A cross-well seismic tomography method and system based on inclination measurement technology
The oblique measurement technology determines the observation system for seismic tomography between wells, which solves the problems of inaccurate positioning and unclear boundary conditions of the underground transmission and reception system, improves the imaging accuracy and data interoperability of the inter-well stratigraphic structure, and is suitable for deep high-temperature drying Hot rock drilling and other projects.
Patent Information
- Application Number
- CN202210874850.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-25
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2042-07-25
AI Technical Summary
In deep drilling projects, in the in-well seismic tomography technology, the underground transmission and reception system is inaccurately positioned and unclear boundary conditions, resulting in low imaging quality and long detection period, which affects the detection quality.
The inter-well seismic tomography method based on inclination measurement technology is adopted. The oblique data is measured by synchronous inclination measuring instruments to determine the observation system of inter-well seismic tomography, collect field seismic data, and use radiological tomography to determine the well. Images of inter-stratigraphic structures to improve imaging accuracy.
It solves the problems of inaccurate positioning and unclear boundary conditions of the underground transmission and reception system, improves the correct relocation ability and imaging accuracy of the inter-well formation structure, saves the process cost of loading positioning systems, reduces damage to the well holes, and improves the Data interoperability between inclination measurement technology and inter-well seismic technology is found.
Smart Images

Figure CN115128674B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of seismic tomography, and in particular to an inter-well seismic tomography method and system based on inclination measurement technology. Background Art
[0002] Seismic transmission tomography is a method of recording seismic transmission wave data by arranging an excitation device at one end and a receiving device at the other end in a well, on the ground or in a tunnel. The physical laws and mathematical relationships implied in the data are then analyzed tomographically. The travel time or amplitude information of the seismic waves is converted into the velocity (inverse of slowness) structure or attenuation characteristics of the internal formation, which is then represented by an image to identify target formations and abnormal geological bodies based on geological data.
[0003] The well detector is the receiving end of the seismic wave signal. It is an electromechanical conversion device that can convert seismic waves transmitted to the formation boundary or water into electrical signals. It is required to be relatively stably coupled with the formation and effectively adapt to the well environment. In actual use, it is often connected in series and fixed into a multi-channel receiving device, connected to the transmission cable, and the collected seismic waves are transmitted to the seismograph. This is an important component of the seismic transmission tomography system for field data collection, but it is suitable for vertical wells. The self-positioning function in deep and variable trajectory inclined wells is less developed.
[0004] When conducting seismic transmission tomography in the field, the detector combination receiving device can only control the moving length of the receiving device by manually or hingedly pulling and lowering the transmission composite cable, but there is no accurate spatial positioning information. Since the position of the lowered receiving device in the hole is unknown (such as deep inclined wells, track change wells, and curved tunnels), many unfavorable factors cause a large deviation in the pushing position of the receiving device on the well wall. When the final map is formed, there is no accurate tomographic boundary and the imaging range is distorted, which not only prolongs the detection cycle but also affects the detection quality.
[0005] Therefore, there is an urgent need for an acquisition method that can quickly, accurately and timely obtain seismic transmission wave signals and boundary conditions to meet the process requirements of in-hole seismic tomography technology in deep drilling projects and the interpretation accuracy requirements for formations. Summary of the invention
[0006] Based on this, an embodiment of the present invention provides an inter-well seismic tomography method and system based on inclinometer technology to solve the problems of inaccurate positioning of the downhole transceiver system and unclear boundary conditions when implementing inter-well seismic tomography in high-temperature conventional directional deep wells, thereby improving the imaging quality.
[0007] To achieve the above object, the present invention provides the following solutions:
[0008] A cross-well seismic tomography method based on inclination measurement technology, comprising:
[0009] The wellhead position coordinates of the exciting well and the wellhead position coordinates of the receiving well are obtained; the exciting well and the receiving well are both directional wells with a bottom hole temperature greater than a set temperature value and a well inclination angle less than a set angle; the wellhead position coordinates of the exciting well are measured by a first inclinometer in the first device when the first device is lowered to the exciting well; the wellhead position coordinates of the receiving well are measured by a second inclinometer in the second device when the second device is lowered to the receiving well; the first device and the second device are lowered simultaneously;
[0010] Acquire first inclination measurement data and second inclination measurement data; the first inclination measurement data is the inclination measurement data measured by the first inclinometer during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well; the second inclination measurement data is the inclination measurement data measured by the second inclinometer during the process of lowering the second device from the wellhead to the bottom of the well into the receiving well; the inclination measurement data includes well depth, well inclination angle and azimuth;
[0011] Determine the downhole trajectory of the entire well section of the stimulation well by the wellhead position coordinates of the stimulation well and the first inclination measurement data, and determine the downhole trajectory of the entire well section of the receiving well by the wellhead position coordinates of the receiving well and the second inclination measurement data;
[0012] Establishing an observation system for inter-well seismic tomography according to the downhole trajectory of the entire well section of the exciting well and the downhole trajectory of the entire well section of the receiving well;
[0013] Based on the observation system of the cross-well seismic tomography, field seismic data is collected; the field seismic data is seismic waves received by the detector in the second device at the corresponding receiving point when the first device and the second device are lifted up at the same time and the source in the first device excites one shot at each excitation point during the lifting process;
[0014] Acquire third inclination measurement data and fourth inclination measurement data; the third inclination measurement data is the inclination measurement data measured by the first inclinometer when the first device is lifting the stimulation well from the bottom of the well to the wellhead; the fourth inclination measurement data is the inclination measurement data measured by the second inclinometer when the second device is lifting the receiving well from the bottom of the well to the wellhead;
[0015] Obtaining the well trajectory of the entire well section of the stimulation well according to the wellhead position coordinates of the stimulation well, the first inclination measurement data, and the third inclination measurement data; obtaining the well trajectory of the entire well section of the receiving well according to the wellhead position coordinates of the receiving well, the second inclination measurement data, and the fourth inclination measurement data;
[0016] Extracting the first arrival wave travel time of the field seismic data;
[0017] Based on the well trajectory of the entire well section of the exciting well, the well trajectory of the entire well section of the receiving well and the travel time of the first arrival wave, the ray tomography method is used to determine the inter-well stratum structure image.
[0018] Optionally, determining the downhole trajectory of the entire well section of the stimulation well by using the wellhead position coordinates of the stimulation well and the first inclination survey data specifically includes:
[0019] Based on the first inclination measurement data, using an inclination measurement method to calculate the coordinate increment of each measurement point during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well;
[0020] Adding the coordinate increment to the wellhead position coordinate of the excitation well to obtain the spatial position coordinate of each measuring point;
[0021] The spatial position coordinates of each measuring point in the process of lowering the first device from the wellhead to the bottom of the stimulation well determine the downhole trajectory of the entire section of the stimulation well.
[0022] Optionally, the determining of the inter-well stratigraphic structure image by using ray tomography based on the well trajectory of the entire well section of the exciting well, the well trajectory of the entire well section of the receiving well and the travel time of the first arrival wave specifically includes:
[0023] Based on the well trajectory of the entire well section of the exciting well and the well trajectory of the entire well section of the receiving well, the formation between the exciting well and the receiving well is discretized, and the shortest path ray tracing method based on the Huygens principle is adopted to obtain the inter-well formation structure image based on the travel time of the first arrival wave.
