A tunnel construction method based on arc steel mold trolley
Through the design of the arc steel formwork trolley, the lifting device and the driving cylinder are used to realize the synchronous movement and demoulding of the formwork, which solves the low demoulding efficiency and collision problems of the traditional trolley and improves the efficiency and safety of the tunnel secondary lining construction. sex.
Patent Information
- Application Number
- CN202210093632.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-31
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2041-12-31
AI Technical Summary
The traditional trolley has low efficiency during the demoulding process and the distance between the formwork and the inner wall of the tunnel is close, which makes it easy to collide, affecting the efficiency of secondary lining construction of the tunnel.
The arc steel mold trolley is used, including the first mast, the second mast and the mold supporting mechanism. The lifting device and the driving cylinder are used to realize the synchronous movement and demoulding of the template to ensure that the template is more closed during demoulding to avoid contact with the tunnel. Inner wall collision and improved construction efficiency through station switching.
It improves the efficiency of tunnel secondary lining construction, reduces the difficulty of demoulding, enhances construction safety, realizes the overall pouring cycle of tunnel segments, and improves construction efficiency and safety.
Smart Images

Figure CN114526091B_ABST
Abstract
Description
[0001] This application is a divisional application with the application date of "2021.12.31", application number "202111679316.4", and application name "Arc steel mold trolley and tunnel construction method using the same". Technical Field
[0002] The invention relates to the technical field of tunnels, and in particular to a tunnel construction method based on an arc steel mold trolley. Background Art
[0003] For tunnels with high sealing requirements, secondary lining is required after shield construction to meet the requirements of reinforcement support, sealing and waterproofing. In related technologies, the secondary lining construction of tunnels generally requires the use of a trolley for pouring, and the trolley's template is driven by the cylinder to support or demold. However, the traditional trolley demolds from top to bottom in the demolding process, resulting in low demolding efficiency, and the distance between the template and the inner wall of the tunnel after demolding is close, which is easy to collide with the inner wall of the tunnel during the movement of the trolley. Summary of the invention
[0004] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a tunnel construction method based on an arc steel mold trolley, which can improve the demoulding efficiency, thereby greatly improving the efficiency of the secondary lining construction of the tunnel.
[0005] According to an embodiment of the present invention, a tunnel construction method based on an arc steel formwork trolley is provided, the arc steel formwork trolley comprises a first gantry, a second gantry and a formwork support mechanism, both ends of the second gantry along the front-to-back direction are provided with lifting devices, the second gantry is provided with a first workstation and a second workstation along the front-to-back direction, the first gantry is movably sleeved on the second gantry and can move between the first workstation and the second workstation; the formwork support mechanism comprises a template assembly, a first driving cylinder, a second driving cylinder, a third driving cylinder and a fourth driving cylinder, the template assembly comprises a first upper template, a second upper template, a first lower template, a second lower template and a lower template; the upper template is located above the first gantry and below the first gantry, the upper template, the first upper template, the first lower template, the lower template, the second lower template The side template and the second upper template are connected in sequence and arranged around the first portal frame, and the lower template is detachably connected to the first lower template and the second lower template; the two ends of the first driving cylinder are respectively hinged to the first upper template and the first portal frame, the two ends of the second driving cylinder are respectively hinged to the second upper template and the first portal frame, the two ends of the third driving cylinder are respectively hinged to one end of the first upper template close to the first lower template and one end of the first lower template close to the first upper template, and the two ends of the fourth driving cylinder are respectively hinged to one end of the second upper template close to the second lower template and one end of the second lower template close to the second upper template; in the front-to-back direction, the length of the second portal frame is L1, and the length of the template assembly is L2, which satisfies: L1 / L2≥2;
[0006] The construction method comprises:
[0007] Setting up a first steel mesh frame on the inner wall of the tunnel;
[0008] The first gantry moves from the first station to the second station;
[0009] The lifting device drives the second gantry to rise to a first target position so that the upper template cooperates with a corresponding partial structure of the first steel mesh frame;
[0010] The first driving cylinder, the second driving cylinder, the third driving cylinder and the fourth driving cylinder are driven respectively to move the first upper template, the second upper template, the first lower template and the second lower template to positions matching the first steel mesh frame;
[0011] Installing the lower template between the first lower template and the second lower template;
[0012] pouring concrete between the formwork assembly and the inner wall of the tunnel;
[0013] The lifting device is retracted and separated from the supporting surface of the tunnel;
[0014] The second gantry moves along the extension direction of the tunnel so that the first gantry switches from the second workstation to the first workstation;
[0015] The lifting device extends out and is supported on the supporting surface;
[0016] Disassembling the lower template;
[0017] The first driving cylinder, the second driving cylinder, the third driving cylinder and the fourth driving cylinder are driven respectively to reset and demould the first upper template, the second upper template, the first lower template and the second lower template;
[0018] The lifting device drives the second door frame to descend to a second target position to demould the upper template.
[0019] The tunnel construction method based on the arc steel mold trolley according to the embodiment of the present invention has at least the following beneficial effects:
[0020] In the construction of the secondary lining of the tunnel, the embodiment of the present invention adopts an arc steel mold trolley to realize the integral casting of the second lining of the cylindrical tunnel segment. The arc steel mold trolley moves along the extension direction of the tunnel and continues to cast the second lining of the remaining tunnel segments; the arc steel mold trolley includes a first gantry, a second gantry and a mold support mechanism. The second gantry is provided with a first station and a second station. The first gantry is fixedly connected to the mold support mechanism and movably sleeved on the second gantry, so that it can switch positions between the first station and the second station. The second gantry is supported on the supporting surface of the tunnel. The mold support mechanism can complete the processes of mold support, casting, and molding at the second station under the drive of the first gantry. At the same time, before demoulding, the second gantry is separated from the supporting surface and moves along the extension direction of the tunnel, so that the mold support mechanism is switched to the first station. The second gantry is supported on the supporting surface of the tunnel again. At this time, the mold support mechanism completes demoulding at the first station, and moves to the second station again to realize the processes of mold support, casting, and molding of the second lining of the next tunnel segment, thereby realizing the cycle of integral casting of the second lining of the tunnel segment. The embodiment of the present invention realizes the integral pouring of the secondary lining of multiple tunnel sections through the step-changing operation of the second gantry and the formwork mechanism, thereby improving the construction efficiency of the secondary lining. The formwork mechanism includes a formwork assembly, a first driving cylinder, a second driving cylinder, a third driving cylinder and a fourth driving cylinder, and the formwork assembly includes a first upper formwork, a second upper formwork, a first lower formwork, a second lower formwork and a lower formwork; the upper formwork is located above the first gantry, the lower formwork is located below the first gantry, and is detachably connected to the first lower formwork and the second lower formwork, the two ends of the first driving cylinder are respectively hinged to the first upper formwork and the first gantry, the two ends of the second driving cylinder are respectively hinged to the second upper formwork and the first gantry, the two ends of the third driving cylinder are respectively hinged to one end of the first upper formwork close to the first lower formwork and one end of the first lower formwork close to the first upper formwork, and the two ends of the fourth driving cylinder are respectively hinged to the second upper formwork. One end of the side formwork is close to the second lower side formwork and one end of the second lower side formwork is close to the second upper side formwork; through the above-mentioned connection method, the first upper side formwork and the first lower side formwork can be synchronously demoulded by the first driving cylinder and the third driving cylinder respectively, the second upper side formwork and the second lower formwork can be synchronously demoulded by the second driving cylinder and the fourth driving cylinder respectively, and the upper formwork can be lowered by the lifting device to achieve gravity demoulding, which reduces the difficulty of demoulding, improves the demoulding efficiency, and further improves the efficiency of the secondary lining construction of the tunnel; and the formwork assembly can be more retracted to the first gantry in the demoulding state, effectively avoiding the collision of the first gantry with the inner wall of the tunnel during movement, thereby improving the safety of construction.
