A construction method for anchoring construction in a sandy soil layer with pressurized water

By using a sectioned static prefabricated concrete anchor construction method in a sandy soil layer with pressure-bearing water, the problem of groundwater and sand loss in traditional anchor construction is solved, and the stability and construction safety of anchors are achieved. The pressure anchor rod is formed to deal with creep and tension losses in traditional anchor rod construction.

CN114108623BActive Publication Date: 2024-11-01陶德明
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111327898.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-10
Publication Date
2024-11-01
Estimated Expiration
2041-11-10

AI Technical Summary

Technical Problem

In sandy soil layers with pressure-bearing water, traditional anchor construction methods are difficult to avoid the loss of groundwater and sand, resulting in an increase in the risk of ground sinking and construction accidents. Especially under the conditions where the extraction of groundwater is prohibited, traditional methods are difficult to achieve. Requirements for disturbing the soil around the anchor rod.

Method used

The construction method of sectional static pressing prefabricated concrete anchors is adopted. The prefabricated concrete anchors are pressed into the soil at the design angle, and the sand and soil are discharged with high pressure water and sealed the holes to avoid groundwater and sand and soil erosion. Then cement slurry is injected to strengthen the Combine forces and form prestressed anchors.

Benefits of technology

Effectively avoid the loss of groundwater and sand, reduce the risk of ground displacement and construction accidents, ensure the stability and construction safety of anchor rods, and form a pressure anchor rod to solve the creep and tension in traditional anchor rod construction. Loss issues.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114108623B_ABST
    Figure CN114108623B_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for anchoring construction in a sandy soil layer with pressurized water. The first section of precast concrete anchor is installed, and the slag discharge chamber is bolted to the male flange side of the concrete anchor; the drilling rig is moved to the construction hole position, and the first section of the precast concrete anchor is lifted by a crane to the drilling rig installation position, and the female flange of the precast concrete anchor is bolted to the drilling rig, and the female flange of the second section of the concrete anchor is bolted to the drilling rig, and cement slurry is injected into the precast anchor rod body through the grouting hole. After the slurry reaches the bottom of the hole, it is fully combined with the soil body, and the grouting is completed. When the cement slurry hardens and reaches the age, the precast concrete anchor is tensioned and locked to form a prestressed anchor rod, and the construction is completed. The construction method and process of the invention are simple, suitable for construction in quicksand layers, pressurized water layers, rich groundwater layers and other geological conditions that are not easy to form holes, and the reliability is high after the anchor is pressed, and there are no problems of construction difficulties in traditional construction methods and groundwater and sand loss after construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of anchoring construction in a sandy soil layer with pressurized water, and in particular to a construction method and process for effectively carrying out anchor rod construction when traditional construction methods cannot be completed. Background Art

[0002] In the field of geotechnical engineering, anchor construction is a very important part of deep foundation pit slope protection projects. In the past two decades, the application of anchor technology has been widely recognized nationwide. However, there are some shortcomings in the construction of conventional anchors in the past. For example, there are huge difficulties and risks in anchor construction in sandy soil layers with pressurized water and in undisturbed strata under buildings. Especially in recent years, the state has banned the extraction of groundwater during deep foundation pit excavation. It is even more difficult to use the conventional methods of the past to carry out anchor construction. It is urgent to adopt a new method that does not disturb the soil around the anchor so that anchors with pressurized water strata can be constructed.