[0024] Optionally, the formation between the excitation well and the receiving well is discretized based on the well trajectory of the whole well section of the excitation well and the well trajectory of the whole well section of the receiving well, and a shortest path ray tracing method based on the Huygens principle is adopted to obtain an inter-well formation structure image based on the travel time of the first arrival wave, specifically including:
[0025] Taking the designated point as the origin, a tomographic imaging calculation coordinate system is established;
[0026] The well trajectory of the whole well section of the exciting well and the well trajectory of the whole well section of the receiving well are uniformly corrected according to the tomographic imaging calculation coordinate system to obtain the corrected well trajectory of the whole well section of the exciting well and the corrected well trajectory of the whole well section of the receiving well;
[0027] In the tomography calculation coordinate system, the coordinate values of each actual seismic shot point, the coordinate values of each actual detection point and the shot-detection relationship are determined by taking the well trajectory of the whole well section of the excitation well and the well trajectory of the whole well section of the receiving well as the spatial boundary conditions of the tomography;
[0028] An initial velocity model for tomographic inversion is given; the tomographic inversion adopts a first relation and an eikonal equation; the first relation represents the relation between the first arrival wave travel time matrix, the velocity matrix, the slowness matrix and the ray coefficient matrix; the eikonal equation represents the relation between the seismic wave travel time model and the slowness model; the slowness model is represented by the slowness matrix; the velocity model is represented by the velocity matrix;
[0029] Based on the initial velocity model, the coordinate values of each actual seismic shot point, the coordinate values of each actual detection point, the shot detection relationship and the set grid discrete step length are used as parameters of tomographic inversion, the first arrival wave travel time is used as the input of the tomographic inversion, and the error is within a set range or the number of iterations reaches a set number of iterations as the goal, and the optimal slowness model is determined by an iterative method; wherein the error of the d-th iteration is the root mean square error between the calculated value of the first arrival wave travel time matrix obtained by the d-th iteration and the actually picked first arrival wave travel time matrix;
[0030] The optimal velocity model between all the excitation points and the receiving points is determined by the optimal slowness model, thereby obtaining an inter-well formation structure image.
[0031] Optionally, the step of calculating the coordinate increment of each measuring point during the process of lowering the first device from the wellhead to the bottom of the well by using an inclinometer method based on the first inclinometer data specifically includes:
[0032] Preprocessing the first inclinometer data to obtain preprocessed first inclinometer data; the preprocessing includes removing gross errors and correcting data;
[0033] The inclinometer method is used to calculate the coordinate increment of each measuring point during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well based on the preprocessed first inclinometer data.
[0034] Optionally, the inclinometer method is one of the minimum curvature method, the radius of curvature method, the corrected mean angle method and the chord step method.
[0035] Optionally, the set temperature value is 200°C; the set angle is 55°.
[0036] The present invention also provides an inter-well seismic tomography system based on the inclination measurement technology, comprising:
[0037] A wellhead position acquisition module is used to acquire the wellhead position coordinates of the excitation well and the wellhead position coordinates of the receiving well; the excitation well and the receiving well are both directional wells with a bottom hole temperature greater than a set temperature value and a well inclination angle less than a set angle; the wellhead position coordinates of the excitation well are measured by a first inclinometer in the first device when the first device is lowered to the excitation well; the wellhead position coordinates of the receiving well are measured by a second inclinometer in the second device when the second device is lowered to the receiving well; the first device and the second device are lowered simultaneously;
[0038] The downhole inclination data acquisition module is used to acquire first inclination data and second inclination data; the first inclination data is the inclination data measured by the first inclinometer during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well; the second inclination data is the inclination data measured by the second inclinometer during the process of lowering the second device from the wellhead to the bottom of the well into the receiving well; the inclination data includes well depth, well inclination angle and azimuth;
[0039] A downhole trajectory determination module, used to determine the downhole trajectory of the entire well section of the stimulation well according to the wellhead position coordinates of the stimulation well and the first inclination measurement data, and to determine the downhole trajectory of the entire well section of the receiving well according to the wellhead position coordinates of the receiving well and the second inclination measurement data;
[0040] An observation system determination module, used to establish an observation system for inter-well seismic tomography according to the downhole trajectory of the entire well section of the excitation well and the downhole trajectory of the entire well section of the receiving well;
[0041] A field seismic data acquisition module, used for acquiring field seismic data based on the observation system of the cross-well seismic tomography; the field seismic data is seismic waves received by the detector in the second device at the corresponding receiving point when the source in the first device excites one shot at each excitation point during the lifting process when the first device and the second device are lifted up simultaneously;
[0042] The lifting inclination measurement data acquisition module is used to acquire third inclination measurement data and fourth inclination measurement data; the third inclination measurement data is the inclination measurement data measured by the first inclinometer when the first device is lifting the stimulation well from the bottom of the well to the wellhead; the fourth inclination measurement data is the inclination measurement data measured by the second inclinometer when the second device is lifting the receiving well from the bottom of the well to the wellhead;
[0043] A full-well trajectory determination module, used to obtain the well trajectory of the full well section of the stimulation well according to the wellhead position coordinates of the stimulation well, the first inclination measurement data and the third inclination measurement data, and to obtain the well trajectory of the full well section of the receiving well according to the wellhead position coordinates of the receiving well, the second inclination measurement data and the fourth inclination measurement data;
[0044] A first-arrival wave travel time extraction module, used for extracting the first-arrival wave travel time of the field seismic data;
[0045] The imaging module is used to determine the inter-well stratum structure image by using ray tomography based on the well trajectory of the whole well section of the exciting well, the well trajectory of the whole well section of the receiving well and the travel time of the first arrival wave.
[0046] Compared with the prior art, the present invention has the following beneficial effects:
[0047] The embodiment of the present invention proposes a method and system for inter-well seismic tomography based on inclination measurement technology. The method uses the inclination measurement data measured by the inclinometer synchronously lowered into the well to determine the observation system of the inter-well seismic tomography; the observation system of the inter-well seismic tomography collects field seismic data; the well trajectory of the whole well section of the exciting well and the well trajectory of the whole well section of the receiving well are obtained by synchronously pulling the inclinometer, the source, and the detector; based on the well trajectory of the whole well section of the exciting well, the well trajectory of the whole well section of the receiving well and the extracted first arrival wave travel time, the ray tomography method is used to determine the inter-well formation structure image. Compared with the tomographic imaging range obtained when there is no measurement of the well trajectory, the imaging range of the present invention is closer to reality, solves the problems of inaccurate positioning and unclear boundary conditions of the downhole transceiver system, improves the correct homing ability and imaging accuracy of the inter-well formation structure, and greatly saves the process cost of loading the positioning system in the seismic detector, avoids the tediousness of various detection devices going down the well separately, reduces the damage to the wellbore, and improves the data interoperability between the inclination measurement technology and the inter-well seismic technology. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0049] Figure 1 A schematic diagram of the structure of a cross-well seismic tomography device based on inclination measurement technology provided by an embodiment of the present invention;
[0050] Figure 2 A flow chart of a cross-well seismic tomography method based on inclination measurement technology provided by an embodiment of the present invention;
[0051] Figure 3 A schematic diagram of a tomography calculation coordinate system provided by an embodiment of the present invention;
[0052] Figure 4 A schematic diagram of a specific implementation process of a cross-well seismic tomography method based on inclination measurement technology provided by an embodiment of the present invention;
[0053] Figure 5 A schematic diagram of the principle of result accuracy analysis based on well trajectory as a boundary provided by an embodiment of the present invention;
[0054] Figure 6 A structural diagram of an inter-well seismic tomography system based on inclination measurement technology provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0056] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0057] The borehole trajectory is the axis of the actual borehole, which is a spatial curve. The inclination measurement technology for measuring the borehole trajectory is a measurement technology developed at the same time as drilling technology. It can locate the trajectory of the drill bit, that is, the route of the hole in the formation. Inclination measurement technology can obtain parameters such as well depth, well inclination angle and well inclination azimuth, which can provide accurate boundary conditions for the seismic tomography forward and inversion technology of downhole measurement.