[0021] According to some embodiments of the present invention, before the second portal moves along the extension direction of the tunnel, the method includes: erecting a second steel mesh frame on the inner wall of the tunnel in the extension direction.
[0022] According to some embodiments of the present invention, the first gantry is provided with a first supporting device at both ends along the front-rear direction, the first supporting device includes a limiting oil cylinder and a first supporting beam, and the two ends of the limiting oil cylinder are respectively connected to the first gantry and the first supporting beam; before pouring concrete between the formwork assembly and the inner wall of the tunnel, it also includes: the limiting oil cylinder drives the first supporting beam to support the supporting surface of the tunnel; before the lifting device drives the second gantry to descend to the second target position, it also includes: the limiting oil cylinder retracts and disengages from the supporting surface.
[0023] According to some embodiments of the present invention, after the first door frame moves from the first station to the second station, the process further includes: cleaning the outer surface of the template assembly.
[0024] According to some embodiments of the present invention, cleaning the outer surface of the formwork assembly includes: cleaning the concrete and curing agent on the outer surfaces of the first upper formwork, the second upper formwork, the first lower formwork and the second lower formwork; and applying a release agent on the outer surfaces of the first upper formwork, the second upper formwork, the first lower formwork and the second lower formwork.
[0025] According to some embodiments of the present invention, the formwork mechanism further includes a plurality of end form units, which are arranged around the front end of the formwork assembly along the moving direction of the formwork mechanism, and the end form unit includes a first baffle, a second baffle, a limiter, a rotating member, a support rod and a limit screw. The first baffle and the second baffle are spaced apart in the radial direction of the formwork assembly and form a connecting port. The first baffle and the second baffle are connected through the limiter, one end of the rotating member is fixedly connected to the first baffle and / or the second baffle, and the other end of the rotating member is hinged to the formwork assembly. One end of the limit screw is fixedly connected to the formwork assembly through the support rod, and the other end is hinged to the first baffle or the second baffle. Before pouring concrete between the formwork assembly and the inner wall of the tunnel, the method further includes: installing a plurality of limit screws, and supporting the plurality of end form units between the formwork assembly and the inner wall of the tunnel through the plurality of limit screws. Before the lifting device drives the second gantry to descend to the second target position, the method further includes: removing a plurality of limit screws and resetting the plurality of end form assemblies.
[0026] According to some embodiments of the present invention, after installing the plurality of limit screws and supporting the plurality of end mold units between the template assembly and the inner wall of the tunnel through the plurality of limit screws, it also includes: installing the embedded parts between the template assembly and the inner wall of the tunnel through the connecting port; and closing the connecting port with a sealing strip.
[0027] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The present invention will be further described below with reference to the accompanying drawings and embodiments, wherein:
[0029] Figure 1 It is a schematic diagram of the overall structure of a circular arc steel mold trolley according to an embodiment of the present invention;
[0030] Figure 2 It is a schematic diagram of the formwork construction of the arc steel formwork trolley according to one embodiment of the present invention;
[0031] Figure 3 It is a schematic diagram of demoulding construction of a circular arc steel mold trolley according to an embodiment of the present invention;
[0032] Figure 4 It is a schematic diagram of the retraction of the lifting device of the arc steel mold trolley according to one embodiment of the present invention;
[0033] Figure 5 yes Figure 4 Sectional view in the AA direction;
[0034] Figure 6 yes Figure 5 The enlarged view of point B in the middle;
[0035] Figure 7 It is a schematic diagram of the template assembly coordination of the arc steel mold trolley according to an embodiment of the present invention;
[0036] Figure 8 It is a schematic diagram of the template assembly coordination of the arc steel mold trolley according to an embodiment of the present invention;
[0037] Fig. 9 It is a schematic diagram of the template assembly coordination of the arc steel mold trolley according to an embodiment of the present invention;
[0038] Fig.10 It is a schematic diagram of a lifting device of a circular arc steel mold trolley according to an embodiment of the present invention;
[0039] Fig.11 This is an exploded view of the second supporting device of the arc steel mold trolley according to an embodiment of the present invention;
[0040] Fig.12 It is a schematic diagram of a synchronous circuit of an arc steel mold trolley according to an embodiment of the present invention;
[0041] Fig.13 It is a schematic diagram of the overall structure of the adjusting screw rod of the arc steel mold trolley according to an embodiment of the present invention;
[0042] Fig.14 It is an exploded schematic diagram of an adjustment screw rod of an arc steel mold trolley according to an embodiment of the present invention;
[0043] Fig.15 It is a schematic diagram of the structure of the end mold unit of the arc steel mold trolley according to an embodiment of the present invention;
[0044] Fig.16a This is a flow chart of a tunnel construction method based on an arc steel mold trolley according to an embodiment of the present invention;
[0045] Fig.16b The present invention is a flow chart of a tunnel construction method based on an arc steel mold trolley according to an embodiment of the present invention.
