A method for synchronous and continuous advancement of large tunnel construction and surrounding rock internal ring support construction
By using a combined construction method of excavation equipment and annular elastic support drilling rigs in the construction of large tunnels, and using the ground shaft transportation system to alternately arrange and use drilling rigs, the problem that excavation equipment and annular support construction cannot be synchronized in traditional construction is solved, and efficient Simultaneous and continuous advancement improves construction efficiency and economic benefits.
Patent Information
- Application Number
- CN202210853874.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-12
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2042-07-12
AI Technical Summary
In the construction of soft rock formations or submarine tunnels, the traditional method of supporting first and then tunneling results in the inability to synchronize the construction of tunneling equipment and annular elastic supports, resulting in time and space conflicts, resulting in low construction efficiency, high costs, and complicated processes.
A method of synchronous and continuous advancement of large-scale tunnel construction and annular support construction inside the surrounding rock is adopted. Through the combined construction method of excavation equipment and annular elastic support drilling rigs, the ground shaft transportation system is used to alternately arrange and use installation drilling rigs and drilling drilling rigs to ensure that drilling The rods are always ahead of the excavation equipment, enabling simultaneous installation of the annular elastic supports.
It realizes the simultaneous and continuous advancement of large-scale tunnel construction and the construction of annular supports inside the tunnel surrounding rock, improves construction efficiency, reduces uncertainties caused by excavation equipment shutdowns, simplifies construction layout, and enhances economic benefits.
Smart Images

Figure CN115182742B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel support, is applicable to soft rock formations or submarine tunnels, and meets the problem of synchronously and continuously advancing the laying of elastic annular supports in the surrounding rock of large tunnels in a supporting manner before excavation and tunnel excavation construction. Background Art
[0002] Under soft rock conditions, tunnel surrounding rock is not easy to support. The traditional technical method and experience is to adopt high-density, high-rigidity combined support technical solutions, but this type of support method has problems such as high cost, complicated support procedures, long construction time, and high support labor intensity. In addition, traditional support is a construction method of first construction and then support. According to the support technology and construction method of annular elastic supports arranged in the rock body, which are newly proposed in recent years, the excavation construction and the drilling construction related to the annular elastic drilling rig have time and space contradictions and cannot be carried out simultaneously.
[0003] Aiming at the technical problems of this engineering equipment, a simple and feasible combined construction method of tunneling equipment (shield machine) and annular elastic support drilling rig is proposed on the basis of analyzing the construction layout process of large-scale tunnel boring equipment (shield machine). The purpose is to realize the synchronous and continuous advancement of large-scale tunnel construction and the construction of annular supports inside the tunnel surrounding rock in an economical and efficient manner through the combined construction method of new tunnel boring equipment (shield machine) and annular elastic support drilling rig, improve construction efficiency, increase economic benefits, and reduce a series of uncertainties caused by the downtime of tunnel boring equipment (shield machine). Summary of the invention
[0004] In view of this, the present invention provides a method for synchronously and continuously advancing the construction of a large tunnel and the construction of an annular support inside the surrounding rock, aiming to solve the problem that the construction of a large tunnel and the construction of annular support inside the tunnel surrounding rock are contradictory in time and space and cannot be constructed synchronously and continuously.
[0005] In order to achieve the above object, the present invention adopts the following technical solution:
[0006] A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction, specifically comprising the following steps:
[0007] S1. The excavation equipment is transported underground through the ground shaft and arranged in the underground excavation working face tunnel, facing the predetermined direction of the underground space; the corresponding supporting system is arranged at the rear of the excavation equipment; the supporting system includes ventilation equipment, transportation equipment and power communication equipment;
[0008] S2. The installation drill rig is transported underground through the ground shaft and arranged on one side of the tunnel directly behind the tunneling equipment. A transportation road is arranged on the other side of the tunnel. The front end of the installation drill rig is directed toward the rear of the tunneling equipment. The installation drill rig is started to drill a circular drill rod along the tunneling direction.
[0009] S3. After the excavation equipment has been constructed to a certain distance, the installation drilling rig 2 is transported to the underground through the ground shaft for installation construction, and the installation drilling rig 2 cooperates with the installation drilling rig 1 to perform construction in an alternating cycle;
[0010] S4. After the tunnel construction reaches a certain progress, the connecting drilling rig 1 is transported underground through the ground shaft, and the tunnel surrounding rock ring support is installed by the connecting drilling rig 1 in conjunction with the installation drilling rig 1;
[0011] S5. After the tunnel construction reaches a certain progress, the second connecting drilling rig is transported to the underground through the ground shaft for installation, and the second connecting drilling rig cooperates with the second installation drilling rig to carry out the installation construction of the tunnel surrounding rock ring support;
[0012] S6. By installing drilling rig 1, installing drilling rig 2, connecting drilling rig 1, and connecting drilling rig 2 in the underground tunnel, the drill rod in the tunnel surrounding rock is always ahead of the excavation working face of the excavation equipment. After the individual drilling construction is completed, the elastic ring support is dragged back into the tunnel surrounding rock, thereby forming a permanent elastic ring support in the tunnel surrounding rock.
