A method, device, equipment and storage medium for load scheduling of energy storage equipment

By obtaining the remaining power and loss level of energy storage equipment, determining the actual power supply and generating a scheduling plan, the problem of low power supply accuracy of energy storage equipment is solved, and more efficient load dispatching and grid stability are achieved.

CN114899849BActive Publication Date: 2024-10-22DONGXU NEW ENERGY INVESTMENT CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202210562618.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-23
Publication Date
2024-10-22
Estimated Expiration
2042-05-23

AI Technical Summary

Technical Problem

Existing load dispatching methods for energy storage equipment have low power supply accuracy, are prone to supply shortages, and are difficult to meet the stable operation needs of the power grid.

Method used

By obtaining the remaining power and consumption level of the energy storage device, the actual power supply of each device is determined, and multiple scheduling plans are generated based on the power to be dispatched and regional demand, and the most appropriate target energy storage device is selected for power supply to ensure the power supply. Accurate scheduling.

Benefits of technology

It improves the accuracy of load dispatching of energy storage equipment, avoids insufficient power, and enhances the stability of the power grid and the reliability of power supply.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114899849B_ABST
    Figure CN114899849B_ABST
Patent Text Reader

Abstract

The present application relates to the field of load scheduling, and provides a method, apparatus, device and storage medium for load scheduling of energy storage equipment, wherein the method comprises: obtaining a load scheduling request at a first moment, and obtaining the remaining power and the degree of consumption of each idle energy storage device, wherein the load scheduling request comprises: the power to be scheduled and the area to be scheduled; determining the actual supply power of each idle energy storage device according to the remaining power and the degree of consumption; determining multiple scheduling schemes according to the power to be scheduled and the actual supply power of each idle energy storage device, wherein the scheduling scheme comprises at least one target energy storage device among multiple idle storage devices; determining a target scheduling scheme from multiple scheduling schemes according to the area to be scheduled and / or the number of target energy storage devices in the scheduling scheme and / or the average degree of consumption of the target energy storage devices in the scheduling scheme, and generating a load scheduling instruction; and sending the load scheduling instruction to all target energy storage devices in the target scheduling scheme.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of load scheduling, and in particular to a load scheduling method, device, equipment and storage medium for energy storage equipment. Background Art

[0002] Power dispatching is an effective management method to ensure the safe and stable operation of the power grid, reliable external power supply, and orderly progress of various power production work. With the intelligentization of life, people's demand for electricity is increasing, power dispatching faces new challenges, and the safety and stability of power grid operation are under great threat. At present, in order to reduce the power load, the commonly used method is to determine the current power dispatched to the area in the time period according to the average power consumption in the historical process. However, with the improvement of life, the use of various intelligent electronic devices, electric vehicle charging, and the use of high-power household appliances are prone to power load, which in turn affects the normal work and life of users.

[0003] In order to solve the problem of electricity load, relevant technologies use energy storage equipment to supplement electricity and use energy storage equipment to supply power according to demand. However, the power supply accuracy is low and it is still easy to have a situation where supply exceeds demand.

[0004] Therefore, how to provide a solution to the above technical problems is a problem that those skilled in the art need to solve at present. Summary of the invention

[0005] In order to improve the accuracy of load scheduling of energy storage equipment, the present application provides a load scheduling method, device, equipment and storage medium for energy storage equipment.

[0006] In a first aspect, the present application provides a load scheduling method for an energy storage device, which adopts the following technical solution:

[0007] A load scheduling method for an energy storage device, comprising:

[0008] Obtaining a load dispatch request at a first moment, and obtaining the remaining power and consumption degree of each idle energy storage device, wherein the load dispatch request includes: the power to be dispatched and the area to be dispatched;

[0009] Determine the actual supply power of each idle energy storage device according to the remaining power and the consumption degree;

[0010] Determine multiple scheduling schemes according to the amount of electricity to be scheduled and the actual amount of electricity supplied by each idle energy storage device, wherein the scheduling schemes include at least one target energy storage device among the multiple idle storage devices;

[0011] Determine a target scheduling scheme from a plurality of scheduling schemes according to the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of wear of the target energy storage devices in the scheduling scheme, and generate a load scheduling instruction;

[0012] The load scheduling instruction is sent to all target energy storage devices in the target scheduling scheme, so that the target energy storage devices supply power according to the load scheduling instruction.

[0013] By adopting the above technical solution, since the storage capacity of the energy storage device is consumed as the number of charge and discharge times of the energy storage device increases, this solution obtains the remaining power and consumption degree of each idle energy storage device to determine the actual supply power of the energy storage device, and then determines multiple scheduling schemes based on the power to be scheduled and the actual supply power, thereby ensuring the accuracy of determining the scheduling scheme based on the power to be scheduled, avoiding the occurrence of insufficient power caused by scheduling due to power consumption of the energy storage device, and can determine the target scheduling scheme from multiple scheduling schemes based on the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average consumption degree of the target energy storage device in the scheduling scheme, and can determine a scheme that meets the needs according to actual needs.

[0014] In another possible implementation, the load scheduling request is a request sent from a node, and the load scheduling method further includes:

[0015] Send communication requests to all energy storage devices according to the preset cycle,

[0016] Obtaining feedback information from the energy storage device and determining the total amount of the feedback information;

[0017] Determine whether the total amount is less than a preset total amount threshold;

[0018] If it is not less than the preset total amount threshold, it is determined that the scheduling operation is normal;

[0019] If it is less than the preset total amount threshold, a scheduling operation failure is determined, and a new scheduling node is determined according to the set rules, wherein the new scheduling node is used to perform subsequent load scheduling; a replacement request including parameter information of the new scheduling node is sent to all slave nodes.

