A method for pushing and dropping steel box beams at high position
By setting up the walking machine and falling beam pier suspension system on the steel box girder bottom plate, combined with the use of adjusting steel cylinders and pads, the steel box girder on the large-slope approach bridge can be stably pushed and safely dropped, solving the problem of uneven The problem of cross-support and jacking slope rate conversion shortens the construction period and improves construction safety.
Patent Information
- Application Number
- CN202210278619.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-21
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2042-03-21
AI Technical Summary
When carrying out steel box girder jacking construction on a large-slope approach bridge, it is necessary to solve problems such as non-equal span support, jacking slope rate conversion, linear adjustment and high-level falling beams, especially when the steel structure main bridge cannot be erected on schedule. How to ensure the smooth progress of construction and meet the clearance and boundary requirements for traffic under the bridge.
By setting up the walking machine and the drop beam pier suspension system on the steel box girder bottom plate, and welding the replacement piers to the steel box girder bottom plate, the limited lifting stroke of the walking machine is used to carry out multiple cycles of graded and graded steel box girder lowering. , combined with the use of adjusting steel cylinders and pads, adjust the support points section by section to achieve smooth pushing and falling of the beam.
Achieved stable pushing and safe falling of steel box girders on large-slope approach bridges, shortened the construction period, improved construction safety and stability, avoided the risk of objects falling during the pushing process, and made full use of the walking machine lifting stroke.
Smart Images

Figure CN114561875B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of civil engineering and construction, relates to bridge engineering construction technology, and particularly to a method for jacking and high-position beam dropping of a steel box beam. Background Art
[0002] For municipal bridge projects that cross busy highways and railways, the top-pushing method is generally used to reduce the interference of bridge construction on traffic under the bridge. For concrete beams, due to their heavy weight and large number of support points, the dragging method is generally used for top-pushing; for steel beams, due to their light weight and small number of support points, the walking method is generally used for top-pushing. If the bridge hole that crosses the highway and railway is called the "main bridge" and the other bridge holes at both ends are called "approach bridges", then in general, the construction sequence of the top-pushing method is: after the construction of all the lower structures of the entire bridge is completed, the top-pushing equipment is set on the piers of the approach bridge, and the main bridge is pushed into place first, and then the construction of the upper structure of the approach bridge is carried out.
[0003] Under special circumstances, such as due to special reasons such as site, transportation, and epidemic, the steel structure main bridge cannot be erected on schedule. In order to ensure the overall construction period, the conventional construction sequence must be adjusted, that is, the upper structure of the approach bridge must be constructed first, and then the main bridge is pushed above the approach bridge. This means that the main bridge must "drop the beam from a high position" above the approach bridge to the permanent support. In order to meet the clearance and limit requirements of the highway and railway under the bridge, the longitudinal section of the bridge crossing the highway and railway is generally arranged in a herringbone shape, with a high main span elevation, and a large longitudinal slope of the approach bridge or ramp. Therefore, the slope of the contact surface between the steel box girder and the supporting structure must be adjusted according to the actual slope of the bottom surface of the steel box girder bottom plate to ensure that the main bridge always remains stable during the jacking process and adjusts the line shape at any time; on the other hand, during the jacking process, the setting of temporary piers must also avoid underground cables, pipe networks and other facilities, and often cannot achieve equal span arrangement.
[0004] In summary, the jacking construction of large-span steel box girders above a steep approach bridge must address problems such as unequal span support, jacking slope conversion, line adjustment, and high-position beam drop. Summary of the invention
[0005] The object of the present invention is to provide a method for jacking and high-position lowering of steel box girders, by arranging a crawler and a beam-dropping pier hanging system on the bottom plate of the steel box girder, and welding the replacement piers to the bottom plate of the steel box girder, so as to remove the adjusting steel cylinders of the beam-dropping piers and the replacement piers section by section from bottom to top, and by fully utilizing the limited jacking stroke of the crawler, the steel box girder is lowered onto the permanent support in batches and grades through multiple cycles, thereby solving the above-mentioned problems.
[0006] To achieve the above object, the present invention discloses a method for jacking and dropping a steel box girder at a high position, comprising the following steps:
[0007] S1: Construction preparation: set up fences, road safety signs and traffic diversion equipment, set up a pre-assembly site on the roadbed at the end of the approach bridge, set up a steel box girder assembly frame, and process and manufacture assembled adjustment steel cylinders, adjustment pads and wedge pads;
[0008] S2: Prefabrication of steel box girders: Steel box girder units are processed and manufactured in a professional factory, transported in blocks to the bridge pre-assembly yard, and then assembled on the assembly cradle;
[0009] S3: Construction of bridge deck ancillary facilities and counterweights: After the single steel box girder is assembled as a whole and passed the inspection, the anti-throwing net, guardrail and related bridge deck ancillary facilities are constructed and installed on the outer side of the steel box girder in the pre-assembly yard, concrete counterweights are stacked on the other side of the steel box girder, and limit plates are welded on the steel box girder panels around the concrete counterweights. A protective fence is set up around the steel box girder bridge deck, and an anti-fall baffle is installed at the bottom of the protective fence;
[0010] S4: Setting up the jacking system: Strengthen the approach bridge support, make and install the front guide beam and rear guide beam of the steel box beam, measure and locate each support point on the jacking route of the steel box beam, set up the foundation of the walking machine, set up temporary piers for jacking the steel box beam, set up replacement piers and beam-dropping piers on the temporary piers, and place the walking machine on the walking machine foundation;
[0011] S5: Pushing construction and alignment adjustment: Use a crawler to push a single steel box girder to the top of the designed bridge position. During the pushing process, adjust the position, alignment and elevation of the steel box girder as the pushing progresses.
[0012] S6: Set up the beam hanging system: weld the hanging ear plate on the bottom plate of the steel box beam above the beam dropping pier, hang the fall chain on the hanging ear plate, and connect the lower end of the fall chain to the lifting ear plate on the base of the crawler. Four fall chains are set for a single crawler.
[0013] S7: High-level graded beam drop and support system conversion: On the replacement pier and beam drop pier, use a crawler to gradedly drop the steel box beam to the top of the permanent support, install the permanent support of the steel box beam in place, and complete the support system conversion of the steel box beam;
[0014] S8: Dismantle various temporary structures: After the beam is lowered, use the horizontal fall chain to drag the crawler, adjustment steel cylinder and related temporary structures out of the plane of the steel box beam along the transverse direction of the bridge, and then use the truck crane to transport them to the designated location;
[0015] S9: Proceed with the construction of the next steel box girder.
[0016] Preferably, the counterweight block is a prefabricated concrete block with a specification of 1500mm×600mm×2000mm, and the limiting plate is a steel plate with a specification of 100mm×100mm×10mm.
[0017] Furthermore, the front guide beam is 26m long and the rear guide beam is 12m long. Both the front and rear steel guide beams are variable stiffness structures, and the stiffness gradually decreases from the root to the end. The front end of the front guide beam is arc-shaped, and the steel guide beam is prefabricated and assembled in sections. The sections of the steel guide beam and the steel guide beam and the steel box beam are connected by bolts and welding. The web is connected by bolts and the flange plate is welded. The connecting bolts are all M24 high-strength bolts.
[0018] Furthermore, the walker foundation adopts a reinforced concrete expanded foundation with a foundation thickness of 500mm. The four sides of the foundation are 500mm to 600mm larger than the walker base plate. A leveling layer is arranged on the bottom surface of the foundation. The leveling layer is filled with C15 concrete. The four sides of the leveling layer are 200mm larger than the walker foundation.
[0019] Furthermore, the lifting capacity of the hanging lugs and fall chains is not less than 20t / piece.
