Method for circulating and pressurizing freezable groundwater for drainage and consolidation of foundation treatment
By freezing the discharged groundwater and using it as foundation ballast, the problem of waste of groundwater resources and environmental damage in foundation treatment is solved, the recycling of groundwater is realized, the construction process is simplified, the cost is reduced and the ecological environment is protected.
Patent Information
- Application Number
- CN202210679621.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-16
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-06-16
AI Technical Summary
In the existing foundation treatment technology, the discharged groundwater cannot be effectively used, resulting in waste of resources and environmental damage, high construction costs and long construction period.
The freezeable groundwater circulation pressure supply and utilization method is adopted, by collecting the groundwater during drainage and consolidation foundation treatment and freezing it as ballast on the foundation. After completion, it is recharged as recharge water to realize the recycling of groundwater.
Effectively utilize groundwater to provide consolidation pressure, reduce resource waste, protect the ecological environment, achieve green construction, energy conservation and emission reduction, simplify structural design, and reduce construction costs.
Smart Images

Figure CN114808919B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of foundation treatment, and in particular to a method for circulating and pressurizing freezable groundwater for drainage and consolidation foundation treatment, which can freeze and recycle groundwater discharged during drainage and consolidation foundation treatment to provide consolidation pressure for foundation treatment. Background Art
[0002] The speed of national infrastructure construction has increased by leaps and bounds. Foundation treatment is a construction link often encountered in various infrastructure projects, especially in civil engineering, railway stations, rail transit stations and other building construction sites. The economic development in the eastern coastal areas of my country is rapid, and the speed of various infrastructure construction projects is increasing. Soft soil is widely distributed in the eastern coastal areas. In the construction process of various types of engineering projects, foundation treatment of soft soil is often required. Drainage consolidation method is a commonly used foundation treatment method. By applying pressure to the foundation soil under specific conditions, the groundwater in the foundation soil is discharged to achieve the effect of consolidating the foundation soil and improving the bearing capacity of the foundation soil.
[0003] In existing engineering operations, the discharged groundwater is often treated as wastewater. Through drainage and other means, the groundwater is discharged into the surrounding environment, causing great damage to the surrounding environment. In addition, the drainage and consolidation foundation treatment period is long, and the amount of discharged groundwater is also large. In the existing technical solutions, the secondary utilization of discharged groundwater resources is not considered, which seriously wastes the groundwater resources of the construction site. The existing technology has high construction costs. At the same time, since the discharge of groundwater causes serious ecological damage to the surrounding environment, it also has a very bad impact on the construction of the project. Summary of the invention
[0004] The purpose of the present invention is to provide a method for circulating and pressurizing freezable groundwater for drainage and consolidation foundation treatment based on the above-mentioned deficiencies of the prior art. The method collects the groundwater generated during the drainage and consolidation foundation treatment and applies it as ballast on the foundation. The groundwater after the foundation treatment is completed can be used as recharge water, thereby realizing the circulating and pressurizing method and utilization of groundwater.
[0005] The purpose of the present invention is achieved by the following technical solutions:
[0006] A method for circulating and pressurizing freezable groundwater for drainage and consolidation foundation treatment, characterized in that groundwater generated during drainage and consolidation treatment of the foundation is collected and introduced into a container, the container is placed on the foundation and the groundwater is frozen, and ballast is applied to the foundation through the container and the groundwater in the container.
[0007] A plurality of containers are placed on a plate body. The plurality of containers can be stacked on the plate body in a height direction and / or laid flat within a plane range of the plate body.
[0008] A limiting component is arranged on the plate body, and the limiting component and the container form a limiting connection to achieve the limiting between the plate body and the container.
[0009] The temperature of several containers stacked in the height direction is controlled by layer-by-layer temperature conduction. That is, the plate controls the temperature of the groundwater in a container above it, and the container controls the temperature of the groundwater in another container stacked above it, so that the temperature of each container on the plate is controlled reciprocally.
[0010] The container is a double-layer structure consisting of a water storage liner and a protective layer, wherein the protective layer is arranged on the outside of the water storage liner, the internal cavity of the water storage liner is a water collecting cavity, and the container is provided with a water pipe, a water inlet at one end of the water pipe is located on the surface of the protective layer, and a water outlet at the other end is connected to the water storage liner.
[0011] The surfaces of the water storage tank body are connected by an elastic body, so that the volume of the water removal tank can change with the change of groundwater volume and temperature.