[0003] Conventional anchor construction begins when the foundation pit is excavated to a certain depth. The drilling is usually done by spiral drilling or casing wall protection, water flushing and slag removal. After the anchor hole is drilled at a certain angle in the horizontal direction, the prestressed steel strand is lowered, and then cement slurry is poured. If the above method is used for construction in soil that is not easily disturbed without quicksand and pressurized water, there will be no problem. However, when the construction conditions are in quicksand formations and formations with abundant groundwater and pressurized water, groundwater and quicksand will gush out of the hole in large quantities during and after the drilling process, resulting in the loss of groundwater and sand, the sinking of the ground and above-ground buildings, changes in the physical properties of the soil, displacement and cracking of the foundation pit, and ultimately serious construction accidents. Summary of the invention

[0004] In view of the above situation, the present invention adopts a new anchoring construction technology to slightly disturb the soil around the anchor rod, and uses a construction method of a segmented static pressure precast concrete anchor body. After the precast concrete anchor body is pressed into the designed depth according to the designed angle, a steel strand is placed in the reserved hole of the precast concrete anchor body, and then a proper amount of cement slurry is pressed into the reserved grouting port of the precast concrete anchor body, so that the precast concrete anchor body is fully combined with the soil body to provide sufficient tensioning force for the anchor rod tensioning; then the central slag outlet is blocked at the top of the precast concrete anchor body to prevent the flowing sand and groundwater at the bottom of the precast concrete anchor body from gushing out of the pipe.

[0005] After the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] The first construction method includes the following steps:

[0008] Step 1: Arrange the site, put the construction equipment in place, check the equipment, and ensure that the drilling rig can operate normally;

[0009] Step 2: Install the first section of prefabricated concrete anchor body, connect the slag discharge chamber to the male flange side of the concrete anchor body with bolts, and then install a detachable anchor lock on the male flange. After installation, transport it to the side of the drilling rig;

[0010] The prefabricated concrete anchor body is prefabricated by injection molding. The concrete anchor body includes a female flange, a male flange, a water pipe, a grouting pipe, a steel strand pipe, etc. The male flange and the female flange are at both ends, and the water pipe, the grouting pipe, and the steel strand pipe are plugged in the middle. The water pipe, the grouting pipe, and the steel strand pipe are in the outer circle and then welded together. A steel wire mesh is used on the outside of the water pipe and the steel strand pipe to make a steel cage, which is then put into the casting mold and concrete is poured to make a concrete anchor body, and the concrete anchor body is hollow in the middle.

[0011] Step 3: Move the drilling rig to the construction hole position, lift the first section of precast concrete anchor body to the drilling rig installation position with a crane, connect the female flange of the precast concrete anchor body to the drilling rig with bolts, seal the connection surface with a rubber pad, complete the connection of the first section of the drill rod, and connect the water pipe at the same time to ensure that water flows out from the bottom end of the precast concrete anchor body;

[0012] Step 4: Press the precast concrete anchor body into the sand layer, and turn on the water pump at the same time to spray high-pressure water through the water holes of the precast concrete anchor body to the position of the slag discharge chamber. Due to the flow and pressure of water, the sand in the slag discharge chamber is discharged to the ground through the inner holes of the precast concrete anchor body, and the sand outside the slag discharge chamber is isolated at the same time, and the surrounding soil is not disturbed, so that the precast concrete anchor body can be drilled under the top pressure of the drilling rig;

[0013] Step 5. After the first section is completed, loosen the connection flange between the drilling rig and the precast concrete anchor body, lift the second section of the precast concrete anchor body with a crane, align the male flange of the second section of the precast concrete anchor body with the female flange of the first section of the precast concrete anchor body, connect them with bolts, and add a rubber pad in the middle; then connect the female flange of the second section of the concrete anchor body with the drilling rig bolts, add a rubber pad in the middle, add one section of the concrete anchor body to complete, and continue construction;

[0014] Step 6: According to step 5, the drilling tools are added in sequence until the drilling reaches the designed construction depth, and the drilling rig is removed;

[0015] Step 7. Lower the steel strands through the precast concrete anchor body steel strand hole to the bottom of the hole to block the hole inside the precast anchor rod body, and then use the grouting hole to inject cement slurry into the precast anchor rod body. After the slurry reaches the bottom of the hole, it fully combines with the soil and the grouting is completed.

[0016] Step 8: When the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod. The precast concrete anchor body remains in the soil and is used as an anchor rod carrier, and the construction is completed.

