Method for monitoring a compressor of a rail brake system
By monitoring the pressure characteristics in the rail braking system, determining the ignition and shutdown moments of the compressor, and calculating the filling rate and duty cycle, the problems of inaccurate maintenance cycle prediction and lack of direct status information in the existing technology are solved, and the control of the compressor is realized. Accurate compressor health assessment and maintenance cycle optimization reduce damage risks and costs.
Patent Information
- Application Number
- CN202080046337.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2019-06-24
- Filing Date
- 2020-06-19
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2040-06-19
AI Technical Summary
In existing rail braking systems, the maintenance cycle of the compressor is difficult to accurately predict, resulting in potentially serious damage and high life cycle costs. The lack of direct ignition or shutdown status information affects the efficiency of the braking system.
By monitoring the pressure characteristics of the main tank and auxiliary tank, the ignition and shutdown moments of the compressor are determined, the filling rate and duty cycle are calculated, the health status and service life of the compressor are evaluated in real time, and the maintenance cycle and monitoring system are optimized.
It achieves accurate assessment of the service life of the compressor and dynamic adjustment of the maintenance cycle, reduces potential damage risks and life cycle costs, and improves the efficiency and reliability of the braking system.
Smart Images

Figure CN114026003B_ABST
Abstract
Description
Technical Field
[0001] The present invention generally belongs to the field of rail brake systems; in particular, the present invention relates to a method for monitoring a compressor of a rail brake system. Background Art
[0002] In rail transit systems, known brake systems use compressed air appropriately injected into brake cylinders to generate braking force. The compressed air is generated by one or more compressors.
[0003] Figure 1 An example of a known rail brake system is shown. This example has been greatly simplified and is used only in an illustrative manner.
[0004] The air generation and treatment unit (AGTU) 100 includes a compressor 101 and a dryer assembly 102 arranged downstream of the compressor 101. The dryer assembly 102 is intended to separate water in liquid and gaseous states from the compressed air. The dryer assembly 102 typically includes one or more cyclone separators for removing liquid water, and a salt or aluminum drying system for removing gaseous water.
[0005] The compressed air generated by the AGTU group 100 is collected in the main tank 104 through the check valve 103 .
[0006] The main tank 104 then supplies the main pipe 105, which distributes the compressed air to one or more braking subsystems 106, 107 arranged along the train through check valves 109, 110... The main pipe 105 also distributes the compressed air to one or more pneumatic suspension systems 108 through a check valve 111. The pneumatic suspension system 108 is arranged between the car body and the bogie that constitute the train (not shown in the figure).
[0007] The pneumatic suspension system 108 generally comprises an auxiliary tank 112, a leveling valve 113, a bellows 114 and a pressure sensing device 115. The bellows 114 is mechanically arranged between the associated bogie and the vehicle body (not shown in the figure) to act as a suspension. The distance between the vehicle body and the bogie depends on the pressure existing inside the bellows 114. In order to keep the distance between the vehicle body and the bogie at a constant value as the weight of the vehicle body changes (corresponding to the change in the weight of the passengers), the distance-sensitive leveling valve 113 between the associated bogie and the vehicle body acts, and when the distance tends to decrease due to an increase in weight, the leveling valve 113 acts by increasing the pressure in the bellows 114, and when the distance tends to increase due to a decrease in weight, the leveling valve 113 acts by reducing the pressure in the bellows 114 by partially discharging the gas in the bellows to the atmosphere.
[0008] The brake subsystem 106, 107, ... typically includes an auxiliary tank 116, 117, ... that supplies a brake control system 118, 119, ...
[0009] The brake control system 118, 119 in turn comprises an electronic unit 120, 121, ... and a pneumatic panel 122, 123, ...
[0010] The pressure sensing devices 124, 125 send electrical signals 126, 127 to the electronic units 120, 121, which are representative of the instantaneous pressure value present in the auxiliary tanks 116, 117. The pressure sensing device or devices 115 measure the pressure in the bellows 114 and send electrical signals 135 to inputs 128, 129, ... of the electronic units 120, 121.
[0011] In current brake systems, the pressure sensing devices 124, 125, ... are usually integrated inside the pneumatic panels 122, 123, ...