[0012] A certain ballast is applied to the foundation by controlling the amount of groundwater in the container, and the ballast can be changed according to the drainage and consolidation process of the foundation.
[0013] After the drainage and consolidation treatment of the foundation is completed, the frozen groundwater is melted and recharged into the foundation.
[0014] The advantages of the present invention are: groundwater is used to provide consolidation pressure for foundation treatment, and groundwater in the container can be frozen to avoid groundwater turbulence and ensure that the container is easy to move, thereby ensuring the ecological environment of the foundation treatment area, realizing green construction, and achieving energy conservation and emission reduction effects; the present invention has complete functions, strong operability, simple and reasonable structure, easy use, and is suitable for promotion. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the system structure that can be used in the present invention;
[0016] Figure 2 It is a structural schematic diagram of the water collecting tank in the present invention;
[0017] Figure 3 It is a partial enlarged schematic diagram of the water pipe in the present invention;
[0018] Figure 4 It is a partial enlarged schematic diagram of the hole cover of the present invention;
[0019] Figure 5 It is a structural schematic diagram of the clamping ring and the clamping plate in the present invention;
[0020] Figure 6 It is a schematic diagram of the implementation process of the present invention. DETAILED DESCRIPTION
[0021] The features of the present invention and other related features are further described in detail below through embodiments in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art:
[0022] like Figure 1-6 As shown, the marks 1-23 in the figure respectively represent: water collecting tank 1, consolidation plate 2, stable main frame 3, groove 4, convex arch 5, temperature control body 6, socket slot 7, high-efficiency temperature control sheet 8, conductive wire 9, temperature control button 10, clamping ring 11, reinforcement body 12, clamping plate 13, water storage liner 14, protective layer 15, elastomer 16, water pipe 17, telescopic hose 18, hard pipe 19, water outlet 20, hole cover 21, force groove 22, water inlet 23.
[0023] Embodiment: The method for utilizing the circulating pressure supply of the freezable groundwater for drainage and consolidation of the foundation in this embodiment can be used as follows: Figure 1 The system shown is implemented, but is not limited to this system. Figure 1 As shown, the system mainly consists of three parts: a water collecting tank 1, a consolidation plate 2 and a stable main frame 3. The water collecting tank 1 as a container is mainly used to collect groundwater generated during drainage and consolidation foundation treatment; the consolidation plate 2 as a plate body is arranged at the bottom of the water collecting tank 1 to transfer groundwater energy to the foundation soil, thereby applying a certain ballast to the foundation, thereby improving the effect and efficiency of drainage and consolidation treatment; and the stable main frame 3 as a limiting member is mainly used to ensure the stability of the connection between the water collecting tank 1 and the consolidation plate 2, thereby ensuring that the groundwater energy can be effectively transferred to the consolidation plate 2.
[0024] Specifically, combined Figure 1 and Figure 2 As shown, a plurality of grooves 4 are distributed on the top of the consolidation plate 2 and the top of the water collecting tank 1, and the grooves 4 are arranged along the side line direction of the consolidation plate 2 or the water collecting tank 1. Convex arches 5 matching the shape and size of the grooves 4 are distributed at the bottom of the water collecting tank 1; when the water collecting tank 1 is placed on the consolidation plate 2, or different water collecting tanks 1 are stacked one by one along the height direction, each convex arch 5 can form a concave-convex fit with the upper groove 4 to form a limit, so as to improve the stability of the connection between different components.
[0025] In this embodiment, if Figure 1 As shown, in order to respectively arrange the water collecting boxes 1 on both sides of the consolidation plate 1 in the horizontal direction, two grooves 4 are respectively arranged on both sides of the plate body of the consolidation plate 1 .
[0026] like Figure 1As shown, a temperature control body 6 arranged throughout the length is provided at the top of the groove 4 of the consolidation plate 2 or the water collecting tank 1, and a socket 7 is correspondingly distributed inside the convex arch 5, and a socket connection of a concave-convex matching is formed between the socket 7 and the temperature control body 6, that is, the temperature control body 6 can be inserted into the socket 7. There is a high-efficiency temperature control sheet 8 inside the temperature control body 6, and the high-efficiency temperature control sheets 8 located on both sides of the consolidation plate 1 are connected by conductive wires 9, and the temperature of the high-efficiency temperature control sheet 8 can be adjusted by a temperature control button 10 placed at the bottom of the consolidation plate 2.