[0013] The method for synchronously and continuously advancing the large-scale tunnel construction and the surrounding rock internal annular support construction provided by the present invention can be divided into the following steps in detail:
[0014] A. The tunneling equipment and its supporting systems are transported to the tunnel working face through the shaft and placed at the shield machine position one; a drilling rig installation construction platform is arranged on one side of the tunnel directly behind the tunneling equipment, and the drilling rig installation one is transported to the drilling rig position one of the drilling rig installation construction platform through the ground shaft; the drilling rig installation is started, and circular drilling construction is performed in the tunnel surrounding rock according to the radius R1 along the direction of the tunneling equipment.
[0015] B. After the annular drill exceeds the front shield of the tunneling equipment by a certain distance, start the tunneling equipment to carry out tunneling support construction.
[0016] C. When the tunneling equipment advances a certain distance and reaches the shield machine position 2, a drilling rig installation platform is arranged on the side of the tunnel directly behind the tunneling equipment, and the drilling rig installation platform is transported to the drilling rig position 2 of the drilling rig installation platform through the ground shaft; the drilling rig installation platform is started, and circular drilling construction is carried out in the tunnel surrounding rock along the direction of the tunneling equipment according to the radius R2.
[0017] D. After the installation drilling rig 1 reaches the target position, stop construction and leave the navigation drill bit in the tunnel surrounding rock. After the excavation equipment reaches the position and continues to excavate for a certain distance, it reaches the shield machine position 3, and arranges the drilling rig connection platform of the drilling rig 1 at the position where the installation drilling rig 1 stops construction to form the drilling rig position 3. The drilling rig 1 is transported to the drilling rig position 3 by the shaft and tunnel transportation tools. The drilling rig 1 is used to guide the drill bit from the tunnel floor into the tunnel. The navigation drill bit is replaced by the drilling rig 1 to the pull-back drill bit, and the elastic ring is connected. The elastic annular bracket is used to pull the elastic annular bracket back to a drilling position in the tunnel surrounding rock borehole, or when the engineering design requires the tunnel surrounding rock borehole to be expanded, the navigation drill bit is replaced with an expansion drill bit by using the connecting drill rig, and the drill rod is connected to expand the hole. After the expansion is completed, the expansion drill bit is replaced with a return drill bit, and the elastic annular bracket is connected to pull the elastic annular bracket back to a drilling position in the tunnel surrounding rock borehole. Finally, the annular elastic bracket in the tunnel surrounding rock is fixed and grouting is performed to complete the construction of the first section of the tunnel surrounding rock annular elastic bracket. Since the borehole is larger than the drill rod, the gap between them cannot rely solely on the mud during drilling, but requires a solidified slurry to fit tightly with the surrounding rock to achieve a synergistic bearing effect between the surrounding rock and the bracket.
[0018] E. The installation drilling rig and tunneling equipment continue construction. When the tunneling equipment is constructed to shield machine position four, a construction platform for installing drilling rig one is set up behind the tunneling equipment, that is, drilling rig position four. The installation drilling rig one is disassembled and transported to the tunneling construction platform. The installation drilling rig one is started and circular drilling construction is carried out in the tunnel surrounding rock along the direction of the tunneling equipment according to the radius R1.
[0019] F. After the installation drilling rig 2 reaches the target position, the construction is stopped and the navigation drill bit is left in the tunnel surrounding rock. After the excavation equipment reaches the position and continues to excavate for a certain distance, it reaches the shield machine position 5. The construction platform for receiving the drilling rig 2 is arranged at the drill outlet position to form the drilling rig position 5. The drilling rig 2 is transported to the construction platform for receiving the drilling rig 2 by the shaft and tunnel transportation tools. The navigation drill bit is introduced from the tunnel floor into the tunnel by the installation drilling rig 2, and the navigation drill bit is replaced by the drilling rig 2 to return to the tunnel. Drag the drill bit and connect the elastic annular bracket, and drag the elastic annular bracket back to the second drilling rig position in the tunnel surrounding rock drill hole; or when it is necessary to expand the tunnel surrounding rock drill hole, use the second drill rig to replace the navigation drill bit with an expansion drill bit, and connect the drill rod to carry out expansion construction. After the expansion is completed, replace the expansion drill bit with a return drill bit, and connect the elastic annular bracket, and drag the elastic annular bracket back to the second drilling rig position in the tunnel surrounding rock drill hole to complete the construction of the second section of the tunnel surrounding rock annular elastic bracket.
[0020] G. Install Drilling Rig 1 and the tunneling equipment to continue construction. When the tunneling equipment reaches the shield machine position 6, set up a construction platform for installing Drilling Rig 2 behind the tunneling equipment. Dismantle Drilling Rig 2 and transport it to the construction platform. Start Drilling Rig 2 and perform circular drilling construction in the tunnel surrounding rock at a radius of R2 along the direction of the tunneling equipment.
[0021] H. According to the construction length of the tunneling equipment, select several sets of drilling systems consisting of installation drills and connecting drills to carry out several cycles of alternating construction of the installation of annular supports inside the tunnel surrounding rock, thereby achieving the laying of continuous annular elastic supports in the tunnel surrounding rock in a support-before-excavation manner, and at the same time meeting the synchronous and continuous advancement of large-scale tunnel construction and annular support construction inside the tunnel surrounding rock.