[0046] Fig.17 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0047] Fig.18 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0048] Fig.19 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0049] Fig. 20 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0050] Fig.21 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0051] Fig. 22 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0052] Fig.23 It is a flow chart of a tunnel construction method based on a circular arc steel mold trolley according to another embodiment of the present invention;
[0053] Fig.24 It is a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention. DETAILED DESCRIPTION
[0054] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0055] In the description of the present invention, it is necessary to understand that descriptions involving orientation, such as up, down, left, right, etc., the orientations or positional relationships indicated are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0056] In the description of the present invention, the meaning of "a plurality" is more than two, and "exceed" etc. is understood to exclude the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0057] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0058] Reference Figure 1 , Figure 4 and Figure 5 The figure is a schematic diagram of the overall structure of the arc steel form trolley 1000 provided in an embodiment of the present invention, which can be used for tunnel lining, especially for secondary lining after initial tunnel support. The arc steel form trolley 1000 includes a second gantry 100, a first gantry 200 and a formwork mechanism 300. A lifting device 110 is provided at both the front and rear ends of the second gantry 100, which is used to drive the second gantry 100 to rise or fall, thereby driving the first gantry 200 and the formwork mechanism 300 to rise or fall; the second gantry 100 is partially penetrated through the first gantry 200, and the second gantry 100 and the first gantry 200 can move relative to each other. When the second gantry 100 supports the first gantry 200, the first gantry 200 can move along the front and rear direction of the second gantry 100; when the first gantry 200 supports the second gantry 100, refer to Figure 4 As shown, the lifting device 110 is retracted, and the second gantry 100 can move along the front-rear direction of the first gantry 200, and the movement of the arc steel mold trolley 1000 is achieved by supporting each other.
[0059] It should be noted that the relative movement of the second gantry 100 and the first gantry 200 can be achieved by a motor driving a gear, the gear and the rack cooperating to move, or by a winch driving a wire rope to move, and the present invention does not make specific restrictions. The second gantry 100 and the first gantry 200 can be matched in the form of a ball and a slide groove, or in the form of a guide wheel 220 and a guide rail 130. In the following description, the present invention is illustrated by the form of the guide wheel 220 cooperating with the guide rail 130.
[0060] Reference Figure 2 and Figure 3 As shown, Figure 2 This is a schematic diagram of the formwork of the arc steel mold trolley 1000. Figure 3 This is a schematic diagram of the arc steel mold trolley 1000 demoulding. Figure 2 and Figure 3 The section line in the figure is concrete, and the outer side of the concrete is the pipe segment. Figure 3 For the convenience of observation, the structures of the lifting device 110 and the second supporting device 120 are hidden. The formwork mechanism 300 includes a template assembly 310, a first driving cylinder 320, a second driving cylinder 330, a third driving cylinder 340 and a fourth driving cylinder 350. The template assembly 310 includes an upper template 311, a first upper template 312, a first lower template 313, a lower template 314, a second lower template 315 and a second upper template 316. The upper template 311 is located above the first gantry 200, the first upper template 312 and the second upper template 316 are respectively located on the upper side of the first gantry 200 in the left-right direction, the first lower template 313 and the second lower template 315 are respectively located on the lower side of the first gantry 200 in the left-right direction, and the lower template 314 needs to refer to Figure 4 As shown, the lower template 314 is located below the first door frame 200. The upper template 311, the first upper template 312, the first lower template 313, the lower template 314, the second lower template 315 and the second upper template 316 are sequentially connected and arranged around the first door frame 200. Among them, the lower template 314 is detachably connected to the first lower template 313 and the second lower template 315. The detachable connection of the lower template 314 is for the convenience of demoulding. The lower template 314 is removed before demoulding so that other templates can be closer to the first door frame 200 during demoulding.
[0061] Continue to refer to Figure 2 and Figure 3As shown, one end of the first driving cylinder 320 is hinged to the first upper template 312, and the other end of the first driving cylinder 320 is hinged to the first gantry 200; one end of the second driving cylinder 330 is hinged to the second upper template 316, and the other end is hinged to the first gantry 200. The first driving cylinder 320 and the second driving cylinder 330 can respectively drive the first upper template 312 or the second upper template 316 to approach the first gantry 200 to achieve demolding or to move away from the first gantry 200 to achieve formwork. One end of the third driving cylinder 340 is hinged to one end of the first upper template 312 close to the first lower template 313, and the other end of the third driving cylinder 340 is hinged to one end of the first lower template 313 close to the first upper template 312; one end of the fourth driving cylinder 350 is hinged to one end of the second upper template 316 close to the second lower template 315, and the other end of the third driving cylinder 340 is hinged to one end of the second lower template 315 close to the second upper template 316. The third driving cylinder 340 and the fourth driving cylinder 350 can respectively drive the first lower template 313 and the second lower template 315 close to the first gantry 200 to realize demoulding, or away from the first gantry 200 to realize formwork.
[0062] It is understandable that the third driving cylinder 340 is arranged on the first upper template 312 and the first lower template 313, and the first driving cylinder 320 has little effect on the driving of the third driving cylinder 340 during the driving process, so the first driving cylinder 320 can work together with the third driving cylinder 340 to improve work efficiency. The third driving cylinder 340 is not connected to the first gantry 200, so the first lower template 313 and the first upper template 312 can be closer to the first gantry 200 during the demoulding process, reducing the situation where the template assembly 310 hits the tunnel wall. It should be noted that the functions of the second driving cylinder 330 and the fourth driving cylinder 350 are basically the same as those of the first driving cylinder 320 and the third driving cylinder 340, and will not be repeated here.
[0063] Reference Figure 2 and Figure 4 As shown, the mold supporting mechanism 300 also includes a first adjusting screw 360, a second adjusting screw 370, a third adjusting screw 380 and a fourth adjusting screw 390. The first upper template 312 is hinged to the first door frame 200 through the first adjusting screw 360; the first lower template 313 is hinged to the first door frame 200 through the second adjusting screw 370; the second lower template 315 is hinged to the first door frame 200 through the third adjusting screw 380; and the second upper template 316 is hinged to the first door frame 200 through the fourth adjusting screw 390.
[0064] It is understandable that, since the first driving oil cylinder 320 may cause the position of the first upper template 312 to deviate when driving the first upper template 312 to support the mold, the pouring cannot be completed well. Therefore, the first adjusting screw 360 is used to adjust the position of the first upper template 312. The position of the first upper template 312 is adjusted by changing the overall length of the first adjusting screw 360, so that the first upper template 312 is in a suitable pouring position. After the position of the first upper template 312 is determined, the first adjusting screw 360 plays the role of fixing the position of the first upper template 312, which can reduce the phenomenon that the position of the first upper template 312 changes due to the loss of pressure in the first driving oil cylinder 320. It should be noted that the functions and effects of the second adjusting screw 370, the third adjusting screw 380 and the fourth adjusting screw 390 are basically similar to those of the first adjusting screw 360, and will not be repeated here. It should also be noted that the first adjusting screw 360, the second adjusting screw 370, the third adjusting screw 380 and the fourth adjusting screw 390 are all detachably connected. The first adjusting screw 360, the second adjusting screw 370, the third adjusting screw 380 and the fourth adjusting screw 390 are installed during mold support and are removed before demolding to avoid affecting the demolding of the template assembly 310.
