Method, device, equipment and storage medium for generating building combination scheme

By obtaining land use information and building type database data, the exhaustive algorithm is used to automatically generate building combination plans in the general building plan, which solves the problem of traditional manual calculation being difficult to exhaustively exhaust all plans, and improves the generation efficiency and accuracy.

CN114756922BActive Publication Date: 2024-10-18SHENZHEN XUMI YUNTU SPACE TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210219902.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-08
Publication Date
2024-10-18
Estimated Expiration
2042-03-08

AI Technical Summary

Technical Problem

In the traditional building master plan layout design, manual calculation is difficult to exhaust all possible building combinations, and it is easy to miss optimization solutions. The calculation complexity is high, resulting in increased error rates and low generation efficiency.

Method used

By obtaining the predetermined land use information and data in the building type library, an exhaustive algorithm is used to automatically generate a building combination plan, including selecting the selected building type from the building type library, executing the building type combination, and generating based on the number of floors and land use restrictions. Plans for different number combinations.

Benefits of technology

It realizes the automatic generation of building combination plans, exhaustively enumerates all possible plans, reduces calculation complexity, improves accuracy and generation efficiency, and saves time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114756922B_ABST
    Figure CN114756922B_ABST
Patent Text Reader

Abstract

The present disclosure provides a method, device, equipment and storage medium for generating a building combination scheme. The method comprises: obtaining land use information pre-set for a predetermined land use, wherein the land use information includes basic data corresponding to the predetermined land use and land use restriction conditions; selecting at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, performing an exhaustive operation based on the to-be-selected building type set to obtain a building type combination; performing an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type, to obtain a building combination; performing an exhaustive operation on the number corresponding to each building in the building combination based on the building combination, the basic data of the predetermined land use and the land use restriction conditions, to obtain a building combination scheme with different number combinations. The present disclosure reduces the complexity of exhaustive calculation, improves the accuracy of the building combination scheme, and reduces the labor time cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of building master plan generation, and in particular to a method, device, equipment and storage medium for generating a building combination plan. Background Art

[0002] The general building plan (general plan for short) indicates the overall layout of the building site, specifically expressing the location and orientation of the new house and the basic situation of the surrounding environment (such as the original buildings, traffic roads, greenery, terrain, etc.), including important information such as volume ratio, building density, building spacing, sunshine, etc., and is one of the most important design contents in the building. As the basic content of the construction project, the general building plan contains the deep-level development logic. The quality of the general plan design has a very important impact on the cost, planning layout and future use effect of the construction project.

[0003] In the process of generating the general plan of the building, it is necessary to carry out the general plan layout design according to the existing building types. In the traditional general plan layout design process, architects need to calculate the layout combination of buildings based on manual experience and with the help of data processing tools such as Excel. However, this layout method through manual calculation cannot exhaust all possible layout combination schemes, resulting in a reduction in the number of layout combination schemes and the easy omission of better layout combination schemes; in addition, due to the large amount of calculated data and the high complexity of manual calculation, the error rate is increased, and the calculation is time-consuming, which reduces the efficiency of generating layout combination schemes. Summary of the invention

[0004] In view of this, the embodiments of the present disclosure provide a method, device, equipment and storage medium for generating a building combination scheme, so as to solve the problems existing in the prior art that it is impossible to enumerate all possible arrangement combination schemes, omissions are prone to occur, the large amount of calculated data leads to an increased error rate, and the efficiency of generating arrangement combination schemes is reduced.

[0005] A first aspect of an embodiment of the present disclosure provides a method for generating a building combination scheme, comprising: obtaining land use information pre-set for a predetermined land use, wherein the land use information includes basic data corresponding to the predetermined land use and land use restriction conditions; selecting at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, performing an exhaustive operation based on the to-be-selected building type set to obtain a building type combination; performing an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type to obtain a building combination; performing an exhaustive operation on the number of floors corresponding to each building type in the building type combination based on the building combination, the basic data of the predetermined land use and the land use restriction conditions to obtain a building combination scheme with different number combinations.