[0020] As a further improvement of the steel box girder jacking and high-position beam dropping method of the present invention, in step S1, the adjusting steel cylinder includes an upper connecting plate, a lower connecting plate, a cylinder body and a steel cylinder stiffening plate, and the height of a single-section adjusting steel cylinder is H t , the diameters of the upper connecting plate and the lower connecting plate are 1000mm to 1200mm, the outer diameter of the cylinder is 800mm to 1000mm, and the upper connecting plate and the lower connecting plate are provided with corresponding bolt holes;
[0021] In step S1, the adjusting pad includes an upper plate, a lower plate and a vertical rib plate, and the height of a single adjusting pad is H. k , the plane is a square with a side length of 300mm;
[0022] In step S1, the wedge-shaped pad has a square plane with a side length of 300 mm to 500 mm, a minimum thickness of 6 mm to 10 mm, a horizontal bottom surface, and a sloped top surface. The slope of the top surface of the wedge-shaped pad is consistent with the slope of the bottom surface of the steel box girder bottom plate during the jacking process. There are multiple types of wedge-shaped pads, which are matched with the jacking slopes respectively.
[0023] As a further improvement of the steel box girder jacking and high-position beam dropping method of the present invention, in step S1, the maximum jacking stroke of the crawler is L d The height of the single-section adjustable steel cylinder is n times the maximum lifting stroke, that is, H t =nL d The height of the single adjusting pad is 5 mm smaller than the maximum lifting stroke, that is, H k =L d -5mm.
[0024] Preferably, the lifting capacity of the crawler is not less than 450t, and the maximum lifting stroke is L d=100mm.
[0025] Preferably, n=5, and the height of the steel cylinder is adjusted to H t =500mm, the upper connecting plate, lower connecting plate and cylinder body of the adjusting steel cylinder are made of steel plates with a wall thickness of 16mm, and the steel cylinder stiffening plate is made of steel plates with a wall thickness of 12mm.
[0026] Preferably, the height of the adjusting pad is H k =95mm, the upper plate, lower plate and vertical ribs of the adjusting pad are all made of steel plates with a wall thickness of 12mm.
[0027] In step S4, the temporary pier adopts a combined structure, including a temporary pile foundation and a temporary cap, a steel pipe column is arranged on the temporary cap, the steel pipe column and the temporary cap are fixed with anchor bolts, a connecting rod is arranged between the steel pipe columns, a pressure beam is arranged on the top of the steel pipe column, and a transverse bridge sliding beam is arranged on the side of the pressure beam;
[0028] Preferably, the temporary piers are arranged with two piles along the cross section of a single steel box girder, with two rows of piles arranged along the bridge direction, with a spacing of 5.0m in the transverse direction and 3.0m in the longitudinal direction, and a reinforced concrete cap of 8.2m×5.0m×1.0m is set on the top of the piles.
[0029] Preferably, the steel pipe column of the temporary pier is Spiral steel pipe, the anchor bolts are M25×800mm, and the connecting rods between steel pipe columns are The steel pipe column is provided with longitudinal and transverse stiffening plates within 500mm of the column top.
[0030] Preferably, the pressure beam adopts a welded box-shaped structure with a cross-section width×height=900mm×700mm, and is made of 16mm steel plate, with stiffening plates arranged at intervals of 900mm to 1200mm.
[0031] Preferably, the transverse bridge sliding beam is made of HM440×300×11×18 steel, and the end of the transverse bridge sliding beam extends 1.0m to 2.0m beyond the edge of the steel box beam.
[0032] In step S4, the replacement pier and the beam-dropping pier are both connected by multiple sections of assembled adjusting steel cylinders, each section of the adjusting steel cylinder is connected to the other by high-strength bolts, a leveling steel plate is arranged at the bottom of the replacement pier, and cross-linking rods are arranged between adjacent replacement piers and adjacent beam-dropping piers.
[0033] Preferably, the high-strength bolts between the adjusting steel cylinders are M20-M24, and the number is 16.
[0034] Preferably, the cross link adopts Steel pipe.
[0035] As the method for pushing and dropping the steel box girder at a high position of the present application, in step S5, the specific steps of pushing and adjusting the linear shape of the steel box girder are as follows:
[0036] S5.1: Construction preparation before jacking: set wedge-shaped pads on the top of the walker slide box and the top of the pier, adjust the initial elevation of the walker pier for the first time, lift the walker, transfer the steel box girder from the assembly tire frame to the walker, and remove the assembly tire frame;
[0037] S5.2: Parallel jacking of steel box girder: Push the steel box girder in a direction parallel to the bridge deck. During the jacking process, use the three-way jack of the crawler to adjust the direction and plane position of the steel box girder. As the jacking progresses, transfer the crawler that has withdrawn from the work at the tail end of the steel box girder to the foundation of the crawler in front and place it firmly.
[0038] S5.3: Set up a horizontal jacking and beam-dropping system: When the front end of the leading beam is jacked to the tail end of the approach bridge, a manual operation platform is set up on the top of the beam-dropping pier, and the crawler machine withdrawing from the tail end of the steel box beam is transferred to the top of the beam-dropping pier. The top section adjustment steel cylinder of the beam-dropping pier, the manual operation platform and the crawler machine base plate are connected by bolts, and a stiffening plate is welded between the top section adjustment steel cylinder of the beam-dropping pier and the stiffening rib of the manual operation platform, and a platform fence is set up around the manual operation platform;
[0039] S5.4: Lifting the steel box girder at the rear support, specifically including the following steps:
[0040] S5.4.1: The steel box girder rear support walker is lifted and the initial elevation of the walker pier is adjusted for the second time;
[0041] S5.4.2: The rear support crawler of the steel box girder is lifted up to make the top surface of the rear support crawler pier empty;
[0042] S5.4.3: Place adjustment pads on the crawler piers at the rear support points of the steel box girder;
[0043] S5.4.4: The walker at the rear support of the steel box girder is lowered so that the rear support of the steel box girder is supported by the walker pier;
[0044] S5.4.5: Place adjustment pads on the walker slide box at the rear support of the steel box girder;
[0045] S5.4.6: Repeat the above steps S5.4.2 to S5.4.5 to adjust the linear shape of the steel box girder until the top surfaces of the front and rear support points of the steel box girder are roughly flush, and replace the wedge pads so that the slope of the top surface of the wedge pads matches the slope of the bottom surface of the bottom plate of the steel box girder after the linear shape adjustment;
[0046] S5.5: Use the three-way jack of the crawler to fine-tune the position, alignment and elevation of the steel box girder, and alternately insert thin steel plates into the sliding box and piers of the crawler at the rear support of the steel box girder to make the position and alignment of the steel box girder basically consistent with the design state;
[0047] S5.6: The crawler is lifted and the initial elevation of the crawler pier is adjusted for the third time. The steel box girder is pushed horizontally to the top of the designed bridge position in the horizontal direction.
[0048] S5.7: Remove the front guide beam and rear guide beam of the steel box girder;
[0049] S5.8: Use the three-way jack of the walking machine to fine-tune the position, alignment and elevation of the steel box girder;
[0050] S5.9: The jacking of the steel box girder is completed and the beam dropping process begins.
[0051] As a further improvement of the steel box girder jacking and high-position beam dropping method of the present application, in the step S5.1, before the steel box girder is jacked in parallel, the initial elevation of the first adjustment of the walker pier must meet the following requirements: when the walker slide box is in the lowering state, the inclined plane where the top surface of the wedge-shaped pads on the front and rear piers of the walker is located is 20 mm to 50 mm higher than the inclined plane where the top surface of the wedge-shaped pads on the slide box is located;
[0052] In step S5.4.1, before the steel box beam is pushed in parallel, the second adjustment of the initial elevation of the walker pier must meet the following requirements: when the rear fulcrum walker slide box is in the descending state, the inclined plane where the top surface of the wedge-shaped pads on the front and rear piers of the rear fulcrum walker is located is higher than the inclined plane where the top surface of the wedge-shaped pads on the slide box is located (L d -H k ) / 2=2.5mm;
[0053] In the step S5.6, before the steel box girder is horizontally pushed, the initial elevation of the crawler pier is adjusted for the third time, so that when the crawler slide box is in the lowered state, the top surface of the crawler pier is 20 mm to 50 mm higher than the top surface of the replacement pier.