[0012] In addition, the latest brake control systems 118, 119 are composed of highly integrated devices, such as shown in EP3328698, in which the pressure sensor device 9a is equivalent to Figure 1 The pressure sensor devices 124, 125 in.
[0013] The hysteresis pressure switch 130 measures the pressure existing at the outlet of the main tank 104. When the measured pressure is less than the hysteresis lower limit value, the hysteresis pressure switch 130 energizes the remote control switch 131 to supply power to the compressor 101. When the pressure reaches and exceeds the hysteresis upper limit value, the hysteresis pressure switch 130 de-energizes the remote control switch 131 to interrupt the supply to the compressor 101. The hysteresis value used in rail applications is generally assumed to be between 2 bar and 3 bar, and the maximum pressure value is generally between 9 bar and 10 bar.
[0014] The maximum pressure reached inside the auxiliary tanks 116, 117, 112 always corresponds to the maximum pressure reached by the main tank 104, i.e. to the upper hysteresis value of the hysteresis pressure switch 130 minus the pressure drop caused by the non-return valves 109, 110, 111. However, for the purposes of the present invention, said pressure drop is considered to be negligible.
[0015] The minimum pressure value achieved inside the auxiliary tanks 116, 117, 112 ... is usually assumed to be different between different auxiliary tanks 116, 117, 112 ..., due to the different air consumption of different brake subsystems 106, 107 ... and pneumatic suspension system 108. Usually, only one of the auxiliary tanks 116, 117, 112 ... reaches a minimum pressure corresponding to the minimum pressure in the main tank 104, which activates the hysteresis pressure switch 130, thereby energizing the remote control switch 131, and then the compressor 101 ignites.
[0016] In the prior art, compressors are maintained according to maintenance cycles that are predetermined at the design stage based on usage predictions, and then remain unchanged throughout the life of the compressor.
[0017] There is an increasing market demand for maintenance of compressors based on concepts known as CBM (condition based maintenance), ie maintenance of compressors based on their actual functional condition which is verified regularly throughout their life cycle.
[0018] Flow measurement is the method used to verify the health of the compressor. The filling time is an indicator of good or poor functioning of the compression sealing elements of the compressor. Filling times greater than the nominal value indicate that these elements are worn and therefore suffer losses during the compression phase, and therefore these elements must be replaced to avoid potentially serious damage to the compressor itself. In this case, the sealing elements must be replaced promptly to avoid any potentially serious damage to the compressor itself.
[0019] A method of flow measurement that can be applied to the compressor 101 during the service life of the compressor on a rail vehicle is to measure the time required by the compressor to bring the pressure from a first initial value to a second final value. The measurement is made based on a reference value that is constant over time, for example the volume represented by the entire pneumatic system, which includes the main tank 104, the pipe 105 and the auxiliary tanks 116, 117, 112. If the initial pressure value and the final pressure value do not repeat from one measurement to another, the correct method is to measure the ratio, with the difference between the final pressure and the initial pressure as the numerator and the difference between the moment of measuring the final pressure and the moment of measuring the initial pressure as the denominator. This ratio is called the flow rate and is proportional to the flow rate of the compressor. A flow rate less than the nominal value indicates that the compression element is worn and therefore suffers losses during the compression phase, which must therefore be replaced.
[0020] Another basic parameter indicating the remaining life of the compressor is the cumulative time spent by the compressor supplying compressed air to the pneumatic system, which can be measured as the sum of the times the compressor has been fired. The analyzed cumulative time can indicate whether the maintenance cycle forecast is overestimated, correct or conservative, while exceeding the limit threshold of the filling time. Therefore, the information obtained may help to re-formulate the maintenance cycle by adapting to the actual use and thus optimizing as much as possible the known "life cycle cost", that is, the cost of the total life of the compressor.