[0006] According to a second aspect of an embodiment of the present disclosure, there is provided a device for generating a building combination scheme, comprising: an acquisition module, configured to acquire land use information pre-set for a predetermined land use, wherein the land use information includes basic data corresponding to the predetermined land use and land use restriction conditions; a first exhaustive module, configured to select at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, and perform an exhaustive operation based on the to-be-selected building type set to obtain a building type combination; a second exhaustive module, configured to perform an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type, to obtain a building combination; a third exhaustive module, configured to perform an exhaustive operation on the number of floors corresponding to each building in the building combination based on the building combination, the basic data of the predetermined land use and the land use restriction conditions, to obtain a building combination scheme with different number combinations.

[0007] According to a third aspect of an embodiment of the present disclosure, an electronic device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the steps of the above method are implemented when the processor executes the program.

[0008] According to a fourth aspect of the embodiments of the present disclosure, a computer-readable storage medium is provided, which stores a computer program, and when the computer program is executed by a processor, the steps of the above method are implemented.

[0009] At least one of the above technical solutions adopted in the embodiments of the present disclosure can achieve the following beneficial effects:

[0010] By obtaining the land use information pre-set for the scheduled land use, wherein the land use information includes the basic data corresponding to the scheduled land use and the land use restriction conditions; selecting at least one type of building to be selected from the pre-configured building type library to form a set of building types to be selected, performing an exhaustive operation based on the set of building types to be selected, and obtaining a building type combination; performing an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type, and obtaining a building combination; performing an exhaustive operation on the number corresponding to each building in the building combination based on the building combination, the basic data of the scheduled land use, and the land use restriction conditions, and obtaining a building combination scheme with different number combinations. The present invention does not rely on manual calculation operations, has a high degree of automation, can exhaustively enumerate all possible building combination schemes, and reduces the calculation complexity, improves the accuracy of the building combination scheme, saves time, and improves the generation efficiency of the arrangement combination scheme. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0012] Figure 1 It is a flowchart of a method for generating a building combination scheme provided by an embodiment of the present disclosure;

[0013] Figure 2 It is a schematic diagram of generating a building combination scheme in a specific application scenario provided by an embodiment of the present disclosure;

[0014] Figure 3 It is a structural schematic diagram of a device for generating a building combination scheme provided by an embodiment of the present disclosure;

[0015] Figure 4 It is a schematic diagram of the structure of an electronic device provided by an embodiment of the present disclosure. DETAILED DESCRIPTION

[0016] In the following description, specific details such as specific system structures and technologies are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present disclosure. However, it should be clear to those skilled in the art that the present disclosure may be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to avoid obstructing the description of the present disclosure with unnecessary details.

[0017] The general building plan, also known as the general building plan, hereinafter referred to as the general plan, mainly indicates the layout of the building on the site and the functional zoning relationship of traffic, fire flow organization, parking spaces, squares, etc. It can also show the number of floors, volume ratio, building density, greening rate and other economic indicators of the building. Based on the general plan, it is convenient for project personnel to fully understand the building land, clarify the location, orientation, base area (that is, the sum of the ground floor areas of all buildings) of the building, and the building's setback red line and other restrictions. The general plan contains a deep development logic, which is of great significance to the maximization of construction project resources, construction cost control, land planning and layout, etc. Therefore, the generated general plan will greatly affect the actual use effect of the construction project.

[0018] In the process of generating the general plan of the building, it is necessary to design the general plan layout according to the existing building types. In the traditional general plan layout process, architects need to calculate the layout combination of buildings based on manual experience and with the help of data processing tools such as Excel. For example, after receiving the planning and design task, when designing the general plan layout plan, architects usually need to take the following two steps:

[0019] Step 1: Preliminary calculation of buildings, that is, preliminary calculation of what type of buildings can be placed in the base and how many of each type of buildings can be placed, so as to meet the planning requirements and achieve the best benefits;

[0020] The first step: building arrangement, that is, the number of buildings determined in the first step are arranged in sequence in the base. The goal is to place all the buildings while meeting the planning indicators.

[0021] However, this method of manually calculating the arrangement combination will result in a reduction in the number of calculation solutions, and it is easy to miss the best arrangement solution, and it is very easy to cause the solution to be not an ideal solution, and it is impossible to achieve the maximum value of goods or other restricted goals. In addition, manual exhaustive enumeration takes a lot of time, is highly dependent on people, and the work is tedious and inefficient. The quality of the results depends on the carefulness of the people.

