Method and device for predicting ice thickness based on wind farm monitoring data
Through the historical data of the wind farm, we establish the relationship between meteorological factor mapping, calculate the changes in the fan ice coating thickness, predict the future ice coating thickness and provide early warning, which solves the shortcomings of the ice coating monitoring and early warning system in the existing technology, and achieves accurate ice coating of the wind farm Forecast and operational adjustments.
Patent Information
- Application Number
- CN202210470121.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2021-11-04
- Filing Date
- 2022-04-28
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-04-28
AI Technical Summary
The existing ice-covered monitoring and early warning system cannot achieve accurate prediction of the recent power of the fan blade ice-covered, making it difficult for the dispatching department to adjust the operating mode in advance, affecting the normal operation and service life of the wind farm.
By obtaining the historical monitoring data of the wind farm, establish the meteorological factor mapping relationship between the wind measuring tower and the fan, calculate the change value of the fan's ice coating thickness, predict the future ice coating thickness, and issue an early warning when the ice coating thickness exceeds the preset value. .
It realizes accurate prediction of fan blades covered with ice, extends the prediction time, and scientifically guides the dispatching department to adjust its operating mode, and protects the normal operation and service life of the wind farm.
Smart Images

Figure CN114856942B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of wind power generation prediction, and in particular to a method, device, storage medium and processor for predicting ice thickness based on wind farm monitoring data. Background Art
[0002] With global climate change, winter cold snaps and freezing weather are becoming more frequent. Wind turbines are often located in mountainous areas with strong winds, bringing in more cold, humid water vapor, which often results in more severe icing on turbine blades than in other areas. Furthermore, even within the same wind farm, the onset of icing and ice thickness vary between turbines in different locations, making it difficult to predict icing at the turbine level.
[0003] Existing icing monitoring and early warning systems based on SCADA systems or other monitoring methods only perform extrapolated calculations of wind turbine blade icing based on real-time data. The early warning period is only a few hours, making it impossible to accurately predict the day-ahead power consumption that would cause a wind turbine to shut down due to icing on its blades, and unable to scientifically guide the dispatching department to adjust its operating mode in advance. Summary of the Invention
[0004] In order to solve the above technical problems, the purpose of the present invention is to provide a method, device, storage medium and processor for predicting ice thickness based on wind farm monitoring data.
[0005] To achieve the above-mentioned objectives, the present application provides, in a first aspect, a method for predicting ice thickness based on wind farm monitoring data, comprising: obtaining historical observation data of a wind tower and historical observation data of each wind turbine within a historical time period; determining a mapping relationship between meteorological elements between the wind tower and each wind turbine based on the historical observation data of the wind tower and the wind turbine; obtaining first observation data of the wind tower at a preset time point; inputting the first observation data into the mapping relationship to determine second observation data of each wind turbine corresponding to the first observation data, the second observation data including the real-time wind speed of the wind turbine; determining an icing status of each wind turbine at a preset time point based on the second observation data of each wind turbine; determining a change in ice thickness of each wind turbine based on the icing status of each wind turbine; obtaining the ice thickness of each wind turbine at a time point before the preset time point; for each wind turbine, determining an ice thickness value of the wind turbine at the preset time point based on the change value and the ice thickness at the previous time point; for each wind turbine, determining a predicted ice thickness value of the wind turbine at a future preset time point based on the ice thickness value of the wind turbine at the preset time point and an estimated ice increment value of the wind turbine at the future preset time point.
[0006] Optionally, the second observation data includes the wind speed v of the fan; determining the icing state of each fan at a preset time point based on the second observation data of each fan includes: determining the theoretical output value P(v) of each fan based on the wind speed v of each fan at the preset time point; obtaining the real-time output value P of each fan; for each fan, determining the power loss rate η of the fan at the preset time point based on the theoretical output value P(v) and the real-time output value P; obtaining the real-time fan parameters of each fan at the preset time point, the fan parameters including the fan blade length r, the fan blade speed ω, the fan head temperature T and the fan humidity RH; determining the icing state of each fan at the preset time point based on the power loss rate η and the real-time fan parameters.
[0007] Optionally, obtaining a fan model of each fan to determine the rated power of each fan; determining the theoretical output value P(v) of each fan according to the wind speed v of each fan at a preset time point includes determining a curve relationship between the real-time wind speed v of each fan at the preset time point and the theoretical output value according to formula (4):
[0008]
[0009] Among them, P(v) refers to the theoretical output value of the wind turbine at wind speed v, v0 is the cut-in wind speed of the wind turbine, that is, the wind speed when the wind turbine starts to generate electricity, and v1 is the rated wind speed of the wind turbine, that is, the wind speed at which the rated power of the wind turbine P is reached. m The wind speed at that time, a, b, c, d are the coefficients of the power curve respectively, and v2 is the wind turbine cut-out wind speed, which means that when the wind speed exceeds the wind turbine cut-out wind speed, the wind turbine triggers a protective shutdown and stops generating electricity.
[0010] Optionally, the icing state includes an icing growth state and an icing melting state. Determining the icing state of each fan at a preset time point based on the power loss rate η and real-time fan parameters includes: when the head temperature T is greater than the preset temperature value, or the fan humidity RH is less than the preset humidity value, determining that the icing state of the fan at the preset time point is an icing melting state; when all of the following conditions are met, determining that the icing state of the fan at the preset time point is an icing growth state: the power loss rate η is greater than the preset loss rate; the head temperature T is less than the preset temperature value; the fan humidity RH is greater than the preset humidity value; the wind speed v is greater than the first wind speed and the fan blade speed ω is less than the first speed, or the wind speed v is greater than the second wind speed, and the fan blade speed ω is less than the second speed.