[0021] Finally, the parameter "duty cycle", i.e. the ratio between the cumulative time spent by the compressor supplying compressed air to the pneumatic system and the cumulative operating time of the train, is an important parameter for evaluating the compressor usage. The cumulative operating time of the train is understood to represent the total time that the train is in operation. This value is usually provided by the customer, i.e. the manufacturer of the rail vehicle, to the supplier of the rail system in order to calculate maintenance intervals and agree on warranty terms. The precise measurement of the "duty cycle" allows a precise evaluation of the data originally provided by the manufacturer to the supplier of the brake system and thus a correct assessment in case of customer complaints during the warranty period.
[0022] In the prior art, the state of the hysteresis pressure switch 130, i.e. the state of the remote control switch 131, is unknown to the electronic units 120, 121, ..., since this information is not considered to contribute to the behavior of the brake subsystems 106, 107. Therefore, the electronic units 120, 121 lack direct information about the ignition or shutdown state of the compressor 101.
[0023] BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The functions and structural features of some preferred embodiments of the electronic system for controlling emergency braking and service braking according to the present invention will now be described. With reference to the accompanying drawings, in which:
[0025] - Figure 1 A complete system for a braking system for a railway train is shown;
[0026] - Figure 2 A first example of a fill cycle and a drain cycle of a brake system is shown;
[0027] - Figure 3 A second example of a fill cycle and a drain cycle for a brake system is shown; and
[0028] - Figure 4 A third example of a fill cycle and a drain cycle of a brake system is shown. DETAILED DESCRIPTION
[0029] Before explaining in detail a number of embodiments of the present invention, it should be noted that the application of the present invention is not limited to the design details and configurations of the components present in the following description or shown in the accompanying drawings. The present invention can take other embodiment forms and be implemented or realized in practice in other ways. It should be understood that the words and terms have descriptive purposes and are not intended to be limiting. The use of "include" and "comprising" and their variations are intended to cover given elements and their equivalents, as well as to cover additional elements and their equivalents.
[0030] First reference Figure 2 , which shows that if the auxiliary tanks 116, 117, ... 112 reach the pressure value P at the same time during the discharge phase on The pressure P(t) can be measured by the pressure sensing devices 124 and 125, for example. on Corresponding to the hysteresis lower limit value for switching the hysteresis pressure switch 130. In this case, the compressor 101 fills the main tank 104 and simultaneously fills the auxiliary tanks 116, 117, ... 112 through the main pipe 105.
[0031] The compressor 101 may generally be positive displacement and have a flow rate that is proportional to the rotational speed.
[0032] In the rail industry, compressors are usually driven by asynchronous motors, which are powered at a fixed frequency, usually 50 Hz or 60 Hz, in which case a constant flow rate can be assumed, taking into account that the typical speed slip of asynchronous motors is negligible. In this case, the expected pressure is an almost constant ramp slope.
[0033] By observing the pressure P(t), the ignition time T1 can be identified as the time when the slope of the pressure P(t) changes from a negative value to a positive value. Equivalently, the electronic unit can sample the pressure P(t) signal at a sampling period T and perform a discrete derivative
[0034] (P(nT+1)-P(nT)) / T,
[0035] Therefore, the ignition time T1 is identified as the time when the discrete derivative changes from a negative sign to a positive sign.
[0036] In addition, by observing the pressure P(t), the closing time T2 can be identified as the time when the slope of the pressure P(t) changes from a positive value to zero or a negative value. Equivalently, the electronic units 120, 121 can sample the pressure P(t) signal at a sampling period T and perform a discrete derivative (P(nT+1)-P(nT)) / T, thereby identifying the closing time T2 as the time when the discrete derivative changes from a negative sign to a positive sign.
[0037] In order to prevent the noise present in the electrical signal from producing inappropriate local sign changes, digital filtering techniques for removing noise are known to experts in the field of digital processing, such as but not limited to the application of a simple moving average FIR (finite impulse filter) algorithm.
[0038] In view of the above, a method for monitoring a compressor of a rail brake system according to the present invention is described below.
[0039] The rail brake system comprises an air generation and treatment module AGTU 100, which comprises a compressor 101 and a main tank 104, which is arranged to supply a main pipe 105, which is suitable for distributing compressed air into at least one braking subsystem 106, which comprises an auxiliary tank 116, which is arranged to supply a braking control system 118.