[0022] Therefore, the traditional process of generating building combination plans has the following shortcomings: it is impossible to enumerate all layout combination plans. Due to the complex steps and many possibilities, the existing layout combination methods cannot obtain the optimal solution. Due to the high calculation complexity, manual calculation is bound to increase the error rate. The calculation takes a long time. Even for experienced architects, it takes several hours to calculate a layout combination plan.

[0023] In view of the above problems in the prior art, it is necessary to provide a system that can automatically generate building combination schemes without relying on manual calculation operations, avoid missing the best building combination scheme, obtain the optimal solution of the building combination scheme, reduce the calculation complexity, thereby improving the accuracy of the building combination scheme, and save time, compressing several hours of workload to milliseconds, and improving the generation efficiency of layout combination schemes.

[0024] Figure 1 It is a flowchart of a method for generating a building combination scheme provided in an embodiment of the present disclosure. Figure 1 The method for generating the building combination scheme can be executed by the server. Figure 1 As shown, the method for generating the building combination scheme may specifically include:

[0025] S101, obtaining land use information pre-set for a scheduled land use, wherein the land use information includes basic data corresponding to the scheduled land use and land use restriction conditions;

[0026] S102, selecting at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, and performing an exhaustive operation based on the to-be-selected building type set to obtain a building type combination;

[0027] S103, according to the building type combination and the building type data corresponding to the building type, perform an exhaustive operation on the number of floors corresponding to each building type in the building type combination to obtain a building combination;

[0028] S104. Based on the building combination, basic data of the scheduled land use, and land use restriction conditions, an exhaustive operation is performed on the number of buildings corresponding to each building in the building combination to obtain building combination schemes with different number combinations.

[0029] Specifically, the predetermined land in the embodiment of the present disclosure corresponds to the planned land in the actual scenario. The planned land can be considered as the site or base corresponding to the actual construction project. The construction site has certain boundaries and planning and is the project land approved by the government. Land information (i.e., land planning information) is related to the plot planning determined based on government planning and plot information, such as the location information of the plot, construction land area, construction land area, floor area ratio, building density and plot apartment ratio, etc. It should be emphasized that the land planning information corresponding to different sites is not the same, so the planning restrictions of different sites may also be different.

[0030] Furthermore, an apartment type refers to a set of basic living spaces including bedrooms and living rooms, such as an apartment type with three bedrooms and one living room; a building type in the disclosed embodiment refers to a residence, including a combination of several apartment types, such as a building type with one elevator and three units; a building type library includes a digital warehouse of several building types, including detailed information and drawings of each building type; a building in the disclosed embodiment refers to a residential building, a building with a certain number of floors, height, and building type; the floor area ratio refers to the total gross floor area of ​​a community divided by the land area, which is used to describe the land utilization rate; the building density refers to the sum of the floor areas of all buildings in the community divided by the land area; the apartment type ratio refers to the ratio of the sum of the numbers of each apartment type in the community; residential area planning refers to a comprehensive and specific arrangement of the layout structure of the residential area, the layout of residential groups, road traffic, life service facilities, various green spaces and recreational venues, municipal public facilities, and various systems of the municipal pipeline network.

[0031] Furthermore, in the disclosed embodiment, forced row design refers to a preliminary calculation of the number and building types of residential buildings before residential area planning, with the goal of preliminarily obtaining a combination of the number, building type, and number of floors that meets planning conditions such as floor area ratio and building density, from which the optimal solution is screened out to guide the next step of residential area planning.

[0032] Furthermore, the disclosed embodiment automatically generates building combination schemes by adopting an exhaustive algorithm. The exhaustive algorithm can be considered to be exhaustive according to a certain exhaustive logic, using preset exhaustive parameters, and exhaustively enumerating all situations within the possible range of the exhaustive parameters to obtain a set composed of different exhaustive results. For example: taking the arrangement direction of the buildings as the exhaustive parameter, then arranging from south to north, from north to south, from east to west, from west to east, etc. respectively correspond to different situations under the exhaustive parameter, and combining the situation corresponding to the exhaustive parameter with the situations of other exhaustive parameters, N different exhaustive results are generated.

