liquid washing pool 2 in real time. When the liquid level drops below a set value, the control system 14 sends an instruction to stop cleaning and issues an alarm to remind the staff to add clean water or cleaning liquid in time. At this time, the degree of automation is high and the labor intensity of the staff can be reduced.

[0026] In this embodiment, temperature sensors are provided in the clean water rinsing pool 1 and the cleaning liquid rinsing pool 2, and the temperature sensors are electrically connected to the control system 14. At this time, the temperature sensors can be used to detect whether the liquid temperature in the clean water rinsing pool 1 and the cleaning liquid rinsing pool 2 reaches the set value, without the need for the staff to stare at the thermometer in real time, which greatly saves the staff's time.

[0027] In this embodiment, a flow meter 19 is provided on the A flushing pipeline 4 for detecting the flow rate of clean water or cleaning liquid flowing through the A flushing pipeline 4. When the detected flow rate does not meet the requirements, the control system 14 sends a signal to adjust the A electric valve 21 or the C electric valve 24 to increase the flow rate, so that cleaning can proceed smoothly and ensure the cleaning effect.

[0028] In this embodiment, three A filters 8 are provided in the clean water washing pool 1, and three B filters 12 are provided in the cleaning liquid washing pool 2. The A filters 8 divide the clean water washing pool 1 into an A liquid inlet chamber 101, an A liquid outlet chamber 102, and an A intermediate chamber 103; the B filters 12 divide the cleaning liquid washing pool 2 into a B liquid inlet chamber 201, a B liquid outlet chamber 202, and a B intermediate chamber 203. The A liquid outlet chamber 102 is connected to the A water pump 3; the A heater 6 is provided in the A liquid inlet chamber 101, the A liquid outlet chamber 102, and the A intermediate chamber 103; the B liquid outlet chamber 202 is connected to the B water pump 9; the B liquid inlet chamber 201, the B liquid outlet chamber 202, and the B intermediate chamber 203 are provided with a B heater 10. At this time, the cleaning liquid and clean water after flushing the cooler can be filtered three times to avoid the presence of impurities in the liquid, thereby further ensuring the cleaning quality of the oil-air cooler 13.

[0029] In this embodiment, the A water pump 3 is connected to the A flushing pipeline 4 through the A connecting pipeline 20, and the A connecting pipeline 20 is provided with an A electric valve 21. The outlet of the clean water flushing pool 1 is connected to the B flushing pipeline 5 through the B connecting pipeline 22, and the B connecting pipeline 22 is provided with a B electric valve 23; the B water pump 9 is connected to the A flushing pipeline 4 through the C connecting pipeline 24, and the C connecting pipeline 24 is provided with a C electric valve 25. The outlet of the cleaning liquid flushing pool 2 is connected to the B flushing pipeline 5 through the D connecting pipeline 26, and the D connecting pipeline 26 is provided with a D electric valve 27; the A electric valve 21, the B electric valve 23, the C electric valve 25, and the D electric valve 27 are all electrically connected to the control system 14.