[0011] Optionally, when the icing state of the wind turbine is an icing growth state, the change value of the icing thickness of the wind turbine at a preset time point is determined according to formula (1):
[0012]
[0013] Among them, ΔI iis the change in ice thickness of the i-th wind turbine, RH i is the humidity of the i-th fan at the preset time point, v i is the wind speed of the i-th wind turbine at the preset time point, T i is the head temperature of the i-th fan at the preset time point, pr i is the precipitation of the i-th wind turbine at the preset time point, ps i is the air pressure of the i-th fan at the preset time point, ω i is the fan blade speed of the i-th fan at the preset time point, r i is the length of the fan blade of the i-th fan.
[0014] When the icing state of the wind turbine is the icing melting state, the change value of the icing thickness of the wind turbine at the preset time point is determined according to formula (2);
[0015]
[0016] Among them, ΔI i is the change in ice thickness of the i-th wind turbine, RH i is the relative humidity of the i-th fan at the preset time point, v i is the wind speed of the i-th wind turbine at the preset time point, T i is the head temperature of the i-th fan at the preset time point, I t-1 is the ice thickness at the previous moment, ω i is the fan blade speed of the i-th fan at the preset time point, r i is the length of the fan blade of the i-th fan.
[0017] Optionally, when all of the following conditions are met, it is determined that the wind turbine blades are in an ice growth state and that the wind turbine blades are completely frozen: the wind speed v is greater than the wind turbine cut-in wind speed v0 and less than or equal to the wind turbine cut-out wind speed v2; the wind turbine blade speed ω is a preset speed value; the wind turbine pitch angle is close to a preset angle; when it is determined that the wind turbine blades are completely frozen, the change in ice thickness of the wind turbine at the preset time point is determined according to formula (3):
[0018]
[0019] Among them, is the change value of the ice cover thickness of the i-th fan, is the relative humidity of the i-th fan at the preset time point, is the wind speed of the i-th fan at the preset time point, is the head temperature of the i-th fan at the preset time point, is the precipitation of the i-th fan at the preset time point, is the air pressure of the i-th fan at the preset time point, is the fan blade speed of the i-th fan at the preset time point, and is the fan blade length of the i-th fan.
[0020] Optionally, the change in ice thickness of each wind turbine from the time point before time t to time t is determined according to formula (5):
[0021]
[0022] Among them, ΔI t is the change in ice thickness of the wind turbine from the moment before time t to time t. The time point before time t to time t refers to the time period from the preset time to the time point before the preset time point. I t-1 is the ice thickness at the previous time point, v is the real-time wind speed of the fan at time t, ω1 is the fan blade speed of the fan at time t, r1 is the fan blade length, pr1 is the precipitation at the fan location, ps1 is the air pressure at the fan location, T1 is the fan head temperature, RH1 is the relative humidity at the fan location, and ω1 is the fan speed of the fan.
[0023] Alternatively, ω1 is calculated according to formula (6):
[0024]
[0025] A second aspect of the present application provides a processor, a device for predicting ice thickness based on wind farm monitoring data, configured to execute a method for predicting ice thickness based on wind farm monitoring data.
[0026] A third aspect of the present application provides a device and a method for predicting ice thickness based on wind farm monitoring data, including the above-mentioned prediction method.
[0027] A fourth aspect of the present application provides a machine-readable storage medium having instructions stored thereon. When the instructions are executed by a processor, the processor is configured to execute the above-mentioned method for predicting ice thickness based on wind farm monitoring data.
[0028] The above technical solution obtains historical observation data from the wind tower and each wind turbine, and maps the meteorological elements between the wind tower and each wind turbine to calibrate the temperature, precipitation, wind speed, wind direction, relative humidity, and air pressure data at the wind turbine location. When the wind turbine blades are identified as being covered with ice, the change in ice thickness at a preset time point is calculated to determine the ice thickness at the preset time point, thereby predicting the ice thickness value of the wind turbine blades at a future time point. Based on the predicted ice thickness, when the ice thickness of the wind turbine exceeds the preset value, a forecast and early warning is carried out for the operating status of the wind turbine. This can avoid the problem of inaccurate wind turbine monitoring data caused by wind turbine blade icing, and extend the future time for predicting the ice thickness of the wind turbine blades. It can also scientifically guide the dispatching department to adjust the operating mode in advance to protect the service life and normal operation of the wind turbine generator set.
[0029] Other features and advantages of the embodiments of the present application will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The accompanying drawings are used to provide a further understanding of the embodiments of the present application and constitute a part of the specification. Together with the following detailed description, they are used to explain the embodiments of the present application but do not constitute a limitation on the embodiments of the present application. In the accompanying drawings:
[0031] Figure 1 The following schematically illustrates a flow chart of a method for predicting ice thickness based on wind farm monitoring data according to an embodiment of the present application;
[0032] Figure 2 The flowchart of step S500 according to an embodiment of the present application is schematically shown;
[0033] Figure 3 The following schematically shows a structural block diagram of a system for predicting ice thickness based on wind farm monitoring data according to an embodiment of the present application;
[0034] Figure 4 The internal structure diagram of a computer device according to an embodiment of the present application is schematically shown. DETAILED DESCRIPTION
[0035] To make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. It should be understood that the specific implementation methods described herein are only used to illustrate and explain the embodiments of the present application and are not used to limit the embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0036] It should be noted that if the implementation methods of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement status, etc. between the various components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indications will also change accordingly.
[0037] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features specified as "first" or "second" may explicitly or implicitly include at least one of such features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the fact that they can be implemented by ordinary technicians in this field. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0038] The embodiment of the present application provided in the present application proposes a method for predicting ice thickness based on wind farm monitoring data. Figure 1 The flowchart of the method for predicting ice thickness based on wind farm monitoring data according to an embodiment of the present invention is schematically shown. Figure 1 , the method comprising:
[0039] S100: Acquire historical observation data of a wind tower and historical observation data of each wind turbine within a historical time period.