[0033] According to the technical solution provided by the embodiment of the present disclosure, by obtaining the land planning information pre-set for the planned land, wherein the land planning information contains the basic data corresponding to the planned land and the planning restriction conditions; selecting at least one to-be-selected building type from the pre-configured building type library to form a to-be-selected building type set, performing an exhaustive operation based on the to-be-selected building type set to obtain a building type combination; performing an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type, to obtain a building combination; performing an exhaustive operation on the number corresponding to each building in the building combination based on the building combination, the basic data of the planned land and the planning restriction conditions, to obtain a building combination scheme with different number combinations. The present disclosure does not rely on manual calculation operations, has a high degree of automation, can exhaustively enumerate all possible building combination schemes, and reduces the calculation complexity, improves the accuracy of the building combination scheme, saves time, and improves the generation efficiency of the arrangement combination scheme.

[0034] In some embodiments, obtaining land use information pre-set for a predetermined land use includes: setting corresponding land use information for the predetermined land use according to land use drawing data corresponding to the predetermined land use, wherein the basic data of the predetermined land use includes the construction land area corresponding to the predetermined land use, and the land use restriction conditions include the floor area ratio, building density and apartment type ratio corresponding to the predetermined land use.

[0035] Specifically, the land use drawing data refers to the CAD drawing of the planned land, which may include a series of polygons, such as the shape of the ground, the shape of surrounding buildings, rivers, substations, high-voltage lines, obstacles, and other geometric figures. The land use drawing can be considered as a complete drawing, and the construction land area in the land use drawing data is used as one of the constraints for the subsequent exhaustive enumeration of building combination plans.

[0036] In some embodiments, at least one to-be-selected building type is selected from a preconfigured building type library to form a to-be-selected building type set, and an exhaustive operation is performed based on the to-be-selected building type set to obtain a building type combination, including: selecting at least one to-be-selected building type from the building type library according to the land use information, combining the to-be-selected building types to obtain a to-be-selected building type set, and exhaustively enumerating all the to-be-selected building types in the to-be-selected building type set in turn to obtain a number of building type combinations.

[0037] Specifically, the generation of the building combination scheme of the embodiment of the present disclosure can be realized based on the secondary development software in the CAD software. First, at least one building type to be selected is selected in the building type library, which stores a large number of pre-designed building types to be selected. In addition to the graphic information of the building type to be selected, the building type library also stores the basic attribute data of the building type to be selected, such as the floor, floor height, number of units, number of elevators, etc.

[0038] Furthermore, some building types to be selected are selected from the building type library as objects for subsequent processing according to the land use planning information. For example, if the land use planning information indicates that the land parcel is for residential use, then the building types corresponding to the residence should be selected from the building type library. For example, building type A, building type B, and building type C are selected in sequence as the building types to be selected, and building type A, building type B, and building type C are placed in the same building type set to be selected. When exhaustively enumerating based on the building type set to be selected, several building type combinations are obtained by combining the building types in the building type set to be selected. For example, exhaustively enumerating the building type combinations of the above building type set to be selected can obtain the following building type combinations: A, B, C, AB, AC, BC, ABC.

[0039] In some embodiments, based on the building type combinations and the building type data corresponding to the building types, an exhaustive operation is performed on the number of floors corresponding to each building type in the building type combination to obtain a building combination, including: for each building type combination, obtaining the building type data corresponding to each building type in the building type combination, determining the floor number interval corresponding to the building type based on the building type data, and based on the floor number interval of the building type, exhaustively enumerating each building type in the building type combination within the floor number interval to obtain multiple building combinations corresponding to each building type combination.

[0040] Specifically, when implementing the exhaustive enumeration of building combination schemes based on the secondary development software in the CAD software, the "Building Preliminary Calculation" command is called in CAD to select the building type product selected in the drawing; and the set land planning information is read from the background, and the land planning information is used as the calculation condition. The building preliminary calculation exhaustive algorithm is called to exhaustively enumerate all possible building combination schemes.

[0041] Furthermore, a building type combination may contain one or more building types, and the building type data corresponding to each building type needs to be obtained in order to determine the floor number range corresponding to the building type, that is, the number of floors allowed to be built for the building type. The following is a detailed description of the exhaustive process of building combination solutions in conjunction with the accompanying drawings and specific embodiments. Figure 2 FIG. 1 is a schematic diagram of generating a building combination scheme in a specific application scenario provided by an embodiment of the present disclosure. Figure 2 As shown, the method for generating the building combination scheme may specifically include:

[0042] Assuming the AB building type combination as an example, the building type data corresponding to building type A and building type B are obtained respectively, and the floor number intervals corresponding to building type A and building type B are determined respectively according to the building type data of building type A and building type B, and the possible floor number combinations of each building type are exhaustively enumerated, that is, all building combinations are exhaustively enumerated. For example: the following building combinations are obtained by exhaustively enumerating the number of floors of the AB building type combination: 8F A+8FB, 9F A+8F B, 10F A+9F B..., where 8F A represents a building of building type A with 8 floors.

