A glass production workshop planning method and system based on RGV trolley load

By detecting the handling parameters of RGV trolleys and performing secondary planning, the congestion problem in the glass production workshop caused by air travel and poor workshop planning is solved, and more efficient and energy-saving production is achieved, which improves production capacity and reduces costs.

CN114895632BActive Publication Date: 2025-04-22TRULY (RENSHOU) HIGH-END DISPLAY TECH LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202210321569.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-29
Publication Date
2025-04-22
Estimated Expiration
2042-03-29

AI Technical Summary

Technical Problem

In the glass production workshop, due to the operation of RGV trolleys, the workflow and poor workshop planning have resulted in congestion, which reduces production efficiency and increases production costs.

Method used

By detecting RGV trolleys, obtaining handling parameters, and using these parameters to calculate the handling load of RGV trolleys per unit time, secondary planning of the glass production workshop is performed based on the handling load, adjusting the layout of the material storage device, and optimizing the layout in the workshop, thereby improving the smoothness of STK handling.

Benefits of technology

It achieves more efficient and energy-saving goods, improves production capacity, reduces production costs, and avoids congestion in the storage device caused by capacity increase, reducing abnormal time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114895632B_ABST
    Figure CN114895632B_ABST
Patent Text Reader

Abstract

The present invention discloses a glass production workshop planning method based on the RGV trolley load, and the method includes the steps of: using the handling parameters to calculate the RGV trolley's handling load per unit time; performing secondary planning on the glass production workshop according to the handling load and outputting the planning image; wherein the handling parameters include the layout of the handling nodes and the time to complete a single handling task; and also discloses a system. By detecting the RGV trolley, obtaining the handling parameters, and using the handling parameters to calculate the RGV trolley's handling load per unit time, performing secondary planning on the glass production workshop according to the handling load and outputting the planning image; adjusting the congestion of the storage device caused by the increase in production capacity, thereby optimizing the layout in the workshop, and improving the smoothness of the storage device STK handling, so as to achieve more efficient and energy-saving production, increase production capacity, and reduce costs; avoiding the congestion of the storage device STK caused by the increase in production capacity, thereby affecting the production of equipment, and reducing abnormal time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of workshop planning, and in particular to a glass production workshop planning method and system based on RGV trolley load. Background Art

[0002] In the production process of digital manufacturing workshops, material distribution is a very important link. With the personalized development of market demand, the production model of enterprises has changed from single-variety mass production to multi-variety small-batch production. In particular, as the concept of just-in-time production has been gradually adopted and promoted by manufacturing companies, the "near-zero inventory production" and "just-in-time delivery" material distribution model has become one of the key means for manufacturing companies to reduce inventory costs and improve production efficiency. This makes the material distribution of digital manufacturing workshops increasingly arduous and complex. How to ensure that the various material resources required for workshop production are delivered to the correct processing location at the right time and in the right quantity has become a bottleneck problem that needs to be solved in the material distribution of digital manufacturing workshops. For example, a Chinese invention patent discloses an RGV scheduling method based on a serial scheduling algorithm, including an RGV scheduling system and a serial scheduling algorithm. The RGV scheduling system includes an RGV scheduling interface, which is characterized in that: the serial scheduling algorithm is placed in the RGV scheduling interface, and the serial scheduling algorithm first pre-creates a configuration file about the line layout, RGV track, and scheduling task priority level; then after obtaining the pre-configured configuration file, the optimal path and the RGV scheduling task allocation operation are performed, and the corresponding control instructions are generated. Finally, the instructions are sent to the RGV for execution through the RGV interface provided by the equipment manufacturer, thereby realizing the panel handling efficiency when controlling multiple RGVs corresponding to multiple automated production lines, thereby improving the utilization rate of the RGV and the flow speed of the panels between each process.