[0022] It can be seen from the above technical solutions that, compared with the prior art, the present invention discloses a method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction, which has the following beneficial effects:
[0023] 1. The present invention is advanced in an alternating and continuous construction manner of installing drilling rig one, connecting drilling rig one, installing drilling rig two, and connecting drilling rig two. The drill rod can be arranged in the tunnel surrounding rock before the construction progress of the excavation equipment, and a certain support effect can be produced. There is no need to stop the excavation equipment when the annular elastic support is installed, thereby affecting the construction progress, and even causing certain negative engineering effects caused by the shutdown of the excavation equipment. Finally, the large-scale tunnel construction and the annular support construction inside the tunnel surrounding rock are synchronously and continuously advanced, and the engineering concept of arranging continuous annular elastic supports in the tunnel surrounding rock is completed.
[0024] 2. The present invention has the advantages of simple construction layout, mature technology and reasonable design. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0026] Figure 1 The accompanying drawing is a perspective view of the time and space position distribution of the ring support installation equipment (installation drill and connection drill) in the tunnel surrounding rock provided by the present invention in the construction tunnel;
[0027] Figure 2 The accompanying drawing is a side view of the time and space position distribution of the ring support installation equipment (installation drill and connection drill) in the tunnel surrounding rock provided by the present invention in the construction tunnel;
[0028] Figure 3 The attached drawing is a front view of the time and space position distribution of the ring support installation equipment (installation drill and connection drill) in the tunnel surrounding rock provided by the present invention in the construction tunnel;
[0029] Figure 4 The accompanying drawing is a top view of the time and space position distribution of the ring support installation equipment (installation drill and connection drill) in the tunnel surrounding rock provided by the present invention in the construction tunnel;
[0030] Figure 5 The accompanying drawing is a side view of the time and space position distribution position in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock;
[0031] Figure 6 The attached drawing is a side view of the time and space position distribution position of the tunnel boring equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock in the tunnel;
[0032] Figure 7 The attached drawings are three side views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0033] Figure 8 The attached drawings are four side views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment of the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0034] Fig. 9 The attached drawings are five side views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0035] Fig.10 The attached drawings are six side views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0036] Fig.11 The attached drawings are seven side views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0037] Fig.12The attached figure is a side view of the time and space position distribution position in the tunnel provided by the present invention during the construction of the tunnel boring equipment (shield machine) and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock;
[0038] Fig.13 The accompanying drawing is a side view of the time and space position distribution position of the tunnel excavation equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock in the tunnel;
[0039] Fig.14 The accompanying drawing is a top view of the time and space position distribution position in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock;
[0040] Fig.15 The attached drawing is a top view of the time and space position distribution position of the tunnel excavation equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock in the tunnel;
[0041] Fig.16 The attached drawings are three top views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0042] Fig.17 The attached drawings are four top views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment of the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0043] Fig.18 The attached drawing is a top view of the time and space position distribution position of the tunnel boring equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock in the tunnel;
[0044] Fig.19 The attached drawings are six top views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0045] Fig. 20 The attached drawings are seven top views of the time and space position distribution positions in the tunnel during the construction of the tunnel boring equipment (shield machine) provided by the present invention and the installation equipment for the ring support in the tunnel surrounding rock (installation drill and connecting drill);
[0046] Fig.21The attached figure is a top view of the time and space position distribution position of the tunnel excavation equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock in the tunnel;
[0047] Fig. 22 The accompanying drawing is a top view of the time and space position distribution position of the tunnel excavation equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill and connecting drill) in the tunnel surrounding rock in the tunnel;
[0048] Fig.23 The attached drawing is a simplified diagram of the time and spatial position distribution of the coordinated continuous construction from position one to position nine in the tunnel of the tunnel boring equipment (shield machine) provided by the present invention and the ring support installation equipment (installation drill rig and receiving drill rig) in the tunnel surrounding rock.
[0049] In the above figures:
[0050] Attached Figures 5 to 13 , from right to left is the construction sequence, side view of the time and spatial position distribution of the coordinated continuous construction of the tunnel boring equipment (shield machine) and the ring support installation equipment (installation drill rig and receiving drill rig) in the tunnel surrounding rock from position one to position nine in the tunnel.
[0051] Attached Figures 14 to 22 , from right to left is the construction sequence, a bird's-eye view of the time and spatial position distribution of the coordinated and continuous construction of the tunnel boring equipment (shield machine) and the ring support installation equipment (installation drill rig and receiving drill rig) in the tunnel surrounding rock from position one to position nine in the tunnel.