[0058] According to the strategic layout of energy resources advancing into the deep earth, seismic tomography technology faces the demands of high temperature and high pressure or even ultra-high temperature and high pressure special environments, deep well transmission and reception tomography, complex variable trajectory well type tomography, group well joint tomography, ground-well joint tomography, etc., and the requirements for tomography hardware and software equipment, improvement of forward and inverse algorithms, actual forward and inversion boundaries, and three-dimensional spatial position of tomography areas are becoming increasingly higher. There is an urgent need for an acquisition method that can quickly, accurately and timely obtain seismic transmission wave signals and boundary conditions to meet the process requirements of in-well seismic tomography technology in deep drilling projects and the requirements for the interpretation accuracy of formations.
[0059] The inter-well seismic tomography method of this embodiment is implemented based on an inter-well seismic tomography device. First, the inter-well seismic tomography device is introduced.
[0060] See also Figure 1The cross-well seismic tomography device comprises: a ground processing unit 1, a measurement control unit 9, a seismograph host 2, a first device and a second device; the first device comprises a seismic source 7 and a first inclinometer 6A arranged on the seismic source 7; the second device comprises a geophone 5 and a second inclinometer 6B arranged under the geophone 5; the ground processing unit 1 is connected to the measurement control unit 9 and the seismograph host 2 respectively; the measurement control unit 9 is connected to the first device and the second device respectively; the seismograph host 2 is connected to the first device and the second device respectively.
[0061] In practical applications, in the excitation well, the first inclinometer 6A is bound to the source 7, the source 7 is connected to the composite transmission cable 3, the source 7 is connected to the seismic instrument host 2 on the ground through the winch 4 installed at the excitation wellhead, the first inclinometer 6A is also connected to the composite transmission cable 8, and the first inclinometer 6A is connected to the ground measurement control unit 9 through the winch 4; in the receiving well, the second inclinometer 6B is bound below the detector 5, the detector 5 is connected to the composite transmission cable 3, the detector 5 is connected to the ground seismic instrument host 2 through the winch 4 installed at the receiving wellhead, the second inclinometer 6B is connected to the composite transmission cable 8, and the second inclinometer 6B is connected to the ground measurement control unit 9 through the winch 4; the ground measurement control unit 9 and the seismic instrument host 2 are respectively connected to the ground processing unit 1. Among them, the detector 5 can be a multi-channel seismic detector connected in series; the ground processing unit 1 can be a computer.
[0062] Based on the above cross-well seismic tomography device, see Figure 2 The cross-well seismic tomography method implemented in this embodiment includes:
[0063] Step 101: Obtain the wellhead position coordinates of the exciting well and the wellhead position coordinates of the receiving well.
[0064] The excitation well and the receiving well are both directional wells (high-temperature conventional directional wells) with a bottom hole temperature greater than a set temperature value and a well inclination angle less than a set angle; the wellhead position coordinates of the excitation well are measured by the first inclinometer in the first device when the first device is lowered to the excitation well; the wellhead position coordinates of the receiving well are measured by the second inclinometer in the second device when the second device is lowered to the receiving well; the first device and the second device are lowered at the same time. The set temperature value can be 200°C; the set angle can be 55°.
[0065] Step 102: Acquire first inclination measurement data and second inclination measurement data.
[0066] The first inclinometer data is the inclinometer data measured by the first inclinometer when the first device is lowered from the wellhead to the bottom of the well into the stimulation well; the second inclinometer data is the inclinometer data measured by the second inclinometer when the second device is lowered from the wellhead to the bottom of the well into the receiving well; the inclinometer data includes well depth, well inclination angle, azimuth, etc.
[0067] Step 103: Determine the downhole trajectory of the entire well section of the stimulation well based on the wellhead position coordinates of the stimulation well and the first inclination survey data, and determine the downhole trajectory of the entire well section of the receiving well based on the wellhead position coordinates of the receiving well and the second inclination survey data.
[0068] Wherein, the method for determining the downhole trajectory of the entire well section of the stimulation well is:
[0069] Based on the first inclination measurement data, the inclination measurement method is used to calculate the coordinate increment of each measuring point during the process of lowering the first device from the wellhead to the bottom of the well to the stimulation well; the coordinate increment is added to the wellhead position coordinate of the stimulation well to obtain the spatial position coordinate of each measuring point during the process of lowering the first device from the wellhead to the bottom of the well to the stimulation well; the wellbore trajectory of the entire section of the stimulation well is determined by the spatial position coordinate of each measuring point during the process of lowering the first device from the wellhead to the bottom of the well to the stimulation well. Among them, the calculation method of the coordinate increment of each measuring point during the process of lowering the stimulation well from the wellhead to the bottom of the well is:
[0070] The first inclination measurement data is preprocessed to obtain preprocessed first inclination measurement data; the preprocessing includes removing gross errors and correcting data; and the inclination measurement method is used to calculate the coordinate increment of each measurement point during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well. The inclination measurement method can be selected from one of the minimum curvature method, the curvature radius method, the corrected average angle method and the chord step method.
[0071] The method for determining the downhole trajectory of the entire well section of the receiving well is as follows:
[0072] Based on the second inclination measurement data, the inclination measurement method is used to calculate the coordinate increment of each measuring point during the lowering of the second device from the wellhead to the bottom of the well into the receiving well; the coordinate increment is added to the wellhead position coordinates of the receiving well to obtain the spatial position coordinates of each measuring point during the lowering of the second device from the wellhead to the bottom of the well into the receiving well; the wellbore trajectory of the entire well section of the receiving well is determined by the spatial position coordinates of each measuring point during the lowering of the second device from the wellhead to the bottom of the well into the receiving well. The method for calculating the coordinate increment of each measuring point during the lowering of the receiving well from the wellhead to the bottom of the well is similar to the method for calculating the coordinate increment corresponding to the excitation well, and will not be described in detail here.
[0073] Step 104: Establish an inter-well seismic tomography observation system according to the downhole trajectory of the entire well section of the exciting well and the downhole trajectory of the entire well section of the receiving well.
[0074] Step 105: Based on the cross-well seismic tomography observation system, field seismic data is collected.
[0075] The field seismic data is seismic waves received by the detector in the second device at the corresponding receiving point when the first device and the second device are lifted up simultaneously and the source in the first device fires a shot at each excitation point during the lifting process.
[0076] Step 106: Acquire third inclination measurement data and fourth inclination measurement data.
[0077] The third inclination measurement data are the inclination measurement data measured by the first inclinometer when the first device is lifting the stimulation well from the bottom of the well to the wellhead; the fourth inclination measurement data are the inclination measurement data measured by the second inclinometer when the second device is lifting the receiving well from the bottom of the well to the wellhead.
[0078] Step 107: Obtain the well trajectory of the entire well section of the excitation well according to the wellhead position coordinates of the excitation well, the first inclination measurement data, and the third inclination measurement data; obtain the well trajectory of the entire well section of the receiving well according to the wellhead position coordinates of the receiving well, the second inclination measurement data, and the fourth inclination measurement data.