[0020] By adopting the above technical solution, the electronic device corresponding to the scheduling node needs to determine whether the scheduling operation is normal according to the preset period. When the scheduling operation fails, a new scheduling node is determined according to the set rules, which ensures the normal scheduling and improves the stability of the scheduling.

[0021] In another possible implementation, the new scheduling node is determined according to a set rule;

[0022] Determine the new scheduling node according to the set identification order of each node;

[0023] Or, obtain election information sent by each slave node, wherein the election information includes a selected target node; and determine the target node with the largest number of selections from all the target nodes as a new scheduling node.

[0024] By adopting the above technical solution, a new scheduling node is determined according to the identification order or the number of times it is selected. The method is simple and easy to operate.

[0025] In another possible implementation, multiple scheduling schemes are determined according to the to-be-scheduled power and the actual supplied power of each idle energy storage device, including:

[0026] Identify idle energy storage devices whose depletion level is less than a preset depletion level threshold;

[0027] Acquire environmental information of idle energy storage devices whose consumption level is less than a preset consumption level threshold;

[0028] determining a failure occurrence rate based on the environmental information;

[0029] Multiple scheduling schemes are determined according to the to-be-scheduled power, the actual supplied power of idle energy storage devices whose consumption level is less than a preset consumption level threshold, and the failure occurrence rate.

[0030] By adopting the above technical solution, this solution determines the scheduling plan from the idle energy storage devices with a wear level less than the preset threshold, the failure rate determined according to the environmental information and the amount of electricity to be scheduled, thereby ensuring the stability of the plan execution and avoiding the problem of power supply failure due to energy storage device failure during the scheduling process.

[0031] In another possible implementation, the environmental information includes an environmental image, weather information, and an environmental temperature, and determining the fault occurrence rate according to the environmental information includes:

[0032] Determine a target object in the current environment according to the environment image;

[0033] The failure occurrence rate is determined according to the ambient temperature and / or weather information and / or the target object.

[0034] By adopting the above technical solution, the present solution determines the fault occurrence rate based on the ambient temperature and / or weather information and / or the target object, thereby improving the accuracy of determining the fault occurrence rate.

[0035] In another possible implementation manner, before obtaining the load scheduling request at the first moment, the method further includes:

[0036] Obtaining power consumption information within a time range corresponding to a second moment of the area to be scheduled; wherein the second moment is earlier than the first moment;

[0037] Using historical power consumption information to perform load forecasting on the power consumption information, and outputting forecasting results;

[0038] When the prediction result is power load, a load report and load prompt information are generated, and the load report and the load prompt information are displayed on a display device.

[0039] By adopting the above technical solution, this solution uses the historical power consumption information collected in advance to predict the current load situation, thereby improving the prediction efficiency and avoiding the problems of low efficiency and high cost caused by manual monitoring; when power load occurs, the generated load report and load prompt information will be displayed on the display device to provide timely load reminders.

[0040] In another possible implementation, before obtaining the remaining power and consumption degree of each idle energy storage device, the method further includes:

[0041] When the energy storage device is scheduled, the energy storage device information table is updated, and the energy storage device information table includes: the waiting time of all energy storage devices;

[0042] An idle energy storage device corresponding to the first moment is determined according to the waiting time.

[0043] By adopting the above technical solution, the present solution updates the energy storage device information table in real time, so as to determine in advance the idle energy storage device corresponding to the first moment according to the time when the energy storage device is ready for use, thereby avoiding the situation where only the idle energy storage device at the current moment is used when the power demand is large, resulting in insufficient power supply, caused by scheduling based only on the idle energy storage device at the current moment, wherein the current moment is not greater than the first moment.

[0044] In a second aspect, the present application provides a load scheduling device for an energy storage device, which adopts the following technical solution:

[0045] A load dispatching device for energy storage equipment, comprising:

[0046] An acquisition module is used to acquire a load dispatch request at a first moment, and to acquire the remaining power and consumption degree of each idle energy storage device, wherein the load dispatch request includes: the power to be dispatched and the area to be dispatched;

[0047] A real supply power determination module, used to determine the real supply power of each idle energy storage device according to the remaining power and the depletion degree;

[0048] A scheduling scheme determination module, used to determine multiple scheduling schemes according to the amount of electricity to be scheduled and the actual supply amount of each idle energy storage device, wherein the scheduling scheme includes at least one target energy storage device among the multiple idle storage devices;

[0049] A target scheduling scheme determination module is used to determine a target scheduling scheme from multiple scheduling schemes according to the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of wear of the target energy storage devices in the scheduling scheme, and generate a load scheduling instruction

[0050] The scheduling instruction sending module is used to send the load scheduling instruction to all target energy storage devices in the target scheduling scheme, so that the target energy storage devices supply power according to the load scheduling instruction.

[0051] In a third aspect, the present application provides an electronic device, which adopts the following technical solution:

[0052] An electronic device, comprising:

[0053] at least one processor;

[0054] Memory;

[0055] At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute a load scheduling method for an energy storage device shown in any possible implementation of the first aspect.

[0056] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution:

[0057] A computer-readable storage medium includes: a computer program that can be loaded and executed by a processor to implement a load scheduling method for an energy storage device shown in any possible implementation of the first aspect.