[0017] Step 9. When the foundation pit needs to be backfilled, the prestressed non-bonded steel strand bundle can be removed after the backfill soil fills a full layer; when the construction does not require the removal of the prestressed steel strand, ordinary steel strand construction is used; the ordinary steel strand bundle is injected together with the precast concrete anchor through cement slurry to form a whole, and after tensioning and locking, it becomes a permanent prestressed anchor rod.

[0018] The prefabricated concrete anchor body, the male flange and the female flange need to reserve water holes, steel strand holes, and bolt fixing holes, so as to ensure that water and steel strands reach the bottom of the hole.

[0019] The male flange and the female flange of the prefabricated concrete anchor body are manufactured with the positions of the clamping grooves and the sealing grooves to prevent the hole positions from being disordered and the connection of the concrete anchor body from being sealed.

[0020] The prefabricated concrete anchor body has a position reserved for installing a detachable anchor cable on the lower side of the male flange, which facilitates the disassembly of the steel strand of the detachable anchor rod.

[0021] The second construction method includes the following steps:

[0022] Step 1: Arrange the site, put the construction equipment in place, check the equipment, and ensure that the drilling rig can operate normally;

[0023] Step 2: Install the first section of prefabricated concrete anchor body, connect the return water and slag discharge chamber to the male flange side of the concrete anchor body with bolts, add rubber pads in the middle, and transport it to the side of the drilling rig after installation;

[0024] The prefabricated concrete anchor body is prefabricated by injection molding. The concrete anchor body includes a female flange, a male flange, a water pipe, etc. The male flange and the female flange are at both ends, and the middle is connected by a water pipe. Between the male flange and the female flange, the outer side of the water pipe is protected by a wire mesh, and then lowered into the casting mold, and concrete is cast to form a concrete anchor body. The middle of the concrete anchor body is a water pipe, and a slag discharge hole is reserved.

[0025] Step 3: Move the drilling rig to the construction hole location, use a crane to lift the first section of precast concrete anchor to the drilling rig installation position, bolt the precast concrete anchor flange to the drilling rig, seal the connection surface with a rubber pad, complete the connection of the first section of the drill rod, and connect the water pipe at the same time to ensure that water flows out from the bottom of the precast concrete anchor.

[0026] Step 4: Press the precast concrete anchor body into the sand layer, and turn on the water pump at the same time to spray high-pressure water through the water pipe of the precast concrete anchor body to the position of the return angle of the return water and slag discharge chamber. Due to the reflux effect of the high-pressure water flow on the return angle, the sand and soil in the return water and slag discharge chamber are discharged to the ground through the inner hole of the precast concrete anchor body, and the sand and soil outside the slag discharge chamber are isolated at the same time, and the surrounding soil is not disturbed, so that the precast concrete anchor body can advance under the top pressure of the drilling rig.

[0027] Step 5. After completing the first section, loosen the connection flange between the drilling rig and the precast concrete anchor body, lift the second section of the precast concrete anchor body with a crane, and connect the male flange of the second section of the precast concrete anchor body with the female flange of the first section of the precast concrete anchor body with bolts, adding a rubber pad in the middle; then connect the female flange of the second section of the concrete anchor body with the drilling rig bolts, adding a rubber pad in the middle, adding one section of the concrete anchor body is completed, and construction continues.

[0028] Step 6. According to step 5, increase the drilling tools in sequence until the drilling reaches the designed construction depth, and then remove the drilling rig.

[0029] Step 7. Lower the steel strand through the inner hole of the precast concrete anchor body to the bottom of the hole to block the inner hole of the precast anchor rod. Then use the grouting hole to inject cement slurry into the precast anchor rod body. After the slurry reaches the bottom of the hole, it fully combines with the soil and the grouting is completed.

[0030] Step 8: When the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod. The precast concrete anchor body remains in the soil and is used as an anchor rod carrier, and the construction is completed.