[0040] The method for monitoring a compressor of a rail brake system comprises a step of monitoring a characteristic of at least one pressure value P(t) measured downstream of the main tank 104 or at the outlet of the auxiliary tank 116 .
[0041] The pressure value P(t) may be measured by a pressure sensing device 132 disposed downstream of the main tank 104 or by a pressure sensing device 124 disposed at the outlet end of the auxiliary tank 116 .
[0042] Furthermore, the method for monitoring a compressor comprises a step of acquiring the usage and / or health status of the compressor 101 based solely on the time characteristics of the measured pressure value P(t).
[0043] During the braking phase, there can be different air consumption between the brake systems 118, 119, ... This often happens in practice, for example because different bogies carry different weights and therefore require different brake pressures, resulting in different discharges of the auxiliary tanks 116, 117, ... At the same time, the suspension system consumes air at different times relative to the brake system. In particular, the suspension consumes air as the weight carried by the bogie changes, which usually changes at stations where passengers enter and leave.
[0044] Due to the presence of the check valves 109 , 110 , ... 111 , different auxiliary tanks 116 , 117 , ... 112 cannot compensate each other.
[0045] In this case, only one of the tanks 116, 117, ... 112 reaches the pressure value P on , then restart the compressor.
[0046] Figure 3For example, it is assumed that the three auxiliary tanks 116, 117, and 112 have reached pressure values P at the ignition time T1. on , P1, P2, and assuming that the flow of the compressor 101 is constant, there will be a first stage between the ignition moment T1 and the moment T3, in which only the main tank 104 and the auxiliary tank 116 are filled. When the value P1 is reached at the moment T3, the auxiliary tank 117 is added to the volume to be filled. This leads to an increase in the overall volume, which in turn leads to a decrease in the slope of the broken line curve P(t). In addition, if the pressure P2 is reached at the moment T4, the tank 112 is added to the volume to be filled, thereby also increasing the overall volume and also reducing the slope of the broken line curve P(t). Obviously, when calculating the filling time of the entire device, the slope that must be taken into account must be the slope of the curve segment included between the moment T4 and the closing moment T2, that is, the slope in the time interval after the last change of the slope.
[0047] The method for monitoring a compressor may also preferably include the step of determining that the closing instant T2 of the compressor 101 coincides with the instant when the derivative of the pressure P(t) changes from a positive value to a nominal zero value or a negative value. The closing instant T2 may be determined by the electronic control unit 120 of the brake control system 118 .
[0048] The method may also preferably include the step of determining that the firing instant T1 of the compressor 101 coincides with the instant at which the derivative of the pressure P(t) is measured to change from a negative value or a nominal zero value to a positive value.
[0049] The ignition timing T1 may be determined by the electronic control unit 120 of the brake control system 118 .
[0050] Alternatively, in the presence of a braking system 119 ..., the method may include a step of determining that the ignition time (T1) of the compressor 101 coincides with the smaller of the times T1, T3, T4, the times T1, T3, T4 corresponding to some instantaneous moments at which the respective pressure values P3, P2, P1 of the pressure P(t) are measured and at which the derivative of the pressure P(t) is measured to change from a negative value or a nominal zero value to a positive value. The pressures P1, P2, P3 ... are measured downstream of the plurality of auxiliary tanks 116, 117 ...
[0051] One or more of the times T1, T3, T4 can be detected by a plurality of electronic units 120, 121, ... The electronic units 120, 121 can be interconnected via a communication device 133 and can transmit the times T1, T3, T4, ... detected by each other.
[0052] The further relevant pressures P2, P3, . . . can be measured by corresponding further pressure sensor devices 125, . . .
[0053] The further ignition times T1 , T3 , T4 can be detected by further electronic control units 121 . . . of further brake control systems 119 . . . and can be transmitted from the electronic control unit 120 and the further electronic control unit 121 via the communication device 133 .
[0054] The method may also preferably include the step of calculating the filling rate by a ratio, wherein the numerator of the ratio is the closing pressure value P of the pressure P(t) at the closing time T2. off The difference between the first pressure value P1 of the pressure P(t) at the negative change moment T4, the negative change moment T4 coincides with the moment when the derivative of the pressure P(t) undergoes the last negative change, and the denominator of the ratio is the difference between the closing moment T2 and the negative change moment T4.