[0054] The method for pushing and dropping the steel box beam at a high position in the present application is characterized in that, in step S7, the specific steps of dropping the beam at a high position and converting the support system are as follows:
[0055] S7.1: The walker is lifted up to make the top surface of the walker pier empty, and the initial elevation of the walker pier is adjusted for the fourth time;
[0056] S7.2: The crawler descends, supports the steel box girder on the replacement pier, and welds the adjustment steel cylinder of the top section of the replacement pier to the bottom plate of the steel box girder;
[0057] S7.3: Remove the connecting bolts of the adjusting steel cylinder of the bottom section of the beam-dropping pier, use the fall chain to hoist the crawler machine and the beam-dropping pier as a whole, remove the adjusting steel cylinder of the bottom section of the beam-dropping pier, and then use the fall chain to lower the crawler machine and the beam-dropping pier to the pressure beam of the temporary supporting pier, and place them firmly;
[0058] S7.4: Place n layers of adjustment pads on the sliding box and the pier of the walker respectively;
[0059] S7.5: Remove the connecting bolts of the adjusting steel cylinder of the bottom section of the replacement pier, and lift it with a crawler to make the bottom surface of the replacement pier empty;
[0060] S7.6: Remove the adjusting steel cylinder at the bottom section of the replacement pier;
[0061] S7.7.1: The crawler is lowered so that the steel box girder is supported on the crawler piers;
[0062] S7.7.2: Remove the top adjustment pads on the top of the walker slide box;
[0063] S7.7.3: The walker is lifted up to lift the steel box girder so that the top surface of the walker pier is free;
[0064] S7.7.4: Remove the top leveling pads from the top of the walker piers;
[0065] S7.8: Repeat the above steps S7.7.1 to S7.7.4 until all the adjustment pads on the crawler slide box and the top of the pier are removed and the crawler is lowered. At this time, the steel box girder is supported on the replacement pier after the height is lowered;
[0066] S7.9: Repeat the above steps S7.3 to S7.8 until all the adjustment steel cylinders of the beam-dropping pier are removed. Use the fall chain to lower the crawler to the pressure beam of the temporary pier. The crawler lands. At this time, the steel box beam is supported on the replacement pier after the height is lowered. The distance between the bottom surface of the steel box beam and the top surface of the permanent support is exactly the height H of one section of the adjustment steel cylinder. k ;
[0067] S7.10: Execute the above steps S7.4 to S7.5, remove all remaining adjustment steel cylinders of the replacement pier, at this time, the steel box girder is supported on the adjustment pads on the top of the crawler slide box, and the position of the steel box girder is fine-tuned by using the three-way jack of the crawler, so that the steel box girder is accurately positioned according to the design position of the permanent support, and the installation and adjustment of the permanent support are performed;
[0068] S7.11: Repeat the above steps S7.7.1 to S7.7.4 to allow the steel box girder to be smoothly lowered to the permanent support. The crawler is unloaded and the steel box girder is supported by the permanent support. The steel box girder support system conversion is completed. The temporary welding parts of the steel box girder are repaired and the beam is lowered.
[0069] As a further improvement of the steel box girder jacking and high-position beam dropping method of the present invention, in step S7.1, before the steel box girder is dropped at a high position, the fourth adjustment of the initial elevation of the walker pier must meet the following requirements: when the walker slide box is in the descending state, the top surface of the walker pier is higher than the top surface of the walker slide box (L d -H k ) / 2=2.5mm.
[0070] As a further improvement of the steel box girder jacking and high-position beam dropping method of the present invention, in step S4, when setting the temporary pier, the top surface elevation of the pressure beam must be calculated in advance, and the calculation method is as follows:
[0071] Known conditions: The top elevation of the permanent support of the steel box girder is Z Z , the height from the bottom of the walking machine base plate to the top of the slide box is H b , the maximum lifting stroke of the crawler is L d , the height of the single-section steel cylinder is H t =nL d , the height of a single adjusting pad is H k =L d -5mm;
[0072] Constraints: When the steel box girder is supported on the replacement pier, the top surface of the replacement pier should be more than 20mm higher than the top surface of the walker pier; when the steel box girder is supported on the adjustment pad on the top of the walker slide box, the top surface of the replacement pier should be more than 20mm lower than the top surface of the adjustment pad on the top of the walker slide box;
[0073] Elevation range: The top elevation of the pressure beam of the temporary pier is set as Z L , then the elevation difference between the top surface of the permanent support and the top surface of the pressure beam is ΔH=(Z Z -Z L ) should meet the following conditions: b +(L d -H k ) / 2+20mm≤ΔH≤H b +nH k +L d -H t -20mm, in order to control the elevation of the top surface of the pressure beam, that is, Z Z -H b -nH k -L d +H t +20mm≤Z L ≤Z Z -H b -(L d -H k ) / 2-20mm.
[0074] As a method for jacking and high-position dropping of steel box girders in this application, deformation and stress monitoring are carried out at key stress-bearing parts of the steel box girder, steel guide beam, temporary piers, approach bridge piers and permanent supports of the approach bridge and related structures during the jacking and dropping process of the steel box girder.
[0075] Compared with the prior art, the advantages of the present invention are:
[0076] (1) The anti-throw net, guardrail and other bridge deck ancillary facilities are constructed and installed on the outer side of the steel box girder in the pre-assembly yard, the counterweight is stacked on the other side of the steel box girder, and the anti-fall baffle is installed at the bottom of the protective fence around the steel box girder bridge deck. While ensuring the lateral symmetry of the steel box girder load, it can reduce the subsequent high-altitude operations and prevent objects from falling from the steel box girder during the jacking process, which is safe.
[0077] (2) By reinforcing the approach bridge supports, the main bridge can be pushed upward above the approach bridge without interrupting traffic under the bridge. During the processing and manufacturing of the steel box girder of the main bridge, the construction of the approach bridge superstructure can be carried out simultaneously, which is conducive to shortening the overall construction period.
[0078] (3) When the steel box girder is pushed on the approach bridge with a large slope, a wedge-shaped pad is set on the top of the crawler. The bottom surface of the wedge-shaped pad is level with the contact surface of the crawler slide box and the pier. The top surface of the wedge-shaped pad is set with the same slope as the bottom surface of the bottom plate of the steel box girder to ensure that the bearing surface of the steel box girder is in close contact during the pushing process and the overall stability is good.
[0079] (4) The crawler machine and the adjusting steel cylinder of the top section of the beam-dropping pier are connected as a whole by bolts. By welding the hanging ear plates under the bottom plate of the steel box girder and setting up the crawler machine hanging system, the crawler machine and the beam-dropping pier are lifted as a whole by the fall chain, so that the adjusting steel cylinder of the beam-dropping pier can be removed section by section from the bottom to the top. The operation is very simple, avoiding the tedious operation of repeated assembly and disassembly when disassembling from top to bottom, and has good safety.
[0080] (5) By pre-adjusting the elevation of the top surface of the walker pier, when the steel box girder is pushed, the minimum height difference between the walker pier and the top surface of the walker slide box is 20mm to 50mm; when the beam is raised or lowered, the minimum height difference between the walker pier and the top surface of the walker slide box is 2.5mm. While smoothly realizing the force conversion between the replacement pier, the walker pier and the walker slide box, the lifting stroke of the walker can be fully utilized.