[0003] In the glass production workshop, after the materials are fed and cleaned, the RGV trolley transports the cassette (CST) storing the glass to the OHS, and then to the stocker (STK) where the next process equipment (EQ) is located. This cycle continues until the production of a single piece of glass is completed. After the production of a single piece of glass is completed, the RGV trolley transports the CST from the STK to the corridor and sends it to the bonding workshop for bonding.

[0004] Generally, a single complete transport of the RGV trolley requires two transports. The first transport is from the RGV trolley to the EQP, and the second transport is from the RGV trolley to the OUT port. Since the RGV trolley cycle is faster than the EQP cycle, the CST can only be placed in the storage position before being sent to the EQP. Since the RGV trolley is not at the required CST transport position when receiving the command, a period of empty running will be generated. The equipment manufacturer provides this value as 2 / 3 of the STK length.

[0005] During the production process, due to the lack of management of glass distribution in the workshop, congestion often occurs between RGV carts, which not only hinders the improvement of production capacity, but also increases production costs. Summary of the invention

[0006] During the distribution process in the glass production workshop, the operation of the RGV cart will produce a part of empty running. On the other hand, due to poor workshop planning, congestion often occurs when the production capacity is increased, which reduces production efficiency and increases production costs.

[0007] In view of the above problems, a planning method and system for a glass production workshop based on the RGV trolley load are proposed. The RGV trolley is detected to obtain the handling parameters, and the handling parameters are used to calculate the handling load of the RGV trolley per unit time. The glass production workshop is secondary planned according to the handling load and the planning image is output. The congestion of the storage device caused by the increase in production capacity is adjusted accordingly, and the layout in the workshop is optimized, and the smoothness of STK transportation is improved to achieve more efficient and energy-saving production, increase production capacity, and reduce costs; avoid congestion of the storage device STK due to increased production capacity, which will affect the production of equipment and reduce abnormal time.

[0008] In a first aspect, a glass production workshop planning method based on RGV trolley load includes:

[0009] Step 100, using the transport parameters to calculate the load carried by the RGV vehicle per unit time;

[0010] Step 200, performing secondary planning of the glass production workshop according to the handling load and outputting a planning image;

[0011] The transport parameters include the transport node layout and the time to complete a single transport task.

[0012] In conjunction with the glass production workshop planning method of the present invention, in a first possible implementation manner, step 100 includes:

[0013] Step 110, obtaining the node distribution of all production nodes that complete a single transport task;

[0014] Step 120: Utilize the node distribution to obtain a glass material process route that connects all the production nodes in series.

[0015] In combination with the first possible implementation manner of the present invention, in a second possible implementation manner, step 100 further includes:

[0016] Step 130, decomposing the process route of the glass material to obtain all the travel routes of the RGV vehicle to complete the transportation task;

[0017] Step 140: According to the walking route, the running action categories of the RGV vehicle to complete all the walking routes are obtained;

[0018] The operation action categories include:

[0019] Loading and unloading, acceleration and deceleration, maximum speed, and empty running.

[0020] In combination with the second possible implementation manner of the present invention, in a third possible implementation manner, step 100 further includes:

[0021] Step 150, obtaining the travel distribution of any of the running action categories in the walking route;

[0022] Step 160: Calculate the time required to complete all travel routes of a single production task based on the travel distribution.

[0023] In combination with the third possible implementation manner of the present invention, in a fourth possible implementation manner, step 160 includes:

[0024] Step 161, respectively calculating the time required to complete any running action category;

[0025] Step 162: Sum the time required to complete all running action categories of a single production task to obtain the single task running time.

[0026] In combination with the fourth possible implementation manner of the present invention, in a fifth possible implementation manner, step 100 further includes:

[0027] Step 170, calculating the number of times the production task is completed per unit time;

[0028] Step 180: Calculate the handling load per unit time of the RGV vehicle according to the number of completed tasks.