[0079] This step is similar to the calculation method of step 103. Step 107 specifically includes:
[0080] After removing gross errors and correcting the data of the first inclinometer data, the second inclinometer data, the third inclinometer data and the fourth inclinometer data, the stable data are selected to calculate the average value, and the curve of the inclinometer data measured by going down and lifting up versus hole depth is plotted. According to the degree of fit, the inclinometer data is corrected, and then the inclinometer method is used to obtain the coordinate increment of each measuring point in the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well, the coordinate increment of each measuring point in the process of lowering the second device from the wellhead to the bottom of the well into the receiving well, the coordinate increment of each measuring point in the process of lifting the first device from the bottom of the well to the wellhead in the stimulation well, and the coordinate increment of each measuring point in the process of lifting the second device from the bottom of the well to the wellhead in the receiving well. Then, based on the coordinate increment, the wellhead position coordinates of the stimulation well, and the wellhead position coordinates of the receiving well, the well trajectory of the entire well section of the stimulation well and the well trajectory of the entire well section of the receiving well are obtained, and an intuitive well trajectory curve is plotted.
[0081] Step 108: extracting the first arrival wave travel time (travel time) of the field seismic data.
[0082] Step 109: Based on the well trajectory of the entire well section of the exciting well, the well trajectory of the entire well section of the receiving well and the travel time of the first arrival wave, a ray tomography method is used to determine the inter-well formation structure image.
[0083] In one example, in both step 103 and step 107, the minimum curvature method is used to calculate the coordinate increment, and the specific process is:
[0084] Assume that the well section between the two measuring points is a plane circular arc, and the arc is tangent to the wellbore directions at the upper and lower measuring points at the two end points.
[0085] Basic formula of minimum curvature method: Assume that there are N inclination survey data and the well depth of the i-th survey point is L i (Unit: m), well inclination angle is α i (unit is °, radians are used for calculation), azimuth is φ i , i = 1, ..., N. Use (X, Y, Z) to represent the north coordinate, east coordinate and vertical depth of any point on the wellbore trajectory. Then, in the i-th measurement section, the coordinate increment is calculated by the following formula:
[0086]
[0087]
[0088]
[0089]
[0090] Where: ΔL i =L i -L i-1 is the measuring section length, L i-1 Indicates the well depth of the i-1th measuring point; ΔX i =X i -X i-1 is the north coordinate increment, X i Indicates the north coordinate of the i-th measuring point, X i-1 Indicates the north coordinate of the i-1th measuring point; ΔY i =Y i -Y i-1 is the easting increment, Y i Indicates the east coordinate of the i-th measuring point, Y i-1 Indicates the east coordinate of the i-1th measuring point; ΔZ i =Z i -Z i-1 is the vertical depth increment, Z i represents the vertical coordinate of the ith measuring point, Z i-1 Indicates the vertical coordinate of the i-1th measuring point. ε i is the bending angle of the measuring segment, is the azimuth increment of the measuring section. i-1 is the well inclination angle of the i-1th measuring point, φ i-1 is the azimuth of the i-1th measuring point.
[0091] Since the calculation of each increment directly according to formula (1) to formula (4) requires many functions and many calculation times, especially for conventional directional deep wells such as exploration deep wells of high-temperature dry hot rocks and exploration and production combined wells, in order to improve the calculation speed and accuracy, the following optimization improvements are made during the inclination measurement calculation:
[0092] 1) Optimize the number of original measuring points of the inclinometer in the well, that is, arrange the measuring points according to the vertical section, inclination section, inclination stabilization section, and inclination reduction section, and increase the number of measuring points in the well section where high-temperature rock mass (hot dry rock reservoir) is encountered and the fracturing well section.
[0093] 2) Prioritize and optimize the functions in equations (1) to (4) to reduce the number of calculations.
[0094] 3) Optimization of the numerical relationship of the coordinate increment: For example, in a certain embodiment, the bending angle ε of the measuring section is i When is very small and close to 0, we can use the formula (1) to (3) Perform power series expansion and substitute equation (5) into equations (1)-(4) to calculate:
[0095]
[0096] In one example, step 109 specifically includes:
[0097] Based on the well trajectory of the entire well section of the excitation well and the well trajectory of the entire well section of the receiving well, the formation between the excitation well and the receiving well is discretized, and the shortest path ray tracing method based on the Huygens principle is used to obtain the inter-well formation structure image based on the first arrival wave travel time. Specifically:
[0098] 1) With the specified point as the origin, establish a tomographic imaging calculation coordinate system. Figure 3 shown.
[0099] 2) The well trajectory of the entire well section of the exciting well and the well trajectory of the entire well section of the receiving well are uniformly corrected according to the tomographic imaging calculation coordinate system to obtain the corrected well trajectory of the entire well section of the exciting well and the corrected well trajectory of the entire well section of the receiving well.
[0100] 3) In the tomographic imaging calculation coordinate system, the coordinate values of each actual seismic shot point, the coordinate values of each actual detection point and the shot-detection relationship are determined using the corrected well trajectory of the entire well section of the exciting well and the corrected well trajectory of the entire well section of the receiving well as the spatial boundary conditions of the tomography.
[0101] 4) Determine and set the discrete step length of the grid.
[0102] Set the discrete step lengths ΔX, ΔY, and ΔZ of the discrete grids in the X, Y, and Z directions of the tomographic area to determine the number of discrete grids and the number of grid nodes. The discrete grid step length is expressed as the horizontal component step length ΔH and the vertical step length ΔZ. The horizontal component step length ΔH and the discrete step length ΔS are introduced. The relationship between them is shown in equations (6) and (7). In order to reduce the amount of calculation, the tomographic calculation adopts the mode of first reducing the dimension and then increasing the dimension. Since the well trajectory is used as the tomographic boundary, the discrete step length ΔS at the boundary of the well trajectory is required to be greater than or equal to the minimum value of the excitation point distance and the detection point distance. No matter how small it is, it cannot achieve a higher resolution, unless the excitation point distance and the detection point distance have been compressed to a very small value during the field acquisition of the inter-well seismic tomography. For example, if a 10m long fracture is to be identified in the inter-well formation, the excitation point distance and the detection point distance should be set to a distance less than 10m during acquisition.
[0103]
[0104]
[0105] Formula (6)-Formula (7) is a dimensionality reduction process: the discrete step length is reduced from three dimensions of ΔX, ΔY, and ΔZ to two dimensions of ΔH and ΔZ. The set grid discrete step lengths determined in this step are ΔH and ΔZ, and the set grid discrete step lengths are used as one of the parameters of tomographic inversion.
[0106] 5) An initial velocity model for tomographic inversion is given; the tomographic inversion adopts a first relation and an oringin equation; the first relation represents the relation between the first arrival wave travel time matrix, the velocity matrix, the slowness matrix and the ray coefficient matrix; the oringin equation represents the relation between the seismic wave travel time model and the slowness model. The slowness model is represented by the slowness matrix; the velocity model is represented by the velocity matrix. The first relation is shown in equation (8), and the oringin equation is shown in equation (9).