[0081] (6) A large and small double cycle method is adopted, in which the steel box girder is alternately supported by the replacement pier, the crawler pier and the crawler slide box, and the beam is dropped in batches and grades. The drop height of a single cycle is slightly less than the maximum lifting stroke of the crawler, thereby transforming the high-position beam drop into a continuous low-position beam drop. The steel box girder has good stability and high safety during the beam dropping process. BRIEF DESCRIPTION OF THE DRAWINGS
[0082] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0083] Figure 1 This is a flow chart of the top pushing and high-position beam dropping of the steel box beam of the present invention;
[0084] Figure 2 This is a flow chart of the top pushing of the steel box girder of the present invention;
[0085] Figure 3 This is a flow chart of high-position beam drop of a steel box beam of the present invention;
[0086] Figure 4 This is a schematic diagram of the three-dimensional structure of the adjusting steel cylinder of the present invention;
[0087] Figure 5 This is a schematic diagram of the three-dimensional structure of the adjusting pad block of the present invention;
[0088] Figure 6 This is a schematic diagram of the structure of the wedge-shaped pad of the present invention;
[0089] Figure 7 This is a schematic diagram of the arrangement of the concrete counterweight blocks of the present invention;
[0090] Figure 8 It is a schematic diagram of the overall arrangement of the steel box girder before jacking of the present invention;
[0091] Fig. 9 It is a schematic diagram of the steel box girder of the present invention when it is pushed up to the tail end of the approach bridge;
[0092] Fig.10 It is a schematic diagram of the steel box girder after the rear support beam lifting is completed;
[0093] Fig.11 This is a schematic diagram of the basic structure of the walking machine of the present invention;
[0094] Fig.12 It is a schematic diagram of the three-dimensional structure of the temporary buttress according to the present invention;
[0095] Fig.13 It is a schematic diagram of the arrangement of the hanging system of the walking machine of the present invention;
[0096] Fig.14 This is a schematic diagram of adjusting the elevation of the pier of the walking machine for the first time according to the present invention;
[0097] Fig.15 This is a schematic diagram of adjusting the elevation of the pier of the walking machine for the second time according to the present invention;
[0098] Fig.16 This is a schematic diagram of adjusting the elevation of the pier of the walking machine for the third time according to the present invention;
[0099] Fig.17 This is a schematic diagram of adjusting the elevation of the pier of the walking machine for the fourth time according to the present invention;
[0100] Fig.18 Schematic diagram of the rear support point of the steel box girder after placing the adjustment pads on the crawler pier;
[0101] Fig.19 Schematic diagram of the slide box of the walking machine after placing the adjustment pads at the rear support of the steel box girder;
[0102] Fig. 20 This is a layout diagram of the crawler before the high-position beam drop of the present invention;
[0103] Fig.21 Schematic diagram of the bottom section adjustment steel cylinder removed and lowered for the beam drop pier;
[0104] Fig. 22 Schematic diagram after removing the bottom section adjustment steel cylinder for the replacement pier;
[0105] Fig.23 This is a schematic diagram after removing the top adjustment pad on the top of the walker slide box;
[0106] Fig.24 This is a schematic diagram after removing the top adjustment pads on the top of the walker pier;
[0107] Fig.25 This is a schematic diagram after all the adjusting steel cylinders of the beam pier have been removed and lowered;
[0108] Fig.26 This is a schematic diagram after all the adjusting steel cylinders of the replacement pier have been removed.
[0109] Figure numerals: 1-adjusting steel cylinder; 1-1-upper connecting plate; 1-2-lower connecting plate; 1-3-cylinder; 1-4-steel cylinder stiffening plate; 2-adjusting pad; 2-1-upper plate; 2-2-lower plate; 2-3-vertical rib plate; 3-wedge pad; 4-concrete counterweight; 5-limiting plate; 6-protective fence; 7-front guide beam; 8-rear guide beam; 9-walking machine foundation; 10-temporary pier; 10-1-temporary pile foundation; 10-2-temporary cap; 10-3-steel pipe column; 10-4-connecting rod; 10-5- Pressure beam; 11-replacement pier; 11-1-leveling steel plate; 12-beam drop pier; 13-hanging ear plate; 14-falling chain; 15-hoisting ear plate; 16-transverse bridge sliding beam; 17-transverse connecting rod; 18-sliding box; 19-pillar; 20-manual operation platform; 21-platform stiffening rib; 22-platform stiffening plate; 23-platform fence; 100-steel box beam; 101-approach bridge main beam; 102-approach bridge reinforcement device; 103-steel box beam bottom plate; 104-elevation difference 20mm~50mm; 105-elevation difference (L d -H k) / 2=2.5mm; 106—permanent support. DETAILED DESCRIPTION
[0110] The embodiments of the present invention are described in detail below with reference to the accompanying drawings, but the present invention can be implemented in many different ways as defined and covered by the claims.
[0111] like Figures 1 to 26 As shown in the figure, a certain overpass bridge over a highway has a total length of 326.4m and a bridge width of 40.5m. The bridge is designed in left and right sections. The main bridge adopts a 52m simple-supported steel box girder with one span, the east approach bridge adopts (2×30m+3×30m) two-unit prestressed concrete cast-in-place continuous box girder, and the west approach bridge adopts (4×30m) one-unit prestressed concrete cast-in-place continuous box girder. The plane is a straight line and the vertical surface is symmetrically arranged. The longitudinal slopes of the approach bridges at both ends are 3.8% and -3.8% respectively, with a large slope. The single-span steel box girder adopts a single-box three-chamber inclined web section. The top width of the single-span steel box girder is 20.14m, the bottom width of the box is 13.862m, the beam height at the center line of the bridge is 2.3m, and the single-span steel box girder weighs about 650t. The steel box girder of the main bridge is constructed by crawler-type jacking. The steel box girder is assembled on the roadbed at the end of the west approach bridge, and a crawler machine is set on the erected approach bridge deck. After the main hole steel box girder is jacked into place, it is necessary to drop the beam from the approach bridge deck to the support position. The steel box girder is 2.3m high, and the height of the crawler machine and the foundation is 1.2m. There is a height difference of 3.5m when dropping the beam. Due to the very busy traffic under the bridge, the safety risks of jacking and beam dropping construction are extremely high.
[0112] In order to achieve safe, stable and accurate jacking and beam dropping, the present invention discloses a method for jacking and high-position beam dropping of a steel box beam, which specifically comprises the following steps:
[0113] S1: Construction preparation: set up fences, road safety signs and traffic diversion equipment, set up a pre-assembly site on the roadbed at the end of the approach bridge, set up a steel box girder assembly frame, and process and manufacture assembled adjustment steel cylinder 1, adjustment pad 2 and wedge pad 3;
[0114] S2: Prefabrication of steel box girders: Steel box girder units are processed and manufactured in a professional factory, transported in blocks to the bridge pre-assembly yard, and then assembled on the assembly cradle;
[0115] S3: Construction of bridge deck ancillary facilities and counterweight: After the single steel box girder is assembled as a whole and passed the inspection, the anti-throwing net, guardrail and related bridge deck ancillary facilities are constructed and installed on the outer side of the steel box girder in the pre-assembly yard, concrete counterweight blocks 4 are stacked on the other side of the steel box girder, and limit plates 5 are welded on the steel box girder panels around the concrete counterweight blocks. A protective fence 6 is set around the steel box girder bridge deck, and an anti-fall baffle is installed at the bottom of the protective fence;
[0116] S4: Setting up the jacking system: strengthening the approach bridge support, manufacturing and installing the front guide beam 7 and the rear guide beam 8 of the steel box beam, measuring and positioning each support point on the jacking route of the steel box beam, setting up the crawler foundation 9, setting up the temporary supporting pier 10 for jacking up the steel box beam, setting up the replacement pier 11 and the beam dropping pier 12 on the temporary supporting pier, and placing the crawler on the crawler foundation 9;
[0117] S5: Pushing construction and alignment adjustment: Use a crawler to push a single steel box girder to the top of the designed bridge position. During the pushing process, adjust the position, alignment and elevation of the steel box girder as the pushing progresses.
[0118] S6: Setting up the beam drop hanging system: welding a hanging lug plate 13 on the bottom plate of the steel box beam above the beam drop pier 12, hanging a fall chain 14 on the hanging lug plate 13, the lower end of the fall chain 14 is connected to the hanging lug plate 15 on the base of the crawler, and four fall chains 14 are set for a single crawler;
[0119] S7: High-level step-by-step beam drop and support system conversion: On the replacement pier 11 and beam drop pier 12, use a walker to step-by-step drop the steel box beam to the top of the permanent support, install the permanent support of the steel box beam in place, and complete the support system conversion of the steel box beam;
[0120] S8: Dismantle various temporary structures: After the beam is dropped, use the horizontal fall chain to drag the crawler, the adjustment steel cylinder 1 and the related temporary structures out of the plane of the steel box beam along the transverse direction of the bridge, and then use the truck crane to transport them to the designated location;
[0121] S9: Proceed with the construction of the next steel box girder.