[0058] In summary, the present application includes at least one of the following beneficial technical effects:

[0059] 1. By adopting the above technical scheme, since the storage capacity of the energy storage device is consumed as the number of charge and discharge times of the energy storage device increases, this scheme obtains the remaining power and consumption degree of each idle energy storage device to determine the actual supply power of the energy storage device, and then determines multiple scheduling schemes based on the power to be scheduled and the actual supply power, thereby ensuring the accuracy of determining the scheduling scheme based on the power to be scheduled, avoiding the occurrence of insufficient power caused by scheduling due to power consumption of the energy storage device, and can determine the target scheduling scheme from multiple scheduling schemes based on the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average consumption degree of the target energy storage device in the scheduling scheme, and can determine a scheme that meets the needs according to actual needs.

[0060] 2. The electronic equipment corresponding to the scheduling node needs to determine whether the scheduling operation is normal according to the preset cycle. When the scheduling operation fails, a new scheduling node is determined according to the set rules to ensure the normal scheduling and improve the stability of the scheduling. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] Figure 1 A schematic diagram of a flow chart of a load scheduling method for an energy storage device provided in an embodiment of the present application;

[0062] Figure 2 A schematic diagram of the structure of a load scheduling device for an energy storage device provided in an embodiment of the present application;

[0063] Figure 3 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0064] The following is combined with Figure 1 -Attached Figure 3 This application is described in further detail.

[0065] After reading this specification, those skilled in the art may make non-creative modifications to this embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of this application.

[0066] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0067] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.

[0068] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.

[0069] The embodiment of the present application provides a load scheduling method for energy storage equipment, which is executed by an electronic device, and the electronic device can be a server or a terminal device, wherein the server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides cloud computing services. The terminal device can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc., but is not limited thereto. The terminal device and the server can be directly or indirectly connected via wired or wireless communication, and the embodiment of the present application does not limit this. Figure 1 As shown, the method includes:

[0070] Step S110: obtaining a load dispatch request at a first moment, and obtaining the remaining power and consumption degree of each idle energy storage device;

[0071] The load dispatch request includes: the amount of electricity to be dispatched and the area to be dispatched.

[0072] The embodiments of the present application implement load scheduling of electricity. Specifically, a client is provided on the electronic device, and the client is used to implement load scheduling of electricity. The client on the electronic device can monitor the supported power supply area. The specific monitoring content includes collected electricity consumption information, monitoring of various abnormal electricity consumption information, analysis and display.

[0073] Regarding the method of obtaining load scheduling requests, in one achievable implementation, it may include: the electronic device monitors power consumption information in real time, and when a power overload is detected, the power to be scheduled is automatically predicted, and a load scheduling request is generated.

[0074] In another achievable implementation, the scheduling system includes a scheduling node, which corresponds to an electronic device and multiple slave nodes, each slave node corresponds to a power consumption area, and each slave node performs real-time monitoring of the power consumption area under its jurisdiction. Correspondingly, a load scheduling request acquisition method may include: acquiring a load scheduling request sent by a slave node, wherein the load scheduling request is generated when each slave node monitors the power consumption information of the area in real time and determines that power scheduling is required based on the allocated power and power consumption information.

[0075] In another achievable implementation, the method for obtaining a load scheduling request may include: determining a time to be scheduled and an amount of power to be scheduled according to historical power consumption information, and automatically generating a load scheduling request when the time to be scheduled is reached.

[0076] In the embodiment of the present application, multiple energy storage devices are provided, and the types of specific energy storage devices include but are not limited to: batteries, supercapacitors, and photovoltaic cells. It is understandable that the performance parameters of each energy storage device include the degree of consumption, power, efficiency, remaining power, number of charging cycles, status label, ID label, and of course, state parameters, which include but are not limited to the state of charge; at the same time, the system detects the changes of the energy storage device in real time and updates the performance parameters in time to ensure that the performance parameters are effective data. Among them, multiple energy storage devices include energy storage devices in working state and energy storage devices in idle state. In a feasible situation, an ID label is set for each energy storage device, and the ID label uniquely represents the energy storage device. The energy storage device can also be quickly located according to the ID label. At the same time, the status label can be specifically 0 for working state and 1 for idle state, which is convenient for quickly determining the current state of the energy storage device.

[0077] It is understandable that the embodiment of the present application needs to collect statistics on the remaining power and consumption level of each idle energy storage device. Specifically, the performance parameters of the idle energy storage device may be read, and the performance parameters may be analyzed to obtain the remaining power and consumption level.

[0078] Furthermore, the process of obtaining the degree of consumption of each idle energy storage device includes:

[0079] Obtain the number of charge and discharge times of the idle energy storage device; determine the degree of wear of the idle energy storage device according to the number of charge and discharge times.

[0080] This embodiment uses the number of charge and discharge times of the idle energy storage device to determine its wear degree. The specific system stores the corresponding relationship between the number of charge and discharge times and the wear degree, and automatically determines the wear degree according to the number of charge and discharge times.

[0081] Step S120: determining the actual power supply of each idle energy storage device according to the remaining power and the degree of consumption.

[0082] When the energy storage device is used frequently, there will be losses, resulting in a difference between the displayed power, i.e., the remaining power, and the final usable power. Therefore, in order to ensure the accuracy of load scheduling, this embodiment needs to determine the actual available power of the idle energy storage device based on the remaining power and the degree of consumption of the energy storage device.