[0043] In some embodiments, based on the building combination, basic data of the scheduled land use, and land use restrictions, an exhaustive operation is performed on the number corresponding to each building in the building combination, including: for each building combination, obtaining the building area corresponding to each building type in the building combination, using the building area, construction land area, floor area ratio, building density, and apartment type ratio as constraints when enumerating the number of each building in the building combination, and based on the constraints, enumerating the number of each building in the building combination to obtain a plurality of building combination schemes corresponding to each building combination; wherein the building combination scheme includes the building combination and the number of buildings corresponding to each building combination.

[0044] Specifically, after exhaustively enumerating the number of floors of each building type combination, we further enumerate the combinations of the number of buildings in each building combination. When enumerating the combinations of the number of buildings, the following information needs to be considered: construction land area, building type area, floor area ratio, building density and apartment type ratio, etc. The construction land area and building type area determine the maximum number of buildings that can be arranged in the construction land, while the floor area ratio, building density and apartment type ratio further constrain the possible combination schemes.

[0045] Furthermore, by using the above information as a constraint condition for enumeration, in the process of enumerating the number of buildings, the volume ratio, building density, and apartment ratio of the building combination scheme obtained by the enumeration are calculated in real time, and unreasonable combination schemes are filtered out in time, and only the building combination schemes that meet the above constraint conditions are retained. For example, continuing with the above embodiment, taking the building combination of 10F A+9F B as an example, the number of buildings in the building combination is enumerated, that is, the number corresponding to 10FA and 9F B is enumerated, and the following enumeration results can be obtained: 1 10FA+1 9FB, 1 10FA+2 9FB, 1 10FA+3 9FB...

[0046] In some embodiments, after obtaining building combination schemes with different numbers of combinations, the method further includes: determining attribute data corresponding to the building combination schemes, screening the building combination schemes according to the attribute data, and obtaining target combination schemes that meet the screening conditions.

[0047] Specifically, since each scheme obtained by exhaustive enumeration has its own data attributes, such as building density, volume ratio, apartment type ratio, etc., after exhaustively enumerating all building combination schemes, the attribute data corresponding to each building combination scheme is calculated respectively, so as to sort and screen the building combination schemes according to the attribute data, and obtain the final combination scheme that meets the user's needs. The process of using attribute data to screen building combination schemes is described in detail below in conjunction with a specific embodiment, which may specifically include the following contents:

[0048] After calculating the attribute data of each building combination scheme, the following two methods can be used for screening. The first is to sort the data attributes of all building combination schemes, for example, sorting by building density or floor area ratio, etc.; setting the value range of the data attribute, such as "building density ≥ 0.2", "floor area ratio ≤ 3.0"; the second is to set screening conditions to screen the building combination schemes according to the conditions, and then obtain the final screening combination scheme (i.e., the target combination scheme), such as setting the screening conditions to "building density ≥ 0.2" and "floor area ratio ≤ 3.0" and "top ten in terms of returns".

[0049] In some embodiments, determining the attribute data corresponding to the building combination scheme includes: obtaining the building type, building area, and number of buildings corresponding to each building in the building combination scheme, and determining the attribute data corresponding to the building combination scheme based on the building type, building area, number of buildings, and the construction land area corresponding to the reserved land; wherein the attribute data includes the floor area ratio, building density and apartment ratio corresponding to the building combination scheme.

[0050] Specifically, when calculating the attribute data of the building combination scheme, the building type, building type area, and number of buildings corresponding to each building in the building combination scheme can be obtained first, and the above data can be used to calculate the floor area ratio, building density, and apartment ratio corresponding to each building combination scheme. For example, when calculating the attribute data corresponding to the floor area ratio, the product of the building type area and the number of buildings can be used as the total floor area of ​​the community, and the total floor area of ​​the community can be divided by the construction land area to obtain the floor area ratio corresponding to the building combination scheme. The specific calculation process is not repeated here.