[0065] Specifically, refer to Fig.13 and Fig.14 As shown, in some embodiments, the fourth adjusting screw 390 includes a first screw 391, a first nut 392, a second nut 393, a second screw 394 and an adjusting sleeve 395. The first screw 391 and the second screw 394 are respectively screwed to the two ends of the adjusting sleeve 395. The first nut 392 is screwed to the first screw 391 to limit the relative rotation between the first screw 391 and the adjusting sleeve 395. The second nut 393 is screwed to the second screw 394 to limit the relative rotation between the second screw 394 and the adjusting sleeve 395. The overall length of the fourth adjusting screw 390 is changed by rotating the adjusting sleeve 395 to adjust the position of the second upper template 316. After determining the position of the second upper template 316, the length of the fourth adjusting screw 390 is fixed by the first nut 392 and the second nut 393, thereby fixing the position of the second upper template 316. It should be noted that the structures and functions of the first adjusting screw 360 , the second adjusting screw 370 and the third adjusting screw 380 may refer to the fourth adjusting screw 390 , and will not be described in detail here.
[0066] Reference Figure 1 and Figure 5As shown, the length of the second gantry 100 along the front-to-back direction is L1, and the length of the template assembly 310 along the front-to-back direction is L2. In some embodiments, the length of L1 is greater than or equal to twice L2. It is understandable that the template assembly 310 needs to move along the front-to-back direction of the second gantry 100 to achieve different positions of the casting tunnel, so the length of the second gantry 100 needs to be greater than or equal to twice the template assembly 310 so that the template assembly 310 can move smoothly to achieve demoulding.
[0067] Reference Figure 7 , Figure 8 and Fig. 9 As shown, the upper template 311 includes a first reinforcing rib plate and a first ear plate device 3111. The first reinforcing rib plates have multiple pieces and are spaced apart on the inner surface of the upper template 311. The first reinforcing rib plates are used to improve the overall strength of the upper template 311, reduce the deformation of the upper template 311, and improve its stability. The first ear plate device 3111 has multiple pieces and is spaced apart along the edge of the upper template 311 close to the second upper template 316. The first ear plate device 3111 is provided with a first connecting hole 3112 and a first reinforcing rib plate 3113. The first connecting hole 3112 and the first reinforcing rib plate 3113 protrude from the first reinforcing rib plate. The second upper template 316 includes a second reinforcing rib plate 3163 and a second ear plate device 3161. The second reinforcing rib plate 3163 has multiple pieces and is spaced apart on the inner surface of the second upper template 316. The second reinforcing rib plate 3163 is used to improve the overall strength of the second upper template 316, reduce the deformation of the second upper template 316, and improve its stability. There are multiple second ear plate devices 3161 and they are spaced apart along the second upper template 316 close to the edge of the second upper template 316 . The second ear plate device 3161 is provided with a second connecting hole 3162 , and the second connecting hole 3162 protrudes from the second reinforcing rib plate 3163 .
[0068] The formwork mechanism 300 further includes a connecting shaft (not shown in the figure), which is passed through the first connecting hole 3112, the first reinforcing rib plate 3113 and the second connecting hole 3162, so as to hinge the upper template 311 and the second upper template 316. The connecting shaft can be a pin, a dowel, etc. It can be understood that since the first connecting hole 3112, the first reinforcing rib plate 3113 protrudes from the first reinforcing rib plate, and the second connecting hole 3162 protrudes from the second reinforcing rib plate 3163, the rotation center of the upper template 311 and the second upper template 316 protrudes from the first reinforcing rib plate 3163. This can make the connection between the upper template 311 and the second upper template 316 more tightly fitted, and can reduce the phenomenon of concrete leakage from the connection between the upper template 311 and the second upper template 316.
[0069] In some embodiments, the formwork assembly 310 is made of manganese steel, which is a high-strength steel material mainly used for harsh working conditions such as impact, extrusion, and material wear, and has excellent alkali and corrosion resistance. It is understandable that concrete is usually alkaline and easily corrodes the formwork assembly 310. Using manganese steel to make the formwork assembly 310 can reduce the corrosion of the formwork assembly 310, improve the strength of the formwork assembly 310, and increase the service life.
[0070] Reference Fig.12 As shown, in some embodiments, in order to improve the synchronization of the driving of multiple first driving cylinders 320 and reduce the deformation of the template assembly 310, multiple first driving cylinders 320 are connected by a synchronization valve (the second driving cylinder 330, the third driving cylinder 340 and the fourth driving cylinder 350 are also connected by a synchronization valve to ensure the synchronization of the driving, and the structure and function are basically similar to the first driving cylinder 320, and the first driving cylinder 320 is used as an example for illustration). Commonly used synchronization valves are diverter valves and diverter and collector valves 420. Taking the diverter and collector valve 420 as an example, the diverter and collector valve 420 can be used to synchronize the first driving cylinder 320 in both directions. The diverter and collector valve 420 can also be used for a synchronization circuit 400 with a large load difference, and the speed synchronization can still be guaranteed when the load is completely biased, and the synchronization accuracy is high. Among them, the synchronization circuit 400 refers to two or more hydraulic actuators in the hydraulic system running synchronously with the same displacement or the same speed (or fixed speed ratio).
[0071] Reference Fig.12 As shown, taking the driving of two oil cylinders as an example, when the reversing valve 440 is connected to the circuit in the left position, the hydraulic oil of the hydraulic pump 460 is divided into two equal amounts of hydraulic oil through the diverter and collector valve 420 and enters the first driving oil cylinder 320, so that the first driving rods of the two cylinders rise synchronously; when the reversing valve 440 is connected to the circuit in the right position, the diverter and collector valve 420 plays a collecting role and controls the pistons of the two cylinders to descend synchronously. The hydraulically controlled one-way valve 410 in the circuit is to prevent the first driving oil cylinder 320 from moving due to different loads when the stroke stops in the middle. If one of the first driving oil cylinders 320 reaches the end of the stroke first, the oil can flow through the throttle hole in the one-way throttle valve 430, so that each cylinder can reach the end, thereby eliminating the accumulated error. Among them, the overflow valve 450 plays a safety protection role and releases the pressure when the pressure exceeds the threshold. The synchronous circuit 400 can keep the driving of multiple first driving oil cylinders 320 synchronized, reduce the deformation of the template, and improve the construction quality.