[0055] The electronic units 120, 121, ... can recognize the value P off , value P off The value of P(t) is calculated when the sign of the discrete derivative (P(nT+1)-P(nT)) / T changes from positive to zero or negative, and the electronic unit 120, 121... compares the value with the nominal value of the pressure switch 130, which is preloaded into the non-volatile memory of the unit to evaluate the health status of the pressure switch 130.
[0056] By setting the “fill rate” ratio (P off -P on ) / (T2-T1) is compared with an acceptance range preloaded into a non-volatile memory of the electronic units 120, 121, ... which can establish the health status of the compressor and optionally activate a request signal for maintenance if the ratio is below a nominal threshold.
[0057] Furthermore, the method may therefore further comprise the step of issuing an abnormality message when the filling rate is below a predetermined threshold. The abnormality message may be issued by at least one of the electronic control units 120 , 121 or by each electronic control unit 120 , 121 .
[0058] P on At least as design data is known to all electronic units, P off As a real-time measured pressure value, the nominal “fill rate” ratio of the system can be calculated by each electronic unit as (T4-T2) / (P off -P2).
[0059] In another aspect, the method may further include the step of cyclically calculating the ignition interval by the electronic control unit 120 , 121 as the difference between the closing time T2 and the ignition time T1 or Tm.
[0060] The electronic units 120, 121, ... may add up the consecutive (T2-T1), thereby accumulating the actual usage time of the compressor.
[0061] The electronic units 120, 121 ... measure the total time that the brake system is on (i.e. activated). In this way, by dividing the actual use time of the compressor by the total time that the brake system is on, the electronic units 120, 121 ... continuously calculate the "duty cycle" of the compressor and store the duty cycle in the non-volatile memory of the electronic units 120, 121 ... so that the duty cycle can be subsequently provided to the maintenance personnel of the railway vehicle manufacturer to potentially evaluate the correct use.
[0062] Therefore, the method may further comprise the step of calculating the total operating time of the compressor 101 as the sum of the calculated firing intervals during the life of the compressor 101 and storing the total operating time.
[0063] The total operating time of the compressor 101 may be calculated by the electronic control units 120 , 121 . . .
[0064] Figure 4 Another cycle situation is shown, where, during the filling phase, an event occurs that causes air consumption, such as a braking event or a change in vehicle weight, requiring filling of the suspension bellows. This potential event causes the slope to decrease for the entire duration of the event, as shown in Figure 4 In this case, the electronics unit uses only the measurement T2-T1 to calculate the accumulated usage time and duty cycle, throwing away the estimated fill time, which is distorted by events that occurred between TA and TB.
[0065] If there is a further pressure sensing device 132 for directly measuring the pressure in the main pipe 105 and a corresponding signal can be obtained in at least one electronic unit 120, 121..., the at least one electronic unit can derive information about the filling time, the accumulation time and the duty cycle by using the same criteria described so far, but without identifying further times Tm between T1, T2...
[0066] If the communication device 133 is available for communication between the control units 120, 121, ..., the control units 120, 121, ... can transmit the precise value P to each other. on , P1, P2...P off , and the subsequently calculated “fill rate” ratios for mutual comparison and verification.
[0067] At least one of the values of fill rate or total operating time or operating duty cycle may also be transmitted from the central unit 134, or alternatively or additionally, at least one of the values of fill rate or total operating time or operating duty cycle may be transmitted from the train to the ground via a wireless system.
[0068] Furthermore, the method may further comprise the step of issuing an information signal when at least one of the ignition time or the closing time T1, T2 exceeds a relevant threshold limit. The method may further comprise issuing a closing pressure value P of the pressure P(t) off and the ignition pressure value P of pressure P(t) on The step of sending a signal when at least one of the filling times exceeds a predetermined limit value.
[0069] The information signal may be sent by at least one of the electronic control units 120 , 121 . . . or by each of the electronic control units 120 , 121 . . .