[0107] 6) Based on the initial velocity model, the coordinate values of each actual seismic shot point, the coordinate values of each actual detection point, the shot detection relationship and the set grid discrete step length are used as parameters of the tomographic inversion, the first arrival wave travel time is used as the input of the tomographic inversion, and the error is within the set range or the number of iterations reaches the set number of iterations. The optimal slowness model is determined by the iteration method; wherein the error of the dth iteration is the root mean square error between the calculated value of the first arrival wave travel time matrix obtained by the dth iteration and the actually picked first arrival wave travel time matrix, and the calculation formula of the root mean square error is shown in formula (11). The actually picked first arrival wave travel time matrix is determined based on the input first arrival wave travel time.
[0108] Specifically: Use finite difference to approximate equation (9) into equation (10) and calculate the travel time T 0 , use formula (11) to calculate T 0 With T real The root mean square error E of the time is 1. When E is outside the set error range, the new travel time T is obtained according to the iterative formula (12): 1 , continue to iterate and get the slowness model M 1 , until the calculation error E is within the set range or the number of iterations reaches the set number of iterations F, the calculation is stopped. Generally, the final slowness model M is selected. F (H, Z) is the optimal slowness model. If the error E is within the set range at the dth iteration, the dth slowness model M can be selected. d (H, Z) is the optimal slowness model.
[0109]
[0110] Among them, A rq represents the length of the rth seismic wave inversion ray in the discrete grid q, R represents the total number of rays (total number of seismic records), Q represents the total number of discrete grids, and T r represents the travel time calculated for the rth seismic wave ray, V q represents the velocity value in the discrete grid q, M q represents the slowness value in the discrete grid q, Indicates M q The reciprocal of .
[0111]
[0112] The wavefront propagation time T(H, Z) and slowness M(H, Z) at a point (H, Z) in a two-dimensional medium are related by the above eikonal equation. By performing finite difference, equation (9) can be expressed as:
[0113]
[0114] Among them, T j,k represents the wavefront propagation time at the discrete grid in the jth row and the kth column, M j,k represents the slowness value at the discrete grid of the jth row and kth column, j represents the row number, k represents the column number, the row number is the number of the discrete grid in the H direction, the column number is the number of the discrete grid in the Z direction, ΔH and ΔZ are the discrete grid spacings in the H direction and the Z direction respectively. When j = 1, T j-1,k =0; when k=1, T j,k-1 =0.
[0115]
[0116] Among them, E d+1 represents the error at the d+1th iteration; R represents the total number of rays (the total number of seismic records), represents the calculated travel time of the e-th ray after the d+1th iteration, It represents the travel time value picked up by the e-th ray, and F is the set number of iterations.
[0117]
[0118] Among them, C real To pick up the data covariance matrix, C cal is the calculation model covariance matrix, f is the regularization factor, T real is the picked travel time matrix, A d is the ray coefficient matrix after the dth iteration, M d represents the slowness matrix obtained at the dth iteration, M d+1 Represents the slowness matrix obtained at the d+1th iteration.
[0119] 7) The optimal velocity model V(X, Y, Z) between all the excitation points and the receiving points is determined by the optimal slowness model, so as to obtain the inter-well formation structure image, which is the optimal inter-well formation structure image.
[0120] The optimal velocity model V(X,Y,Z) characterizes the inter-well seismic tomography results of the discrete grids between all the excitation points and the receiving points, that is, the inter-well formation structure image is obtained.
[0121] In practical applications, the working process of the above cross-well seismic tomography method is as follows:
[0122] Inclinometer and interwell seismic tomography technology are implemented simultaneously in high-temperature, deep and conventional directional wells. In the excitation and receiving wells, the inclinometer is bound to the source and the serial multi-channel seismic detector respectively. During the downhole process, the inclinometer can collect primary inclinometer data of the entire well section, laying the foundation for the deployment of the interwell seismic tomography observation system, and basically determine the tomographic boundary of the target layer. During the uphole process, the inclinometer and the interwell seismic tomography transceiver work independently and collect synchronously to obtain secondary inclinometer data of the entire well section and interwell seismic tomography acquisition data. In an independent coordinate system, the inclinometer calculation method such as minimum curvature is used, and the upper and lower well data are matched and corrected to obtain the well trajectory of each transmitting and receiving well. After the well trajectory is corrected to the new coordinate system of interwell seismic tomography, the real coordinates of the excitation point and the receiving point are implemented, and the discrete step length is determined. Through the travel time ray tomography calculation method of first reducing the dimension and then increasing the dimension, a high-precision seismic interpretation image of the interwell formation velocity structure is obtained.
[0123] See also Figure 4 , the specific working process is as follows:
[0124] Step 1: In a known high-temperature (T≥200℃) hot dry rock resource potential area, for inter-well seismic tomography field data acquisition (applicable to well spacing of about several hundred meters), select two conventional directional deep wells (well inclination angle α<55°) as the excitation well and the receiving well respectively.
[0125] Step 2: In the exciting well, the first inclinometer 6A is bound to the seismic source 7, the seismic source 7 is connected to the composite transmission cable 3, and is connected to the seismic instrument host 2 on the ground through the winch 4 installed at the exciting wellhead, the first inclinometer 6A is connected to the composite transmission cable 8, and is connected to the measurement control unit 9 on the ground through the winch 4; in the receiving well, the second inclinometer 6B is bound below the multi-channel seismic detector 5 in series, the detector 5 is connected to the composite transmission cable 3, and is connected to the seismic instrument host 2 on the ground through the winch 4 installed at the receiving wellhead, the second inclinometer 6B is connected to the composite transmission cable 8, and is connected to the measurement control unit 9 on the ground through the winch 4; the measurement control unit 9 and the seismic instrument host 2 on the ground are respectively connected to the ground processing unit 1.
[0126] Step three: In the excitation well, the seismic source 7 and the first inclinometer 6A are ready to be lowered into the well, and the first inclinometer 6A is used to obtain the wellhead position parameters of the excitation well, determine the wellhead position coordinates of the excitation well, and establish a coordinate system Co-A with the wellhead position of the excitation well as the origin, so that the subsequent original inclinometer data of the excitation well can be calculated uniformly in the same coordinate system Co-A.
[0127] Similarly, in the receiving well, the multi-channel seismic detector 5 and the second inclinometer 6B are ready to be lowered into the well, and the inclinometer 6B is used to obtain the wellhead position parameters of the receiving well, determine the wellhead position coordinates of the receiving well, and establish a coordinate system Co-B with the wellhead position of the receiving well as the origin, so that the subsequent measured original inclinometer data of the receiving well can be calculated uniformly in the same coordinate system Co-B.
[0128] Step 4: All equipment in the two wells are lowered into the wells. During the lowering process, the tomography equipment (source, detector) is only lowered into the well without being started, while the first inclinometer 6A and the second inclinometer 6B are measuring until the bottom of the well: 1) The working mode and transmission speed of the first inclinometer 6A are debugged, and the combined excitation equipment (first equipment) composed of the source 7 in the excitation well and the first inclinometer 6A begins to be lowered into the well. The first inclinometer A6 begins to measure until it reaches the bottom of the excitation well. The first inclinometer 6A measures the time, well inclination, azimuth, etc., and transmits the data back to the measurement control unit 9 on the ground. Compared with the time recorded on the ground and the measured hole depth recorded by the winch 4, the ground processing unit 1 obtains the inclination data A1 (i.e., the first inclinometer data) of the entire well section obtained during the downhole measurement process, including hole depth, well inclination, azimuth, etc. 2) Debug the working mode and transmission speed of the second inclinometer 6B, the joint receiving device (second device) composed of the detector 5 and the second inclinometer 6B in the receiving well starts to go down the well, and the second inclinometer 6B starts to measure until it reaches the bottom of the receiving well. The second inclinometer 6B measures the time, well inclination, azimuth, etc., and transmits the data back to the measurement control unit 9 on the ground. Compared with the time recorded on the ground and the measured hole depth recorded by the winch 4, the ground processing unit 1 obtains the inclination data B1 (i.e., the second inclinometer data) of the entire well section obtained during the downhole measurement process, including hole depth, well inclination, azimuth, etc.