[0072] Reference Figure 5 and Figure 6As shown, in some embodiments, the second gantry 100 includes a guide rail 130, which extends along the front-rear direction of the second gantry 100, and two guide rails 130 are arranged at intervals at the upper end and the lower end of the second gantry 100, and the first gantry 200 includes a guide wheel 220 group, and two rows of guide wheel 220 groups corresponding to the positions of the guide rail 130 are arranged at intervals at the upper end and the lower end of the first gantry 200, and each row of guide wheel 220 groups includes a plurality of guide wheels 220, which are arranged at intervals along the extension direction of the guide rail 130. The guide rail 130 and the guide wheel 220 cooperate to roll, so that the second gantry 100 and the first gantry 200 can slide relative to each other.
[0073] It should be noted that the number of guide rails 130 can be three, four or other numbers, which can be selected according to actual needs; the number of guide wheels 220 can also be other numbers, which can be selected according to actual needs. In some embodiments, the guide rails 130 can also be arranged on the first door frame 200, and the guide wheels 220 can be arranged on the second door frame 100.
[0074] Reference Figure 4 As shown, the first portal 200 also includes a first support device 210. Two first support devices 210 are respectively provided at the front and rear ends of the first portal 200, and one first support device 210 is respectively provided on the left and right sides of the front end or the rear end. The first support device 210 can abut against the side wall of the tunnel. It can be understood that the arc steel mold trolley 1000 is basically supported in the tunnel by its own gravity. During the pouring process, the concrete easily lifts the arc steel mold trolley 1000, causing the position of the arc steel mold trolley 1000 to change, affecting the pouring effect. Therefore, the first support device 210 is used to fix the position of the arc steel mold trolley 1000. The first support device 210 includes a first support beam 211 and two limit cylinders 212. The two cylinders are spaced apart on the left and right sides of the first portal 200, and the output ends are fixedly connected to the first support beam 211. The shape of the first support beam 211 matches the wall surface of the tunnel or the shape of the steel mesh. The limiting cylinder 212 drives the first support beam 211 in the left and right direction to abut against the tunnel wall or the steel bars of the tunnel wall to limit the position of the arc steel mold trolley 1000, reduce the problem of the arc steel mold trolley 1000 being lifted up, and improve the stability of the arc trolley.
[0075] Reference Fig.10 and Fig.11As shown, the lifting device 110 includes two legs 111, each leg 111 is provided with a lifting cylinder 1112, a fixing member 1111, a guide member 1114 and a sliding member 1113. The fixing member 1111 is fixedly connected to the guide member 1114, a cavity is formed inside the guide member 1114, and a sliding member 1113 is provided in the cavity. One end of the lifting cylinder 1112 is connected to the fixing member 1111, and the other end of the lifting cylinder 1112 is connected to the sliding member 1113, so that the sliding member 1113 can slide along the axial direction of the guide member 1114, thereby driving the second gantry 100 to move in the vertical direction.
[0076] Continue to refer to Fig.10 and Fig.11 As shown, the second gantry 100 also includes a second supporting device 120, and the second supporting device 120 is provided at both the front and rear ends of the second gantry 100. The second supporting device 120 is connected to the two legs 111 and is used to drive the arc steel mold trolley 1000 to deviate to the left or right. The second supporting device 120 includes a connecting member 121, a second supporting beam 123 and an adjusting cylinder 122. The connecting member 121 includes a plurality of channel steels 1211 and a plurality of connecting ribs 1212. The plurality of channel steels 1211 are connected in sequence to enclose a cavity, and some of the channel steels 1211 are fixedly connected to the legs 111 through the connecting ribs 1212. The adjusting cylinder 122 is arranged in the cavity enclosed by the channel steels 1211, and one end of the adjusting cylinder 122 is connected to the channel steel 12111, and the other end is connected to the second supporting beam 123. The legs 111 are provided with a moving member 112, and the cross section of the moving member 112 is "L" shaped. There are four moving parts 112, and each support leg 111 is provided with a moving part 112 in the front and rear directions (the "four, two" mentioned above are only some embodiments of the present invention, and can also be other numbers, for example, there are eight moving parts 112, and each support leg 111 is provided with four, which is selected according to the actual situation), and the second support beam 123 is slidably connected to the support leg 111 through the moving part 112. It can be understood that when the tunnel turns, it is necessary to adjust the position of the arc steel mold trolley 1000, and the second support beam 123 abuts against the inner wall of the tunnel. Under the drive of the adjusting cylinder 122, the arc steel mold trolley 1000 can be offset as a whole, thereby adjusting the lateral position of the arc steel mold trolley 1000.
[0077] Reference Fig.11As shown, the second support beam 123 is provided with a partition 124, which is arranged between the second support beam 123 and the support leg 111 and fixedly connected to the second support beam 123. The partition 124 is used to reduce the contact area between the second support beam 123 and the support leg 111, thereby reducing the friction force, which can improve the smoothness of sliding and reduce the phenomenon of getting stuck. In some embodiments, the partition 124 is in the shape of a long strip and is arranged along the extension direction of the second support beam 123. Two partitions 124 are arranged at each end of the second support beam 123, which can reduce the shaking of the second support beam 123. It should be noted that the partition 124 can also be other shapes, such as cylindrical, elliptical, etc. The partition 124 can also be other quantities, such as six, eight, etc.
[0078] Reference Figure 4 As shown, the formwork mechanism 300 also includes an end form unit 500, which is arranged at the end of the moving direction of the formwork assembly 310. The end form unit 500 has multiple pieces and is arranged around the formwork assembly 310. The end form unit 500 is used to cooperate with the formwork assembly 310 and the tunnel wall to form a closed space for pouring concrete. It can be understood that during the first pouring process of the tunnel, the front and rear ends of the formwork assembly 310 are provided with end form units 500 to pour the first reinforced concrete structure. After the pouring is completed, the first reinforced concrete structure can act as the end form unit 500. Therefore, the end of the formwork assembly 310 close to the reinforced concrete structure does not need to be provided with the end form unit 500, and only the end of the formwork assembly 310 away from the reinforced concrete structure needs to be provided with the end form unit 500, that is, the end of the moving direction of the formwork assembly 310. It should be noted that the moving direction refers to the forward direction of the arc steel form trolley 1000 during construction.