[0031] Step 9. When the foundation pit needs to be backfilled, the prestressed non-bonded steel strand bundle can be removed after the backfill soil fills a full layer; when the construction does not require the removal of the prestressed steel strand, ordinary steel strand construction is used; the ordinary steel strand bundle is injected together with the precast concrete anchor through cement slurry to form a whole, and after tensioning and locking, it becomes a permanent prestressed anchor rod.

[0032] The construction method for anchoring construction in a sandy soil layer with pressurized water is characterized in that the precast concrete anchor body is directly pressed into the soil by a drilling machine, and water or air is injected into the bottom of the hole at the same time, so that the sand in the slag discharge chamber is discharged to the ground through the inner hole of the precast concrete anchor body, and the surrounding soil and groundwater of the precast concrete anchor body except the end face are not disturbed or lost. At the same time, the mud and sand outside the slag discharge chamber are isolated, so that the precast concrete anchor body is pressed into the advance.

[0033] The construction method for anchoring construction in a sandy soil layer with pressurized water is characterized in that during the construction process, high-pressure water or high-pressure gas is transported to the middle of the prefabricated concrete anchor body, or both are transported simultaneously.

[0034] The construction method for anchor rod construction in sandy soil layers is characterized in that the pressed-in prefabricated concrete anchor body can also rotate appropriately under the action of a drilling rig.

[0035] The prefabricated concrete anchor body is characterized in that when the concrete anchor body is manufactured, some conical platforms (commonly known as barbs) are manufactured on the outer wall to increase the pulling force. The surface of the last concrete anchor body pressed into the hole is smooth, which is convenient for sealing water leakage around the concrete anchor body.

[0036] The prefabricated concrete anchor body is characterized in that the two concrete anchor rods can be connected by threaded connection, pin connection, or other connection forms, as long as the connection between the two rods is stable.

[0037] The actual effect of the present invention is that the pressed-in precast concrete anchor body, because the steel strands are locked or injected in the bottom section (one) or two sections of the precast concrete anchor body; when the steel strands are tensioned, the resistance to tension is transmitted from the bottom to the top, and the tension of the steel strands is transmitted upward section by section through the bottom precast concrete anchor body, so the anchor rod finally formed by this pressed-in precast concrete anchor body can be classified as a pressure-type anchor rod. The pressure-type anchor rod is also the most conducive to solving the problems of endless creep of the anchor body, loss of tension, large displacement of the foundation pit, etc. after the prestressed steel strands are tensioned and locked during the construction of conventional anchor rods. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a schematic diagram of the tensioning of precast concrete anchor bodies.

[0039] Figure 2 It is the cross-sectional view of the first precast concrete anchor body.

[0040] Figure 3 It is a schematic diagram of the end face of the first precast concrete anchor body.

[0041] Figure 4 This is the schematic diagram of the first section of the first type of precast concrete anchor body.

[0042] Figure 5 This is a schematic diagram of the second type of precast concrete anchor tensioning.

[0043] Figure 6 This is the cross-sectional view of the second type of precast concrete anchor body.

[0044] Figure 7 This is a schematic diagram of the end face of the second type of precast concrete anchor body.

[0045] Figure 8 This is a schematic diagram of the first section of the second type of precast concrete anchor body.

[0046] Fig. 9 It is a schematic diagram of the connection between two precast concrete anchors.

[0047] Fig.10 This is the appearance drawing of precast concrete anchor body. DETAILED DESCRIPTION

[0048] The present invention is described in detail below with reference to the accompanying drawings and embodiments.

[0049] The present invention has two embodiments. The first embodiment is a construction method for anchoring a sandy soil layer with pressurized water, comprising the following steps:

[0050] Step 1: Arrange the site, put the construction equipment in place, check the equipment, and ensure the normal operation of the drilling rig;

[0051] Step 2: Install the first section of prefabricated concrete anchor body, connect the slag discharge chamber to the male flange side of the concrete anchor body with bolts, and then install a detachable anchor lock on the male flange. After installation, transport it to the side of the drilling rig;

[0052] The prefabricated concrete anchor body is prefabricated by injection molding. The concrete anchor body includes a female flange, a male flange, a water pipe, a grouting pipe and a steel strand pipe; the male flange and the female flange are at both ends, and the water pipe, the grouting pipe and the steel strand pipe are plugged in the middle, and the water pipe, the grouting pipe and the steel strand pipe are in the outer circle and then welded together; a steel wire mesh is used on the outside of the water pipe and the steel strand pipe to make a steel cage, which is then put into the casting mold and concrete is poured to make a concrete anchor body, and the middle of the concrete anchor body is hollow.

