A power dispatching fault handling system and method

By using data modeling, parameter display and fault processing modules in the power scheduling system, accurate positioning and automated disposal solution generation of power scheduling faults is achieved, and the problem of fault positioning difficulties in the existing technology is solved and work efficiency is improved.

CN115081692BActive Publication Date: 2024-11-22STATE GRID SHANDONG ELECTRIC POWER CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210634470.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-07
Publication Date
2024-11-22
Estimated Expiration
2042-06-07

AI Technical Summary

Technical Problem

The existing power scheduling fault handling methods cannot accurately locate the location of the fault point, find the line parameters, and it is very difficult to judge the fault location.

Method used

Provide a power scheduling fault handling system, including data modeling module, parameter display module and fault handling module. The tower and connection lines are displayed on the simulation display screen through the data modeling module, the parameter display module displays line attribute data, and fault handling The module uses algorithm models to predict fault locations and causes and generates a preliminary disposal report.

Benefits of technology

It realizes automatic fault positioning and disposal solution generation, quickly obtains fault positioning points, solves the problem of being unable to accurately locate fault points and find line parameters in the existing technology, and improves the work efficiency of dispatchers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115081692B_ABST
    Figure CN115081692B_ABST
Patent Text Reader

Abstract

The present application discloses a power dispatching fault handling system and method, which mainly relates to the field of fault handling technology. It is used to solve the technical problems that the existing power dispatching fault handling methods cannot accurately locate the fault point, cannot find the line parameters, and it is very difficult to determine the fault location. The method includes: a data modeling module, which is used to display the pole tower and connecting line construction on a simulated display screen; a parameter display module, which is used to update the line parameter data to the text encoding box; a fault handling module, which is used to determine the predicted fault location point and the connecting line corresponding to the predicted fault location point; synthesize a preliminary handling report; a report verification module, which is used to obtain a verification handling report corresponding to the preliminary handling report; after obtaining the upload instruction, the verification handling report is sent to the preset processing terminal. The present application realizes the automatic generation of prediction handling plans and predicted fault causes through the above method, and effectively and quickly obtains the predicted fault location point.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of electric power dispatching, and in particular to a system and method for handling electric power dispatching faults. Background Art

[0002] After a thousand-volt line is shut down due to a fault, the on-duty personnel at the local and county power dispatching and control centers should immediately collect and summarize relevant information such as the smart grid dispatching and control system, distribution network management system, video surveillance, etc., analyze and determine the line fault situation to confirm whether to conduct remote trial transmission on the line.

[0003] At present, the main method to determine whether to conduct a remote trial transmission on the line is: after the control duty personnel obtain the transmission line fault distance from the fault recording system, they need to consult the electronic document data and calculate the location of the fault point, which brings inconvenience to the dispatcher's forced transmission work and affects the dispatcher's accident handling.

[0004] Therefore, there is an urgent need for a power dispatching fault handling system and method to solve the problems that the existing power dispatching fault handling method cannot accurately locate the fault point, cannot find line parameters, and is very difficult to determine the fault location. Summary of the invention

[0005] In view of the above-mentioned deficiencies in the prior art, the present invention provides a power dispatching fault handling system and method to solve the above-mentioned technical problems.

[0006] In the first aspect, the present application provides a power dispatching fault handling system, the system comprising: a data modeling module, for determining the tower number of the tower to be monitored for faults according to the received data construction instruction; and then obtaining the tower data corresponding to the tower and the basic attribute data of the connecting line between adjacent towers; based on the tower data and the basic attribute data, the tower and the connecting line are displayed on the simulation display screen; and a text code box is preset on the connecting line identification displayed on the simulation display screen; a parameter display module is used to obtain the line attribute data of the connecting line when receiving the parameter update instruction; so as to update the line parameter data into the text code box; wherein the line attribute data includes: basic attribute data, location data and meteorological data; a fault processing module, which is used to generate data building instructions and parameter updating instructions when receiving fault data; determine the predicted fault location point and the connection line corresponding to the predicted fault location point based on the location data and fault distance of the fault detection point in the fault data; import the line parameter data and fault data of the corresponding connection line into the trained algorithm model to determine the predicted disposal plan and the predicted fault cause from the preset fault processing database, and then synthesize the preliminary disposal report; a report verification module, which is used to obtain the update data or confirmation data corresponding to the preliminary disposal report to obtain the verification disposal report corresponding to the preliminary disposal report; after obtaining the upload instruction, send the verification disposal report to the preset processing terminal.