[0029] In a second aspect, a glass production workshop planning system based on RGV trolley load adopts the planning method described in the first aspect, including:

[0030] Control unit;

[0031] accounting unit;

[0032] Planning and design unit;

[0033] The calculation unit is used to calculate the transport load of the RGV trolley per unit time according to the transport parameters, and transmit the transport load to the control unit;

[0034] The planning and design unit is used to perform secondary planning and design of the glass production workshop according to the control unit instruction and the existing layout information, and output design image information;

[0035] The transport parameters include the transport node layout and the time to complete a single transport task.

[0036] In conjunction with the planning system described in the second aspect, in a first possible implementation manner, the accounting unit includes:

[0037] A first acquisition unit;

[0038] Detection unit;

[0039] A first judgment unit;

[0040] The first acquisition unit is used for:

[0041] Obtain the node distribution of all production nodes that complete a single handling task, use the node distribution to obtain the glass material process route that connects all the production nodes in series, decompose the glass material process route, and obtain all the travel routes of the RGV trolley to complete the handling task;

[0042] The detection unit is used for:

[0043] Detecting the traveling speed information of the RGV trolley and transmitting the traveling speed information to the judgment unit;

[0044] The first judgment unit is used to judge the running action category of the RGV trolley according to the speed information;

[0045] The operation action categories include:

[0046] Loading and unloading, acceleration and deceleration, maximum speed, and empty running.

[0047] In combination with the first possible implementation manner of the second aspect, in a second possible implementation manner, the accounting unit further includes:

[0048] A second judgment unit;

[0049] Computational unit;

[0050] The second judgment unit is used to obtain the travel distribution of the running action category in the walking route;

[0051] The computing unit is used for:

[0052] The time required to complete all operating action categories of a single production task is summed up to obtain the single task running time, and the handling load per unit time of the RGV trolley is calculated based on the number of completed tasks.

[0053] In combination with the second possible implementation manner of the second aspect, in a third possible implementation manner, the accounting unit further includes:

[0054] A second acquisition unit;

[0055] The second acquisition unit is used to acquire the number of times the production task is completed within a unit time.

[0056] The present invention is implemented in a glass production workshop planning method and system based on the RGV trolley load. The RGV trolley is detected to obtain the handling parameters, and the handling parameters are used to calculate the RGV trolley's handling load per unit time. The glass production workshop is replanned according to the handling load and a planning image is output. The congestion of the storage device caused by the increase in production capacity is adjusted accordingly, and the layout in the workshop is optimized, and the smoothness of STK transportation is improved to achieve more efficient and energy-saving production, increase production capacity, and reduce costs; avoid congestion of the storage device STK due to increased production capacity, thereby affecting equipment production and reducing abnormal time. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0058] Figure 1 It is a schematic diagram of a first embodiment of a glass production workshop planning method based on RGV trolley load in the present invention;

[0059] Figure 2 It is a schematic diagram of a second embodiment of a glass production workshop planning method based on RGV trolley load in the present invention;

[0060] Figure 3 It is a schematic diagram of a third embodiment of a glass production workshop planning method based on RGV trolley load in the present invention;

[0061] Figure 4 It is a schematic diagram of a fourth embodiment of a glass production workshop planning method based on RGV trolley load in the present invention;

[0062] Figure 5 It is a schematic diagram of a fifth embodiment of a glass production workshop planning method based on RGV trolley load in the present invention;

[0063] Figure 6 It is a schematic diagram of a sixth embodiment of a glass production workshop planning method based on RGV trolley load in the present invention;

[0064] Figure 7 It is a schematic diagram of the internal handling of the storage container STK in the present invention;

[0065] Figure 8This is a schematic diagram of the distribution of glass production workshops in the present invention;

[0066] Fig. 9 It is a schematic diagram of a first embodiment of a glass production workshop planning system based on RGV trolley load in the present invention;

[0067] Fig.10 It is a schematic diagram of a second embodiment of a glass production workshop planning system based on RGV trolley load in the present invention;

[0068] The names of the parts indicated by the numbers in the accompanying drawings are: 10 - control unit, 20 - accounting unit, 30 - planning and design unit, 21 - first acquisition unit, 22 - detection unit, 23 - first judgment unit, 24 - second judgment unit, 25 - calculation unit, 26 - second acquisition unit. DETAILED DESCRIPTION

[0069] The following will be combined with the accompanying drawings in the invention to clearly and completely describe the technical solutions in the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments in the present invention, other embodiments obtained by ordinary technicians in this field without creative work are all within the scope of protection of the present invention.