[0122] Preferably, the counterweight block is a prefabricated concrete block with a specification of 1500mm×600mm×2000mm, and the limiting plate is a steel plate with a specification of 100mm×100mm×10mm.
[0123] Furthermore, the front guide beam is 26m long and the rear guide beam is 12m long. Both the front and rear steel guide beams are variable stiffness structures, and the stiffness gradually decreases from the root to the end. The front end of the front guide beam is arc-shaped, and the steel guide beam is prefabricated and assembled in sections. The sections of the steel guide beam and the steel guide beam and the steel box beam are connected by bolts and welding. The web is connected by bolts and the flange plate is welded. The connecting bolts are all M24 high-strength bolts.
[0124] Furthermore, the walker foundation adopts a reinforced concrete expanded foundation with a foundation thickness of 500mm. The four sides of the foundation are 500mm to 600mm larger than the walker base plate. A leveling layer is arranged on the bottom surface of the foundation. The leveling layer is filled with C15 concrete. The four sides of the leveling layer are 200mm larger than the walker foundation.
[0125] Furthermore, the lifting capacity of the hanging lugs and fall chains is not less than 20t / piece.
[0126] In this embodiment, in step S1, the adjusting steel cylinder 1 includes an upper connecting plate 1-1, a lower connecting plate 1-2, a cylinder body 1-3 and a steel cylinder stiffening plate 1-4. The height of the single-section adjusting steel cylinder 1 is H t , the diameters of the upper connecting plate 1-1 and the lower connecting plate 1-2 are 1000mm to 1200mm, the outer diameter of the cylinder 1-3 is 800mm to 1000mm, and the upper connecting plate 1-1 and the lower connecting plate 1-2 are provided with corresponding bolt holes;
[0127] In step S1, the adjusting pad 2 includes an upper plate 2-1, a lower plate 2-2 and a vertical rib 2-3, and the height of a single adjusting pad 2 is H k , the plane is a square with a side length of 300mm;
[0128] In step S1, the wedge-shaped pad 3 has a square plane, a side length of 300 mm to 500 mm, a minimum thickness of 6 mm to 10 mm, a horizontal bottom surface, and a sloped top surface. The slope of the top surface of the wedge-shaped pad 3 is consistent with the slope of the bottom surface of the steel box girder bottom plate during the jacking process. There are multiple types of wedge-shaped pads 3, which match the jacking slopes respectively.
[0129] In this embodiment, in step S1, the maximum lifting stroke of the walking machine is L d The height of the single-section adjusting steel cylinder 1 is n times the maximum lifting stroke, that is, H t =nL d The height of the single adjusting pad 2 is 5 mm smaller than the maximum lifting stroke, that is, H k =L d -5mm.
[0130] Preferably, the lifting capacity of the crawler is not less than 450t, and the maximum lifting stroke is L d =100mm.
[0131] Preferably, n=5, and the height of the steel cylinder is adjusted to H t =500mm, the upper connecting plate, lower connecting plate and cylinder body of the adjusting steel cylinder are made of steel plates with a wall thickness of 16mm, and the steel cylinder stiffening plate is made of steel plates with a wall thickness of 12mm.
[0132] Preferably, the height of the adjusting pad is H k =95mm, the upper plate, lower plate and vertical ribs of the adjusting pad are all made of steel plates with a wall thickness of 12mm.
[0133] In this embodiment, in step S4, the temporary pier 10 adopts a combined structure, including a temporary pile foundation 10-1 and a temporary cap 10-2. A steel pipe column 10-3 is arranged on the temporary cap 10-2. The steel pipe column 10-3 and the temporary cap 10-2 are fixed with anchor bolts. A connecting rod 10-4 is arranged between the steel pipe columns 10-3. A pressure beam 10-5 is arranged on the top of the steel pipe column 10-3. A transverse bridge sliding beam 16 is arranged on the side of the pressure beam 10-5.
[0134] Preferably, the temporary piers are arranged with two piles along the cross section of a single steel box girder, with two rows of piles arranged along the bridge direction, with a spacing of 5.0m in the transverse direction and 3.0m in the longitudinal direction, and a reinforced concrete cap of 8.2m×5.0m×1.0m is set on the top of the piles.
[0135] Preferably, the steel pipe column of the temporary pier is Spiral steel pipe, the anchor bolts are M25×800mm, and the connecting rods between steel pipe columns are The steel pipe column is provided with longitudinal and transverse stiffening plates within 500mm of the column top.
[0136] Preferably, the pressure beam adopts a welded box-shaped structure with a cross-section width×height=900mm×700mm, and is made of 16mm steel plate, with stiffening plates arranged at intervals of 900mm to 1200mm.
[0137] Preferably, the transverse bridge sliding beam is made of HM440×300×11×18 steel, and the end of the transverse bridge sliding beam extends 1.0m to 2.0m beyond the edge of the steel box beam.
[0138] In step S4, the replacement pier 11 and the beam-dropping pier 12 are both connected by multiple sections of assembled adjusting steel cylinders 1, and each section of the adjusting steel cylinder 1 is connected to the adjusting steel cylinder 1 by high-strength bolts. A leveling steel plate 11-1 is arranged at the bottom of the replacement pier 11, and a cross-linking rod 17 is arranged between adjacent replacement piers 11 and adjacent beam-dropping piers 12.
[0139] Preferably, the high-strength bolts between the adjusting steel cylinders are M20-M24, and the number is 16.
[0140] Preferably, the cross link adopts Steel pipe.
[0141] In this embodiment, in step S5, the specific steps of the steel box girder top-pushing construction and line shape adjustment are as follows:
[0142] S5.1: Construction preparation before jacking: set wedge-shaped pads 3 on the top of the walker slide box 18 and the top of the pier 19, adjust the initial elevation of the walker pier 19 for the first time, lift the walker, transfer the steel box girder from the assembly tire frame to the walker, and remove the assembly tire frame;
[0143] S5.2: Parallel jacking of steel box girder: Push the steel box girder in a direction parallel to the bridge deck. During the jacking process, use the three-way jack of the crawler to adjust the direction and plane position of the steel box girder. As the jacking progresses, transfer the crawler that exits the work at the tail end of the steel box girder to the front crawler foundation 9 and place it firmly.
[0144] S5.3: Set up a horizontal jacking and beam-dropping system: When the front end of the front guide beam 7 is jacked to the tail end of the approach bridge, a manual operation platform 20 is set up on the top of the beam-dropping pier 12, and the walker that withdraws from the work at the tail end of the steel box beam is transferred to the top of the beam-dropping pier 12. The top section adjustment steel cylinder 1 of the beam-dropping pier 12, the manual operation platform 20 and the walker base plate are connected by bolts, and a stiffening plate 22 is welded between the top section adjustment steel cylinder 1 of the beam-dropping pier 12 and the stiffening rib 21 of the manual operation platform 20, and a platform fence 23 is set around the manual operation platform 20;
[0145] S5.4: Lifting the steel box girder at the rear support, specifically including the following steps:
[0146] S5.4.1: The steel box girder rear support walker is lifted and the initial elevation of the walker pier 19 is adjusted for the second time;
[0147] S5.4.2: The rear support crawler of the steel box girder is lifted up to make the top surface of the rear support crawler pier 19 empty;
[0148] S5.4.3: Place adjustment pad 2 on the walker pier 19 at the rear support of the steel box girder;
[0149] S5.4.4: The walker at the rear support of the steel box girder is lowered so that the rear support of the steel box girder is supported by the walker pier 19;
[0150] S5.4.5: Place an adjustment pad 2 on the walker slide box 18 at the rear support of the steel box girder;
[0151] S5.4.6: Repeat the above steps S5.4.2 to S5.4.5 to adjust the linear shape of the steel box girder until the top surfaces of the front and rear support points of the steel box girder are roughly flush, and replace the wedge-shaped pad 3 so that the slope of the top surface of the wedge-shaped pad 3 matches the slope of the bottom surface of the bottom plate of the steel box girder after the linear shape adjustment;
[0152] S5.5: Use the three-way jack of the crawler to fine-tune the position, alignment and elevation of the steel box girder, and alternately insert thin steel plates into the sliding box 18 and the pier 19 of the crawler at the rear support of the steel box girder to make the position and alignment of the steel box girder basically consistent with the design state;
[0153] S5.6: The crawler is lifted and the initial elevation of crawler pier 19 is adjusted for the third time. The steel box girder is pushed horizontally to the top of the designed bridge position in the horizontal direction.