[0051] Furthermore, in addition to using attribute data to screen building combination plans, in actual applications, the final target combination plan can also be checked for compliance. Compliance verification refers to the verification of the master plan obtained after point sorting and building filling based on the evaluation model according to preset restriction rules and information, so as to determine which master plan plans are compliant and which are not compliant, and discard the non-compliant master plan plans, and only retain the compliant master plan plans. In actual applications, compliance verification includes verification of building sunlight and spacing.

[0052] According to the technical solution provided by the embodiment of the present disclosure, the building type combinations, building combinations and building combination schemes are continuously enumerated according to the basic data of the plot and the land use restriction conditions, and the number of buildings is automatically calculated according to the density, volume ratio, apartment type ratio, etc. during the enumeration process, thereby automatically generating all building combination schemes that meet the constraints. The embodiment of the present disclosure is not dependent on manual calculation operations for the "initial calculation of buildings" in the forced row design process, and can enumerate all possible building combination schemes, reduce the calculation complexity, and improve the accuracy of the building combination scheme. Based on this scheme, the best combination of the number of buildings can be obtained quickly and accurately. The present disclosure implements functional integration on the CAD side, which can avoid non-linked operations of data and models.

[0053] The following are embodiments of the device disclosed herein, which can be used to execute the method embodiments disclosed herein. For details not disclosed in the device embodiments disclosed herein, please refer to the method embodiments disclosed herein.

[0054] Figure 3 Schematic diagram of the structure of the device for generating the building combination scheme provided by the embodiment of the present disclosure. Figure 3 As shown, the generating device of the building combination scheme includes:

[0055] The acquisition module 301 is configured to acquire land use planning information pre-set for the scheduled land use, wherein the land use information includes basic data corresponding to the scheduled land use and land use restriction conditions;

[0056] The first exhaustive module 302 is configured to select at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, and perform an exhaustive operation based on the to-be-selected building type set to obtain a building type combination;

[0057] The second exhaustive module 303 is configured to perform an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type, so as to obtain a building combination;

[0058] The third exhaustive module 304 is configured to perform an exhaustive operation on the number of each building in the building combination based on the building combination, basic data of the scheduled land use, and land use restriction conditions, to obtain building combination solutions with different number combinations.

[0059] In some embodiments, Figure 3 The acquisition module 301 sets corresponding land use information for the scheduled land according to the land use drawing data corresponding to the scheduled land, wherein the basic data of the scheduled land includes the construction land area corresponding to the scheduled land, and the land use restriction conditions include the plot ratio, building density and apartment ratio corresponding to the scheduled land.

[0060] In some embodiments, Figure 3The first exhaustive module 302 selects at least one candidate building type from the building type library according to the land use information, combines the candidate building types to obtain a candidate building type set, and exhaustively enumerates all the candidate building types in the candidate building type set in turn to obtain a plurality of building type combinations.

[0061] In some embodiments, Figure 3 The second exhaustive module 303 obtains the building type data corresponding to each building type in the building type combination for each building type combination, determines the floor number interval corresponding to the building type based on the building type data, and exhaustively enumerates each building type in the building type combination within the floor number interval according to the floor number interval of the building type to obtain multiple building combinations corresponding to each building type combination.

[0062] In some embodiments, Figure 3 The third exhaustive module 304 obtains the building area corresponding to each building type in the building combination for each building combination, and uses the building area, construction land area, volume ratio, building density and apartment ratio as constraints for enumerating the number of each building in the building combination. Based on the constraints, the number of each building in the building combination is enumerated to obtain multiple building combination schemes corresponding to each building combination; wherein the building combination scheme includes the building combination and the number of buildings corresponding to each building combination.

[0063] In some embodiments, Figure 3 After obtaining the building combination schemes with different numbers of combinations, the screening module 305 determines the attribute data corresponding to the building combination schemes, and screens the building combination schemes according to the attribute data to obtain a target combination scheme that meets the screening conditions.

[0064] In some embodiments, Figure 3 The screening module 305 obtains the building type, building area, and number of buildings corresponding to each building in the building combination plan, and determines the attribute data corresponding to the building combination plan based on the building type, building area, number of buildings, and the construction land area corresponding to the reserved land; wherein the attribute data includes the floor area ratio, building density and apartment ratio corresponding to the building combination plan.