[0027] When the high-efficiency temperature control sheet 8 is powered, its temperature is controllable, and the temperature control body 6 provided with the high-efficiency temperature control sheet 8 can conduct the temperature of the high-efficiency temperature control sheet 8 to the inside of the socket 7 at the bottom of the water collecting tank 1 above, thereby controlling the groundwater temperature in the water collecting tank 1 and freezing it; the same applies to the water collecting tanks 1 stacked in the height direction. When multiple layers of water collecting tanks 1 are arranged above the consolidation plate 2, the temperature conduction direction is from bottom to top, that is, after the bottom water collecting tank 1 is affected by the temperature control body 6 with the high-efficiency temperature control sheet 8, the bottom water collecting tank 1 conducts the temperature influence to another water collecting tank above it through the temperature control body 6 arranged on its top, and so on and so forth until the temperature control of each water collecting tank 1 is completed; there is no need to separately set a temperature control device on each water collecting tank 1, which effectively simplifies the structure and reduces the manufacturing cost, making it easy to use.
[0028] Combination Figure 1 and Figure 5 As shown, a clamping ring 11 is distributed on the side of the water collecting tank 1, and a stable main frame 3 is arranged in the middle of the consolidation plate 1. One side of the stable main frame 3 is connected with a clamping plate 13 through a reinforcement body 12. The clamping plate 13 can be clamped in the clamping groove of the clamping ring 11, so that the water collecting tank 1 is embedded in the stable main frame 3, thereby realizing a limited connection between the water collecting tank 1 and the stable main frame 3.
[0029] In this embodiment, if Figure 5 As shown, clamping plates 13 are respectively provided on both sides of the stable main frame 3 to limit the water collecting tanks 1 on both sides thereof, so as to further ensure the balance of the ballast transmitted by the consolidation plate 2 .
[0030] like Figure 2 and Figure 3As shown, the water collection tank 1 is composed of a double-layer structure, namely a water storage tank 14 and a protective layer 15, wherein the internal cavity of the water storage tank 14 is a water collection cavity for groundwater, and the protective layer 15 is located on the outside of the water storage tank 14 to play a protective role. The protective layer 15 has compressibility and heat preservation functions, and can adapt to the spatial volume change of the water storage tank 14, while keeping the temperature of the groundwater in the water storage tank 14 unaffected by the surrounding environment. The different side elevations of the water storage tank 14 are connected by an elastic body 16. When the groundwater in the water collection tank 1 is frozen, the water storage tank 14 can flexibly respond to the volume change of the groundwater in the water collection tank 1 due to temperature changes, ensuring that the water collection tank 1 will not be damaged.
[0031] A water pipe 17 is provided on the opposite side of the water collecting box 1 without the clamp ring 11, which is the inlet and outlet channel of the groundwater in the water collecting box 1. The water pipe 17 is a telescopic hose 18 at the contact part between the water storage liner 14 and the protective layer 15, and the rest of the water pipe 17 is a hard pipe 19. Figure 3 As shown, the upper hard tube 19 is located in the protective layer 15, while the lower hard tube 19 is located in the side wall of the water storage tank 14; the structural design of the water pipe 17 allows it to adapt to the volume change of the groundwater in the water collection tank 1 caused by freezing, avoiding damage during repeated squeezing of the water storage tank 14. The lower hard tube 19 is provided with a water outlet 20 near the inner side of the water storage tank 14, and the groundwater mainly enters or is discharged from the water collection tank 1 through the water outlet 20. Figure 4 As shown, the upper hard tube 19 is provided with a water inlet 23 near the outer side of the protective layer 15, and is equipped with a hole cover 21 for blocking the water inlet 23, and the hole cover 21 is threadedly connected with the pipe body at the water inlet 23. A force groove 22 is provided on the hole cover 21, and when the hole cover 21 is tightly connected to the water inlet 24 through the force groove 22, the outer surface of the hole cover 21 can be flush with the outer surface of the protective layer 15 on the side, so as to facilitate the transportation of the water collecting box 1.
[0032] Combination Figures 1 to 6 As shown, this embodiment includes the following steps when using the system:
[0033] 1) If Figure 6 As shown in (a), in the area where drainage consolidation foundation treatment is to be carried out, the consolidation plate 2 is placed at the designed position.
[0034] 2) If Figure 6 As shown in (b), the clamp ring 11 on one side of the water collecting tank 1 is clamped on the clamping plate 13 from the top of the stable main frame 3, and placed downward on the consolidation plate 2. The convex arch 5 at the bottom of the water collecting tank 1 is placed corresponding to the groove 4 at the top of the consolidation plate 2, and at the same time, the temperature control body 6 at the top of the groove 4 is embedded in the socket 7 inside the convex arch 5.