[0052] in:
[0053] 1-Connect the drilling rig; 2-Install the drilling rig; 3-Automatic drill rod storage and retrieval machine; 4-Connect the drilling rig construction platform; 5-Install the drilling rig construction platform; 6-Tunnel surrounding rock elastic support; 7-Tunnel; 8-Drilling rig position one; 9-Shield machine position one; 10-Drilling rig position two; 11-Shield machine position two; 12-Drilling rig position three; 13-Shield machine position three; 14-Drilling rig position four; 15-Shield machine position four; 16-Drilling rig position five; 17-Shield machine position five; 18-Drilling rig position six; 19-Shield machine position six; 20-Drilling rig position seven; 21-Shield machine position seven; 22-Drilling rig position eight; 23-Shield Tunneling machine position eight; 24-drilling machine position nine; 25-shield machine position nine; 26-shield machine position ten; 27-installation drill rig one; 28-installation drill rig two; 29-connection drill rig one; 30-connection drill rig two; 31-shield machine; 32-vertical shaft; 33-annular elastic support in the tunnel surrounding rock; 34-platform ramp; 35-segment mud chamber; 36-drilling buckle; 37-transport vehicle; 38-supporting system; 39-belt conveyor; 40-shield machine installation pipe; 41-segment assembly drill rig; 42-screw conveyor; 43-front shield; 44-middle shield; 45-tail shield; 46-pressure partition; 47-cutter head. DETAILED DESCRIPTION
[0054] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0055] like Figure 1-23 As shown, the present invention discloses a method for synchronously and continuously advancing the construction of a large tunnel and the construction of an annular support inside the tunnel surrounding rock, including: a shield machine 31, an installation drill rig 27, a connecting drill rig 29, an installation drill rig 28, and a connecting drill rig 30.
[0056] like Figure 1-23 As shown, an installation drilling rig system of a tunnel ring support is formed by an installation drilling rig 2 and a connecting drilling rig 1.
[0057] like Figure 5 and 14 As shown, the shield machine 31 is transported underground through a ground shaft 32 and arranged in a tunnel 7 of an underground excavation working face, facing a predetermined direction of the underground space, and a corresponding supporting system 38 is arranged at its rear, such as ventilation equipment, transportation equipment, power communication equipment, specifically including a pressure maintaining system, a material lifting system, a secondary ventilation system, a ventilation and refrigeration system, a sewage system, a pipeline extension device, and a bentonite system; this position is the shield machine position 9.
[0058] like Figure 5 and 14 As shown, the installation drilling rig 27 is transported underground through the ground shaft 32 and arranged on one side of the tunnel directly behind the shield machine 31. A transportation road is arranged on the other side of the tunnel. The front end of the installation drilling rig 27 faces the tail of the shield machine 31. This position is the drilling rig position 8. The installation drilling rig 27 starts construction and drill rods are drilled in a ring along the tunnel excavation direction. The drilling rod progress is required to be ahead of the shield machine 31.
[0059] like Figure 5-6 As shown in Figures 14-15, the installation drilling rig 28 is used to cooperate with the installation drilling rig 1 27 for alternating and cyclic construction. When the tunnel shield machine 31 is constructed to a certain distance, the position is the shield machine position 2 11, and the installation drilling rig 28 is transported to the underground drilling rig position 2 10 through the ground shaft 32 for installation construction. The specific process is: the installation drilling rig 1 27 starts construction first, and an annular drill rod is driven along the tunnel 7 excavation direction. When the drill bit exceeds the position of the shield machine 31, that is, the shield machine position 1 9, the shield machine 31 starts construction. When the shield machine 31 is constructed to a certain distance, that is, the shield machine position 2 11, the installation drilling rig 28 is arranged on one side of the tunnel directly behind the shield machine 31, that is, the drilling rig position 2 10, and a transportation road is arranged on the other side of the tunnel. The front end of the installation drilling rig 28 faces the tail of the shield machine 31, and the installation drilling rig 28 starts construction, and an annular drill rod is driven along the tunnel 7 excavation direction. The progress of the annular drill rod should be faster than that of the shield machine 31 by a certain distance.
[0060] like Figure 5-8As shown in Figures 14-17, the receiving drill rig 29 is used to cooperate with the installation drill rig 27 to install the tunnel surrounding rock ring support. When the tunnel 7 is constructed to a certain progress, that is, the position is the shield machine position 3 13, the receiving drill rig 29 is transported to the underground drill position 3 12 through the ground shaft 32 for installation. The specific process is: the installation drill rig 27 starts construction first, and an annular drill rod is driven along the tunnel excavation direction. When the drill rod exceeds the shield machine 31 position, that is, the shield machine position 19, the shield machine 31 starts construction. When the shield machine 31 is constructed to a certain distance, that is, the shield machine position 2 11, the installation drill rig 28 is arranged on one side of the tunnel 7 directly behind the shield machine 31, that is, the drill position 2 10, and a transportation road is arranged on the other side of the tunnel 7. The front end of the installation drill rig 28 faces the tail of the shield machine 31. The installation drill rig 28 starts construction and drives an annular drill rod along the tunnel 7 excavation direction. The progress of the annular drill rod should be faster than that of the shield machine 31 by a certain distance. When the shield machine 31 reaches the position for installing the drill bit of the drilling rig 27, it is necessary to wait until the shield machine 31 has advanced a certain distance, that is, when it reaches the shield machine position 313, the drilling rig 27 is installed to guide the navigation drill bit from the tunnel floor into the tunnel 7, and the drill bit is replaced with a return drill bit by using the connecting drill rig 27, and the elastic annular bracket is connected to drag the elastic annular bracket back to the specified position in the tunnel surrounding rock borehole, that is, the drilling rig position 8; or when the engineering design requires expansion construction of the tunnel surrounding rock borehole, the navigation drill bit is replaced with an expansion drill bit by using the connecting drill rig 29, and the drill rod is connected to carry out expansion construction. After the expansion is completed, the expansion drill bit is replaced with a return drill bit, and the tunnel surrounding rock elastic bracket 6 is connected, and the tunnel surrounding rock elastic bracket 6 is directly dragged back to the specified position in the tunnel surrounding rock borehole, that is, the drilling rig position 8. The first stage of the installation and construction of the elastic annular bracket in the tunnel surrounding rock is completed. While the elastic annular bracket in the tunnel surrounding rock is being fixed and grouting finished, the tunnel shield machine 31 continues to move forward for a distance, that is, the shield machine position 4 15. At this time, the installation drill 27 is transported from the drill position 8 to the side of the tunnel directly behind the tunnel shield machine 31 through the tunnel transportation system, that is, the drill position 4 14, and the transportation road is arranged on the other side of the tunnel. The front end of the installation drill 27 faces the tail of the shield machine 31, and the installation drill 27 starts construction, and the ring drill rod is driven along the tunnel 7 excavation direction. The progress of the ring drill rod should be faster than the shield machine 31 by a certain distance.