[0065] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present disclosure.

[0066] Figure 4 Schematic diagram of the structure of the electronic device 4 provided by the embodiment of the present disclosure. Figure 4As shown, the electronic device 4 of this embodiment includes: a processor 401, a memory 402, and a computer program 403 stored in the memory 402 and executable on the processor 401. When the processor 401 executes the computer program 403, the steps in the above-mentioned method embodiments are implemented. Alternatively, when the processor 401 executes the computer program 403, the functions of the modules / units in the above-mentioned device embodiments are implemented.

[0067] Exemplarily, the computer program 403 may be divided into one or more modules / units, which are stored in the memory 402 and executed by the processor 401 to complete the present disclosure. The one or more modules / units may be a series of computer program instruction segments capable of completing specific functions, which are used to describe the execution process of the computer program 403 in the electronic device 4.

[0068] The electronic device 4 may be a desktop computer, a notebook, a PDA, a cloud server, or other electronic device. The electronic device 4 may include, but is not limited to, a processor 401 and a memory 402. Those skilled in the art will appreciate that Figure 4 It is only an example of the electronic device 4 and does not constitute a limitation of the electronic device 4. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the electronic device may also include input and output devices, network access devices, buses, etc.

[0069] The processor 401 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may be any conventional processor, etc.

[0070] The memory 402 may be an internal storage unit of the electronic device 4, for example, a hard disk or memory of the electronic device 4. The memory 402 may also be an external storage device of the electronic device 4, for example, a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the electronic device 4. Further, the memory 402 may also include both an internal storage unit and an external storage device of the electronic device 4. The memory 402 is used to store computer programs and other programs and data required by the electronic device. The memory 402 may also be used to temporarily store data that has been output or is to be output.

[0071] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0072] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0073] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this disclosure.

[0074] In the embodiments provided in the present disclosure, it should be understood that the disclosed apparatus / computer equipment and methods can be implemented in other ways. For example, the apparatus / computer equipment embodiments described above are merely schematic. For example, the division of modules or units is only a logical function division. There may be other division methods in actual implementation. Multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed may be through some interfaces, indirect coupling or communication connection of the apparatus or unit, which may be electrical, mechanical or other forms.

[0075] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0076] In addition, each functional unit in each embodiment of the present disclosure may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0077] If the integrated module / unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present disclosure implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. The computer program may include computer program code, and the computer program code may be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include: any entity or device capable of carrying computer program code, recording medium, U disk, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM), random access memory (RAM), electric carrier signal, telecommunication signal and software distribution medium. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, the computer-readable medium does not include electric carrier signals and telecommunication signals.

[0078] The above embodiments are only used to illustrate the technical solutions of the present disclosure, rather than to limit them. Although the present disclosure has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present disclosure, and should all be included in the protection scope of the present disclosure.

Claims

1. A method for generating a building combination scheme, It is characterized in that include: Acquire land use information pre-set for a predetermined land use, wherein the land use information includes basic data corresponding to the predetermined land use and land use restriction conditions; Selecting at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, and performing an exhaustive operation based on the to-be-selected building type set to obtain a building type combination; According to the building type combination and the building type data corresponding to the building type, an exhaustive operation is performed on the number of floors corresponding to each building type in the building type combination to obtain a building combination; Based on the building combination, the basic data of the scheduled land use, and the land use restriction conditions, an exhaustive operation is performed on the number corresponding to each building in the building combination to obtain building combination schemes with different number combinations; The obtaining of land use information pre-set for the scheduled land use includes: According to the land use drawing data corresponding to the predetermined land use, corresponding land use information is set for the predetermined land use, wherein the basic data of the predetermined land use includes the construction land area corresponding to the predetermined land use, and the land use restriction conditions include the plot ratio, building density and apartment ratio corresponding to the predetermined land use; According to the building type combination and the building type data corresponding to the building type, an exhaustive operation is performed on the number of floors corresponding to each building type in the building type combination to obtain a building combination, including: For each of the building type combinations, obtain building type data corresponding to each building type in the building type combination, determine the floor number interval corresponding to the building type based on the building type data, and according to the floor number interval of the building type, exhaustively enumerate each of the building types in the building type combination within the floor number interval to obtain multiple building combinations corresponding to each of the building type combinations; The performing an exhaustive operation on the number corresponding to each building in the building combination based on the building combination, the basic data of the scheduled land use, and the land use restriction condition comprises: For each of the building combinations, the building area corresponding to each building type in the building combination is obtained, and the building area, the construction land area, the volume ratio, the building density and the apartment ratio are used as constraints when enumerating the number of each of the buildings in the building combination. Based on the constraints, the number of each of the buildings in the building combination is enumerated to obtain a plurality of building combination schemes corresponding to each of the building combinations; wherein the building combination scheme includes the building combination and the number of buildings corresponding to each of the building combinations; After obtaining the building combination schemes with different numbers of combinations, the method further includes: Determine the attribute data corresponding to the building combination scheme, filter the building combination scheme according to the attribute data, and obtain a target combination scheme that meets the filtering conditions.