[0040] A historical time period refers to a reference point in time. For example, if the reference point is the current time, then the historical time period can refer to any period within the past 15 days, month, or three months prior to the current time. Historical observation data from a wind tower refers to meteorological elements monitored by the tower over the past period, including ambient temperature, precipitation, wind speed, wind direction, relative humidity, and air pressure. Historical observation data for each wind turbine refers to meteorological elements monitored at each wind turbine location over the past period. These include turbine head temperature, precipitation, wind speed, wind direction, relative humidity, air pressure, and ice thickness. Observational data on these meteorological elements can significantly impact wind turbine power generation, particularly for wind turbines located in mountainous areas with strong winds. Frequent winter cold snaps and freezing events can lead to ice buildup on wind turbine blades. Therefore, monitoring meteorological data can scientifically guide dispatching departments to proactively adjust operating modes to protect the lifespan and proper operation of wind turbines.
[0041] S200: Determine a mapping relationship of meteorological elements between the wind tower and each wind turbine based on historical observation data of the wind tower and the wind turbine.
[0042] S300: Obtain first observation data of the wind tower at a preset time point. The first observation data refers to meteorological elements monitored by the wind tower at the preset time point, including ambient temperature, precipitation, wind speed, wind direction, relative humidity, air pressure, etc.
[0043] S400: Input the first observation data into the mapping relationship to determine the second observation data of each wind turbine corresponding to the first observation data, wherein the second observation data includes the real-time wind speed of the wind turbine.
[0044] The second observation data refers to the meteorological elements monitored by the wind turbine at the preset time point, including the ambient temperature, precipitation, wind speed, wind direction, relative humidity, air pressure, ice thickness, etc.
[0045] The mapping relationship between the meteorological elements of the wind tower and each wind turbine can be established using regression statistics, namely:
[0046] Among them, W1, W2, W3, W4, W5, etc. represent the meteorological elements such as temperature, precipitation, wind speed, relative humidity, and air pressure in the historical observation data of the wind tower and wind turbine respectively. The superscript F represents the second observation data of the wind turbine at a preset time point, the superscript c represents the first observation data of the wind tower at a preset time point, and the superscript T represents transposition. represents a mapping relationship, which refers to the "correspondence" between elements in two sets of elements. (C1, C2, C3, ...) represent the mapping relationship parameters. Using this mapping relationship, the observed values from the wind tower can be corrected to obtain the corrected values at each wind turbine location. This can be used to address issues such as turbulent interactions between wind turbines and inaccurate wind measurements caused by ice blocking anemometers after freezing.
[0047] S500: Determine an icing state of each wind turbine at a preset time point based on second observation data of each wind turbine.
[0048] The wind turbine's icing status includes ice growth and ice melting. When the ice thickness is gradually increasing, the wind turbine's current icing status can be determined as ice growth. When the ice thickness is gradually decreasing, the wind turbine's current icing status can be determined as ice melting. Based on the mapping relationship, the wind turbine's historical meteorological element observations can be determined to determine the wind turbine's location and environment, and to determine whether the wind turbine's icing status at a preset time point is ice growth or ice melting.
[0049] S600: Determine a change value of ice coating thickness of each wind turbine according to an ice coating state of each wind turbine.
[0050] The change value of the ice thickness of the wind turbine refers to the increase value of the ice thickness of the wind turbine when the wind turbine is determined to be in the ice growth state, and the decrease value of the ice thickness of the wind turbine when the wind turbine is determined to be in the ice melting state.
[0051] S700: Obtain ice thickness of each wind turbine at a time point before a preset time point.
[0052] The previous time point can be customized. For example, the previous time point of the fan before the preset time point can be half an hour before the preset time point, an hour before the preset time point, or any time point before the preset time point.
[0053] S800: For each wind turbine, determine the ice thickness value of the wind turbine at a preset time point according to the change value and the ice thickness at a previous time point.
[0054] The ice thickness value of the fan at a preset time point is the sum of the ice thickness value at the previous time point and the change in the ice thickness of the fan.
[0055] S900. For each wind turbine, determine a predicted ice thickness value for the wind turbine at a preset future time point based on the ice thickness value of the wind turbine at the preset future time point and an estimated ice increment value of the wind turbine at a preset future time point at the preset future time point.
[0056] Future preset time points can be customized. For example, a wind turbine's future preset time point can be half an hour, an hour, or any other time point in the future. The estimated ice increase for the wind turbine at the future preset time point can be determined based on the weather forecast for the future preset time point. The predicted ice thickness for the wind turbine at the future preset time point is the sum of the wind turbine's ice thickness at the preset time point and the estimated ice increase at the future preset time point.
[0057] In one embodiment, the second observation data includes the wind speed v of the wind turbine, and the icing state of each wind turbine at a preset time point can be determined based on the second observation data of each wind turbine. Figure 2 The flowchart of step S500 is schematically shown. Figure 2 , which includes:
[0058] S210 , determining a theoretical output value P(v) of each wind turbine according to the wind speed v of each wind turbine at a preset time point.
[0059] S220: Obtain the real-time output value P of each wind turbine.
[0060] S230 : For each wind turbine, determine the power loss rate η of the wind turbine at a preset time point according to the theoretical output value P(v) and the real-time output value P.
[0061] The theoretical output value P(v) of a fan is the power value produced by the fan when the wind speed is v, according to the fan operating standard, under ideal conditions without interference from external factors. This can be calculated using the real-time wind speed at a preset time point. The real-time output value P of a fan is the actual power value produced by the fan blades when the wind speed is v, influenced by external factors such as temperature, precipitation, wind speed, wind direction, relative humidity, air pressure, and ice thickness, as well as the fan's own parameters such as blade length, blade speed, and power. The real-time output value P can be directly obtained based on the fan's operating status.
[0062] The power loss rate η of each fan at a preset time point can be determined based on the fan's theoretical output value P(v) and real-time output value P. The fan's power loss rate η is the ratio of the difference between the fan's real-time output value P and the theoretical output value P(v) to the fan's theoretical output value P(v).
[0063] S240 , obtaining real-time fan parameters of each fan at a preset time point, where the fan parameters include fan blade length r, fan blade speed ω, fan head temperature T, and fan humidity RH.
[0064] S250: Determine the icing state of each wind turbine at a preset time point according to the power loss rate η and the real-time wind turbine parameters.