[0061] like Figure 5-10As shown in Figures 14-19, the receiving drilling rig 29 is used to cooperate with the installation drilling rig 28 to install the tunnel surrounding rock ring support 6. After the tunnel construction reaches a certain progress, that is, the position is the shield machine position 5 17, the receiving drilling rig 2 30 is transported to the underground drilling rig position 5 16 through the ground shaft 32 for installation. The specific process is: first start the construction of the installation drilling rig 27, and drive a ring-shaped drill rod along the excavation direction of the tunnel 7. When the drill rod exceeds the position of the shield machine 31, that is, the shield machine position 9, the shield machine 31 starts construction. When the shield machine 31 constructs to a certain distance, that is, the shield machine position 11, the installation drilling rig 28 is arranged on one side of the tunnel directly behind the shield machine 31, that is, the drilling rig position 10, and a transportation road is arranged on the other side of the tunnel. The front end of the installation drilling rig 28 faces the tail of the shield machine 31, and the installation drilling rig 28 starts construction, and drives a ring-shaped drill rod along the excavation direction of the tunnel 7. The progress of the ring drill rod should be faster than that of the shield machine 31 by a certain distance. When the shield machine 31 reaches the position for installing the drill bit of the drilling rig 27, it is necessary to wait until the shield machine 31 has advanced a certain distance, that is, when it reaches the shield machine position 313, the drilling rig 27 is installed to guide the navigation drill bit from the tunnel floor into the tunnel 7, and the drill bit is replaced with a return drill bit by using the connecting drill rig 29, and the elastic support 6 of the tunnel surrounding rock is connected, and the elastic support 6 of the tunnel surrounding rock is directly returned to the designated position in the tunnel surrounding rock borehole, that is, the drilling rig position 8; or when the engineering design requires the expansion of the tunnel surrounding rock borehole, the navigation drill bit is replaced with an expansion drill bit by using the connecting drill rig 29, and the drill rod is connected to carry out the expansion construction. After the expansion is completed, the expansion drill bit is replaced with a return drill bit, and the elastic support 6 of the tunnel surrounding rock is connected, and the elastic support 6 of the tunnel surrounding rock is directly returned to the designated position in the tunnel surrounding rock borehole, that is, the drilling rig position 8. The first stage of the installation and construction of the elastic annular support in the tunnel surrounding rock is completed. While fixing and finishing the tunnel surrounding rock elastic support 6 in the tunnel surrounding rock, the shield machine 31 continues to move forward for a distance, that is, the shield machine position 4 15. At this time, the installation drill 27 is transported from the drill position 8 to the side of the tunnel directly behind the tunnel shield machine 31 through the tunnel transportation system, that is, the drill position 5 16, and the transportation road is arranged on the other side of the tunnel. The front end of the installation drill 27 faces the tail of the shield machine 31, and the installation drill 27 starts construction, and the ring drill rod is driven along the tunnel 7 excavation direction. The progress of the ring drill rod should be faster than the shield machine 31 by a certain distance.When the shield machine 31 reaches the drill bit position of the second drilling rig 28, it is necessary to wait until the shield machine 31 has advanced a certain distance, that is, when it reaches the shield machine position five 17, the second drilling rig 28 is installed to guide the navigation drill bit from the tunnel floor into the tunnel 7, and the second drilling rig 30 is used to replace the navigation drill bit with a return drill bit, and the tunnel surrounding rock elastic support 6 is connected to the elastic support 6 of the tunnel surrounding rock, and the elastic support 6 of the tunnel surrounding rock is returned to the designated position in the tunnel surrounding rock borehole, that is, the drilling rig position two 10; or when the engineering design requires the expansion of the tunnel surrounding rock borehole, the second drilling rig 30 is used to replace the navigation drill bit with a reaming drill bit, and the drill rod is connected to carry out the expansion construction. After the expansion is completed, the reaming drill bit is replaced with a return drill bit, and the elastic support 6 of the tunnel surrounding rock is connected to the elastic support 6 of the tunnel surrounding rock, and the elastic support 6 of the tunnel surrounding rock is returned to the designated position in the tunnel surrounding rock borehole, that is, the drilling rig position two 10. The second stage of the installation and construction of the elastic annular support in the tunnel surrounding rock is completed. While the tunnel surrounding rock elastic support 6 is being fixed and finished, the tunnel shield machine 31 continues to move forward for a distance, i.e., to the shield machine position 6 19. At this time, the installation drill rig 28 is transported from the drill rig position 2 10 through the tunnel transportation system to the side of the tunnel directly behind the tunnel shield machine 31, i.e., the drill rig position 6 18, and a transportation road is arranged on the other side of the tunnel. The front end of the installation drill rig 2 28 faces the tail of the shield machine 31, and the installation drill rig 2 28 starts construction, and a ring drill rod is drilled along the excavation direction of the tunnel 7. The progress of the ring drill rod should be faster than that of the shield machine 31 by a certain distance. As shown above, the installation drill rig 1 27 and the connecting drill rig 1 29 are the installation drill rig system of the first group of tunnel ring supports, and the installation drill rig 2 28 and the connecting drill rig 2 30 are the installation drill rig system of the second group of tunnel ring supports, thereby realizing an alternating construction cycle in which the large-scale tunnel construction and the construction of the ring supports inside the tunnel surrounding rock are synchronously and continuously advanced. If the advance speed of the shield machine 31 does not match the construction speed of the installation drilling system of the tunnel ring support 6 under special conditions, a certain number of drilling systems can be added or reduced, so as to realize the synchronous and continuous advancement of large-scale tunnel construction and the construction of the ring support inside the tunnel surrounding rock in a more flexible and changeable manner. In addition, after the installation drilling system of a group of tunnel ring supports composed of the installation drilling rig 2 and the connecting drilling rig 1 is completed, the tunnel segments can be immediately laid with steel bars, poured with cement and other engineering construction.