[0053] Step 3: Move the drilling rig to the construction hole position, lift the first section of precast concrete anchor body to the drilling rig installation position with a crane, connect the female flange of the precast concrete anchor body to the drilling rig with bolts, seal the connection surface with a rubber pad, complete the connection of the first section of the drill rod, connect the water pipe, and ensure that the water flows out from the bottom of the precast concrete anchor body;

[0054] Step 4: Press the precast concrete anchor body into the sand layer, and turn on the water pump at the same time to spray high-pressure water through the water holes of the precast concrete anchor body to the position of the slag discharge chamber. Due to the flow and pressure of water, the sand in the slag discharge chamber is discharged to the ground through the inner holes of the precast concrete anchor body, and the sand outside the slag discharge chamber is isolated at the same time, so that the precast concrete anchor body can advance under the top pressure of the drilling rig;

[0055] Step 5. After the first section is completed, loosen the connection flange between the drilling rig and the precast concrete anchor body, lift the second section of the precast concrete anchor body with a crane, align the male flange of the second section of the precast concrete anchor body with the female flange of the first section of the precast concrete anchor body, connect them with bolts, and add a rubber pad in the middle; then connect the female flange of the second section of the concrete anchor body with the drilling rig bolts, add a rubber pad in the middle, add one section of the concrete anchor body to complete, and continue construction;

[0056] Step 6: According to step 5, the drilling tools are added in sequence until the drilling reaches the designed construction depth, and the drilling rig is removed;

[0057] Step 7. Lower the steel strands through the precast concrete anchor body steel strand hole to the bottom of the hole to block the hole inside the precast anchor rod body, and then use the grouting hole to inject cement slurry into the precast anchor rod body. After the slurry reaches the bottom of the hole, it fully combines with the soil and the grouting is completed.

[0058] Step 8: When the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod. The precast concrete anchor body remains in the soil and is used as an anchor rod carrier, and the construction is completed.

[0059] Step 9. When the foundation pit needs to be backfilled, the prestressed non-bonded steel strand bundle can be removed after the backfill soil fills a full layer; when the construction does not require the removal of the prestressed steel strand, ordinary steel strands are used for construction; ordinary steel strand bundles are injected together with precast concrete anchors through cement slurry to form a whole, and after tensioning and locking, they become permanent prestressed anchor rods.

[0060] Furthermore, the male flange and the female flange need to reserve water holes, steel strand holes and bolt fixing holes to ensure that water and steel strands reach the bottom of the holes.

[0061] Furthermore, the male flange and the female flange are manufactured with a clamping groove and a sealing groove to prevent the hole position from being misplaced and the connection of the concrete anchor body from being sealed.

[0062] Furthermore, a position for installing a detachable anchor cable is reserved on the lower side of the male flange to facilitate the disassembly of the steel strand of the detachable anchor rod.

[0063] The second method is a construction method for anchoring in a sandy soil layer with pressurized water, characterized in that it comprises the following steps:

[0064] Step 1: Arrange the site, put the construction equipment in place, check the equipment, and ensure that the drilling rig can operate normally;

[0065] Step 2: Install the first section of prefabricated concrete anchor body, connect the return water and slag discharge chamber to the male flange side of the concrete anchor body with bolts, add rubber pads in the middle, and transport it to the side of the drilling rig after installation;

[0066] The prefabricated concrete anchor body is prefabricated by injection molding. The concrete anchor body includes a female flange, a male flange, and a water pipe; the male flange and the female flange are at both ends, and the water pipe is inserted in the middle; between the male and female flanges, the outer side of the water pipe is protected with a wire mesh, and then lowered into the casting mold, and concrete is cast to form a concrete anchor body, and the middle of the concrete anchor body is a water pipe, and a slag discharge hole is reserved.