[0070] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0071] During the distribution process in the glass production workshop, the operation of the RGV cart will produce a part of empty running. On the other hand, due to poor workshop planning, congestion often occurs when the production capacity is increased, which reduces production efficiency and increases production costs.

[0072] Aiming at the above problems, a glass production workshop planning method and system based on RGV trolley load is proposed.

[0073] First, as Figure 1 , Figure 1It is a schematic diagram of the first embodiment of the glass production workshop planning method based on the RGV trolley load in the present invention. A glass production workshop planning method based on the RGV trolley load includes: step 100, using the handling parameters to calculate the RGV trolley's handling load per unit time; step 200, secondary planning of the glass production workshop according to the handling load and output of the planning image; wherein the handling parameters include the layout of the handling nodes and the time to complete a single handling task. By detecting the RGV trolley, the handling parameters are obtained, and the handling parameters are used to calculate the RGV trolley's handling load per unit time, and the glass production workshop is secondary planned according to the handling load and the planning image is output; accordingly, the congestion of the storage device caused by the increase in production capacity is adjusted, and then the layout in the workshop is optimized, and the smoothness of STK handling is improved, so as to achieve more efficient and energy-saving production, increase production capacity, and reduce costs; avoid congestion of the storage device STK due to the increase in production capacity, thereby affecting the production of equipment and reducing abnormal time.

[0074] Preferably, if Figure 2 , Figure 2 It is a schematic diagram of the second embodiment of the glass production workshop planning method based on the RGV trolley load in the present invention, and step 100 includes: step 110, obtaining the node distribution of all production nodes that complete a single handling task; step 120, using the node distribution to obtain the glass material process route of all production nodes in series.

[0075] like Figure 7 and 8 , Figure 7 This is a schematic diagram of the internal handling of the storage container STK in the present invention. Figure 8 It is a distribution diagram of the glass production workshop in the present invention. The glass production workshop includes nodes such as entrance, storage, production equipment, material storage, and exit. Often, to complete a production process, all nodes need to be connected in series, that is, the RGV car needs to traverse all nodes in a single task.

[0076] Preferably, if Figure 3 , Figure 3 It is a schematic diagram of the third embodiment of the glass production workshop planning method based on the RGV trolley load in the present invention. Step 100 also includes: Step 130, decomposing the glass material process route to obtain all the walking routes of the RGV trolley to complete the handling task; Step 140, according to the walking route, obtaining the operating action category of the RGV trolley to complete all the walking routes; wherein the operating action categories include: loading and unloading, acceleration and deceleration, maximum speed, and empty running.

[0077] In the glass production workshop, after the material is fed and cleaned, the RGV cart will transport the cassette storing the glass (hereinafter referred to as CST) to the transfer station (hereinafter referred to as OHS), and then transfer it to the storage device (hereinafter referred to as STK) where the next process equipment (hereinafter referred to as EQ) is located. This cycle continues until the production of a single piece of glass is completed. After the production of a single piece of glass is completed, the RGV cart will transport the CST from the STK to the corridor and send it to the bonding workshop for bonding.

[0078] Generally, a single complete transport of the RGV trolley requires two transports. The first transport is from the RGV trolley to the EQP, and the second transport is from the RGV trolley to the OUT port. Since the RGV trolley cycle is faster than the equipment EQP cycle, the CST can only be placed in the storage position before being sent to the EQP. Since the RGV trolley is not at the required CST transport position when receiving the command, a period of empty running will be generated, which is 2 / 3 of the STK length.