[0154] S5.7: Remove the front guide beam 7 and the rear guide beam 8 of the steel box beam;
[0155] S5.8: Use the three-way jack of the walking machine to fine-tune the position, alignment and elevation of the steel box girder;
[0156] S5.9: The jacking of the steel box girder is completed and the beam dropping process begins.
[0157] In this embodiment, in step S5.1, before the steel box beam is pushed in parallel, the initial elevation of the walker pier 19 is adjusted for the first time to meet the following requirements: when the walker slide box 18 is in the lowering state, the inclined plane where the top surface of the wedge-shaped pad 3 on the front and rear piers 19 of the walker is located is 20 mm to 50 mm higher than the inclined plane where the top surface of the wedge-shaped pad 3 on the slide box 18 is located;
[0158] In step S5.4.1, before the steel box beam is pushed in parallel, the initial elevation of the second adjustment of the walker pier 19 must meet the following requirements: when the rear fulcrum walker slide box 18 is in the descending state, the inclined plane where the top surface of the wedge-shaped pad 3 on the front and rear piers 19 of the rear fulcrum walker is located is higher than the inclined plane where the top surface of the wedge-shaped pad 3 on the slide box 18 is located (L d -H k ) / 2=2.5mm;
[0159] In step S5.6, before the horizontal jacking of the steel box girder, the initial elevation of the crawler pier 19 is adjusted for the third time, so that when the crawler slide box 18 is in the lowering state, the top surface of the crawler pier 19 is 20mm to 50mm higher than the top surface of the replacement pier 11.
[0160] In this embodiment, in step S7, the specific steps of high-level graded beam dropping and support system conversion are as follows:
[0161] S7.1: The walking machine is lifted up to make the top surface of the walking machine pier 19 empty, and the initial elevation of the walking machine pier 19 is adjusted for the fourth time;
[0162] S7.2: The crawler descends, supports the steel box girder on the replacement pier 11, and welds the top section adjustment steel cylinder 1 of the replacement pier 11 to the bottom plate of the steel box girder;
[0163] S7.3: Remove the connecting bolts of the adjusting steel cylinder 1 at the bottom section of the beam-dropping pier 12, use the fall chain 14 to hoist the walker and the beam-dropping pier 12 as a whole, remove the adjusting steel cylinder 1 at the bottom section of the beam-dropping pier 12, and then use the fall chain 14 to lower the walker and the beam-dropping pier 12 onto the pressure beam 10-5 of the temporary supporting pier 10, and place them firmly;
[0164] S7.4: Place n layers of adjustment pads 2 on the sliding box 18 and the pier 19 of the walker respectively;
[0165] S7.5: Remove the connecting bolts of the adjusting steel cylinder 1 at the bottom section of the replacement pier 11, and lift the crawler to make the bottom surface of the replacement pier 11 empty;
[0166] S7.6: Remove and replace the bottom section adjustment steel cylinder 1 of pier 11;
[0167] S7.7.1: The crawler is lowered so that the steel box girder is supported on crawler pier 19;
[0168] S7.7.2: Remove the top adjustment pad 2 on the top of the walking machine slide box 18;
[0169] S7.7.3: The walking machine is lifted up to lift up the steel box girder so that the top surface of the walking machine pier 19 is free;
[0170] S7.7.4: Remove the top adjustment pad 2 on top of the walker pier 19;
[0171] S7.8: Repeat the above steps S7.7.1 to S7.7.4 until all the adjusting pads 2 on the top of the walker slide box 18 and the pier 19 are removed, and the walker is lowered. At this time, the steel box beam is supported on the replacement pier 11 after the height is lowered;
[0172] S7.9: Repeat the above steps S7.3 to S7.8 until all the adjustment steel cylinders 1 of the beam-dropping pier 12 are completely removed, and the crawler is lowered to the pressure beam 10-5 of the temporary pier 10 by using the fall chain 14. The crawler is lowered. At this time, the steel box beam is supported on the replacement pier 11 after the height is lowered. The distance between the bottom surface of the steel box beam and the top surface of the permanent support is exactly the height H of one section of the adjustment steel cylinder 1. k ;
[0173] S7.10: Execute the above steps S7.4 to S7.5, remove all remaining adjustment steel cylinders 1 of the replacement pier 11, at this time, the steel box beam is supported on the adjustment pad 2 on the top of the walker slide box 18, and the position of the steel box beam is fine-tuned by using the three-way jack of the walker, so that the steel box beam is accurately positioned according to the design position of the permanent support, and the installation and adjustment of the permanent support are performed;
[0174] S7.11: Repeat the above steps S7.7.1 to S7.7.4 to allow the steel box girder to be smoothly lowered to the permanent support. The crawler is unloaded and the steel box girder is supported by the permanent support. The steel box girder support system conversion is completed. The temporary welding parts of the steel box girder are repaired and the beam is lowered.
[0175] In this embodiment, in step S7.1, before the steel box beam is lowered at a high position, the fourth adjustment of the initial elevation of the walker pier 19 must satisfy the following requirements: when the walker slide box 18 is in the lowering state, the top surface of the walker pier 19 is higher than the top surface of the walker slide box 18 (L d -H k ) / 2=2.5mm.
[0176] In this embodiment, in step S4, when setting the temporary buttress 10, the top surface elevation of the pressure beam 10-5 must be calculated in advance, and the calculation method is as follows:
[0177] Known conditions: The top elevation of the permanent support of the steel box girder is Z Z The height from the bottom of the walking machine base plate to the top of the slide box 18 is H b , the maximum lifting stroke of the crawler is L d , the height of the single-section steel cylinder 1 is H t =nL d , the height of a single adjusting pad 2 is H k =L d -5mm;
[0178] Constraints: When the steel box girder is supported on the replacement pier 11, the top surface of the replacement pier 11 should be more than 20 mm higher than the top surface of the walker pier 19; when the steel box girder is supported on the adjustment pad 2 on the top of the walker slide box 18, the top surface of the replacement pier 11 should be more than 20 mm lower than the top surface of the adjustment pad 2 on the top of the walker slide box 18;
[0179] Elevation range: Assume that the top elevation of the pressure beam 10-5 of temporary pier 10 is Z L , then the elevation difference between the top surface of the permanent support and the top surface of the pressure beam 10-5 is ΔH=(Z Z -Z L ) should meet the following conditions: b +(L d -H k ) / 2+20mm≤ΔH≤H b +nH k +L d -H t -20mm, in order to control the elevation of the top surface of the pressure beam 10-5, that is, Z Z -H b -nH k -L d +H t +20mm≤Z L ≤Z Z -H b -(L d -H k ) / 2-20mm.
[0180] In this embodiment, during the process of pushing and dropping the steel box girder, deformation and stress monitoring are performed on key stress-bearing parts of the steel box girder, the front guide beam 7 and the rear guide beam 8, the temporary piers 10, the approach bridge piers and the permanent supports of the approach bridge and related structures.