[0067] Step 3: Move the drilling rig to the construction hole position, lift the first section of precast concrete anchor body to the drilling rig installation position with a crane, connect the female flange of the precast concrete anchor body to the drilling rig with bolts, seal the connection surface with a rubber pad, complete the connection of the first section of the drill rod, and connect the water pipe at the same time to ensure that water flows out from the bottom end of the precast concrete anchor body;

[0068] Step 4: Press the precast concrete anchor body into the sand layer, and turn on the water pump at the same time, so that high-pressure water is sprayed through the water pipe of the precast concrete anchor body to the position of the return angle of the return water and slag discharge chamber. Due to the effect of the high-pressure water flow rushing to the return angle and reflux, the sand and soil at the return water and slag discharge chamber are discharged to the ground through the inner hole of the precast concrete anchor body, and the sand and soil outside the slag discharge chamber are isolated at the same time, and the surrounding soil is not disturbed, so that the precast concrete anchor body is advanced under the top pressure of the drilling rig;

[0069] Step 5. After the first section is completed, loosen the connection flange between the drilling rig and the precast concrete anchor body, lift the second section of the precast concrete anchor body with a crane, and connect the male flange of the second section of the precast concrete anchor body with the female flange of the first section of the precast concrete anchor body with bolts, and add a rubber pad in the middle; then connect the female flange of the second section of the concrete anchor body with the drilling rig bolts, add a rubber pad in the middle, add one section of the concrete anchor body to complete, and continue construction;

[0070] Step 6: According to step 5, the drilling tools are added in sequence until the drilling reaches the designed construction depth, and the drilling rig is removed;

[0071] Step 7. Lower the steel strand through the inner hole of the precast concrete anchor body to the bottom of the hole to block the inner hole of the precast anchor rod. Then use the grouting hole to inject cement slurry into the precast anchor rod body. After the slurry reaches the bottom of the hole, it fully combines with the soil and the grouting is completed.

[0072] Step 8: When the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod. The precast concrete anchor body remains in the soil and is used as an anchor rod carrier, and the construction is completed.

[0073] Step 9. When the foundation pit needs to be backfilled, after the backfill soil fills a full layer, the prestressed non-bonded steel strand bundle is removed; when the construction does not require the removal of the prestressed steel strand, ordinary steel strands are used for construction; ordinary steel strand bundles are injected together with precast concrete anchors through cement slurry to form a whole, and after tensioning and locking, they become permanent prestressed anchor rods.

[0074] Furthermore, the precast concrete anchor is directly pressed into the soil with a drilling rig, and water or air is injected into the bottom of the hole at the same time, so that the sand in the slag discharge chamber is discharged to the ground through the inner hole of the precast concrete anchor, and the surrounding soil and groundwater of the precast concrete anchor except the end face are not disturbed or lost. At the same time, the mud and sand outside the slag discharge chamber are isolated, so that the precast concrete anchor is pressed into the advance.

[0075] Furthermore, during the construction process, high-pressure water or high-pressure gas, or both, must be delivered to the middle of the precast concrete anchor body.

[0076] Furthermore, the pressed-in precast concrete anchor body can rotate under the action of the drilling rig.

[0077] Furthermore, when the concrete anchor rod is solidly manufactured, a conical platform is manufactured on the outer wall to increase the pulling force.

[0078] Furthermore, the two concrete anchor bodies are connected by threaded connection or through pin connection to ensure a stable connection.