[0083] Specifically, the method of determining the actual power supply may include:

[0084] Determine the adjustment value according to the correspondence between the preset wear degree and the adjustment value;

[0085] The remaining power is adjusted according to the adjustment value to determine the actual supply power;

[0086] The corresponding relationship may be determined based on empirical values ​​or wear tests.

[0087] Step S130, determining multiple scheduling schemes according to the amount of power to be scheduled and the actual amount of power supplied by each idle energy storage device;

[0088] The scheduling scheme includes at least one target energy storage device among a plurality of idle storage devices.

[0089] It is understandable that multiple scheduling schemes that can meet the power to be scheduled can be determined based on the actual power supply of multiple idle energy storage devices. This embodiment determines the scheduling scheme based on the power to be scheduled and the actual power supply of each idle energy storage device to ensure normal power supply.

[0090] Furthermore, this embodiment sets a surplus coefficient, and determines the target energy storage device according to the amount of electricity to be dispatched, the surplus coefficient, and the actual supply electricity of the idle energy storage device, so as to ensure that the final dispatched electricity is surplus, avoid actual emergencies, and ensure the normal supply of electricity.

[0091] Step S140: determining a target scheduling scheme from multiple scheduling schemes according to the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of wear of the target energy storage devices in the scheduling scheme, and generating a load scheduling instruction;

[0092] The method for determining the target scheduling scheme from multiple initial scheduling schemes in this embodiment can be based on the number of energy storage devices in each scheduling scheme, and / or, based on the average degree of wear of each energy storage device in each scheduling scheme, and / or, based on the location information of each energy storage device in the scheduling scheme and the relative position of the area to be scheduled; this embodiment is no longer limited, as long as the purpose of this embodiment can be achieved.

[0093] Therefore, in an achievable implementation, determining a target scheduling scheme from multiple scheduling schemes may include: based on the number of energy storage devices in each scheduling scheme, determining the scheduling scheme with the least number as the target scheduling scheme. The fewer the number of energy storage devices, the higher the actual power supply of the corresponding energy storage devices, which reduces the number of energy storage devices to be scheduled and reduces the supervision cost after scheduling.

[0094] In another achievable implementation, determining a target scheduling scheme from a plurality of scheduling schemes includes:

[0095] Determine the matching results of multiple scheduling schemes and the area to be scheduled;

[0096] According to the matching results, the target scheduling plan is determined.

[0097] Specifically, the location information of all energy storage devices in multiple scheduling schemes is determined, and then the distance is matched with the area to be scheduled according to the location information to determine the matching result, wherein the matching result includes: the proportion of target energy storage devices within the set range of the area to be scheduled among all target energy storage devices, and the scheduling scheme is determined according to the matching result, which may be to determine the scheduling scheme with the highest proportion as the target scheduling scheme

[0098] It can be seen that the energy storage devices provided in this embodiment can be energy storage devices dispersed in various areas. When determining the scheduling plan, the energy storage devices in the area to be scheduled are given priority to ensure the supply of each area.

[0099] In another achievable implementation, determining a target scheduling scheme from a plurality of scheduling schemes includes:

[0100] Determine the matching degree between all energy storage devices in a plurality of scheduling schemes and the area to be scheduled, and determine a first value according to the matching degree;

[0101] Determine the number of target energy storage devices in the scheduling plan, and determine a second value according to the number;

[0102] Determine the average value of the degree of wear of the target energy storage device in the scheduling plan, and determine the third value according to the average value of the degree of wear;

[0103] Determine a total value according to the first value, the second value, and the third value;

[0104] The target scheduling scheme is determined according to the total value of all scheduling schemes.

[0105] Step S150: Send a load scheduling instruction to all target energy storage devices in the target scheduling scheme, so that the target energy storage devices supply power according to the load scheduling instruction.

[0106] All energy storage devices establish communication connections with electronic devices in advance to ensure the normal transmission of information. At the same time, the system will monitor the information transmission between the two in real time to ensure that no information transmission failure occurs.

[0107] The load dispatch instruction includes the information of the target energy storage device and the power supply time to ensure that the target energy storage device can supply power normally.

[0108] Based on the above technical solution, as the storage capacity of the energy storage device is consumed as the number of charge and discharge times of the energy storage device increases, this solution obtains the remaining power and consumption degree of each idle energy storage device to determine the actual supply power of the energy storage device, and then determines multiple scheduling schemes based on the power to be scheduled and the actual supply power, thereby ensuring the accuracy of determining the scheduling scheme based on the power to be scheduled, avoiding the occurrence of insufficient power caused by scheduling due to power consumption of the energy storage device, and can determine the target scheduling scheme from multiple scheduling schemes based on the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average consumption degree of the target energy storage devices in the scheduling scheme, and can determine a scheme that meets the needs based on actual needs.

[0109] Furthermore, the load scheduling request is a request sent from the node, and the load scheduling method further includes:

[0110] Send communication requests to all energy storage devices according to the preset cycle,

[0111] Obtain feedback information from the energy storage device and determine the total amount of feedback information;

[0112] Determine whether the total amount is less than the preset total amount threshold;

[0113] If it is not less than the preset total amount threshold, it is determined that the scheduling operation is normal;

[0114] If it is less than the preset total amount threshold, a scheduling operation failure is determined, and a new scheduling node is determined according to the set rules, where the new scheduling node is used to perform subsequent load scheduling; a replacement request including parameter information of the new scheduling node is sent to all slave nodes.