[0062] like Fig.23As shown, by installing drilling rig 1 27, installing drilling rig 28, connecting drilling rig 1 29, and connecting drilling rig 2 30 in the underground tunnel in turn, the drill rod in the tunnel surrounding rock is always ahead of the excavation working face of the shield machine 31. Since the drill rod is elastic and is annular in the tunnel surrounding rock, the drill rod can stabilize the tunnel surrounding rock. After the drilling construction is completed, the tunnel surrounding rock elastic support 6 is dragged back into the tunnel surrounding rock, thereby forming a permanent tunnel surrounding rock elastic support 6 in the tunnel surrounding rock, thereby enhancing the mutual support between the tunnel surrounding rock elastic support 6 and the surrounding rock. Bearing function; at the same time, annular brackets made of materials with different characteristics can be selected according to the actual situation of the tunnel surrounding rock; the tunnel surrounding rock can also be grouting treated by the annular elastic bracket 6, so as to further strengthen the tunnel surrounding rock and reduce the impact of static and dynamic loads on the tunnel 7; or a series of sensors can be arranged inside the tunnel surrounding rock elastic bracket 6 to monitor the deformation, pressure and other conditions of the tunnel surrounding rock while strengthening the tunnel surrounding rock, so as to predict and prevent the damage of the tunnel in advance, which plays a vital role in preventing the occurrence of tunnel safety accidents.
[0063] The present invention provides a method for synchronously and continuously advancing the construction of a large tunnel and the construction of an annular support inside the tunnel surrounding rock as follows:
[0064] A. First, transport the shield machine 31 and its supporting system 38 through the shaft to the working face of the tunnel 7, i.e., the shield machine position 9;
[0065] B. Arrange a drilling rig construction platform 5 on one side of the tunnel directly behind the tunnel shield machine 31, and transport the drilling rig 27 to the drilling rig construction platform 5, i.e., the drilling rig position 8, through the ground shaft 32;
[0066] C. Start the installation drilling machine 1 and perform circular drilling construction in the tunnel surrounding rock at a certain radius R1 along the direction of the shield machine 31;
[0067] D. After the annular drill exceeds the front shield 43 of the shield machine 31 by a certain distance, the shield machine 31 is started and the tunneling support construction is carried out normally;
[0068] E. After the shield machine 31 advances to a certain distance, i.e., the shield machine position 2 11, the installation drilling rig construction platform 5 is arranged on one side of the tunnel 7 directly behind the shield machine 31, and the installation drilling rig 28 is transported to the installation drilling rig construction platform 5, i.e., the drilling rig position 2 10, through the ground shaft 32;
[0069] F. Start the installation drilling machine 28 and perform circular drilling construction in the tunnel surrounding rock at a certain radius R2 along the direction of the shield machine 31;
[0070] G. After the installation drilling rig 27 reaches the target position, the construction is stopped and the drill bit is left in the tunnel surrounding rock. After the shield machine 31 reaches the position and continues to excavate for a certain distance, i.e., the shield machine position 3 13, a drilling rig construction platform 4 for receiving the drilling rig 29 is arranged at this position, i.e., the drilling rig position 3 12, and the drilling rig 27 is transported to the drilling rig construction platform 4, i.e., the drilling rig position 3 12, by the shaft 32 and the tunnel transportation tool. The drilling rig 27 is used to guide the drill bit from the tunnel floor into the tunnel 7, the drilling rig 29 is used to replace the navigation drill bit with a pull-back drill bit, and the elastic support of the tunnel surrounding rock is connected. The tunnel surrounding rock elastic support 6 is directly dragged back to the designated position in the tunnel surrounding rock borehole, i.e., the drilling rig position 8; or when the engineering design requires the tunnel surrounding rock borehole to be expanded, the navigation drill bit is replaced with the expansion drill bit by using the connecting drill rig 1, and the drill rod is connected to carry out the expansion construction. After the expansion is completed, the expansion drill bit is replaced with the return drill bit, and the tunnel surrounding rock elastic support 6 is connected, and the tunnel surrounding rock elastic support 6 is directly dragged back to the designated position in the tunnel surrounding rock borehole, i.e., the drilling rig position 8; finally, the annular elastic support 6 in the tunnel surrounding rock is fixed, and the construction of the first section of the tunnel surrounding rock annular elastic support is completed;
[0071] H. At this time, the installation drilling rig 28 and the shield machine 31 are still under construction. When the shield machine 31 reaches the designated location, i.e., the shield machine position 15, a construction platform 5 for installing the drilling rig 27 is set up directly behind the shield machine 31, and the installation drilling rig 27 is disassembled and transported to the construction platform 5 for excavating the installation drilling rig. The installation drilling rig 27 is started, and a circular drilling construction is performed in the surrounding rock of the tunnel along the direction of the shield machine 31 according to a certain radius R1;