Claims

1. A construction method for anchoring construction in a sandy soil layer with pressurized water, comprising the following steps: Step 1: Arrange the site, put the construction equipment in place, check the equipment, and ensure the normal operation of the drilling rig; Step 2: Install the first section of prefabricated concrete anchor body, connect the slag discharge chamber to the male flange side of the concrete anchor body with bolts, and then install a detachable anchor lock on the male flange. After installation, transport it to the side of the drilling rig; The prefabricated concrete anchor body is prefabricated by injection molding; the prefabricated concrete anchor body includes a female flange, a male flange, a water pipe, a grouting pipe and a steel strand pipe; the male flange and the female flange are at both ends, and the water pipe, the grouting pipe and the steel strand pipe are plugged in the middle, and the water pipe, the grouting pipe and the steel strand pipe are in the outer circle and then welded together; a steel wire mesh is used on the outside of the water pipe and the steel strand pipe to make a steel cage, which is then put into the casting mold, and concrete is poured to make a concrete anchor body, and the middle of the concrete anchor body is hollow; Step 3: Move the drilling rig to the construction hole position, lift the first section of precast concrete anchor body to the drilling rig installation position with a crane, connect the female flange of the precast concrete anchor body to the drilling rig with bolts, seal the connection surface with a rubber pad, complete the connection of the first section of the drill rod, connect the water pipe, and ensure that the water flows out from the bottom of the precast concrete anchor body; Step 4: Press the precast concrete anchor body into the sand layer, and turn on the water pump at the same time to spray high-pressure water through the water holes of the precast concrete anchor body to the position of the slag discharge chamber. Due to the flow and pressure of water, the sand in the slag discharge chamber is discharged to the ground through the inner holes of the precast concrete anchor body, and the sand outside the slag discharge chamber is isolated at the same time, so that the precast concrete anchor body can advance under the top pressure of the drilling rig; Step 5. After the first section is completed, loosen the connection flange between the drilling rig and the precast concrete anchor body, lift the second section of the precast concrete anchor body with a crane, align the male flange of the second section of the precast concrete anchor body with the female flange of the first section of the precast concrete anchor body, connect them with bolts, and add a rubber pad in the middle; then connect the female flange of the second section of the concrete anchor body with the drilling rig bolts, add a rubber pad in the middle, add one section of the concrete anchor body to complete, and continue construction; Step 6: According to step 5, the drilling tools are added in sequence until the drilling reaches the designed construction depth, and the drilling rig is removed; Step 7: Lower the steel strands through the precast concrete anchor body steel strand hole to the bottom of the hole to block the inner hole of the precast anchor rod, and then use the grouting hole to inject cement slurry into the precast anchor rod body. After the slurry reaches the bottom of the hole, it is fully combined with the soil, and the grouting is completed; Step 8: When the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod. The precast concrete anchor body is left in the soil and used as an anchor rod carrier. The construction is completed; Step 9. When the foundation pit needs to be backfilled, the prestressed non-bonded steel strand bundle can be removed after the backfill soil fills a full layer; when the construction does not require the removal of the prestressed steel strand, ordinary steel strands are used for construction; ordinary steel strand bundles are injected together with precast concrete anchors through cement slurry to form a whole, and after tensioning and locking, they become permanent prestressed anchor rods.

2. A construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: The male flange and female flange need to reserve water holes, steel strand holes and bolt fixing holes to ensure that water and steel strands reach the bottom of the holes.

3. A construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 2, characterized in that: The male flange and the female flange are manufactured with a clamping groove and a sealing groove to prevent the hole position from being disordered and the connection of the concrete anchor body from being sealed.

4. A construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: A position for installing a detachable anchor cable is reserved on the lower side of the male flange to facilitate the disassembly of the steel strand of the detachable anchor rod.

5. The construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: The precast concrete anchor body is directly pressed into the soil with a drilling rig, and water or air is injected into the bottom of the hole at the same time, so that the sand in the slag discharge chamber is discharged to the ground through the inner hole of the precast concrete anchor body. The surrounding soil and groundwater of the precast concrete anchor body except the end face are not disturbed or lost; at the same time, the mud and sand outside the slag discharge chamber are isolated, so that the precast concrete anchor body can be pressed into the advance.