[0129] Step 5: Pre-process the original inclination data A1 and B1 obtained in step 4, remove gross errors and correct the data, and then use the inclination method to obtain the downhole trajectory AX of the entire well section of the exciting well and the downhole trajectory BX of the entire well section of the receiving well, and draw an intuitive well trajectory curve on the computer.
[0130] In the process of calculating the well trajectory of a single well: the well inclination angle α and azimuth angle in the inclination data are Substitute into equations (1) to (5) to calculate the coordinate increment ΔX of all measuring points obtained by inclinometric calculation: i , ΔY i , ΔZi , and then add it to the coordinates of the wellhead origin position to obtain the spatial position coordinates X, Y, Z in the coordinate system, that is, the well trajectory in space.
[0131] Step 6: Based on the downhole trajectory AX, BX of step 5, i.e., the coordinates X, Y, Z of all the measuring points in the whole well section of the excitation well and the receiving well, the observation system of the inter-well seismic tomography is preliminarily designed in the ground processing unit 1. The observation system of the seismic tomography includes selecting the target layer section, setting the position of the excitation point of the source 7, the excitation point spacing, the position of the receiving point of the geophone 5, the receiving point spacing, the number of excitation points (shots) of the source 7, the number of lifting times of the multi-channel seismic geophones 5 in series, etc., so as to achieve the predetermined resolution of the inter-well seismic tomography, cover the target layer, etc.
[0132] Step 7: After the equipment is lifted, implement field seismic data acquisition of inter-well seismic tomography based on the designed observation system. The excitation or receiving section should include the exploration target layer as much as possible:
[0133] 1) The combined excitation device consisting of the seismic source 7 and the first inclinometer 6A in the excitation well begins to be lifted to the starting excitation point, and the combined receiving device consisting of the series multi-channel seismic detector 5 and the second inclinometer 6B in the receiving well begins to be lifted to the starting receiving point;
[0134] 2) The geophone 5 is pushed against the receiving well wall, and the seismic source 7 excites a shot, which is transmitted in the inter-well formation and then received by the geophone 5 and transmitted to the seismic control unit 2 on the ground and stored as a seismic single shot record;
[0135] 3) The source 7 is lifted up to the next shot point for excitation, and the multi-channel seismic detectors 5 connected in series are lifted up to the next receiving section for reception, and the excitation and reception are repeated in this way until the acquisition is completed to obtain the field seismic data.
[0136] Step 8: As the equipment in the well is lifted up, the inter-well seismic tomography equipment is working, and the first inclinometer 6A and the second inclinometer 6B are lifted up for re-measurement until they are lifted out of the wellhead. The first inclinometer 6A and the second inclinometer 6B measure the time, well inclination, azimuth, etc., and transmit the data back to the ground measurement control unit 9, which is compared with the time recorded on the ground and the measured hole depth recorded by the winch 4. The ground processing unit 1 obtains the inclination data A2 and B2 of the entire well section obtained during the lifting measurement process, including the hole depth, well inclination, azimuth, etc.
[0137] Step nine: For a large amount of original inclination measurement data A1, B1, A2, B2 obtained in steps four and eight, after removing gross errors and correcting the data, select the stabilized data to find the average value, and draw the curve of the inclination measurement data measured by going down and up with the hole depth. According to the degree of fit, correct the inclination measurement data, and then use the inclination measurement method to obtain the well trajectory AF of the entire well section of the exciting well and the well trajectory BF of the entire well section of the receiving well, and draw an intuitive well trajectory curve on the computer.
[0138] Step 10: In order to perform seismic tomography calculations between the excitation well and the receiving well, the coordinate values need to be unified in the same coordinate system: a new coordinate system Co-C is established with the specified point as the origin; the well trajectory coordinates AF and BF obtained in step 9 are uniformly corrected and calculated as the well trajectory coordinates under the coordinate system Co-C;
[0139] Step 11: In the new coordinate system Co-C established for interwell seismic tomography, the exciting well trajectory AF and the receiving well trajectory BF are used as the spatial boundary conditions of the tomography, the coordinate values of the actual shot points and receiver points in the field of the interwell seismic tomography method, and the shot-receiver relationship file are determined, the grid discrete step lengths ΔX, ΔY, ΔZ of the interwell seismic tomography calculation are set, and the initial velocity model is set as the parameters of the tomography inversion;
[0140] Step 12: extracting the first arrival wave travel time (travel time) t from the field seismic data record obtained in step 7 as input data for ray tomography inversion;
[0141] Step 13: Adopt the calculation sequence of first reducing dimension and then increasing dimension, use the travel time ray tracing tomography method, after F iterations, calculate F slowness models, use the Fth model or the previous dth model as the inversion slowness model result of inter-well seismic tomography, and obtain the optimal velocity model V (X, Y, Z), so as to obtain a high-precision inter-well formation velocity structure image. The specific processing flow is as follows:
[0142] 1) According to equations (6) and (7), the grid discrete step lengths ΔX, ΔY, and ΔZ are reduced in dimension to determine and set the grid discrete step lengths to ΔH and ΔZ.
[0143] 2) The discrete grids are numbered in a certain order, the initial wave velocity of each discrete grid node is set, and the corresponding initial slowness model is obtained.
[0144] 4) Pick up the first arrival wave travel time (travel time) t of the earthquake record as the tomographic input data.
[0145] 5) Combining equations (8) to (12), we obtain the optimal velocity model V(H, Z) corresponding to the optimal slowness model. We upgrade the dimension of V(H, Z) to obtain the final optimal velocity model V(X, Y, Z), and enter the mapping and next geological interpretation stage.
[0146] The working principle of the cross-well seismic tomography in this embodiment is:
[0147] Without changing the original geophone positioning process, when implementing the field acquisition seismic tomography method in conventional directional deep wells in high-temperature hot dry rock resource potential areas, the inclinometer for measuring the well trajectory is fixedly connected to the inter-well seismic tomography device (source or geophone), and the two are synchronously lowered into the well and work independently. They are interconnected during processing and calculation in the ground processing unit. The drilling inclinometer data is used to guide the design of the inter-well seismic tomography observation system. The inclinometer is synchronously lifted with the source and geophone of the inter-well seismic tomography to obtain the real spatial coordinates of the excitation receiving point, providing accurate boundary constraints for inter-well seismic tomography.
[0148] Based on the above principles, the inter-well seismic tomography method of this embodiment, regardless of whether the well trajectory data is lacking or not, is not limited by the transmission length and stratum lithology, and the synchronous detection reduces the damage to the wellbore caused by the various detection devices being lowered into the well separately. It only needs to bind the inclinometer and the inter-well seismic transceiver without permanent fixation, does not limit the number of seismic detectors, saves the process cost of installing the self-positioning system in the seismic detector, has small interference during detection, accurate imaging range, higher interpretation accuracy, and improves the data interoperability between the inclinometer technology and the inter-well seismic technology. It can be applied to conventional directional well projects such as deep high-temperature dry hot rock drilling, hydrothermal drilling, scientific drilling wells, oil and gas drilling, and mine tunnels.