[0007] Furthermore, the data modeling module includes: a data response unit and a data modeling unit; the data response unit is used to read the data construction instruction to obtain a number of pole tower data for data construction and basic attribute data of the connection line; wherein the pole tower data includes the pole tower number, the pole tower position, and the connection line number corresponding to the pole tower, and the basic attribute data includes the connection line number, the pole tower number corresponding to the first end, the pole tower number corresponding to the second end, the line length, the line type and the line model; and the line types include: overhead wires, all-cable lines and hybrid lines; the data modeling unit is used to arrange the pole tower logo on the simulation display screen based on the pole tower position and the plane rectangular coordinate system; based on the basic attribute data, the connection line logo is arranged on the simulation display screen.

[0008] Furthermore, the parameter display module includes: a basic attribute unit and a dynamic attribute unit; the basic attribute unit is used to obtain the position data corresponding to the connection line based on the tower number corresponding to the first end of the connection line and the tower number corresponding to the second end of the connection line; the position data and the basic attribute data are imported into the text coding box and the preset line attribute database; the dynamic attribute unit is used to obtain the meteorological data corresponding to the connection line based on the tower number corresponding to the first end and the tower number corresponding to the second end; the meteorological data is imported into the text coding box and the preset line attribute database; wherein the meteorological data includes: first end meteorological data, second end meteorological data and center point meteorological data.

[0009] Furthermore, the fault processing module includes: a fault determination unit and a neural algorithm unit; the fault determination unit is used to determine the predicted line data corresponding to the predicted fault location point based on the position data and fault distance of the fault detection point; and then calculate the predicted fault location point based on the position data, fault distance and line length of the fault detection point; the neural algorithm unit is used to determine the basic attribute data and meteorological data of the connection line corresponding to the predicted fault location point; import the basic attribute data and meteorological data into the fuzziness algorithm, determine the first fuzziness of the connection line and each preset treatment plan in the fuzziness algorithm, so as to determine the second fuzziness of the connection line and each preset fault cause in the fuzziness algorithm; determine the preset treatment plan whose first fuzziness exceeds the preset first fuzzy threshold as the predicted treatment plan; determine the preset fault cause whose second fuzziness exceeds the preset second fuzzy threshold as the predicted fault cause.

[0010] Furthermore, the system also includes a data update module; the data update module is used to obtain the actual handling report uploaded by the preset processing terminal, so as to update the preset fault processing database and re-train the algorithm model through the actual handling report.

[0011] In a second aspect, the present application provides a method for handling electric power dispatching faults, characterized in that the method includes: upon receiving fault data, generating data construction instructions and parameter update instructions; wherein the fault data includes location data of the fault detection point and the fault distance; determining a number of pole towers for fault monitoring according to the received data construction instructions; obtaining pole tower data corresponding to the pole towers and basic attribute data of the connecting lines between adjacent pole towers; based on the pole tower data and the basic attribute data, displaying the pole towers and the connecting lines on a simulated display screen; and presetting a text coding box on the connecting line identifier displayed on the simulated display screen; obtaining the line attribute data corresponding to the connecting line according to the received parameter update instructions. ; to update the parameter data into the text coding box; wherein the line attribute data includes: basic attribute data, location data and meteorological data; based on the location data and fault distance of the fault detection point in the fault data, determine the predicted fault location point and the connection line corresponding to the predicted fault location point; import the line parameter data and fault data of the corresponding connection line into the trained algorithm model to determine the predicted disposal plan and the predicted fault cause from the preset fault processing database, and then synthesize the preliminary disposal report; obtain the update data or confirmation data corresponding to the preliminary disposal report to obtain the verification disposal report corresponding to the preliminary disposal report; after obtaining the upload instruction, send the verification disposal report to the preset processing terminal.

[0012] Furthermore, the line parameter data and fault data of the corresponding connecting line are imported into the trained algorithm model to determine the prediction disposal plan and the predicted fault cause from the preset fault processing database, specifically including: determining the basic attribute data and meteorological data of the connecting line corresponding to the predicted fault location point; importing the basic attribute data and meteorological data into the fuzziness algorithm to determine the first fuzziness of the connecting line and each preset disposal plan in the fuzziness algorithm to determine the second fuzziness of the connecting line and each preset fault cause in the fuzziness algorithm; determining the preset disposal plan whose first fuzziness exceeds the preset first fuzzy threshold as the predicted disposal plan; determining the preset fault cause whose second fuzziness exceeds the preset second fuzzy threshold as the predicted fault cause.