2. The method according to claim 1, It is characterized in that The selecting at least one to-be-selected building type from the pre-configured building type library to form a to-be-selected building type set, and performing an exhaustive operation based on the to-be-selected building type set to obtain a building type combination, includes: At least one candidate building type is selected from the building type library according to the land use information, the candidate building types are combined to obtain the candidate building type set, and all the candidate building types in the candidate building type set are sequentially enumerated to obtain a plurality of the building type combinations.

3. The method according to claim 1, It is characterized in that The determining of the attribute data corresponding to the building combination scheme includes: Obtaining the building type, building type area, and number of the buildings corresponding to each of the buildings in the building combination scheme, and determining the attribute data corresponding to the building combination scheme based on the building type, the building type area, the number of the buildings, and the construction land area corresponding to the scheduled land; Among them, the attribute data includes the floor area ratio, building density and apartment ratio corresponding to the building combination plan.

4. A device for generating a building combination plan, It is characterized in that include: An acquisition module is configured to acquire land use information pre-set for a predetermined land use, wherein the land use information includes basic data corresponding to the predetermined land use and land use restriction conditions; A first exhaustive module is configured to select at least one to-be-selected building type from a pre-configured building type library to form a to-be-selected building type set, and perform an exhaustive operation based on the to-be-selected building type set to obtain a building type combination; A second exhaustive module is configured to perform an exhaustive operation on the number of floors corresponding to each building type in the building type combination according to the building type combination and the building type data corresponding to the building type, so as to obtain a building combination; A third exhaustive module is configured to perform an exhaustive operation on the number of each building in the building combination based on the building combination, the basic data of the scheduled land use, and the land use restriction condition, to obtain building combination schemes with different number combinations; The acquisition module is used to set corresponding land use information for the predetermined land according to the land use drawing data corresponding to the predetermined land, wherein the basic data of the predetermined land includes the construction land area corresponding to the predetermined land, and the land use restriction conditions include the plot ratio, building density and apartment ratio corresponding to the predetermined land; The second enumeration module is used for obtaining, for each of the building type combinations, the building type data corresponding to each building type in the building type combination, determining the number of floors interval corresponding to the building type based on the building type data, and enumerating each of the building types in the building type combination within the number of floors interval according to the number of floors interval of the building type, to obtain multiple building combinations corresponding to each of the building type combinations; The third enumeration module is used for obtaining the building area corresponding to each building type in the building combination for each building combination, taking the building area, the construction land area, the volume ratio, the building density and the apartment ratio as constraints for enumerating the number of each building in the building combination, and enumerating the number of each building in the building combination based on the constraints to obtain a plurality of building combination schemes corresponding to each building combination; wherein the building combination scheme includes the building combination and the number of buildings corresponding to each building combination; The screening module is configured to determine the attribute data corresponding to the building combination scheme after obtaining the building combination scheme with different numbers of combinations, and screen the building combination scheme according to the attribute data to obtain a target combination scheme that meets the screening conditions.

5. An electronic device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the method according to any one of claims 1 to 3 when executing the program.

6. A computer-readable storage medium storing a computer program, It is characterized in that When the computer program is executed by a processor, the method according to any one of claims 1 to 3 is implemented.

Citation Information

Patent Citations

  • Method and device for estimating building function house type ratio

    CN111415035A

  • Building lighting simulation method based on smart phone

    CN112164142A