[0149] The effectiveness of the method of this embodiment is verified below. Figure 5 , the existing tomographic imaging range obtained when there is no measurement well trajectory is the range surrounded by A, B, C, and D, where A represents the distorted left boundary of the imaging area, B represents the distorted upper boundary of the imaging area, C represents the distorted right boundary of the imaging area, and D represents the distorted lower boundary of the imaging area. Based on the above principle, the imaging range of the method implemented in this embodiment is the range surrounded by A', B', C', and D', where A' represents the true left boundary of the imaging area, B' represents the true upper boundary of the imaging area, C' represents the true right boundary of the imaging area, and D' represents the true lower boundary of the imaging area. Compared with the tomographic imaging range obtained when there is no measurement well trajectory, the imaging range of the method in this embodiment is closer to the truth and can more accurately interpret the inter-well formation characteristics, which is reflected in the fact that the distorted predicted fracture F interpreted is relocated to the real predicted fracture F', which improves the correct relocation capability and imaging accuracy of the inter-well formation structure, and at the same time greatly saves the process cost of loading the positioning system in the seismic detector, avoids the cumbersomeness of various detection devices going down the well separately, reduces the damage to the wellbore, and improves the data interoperability between the inclination measurement technology and the inter-well seismic technology.
[0150] The present invention also provides a cross-well seismic tomography system based on inclination measurement technology, see Figure 6 , the system comprising:
[0151] The wellhead position acquisition module 201 is used to obtain the wellhead position coordinates of the excitation well and the wellhead position coordinates of the receiving well; the excitation well and the receiving well are both directional wells with bottom hole temperature greater than a set temperature value and well inclination angle less than a set angle; the wellhead position coordinates of the excitation well are measured by the first inclinometer in the first device when the first device is lowered to the excitation well; the wellhead position coordinates of the receiving well are measured by the second inclinometer in the second device when the second device is lowered to the receiving well; the first device and the second device are lowered simultaneously.
[0152] The downhole inclinometer data acquisition module 202 is used to acquire first inclinometer data and second inclinometer data; the first inclinometer data is the inclinometer data measured by the first inclinometer when the first device is lowered from the wellhead to the bottom of the well into the stimulation well; the second inclinometer data is the inclinometer data measured by the second inclinometer when the second device is lowered from the wellhead to the bottom of the well into the receiving well; the inclinometer data includes well depth, well inclination angle and azimuth.
[0153] The downhole trajectory determination module 203 is used to determine the downhole trajectory of the entire well section of the stimulation well based on the wellhead position coordinates of the stimulation well and the first inclination measurement data, and to determine the downhole trajectory of the entire well section of the receiving well based on the wellhead position coordinates of the receiving well and the second inclination measurement data.
[0154] The observation system determination module 204 is used to establish an observation system for inter-well seismic tomography according to the downhole trajectory of the entire well section of the exciting well and the downhole trajectory of the entire well section of the receiving well.
[0155] The field seismic data acquisition module 205 is used to collect field seismic data based on the observation system of the inter-well seismic tomography; the field seismic data is the seismic waves received by the detector in the second device at the corresponding receiving point when the first device and the second device are lifted up at the same time and the source in the first device fires a shot at each excitation point during the lifting process.
[0156] The lifting inclination data acquisition module 206 is used to obtain third inclination data and fourth inclination data; the third inclination data is the inclination data measured by the first inclinometer when the first device is lifting the stimulation well from the bottom of the well to the wellhead; the fourth inclination data is the inclination data measured by the second inclinometer when the second device is lifting the receiving well from the bottom of the well to the wellhead.
[0157] The full-well trajectory determination module 207 is used to obtain the well trajectory of the entire well section of the stimulation well based on the wellhead position coordinates of the stimulation well, the first inclination measurement data and the third inclination measurement data, and to obtain the well trajectory of the entire well section of the receiving well based on the wellhead position coordinates of the receiving well, the second inclination measurement data and the fourth inclination measurement data.
[0158] The first-arrival traveltime extraction module 208 is used to extract the first-arrival traveltime of the field seismic data.
[0159] The imaging module 209 is used to determine the inter-well formation structure image by using ray tomography based on the well trajectory of the entire well section of the exciting well, the well trajectory of the entire well section of the receiving well and the travel time of the first arrival wave.
[0160] The inter-well seismic tomography system of this embodiment is a new idea of tomography acquisition and processing based on the inclination measurement technology and the boundary requirements of the in-well seismic transmission tomography. It is applicable to a wide range of well types and is no longer limited to the use of manual or hinged moving distance in vertical wells to directly determine the well depth and receiving position, but can also truly locate the transceiver system in conventional directional deep wells. The present invention is not limited by the transmission length, drilling depth, formation temperature, and lithology, and has no effect on the process and drilling tools and measuring devices of the receiving detector. It effectively avoids the limitations of the existing in-well seismic tomography technology being limited by high-temperature deep inclined wells, lack of well trajectory data, and inaccurate lowering position of the receiving device. The accurate position and boundary range corresponding to the seismic tomography velocity, amplitude and other information obtained are highly accurate, and can be applied to deep high-temperature hot dry rock drilling, hydrothermal drilling, scientific drilling wells, oil and gas drilling and other projects.
[0161] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the system disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0162] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A cross-well seismic tomography method based on inclination measurement technology, characterized in that: include: The wellhead position coordinates of the exciting well and the wellhead position coordinates of the receiving well are obtained; the exciting well and the receiving well are both directional wells with a bottom hole temperature greater than a set temperature value and a well inclination angle less than a set angle; the wellhead position coordinates of the exciting well are measured by a first inclinometer in the first device when the first device is lowered to the exciting well; the wellhead position coordinates of the receiving well are measured by a second inclinometer in the second device when the second device is lowered to the receiving well; the first device and the second device are lowered simultaneously; Acquire first inclination measurement data and second inclination measurement data; the first inclination measurement data is the inclination measurement data measured by the first inclinometer during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well; the second inclination measurement data is the inclination measurement data measured by the second inclinometer during the process of lowering the second device from the wellhead to the bottom of the well into the receiving well; the inclination measurement data includes well depth, well inclination angle and azimuth; Determine the downhole trajectory of the entire well section of the stimulation well by the wellhead position coordinates of the stimulation well and the first inclination measurement data, and determine the downhole trajectory of the entire well section of the receiving well by the wellhead position coordinates of the receiving well and the second inclination measurement data; Establishing an observation system for inter-well seismic tomography according to the downhole trajectory of the entire well section of the exciting well and the downhole trajectory of the entire well section of the receiving well; Based on the observation system of the cross-well seismic tomography, field seismic data is collected; the field seismic data is seismic waves received by the detector in the second device at the corresponding receiving point when the first device and the second device are lifted up at the same time and the source in the first device excites one shot at each excitation point during the lifting process; Acquire third inclination measurement data and fourth inclination measurement data; the third inclination measurement data is the inclination measurement data measured by the first inclinometer when the first device is lifting the stimulation well from the bottom of the well to the wellhead; the fourth inclination measurement data is the inclination measurement data measured by the second inclinometer when the second device is lifting the receiving well from the bottom of the well to the wellhead; Obtaining the well trajectory of the entire well section of the stimulation well according to the wellhead position coordinates of the stimulation well, the first inclination measurement data, and the third inclination measurement data; obtaining the well trajectory of the entire well section of the receiving well according to the wellhead position coordinates of the receiving well, the second inclination measurement data, and the fourth inclination measurement data; Extracting the first arrival wave travel time of the field seismic data; Based on the well trajectory of the entire well section of the exciting well, the well trajectory of the entire well section of the receiving well and the travel time of the first arrival wave, the ray tomography method is used to determine the inter-well stratum structure image.