[0065] The icing state of the fan includes the icing growth state and the icing melting state. When the ice thickness is gradually increasing, it can be determined that the current icing state of the fan is the icing growth state. When the ice thickness is gradually decreasing, it can be determined that the current icing state of the fan is the icing melting state. Real-time fan parameters include the fan blade length r, the fan blade speed ω, the fan head temperature T, and the fan humidity RH. Based on the meteorological environment in which the fan is located and the fan power loss rate, it can be determined whether the icing state of the fan is the icing growth state or the icing melting state. Based on these two states, the change in the fan's ice thickness within a preset time can be predicted.
[0066] In one embodiment, the rated power of each wind turbine is determined based on the obtained wind turbine model of each wind turbine. The theoretical output value P(v) of each wind turbine is determined based on the wind speed v of each wind turbine at a preset time point, including: determining a curve relationship between the real-time wind speed v of each wind turbine at the preset time point and the theoretical output value according to formula (4):
[0067]
[0068] Among them, P(v) refers to the theoretical output value of the wind turbine at wind speed v. The theoretical output value of the wind turbine P(v) refers to the power value of the wind turbine blade output when the wind speed is v and the wind turbine is in an ideal state without interference from external factors, according to the wind turbine operation standard. v0 is the cut-in wind speed of the wind turbine, that is, the wind speed when the wind turbine starts to generate electricity. v1 is the rated wind speed of the wind turbine, that is, the wind speed at which the rated power of the wind turbine P is reached. m where a, b, c, and d are the coefficients of the power curve. v2 is the wind turbine cut-out wind speed, which means that when the wind speed exceeds the wind turbine cut-out wind speed, the wind turbine triggers a protective shutdown and stops generating power.
[0069] The wind turbine's cut-in wind speed is the wind speed that meets grid connection requirements, meaning it's the minimum wind speed at which the turbine can generate electricity. Below this wind speed, the turbine automatically shuts down. The rated wind speed of a wind turbine refers to the wind speed at which it operates at optimal efficiency. The rated power of a wind turbine refers to the power it generates at optimal efficiency. The cut-out wind speed of a wind turbine is the maximum wind speed at which the turbine can generate electricity. Above this speed, the turbine triggers a protective shutdown and stops generating electricity.
[0070] Furthermore, the power loss rate η of the wind turbine at a preset time point is determined according to the calculation formula (7):
[0071]
[0072] Among them, P(v) is the theoretical output value of the fan at the real-time wind speed v. The theoretical output value P(v) of the fan refers to the power value of the fan blade output when the wind speed of the fan is v, according to the fan operation standard, under ideal conditions without interference from external factors. P is the real-time output value P of the fan at the real-time wind speed v. The real-time output value P of the fan refers to the power value of the fan blade's actual output at this preset time point based on the real-time wind speed, when the fan is affected by external factors such as temperature, precipitation, wind speed, wind direction, relative humidity, air pressure, ice thickness, and its own parameters such as fan blade length, fan blade wind speed, and power. It can be directly obtained through the fan operation status. In actual applications, due to climate disasters such as winter cold waves and freezing, the operating states of the fan blades are different when the fan is in the un-iced state and the iced state at the same wind speed, resulting in a deviation between the real-time output value of the fan and the theoretical output value of the fan. According to the monitored actual output value P and the calculated theoretical output value P(v), the power loss rate η of the fan at the preset time point can be obtained.
[0073] In one embodiment, the ice cover state includes an ice cover growth state and an ice cover melting state. Determining the ice cover state of each wind turbine at a preset time point based on the power loss rate η and the real-time wind turbine parameters includes:
[0074] (1) When the head temperature T is greater than a preset temperature value, or the fan humidity RH is less than a preset humidity value, it is determined that the icing state of the fan at the preset time point is the icing melting state.
[0075] (2) When all of the following conditions are met, the icing state of the wind turbine at the preset time point is determined to be the icing growth state:
[0076] Condition 1: The power loss rate η is greater than the preset loss rate;
[0077] Condition 2: The head temperature T is lower than the preset temperature value;
[0078] Condition 3: The fan humidity RH is greater than the preset humidity value;
[0079] Condition 4: the wind speed v is greater than the first wind speed and the fan blade rotation speed ω is less than the first rotation speed, or the wind speed v is greater than the second wind speed and the fan blade rotation speed ω is less than the second rotation speed.
[0080] When the environment starts to heat up, the fan head temperature is greater than the preset temperature value when the environment is not heated up. Humidity RH is relative humidity, which refers to the percentage of water vapor pressure in the air to the saturated water vapor pressure at the same temperature. When the head temperature T is greater than the preset temperature value and the fan humidity RH is less than the preset humidity value, the fan's icing state can be determined as an ice melting state. When the ambient temperature is in a falling state, the fan head temperature T will also gradually decrease. At this time, it can be determined whether the fan head temperature T is less than the preset temperature value. At the same time, it is also necessary to determine whether the fan humidity RH is greater than the preset humidity value, whether the power loss rate η is greater than the preset loss rate, and whether the wind speed v is greater than the first wind speed and the fan blade speed ω is less than the first speed, or the wind speed v is greater than the second wind speed and the fan blade speed ω is less than the second speed. When all of the above conditions are met, that is, when the above conditions one to four are met, it can be determined that the fan is in an ice growth state.
[0081] In one embodiment, when the icing state of the wind turbine is an icing growth state, the change value of the icing thickness of the wind turbine at a preset time point is determined according to formula (1);
[0082]
[0083] Among them, ΔI i is the change in ice thickness of the i-th wind turbine, RH i is the relative humidity of the i-th fan at the preset time point, v i is the wind speed of the i-th wind turbine at the preset time point, T i is the head temperature of the i-th fan at the preset time point, pr i is the precipitation of the i-th wind turbine at the preset time point, ps iis the air pressure of the i-th fan at the preset time point, ω i is the fan blade speed of the i-th fan at the preset time point, r i is the length of the fan blade of the i-th fan.