[0115] It can be understood that the construction of the load scheduling method for the energy storage device of the embodiment of the present application includes: an electronic device, which serves as a scheduling node; multiple slave nodes, wherein each node communicates with each other, and each node communicates with the energy storage device. This embodiment uses the scheduling node as the scheduling center to ensure stable and efficient operation of the scheduling, and avoids repeated scheduling and unreasonable scheduling caused by simultaneous scheduling of multiple nodes.

[0116] Specifically, in this embodiment, the electronic device will periodically communicate with the energy storage device to determine whether the communication is normal so that the scheduling operation can be performed normally. Specifically, when the total amount of feedback information is less than the preset total amount threshold, it is determined that the scheduling operation fails and there is a probability that the scheduling cannot be performed normally. Therefore, a new scheduling node is determined according to the set rules to ensure the normal operation of the scheduling work.

[0117] It can be seen that the electronic device corresponding to the scheduling node needs to determine whether the scheduling operation is normal according to the preset period. When the scheduling operation fails, a new scheduling node is determined according to the set rules, which ensures the normal scheduling and improves the stability of the scheduling.

[0118] Further, a new scheduling node is determined according to the set rules;

[0119] Determine the new scheduling node according to the set identification order of each node;

[0120] Or, obtain the election information sent by each slave node, the election information including the selected target node; determine the target node with the largest number of selections from all the target nodes as the new scheduling node.

[0121] In this embodiment, each node is set with an identification order according to the order of participating in the scheduling, and the new scheduling node is determined according to the identification order of each node. For example, if the identification of each node is set to 0, 1, 2...n, and the identification information of the current scheduling node is 0, the identification information of the determined new scheduling node is 1; if the identification information of the current scheduling node is 1, the identification information of the determined new scheduling node is 2.

[0122] Or, in this embodiment, according to the principle of fairness, each node is required to be elected, and then according to the final number of elections, the target node with the most elections is determined as the new scheduling node.

[0123] Furthermore, according to the amount of electricity to be dispatched and the actual amount of electricity supplied by each idle energy storage device, multiple dispatching schemes are determined, including:

[0124] Identify idle energy storage devices whose depletion level is less than a preset depletion level threshold;

[0125] Obtaining environmental information of idle energy storage devices whose depletion level is less than a preset depletion level threshold;

[0126] Determine the failure rate based on environmental information;

[0127] Multiple scheduling plans are determined based on the amount of power to be scheduled, the actual supply power of idle energy storage devices whose consumption level is less than a preset consumption level threshold, and the failure rate.

[0128] Among them, this embodiment is provided with a preset loss degree threshold value, and energy storage devices exceeding the threshold value are prone to power supply failure. The loss degree of each idle energy storage device is first determined, and the idle energy storage devices with a loss degree not less than the preset loss degree threshold value are eliminated. At the same time, the environment also has a certain impact on the energy storage device. Therefore, according to the power to be scheduled, the actual supply power of the idle energy storage devices with a loss degree less than the preset loss degree threshold value, and the failure rate, multiple scheduling schemes are determined, which ensures the stability of the execution of the scheme and avoids the problem of power supply failure due to energy storage device failure during the scheduling process.

[0129] Furthermore, this embodiment may also issue an early warning based on the energy storage device information whose depletion level is not less than a preset depletion level threshold.

[0130] Furthermore, the environmental information includes environmental images, weather information, and environmental temperature. The failure rate is determined based on the environmental information, including:

[0131] Determine the target object in the current environment according to the environmental image;

[0132] The failure occurrence rate is determined based on the ambient temperature and / or weather information and / or the target object.

[0133] Among them, a camera device is arranged around each energy storage device to collect the environmental image of the energy storage device. The environmental image at least includes the corresponding storage device and the target objects around the storage device. The weather information includes: sunny days, rainy days, stormy days, and snowy days. This embodiment needs to determine the properties of the target object, such as flammable properties, explosive properties, and properties that are easy to hit the energy storage device and cause irreparable damage.

[0134] In this embodiment, corresponding sub-fault occurrence rates are set for various conditions in the ambient temperature, weather information, and target objects; the fault occurrence rate is finally determined based on the sub-fault occurrence rate corresponding to the specific ambient temperature and / or the sub-fault occurrence rate corresponding to the weather information and / or the sub-fault occurrence rate corresponding to the target object. This embodiment examines the influence of multiple environmental factors on the occurrence of faults, and improves the accuracy of determining the fault occurrence rate.

[0135] Furthermore, before obtaining the load dispatch request at the first moment, the method further includes:

[0136] Obtaining power consumption information within a time range corresponding to a second moment of the area to be scheduled; wherein the second moment is earlier than the first moment;

[0137] Use historical power consumption information to perform load forecasting on power consumption information and output forecast results;

[0138] When the prediction result is power load, a load report and load prompt information are generated, and the load report and load prompt information are displayed on a display device.

[0139] The power consumption information may include the total power consumption within a set time period and the power consumption rate.

[0140] It can be understood that this embodiment uses historical power consumption information to perform load forecasting on power consumption information. Of course, load forecasting can also be performed based on any one of the least squares fitting method, Kalman filtering method, regression model prediction technology, time series prediction technology, artificial neural network method, and fuzzy prediction method.

[0141] When the prediction result is power load, a load report and load prompt information are generated, and the load report and prompt information are displayed on the display device, so as to focus on effectively ensuring the stable operation of the power grid and ensuring normal power supply.