[0013] Furthermore, the method also includes: obtaining an actual handling report uploaded by a preset processing terminal, so as to update a preset fault handling database and re-train the algorithm model through the actual handling report.

[0014] It can be understood by those skilled in the art that the present invention has at least the following beneficial effects: through the data modeling module, it is realized that the pole tower and the connecting line are displayed on the simulation display screen, so that the relevant staff can effectively and quickly know the positional relationship between the pole tower and the connecting line. Through the parameter display module, the line attribute data of the connecting line is displayed on the simulation display screen, so that the relevant operating personnel can quickly check the connecting line data, avoiding the time loss of checking the electronic document data. Through the fault handling module, it is realized to automatically generate the prediction and disposal plan, predict the cause of the fault, and effectively and quickly obtain the predicted fault location point, which solves the problems that the existing power dispatching fault handling method cannot accurately locate the fault point, cannot find the line parameters, and it is very difficult to determine the fault location. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Some embodiments of the present disclosure are described below with reference to the accompanying drawings, in which:

[0016] Figure 1 This is a schematic diagram of the internal structure of a power dispatching fault handling system provided in this application.

[0017] Figure 2 This is a flow chart of a method for handling power dispatching faults provided in this application. DETAILED DESCRIPTION

[0018] It should be understood by those skilled in the art that the embodiments described below are only preferred embodiments of the present disclosure, and do not mean that the present disclosure can only be implemented through the preferred embodiments. The preferred embodiments are only used to explain the technical principles of the present disclosure, and are not used to limit the protection scope of the present disclosure. Based on the preferred embodiments provided by the present disclosure, all other embodiments obtained by ordinary technicians in this field without creative work should still fall within the protection scope of the present disclosure.

[0019] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0020] The technical solution proposed in this application is described in detail below with reference to the accompanying drawings.

[0021] Figure 1 This application provides a power dispatching fault handling system. Figure 1 As shown, the fault handling system provided by the present application mainly includes: a data modeling module 110, a parameter display module 120, a fault handling module 130, and a report verification module 140.

[0022] Among them, the data modeling module 110 is any feasible equipment or device that can build data on the simulation display screen, etc., which is mainly used to determine the tower number of the tower for fault monitoring according to the received data building instructions; obtain the tower data corresponding to the tower, the connecting lines between adjacent towers and the basic attribute data corresponding to the connecting lines; based on the tower data and the basic attribute data, the tower and the connecting line are built and displayed on the simulation display screen; wherein a text code box is preset on the connecting line logo displayed on the simulation display screen.

[0023] It should be noted that the data building instruction is used to trigger the data modeling module 110 to perform data visualization building operations. The data building instruction can specifically be a set of tower numbers. The server can determine a number of towers for fault monitoring by reading the tower number set; wherein the tower number corresponds to the tower one-to-one and is unique. And it is also possible to obtain tower data, connecting lines between adjacent towers, and basic attribute data corresponding to the connecting lines from the preset line attribute database according to the read tower number. The preset line attribute database is used to store tower data and basic attribute data.

[0024] In addition, it should be noted that the preset text encoding box is any feasible encoding box that can input a character string, and can be set in any feasible area around the connection line mark.

[0025] As an example, the data modeling module 110 includes: a data response unit 111 and a data modeling unit 112 .

[0026] Specifically, the data response unit 111 is any feasible device or apparatus capable of performing data response, etc., which is mainly used to read data construction instructions to obtain several tower data for data construction and basic attribute data of the connection line; wherein the tower data includes the tower number, tower location, and the connection line number corresponding to the tower.

[0027] Specifically, the data modeling unit 112 is any feasible device or apparatus capable of mapping data onto a simulated display screen, and is mainly used to arrange the pole tower identification on the simulated display screen based on the pole tower position and the plane rectangular coordinate system; arrange the connection line identification on the simulated display screen based on the basic attribute data; wherein the basic attribute data includes the connection line number, the pole tower number corresponding to the first end, the pole tower number corresponding to the second end, the line length, the line type, and the line model. It should be noted that the identification corresponding to the pole tower identification and the connection line identification can be any feasible identification, and those skilled in the art can determine the specific form of the identification according to the actual situation. The pole tower number and the connection line number can be any feasible data with distinguishing functions. The line type and the line model can be any feasible content.