[0072] I. After the installation drilling rig 28 reaches the target position, construction is stopped and the navigation drill bit is left in the tunnel surrounding rock. After the shield machine 31 reaches the position and continues to excavate for a certain distance, i.e., the shield machine position 5 17, a construction platform 4 for receiving the drilling rig 2 is arranged at the drill outlet position, i.e., the drilling rig position 5 16, and the receiving drilling rig 2 30 is transported to the construction platform 4 for receiving the drilling rig 2 30 through the shaft 32 and the tunnel transportation tool, and the navigation drill bit is introduced from the tunnel floor into the tunnel 7 by the installation drilling rig 28, and the navigation drill bit is replaced with a back-drag drill bit by the receiving drilling rig 2 30, and connected. Connect the tunnel surrounding rock elastic support 6, and directly drag the tunnel surrounding rock elastic support 6 back to the designated position in the tunnel surrounding rock borehole, that is, the drilling rig position 2 10; or when it is necessary to expand the tunnel surrounding rock borehole, use the drilling rig 2 30 to replace the navigation drill bit with the expansion drill bit, and connect the drill rod to carry out the expansion construction. After the expansion is completed, the expansion drill bit is replaced with the return drill bit, and the tunnel surrounding rock elastic support 6 is connected, and the tunnel surrounding rock elastic support 6 is dragged back to the designated position in the tunnel surrounding rock borehole, that is, the drilling rig position 2 10, and the construction of the second section of the tunnel surrounding rock annular elastic support is completed;
[0073] J. At this time, the installation drilling rig 1 27 and the shield machine 31 are still under construction. When the shield machine 31 reaches the designated location, i.e., the shield machine position 6 19, a construction platform 5 for installing the drilling rig 28 is set up directly behind the shield machine 31, and the installation drilling rig 28 is disassembled and transported to the construction platform 5 for installing the drilling rig 28. The installation drilling rig 28 is started, and a circular drilling construction is performed in the tunnel surrounding rock along the direction of the shield machine 31 according to a certain radius R1;
[0074] K. According to the construction length of the shield machine 31, select a drilling system consisting of several groups of installation drills 2 and connecting drills 1, and perform several cycles of alternating construction of the installation of annular supports inside the tunnel surrounding rock, thereby economically and effectively laying continuous annular elastic supports in the tunnel surrounding rock in a support-before-excavation manner, and at the same time meet the synchronous and continuous advancement of large-scale tunnel construction and the construction of annular supports inside the tunnel surrounding rock, thereby meeting the demand for surrounding rock control in large-scale soft rock tunnel excavation construction.
[0075] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0076] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction, characterized in that: The specific steps include: S1. The excavation equipment is transported underground through the surface shaft and arranged in the tunnel of the underground excavation working face, facing the predetermined direction of the underground space; S2. The installation drill rig is transported underground through the ground shaft and arranged on one side of the tunnel directly behind the tunneling equipment. A transportation road is arranged on the other side of the tunnel. The front end of the installation drill rig is directed toward the rear of the tunneling equipment. The installation drill rig is started to drill a circular drill rod along the tunneling direction. S3. After the excavation equipment has been constructed to a certain distance, the installation drilling rig 2 is transported to the underground through the ground shaft for installation construction, and the installation drilling rig 2 cooperates with the installation drilling rig 1 to perform construction in an alternating cycle; S4. After the tunnel construction reaches a certain progress, the connecting drilling rig 1 is transported underground through the ground shaft, and the tunnel surrounding rock ring support is installed by the connecting drilling rig 1 in conjunction with the installation drilling rig 1; S5. After the tunnel construction reaches a certain progress, the second connecting drilling rig is transported to the underground through the ground shaft for installation, and the second connecting drilling rig cooperates with the second installation drilling rig to carry out the installation construction of the tunnel surrounding rock ring support; S6. By installing drilling rig 1, installing drilling rig 2, connecting drilling rig 1, and connecting drilling rig 2 in the underground tunnel, the drill rod in the tunnel surrounding rock is always ahead of the excavation working face of the excavation equipment. After the individual drilling construction is completed, the elastic ring support is dragged back into the tunnel surrounding rock, thereby forming a permanent elastic ring support in the tunnel surrounding rock.
2. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 1, characterized in that: The corresponding supporting system is arranged at the rear of the tunneling equipment; the supporting system includes ventilation equipment, transportation equipment and power communication equipment.
3. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 2, characterized in that: The tunneling equipment and its supporting systems are transported to the tunnel working face through the vertical shaft and placed at the shield machine position one; a drilling rig installation construction platform is arranged on one side of the tunnel directly behind the tunneling equipment, and the drilling rig installation one is transported to the drilling rig position one of the drilling rig installation construction platform through the ground vertical shaft; the drilling rig installation is started, and circular drilling construction is performed in the tunnel surrounding rock along the direction of the tunneling equipment according to the radius R1.
4. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 3, characterized in that: After the annular drill exceeds the front shield of the tunneling equipment by a certain distance, the tunneling equipment is started to carry out tunneling support construction.
5. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 4, characterized in that: When the tunneling equipment advances a certain distance and reaches the shield machine position two, a drilling rig installation construction platform is arranged on the side of the tunnel directly behind the tunneling equipment, and the drilling rig installation two is transported to the drilling rig position two of the drilling rig installation construction platform through the ground shaft; the drilling rig installation two is started, and circular drilling construction is carried out in the tunnel surrounding rock along the direction of the tunneling equipment according to the radius R2.
6. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 5, characterized in that: After the installation drilling rig 1 has been constructed to the target position, the construction is stopped and the drill bit is left in the tunnel surrounding rock. After the excavation equipment has been constructed to the position and the excavation construction continues for a certain distance, it reaches the shield machine position 3, and a drilling rig construction platform for the drilling rig 1 is arranged at the position where the installation drilling rig 1 stops construction to form the drilling rig position 3. The drilling rig 1 is transported to the drilling rig position 3 by the shaft and tunnel transportation tools, the drilling rig 1 is used to guide the drill bit from the tunnel floor into the tunnel, the navigation drill bit is replaced by the drilling rig 1 to the back-drag drill bit, and the elastic annular support is connected. The elastic annular bracket is used to drag the elastic annular bracket back to a drilling rig position in the tunnel surrounding rock borehole, or when the engineering design requires hole expansion construction on the tunnel surrounding rock borehole, the navigation drill bit is replaced with a hole expansion drill bit by using the connecting drill rig, and the drill rod is connected to carry out hole expansion construction. After the hole expansion is completed, the hole expansion drill bit is replaced with a return drill bit, and the elastic annular bracket is connected, and the elastic annular bracket is dragged back to a drilling rig position in the tunnel surrounding rock borehole. Finally, the annular elastic bracket in the tunnel surrounding rock is fixedly grouted to complete the construction of the first section of the tunnel surrounding rock annular elastic bracket.
7. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 6, characterized in that: The installation drilling rig and tunneling equipment continued construction. When the tunneling equipment was constructed to the shield machine position four, a construction platform for installing the drilling rig one was set up behind the tunneling equipment. The installation drilling rig one was disassembled and transported to the tunneling construction platform. The installation drilling rig one was started and circular drilling construction was carried out in the tunnel surrounding rock according to the radius R1 along the direction of the tunneling equipment.
8. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 7, characterized in that: After the installation drilling rig 2 reaches the target position, the construction is stopped and the navigation drill bit is left in the tunnel surrounding rock. After the excavation equipment reaches the position and continues to excavate for a certain distance, it reaches the shield machine position 5. The construction platform for receiving the drilling rig 2 is arranged at the drill outlet position to form the drilling rig position 5. The drilling rig 2 is transported to the construction platform for receiving the drilling rig 2 by the shaft and tunnel transportation tools. The installation drilling rig 2 is used to guide the navigation drill bit from the tunnel floor into the tunnel. The drilling rig 2 is used to replace the navigation drill bit with a backhaul The drill bit is connected and the elastic annular bracket is connected, and the elastic annular bracket is dragged back to the second drilling rig position in the tunnel surrounding rock borehole; or when it is necessary to expand the tunnel surrounding rock borehole, the navigation drill bit is replaced with an expansion drill bit by using the second drilling rig, and the drill rod is connected to carry out expansion construction. After the expansion is completed, the expansion drill bit is replaced with a return drill bit, and the elastic annular bracket is connected, and the elastic annular bracket is dragged back to the second drilling rig position in the tunnel surrounding rock borehole to complete the construction of the second section of the tunnel surrounding rock annular elastic bracket.
9. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to claim 8, characterized in that: Installation drilling rig 1 and tunneling equipment continued construction. When the tunneling equipment reached shield machine position six, a construction platform for installation drilling rig 2 was set up directly behind the tunneling equipment. Installation drilling rig 2 was disassembled and transported to the construction platform for installation drilling rig 2. Installation drilling rig 2 was started and circular drilling construction was carried out in the tunnel surrounding rock along the direction of the tunneling equipment according to the radius R2.
10. A method for synchronously and continuously advancing large-scale tunnel construction and surrounding rock internal annular support construction according to any one of claims 1 to 9, characterized in that: According to the construction length of the tunneling equipment, several groups of drilling systems consisting of installation drills and connecting drills are selected to carry out several cycles of alternating construction of the installation of annular supports inside the tunnel surrounding rock, thereby achieving the laying of continuous annular elastic supports in the tunnel surrounding rock in a support-before-excavation manner, and at the same time meeting the synchronous and continuous advancement of large-scale tunnel construction and annular support construction inside the tunnel surrounding rock.