[0142] It can be seen that this embodiment uses a preset load forecasting method to forecast the current load situation, which improves the forecasting efficiency and avoids the problems of low efficiency and high cost caused by manual monitoring.

[0143] Furthermore, it also includes:

[0144] During the off-peak hours of electricity consumption, a charging instruction is sent to the working energy storage device so that the working energy storage device is charged according to the charging instruction.

[0145] In this embodiment, the energy storage device is controlled to be charged during the off-peak hours, thereby ensuring that sufficient electricity is stored in the energy storage device so as to be dispatched during the actual power load and ensure normal power consumption.

[0146] Furthermore, before obtaining the remaining power and consumption level of each idle energy storage device, it also includes:

[0147] When the energy storage device is dispatched, the energy storage device information table is updated, and the energy storage device information table includes: the waiting time of all energy storage devices;

[0148] The idle energy storage device corresponding to the first moment is determined according to the waiting time.

[0149] The energy storage device information table is updated in real time so that the idle energy storage device corresponding to the first moment can be determined in advance according to the time when the energy storage device is ready for use, thereby avoiding the situation where only the idle energy storage devices at the current moment are used when the power demand is large due to scheduling based only on the idle energy storage devices at the current moment, resulting in insufficient power supply, wherein the current moment is not greater than the first moment.

[0150] The following is an introduction to a load scheduling device for an energy storage device provided in an embodiment of the present disclosure. The load scheduling device for an energy storage device described below and the load scheduling method for an energy storage device described above can be referred to each other. Figure 2 , Figure 2 A schematic diagram of a load scheduling device for an energy storage device provided in an embodiment of the present application includes:

[0151] The acquisition module 210 is used to acquire the load dispatch request at the first moment, and acquire the remaining power and consumption degree of each idle energy storage device, wherein the load dispatch request includes: the power to be dispatched and the area to be dispatched;

[0152] A real supply power determination module 220, used to determine the real supply power of each idle energy storage device according to the remaining power and the degree of consumption;

[0153] A scheduling scheme determination module 230 is used to determine multiple scheduling schemes according to the amount of electricity to be scheduled and the actual supply amount of each idle energy storage device, wherein the scheduling scheme includes at least one target energy storage device among the multiple idle storage devices;

[0154] The target scheduling scheme determining module 240 is used to determine the target scheduling scheme from multiple scheduling schemes according to the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of wear of the target energy storage devices in the scheduling scheme, and generate a load scheduling instruction;

[0155] The scheduling instruction sending module 250 is used to send load scheduling instructions to all target energy storage devices in the target scheduling scheme, so that the target energy storage devices supply power according to the load scheduling instructions.

[0156] Preferably, it also includes:

[0157] The communication request sending module is used to send communication requests to all energy storage devices according to a preset period.

[0158] A total amount determination module is used to obtain feedback information of the energy storage device and determine the total amount of the feedback information;

[0159] A judgment module, used to judge whether the total amount is less than a preset total amount threshold;

[0160] A first determination module, used to determine that the scheduling operation is normal if it is not less than a preset total amount threshold;

[0161] The second determination module is used to determine the scheduling operation failure if it is less than a preset total threshold, and determine a new scheduling node according to the set rules, wherein the new scheduling node is used to perform subsequent load scheduling; send a replacement request including parameter information of the new scheduling node to all slave nodes.

[0162] Preferably, the second determining module includes:

[0163] A first new scheduling node determination unit, used to determine a new scheduling node according to a set identification order of each node;

[0164] The second new scheduling node determination unit is used to obtain election information sent by each slave node, the election information includes the selected target node; and determine the target node with the largest number of selections from all the target nodes as the new scheduling node.

[0165] Preferably, the scheduling scheme determination module 230 includes:

[0166] A determination unit, configured to determine an idle energy storage device whose degree of consumption is less than a preset degree of consumption threshold;

[0167] An environmental information acquisition unit, used to acquire environmental information of idle energy storage devices whose consumption level is less than a preset consumption level threshold;

[0168] A fault occurrence rate determination unit, used to determine the fault occurrence rate according to the environmental information;

[0169] The scheduling scheme determination unit is used to determine multiple scheduling schemes according to the amount of power to be scheduled, the actual supply power of idle energy storage devices whose consumption level is less than a preset consumption level threshold, and the failure rate.

[0170] Preferably, the environmental information includes environmental images, weather information, and environmental temperature, and the fault occurrence rate determination unit includes:

[0171] A target object determination subunit, used to determine the target object in the current environment according to the environment image;

[0172] The fault occurrence rate determination subunit is used to determine the fault occurrence rate according to the ambient temperature and / or weather information and / or the target object.

[0173] Preferably, it also includes:

[0174] The power consumption information acquisition module is used to acquire the power consumption information within the time range corresponding to the second moment of the area to be scheduled; wherein the second moment is earlier than the first moment;

[0175] A prediction module is used to use historical power consumption information to perform load prediction on power consumption information and output prediction results;

[0176] The display module is used to generate a load report and load prompt information when the prediction result is power load, and display the load report and load prompt information on a display device.

[0177] Preferably, it also includes:

[0178] An updating module, used to update the energy storage device information table after the energy storage device is scheduled, the energy storage device information table including: the waiting time of all energy storage devices;

[0179] The idle energy storage device determination module is used to determine the idle energy storage device corresponding to the first moment according to the waiting time.