[0030] The oil-air cooler cleaning method uses the oil-air cooler cleanliness processing system in the aforementioned embodiment to flush and dry the oil-air cooler, and the cleaning process is as follows: the A flushing pipeline 4 and the B flushing pipeline 5 are respectively connected to the inlet and outlet of the oil-air cooler 13 to be cleaned, and the flushing time and the drying time are set in the control system 14; when flushing, the B heater 10 is started to heat the cleaning liquid in the cleaning liquid flushing tank 2 (the cleaning liquid uses water as the medium, and a certain proportion of special cleaning agent is added to the water) to 60°C ± 5, and the temperature sensor sends a signal to the control system 14, and the control system 14 controls the B water pump 9 and the C electric Valve 25 and D electric valve 27 are opened, and the cleaning liquid is pumped by B water pump 9 and enters the oil-air cooler 13 through A flushing pipeline 4 to flush the oil-air cooler 13 (after flushing with a special cleaning agent, the surface of the oil-air cooler 13 is protected, and the flushed surface can remain clean for 8 hours without rust). The cleaned cleaning liquid flows out from the inside of the oil-air cooler 13, re-enters the cleaning liquid flushing tank 2 through B flushing pipeline 5, and is filtered by B filter 12 and then pumped by B water pump 9 again to circulate and flush the oil-air cooler 13; after pulse flushing for 1 hour, the control system 14 controls B water pump 9 to close, and at the same time, Turn off the B heater 10, start the A heater 6 (you can also choose to electrically connect the A heater 6 and the B heater 10 to the control system 14, and the control system 14 controls the opening and closing of the heaters, and no manual operation is required), when the clean water in the clean water flushing tank 1 is heated to 60℃±5, the temperature sensor sends a signal to the control system 14, and the control system 14 controls the A water pump 3, the A electric valve 21 and the B electric valve 23 to open, and the clean water is pumped by the A water pump 3, enters the oil-air cooler 13 through the A flushing pipeline 4, and flushes the oil-air cooler 13. The cleaned water flows out from the inside of the oil-air cooler 13 and flows through the B flushing pipeline The washing pipeline 5 re-enters the clean water flushing pool 2, and is filtered by the A filter 8 and then pumped out by the A water pump 3 again to circulate and flush the oil-air cooler 13; after pulse flushing for 0.5 hours, the control system 14 controls the A water pump 3 to turn off, and at the same time turns off the A heater 6; after the flushing is completed, the oil-air cooler 13 is removed and connected to the ventilation pipeline 16; the high-temperature and high-pressure fan 15 is started (a 300-degree high-temperature and high-pressure fan can be used) to blow air into the oil-air cooler 13; after drying for 0.1 hours, all the accumulated water inside the oil-air cooler 13 is vaporized and blown dry, the drying is completed, the oil-air cooler 13 is removed, and the entire cleaning process is completed.

[0031] The above general description of the invention involved in this application and the description of its specific implementation methods should not be understood as limiting the technical solutions of the invention. Based on the disclosure of this application, those skilled in the art can add, reduce or combine the disclosed technical features in the above general description and / or specific implementation methods (including examples) without violating the constituent elements of the invention involved, to form other technical solutions within the scope of protection of this application.

Claims

1. The oil-air cooler cleaning method is characterized in that: The method uses an oil-air cooler cleanliness treatment system to rinse and dry the oil-air cooler. The oil-air cooler cleanliness treatment system comprises a rinse system and a drying system. The rinse system comprises a clean water rinse tank (1) and a clean liquid rinse tank (2). An A water pump (3) is provided at the outlet of the clean water rinse tank. The A water pump (3) is connected to an A rinse pipeline (4). The inlet of the clean water rinse tank (1) is connected to a B rinse pipeline (5). An A heater (6), an A thermometer (7) and an A filter (8) are provided in the clean water rinse tank (1). The clean liquid rinse tank (2) comprises a clean water rinse tank (1) and a clean water rinse tank (2). A B water pump (9) is provided at the outlet of the pool (2), the B water pump (9) is connected to the A flushing pipeline (4), the inlet of the cleaning liquid flushing pool (2) is connected to the B flushing pipeline (5), and a B heater (10), a B thermometer (11) and a B filter (12) are provided in the cleaning liquid flushing pool (2); the A flushing pipeline (4) and the B flushing pipeline (5) are used to connect to the oil-air cooler (13) to be cleaned; the A water pump (3) and the B water pump (9) are electrically connected to the control system (14); the drying system is used to dry the cleaned oil-air cooler (13); The cleaning process is as follows: the A flushing pipeline (4) and the B flushing pipeline (5) are respectively connected to the inlet and outlet of the oil-air cooler to be cleaned, and the flushing time and the drying time are set in the control system (14); during flushing, the B heater (10) is started to heat the cleaning liquid in the cleaning liquid flushing tank (2) to 60°C±5, and the control system (14) controls the B water pump (9) to start and flush the oil-air cooler (13); after flushing for T1 hour, the control system (14) controls the B water pump (9) to turn off, and at the same time turns off the B heater (10), and starts the A heater ( 6), the clean water in the clean water flushing tank (1) is heated to 60°C ± 5, and the control system (14) controls the A water pump (3) to open to flush the oil-air cooler (13); after flushing for T2 hours, the control system (14) controls the A water pump (3) to close, and at the same time, turns off the A heater (6); after the flushing is completed, the oil-air cooler (13) is removed and connected to the drying system, and the drying system dries the inside of the oil-air cooler (13) until all the accumulated water inside is vaporized and dried; after the drying is completed, the oil-air cooler (13) is removed, and the entire cleaning process is completed.