[0084] In one embodiment, when the icing state of the wind turbine is the icing melting state, the change value of the icing thickness of the wind turbine at the preset time point is determined according to formula (2);
[0085]
[0086] Among them, ΔI i is the change in ice thickness of the i-th wind turbine, RH i is the relative humidity of the i-th fan at the preset time point, v i is the wind speed of the i-th wind turbine at the preset time point, T i is the head temperature of the i-th fan at the preset time point, I t-1 is the ice thickness at the previous moment, ω i is the fan blade speed of the i-th fan at the preset time point, r i is the length of the fan blade of the i-th fan.
[0087] When determining that a wind turbine's icing state is in the growth state, factors directly influencing the change in ice thickness at a preset time point include the turbine's real-time meteorological observations and its own parameters. These include humidity (RH), wind speed, head temperature, precipitation at the turbine's location, and air pressure. Real-time parameters include blade speed (ω) and blade length (r). Based on these parameters, the change in ice thickness during the growth state can be accurately calculated.
[0088] When determining whether the wind turbine's icing state is melting, the factors affecting the change in the wind turbine's ice thickness at a preset time point are only affected by some of the wind turbine's real-time meteorological factors, including the wind turbine's humidity (RH), wind speed, and head temperature. Based on the mapping relationship between meteorological factors established between the wind tower and each wind turbine based on historical observation data from the wind tower and the wind turbine, and according to the calculation formula for different wind turbine icing states, the change in the wind turbine's ice thickness at a preset time can be more accurately calculated. Furthermore, when the wind turbine's icing state is melting, the change in ice thickness only needs to be calculated based on three parameters, reducing the amount of calculation and increasing the calculation speed.
[0089] In one embodiment, it is determined that the wind turbine blades are in an ice growth state and are completely frozen when all of the following conditions are met:
[0090] Condition 1: The wind speed v is greater than the wind turbine’s cut-in wind speed v0 and less than or equal to the wind turbine’s cut-out wind speed v2;
[0091] Condition 2: the fan blade speed ω is a preset speed value;
[0092] Condition three: the pitch angle of the wind turbine is close to the preset angle.
[0093] When it is determined that the icing state of the fan blades is in the icing growth state, the icing of the fan blades will gradually increase until the fan blades are completely frozen. Therefore, when the fan blades are in the icing growth state, it is further necessary to determine whether the wind speed v of the fan is greater than the fan's cut-in wind speed v0, and whether it is less than or equal to the fan's cut-out wind speed v2, to determine whether the fan is in operation at this time, and to eliminate the problem of the fan shutting down due to the wind speed being too high or too low. At the same time, it is determined whether the fan blade speed ω is the preset speed value, and whether the fan's pitch angle is close to the preset angle. When all of the above conditions are met, that is, when all of the above conditions one to three are met, it can be determined that the fan blades are completely frozen. The preset speed value of the fan blade speed refers to the fan speed value when the fan blades are completely frozen, and the fan pitch angle close to the preset angle refers to the fan pitch angle when the fan blades are completely frozen.
[0094] When it is determined that the wind turbine blades are completely frozen, the change in ice thickness of the wind turbine at the preset time point is determined according to formula (3):
[0095]
[0096] Among them, ΔI i is the change in ice thickness of the i-th wind turbine, RH i is the relative humidity of the i-th fan at the preset time point, v i is the wind speed of the i-th wind turbine at the preset time point, T i is the head temperature of the i-th fan at the preset time point, pr i is the precipitation of the i-th wind turbine at the preset time point, ps i is the air pressure of the i-th fan at the preset time point, ω i is the fan blade speed of the i-th fan at the preset time point, r i is the length of the fan blade of the i-th fan.
[0097] Furthermore, the change in ice thickness of each wind turbine from the time point before time t to time t based on different temperatures is determined according to formula (5):
[0098]
[0099] Among them, ΔIt is the change in ice thickness of the wind turbine from the time point before time t to time t. The time point before time t to time t refers to the time period from the preset time to the time point before the preset time point. I t-1 is the ice thickness at the previous time point, v is the real-time wind speed of the fan at time t, ω1 is the fan blade speed of the fan at time t, r1 is the fan blade length, pr1 is the precipitation at the location of the fan, ps1 is the air pressure at the location of the fan, T1 is the head temperature of the fan, RH1 is the relative humidity at the location of the fan, and ω1 is the fan speed of the fan.
[0100] When it is determined that the fan blades are completely frozen, the factors that have a direct impact on the change in the ice thickness of the fan at the preset time point include: the real-time meteorological element observation value of the fan and the real-time self-parameters of the fan. Among them, the real-time meteorological element of the fan includes at least one of the humidity RH of the fan, the wind speed of the fan, the temperature of the fan head, the precipitation at the fan location, and the air pressure of the fan. The real-time self-parameters of the fan include at least one of the fan blade speed ω and the fan blade length r. Then, according to the mapping relationship, the second observation data of the fan after correction is obtained. According to the calculation formula when the fan blades are completely frozen, the change value of the ice thickness of the fan at the preset time when the fan blades are completely frozen can be accurately calculated.
[0101] Where ω1 is the fan speed of the fan, and the fan blade speed ω is calculated according to formula (6):
[0102]
[0103] Among them, v is the real-time wind speed of the fan when the fan blades are frozen, v0 is the cut-in wind speed of the fan, that is, the wind speed when the fan starts to generate electricity, and v1 is the rated wind speed of the fan, that is, the wind speed at which the rated power of the fan P is reached. m Where a, b, c, and d are the coefficients of the power curve. V2 is the wind turbine cut-out wind speed, which means that when the wind speed exceeds the cut-out wind speed, the wind turbine triggers a protective shutdown and stops generating power. The wind speed drives the wind turbine blades to rotate, and the blade speed is determined by the wind speed.