[0028] Among them, the parameter display module 120 is any feasible device or apparatus with data acquisition and data import functions, etc., which is mainly used to obtain the line attribute data corresponding to the connection line when receiving the parameter update instruction; to update the line parameter data into the text coding box; wherein the line attribute data includes: basic attribute data, location data and meteorological data.

[0029] It should be noted that the parameter update instruction is used to trigger the parameter display module 120 to execute the line attribute data acquisition operation.

[0030] As an example, the parameter display module 120 includes: a basic attribute unit 121 and a dynamic attribute unit 122 .

[0031] Specifically, the basic attribute unit 121 is used to obtain the position data corresponding to the connection line based on the tower number corresponding to the first end of the connection line and the tower number corresponding to the second end of the connection line; and update the position data and basic attribute data to the text code box and the preset line attribute database.

[0032] Specifically, the dynamic attribute unit 122 is used to obtain meteorological data corresponding to the connecting line based on the tower number corresponding to the first end and the tower number corresponding to the second end; import the meteorological data into the text coding box and the preset line attribute database; wherein the meteorological data includes: first end meteorological data, second end meteorological data and center point meteorological data.

[0033] Among them, the fault handling module 130 is any feasible equipment or device that can perform fault handling, etc., which is mainly used to generate data construction instructions and parameter update instructions when receiving fault data; wherein the fault data includes the location data of the fault detection point and the fault distance; the line parameter data and the fault data are imported into the trained algorithm model to determine the prediction and disposal plan, predict the cause of the fault, and predict the fault location point from the preset fault handling database, and then synthesize the preliminary disposal report.

[0034] It should be noted that the preliminary disposal report includes the predicted disposal plan, predicted cause of failure, and predicted fault location point.

[0035] As an example, the fault processing module 130 includes: a fault determination unit 131 and a neural algorithm unit 132 .

[0036] Specifically, the fault determination unit 131 is used to determine the predicted line data corresponding to the predicted fault location point based on the position data of the fault detection point and the fault distance; and then calculate the predicted fault location point based on the position data of the fault detection point, the fault distance, and the line length of the predicted connecting line.

[0037] It should be noted that the calculation formula corresponding to the predicted fault location point is: predicted fault location point = location data of the fault detection point - (fault distance - predicted line length of the connecting line).

[0038] Specifically, the neural algorithm unit 132 is used to determine the basic attribute data and meteorological data of the connection line corresponding to the predicted fault location point; import the basic attribute data and meteorological data into the fuzzy algorithm, determine the first fuzziness of the connection line and each preset treatment plan in the fuzzy algorithm, so as to determine the second fuzziness of the connection line and each preset fault cause in the fuzzy algorithm; determine the preset treatment plan whose first fuzziness exceeds the preset first fuzzy threshold as the predicted treatment plan; determine the preset fault cause whose second fuzziness exceeds the preset second fuzzy threshold as the predicted fault cause.

[0039] It should be noted that, through the first fuzziness formula: Calculate the first ambiguity; use the second ambiguity formula: Calculate the second fuzziness. Wherein, F(μ) represents the first fuzziness, Q(μ) represents the second fuzziness, and μ represents the basic attribute data and meteorological data.

[0040] Among them, the report verification module 140 is used to obtain the update data or confirmation data corresponding to the preliminary disposal report to obtain the verification disposal report corresponding to the preliminary disposal report; after obtaining the upload instruction, the verification disposal report is sent to the preset processing terminal.

[0041] As an example, the report verification module 140 presets an upload interface, through which the relevant operator can upload the updated data, and the report verification module 140 presets an upload button, and when the upload button is triggered, an upload instruction is automatically generated. The report verification module 140 also presets a confirmation button, and when the confirmation button is triggered, confirmation data is automatically generated.

[0042] In addition, the present application can also update the preset fault handling database and retrain the algorithm model.

[0043] As an example, the system also includes a data updating module 150; the data updating module 150 is used to obtain the actual handling report uploaded by the preset processing terminal, so as to update the preset fault handling database and re-train the algorithm model through the actual handling report.

[0044] In addition, the present application also provides a method for handling power dispatching faults, the execution subject of which is a server. Figure 2 As shown, the fault handling method provided by this application mainly includes the following steps:

[0045] Step 210: upon receiving fault data, generating data building instructions and parameter updating instructions; wherein the fault data includes location data of the fault detection point and the fault distance.