[0181] In this example, the height from the bottom surface of the walking machine base plate to the top surface of the slide box is H b=1037mm, the height of the crawler pier can be adjusted by screw thread. Under the condition that the maximum lifting stroke of the crawler is only 100mm, the steel box beam is lowered to the permanent support one by one through the large and small double cycle graded beam dropping method, and the total beam dropping height reaches 3.5m. Among them: the small cycle is to operate the vertical jack of the crawler, alternately remove the adjustment pads on the crawler slide box and the pier, and divide the steel box beam into 5 small cycles, each time dropping 95mm, a total of 475mm; the large cycle is to alternately remove the adjustment steel cylinder of the replacement pier and the beam dropping pier, each time dropping 500mm. After completing 5 small cycles, execute a large cycle, and execute 7 large cycles in total, so that the steel box beam is lowered by 3.5m in total.
[0182] The beam-dropping pier and replacement pier used in this embodiment are both placed on temporary supporting piers. By setting a crawler and a beam-dropping pier hanging system on the bottom plate of the steel box beam, and welding the replacement pier to the bottom plate of the steel box beam, and by alternately switching the supporting points between the beam-dropping pier and the replacement pier, large and small cycle graded beam-dropping is achieved. When the steel box beam is supported by the replacement pier, the crawler and the beam-dropping pier are hoisted as a whole by the hanging system, and then the adjusting steel cylinder of the bottom section of the beam-dropping pier is removed; when the steel box beam is supported by the crawler, the steel box beam lifts the replacement pier, thereby removing the adjusting steel cylinder of the bottom section of the replacement pier. Both the beam-dropping pier and the replacement pier are removed from bottom to top, which is convenient, labor-saving and safe.
[0183] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for pushing and dropping a steel box girder at a high position, characterized in that: The following steps are involved: S1: Construction preparation: setting up fences, road safety signs and traffic diversion equipment, setting up a pre-assembly site on the roadbed at the end of the approach bridge, setting up a steel box girder assembly frame, and processing and manufacturing assembled adjustment steel cylinders (1), adjustment pads (2) and wedge pads (3); S2: Prefabrication of steel box girders: Steel box girder units are processed and manufactured in a professional factory, transported in blocks to the bridge pre-assembly yard, and then assembled on the assembly cradle; S3: Construction of bridge deck ancillary facilities and counterweight: After the single steel box girder is assembled as a whole and passed the inspection, the anti-throwing net, guardrail and related bridge deck ancillary facilities are constructed and installed on the outer side of the steel box girder in the pre-assembly yard, concrete counterweight blocks (4) are stacked on the other side of the steel box girder, and limit plates (5) are welded on the steel box girder panels around the concrete counterweight blocks. A protective fence (6) is set around the steel box girder bridge deck, and an anti-fall baffle is installed at the bottom of the protective fence; S4: Setting up the jacking system: reinforcing the approach bridge support, manufacturing and installing the front guide beam (7) and the rear guide beam (8) of the steel box beam, measuring and locating each support point on the jacking route of the steel box beam, setting up a crawler foundation (9), erecting a temporary supporting pier (10) for jacking up the steel box beam, setting up a replacement pier (11) and a beam-dropping pier (12) on the temporary supporting pier, and placing a crawler on the crawler foundation (9); S5: Pushing construction and alignment adjustment: Use a crawler to push a single steel box girder to the top of the designed bridge position. During the pushing process, adjust the position, alignment and elevation of the steel box girder as the pushing progresses. S6: Setting up a beam drop hanging system: welding a hanging ear plate (13) on the bottom plate of the steel box beam above the beam drop pier (12), hanging a fall chain (14) on the hanging ear plate (13), and connecting the lower end of the fall chain (14) to the hanging ear plate (15) on the base of the crawler. Four fall chains (14) are set for a single crawler. S7: High-level step-by-step beam drop and support system conversion: On the replacement pier (11) and beam drop pier (12), a walking machine is used to step-by-step drop the steel box beam to the top of the permanent support, and the permanent support of the steel box beam is installed in place, completing the support system conversion of the steel box beam; S8: Dismantling various temporary structures: After the beam is lowered, the crawler, the adjusting steel cylinder (1) and the related temporary structures are dragged out of the plane of the steel box beam along the horizontal direction of the bridge using a horizontal fall chain, and then lifted to the designated location using a truck crane; S9: Carry out the construction of the next steel box girder; In step S7, the specific steps of high-level graded beam dropping and support system conversion are as follows: S7.1: The walking machine is lifted up to make the top surface of the walking machine pier (19) empty, and the initial elevation of the walking machine pier (19) is adjusted for the fourth time; S7.2: The crawler descends, supports the steel box girder on the replacement pier (11), and welds the top section adjustment steel cylinder (1) of the replacement pier (11) to the bottom plate of the steel box girder; S7.3: Remove the connecting bolts of the adjusting steel cylinder (1) at the bottom section of the beam-dropping pier (12), use the fall chain (14) to hoist the walker and the beam-dropping pier (12) as a whole, remove the adjusting steel cylinder (1) at the bottom section of the beam-dropping pier (12), and then use the fall chain (14) to lower the walker and the beam-dropping pier (12) onto the pressure beam (10-5) of the temporary supporting pier (10), and place them firmly; S7.4: Place on the sliding box (18) and the pier (19) of the walking machine respectively n Layer adjustment pad (2); S7.5: Remove the connecting bolts of the adjusting steel cylinder (1) at the bottom section of the replacement pier (11), and lift the crawler to make the bottom surface of the replacement pier (11) empty; S7.6: Remove the bottom adjustment steel cylinder (1) of the replacement pier (11); S7.7.1: The crawler is lowered so that the steel box girder is supported on the crawler pier (19); S7.7.2: Remove the top adjustment pad (2) from the top of the walker slide box (18); S7.7.3: The walking machine is lifted up to lift the steel box girder so that the top surface of the walking machine pier (19) is free; S7.7.4: Remove the top adjustment pad (2) from the top of the walker pier (19); S7.8: Repeat the above steps S7.7.1 to S7.7.4 until all the adjustment pads (2) on the top of the walker slide box (18) and the pier (19) are removed, and the walker is lowered. At this time, the steel box beam is supported on the replacement pier (11) after the height is lowered; S7.9: Repeat the above steps S7.3 to S7.8 until all the adjustment steel cylinders (1) of the beam-dropping pier (12) are completely removed, and the crawler is lowered to the pressure beam (10-5) of the temporary pier (10) by using the fall chain (14). The crawler is lowered, and the steel box beam is supported on the replacement pier (11) after the height is lowered. The distance between the bottom surface of the steel box beam and the top surface of the permanent support is exactly the height of one section of the adjustment steel cylinder (1). H k ; S7.10: Execute the above steps S7.4 to S7.5, remove all remaining adjustment steel cylinders (1) of the replacement pier (11), and at this time, the steel box beam is supported on the adjustment pad (2) on the top of the walker slide box (18), and the position of the steel box beam is fine-tuned by using the three-way jack of the walker, so that the steel box beam is accurately positioned according to the design position of the permanent support, and the installation and adjustment of the permanent support are performed; S7.11: Repeat the above steps S7.7.1 to S7.7.4 to make the steel box girder fall smoothly onto the permanent support, unload the crawler, and support the steel box girder on the permanent support, completing the conversion of the steel box girder support system, repairing the temporary welding parts of the steel box girder, and completing the beam drop; In step S1, the adjusting steel cylinder (1) comprises an upper connecting plate (1-1), a lower connecting plate (1-2), a cylinder body (1-3) and a steel cylinder stiffening plate (1-4), and the height of a single-section adjusting steel cylinder (1) is H t =500mm, the diameters of the upper connecting plate (1-1) and the lower connecting plate (1-2) are 1000mm to 1200mm, the outer diameter of the cylinder (1-3) is 800mm to 1000mm, and the upper connecting plate (1-1) and the lower connecting plate (1-2) are provided with bolt holes corresponding to each other; In step S1, the adjusting pad (2) comprises an upper plate (2-1), a lower plate (2-2) and a vertical rib (2-3), and