[0104] In a specific embodiment, a method for predicting ice thickness based on wind farm monitoring data includes: step 1, collecting 15-minute temperature, precipitation, wind speed, relative humidity, and air pressure monitoring values of a wind tower 10 and a wind turbine 20 in a certain wind farm in the past three winters (December, January, and February).
[0105] Step 2: Using regression statistics, a calibration equation is established based on meteorological factors such as temperature, precipitation, wind speed, relative humidity, and air pressure at the locations of the wind tower 10 and the wind turbine generator set 20:
[0106]
[0107] Step 3, the observation data collected from the wind tower 10 at time t is calculated according to the correction equation of the mapping relationship in step 2, and the wind speed at the wind turbine generator group 20 is v = 7m / s, the temperature of the wind turbine head T1 = -0.7℃, the humidity of the wind turbine RH1 = 88%, the precipitation pr1 = 0.7mm, and the air pressure ps1 = 100300Pa.
[0108] Step 4: Obtain the wind turbine model of the wind turbine generator set 20 and determine the relationship between the wind speed of the wind turbine and the theoretical power curve of the wind turbine at time t according to formula (4):
[0109]
[0110] Where P(v) refers to the theoretical output value of the wind turbine at wind speed v. The cut-in wind speed of the wind turbine generator set 20 is 2.5m / s, that is, the wind speed when the wind turbine starts to generate electricity. The rated wind speed of the wind turbine generator set 20 is 12.5m / s, that is, the rated power P of the wind turbine is reached. m =2560. a = -5.1023, b = 130.56, c = -721.94, and d = 1147.7 are the coefficients of the power curve. The wind turbine generator set 20 has a cut-out wind speed of 25 m / s, which means that when the wind speed exceeds the cut-out wind speed, the wind turbine triggers a protective shutdown and stops generating electricity.
[0111] At time t, the theoretical output value calculated by the above formula is P(v1)=669kw, and the actual output value of the fan is P=140kw.
[0112] Step 5: Determine the power loss rate of the wind turbine generator set 20 according to the power loss rate η calculation formula (7) at the preset time point:
[0113]
[0114] Step 6: At time t, read the blade length r of wind turbine generator set 20, which is 43 m, and the real-time blade speed ω of wind turbine generator set 20, which is 7 rpm. Furthermore, wind turbine generator set 20 satisfies the following conditions: power loss η > 55%, turbine head temperature T1 < 0°C, and fan humidity RH1 > 80%. Therefore, it is determined that the icing state of the wind turbine generator set at time t is in the growing icing state.
[0115] Step 7: At time t, the wind speed at wind turbine generator set 20 calculated according to the correction equation of the mapping relationship in step 2 is v = 7m / s, the temperature of the wind turbine head T1 = -0.7m / s, the humidity of the wind turbine RH1 = 80%, the precipitation pr1 = 0.7mm, the air pressure ps1 = 100300Pa, and the wind turbine blade length r = 43m and the wind turbine speed ω = 7rpm of wind turbine generator set 20 are read. When wind turbine generator set 20 is determined to be in the ice growth state, the change in ice thickness from time t to time t+1 can be determined according to formula (1):
[0116]
[0117] Step 8: At time t, the ice thickness of the wind turbine generator set 20 is I t =0, so:
[0118] I t+1 =max(I t +ΔI i ,0)=0.5mm
[0119] Among them, I t+1 is the ice thickness of the wind turbine at time t+1, ΔI i is the change in ice thickness from time t to time t+1, I t +ΔI i Indicates the ice thickness from time t to time t+1, max(a, b) means taking the larger value of a and b. If the ice is melting, the change in ice thickness from time t to time t+1, ΔI i When it is less than 0, I t +ΔI i The calculated result is also less than 0. At this time, it is judged that there is no ice on the fan, so the actual ice thickness value I needs to be converted into ice by the max(a, b) function. t+1 Take it as 0.
[0120] Step 9: superimpose this ice cover value onto the ice cover thickness increment prediction value sequence for the next three days (Table 1).
[0121] Table 1 Original ice thickness series
[0122] time Ice thickness (mm) time Ice thickness (mm) t+1 0.0 t+6 6.0 t+2 0.9 … … t+3 1.6 t+18 6.6 t+4 2.2 … … t+5 3.9 t+288 8.2
[0123] That is, the predicted ice thickness for the next three days based on monitoring correction is obtained, as shown in Table 2 below.
[0124] Table 2 Ice thickness series corrected by this method
[0125] time Ice thickness (mm) time Ice thickness (mm) t+1 0.5 t+6 6.5 t+2 1.4 … … t+3 2.1 t+18 7.1 t+4 2.7 … … t+5 4.4 t+288 8.7
[0126] Step 10: Calculate that at time t+18, the ice thickness is greater than 7 mm, and the ice prediction and warning module issues an ice shutdown alarm message, indicating that the wind turbine generator set 20 will be shut down due to ice at this moment.
[0127] The above technical solution can be used to calibrate the temperature, precipitation, wind speed, wind direction, relative humidity, and air pressure data at the wind turbine location. When the wind turbine blades are identified as being covered with ice, the change in ice thickness at a preset time point is calculated to determine the ice thickness at the preset time point, thereby predicting the ice thickness value of the wind turbine blades at a future time point. Based on the predicted ice thickness, when the ice thickness of the wind turbine exceeds the preset value, a forecast and early warning is carried out for the wind turbine operating status. This can avoid the problem of inaccurate wind turbine monitoring data caused by wind turbine blade icing, and extend the future time for predicting the wind turbine blade ice thickness. It can also scientifically guide the dispatching department to adjust the operating mode in advance to protect the service life and normal operation of the wind turbine generator set.
[0128] In one embodiment, Figure 3 As shown, a device 30 for predicting ice thickness based on wind farm monitoring data is provided, comprising a data collection module 31, a mapping relationship module 32, an ice state judgment module 33, an ice thickness change calculation module 34, and an ice prediction and warning module 35, wherein:
[0129] The data collection module 31 is used to collect data such as wind towers, historical meteorological observation data of wind turbines, blade length, rotation speed, and output of wind turbines required for predicting the ice thickness of wind turbine blades.