[0046] Step 220: determine a number of pole towers for fault monitoring based on the received data construction instructions; obtain the pole tower data corresponding to the pole towers and the basic attribute data of the connection lines between adjacent pole towers; based on the pole tower data and the basic attribute data, display the pole towers and the connection lines on the simulation display screen; and preset a text code box on the connection line logo displayed on the simulation display screen.

[0047] Step 230: Acquire the line attribute data corresponding to the connection line according to the received parameter update instruction; update the parameter data into the text encoding frame; wherein the line attribute data includes: basic attribute data, location data and meteorological data.

[0048] Step 240: Based on the position data of the fault detection point in the fault data and the fault distance, determine the predicted fault location point and the connection line corresponding to the predicted fault location point; import the line parameter data of the corresponding connection line and the fault data into the trained algorithm model to determine the predicted handling plan and the predicted fault cause from the preset fault handling database, and then synthesize a preliminary handling report.

[0049] As an example, the line parameter data and fault data of the corresponding connecting line are imported into the trained algorithm model to determine the predicted disposal plan and the predicted fault cause from the preset fault processing database, specifically including: determining the basic attribute data and meteorological data of the connecting line corresponding to the predicted fault location point; importing the basic attribute data and meteorological data into the fuzziness algorithm to determine the first fuzziness of the connecting line and each preset disposal plan in the fuzziness algorithm, so as to determine the second fuzziness of the connecting line and each preset fault cause in the fuzziness algorithm; determining the preset disposal plan whose first fuzziness exceeds the preset first fuzzy threshold as the predicted disposal plan; determining the preset fault cause whose second fuzziness exceeds the preset second fuzzy threshold as the predicted fault cause.

[0050] Step 250: Obtain update data or confirmation data corresponding to the preliminary disposal report to obtain a verification disposal report corresponding to the preliminary disposal report; after obtaining the upload instruction, send the verification disposal report to a preset processing terminal.

[0051] In addition, the present application can also update the preset fault handling database and re-train the algorithm model.

[0052] As an example, the server can obtain the actual processing report uploaded by the preset processing terminal, so as to update the preset fault processing database and re-train the algorithm model through the actual processing report.

[0053] So far, the technical solutions of the present disclosure have been described in combination with the above multiple embodiments, but it is easy for those skilled in the art to understand that the protection scope of the present disclosure is not limited to these specific embodiments. Without departing from the technical principles of the present disclosure, those skilled in the art can split and combine the technical solutions in the above-mentioned various embodiments, and can also make equivalent changes or replacements to the relevant technical features. Any changes, equivalent replacements, improvements, etc. made within the technical concept and / or technical principle of the present disclosure will fall within the protection scope of the present disclosure.

Claims

1. A power dispatching fault handling system, It is characterized in that The system comprises: The data modeling module is used to determine the pole tower and the pole tower number for fault monitoring according to the received data construction instruction; then obtain the pole tower data corresponding to the pole tower and the basic attribute data of the connection line between adjacent pole towers; based on the pole tower data and the basic attribute data, the pole tower and the connection line are displayed on the simulation display screen; and a text code box is preset on the connection line logo displayed on the simulation display screen; The parameter display module is used to obtain the line attribute data of the connection line when receiving the parameter update instruction; so as to update the line parameter data into the text code frame; wherein the line attribute data includes: basic attribute data, location data and meteorological data; A fault processing module is used to generate data building instructions and parameter updating instructions when receiving fault data; determine the predicted fault location point and the connection line corresponding to the predicted fault location point based on the location data of the fault detection point and the fault distance in the fault data; import the line parameter data and fault data of the corresponding connection line into the trained algorithm model to determine the predicted disposal plan and the predicted fault cause from the preset fault processing database, and then synthesize a preliminary disposal report; The report verification module is used to obtain the update data or confirmation data corresponding to the preliminary disposal report to obtain the verification disposal report corresponding to the preliminary disposal report; after obtaining the upload instruction, the verification disposal report is sent to the preset processing terminal.

2. The power dispatching fault handling system according to claim 1, It is characterized in that The data modeling module includes: a data response unit and a data modeling unit; The data response unit is used to read the data construction instruction to obtain a number of pole tower data for data construction and basic attribute data of the connection line; wherein the pole tower data includes the pole tower number, the pole tower position, and the connection line number corresponding to the pole tower; the basic attribute data includes the connection line number, the pole tower number corresponding to the first end, the pole tower number corresponding to the second end, the line length, the line type and the line model; and the line type includes: overhead wire, full cable line and hybrid line; The data modeling unit is used to arrange the pole tower logo on the simulation display screen based on the pole tower position and the plane rectangular coordinate system; and arrange the connection line logo on the simulation display screen based on the basic attribute data.