[0079] Specifically, refer to Fig.15As shown, the end mold unit 500 includes a first baffle 510, a second baffle 520, a stopper 530, a rotating member 540, a support rod 550 and a stopper screw 560. The first baffle 510 and the second baffle 520 are arranged at intervals along the radial direction of the template assembly 310, and a gap is formed by the interval. The embedded parts can be placed through this gap to improve the construction efficiency. The first baffle 510 and the second baffle 520 are connected by a stopper 530. There are two stoppers 530 to make the connection between the first baffle 510 and the second baffle 520 more stable. After the embedded parts are set, it is necessary to use rubber strips to block the gap, and then apply foam glue to improve the sealing effect. The stopper 530 is used to prevent the rubber strip from falling and play a role in limiting the position of the rubber strip. The first baffle 510 and the second baffle 520 are also connected by a rotating member 540, one end of the rotating member 540 is fixedly connected to any one of the first baffle 510 and the second baffle 520, and the other end of the rotating member 540 is hinged to the template assembly 310, so that the end mold unit 500 can be rotatably connected to the template assembly 310 to achieve demolding or supporting the mold. In order to fix the position of the end mold unit 500 when the end mold unit 500 is supporting the mold, a limiting screw 560 is also provided. One end of the support rod 550 is fixedly connected to the template assembly 310, and the other end of the support rod 550 is hinged to one end of the limiting screw 560, and the other end of the limiting screw 560 is hinged to any one of the first baffle 510 and the second baffle 520. The position of the end mold unit 500 can be adjusted by adjusting the length of the limiting screw 560. It should be noted that the structure of the limiting screw 560 can refer to the structure of the first adjustment screw 360.
[0080] In the arc steel mold trolley of the embodiment of the present invention, the second gantry is provided with a first station and a second station along the front-to-back direction, and the first gantry is movably sleeved on the second gantry and can move between the first station and the second station. The first station is located at the rear end along the front-to-back direction, and the second station is located at the front end along the front-to-back direction. The first station and the second station are the positions of the mold support mechanism during casting, and the first gantry can drive the mold support mechanism to move back and forth on the second gantry, thereby switching positions between the first station and the second station.
[0081] Reference Fig.16a and Fig.16b As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to an embodiment of the present invention specifically includes the following steps:
[0082] S1601: A first steel mesh is set up on the inner wall of the tunnel. The first steel mesh is formed by tying steel bars inside the tunnel segments, and the first steel mesh is tied according to the design of the secondary lining of the tunnel.
[0083] S1602: The first gantry moves from the first workstation to the second workstation. The first gantry can achieve relative movement with the second gantry through the cooperation of a winch and a steel wire rope, or the cooperation of a motor and a rack, which is not specifically limited here.
[0084] S1603: The lifting device drives the second gantry to rise to the first target position so that the upper template matches the partial structure corresponding to the first steel mesh frame. The first target position refers to the height position of the second gantry, so that the first gantry rises to the height position ready for construction, that is, the position where the upper template matches the partial structure corresponding to the first steel mesh frame.
[0085] S1604: The first driving cylinder, the second driving cylinder, the third driving cylinder and the fourth driving cylinder are driven respectively to move the first upper template, the second upper template, the first lower template and the second lower template to positions that match the first steel mesh frame, so as to facilitate the pouring of concrete in subsequent steps. It should be noted that the third driving cylinder and the first driving cylinder can be operated simultaneously, or successively, or alternately according to actual working conditions, so as to realize the formwork of the first lower template and the first upper template; the fourth driving cylinder and the second driving cylinder can be operated simultaneously, or successively, or alternately according to actual working conditions, so as to realize the formwork of the second lower template and the second upper template.
[0086] S1605: Install the lower template between the first lower template and the second lower template. The lower template can be formed by splicing a plurality of template units, and the plurality of template units are detachably connected, so that the lower template can be easily installed and disassembled. In addition, by disassembling some template units, the lower template can form a plurality of pouring ports, thereby improving the pouring efficiency and pouring quality when pouring concrete in subsequent steps.
[0087] S1606: pouring concrete between the formwork assembly and the inner wall of the tunnel to form a reinforced concrete structure. It is understandable that a pouring port is provided on the formwork assembly, and a plurality of pouring ports may be provided as required, and the plurality of pouring ports are arranged at intervals. During pouring, the pouring port is opened and concrete is poured through the pouring port. When the liquid level of the concrete is about to reach the pouring port, the corresponding pouring port is closed, and a pouring port at a higher position is replaced for pouring. A vibrator may be provided during the pouring process to reduce the formation of bubbles inside the concrete and improve the quality of pouring.
[0088] S1607: The lifting device retracts and leaves the supporting surface of the tunnel. When the reinforced concrete structure reaches the expected strength, the lifting device retracts. At this time, the first gantry supports the second gantry. The retraction of the lifting device can reduce the situation where the lifting device hits the inner wall of the tunnel during the movement of the second gantry.
[0089] S1608: The second gantry moves along the extension direction of the tunnel to switch the first gantry from the second station to the first station. The second gantry moves forward to facilitate the first gantry to move forward in the subsequent steps, so as to realize the overall movement of the arc steel mold trolley, that is, from one tunnel section to the next tunnel section.
[0090] S1609: The lifting device extends and is supported on the support surface. At this time, the second door frame supports the first door frame, so that the first door frame can move forward in the subsequent steps.
[0091] S1610: Remove the lower template. After removing the lower template, the first lower template and the second lower template can be demoulded smoothly, improving demoulding efficiency. At the same time, after demoulding, the first lower template and the second lower template can be closer to the first portal, reducing the situation where the template assembly hits the inner wall of the tunnel during subsequent movement.
[0092] S1611: The first driving cylinder, the second driving cylinder, the third driving cylinder and the fourth driving cylinder are driven respectively to reset and demould the first upper template, the second upper template, the first lower template and the second lower template. It should be noted that the third driving cylinder and the first driving cylinder can be operated synchronously, or sequentially, or alternately according to the actual working conditions, so as to realize the demoulding of the first lower template and the first upper template; the fourth driving cylinder and the second driving cylinder can be operated synchronously, or sequentially, or alternately according to the actual working conditions, so as to realize the demoulding of the second lower template and the second upper template.