[0130] The mapping relationship module 32 is used to construct a mapping relationship between the elements of the historical meteorological observation data of the wind tower and the wind turbine. After the mapping relationship is established according to the regression statistical model, the observation value of the wind tower is corrected to obtain the corrected value of each data at each wind turbine position.
[0131] The icing state identification module 33 is used to determine whether the icing state of the wind turbine blades is an icing growth state or an icing melting state, and if it is determined to be an icing growth state, determine whether the wind turbine blades are completely frozen.
[0132] Ice thickness change calculation module 34 is used to calculate the change in ice thickness on the wind turbine blades at a preset time point. The ice thickness on the wind turbine blades at the preset time point is determined based on the change in ice thickness at the preset time point and the ice thickness value at the previous time point. An estimated incremental ice thickness value for the wind turbine blades at a preset time point in the future is calculated. The estimated incremental ice thickness value at the preset time point in the future is combined with the estimated incremental ice thickness value at the preset time point to obtain a final prediction of ice thickness for each wind turbine blade in the preset future time period.
[0133] The icing prediction and warning module 35 is used to collect ice thickness calculation results and carry out prediction and warning for the wind turbine operating conditions when the ice thickness exceeds a preset value.
[0134] The method for predicting ice thickness based on wind farm monitoring data includes a processor and a memory. The above implementation plans are all stored in the memory as program units, and the processor executes the above program modules stored in the memory to implement corresponding functions.
[0135] The processor includes a core, which retrieves the corresponding program unit from the memory. One or more cores can be provided, and the method for predicting ice thickness based on wind farm monitoring data can be implemented by adjusting the core parameters.
[0136] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM, and the memory includes at least one memory chip.
[0137] An embodiment of the present application provides a storage medium having a program stored thereon, which, when executed by a processor, implements the above-mentioned method for predicting ice thickness based on wind farm monitoring data.
[0138] An embodiment of the present application provides a processor, which is used to run a program, wherein the program, when running, executes the above-mentioned method for predicting ice thickness based on wind farm monitoring data.
[0139] In one embodiment, a computer device is provided. The computer device may be a server, and its internal structure diagram may be as follows: Figure 4 As shown. The computer device includes a processor A01, a network interface A02, a memory (not shown in the figure) and a database (not shown in the figure) connected via a system bus. Among them, the processor A01 of the computer device is used to provide computing and control capabilities. The memory of the computer device includes an internal memory A03 and a non-volatile storage medium A04. The non-volatile storage medium A04 stores an operating system B01, a computer program B02 and a database (not shown in the figure). The internal memory A03 provides an environment for the operation of the operating system B01 and the computer program B02 in the non-volatile storage medium A04. The database of the computer device is used to store wind farm monitoring data. The network interface A02 of the computer device is used to communicate with an external terminal through a network connection. When the computer program B02 is executed by the processor A01, it realizes a method for predicting ice thickness based on wind farm monitoring data.
[0140] Those skilled in the art will understand that Figure 4The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than shown in the figure, or combine certain components, or have a different component arrangement.
[0141] In one embodiment, the device for predicting ice thickness based on wind farm monitoring data provided by the present application can be implemented in the form of a computer program. The computer program can be used in Figure 4 The computer device is run on the computer device shown. The memory of the computer device can store various program modules that constitute the device for predicting ice thickness based on wind farm monitoring data, such as: Figure 3 The computer program composed of modules 31, 32, 33, 34 and 35 enables the processor to execute the steps of the method for predicting ice thickness based on wind farm monitoring data of each embodiment of the present application described in this specification.
[0142] Those skilled in the art will appreciate that the embodiments of the present application can be provided as methods, systems, or computer program products. Therefore, the present application can adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application can adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to magnetic disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code.
[0143] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the steps in the process. Figure 1 a process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0144] These computer program instructions may also be stored in a computer readable memory that can direct a computer or other programmable data processing device to work in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 a process or multiple processes and / or boxes Figure 1 The function specified in one or more boxes.
[0145] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operational steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing the instructions executed on the computer or other programmable device for implementing the process. Figure 1 a process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.
[0146] In a typical configuration, a computing device includes one or more processors (CPUs), input / output interfaces, network interfaces, and memory.
[0147] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.
[0148] Computer-readable media includes permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. The information can be computer-readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disc read-only memory (CD-ROM), digital versatile disc (DVD) or other optical storage, magnetic cassettes, magnetic tape, magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer-readable media does not include transitory computer-readable media (transitory media), such as modulated data signals and carrier waves.
[0149] It should also be noted that the terms "comprises," "includes," or any other variations thereof are intended to encompass non-exclusive inclusion, such that a process, method, commodity, or apparatus that includes a series of elements includes not only those elements but also other elements not explicitly listed, or includes elements inherent to such process, method, commodity, or apparatus. In the absence of further limitations, an element defined by the phrase "comprises a ..." does not exclude the presence of other identical elements in the process, method, commodity, or apparatus that includes the element.
[0150] The above are merely embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present application should all be included within the scope of the claims of the present application.
Claims
1. A method for predicting ice thickness based on wind farm monitoring data, characterized in that: include: Obtain historical observation data for the wind tower and each wind turbine in the historical time period; Determine a mapping relationship between meteorological elements between the wind tower and each wind turbine according to historical observation data of the wind tower and the wind turbine; Obtaining first observation data of the wind tower at a preset time point; Inputting the first observation data into the mapping relationship to determine second observation data of each wind turbine corresponding to the first observation data, wherein the second observation data includes a real-time wind speed of the wind turbine; According to the wind speed of each fan at the preset time point v Determine the theoretical output of each fan ; Get the real-time output value of each fan P ; For each fan, according to the theoretical output value and the real-time output value P Determine the power loss rate of the fan at the preset time point ; Obtain the real-time fan parameters of each fan at the preset time point, wherein the fan parameters include the fan blade length r , fan blade speed , fan head temperature T and fan humidity RH ; According to the power loss rate and the real-time fan parameters to determine the icing state of each fan at the preset time point; Determine the change value of ice thickness of each wind turbine according to the ice state of each wind turbine; Obtaining the ice thickness of each wind turbine at a time point before the preset time point; For each wind turbine, determining the ice thickness of the wind turbine at the preset time point according to the change value and the ice thickness at the previous time point; For each wind turbine, a predicted value of ice thickness of the wind turbine at a preset time point in the future of the preset time point is determined according to the ice thickness value of the wind turbine at the preset time point and the estimated value of ice increment of the wind turbine at the preset time point in the future.