[0079] Preferably, if Figure 4 , Figure 4 It is a schematic diagram of the fourth embodiment of the glass production workshop planning method based on the RGV trolley load in the present invention. Step 100 also includes: step 150, obtaining the travel distribution of any operating action category in the walking route; step 160, calculating the time to complete all walking routes of a single production task according to the travel distribution.

[0080] Therefore, the RGV trolley actually needs four moves to complete a complete transport. The first is to run idly for 2 / 3S after receiving the command to pick up the CST from the IN port and put it in the storage position; the second is to run idly for 2 / 3S after receiving the command to move the CST from the storage position to the EQP; the third is to run idly for 2 / 3S after receiving the command to move the CST that has finished the goods on the EQP to the storage position; the fourth is to run idly for 2 / 3S after receiving the command to move the CST in the storage position to the OUT port.

[0081] Each of the four transfers includes four acceleration and deceleration times and one loading and unloading time. By detecting the speed of the RGV trolley, the T required to reach Vmax and the movement S within this T are calculated.

[0082] Single task time = T1*8+16*T2+T3*4+T4 (T1 = loading and unloading time; T2 = acceleration and deceleration time; T3 = 2 / 3 of the idle running time; T4 = the time of transporting at the maximum speed.)

[0083] Preferably, if Figure 5 , Figure 5 It is a schematic diagram of the fifth embodiment of the glass production workshop planning method based on the RGV trolley load in the present invention, and step 160 includes: step 161, respectively calculating the time required to complete any operating action category; step 162, summing the time required to complete all operating action categories of a single production task to obtain the single task running time.

[0084] Preferably, if Figure 6 , Figure 6 It is a schematic diagram of the sixth embodiment of the glass production workshop planning method based on the RGV trolley load in the present invention, and step 100 also includes: step 170, calculating the number of times the production tasks are completed per unit time; step 180, calculating the handling load of the RGV trolley per unit time according to the number of times the tasks are completed.

[0085] Second, as Fig. 9 , Fig. 9 It is a schematic diagram of the first embodiment of the glass production workshop planning system based on the RGV trolley load in the present invention, a glass production workshop planning system based on the RGV trolley load, adopts the planning method of the first aspect, including a control unit 10, a calculation unit 20, and a planning and design unit 30; the calculation unit 20 is used to calculate the handling load of the RGV trolley per unit time according to the handling parameters, and transmit the handling load to the control unit 10; the planning and design unit 30 is used to perform secondary planning and design of the glass production workshop according to the instructions of the control unit 10 and the existing layout information, and output the design image information; wherein the handling parameters include the handling node layout and the time to complete a single handling task.

[0086] Preferably, if Fig.10 , Fig.10 It is a schematic diagram of the second embodiment of the glass production workshop planning system based on the RGV trolley load in the present invention; the accounting unit 20 includes a first acquisition unit 21, a detection unit 22, and a first judgment unit 23; the first acquisition unit 21 is used to: obtain the node distribution of all production nodes that complete a single handling task, use the node distribution to obtain the glass material process route of all production nodes in series, decompose the glass material process route, and obtain all the walking routes of the RGV trolley to complete the handling task;

[0087] The detection unit 22 is used to detect the travel speed information of the RGV trolley and transmit the travel speed information to the judgment unit; the first judgment unit 23 is used to judge the operating action category of the RGV trolley according to the speed information; wherein the operating action categories include: loading and unloading, acceleration and deceleration, maximum speed, and idling.

[0088] Preferably, the accounting unit 20 also includes a second judgment unit 24 and a calculation unit 25; the second judgment unit 24 is used to obtain the travel distribution of the operating action categories in the walking route; the calculation unit 25 is used to: sum up the time required to complete all operating action categories of a single production task, obtain the running time of a single task, and calculate the handling load of the RGV trolley per unit time according to the number of completed tasks.