2. The method for cross-well seismic tomography based on inclination measurement technology according to claim 1, characterized in that: The method of determining the downhole trajectory of the entire well section of the stimulation well by using the wellhead position coordinates of the stimulation well and the first inclination survey data specifically includes: Based on the first inclination measurement data, using an inclination measurement method to calculate the coordinate increment of each measurement point during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well; Adding the coordinate increment to the wellhead position coordinate of the excitation well to obtain the spatial position coordinate of each measuring point; The spatial position coordinates of each measuring point in the process of lowering the first device from the wellhead to the bottom of the stimulation well determine the downhole trajectory of the entire section of the stimulation well.
3. The method for cross-well seismic tomography based on inclination measurement technology according to claim 1, characterized in that: The method of determining the inter-well stratigraphic structure image by using ray tomography based on the well trajectory of the entire well section of the excitation well, the well trajectory of the entire well section of the receiving well and the travel time of the first arrival wave specifically includes: Based on the well trajectory of the entire well section of the exciting well and the well trajectory of the entire well section of the receiving well, the formation between the exciting well and the receiving well is discretized, and the shortest path ray tracing method based on the Huygens principle is adopted to obtain the inter-well formation structure image based on the travel time of the first arrival wave.
4. The method for cross-well seismic tomography based on inclination measurement technology according to claim 3, characterized in that: The well trajectory of the whole well section of the exciting well and the well trajectory of the whole well section of the receiving well are used to discretize the formation between the exciting well and the receiving well, and the shortest path ray tracing method based on the Huygens principle is used to obtain the inter-well formation structure image based on the travel time of the first arrival wave, which specifically includes: Taking the designated point as the origin, a tomographic imaging calculation coordinate system is established; The well trajectory of the whole well section of the exciting well and the well trajectory of the whole well section of the receiving well are uniformly corrected according to the tomographic imaging calculation coordinate system to obtain the corrected well trajectory of the whole well section of the exciting well and the corrected well trajectory of the whole well section of the receiving well; In the tomography calculation coordinate system, the coordinate values of each actual seismic shot point, the coordinate values of each actual detection point and the shot-detection relationship are determined by taking the well trajectory of the whole well section of the excitation well and the well trajectory of the whole well section of the receiving well as the spatial boundary conditions of the tomography; An initial velocity model for tomographic inversion is given; the tomographic inversion adopts a first relation and an eikonal equation; the first relation represents the relation between the first arrival wave travel time matrix, the velocity matrix, the slowness matrix and the ray coefficient matrix; the eikonal equation represents the relation between the seismic wave travel time model and the slowness model; the slowness model is represented by the slowness matrix; the velocity model is represented by the velocity matrix; Based on the initial velocity model, the coordinate values of each actual seismic shot point, the coordinate values of each actual detection point, the shot detection relationship and the set grid discrete step length are used as parameters of tomographic inversion, the first arrival wave travel time is used as the input of the tomographic inversion, and the error is within a set range or the number of iterations reaches a set number of iterations as the goal, and the optimal slowness model is determined by an iterative method; wherein the error of the d-th iteration is the root mean square error between the calculated value of the first arrival wave travel time matrix obtained by the d-th iteration and the actually picked first arrival wave travel time matrix; The optimal velocity model between all the excitation points and the receiving points is determined by the optimal slowness model, thereby obtaining an inter-well formation structure image.
5. The method for cross-well seismic tomography based on inclination measurement technology according to claim 2, characterized in that: The step of calculating the coordinate increment of each measuring point in the process of lowering the first device from the wellhead to the bottom of the well by using the inclinometer method based on the first inclinometer data specifically includes: Preprocessing the first inclinometer data to obtain preprocessed first inclinometer data; the preprocessing includes removing gross errors and correcting data; The inclinometer method is used to calculate the coordinate increment of each measuring point during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well based on the preprocessed first inclinometer data.
6. The method for cross-well seismic tomography based on inclination measurement technology according to claim 2, characterized in that: The inclinometer method is one of a minimum curvature method, a curvature radius method, a corrected mean angle method, and a chord step method.
7. The method for cross-well seismic tomography based on inclination measurement technology according to claim 1, characterized in that: The set temperature value is 200°C; the set angle is 55°.
8. A cross-well seismic tomography system based on inclination measurement technology, characterized in that: include: A wellhead position acquisition module is used to acquire the wellhead position coordinates of the excitation well and the wellhead position coordinates of the receiving well; the excitation well and the receiving well are both directional wells with a bottom hole temperature greater than a set temperature value and a well inclination angle less than a set angle; the wellhead position coordinates of the excitation well are measured by a first inclinometer in the first device when the first device is lowered to the excitation well; the wellhead position coordinates of the receiving well are measured by a second inclinometer in the second device when the second device is lowered to the receiving well; the first device and the second device are lowered simultaneously; The downhole inclination data acquisition module is used to acquire first inclination data and second inclination data; the first inclination data is the inclination data measured by the first inclinometer during the process of lowering the first device from the wellhead to the bottom of the well into the stimulation well; the second inclination data is the inclination data measured by the second inclinometer during the process of lowering the second device from the wellhead to the bottom of the well into the receiving well; the inclination data includes well depth, well inclination angle and azimuth; A downhole trajectory determination module, used to determine the downhole trajectory of the entire well section of the stimulation well according to the wellhead position coordinates of the stimulation well and the first inclination measurement data, and to determine the downhole trajectory of the entire well section of the receiving well according to the wellhead position coordinates of the receiving well and the second inclination measurement data; An observation system determination module, used to establish an observation system for inter-well seismic tomography according to the downhole trajectory of the entire well section of the excitation well and the downhole trajectory of the entire well section of the receiving well; A field seismic data acquisition module, used for acquiring field seismic data based on the observation system of the cross-well seismic tomography; the field seismic data is seismic waves received by the detector in the second device at the corresponding receiving point when the source in the first device excites one shot at each excitation point during the lifting process when the first device and the second device are lifted up simultaneously; The lifting inclination measurement data acquisition module is used to acquire third inclination measurement data and fourth inclination measurement data; the third inclination measurement data is the inclination measurement data measured by the first inclinometer when the first device is lifting the stimulation well from the bottom of the well to the wellhead; the fourth inclination measurement data is the inclination measurement data measured by the second inclinometer when the second device is lifting the receiving well from the bottom of the well to the wellhead; A full-well trajectory determination module, used to obtain the well trajectory of the full well section of the stimulation well according to the wellhead position coordinates of the stimulation well, the first inclination measurement data and the third inclination measurement data, and to obtain the well trajectory of the full well section of the receiving well according to the wellhead position coordinates of the receiving well, the second inclination measurement data and the fourth inclination measurement data; A first-arrival wave travel time extraction module, used for extracting the first-arrival wave travel time of the field seismic data; The imaging module is used to determine the inter-well stratum structure image by using ray tomography based on the well trajectory of the whole well section of the exciting well, the well trajectory of the whole well section of the receiving well and the travel time of the first arrival wave.