[0180] An electronic device is provided in an embodiment of the present application, such as Figure 3 As shown, Figure 3 The electronic device 300 shown includes: a processor 301 and a memory 303. The processor 301 and the memory 303 are connected, such as through a bus 302. Optionally, the electronic device 300 may also include a transceiver 304. It should be noted that in actual applications, the transceiver 304 is not limited to one, and the structure of the electronic device 300 does not constitute a limitation on the embodiments of the present application.

[0181] The processor 301 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. It may implement or execute various exemplary logic blocks, modules and circuits described in conjunction with the disclosure of this application. The processor 301 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, etc.

[0182] The bus 302 may include a path to transmit information between the above components. The bus 302 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 302 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 3 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0183] The memory 303 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited thereto.

[0184] The memory 303 is used to store the application code for executing the solution of the present application, and the execution is controlled by the processor 301. The processor 301 is used to execute the application code stored in the memory 303 to implement the contents shown in the above method embodiment.

[0185] The electronic devices include, but are not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), and fixed terminals such as digital TVs, desktop computers, etc. It can also be a server, etc. Figure 3 The electronic device shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present disclosure.

[0186] The embodiment of the present application provides a computer-readable storage medium, on which a computer program is stored, and when the computer is run on a computer, the computer can execute the corresponding content in the aforementioned method embodiment. Compared with the related art, the embodiment of the present application first obtains the remaining power and the degree of consumption of each idle energy storage device to determine the actual supply power of the energy storage device, and then determines multiple scheduling schemes according to the power to be scheduled and the actual supply power, thereby ensuring the accuracy of determining the scheduling scheme according to the power to be scheduled, avoiding the occurrence of insufficient power caused by scheduling due to power consumption of the energy storage device, and can determine the target scheduling scheme from multiple scheduling schemes based on the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of consumption of the target energy storage device in the scheduling scheme, and can determine the scheme that meets the needs according to actual needs.

[0187] It should be understood that, although the steps in the flowchart of the accompanying drawings are displayed in sequence as indicated by the arrows, these steps are not necessarily executed in sequence in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least a part of the steps in the flowchart of the accompanying drawings may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and their execution order is not necessarily sequential, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.

[0188] The above are only some implementation methods of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A load scheduling method for energy storage equipment, characterized in that: include: Obtaining a load dispatch request at a first moment, and obtaining the remaining power and consumption degree of each idle energy storage device, wherein the load dispatch request includes: the power to be dispatched and the area to be dispatched; Determine the actual supply power of each idle energy storage device according to the remaining power and the consumption degree; Determine multiple scheduling schemes according to the amount of electricity to be scheduled and the actual amount of electricity supplied by each idle energy storage device, wherein the scheduling schemes include at least one target energy storage device among the multiple idle storage devices; Determine a target scheduling scheme from a plurality of scheduling schemes according to the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of wear of the target energy storage devices in the scheduling scheme, and generate a load scheduling instruction; Sending the load scheduling instruction to all target energy storage devices in the target scheduling scheme, so that the target energy storage devices supply power according to the load scheduling instruction; Determining multiple scheduling schemes according to the amount of power to be scheduled and the actual amount of power supplied by each idle energy storage device includes: Identify idle energy storage devices whose depletion level is less than a preset depletion level threshold; Acquire environmental information of idle energy storage devices whose consumption level is less than a preset consumption level threshold; determining a failure occurrence rate based on the environmental information; Determine multiple scheduling schemes according to the to-be-scheduled power, the actual supply power of the idle energy storage device whose loss degree is less than the preset loss degree threshold, and the failure occurrence rate; The environmental information includes environmental images, weather information, and environmental temperature. The determining of the fault occurrence rate according to the environmental information includes: Determine a target object in the current environment according to the environment image; Determine the fault occurrence rate according to the ambient temperature and / or weather information and / or target object, wherein the sub-fault occurrence rates corresponding to various conditions in the ambient temperature, weather information, and target object are obtained; and finally determine the fault occurrence rate according to the sub-fault occurrence rate corresponding to the specific ambient temperature, the sub-fault occurrence rate corresponding to the weather information, and the sub-fault occurrence rate corresponding to the target object; Among them, determining the target scheduling scheme from multiple scheduling schemes includes the following process: Determine the matching degree between all energy storage devices in a plurality of scheduling schemes and the area to be scheduled, and determine a first value according to the matching degree; Determine the number of target energy storage devices in the scheduling plan, and determine a second value according to the number; Determine the average value of the degree of wear of the target energy storage device in the scheduling plan, and determine the third value according to the average value of the degree of wear; Determine a total value according to the first value, the second value, and the third value; Determine the target scheduling scheme according to the total values ​​of all scheduling schemes; The load scheduling request is a request sent from a node, and the load scheduling method further includes: Send communication requests to all energy storage devices according to the preset cycle, Obtaining feedback information from the energy storage device and determining the total amount of the feedback information; Determine whether the total amount is less than a preset total amount threshold; If it is not less than the preset total amount threshold, it is determined that the scheduling operation is normal; If it is less than the preset total amount threshold, a scheduling operation failure is determined, and a new scheduling node is determined according to the set rules, wherein the new scheduling node is used to perform subsequent load scheduling; a replacement request including parameter information of the new scheduling node is sent to all slave nodes; The determining of a new scheduling node according to a set rule includes: Determine the new scheduling node according to the set identification order of each node; Or, obtain election information sent by each slave node, wherein the election information includes a selected target node; and determine the target node with the largest number of selections from all the target nodes as a new scheduling node.