2. The method for predicting ice thickness based on wind farm monitoring data according to claim 1 is characterized in that: The ice cover state includes an ice cover growth state and an ice cover melting state; The power loss rate Determining the icing state of each fan at the preset time point with the real-time fan parameter includes: At the head temperature T Greater than the preset temperature or the fan humidity RH When the humidity is less than a preset humidity value, determining that the ice-covered state of the fan at the preset time point is the ice-covered melting state; When all of the following conditions are met, it is determined that the icing state of the fan at the preset time point is the icing growth state: The power loss rate Greater than the preset loss rate; The head temperature T is lower than the preset temperature value; The humidity of the fan RH Greater than the preset humidity value; The wind speed v Greater than the first wind speed and the fan blade speed is less than the first speed, or the wind speed v is greater than the second wind speed, and the fan blade speed is less than the second speed.
3. The method for predicting ice thickness based on wind farm monitoring data according to claim 1, characterized in that: The ice cover state includes an ice cover growth state and an ice cover melting state; Determining the change value of ice thickness of each wind turbine according to the ice coating state of each wind turbine includes: When the icing state of the fan is the icing growth state, the change value of the icing thickness of the fan at the preset time point is determined according to formula (1): = (1); in, For the i The change in ice thickness of each wind turbine is For the i The relative humidity of each fan at the preset time point, For the i The wind speed of each fan at the preset time point, For the i The head temperature of each fan at the preset time point, For the i The amount of precipitation per wind turbine at the preset time point, For the i The air pressure of each fan at the preset time point, For the i the fan blade speed of each fan at the preset time point, For the i The length of the fan blades of each fan; When the ice-covered state of the fan is the ice-melting state, the change value of the ice-covered thickness of the fan at the preset time point is determined according to formula (2): (2); in, For the i The change in ice thickness of each wind turbine is For the i The relative humidity of each fan at the preset time point, For the i The wind speed of each fan at the preset time point, For the i The head temperature of each fan at the preset time point, is the ice thickness at the previous moment, For the i the fan blade speed of each fan at the preset time point, For the i The length of the fan blades of a fan.
4. The method for predicting ice thickness based on wind farm monitoring data according to claim 3 is characterized in that: The step of determining the change value of ice thickness of each wind turbine according to the ice coating state of each wind turbine further includes: When all of the following conditions are met, it is determined that the fan blade is in the ice growth state and the fan blade is completely frozen: The wind speed v Greater than the cut-in wind speed of the fan , and is less than or equal to the cut-out wind speed of the fan ; The fan blade speed is the preset speed value; The pitch angle of the wind turbine is close to a preset angle; When it is determined that the fan blades are completely frozen, the change value of the ice thickness of the fan at the preset time point is determined according to formula (3): = (3); in, For the i The change in ice thickness of each wind turbine is For the i The relative humidity of each fan at the preset time point, For the i The wind speed of each fan at the preset time point, For the i The head temperature of each fan at the preset time point, For the i The amount of precipitation per wind turbine at the preset time point, For the i The air pressure of each fan at the preset time point, For the i the fan blade speed of each fan at the preset time point, For the i The length of the fan blades of a fan.
5. The method for predicting ice thickness based on wind farm monitoring data according to claim 1, characterized in that: The method further includes: obtaining a fan model of each fan to determine a rated power of each fan; According to the wind speed of each fan at the preset time point Determine the theoretical output of each fan Including, according to formula (4), determining the real-time wind speed of each wind turbine at the preset time point v The curve relationship with the theoretical output value: (4); in, The wind speed of the fan v The theoretical output value when is the cut-in wind speed of the wind turbine, that is, the wind speed when the wind turbine starts to generate electricity, is the rated wind speed of the fan, that is, the rated power of the fan P m The wind speed at a, b, c, d are the coefficients of the power curve, The wind turbine cut-out wind speed refers to the wind turbine triggering a protective shutdown and no longer generating electricity after the wind speed exceeds the wind turbine cut-out wind speed.
6. The method for predicting ice thickness based on wind farm monitoring data according to claim 1, characterized in that: The method further comprises: According to formula (5), the change in ice thickness of each wind turbine from the time point before time t to time t based on different temperatures is determined as follows: (5); in, is the change value of the ice thickness of the wind turbine from the time point before the time t to the time t, and the time point before the time t to the time t refers to the time period from the preset time to the time point before the preset time point, is the ice thickness at the previous time point, For the fan t Real-time wind speed at the moment, is the fan blade speed at time t, is the fan blade length, is the precipitation at the location of the wind turbine, is the air pressure at the location of the fan, is the head temperature of the fan, is the relative humidity at the location of the fan, is the fan speed of the fan.
7. The method for predicting ice thickness based on wind farm monitoring data according to claim 6, characterized in that: Said According to formula (6), we can get: (6); in, The real-time wind speed of the fan when the fan blades are frozen. is the cut-in wind speed of the wind turbine, that is, the wind speed when the wind turbine starts to generate electricity, is the rated wind speed of the fan, that is, the rated power of the fan The wind speed at a, b, c, d are the coefficients of the power curve, Cut out wind speed for the fan.
8. A processor, characterized in that: The method is configured to execute the method for predicting ice thickness based on wind farm monitoring data according to any one of claims 1 to 7.
9. A device for predicting ice thickness based on wind farm monitoring data, characterized in that Comprising a processor according to claim 8.