3. The power dispatching fault handling system according to claim 2, It is characterized in that The parameter display module includes: a basic attribute unit and a dynamic attribute unit; The basic attribute unit is used to obtain the position data corresponding to the connection line based on the pole tower number corresponding to the first end of the connection line and the pole tower number corresponding to the second end of the connection line; import the position data and the basic attribute data into the text encoding box and the preset line attribute database; The dynamic attribute unit is used to obtain meteorological data corresponding to the connecting line based on the tower number corresponding to the first end and the tower number corresponding to the second end; import the meteorological data into a text encoding box and a preset line attribute database; wherein the meteorological data includes: first end meteorological data, second end meteorological data and center point meteorological data.

4. The power dispatching fault handling system according to claim 1, It is characterized in that The fault processing module includes: a fault determination unit and a neural algorithm unit; The fault determination unit is used to determine the predicted line data corresponding to the predicted fault location point based on the position data of the fault detection point and the fault distance; and then calculate the predicted fault location point based on the position data of the fault detection point, the fault distance, and the line length of the predicted connection line; The neural algorithm unit is used to determine the basic attribute data and meteorological data of the connection line corresponding to the predicted fault location point; import the basic attribute data and meteorological data into the fuzziness algorithm, determine the first fuzziness of the connection line and each preset treatment plan in the fuzziness algorithm, and determine the second fuzziness of the connection line and each preset fault cause in the fuzziness algorithm; determine the preset treatment plan whose first fuzziness exceeds the preset first fuzzy threshold as the predicted treatment plan; determine the preset fault cause whose second fuzziness exceeds the preset second fuzzy threshold as the predicted fault cause.

5. The power dispatching fault handling system according to claim 1, It is characterized in that The system also includes a data updating module; The data updating module is used to obtain the actual handling report uploaded by the preset processing terminal, so as to update the preset fault handling database and re-train the algorithm model through the actual handling report.

6. A method for handling power dispatching faults, It is characterized in that The method comprises: When receiving fault data, generating data building instructions and parameter updating instructions; wherein the fault data includes the location data of the fault detection point and the fault distance; According to the received data construction instruction, a number of pole towers for fault monitoring are determined; the pole tower data corresponding to the pole tower and the basic attribute data of the connection line between adjacent pole towers are obtained; based on the pole tower data and the basic attribute data, the pole tower and the connection line are displayed on the simulation display screen; and a text code box is preset on the connection line logo displayed on the simulation display screen; According to the received parameter update instruction, the line attribute data corresponding to the connection line is obtained; the parameter data is updated into the text code frame; wherein the line attribute data includes: basic attribute data, location data and meteorological data; Based on the location data of the fault detection point and the fault distance in the fault data, determine the predicted fault location point and the connection line corresponding to the predicted fault location point; import the line parameter data and fault data of the corresponding connection line into the trained algorithm model to determine the predicted disposal plan and the predicted fault cause from the preset fault processing database, and then synthesize a preliminary disposal report; Acquire update data or confirmation data corresponding to the preliminary disposal report to obtain a verification disposal report corresponding to the preliminary disposal report; after acquiring the upload instruction, send the verification disposal report to a preset processing terminal.

7. The method for handling power dispatching faults according to claim 6, It is characterized in that Import the line parameter data and fault data of the corresponding connection line into the trained algorithm model to determine the prediction and treatment plan and the cause of the fault from the preset fault processing database, including: Determine the basic attribute data and meteorological data of the connection line corresponding to the predicted fault location point Importing basic attribute data and meteorological data into the fuzziness algorithm, determining the first fuzziness of the connection route and each preset treatment plan in the fuzziness algorithm, and determining the second fuzziness of the connection route and each preset fault cause in the fuzziness algorithm; Determine a preset handling solution when the first ambiguity exceeds a preset first ambiguity threshold as a predicted handling solution; determine a preset fault cause when the second ambiguity exceeds a preset second ambiguity threshold as a predicted fault cause.

8. The method for handling power dispatching faults according to claim 6, It is characterized in that The method further comprises: The actual handling report uploaded by the preset handling terminal is obtained, so as to update the preset fault handling database and train the algorithm model again through the actual handling report.