Solidified soil stirring field and solidified soil backfill construction method in narrow high backfill area
A construction method and technology for solidifying soil, applied in the directions of chemical instruments and methods, excavation, fertilization devices, etc., can solve the problems of inability to perform construction by personnel and machinery, high backfilling depth, and narrow backfilling area, so as to achieve reasonable distribution and reuse. , the effect of short curing time
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2022-04-15
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention relates to the technical field of building construction, in particular to a solidified soil backfill construction method for a solidified soil mixing field and a narrow high backfill area. Background technique
[0002] With the rapid development of the construction industry, in order to solve the problem of tight urban land use, underground space construction projects are becoming more and more extensive. For underground projects such as basements and underground shopping malls, there is a large amount of earthwork excavation, which often requires high costs. Transshipment treatment, even dumping on the ground, increases the construction cost and causes damage to the ecological environment at the same time.
[0003] At the same time, after the construction of the main body, it is necessary to backfill the outer walls of the basement, underground shopping malls, etc. The traditional technology mostly uses plain soil or lime soil layered wi...
Examples
Embodiment 1
[0058] This embodiment discloses a solidified soil mixing field and the positioning of the solidified soil backfill construction method in the narrow high backfill area, such as figure 1 As shown, it includes a solidified soil mixing field, which is characterized in that it is arranged on a flat place near the construction site, surrounded by slopes 1 that have been treated with grading, and a concrete hardened layer 2 that is high in the middle and low in the surroundings on the bottom surface. Drainage system 3, material storage area 4, raw material delivery area 5, mixing area 6 and solidified soil delivery area 7 are set in the mixing field.
[0059] The hardened concrete layer 2 is processed by C20 concrete, and the hardened concrete layer 2 has a thickness of 10cm-20cm.
[0060] Drainage system 3 comprises drainage ditches, sump well and the water pump that water is drawn out from the sump well.
[0061] A construction method for backfilling solidified soil in a narrow ...