6. A construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: During the construction process, high-pressure water or high-pressure gas, or both, must be delivered to the middle of the precast concrete anchor body.

7. A construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: The pressed-in precast concrete anchor body can rotate under the action of the drilling rig.

8. The construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: When the prefabricated concrete anchor body is manufactured, a conical platform is manufactured on the outer wall to increase the pulling force.

9. A construction method for anchoring construction in a sandy soil layer with pressurized water according to claim 1, characterized in that: The two concrete anchor bodies are connected by threaded connection or through pin connection to ensure a stable connection.

10. A construction method for anchoring construction in a sandy soil layer with pressurized water, characterized in that: The steps include: Step 1: Arrange the site, put the construction equipment in place, check the equipment, and ensure that the drilling rig can operate normally; Step 2: Install the first section of prefabricated concrete anchor body, connect the return water and slag discharge chamber to the male flange side of the concrete anchor body with bolts, add rubber pads in the middle, and transport it to the side of the drilling rig after installation; The prefabricated concrete anchor body is prefabricated by injection molding; the concrete anchor body includes a female flange, a male flange, and a water pipe; the male flange and the female flange are at both ends, and the water pipe is inserted in the middle; between the male and female flanges, the outer side of the water pipe is protected with a wire mesh, and then lowered into the casting mold, and concrete is cast to form a concrete anchor body, and the middle of the concrete anchor body is a water pipe, and a slag discharge hole is reserved; Step 3: Move the drilling rig to the construction hole position, lift the first section of precast concrete anchor body to the drilling rig installation position with a crane, connect the female flange of the precast concrete anchor body to the drilling rig with bolts, seal the connection surface with a rubber pad, complete the connection of the first section of the drill rod, and connect the water pipe at the same time to ensure that water flows out from the bottom end of the precast concrete anchor body; Step 4: Press the precast concrete anchor body into the sand layer, and turn on the water pump at the same time, so that high-pressure water is sprayed through the water pipe of the precast concrete anchor body to the position of the return angle of the return water and slag discharge chamber. Due to the effect of the high-pressure water flow rushing to the return angle and reflux, the sand and soil at the return water and slag discharge chamber are discharged to the ground through the inner hole of the precast concrete anchor body, and the sand and soil outside the slag discharge chamber are isolated at the same time, and the surrounding soil is not disturbed, so that the precast concrete anchor body is advanced under the top pressure of the drilling rig; Step 5. After the first section is completed, loosen the connection flange between the drilling rig and the precast concrete anchor body, lift the second section of the precast concrete anchor body with a crane, and connect the male flange of the second section of the precast concrete anchor body with the female flange of the first section of the precast concrete anchor body with bolts, and add a rubber pad in the middle; then connect the female flange of the second section of the concrete anchor body with the drilling rig bolts, add a rubber pad in the middle, add one section of the concrete anchor body to complete, and continue construction; Step 6: According to step 5, the drilling tools are added in sequence until the drilling reaches the designed construction depth, and the drilling rig is removed; Step 7: Lower the steel strand through the inner hole of the precast concrete anchor body to the bottom of the hole to block the inner hole of the precast anchor rod, and then use the grouting hole to inject cement slurry into the precast anchor rod body. After the slurry reaches the bottom of the hole, it is fully combined with the soil, and the grouting is completed; Step 8: When the cement slurry hardens and reaches the age, the precast concrete anchor body is tensioned and locked to form a prestressed anchor rod. The precast concrete anchor body is left in the soil and used as an anchor rod carrier. The construction is completed; Step 9. When the foundation pit needs to be backfilled, after the backfill soil fills a full layer, the prestressed non-bonded steel strand bundle is removed; when the construction does not require the removal of the prestressed steel strand, ordinary steel strands are used for construction; ordinary steel strand bundles are injected together with precast concrete anchors through cement slurry to form a whole, and after tensioning and locking, they become permanent prestressed anchor rods.