[0093] S1612: The lifting device drives the second gantry to descend to the second target position to demould the upper template. The second target position refers to the height position of the second gantry. The descent of the second gantry drives the descent of the first gantry, thereby driving the template assembly to descend, and realizing demoulding of the upper template.
[0094] In the construction of the secondary lining of the tunnel, the construction method of the embodiment of the present invention adopts an arc steel mold trolley to realize the integral casting of the second lining of the cylindrical tunnel segment. The arc steel mold trolley moves along the extension direction of the tunnel and continues to cast the second lining of the remaining tunnel segments; the arc steel mold trolley includes a first gantry, a second gantry and a mold support mechanism. The second gantry is provided with a first station and a second station. The first gantry is fixedly connected to the mold support mechanism and movably sleeved on the second gantry, so that it can switch positions between the first station and the second station. The second gantry is supported on the supporting surface of the tunnel. The mold support mechanism can complete the processes of mold support, casting, and molding at the second station under the drive of the first gantry. At the same time, before demoulding, the second gantry is separated from the supporting surface and moves along the extension direction of the tunnel, so that the mold support mechanism is switched to the first station. The second gantry is supported on the supporting surface of the tunnel again. At this time, the mold support mechanism completes demoulding at the first station and moves to the second station again to realize the processes of mold support, casting, and molding of the second lining of the next tunnel segment, thereby realizing the cycle of integral casting of the second lining of the tunnel segment. The embodiment of the present invention realizes the integral casting of the secondary lining of multiple tunnel sections through the step-changing operation of the second portal and the formwork mechanism, thereby improving the secondary lining construction efficiency.
[0095] The construction method of the embodiment of the present invention adopts an arc steel formwork trolley, and the formwork mechanism includes a formwork assembly, a first driving cylinder, a second driving cylinder, a third driving cylinder and a fourth driving cylinder, and the formwork assembly includes a first upper formwork, a second upper formwork, a first lower formwork, a second lower formwork and a lower formwork; the upper formwork is located above the first door frame, the lower formwork is located below the first door frame, and is detachably connected to the first lower formwork and the second lower formwork, the two ends of the first driving cylinder are respectively hinged to the first upper formwork and the first door frame, the two ends of the second driving cylinder are respectively hinged to the second upper formwork and the first door frame, the two ends of the third driving cylinder are respectively hinged to one end of the first upper formwork close to the first lower formwork and one end of the first lower formwork close to the first upper formwork, and the fourth driving cylinder The two ends are respectively hinged to one end of the second upper formwork close to the second lower formwork and one end of the second lower formwork close to the second upper formwork; through the above connection method, the first upper formwork and the first lower formwork can be synchronously demoulded by the first driving cylinder and the third driving cylinder respectively, and the second upper formwork and the second lower formwork can be synchronously demoulded by the second driving cylinder and the fourth driving cylinder respectively, and the upper formwork can be lowered by the lifting device to achieve gravity demoulding, which reduces the difficulty of demoulding, improves the demoulding efficiency, and further improves the efficiency of secondary lining construction of the tunnel; and the formwork assembly can be more retracted to the first portal frame in the demoulding state, effectively avoiding the collision of the first portal frame with the inner wall of the tunnel during movement, and improving the safety of construction.
[0096] Reference Fig.17As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps before step S1608:
[0097] S1701: Set up a second steel mesh on the inner wall in the extension direction of the tunnel. The second steel mesh is tied by tying the steel bars in the tunnel segments according to the design of the secondary lining of the tunnel. Step S1701 is generally set between steps S1606 and S1607. While waiting for the reinforced concrete to reach the expected strength, workers can continue to construct the steel mesh for the secondary lining of the next section of the tunnel, thereby shortening the downtime and improving the construction efficiency of the secondary lining of the tunnel.
[0098] Reference Fig.18 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps before step S1606:
[0099] S1801: The limit cylinder drives the first support beam to support the support surface of the tunnel. Step S1801 is generally arranged between steps S1603 and S1606, and a force is applied to the inner wall of the tunnel through the first support beam, so that the first door frame and the formwork mechanism can be more accurately positioned with the inner wall of the tunnel, and the first door frame and the formwork mechanism are prevented from slipping when the formwork assembly and the inner wall of the tunnel are poured with concrete, thereby affecting the pouring quality.
[0100] Reference Fig.19 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps before step S1612:
[0101] S1901: The limit cylinder retracts and leaves the supporting surface. Step S1901 is generally set between steps S1610 and S1612. After the reinforced concrete reaches the expected strength, the formwork assembly is demoulded from the reinforced concrete. Since the demoulding of the upper formwork requires the lifting device to drive the second gantry to descend, thereby driving the first gantry and the formwork assembly to descend, the limit cylinder needs to be retracted to ensure that the limit cylinder does not interfere with the movement of the lifting device.
[0102] Reference Fig. 20 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps after step S1602:
[0103] S2001: Clean the outer surface of the formwork assembly. After multiple demoldings, the outer surface of the formwork assembly will contain a lot of substances that affect demolding. Cleaning can improve the demolding effect. In addition, the formwork assembly is cleaned when the formwork mechanism moves to the second station, which has a larger operating space and is more convenient for workers to clean, thereby improving the cleaning efficiency. In addition, in order to further improve the convenience and safety of workers' cleaning, the second steel mesh frame may not be erected on the inner wall in the extension direction of the tunnel first, but the formwork mechanism may be moved to the second station to clean the formwork assembly first, and then returned to the first station after cleaning, and then the second steel mesh frame may be erected. After the second steel mesh frame is erected, the second lining of the next tunnel segment may be poured.
[0104] Reference Fig.21 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention, step S2001 specifically includes the following steps:
[0105] S2101: Clean the concrete and curing agent on the outer surfaces of the first upper formwork, the second upper formwork, the first lower formwork and the second lower formwork.
[0106] S2102: Apply a release agent to the outer surfaces of the first upper template, the second upper template, the first lower template, and the second lower template.
[0107] By cleaning the curing agent and concrete on the outer surfaces of the first upper formwork, the second upper formwork, the first lower formwork and the second lower formwork, the demoulding efficiency can be improved. After cleaning, applying a release agent according to the actual situation can reduce the adhesion of concrete after subsequent pouring and improve the flatness of the inner surface of the secondary lining of the tunnel after demoulding.
[0108] Reference Fig. 22 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps before step S1606:
[0109] S2201: Install multiple limit screws, and support multiple end form units between the formwork assembly and the inner wall of the tunnel through the multiple limit screws. Before pouring concrete, the end form units are supported by the limit screws to prevent concrete from flowing out of the end of the formwork assembly. The structure of the end form unit is conducive to improving the formwork efficiency and the pouring quality of the secondary lining.