2. A load scheduling method for energy storage equipment according to claim 1, characterized in that: Before obtaining the load dispatching request at the first moment, the method further includes: Obtaining power consumption information within a time range corresponding to a second moment in the area to be scheduled; wherein the second moment is earlier than the first moment; Using historical power consumption information to perform load forecasting on the power consumption information, and outputting forecasting results; When the prediction result is power load, a load report and load prompt information are generated, and the load report and the load prompt information are displayed on a display device.

3. A load scheduling method for energy storage equipment according to claim 1, characterized in that: Before obtaining the remaining power and consumption degree of each idle energy storage device, the method further includes: When the energy storage device is scheduled, the energy storage device information table is updated, and the energy storage device information table includes: the waiting time of all energy storage devices; An idle energy storage device corresponding to the first moment is determined according to the waiting time.

4. A device for load scheduling of energy storage equipment, characterized in that: include: An acquisition module is used to acquire a load dispatch request at a first moment, and to acquire the remaining power and consumption degree of each idle energy storage device, wherein the load dispatch request includes: the power to be dispatched and the area to be dispatched; A real supply power determination module, used to determine the real supply power of each idle energy storage device according to the remaining power and the depletion degree; A scheduling scheme determination module, used to determine multiple scheduling schemes according to the amount of electricity to be scheduled and the actual supply amount of each idle energy storage device, wherein the scheduling scheme includes at least one target energy storage device among the multiple idle storage devices; A target scheduling scheme determination module, used to determine a target scheduling scheme from multiple scheduling schemes according to the area to be scheduled, and / or the number of target energy storage devices in the scheduling scheme, and / or the average degree of wear of the target energy storage devices in the scheduling scheme, and generate a load scheduling instruction; A dispatching instruction sending module, used to send the load dispatching instruction to all target energy storage devices in the target dispatching scheme, so that the target energy storage devices supply power according to the load dispatching instruction; The scheduling scheme determination module includes: A determination unit, configured to determine an idle energy storage device whose degree of consumption is less than a preset degree of consumption threshold; An environmental information acquisition unit, used to acquire environmental information of the idle energy storage device whose consumption degree is less than a preset consumption degree threshold; a fault occurrence rate determination unit, configured to determine the fault occurrence rate according to the environmental information; A scheduling scheme determination unit, configured to determine a plurality of scheduling schemes according to the to-be-scheduled power, the actual supply power of the idle energy storage device whose loss degree is less than a preset loss degree threshold, and the failure occurrence rate; The environmental information includes environmental images, weather information, and environmental temperature. The fault occurrence rate determination unit includes: A target object determination subunit, used to determine a target object in the current environment according to the environment image; A fault occurrence rate determination subunit is used to determine the fault occurrence rate according to the ambient temperature and / or weather information and / or target object, wherein the sub-fault occurrence rates corresponding to various conditions in the ambient temperature, weather information, and target object are obtained; the fault occurrence rate is finally determined according to the sub-fault occurrence rate corresponding to the specific ambient temperature, the sub-fault occurrence rate corresponding to the weather information, and the sub-fault occurrence rate corresponding to the target object; The target scheduling scheme determination module is used to: determine the matching degree between all energy storage devices in a plurality of scheduling schemes and the area to be scheduled, and determine a first value according to the matching degree; Determine the number of target energy storage devices in the scheduling plan, and determine a second value according to the number; Determine the average value of the degree of wear of the target energy storage device in the scheduling plan, and determine the third value according to the average value of the degree of wear; Determine a total value according to the first value, the second value, and the third value; Determine the target scheduling scheme according to the total values ​​of all scheduling schemes; The load scheduling request is a request sent from a node, and the device further includes: The communication request sending module is used to send communication requests to all energy storage devices according to a preset period. A total amount determination module, used to obtain feedback information of the energy storage device and determine the total amount of the feedback information; A judging module, used to judge whether the total amount is less than a preset total amount threshold; A first determination module, configured to determine that the scheduling operation is normal if the amount is not less than the preset total amount threshold; A second determination module is used to determine a scheduling operation failure if the total amount is less than the preset total amount threshold, and determine a new scheduling node according to a set rule, wherein the new scheduling node is used to perform subsequent load scheduling; and send a replacement request including parameter information of the new scheduling node to all slave nodes; The second determination module includes: A first new scheduling node determination unit, used to determine a new scheduling node according to a set identification order of each node; The second new scheduling node determination unit is used to obtain election information sent by each slave node, wherein the election information includes a selected target node; and determine the target node with the largest number of selections from all the target nodes as a new scheduling node.

5. An electronic device, characterized in that: It includes: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute the load scheduling method for an energy storage device according to any one of claims 1 to 3.

6. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores instructions, and when the instructions are executed on a computer, the computer executes the load scheduling method for an energy storage device according to any one of claims 1 to 3.

Citation Information

Patent Citations

  • Energy storage type fan scheduling response method based on distributed accounting

    CN111327076A

  • Electric quantity scheduling method and device based on block chain and computer equipment

    CN111612363A

  • Energy scheduling management and control method and system based on cloud platform and block chain

    CN112465355A

  • Distributed energy storage optimization scheduling method and device, computer equipment and storage medium

    CN112510679A

  • Load scheduling method and device for energy storage equipment, equipment and storage medium

    CN113315160A