[0035] 3) Open the hole cover 21 and inject the groundwater discharged during the drainage and consolidation foundation treatment operation into the water storage liner 14 inside the water collecting box 1 through the water pipe 17 to collect the groundwater.
[0036] 4) When the groundwater in the water storage tank 14 is filled, the hole cover 21 is tightened through the force application groove 22 .
[0037] 5) Repeat steps 1-5 to stack the remaining water collecting tanks 1 in sequence. Figure 6 (c) and fill each water collecting tank 1 with water. Figure 6 (d) shown.
[0038] 6) When the water collection tank 1 of a region is placed to meet the design requirements, the temperature of the high-efficiency temperature control sheet 8 and the temperature control body 6 is controlled by the temperature control button 10 on the consolidation plate 2, and then the temperature of the water storage tank 14 in each water collection tank 1 is adjusted in turn to achieve the freezing treatment of groundwater. Figure 6 As shown in (e), each water collecting tank 1 after freezing treatment applies ballast to the foundation treatment area through the consolidation plate 2, which effectively improves its treatment effect.
[0039] 7) Following the above operations, carry out groundwater circulation and pressure supply operations in other areas in sequence.
[0040] In addition to the above embodiments, consolidation plates 2 in multiple areas can also be placed at the same time according to construction needs to adapt to the regional scope of drainage consolidation foundation treatment. Different numbers of water collecting tanks 1 can be installed simultaneously according to the groundwater discharge situation, and water collecting tanks 1 can be filled with water to achieve the effect of providing quantitative ballast; for example, as the drainage consolidation foundation treatment proceeds, the water collecting tanks 1 are gradually increased to increase the total ballast on the consolidation plate 2, thereby improving the effect of drainage consolidation foundation treatment. It is also possible to freeze the water collecting tanks 1 in multiple areas at the same time as needed, and to freeze the water collecting tanks 1 in the same area separately. It is also possible to adjust the position of the water collecting tanks that have been filled with water and frozen in real time according to the drainage consolidation situation, foundation treatment effect and groundwater discharge requirements of different areas. The freezable groundwater circulation function system can flexibly adjust the operation plan according to construction needs and quickly realize the auxiliary operation of drainage consolidation foundation treatment. After the drainage and consolidation foundation treatment is completed, the temperature of the temperature control body 6 can also be adjusted by the temperature button 10 to melt the frozen groundwater in the water collecting tank 1 and use it for in-situ recharging.
[0041] Although the above embodiments have described in detail the concepts and embodiments of the present invention with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and changes can still be made to the present invention without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A method for circulating and pressurizing freezable groundwater for drainage and consolidation of foundation treatment, characterized in that: Collecting groundwater generated during drainage and consolidation of the foundation and introducing the groundwater into a container, placing the container on the foundation and freezing the groundwater, applying ballast to the foundation through the container and the groundwater in the container; after the drainage and consolidation of the foundation is completed, melting the frozen groundwater and recharging it into the foundation; Placing a plurality of containers on a plate, wherein the plurality of containers may be stacked on the plate in a height direction and / or laid flat within a plane of the plate; A limiting member is disposed on the plate body, and the limiting member and the container form a limiting connection to achieve the limiting between the plate body and the container; The temperature of several containers stacked in the height direction is controlled by temperature conduction layer by layer, that is, the plate controls the temperature of the groundwater in a container above it, and the container controls the temperature of the groundwater in another container stacked above it, so that the temperature of each container on the plate is controlled reciprocally; The container is a double-layer structure consisting of a water storage liner and a protective layer, wherein the protective layer is arranged on the outside of the water storage liner, the internal cavity of the water storage liner is a water collecting cavity, and the container is provided with a water pipe, a water inlet at one end of the water pipe is located on the surface of the protective layer, and a water outlet at the other end is connected to the water storage liner; The surfaces of the water storage tank body are connected by an elastic body, so that the volume of the water storage tank can change with the change of groundwater volume and temperature; A certain ballast is applied to the foundation by controlling the amount of groundwater in the container, and the ballast can be changed according to the drainage and consolidation process of the foundation.
Citation Information
Patent Citations
Separated rubber water tank device
CN108222081A
Water body prepressing loading structure for soft soil foundation
CN2866610Y
Method of preloading construction utilizing ice and snow in cold district
JP1994057731A