[0110] Reference Fig.23 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps before step S1612:
[0111] S2301: Remove multiple limit screws and reset multiple end mold assemblies. When the reinforced concrete reaches the expected strength, the end mold unit can be easily reset by removing the limit screws, which improves the demoulding efficiency and facilitates the formwork for pouring the second lining of the next tunnel segment.
[0112] Reference Fig.24 As shown, a flow chart of a tunnel construction method based on an arc steel mold trolley according to another embodiment of the present invention includes the following steps after step S2301:
[0113] S2401: Install the embedded parts between the formwork assembly and the inner wall of the tunnel through the connecting port.
[0114] S2402: Use sealing strips to seal the connecting openings.
[0115] It is understandable that after the end mold unit is supported, the embedded parts can be placed through the connecting port, and placing the embedded parts through the connecting port can improve the construction efficiency of the embedded parts and reduce the construction difficulty of the embedded parts. After the embedded parts are constructed, the connecting port can be sealed with a sealing strip such as a rubber strip, or foam glue can be further applied in the gap between the sealing strip and the connecting port, thereby improving the sealing effect of the end mold unit and improving the casting quality of the secondary lining.
[0116] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.
Claims
1. A tunnel construction method based on an arc steel mold trolley, characterized in that: The arc steel mold trolley includes a first gantry, a second gantry and a mold support mechanism, both ends of the second gantry along the front-to-back direction are provided with lifting devices, the second gantry is provided with a first station and a second station along the front-to-back direction, the first gantry is movably sleeved on the second gantry and can move between the first station and the second station; the mold support mechanism includes a template assembly, a first driving cylinder, a second driving cylinder, a third driving cylinder and a fourth driving cylinder, the template assembly includes an upper template, a first upper template, a second upper template, a first lower template, a second lower template and a lower template; the upper template is located above the first gantry and below the first gantry, the upper template, the first upper template, the first lower template, the lower template, the second lower template and the second upper template are sequentially connected and arranged around the first gantry, and the lower template is detachably connected to the first lower template and the second lower template; the two ends of the first driving cylinder are respectively hinged to the first upper template and the first gantry, the two ends of the second driving cylinder are respectively hinged to the second upper template and the first gantry, and the two ends of the third driving cylinder are respectively hinged to the second upper template and the first gantry. One end of the first upper template close to the first lower template and one end of the first lower template close to the first upper template are hinged, and the two ends of the fourth driving cylinder are respectively hinged to one end of the second upper template close to the second lower template and one end of the second lower template close to the second upper template; in the front-to-back direction, the length of the second door frame is L1, and the length of the template assembly is L2, satisfying: L1 / L2≥2, and the formwork mechanism also includes a plurality of end mold units, and the plurality of end mold units are arranged around the template assembly along the moving direction of the formwork mechanism The front end portion of the end mold unit comprises a first baffle, a second baffle, a limiting member, a rotating member, a support rod and a limiting screw, the first baffle and the second baffle are spaced apart in the radial direction of the template assembly and form a communication port, the first baffle and the second baffle are connected through the limiting member, one end of the rotating member is fixedly connected to the first baffle and / or the second baffle, the other end of the rotating member is hinged to the template assembly, one end of the limiting screw is fixedly connected to the template assembly through the support rod, and the other end is hinged to the first baffle or the second baffle; The construction method comprises: Setting up a first steel mesh frame on the inner wall of the tunnel; The first gantry moves from the first station to the second station; The lifting device drives the second gantry to rise to a first target position so that the upper template cooperates with a corresponding partial structure of the first steel mesh frame; The first driving cylinder, the second driving cylinder, the third driving cylinder and the fourth driving cylinder are driven respectively to move the first upper template, the second upper template, the first lower template and the second lower template to positions matching the first steel mesh frame; Installing the lower template between the first lower template and the second lower template; Installing a plurality of the limit screws, and supporting a plurality of the end mold units between the template assembly and the inner wall of the tunnel through the plurality of the limit screws; pouring concrete between the formwork assembly and the inner wall of the tunnel; The lifting device is retracted and separated from the supporting surface of the tunnel; The second gantry moves along the extension direction of the tunnel so that the first gantry switches from the second workstation to the first workstation; The lifting device extends out and is supported on the supporting surface; Disassembling the lower template; The first driving cylinder, the second driving cylinder, the third driving cylinder and the fourth driving cylinder are driven respectively to reset and demould the first upper template, the second upper template, the first lower template and the second lower template; Removing a plurality of the limit screws and resetting a plurality of the end die units; The lifting device drives the second door frame to descend to a second target position to demould the upper template.
2. A tunnel construction method based on an arc steel mold trolley according to claim 1, characterized in that: Before the second gantry moves along the extension direction of the tunnel, the method comprises: A second steel mesh frame is set up on the inner wall in the extension direction of the tunnel.
3. The tunnel construction method based on the circular arc steel mold trolley according to claim 1 is characterized in that: Both ends of the first mast in the front-to-back direction are provided with a first supporting device, the first supporting device comprises a limit cylinder and a first supporting beam, and both ends of the limit cylinder are respectively connected to the first mast and the first supporting beam; Before pouring concrete between the formwork assembly and the inner wall of the tunnel, the method further comprises: The limiting oil cylinder drives the first support beam to be supported on the support surface of the tunnel; Before the lifting device drives the second gantry to descend to the second target position, the lifting device further includes: The limiting oil cylinder retracts and leaves the supporting surface.
4. The tunnel construction method based on the arc steel mold trolley according to claim 1 is characterized in that: After the first gantry moves from the first station to the second station, the method further comprises: Cleaning the outer surface of the template assembly.
5. The tunnel construction method based on the arc steel mold trolley according to claim 4 is characterized in that: The step of cleaning the outer surface of the template assembly comprises: Cleaning concrete and curing agent on the outer surfaces of the first upper formwork, the second upper formwork, the first lower formwork, and the second lower formwork; A release agent is applied to outer surfaces of the first upper formwork, the second upper formwork, the first lower formwork, and the second lower formwork.
6. The tunnel construction method based on the arc steel mold trolley according to claim 1 is characterized in that: After the plurality of limit screws are installed and the plurality of end mold units are supported between the template assembly and the inner wall of the tunnel by the plurality of limit screws, the method further includes: Installing the embedded part between the formwork assembly and the inner wall of the tunnel through the communication port; The communication port is sealed with a sealing strip.