[0070] Obviously, this method based on observation of the P(t) curve is more accurate and reliable than the measurement of the nominal filling time performed by simply measuring the time the pressure switch 130 or the remote control switch 131 remains activated, in which case it is impossible to take into account the gradual increase in the volume to be filled.
[0071] Various aspects and embodiments of the method for monitoring the use and health of a compressor of a rail brake system according to the present invention have been described. It should be understood that each embodiment can be combined with any other embodiment. In addition, the present invention is not limited to the described embodiments, but can be varied within the scope defined by the appended claims.
Claims
1. A method for monitoring a compressor for a rail brake system, the rail brake system comprising an air generation and treatment module AGTU (100), the air generation and treatment module AGTU (100) comprising a compressor (101) and a main tank (104), the main tank (104) being arranged to supply a main pipe (105), the main pipe (105) being adapted to distribute compressed air to at least one brake subsystem (106), the brake subsystem (106) comprising an auxiliary tank (116), the auxiliary tank (116) being arranged to supply a brake control system (118); It is characterized in that The monitoring process includes the following steps: - monitoring a characteristic of at least one pressure value (P(t)) measured downstream of said main tank (104) or measured at the outlet of said auxiliary tank (116); - Obtaining the usage and / or health status of the compressor (101) based solely on the time characteristics of the measured pressure value (P(t)).
2. The method according to claim 1, further comprising the steps of: - Determining that the closing moment (T2) of the compressor (101) coincides with the moment at which the derivative of the pressure value (P(t)) is measured to change from a positive value to a nominal zero value or a negative value.
3. The method according to claim 1 or 2, further comprising the following steps: - Determining that the ignition moment (T1) of the compressor (101) coincides with the moment at which the derivative of the pressure value (P(t)) is measured to change from a negative value or a nominal zero value to a positive value.
4. The method according to claim 1 or 2, comprising the following steps: - determining that the ignition moment (T1) of the compressor (101) coincides with the smaller of the instantaneous moments (T1, T3, T4, ...) at which the derivatives of the pressure values (P1, P2, P3, ...) of the detected pressure value (P(t)) are measured to change from a negative value or a nominal zero value to a positive value; The pressure values (P1, P2, P3, ...) are measured downstream of the plurality of auxiliary tanks (116, 117, ...).
5. The method according to claim 2, further comprising the steps of: - Calculate the filling rate by means of a ratio in which the closing pressure value (P off ) and the first pressure value (P1) of the pressure value (P(t)) at the negative change moment (T4), the negative change moment (T4) coincides with the moment when the derivative of the pressure value (P(t)) undergoes the last negative change, and the difference between the closing moment (T2) and the negative change moment (T4) is placed in the denominator, at which the derivative of the pressure value (P(t)) undergoes the last negative change.
6. The method according to claim 5, further comprising the steps of: - When the filling rate is lower than a predetermined threshold, an abnormality message is issued.
7. The method according to claim 3, further comprising the steps of: - cyclically calculate the ignition interval as the difference between the switch-off time (T2) and the ignition time (T1).
8. The method according to claim 1, further comprising the steps of: - calculating the total operating time of the compressor (101) as the sum of the firing intervals calculated during the life of the compressor (101), - storing the total operating time during the lifetime of the compressor (101).
9. The method according to claim 8, further comprising the steps of: - calculating the operating duty cycle of the compressor (101) as a ratio between the calculated total operating time and the operating time of the rail vehicle.
10. The method according to claim 8 or 9, further comprising the following steps: - transmitting at least one value of the fill rate, the total operating time and the operating duty cycle to a central unit (134).
11. The method according to claim 8 or 9, further comprising the following steps: - transmitting at least one of the fill rate, the total operating time and the operating duty cycle from the train to the ground via a wireless system.
12. The method according to claim 3, further comprising the steps of: - the closing pressure value (P) of the pressure value (P(t)) at the closing time (T2) off ) and the ignition pressure value (P(t)) of the pressure value (P) at the ignition time (T1) on ) when at least one of them deviates from the corresponding tolerance band, an information signal is issued.
13. The method according to claim 1, further comprising the steps of: - at least when the filling time exceeds a predetermined limit value, an information signal is emitted.