[0089] Preferably, the accounting unit 20 further includes: a second acquisition unit 26; the second acquisition unit 26 is used to acquire the number of times the production task is completed within a unit time.

[0090] The present invention is implemented in a glass production workshop planning method and system based on the RGV trolley load. The RGV trolley is detected to obtain the handling parameters, and the handling parameters are used to calculate the RGV trolley's handling load per unit time. The glass production workshop is replanned according to the handling load and a planning image is output. The congestion of the storage device caused by the increase in production capacity is adjusted accordingly, and the layout in the workshop is optimized, and the smoothness of STK transportation is improved to achieve more efficient and energy-saving production, increase production capacity, and reduce costs; avoid congestion of the storage device STK due to increased production capacity, thereby affecting equipment production and reducing abnormal time.

[0091] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A glass production workshop planning method based on RGV trolley load, characterized in that: include: Step 100, using the transport parameters to calculate the load carried by the RGV vehicle per unit time; Step 200, performing secondary planning of the glass production workshop according to the handling load and outputting a planning image; The transport parameters include the transport node layout and the time to complete a single transport task; The step 100 comprises: Step 110, obtaining the node distribution of all production nodes that complete a single transport task; Step 120, using the node distribution to obtain a glass material process route that connects all the production nodes in series; The step 100 further includes: Step 130, decomposing the process route of the glass material to obtain all the travel routes of the RGV vehicle to complete the transportation task; Step 140: According to the walking route, the running action categories of the RGV vehicle to complete all the walking routes are obtained; The operation action categories include: Loading and unloading, acceleration and deceleration, maximum speed, and empty running; The step 100 further includes: Step 150, obtaining the travel distribution of any of the running action categories in the walking route; Step 160: Calculate the time required to complete all travel routes of a single production task based on the travel distribution.

2. The glass production workshop planning method based on RGV trolley load according to claim 1 is characterized in that: The step 160 includes: Step 161, respectively calculating the time required to complete any running action category; Step 162: Sum the time required to complete all running action categories of a single production task to obtain the single task running time.

3. The glass production workshop planning method based on RGV trolley load according to claim 2 is characterized in that: The step 100 further includes: Step 170, calculating the number of times the production task is completed per unit time; Step 180: Calculate the handling load per unit time of the RGV vehicle according to the number of completed tasks.

4. A glass production workshop planning system based on RGV trolley load, using the planning method described in any one of claims 1 to 3, comprising: Control unit; accounting unit; Planning and design unit; The calculation unit is used to calculate the transport load of the RGV trolley per unit time according to the transport parameters, and transmit the transport load to the control unit; The planning and design unit is used to perform secondary planning and design of the glass production workshop according to the control unit instruction and the existing layout information, and output design image information; The transport parameters include the transport node layout and the time to complete a single transport task; The accounting unit comprises: A first acquisition unit; Detection unit; A first judgment unit; The first acquisition unit is used for: Obtain the node distribution of all production nodes that complete a single handling task, use the node distribution to obtain the glass material process route that connects all the production nodes in series, decompose the glass material process route, and obtain all the travel routes of the RGV trolley to complete the handling task; The detection unit is used for: Detecting the traveling speed information of the RGV trolley and transmitting the traveling speed information to the judgment unit; The first judgment unit is used to judge the running action category of the RGV trolley according to the speed information; The operation action categories include: Loading and unloading, acceleration and deceleration, maximum speed, and empty running; The accounting unit also includes: A second judgment unit; Computational unit; The second judgment unit is used to obtain the travel distribution of the running action category in the walking route; The computing unit is used for: The time required to complete all operating action categories of a single production task is summed up to obtain the single task running time, and the handling load per unit time of the RGV trolley is calculated based on the number of completed tasks.

5. The glass production workshop planning system based on RGV trolley load according to claim 4 is characterized in that: The accounting unit also includes: A second acquisition unit; The second acquisition unit is used to acquire the number of times the production task is completed within a unit time.