2. The oil-air cooler cleaning method according to claim 1, characterized in that: The drying system comprises a high-pressure and high-temperature fan (15), the air outlet of the high-pressure and high-temperature fan (15) is connected to a ventilation pipeline (16), and the ventilation pipeline (16) is used to connect to the oil-air cooler (13) to be dried after cleaning.

3. The oil-air cooler cleaning method according to claim 1, characterized in that: The A water pump (3) is connected to the A flushing pipeline (4) through the A connecting pipeline (20), and the A electric valve (21) is provided on the A connecting pipeline (20); the outlet of the clean water flushing pool (1) is connected to the B flushing pipeline (5) through the B connecting pipeline (22), and the B electric valve (23) is provided on the B connecting pipeline (22); the B water pump (9) is connected to the A flushing pipeline (4) through the C connecting pipeline (24), and the C electric valve (25) is provided on the C connecting pipeline (24); the outlet of the cleaning liquid flushing pool (2) is connected to the B flushing pipeline (5) through the D connecting pipeline (26), and the D electric valve (27) is provided on the D connecting pipeline (26); the A electric valve (21), the B electric valve (23), the C electric valve (25), and the D electric valve (27) are all electrically connected to the control system (14).

4. The oil-air cooler cleaning method according to claim 1, characterized in that: The clean water flushing tank (1) is provided with an A liquid level gauge (17), and the cleaning liquid flushing tank (2) is provided with a B liquid level gauge (18).

5. The oil-air cooler cleaning method according to claim 1, characterized in that: The A flushing pipeline (4) is provided with a flow meter (19).

6. The oil-air cooler cleaning method according to claim 1, characterized in that: The clean water flushing pool (1) is provided with three A filter screens (8), and the cleaning liquid flushing pool (2) is provided with three B filter screens (12).

7. The oil-air cooler cleaning method according to claim 6, characterized in that: The three A filter nets (8) divide the clean water flushing pool (1) into an A liquid inlet chamber (101), an A liquid outlet chamber (102) and an A intermediate chamber (103); the three B filter nets (12) divide the clean liquid flushing pool (2) into a B liquid inlet chamber (201), a B liquid outlet chamber (202) and a B intermediate chamber (203).

8. The oil-air cooler cleaning method according to claim 1, characterized in that: Liquid level sensors are provided in the clean water flushing tank (1) and the cleaning liquid flushing tank (2), and the liquid level sensors are electrically connected to the control system (14).

9. The oil-air cooler cleaning method according to claim 1, characterized in that: Temperature sensors are provided in the clean water flushing pool (1) and the cleaning liquid flushing pool (2), and the temperature sensors are electrically connected to the control system (14).

Citation Information

Patent Citations

  • Cleaning device for forced oil circulation water cooling transformer water cooler

    CN105321666A

  • Automatic cleaning line

    CN106216320A

  • Air cooler cleaning system for wind driven generator

    CN106733859A

  • Oil cooler's cleaning system

    CN205762761U

  • Cooler inner cavity cleaning system for transformer

    CN210535471U