the height of a single adjusting pad (2) is H k , the plane is a square with a side length of 300mm; In step S1, the wedge-shaped pad (3) has a square plane, a side length of 300 mm to 500 mm, a minimum thickness of 6 mm to 10 mm, a horizontal bottom surface, and a sloped top surface. The slope of the top surface of the wedge-shaped pad (3) is consistent with the slope of the bottom surface of the bottom plate of the steel box girder during the jacking process. The wedge-shaped pad (3) has multiple types, each of which matches the jacking slope. In step S1, the maximum lifting stroke of the walking machine is L d =100mm, the height of the single-section adjusting steel cylinder (1) is the maximum lifting stroke n times, that is H t = nL d , the height of the single adjusting pad (2) is 5 mm smaller than the maximum lifting stroke, that is, H k = L d -5mm=95mm; In step S4, the temporary pier (10) adopts a combined structure, including a temporary pile foundation (10-1) and a temporary cap (10-2), a steel pipe column (10-3) is arranged on the temporary cap (10-2), the steel pipe column (10-3) and the temporary cap (10-2) are fixed with anchor bolts, a connecting rod (10-4) is arranged between the steel pipe columns (10-3), a pressure beam (10-5) is arranged on the top of the steel pipe column (10-3), and a transverse bridge sliding beam (16) is arranged on the side of the pressure beam (10-5); In step S4, the replacement pier (11) and the beam-dropping pier (12) are both connected by a plurality of assembled adjustment steel cylinders (1), each section of the adjustment steel cylinder (1) is connected to the other adjustment steel cylinder (1) by high-strength bolts, a leveling steel plate (11-1) is provided at the bottom of the replacement pier (11), and a transverse connecting rod (17) is provided between adjacent replacement piers (11) and between adjacent beam-dropping piers (12); In step S5, the specific steps of the steel box girder top-pushing construction and line shape adjustment are as follows: S5.1: Construction preparation before jacking: a wedge-shaped pad (3) is set on the top of the walker slide box (18) and the top of the pier (19), the initial elevation of the walker pier (19) is adjusted for the first time, the walker is jacked up, the steel box girder is transferred from the assembly tire frame to the walker, and the assembly tire frame is removed; S5.2: Parallel jacking of steel box girder: Push the steel box girder in a direction parallel to the bridge deck. During the jacking process, use the three-way jack of the crawler to adjust the direction and plane position of the steel box girder. As the jacking progresses, transfer the crawler that has withdrawn from the work at the rear end of the steel box girder to the front crawler foundation (9) and place it firmly. S5.3: Setting a horizontal pushing and beam dropping system: When the front end of the front guide beam (7) is pushed to the rear end of the approach bridge, a manual operation platform (20) is set on the top of the beam dropping pier (12), and the walking machine that withdraws from the work at the rear end of the steel box beam is transferred to the top of the beam dropping pier (12). The top section adjustment steel cylinder (1) of the beam dropping pier (12), the manual operation platform (20) and the walking machine base plate are connected by bolts, and a stiffening plate (22) is welded between the top section adjustment steel cylinder (1) of the beam dropping pier (12) and the stiffening rib (21) of the manual operation platform (20), and a platform fence (23) is set around the manual operation platform (20); S5.4: Lifting the steel box girder at the rear support, specifically including the following steps: S5.4.1: The steel box girder rear support is lifted by the walking machine, and the initial elevation of the walking machine pier (19) is adjusted for the second time; S5.4.2: The rear support crawler of the steel box girder is lifted up to make the top surface of the rear support crawler pier (19) empty; S5.4.3: Place an adjustment pad (2) on the walker support (19) at the rear support of the steel box girder; S5.4.4: The walker at the rear support of the steel box girder is lowered so that the rear support of the steel box girder is supported by the walker pier (19); S5.4.5: Place an adjustment pad (2) on the walker slide box (18) at the rear support of the steel box girder; S5.4.6: Repeat the above steps S5.4.2 to S5.4.5 to adjust the linear shape of the steel box girder until the top surfaces of the front and rear support points of the steel box girder are roughly flush, and replace the wedge-shaped pad (3) so that the slope of the top surface of the wedge-shaped pad (3) matches the slope of the bottom surface of the bottom plate of the steel box girder after the linear shape adjustment; S5.5: Use the three-way jack of the crawler to fine-tune the position, alignment and elevation of the steel box girder, and alternately insert thin steel plates into the sliding box (18) and the pier (19) of the crawler at the rear support of the steel box girder, so that the position and alignment of the steel box girder are basically consistent with the design state; S5.6: The crawler is lifted and the initial elevation of the crawler pier (19) is adjusted for the third time. The steel box girder is pushed horizontally to the top of the designed bridge position in the horizontal direction. S5.7: Remove the front guide beam (7) and the rear guide beam (8) of the steel box beam; S5.8: Use the three-way jack of the walking machine to fine-tune the position, alignment and elevation of the steel box girder; S5.9: The top pushing of the steel box girder is completed and the beam dropping process begins; In step S5.1, before the steel box beam is pushed in parallel, the initial elevation of the walking machine pier (19) is adjusted for the first time to meet the following requirements: when the walking machine slide box (18) is in the lowering state, the inclined plane where the top surface of the wedge-shaped pads (3) on the front and rear piers (19) of the walking machine is located is 20 mm to 50 mm higher than the inclined plane where the top surface of the wedge-shaped pads (3) on the slide box (18) is located; In step S5.4.1, before the steel box beam is pushed in parallel, the second adjustment of the initial elevation of the walker pier (19) must meet the following requirements: when the rear fulcrum walker slide box (18) is in the lowering state, the inclined plane where the top surface of the wedge-shaped pads (3) on the front and rear piers (19) of the rear fulcrum walker is located is higher than the inclined plane where the top surface of the wedge-shaped pads (3) on the slide box (18) is located ( L d - H k ) / 2=2.5mm; In step S5.6, before the steel box girder is horizontally pushed, the initial elevation of the walker pier (19) is adjusted for the third time so that when the walker slide box (18) is in the lowered state, the top surface of the walker pier (19) is 20 mm to 50 mm higher than the top surface of the replacement pier (11); In step S7.1, before the steel box beam is lowered from the high position, the initial elevation of the walking machine pier (19) is adjusted for the fourth time to meet the following requirements: when the walking machine slide box (18) is in the lowering state, the top surface of the walking machine pier (19) is higher than the top surface of the walking machine slide box (18) by ( L d - H k ) / 2=2.5mm; In step S4, when setting the temporary pier (10), the top surface elevation of the pressure beam (10-5) must be calculated in advance, and the calculation method is as follows: Known conditions: The top elevation of the permanent support of the steel box girder is Z Z , the height from the bottom surface of the walking machine base plate to the top surface of the slide box (18) is H b , the maximum lifting stroke of the crawler is L d , the height of the single-section adjusting steel cylinder (1) is H t = nL d , the height of a single adjusting pad (2) is H k = L d -5mm; Constraint conditions: When the steel box girder is supported on the replacement pier (11), the top surface of the replacement pier (11) should be at least 20 mm higher than the top surface of the walker pier (19); when the steel box girder is supported on the adjustment pad (2) on the top of the walker slide box (18), the top surface of the replacement pier (11) should be at least 20 mm lower than the top surface of the adjustment pad (2) on the top of the walker slide box (18); Elevation range: Assume that the top elevation of the pressure beam (10-5) of the temporary pier (10) is Z L , then the elevation difference Δ between the top surface of the permanent support and the top surface of the pressure beam (10-5) H =( Z Z - Z L ) The conditions that should be met are: H b +( L d - H k ) / 2+20mm≤Δ H ≤ H b + nH k + L d - H t -20mm, in order to control the elevation of the top surface of the pressure beam (10-5), that is, Z Z - H b - nH k - L d + H t +20mm ≤ Z L ≤ Z Z - H b -( L d - H k ) / 2-20mm; During the process of pushing and dropping the steel box girder, deformation and stress monitoring is performed on key stress-bearing parts of the steel box girder, the front guide girder (7), the rear guide girder (8), the temporary piers (10), the approach bridge piers, the approach bridge permanent bearings and related structures; Among them, the longitudinal slopes of the approach bridges at both ends of the steel box girder are 3.8% and -3.8% respectively.